Date post: | 14-Apr-2017 |
Category: |
Leadership & Management |
Upload: | iftikhar-anjum |
View: | 483 times |
Download: | 2 times |
EARNED VALUE MANAGEMENTIncorporating Risks and integrated Master-EVM models
Muhammad Iftikhar Anjum
“You cannot manage what you cannot measure…and what gets measured gets
done.”
Bill Hewlett,Co-founder Hewlett Packard
INTRODUCTION Earned Value Management (EVM) is an
effective tool for project performance measurement on Time, Cost & Scope baselines
If used properly, EVM can ensure project success without major delays
EVM models are mainly effective for Predictive Life Cycle Projects
Certain limitations are associated with use of EVM, for which different extensions have been proposed by various researchers
INTRODUCTION
In this Study EVM models (Task-EVM) for each task is
proposed that are to be integrated for Project or Master-EVM
Risk Costs and Time Buffers are added in Planned Value (PV) calculations based on probability-impact factors for Risk
In order to apply the proposed EVM extensions, a hypothetical tourism facility project is taken as a model
AIM OF STUDYAim of the study is to propose techniques for addressing EVM model limitations based on a
Hypothetical Tourism Facility Project
BASIC CONCEPTS - EVMPV: Planned ValueEV: Earned ValueAC: Actual Cost
SV: Schedule VarianceSV = EV – PV
CV: Cost VarianceCV = EV – AC
Cost
TimeTime t
PV
EV
ACScheduleVariance
Management Reserve
CostVariance
COST & SCHEDULE PERFORMANCE INDICES
Excellent
Bad
Cost Performance Index
CPI = EV/AC
Schedule Performance Index
SPI = EV/PV
1 or 100%
CPI, SPI = 1, Cost & Schedule are as planned
BASIC CONCEPTS - EVM
Cost
TimeTime t
PV
EV
ACScheduleVariance
Management Reserve
CostVariance
BAC
EAC
LIMITATIONS OF EVM Risks are not accounted for in EVM model
Exact measurement of Earned Value (Physical work completed) may not be accurate
There may be variations in Cumulative Earned Value and Physical work done on individual tasks
HYPOTHETICAL MODELVash-Rung MakranTourism Facility Project
HYPOTHETICAL MODEL FOR RESEARCH A Tourism Business Company planned for
establishing a tourism facility at Kund Malir, Balochistan
Tourism attractions include, Beach, Landscape, Hangol River, Nani mandar, graves of Bin Qasim’s soldiers, Princes of Hope, Star-sighting etc
Project is named as Vash-Rung Makran (VRM)
Company believes in use of sustainable energy, clean environment and use of local human resource
TASKSTask Time (weeks) Cost (million of rupees)
Hotel Renovation 13 13Security 12 10Training 26 10Patrol Pump 12 20Shuttle Service 12 40Wind-Solar Energy System 20 40Marketing 26 20Hospital 12 10Seawater Treatment 24 40Sewerage Treatment 24 20Trial Trip 1 1Plan for Expansion 1 1Total 50 (based on PERT) 225
Project Vash Rung
PERT/CPM FOR THE MODEL
PROPOSED EVM MODELS to address the limitations
TASK-EVMS INTO MASTER-EVM MODEL In order to get the real time data of AC and EV a
separate EVM for each task is to be planned and maintained
Task manager, with assistance of accounting/ stores professionals should keep his Task-EVM updated
Data for each Task-EVM is to be communicated to Master-EVM, by a network or data link
Periodicity of update of EVM is to be planned and same is to be used for keeping every concerned onboard of actual project performance
EXAMPLEAt time t, there are 3 parallel tasks A, B & C
Cumulative Calculations for Master-EVM
EVP = EVA + EVB + EVC
ACP = ACA + ACB + ACC + Ο
Ο is other associated costs, that does not add to the Physical Work done in terms of cost
TASK & MASTER EVM
*Calculations were made from POM-QM software PERT cost-budgeting module
INCORPORATION OF RISK FACTORS Project Risk Management is a factor that
assures a project performance and completion as per schedule
PMs usually avoid maintaining a Risk Register A conflict situation may occur or project
performance may be affected badly, if risk management is not done properly
In order to avoid this situation, it is proposed that risks are to be added to EVM planned value (PV)
INCORPORATION OF RISK FACTORS
0.36 here is Probability-Impact Factor
INCORPORATION OF RISK FACTORS All other Risks can be converted in terms of
Cost and Schedule
In the model, only Cost & Schedule risks are proposed for incorporation into EVM
For calculation of risk values, Probability-Impact factor (PI) is used in proposed EVM model
SCHEDULE RISKS It is proposed that for schedule risks, buffer
times are to be added to all tasks Calculations of buffer times are on the basis
of PI factors for proposed modelPIp: Probability-Impact factor (positive risks)RVp : Risk Value (positive risks) RVp
PIn : Probability-Impact factor (negative risks)
RVn : Risk Value (negative risks)TB: Time BufferEquation for Buffer Time:
TB = (PIn)*(RVn) – (PIp)*(RVp)
SCHEDULE RISKS - CALCULATIONS Following table, taking hypothetical values of
risks, in 4 tasks was created
RV, PS, PR in weeksPetrolPump
EnergyPlant
SeawaterPlant
SeweragePlant
PIp 0.4 0.2 0.3 0.7RVp 1 1 2 1(PIn)*(RVn) 0.4 0.2 0.86 0.7PIn 0.68 0.74 0.7 0.9RVn 5 7 3 4(PIp)*(RVp) 3.4 5.2 2.6 3.7Time Buffer 3 5 4 3Planned Schedule 12 20 24 24Planned Schedule with Risks 15 25 28 27
SCHEDULE RISKS – PERT/CPM
SCHEDULE RISKS – EVM
COST RISKS It is proposed that for cost risks, additional
cost, based on PI factor is to be added to tasks
PIp: Probability-Impact factor (positive risks)RVp : Risk Value (positive risks) RVp
PIn : Probability-Impact factor (negative risks)
RVn : Risk Value (negative risks)RC: Risk Cost (in million of rupees)Equation for Risk Cost:
RC = (PIn)*(RVn) – (PIp)*(RVp)
COST RISKS - CALCULATIONS Following table, taking hypothetical values of
risks, in 4 tasks was created
RV, PB, PR in million of Rupees TrainingShuttle Service Marketing
SeweragePlant
PIp 0.4 0.2 0.3 0.7RVp 1 1 2 1(PIn)*(RVn) 0.4 0.2 0.6 0.7PIn 0.7 0.6 0.7 0.9RVn 2 2 3 2(PIp)*(RVp) 1.4 1.2 2.1 1.8Risk Costs 1 1 1.5 1.1Planned Cost 12 20 24 24Planned Cost with Risks 13 21 25.5 25.1
COST RISKS – EVM
EVM WITH ALL RISKS
IMPLICATIONS OF STUDY In practical approach, some risks cannot be quantified and
are based on previous experience and expert judgment of PM. There are Force Majeure Risks, like natural disasters, those
can only be dealt with by a project team’s efficiency, experience, knowledge and resources.
Efficiency in upkeep of Task EVMs by Task-Managers can vary as per the priority of the task itself, associated works, time and expertise in finance/management.
Model of Vash-Rung tourism facility project is based on hypothetical company, costs, schedules, team members and potential for revenue in the project. It is not to be used for any practical approaches, except for getting an idea for such projects.
CONCLUSION Earned value management methodology takes into
account all three triple constraints that may delay a project or cost extra expenditure.
There always remain an element of error and difference between on-ground project status and management level documentation and tools like EVM. Proposed model for dividing Master-EVM into task-EVMs will keep all stakeholders onboard at any instant of time and real-time project performance will be measured affectively.
Project Risk Management is another major factor that assures project performance and efficiency of team. Project Managers generally avoid maintaining a risk register. Proposed model for incorporating risks into EVM at planning level will give a clear insight to all stakeholders. Moreover, during the project life cycle, clear visibility of forthcoming risks will ensure early risk responses.
FUTURE RESEARCHES Future researches can target reducing the gap
between theoretical/financial models and practice/physical status of a Project.
Identifying and quantifying risks is core competency of any project management organization. Project Risk Management integration with planning, execution and monitoring & controlling of a project can be another area of research.
Hypothetical model of a tourism facility in Kund Malir can be a full fledge research and business project, that can be studied and implemented practically.
Use of sustainable energy resources, capacity building of local population and self-sufficiency in water resources are few other areas that can be researched for business as well as for poverty alleviation.
REFERENCES PMI’s Project Management Body of
Knowledge PMBOK®.
Practice Standard for Earned Value Management.
Practice Standard for Project Risk management.
"Technical Performance Measurement, Earned Value, and Risk Management: An Integrated Diagnostic Tool for Program Management". Defense Acquisition University Acquisition Research Symposium, 1999.
"ANSI EIA-748 Standard - Earned Value Management Systems", Electronic Industries Alliance. 1998.
F. T. Anbari, “Earned value management: method and extensions”, Project Management Journal, Dec 2003; 34:4.
Andrzej Czemplik, “Application of Earned Value Method to Progress Control of Construction projects”, seminar, Theoretical Foundation of Civil Engineering, 2014.
Quentin W. F., Joel M. K., “Earned Value Management: Mitigating the Risks Associated with Construction Projects” Project Management March-April 2002.
Azeem S.A., Hossam E. Hosny, Ahmed H. Ibrahim, “Forecasting project schedule performance using probabilistic and deterministic models” HBRC Journal (2014)10, 35–42.
Fernando A., Javier P., José M. G. & Adolfo L. P., “Beyond Earned Value Management: A Graphical Framework for Integrated Cost, Schedule and Risk Monitoring”, 26th IPMA World Congress, Crete, Greece, 2012.
Robert T., Shaw C. & Mark B., “Earned Value Management: Moving towards government-wide implementation”, Acquisition Advisory, August 2005.
Quentin W. F. & Joel M. K., “Earned Value Project Management: A Powerful Tool for Software Projects”, Crosstalk The Journal of Defense Software Engineering, July 1998, 19-23.
A. Naderpour & M. Mofid, “Improving Construction Management of an Educational Center by Applying Earned Value Technique”, The Twelfth East Asia-Pacific Conference on Structural Engineering and Construction, 2011.
THANK YOU
Dedicated to:Dr. Muhammad Zaki Rashidi
Mr. Syed Ahsan RizviMr. Kashif Siddiqui
Mr. Muhammad Iftikhar Mubashir