Date post: | 05-Apr-2018 |
Category: |
Documents |
Upload: | truongtruc |
View: | 218 times |
Download: | 3 times |
1
Earned Value Project Management
Colonel John KeeseeColonel John Keesee
2
Objective
To introduce and discuss the fundamentals To introduce and discuss the fundamentals of earned value project managementof earned value project management
Work Breakdown StructuresWork Breakdown StructuresProgram plans and schedulesProgram plans and schedulesEarned value management systemsEarned value management systemsCost and schedule variancesCost and schedule variancesEstimates at completionEstimates at completion
3
Scenario
You have been tasked to be the project You have been tasked to be the project manager for an important projectmanager for an important project
You have been directed to use an earned You have been directed to use an earned value management systemvalue management systemTime to market is critical for this Time to market is critical for this developmentdevelopment
4
Work Breakdown Structure
Identifies 100 % of the work to be Identifies 100 % of the work to be accomplishedaccomplishedWBS dictionary breaks the scope into WBS dictionary breaks the scope into measurable tasksmeasurable tasks
Each with an estimated valueEach with an estimated valueResponsibility for each task assigned to Responsibility for each task assigned to individuals or work teamsindividuals or work teams
5
Work Breakdown Structure
Launch Vehicle
Payload Spacecraft Reentry vehicle Integration, Assembly,Test and Checkout
Space Vehicle Ground Command,Control, Communicationsand Mission Equipment
Space System
6
Project Master Schedule
Detailed plan and scheduleDetailed plan and scheduleIdentified dependencies between tasksIdentified dependencies between tasks
18 months18 monthsEstimated resources for each taskEstimated resources for each task
10 units at $150K each10 units at $150K each
7
Project Master ScheduleTask/Event Jan - Jun Jul - Dec Jan - JunAward ^Design ^Buy specifications ^Vendor quotes ^ Purchase orders ^Receive materials ^Factory plans ^Tool design ^Tool fabrication ^Parts fabrication ^Assembly: sub and final ^Test & checkout ^
8
Project Performance Display
0
200000
400000
600000
800000
1000000
1200000
1400000
1600000
Jan
April
July
Octobe
rJa
nuary Apri
l
July
BCWSBCWPACWP
9
Plan Review Before Go-Ahead
CEO:CEO:“Time to market is critical. You have 12 “Time to market is critical. You have 12 months.”months.”“This looks gold“This looks gold--plated at $1.5M. You plated at $1.5M. You have $1.0M.”have $1.0M.”“Go ahead, but come back to me with “Go ahead, but come back to me with your progress in three months.”your progress in three months.”
10
The Three Month Review
Three units scheduled for completionThree units scheduled for completionTwo units actually completedTwo units actually completed$300,000 budgeted at this point$300,000 budgeted at this point$300,000 actually spent$300,000 actually spentOptimist PM: “A little behind schedule but Optimist PM: “A little behind schedule but right on the cost plan.”right on the cost plan.”
11
Earned Value System
Requires a detailed, bottomsRequires a detailed, bottoms--up up performance planperformance planPerformance measured against the planPerformance measured against the planProvides forecast of final expected results Provides forecast of final expected results based on databased on data
12
Earned Value Measurements
1.1. Work scheduledWork scheduled2.2. Budgeted cost of work scheduled (BCWS)Budgeted cost of work scheduled (BCWS)3.3. Work performedWork performed4.4. Budgeted cost of work performed (BCWP)Budgeted cost of work performed (BCWP)5.5. Actual cost of work performed (ACWP)Actual cost of work performed (ACWP)6.6. Schedule variance (SV) = BCWP Schedule variance (SV) = BCWP -- BCWSBCWS7.7. Cost Variance (CV) = BCWP Cost Variance (CV) = BCWP -- ACWPACWP
13
New Project Performance Display
0
200000
400000
600000
800000
1000000
1200000
Janu
ary April
July
Octobe
rDec
embe
rBCWSBCWPACWP
14
Estimate at Completion
Cost efficiency CPI = BCWP/ACWPCost efficiency CPI = BCWP/ACWPSchedule efficiency SPI = BCWP/BCWSSchedule efficiency SPI = BCWP/BCWSEstimate at completionEstimate at completion
CPIBACEAC =1
SPICPIBCWPBACACWPEAC
*2
−+=
15
Management Reserve
Budgeted to provide the ability to adjust for Budgeted to provide the ability to adjust for uncertaintyuncertaintyAlways accounted at the total project levelAlways accounted at the total project levelNormally retained and controlled at the total Normally retained and controlled at the total project levelproject levelMust not be eliminated by negotiationsMust not be eliminated by negotiations
16
Summary
Earned value management system provides Earned value management system provides a key link between the cost, schedule, and a key link between the cost, schedule, and technical aspects of a projecttechnical aspects of a projectProvides an early and reliable prediction of Provides an early and reliable prediction of future performancefuture performance
17
References
Fleming, Quentin W. and Joel M. Fleming, Quentin W. and Joel M. KoppelmanKoppelman, , Earned Value Project Earned Value Project Management, Management, PMI, Newtown Square, PA PMI, Newtown Square, PA 20002000Lewis, James P., Lewis, James P., Fundamentals of Project Fundamentals of Project ManagementManagement, AMACOM, NY 2002, AMACOM, NY 2002