Earthwork Activities in Private Housing Industry LAM YUEN SIONG A project report submitted in partial fulfilment of the requirement for the award of the degree of Master of Science (Construction Management) Faculty of Civil Engineering Universiti Teknologi Malaysia NOVEMBER 2005
Transcript
Page 1: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

Earthwork Activities in Private Housing Industry

LAM YUEN SIONG

A project report submitted in partial fulfilment of the requirement for the

award of the degree of Master of Science (Construction Management)

Faculty of Civil Engineering

Universiti Teknologi Malaysia

NOVEMBER 2005

Page 2: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

iv

For my loving wife, Ho Chee Peng, and daughters

Christine, Stephanie, Odelia and Gene….

Page 3: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

v

ACKNOWLEDGEMENT

My special thanks and sincere gratitude to my supervisors, Assoc. Prof.

Aziruddin Ressang and Mr Bachan Singh, for their wise counsel and professional

comments and suggestions throughout our discussion has been a potent source of

inspiration. Their constant encouragement and able guidance without which it would

not have been possible for me to achieve this master project.

I whole heartedly thank all the academic and non-academic staff of the School

of Post Graduate Studies and the Civil Engineering Post Graduate Office of

University Teknologi Malaysia.

I am very grateful to all the respondents who participated in this study and

help me realize this master project, for it would not have been possible without all of

your contribution.

I also wish to thank Jasin Construction Development Sdn. Bhd. for allowing

me to conduct my study in one of their project without which I would not be able to

complete this study.

Last but not least I wish to thank my dear wife, Ho Chee Peng, and my

obedient and understanding daughters, Christine, Stephanie, Odelia and Gene who

unfailingly offered comfort and love throughout my studies.

Page 4: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

vi

ABSTRAK

Kejayaan dan kegagalan sesebuah projek perumahan bergantung kepada

aktiviti kerja tanah kerana aktiviti kerja tanah adalah aktiviti pertama dalam projek

perumahan. Dalam pelbagai situasi, keadaan yang tidak dapat diramalkan boleh

mempengaruhi anggaran perlaksanaan serta output jentera menyebabkan tempoh

aktiviti sebenar lebih panjang daripada tempoh perancangan. Tujuan kajian ini adalah

untuk mengkaji operasi pemindahan tanah dalam projek perumahan, mengkaji kadar

penghasilan permindahan tanah dalam projek perumahan, mengenalpasti masalah

yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan untuk

mengenalpasti faktor-faktor yang mempengaruhi harga tender kontraktor. Data

dikumpul dari organisasi pembinaan melalui soal selidik. Data yang diperolehi

dianalisa dengan kaedah indeks purata. Perbandingan pengeluaran pemindahan tanah

menggunakan kitaran purata masa berdasarkan kepada jadual anggaran permindahan

tanah dan kajian masa dan pergerakan yang dijalankan di tapah bina dilakukan. Hasil

kajian didapati secara am, prosedur kerja tanah bagi projek perumahan tidak

mengambil berat tentang persekitaran dan kawalan kualiti, meyebabkan kerja kerja

pemindahan tanah tidak mengikut spesifikasi piawai JKR. Tiada perbezaan yang

ketara bagi pengeluaran permindahan tanah di antara jadual anggaran pemindahan

tanah berbanding dengan kajian masa dan pergerakan semasa pembinaan. Masalah

dihadapi oleh kontraktor berpunca daripada keputusan klien dan kepastian asas

pelantaran akhir projek, rekabentuk daripada perunding dan maklumat ukur tanah

yang tidak tepat. Harga tender kontraktor dipengaruhi oleh reputasi klien untuk

membayar serta kelarasan penjualan rumah oleh klien.

Page 5: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

vii

ABSTRACT

The success and failure of a housing project depends on the earthwork

activities as it is the first activity in any housing development project. In many

instances, many unforeseen circumstances that affect the estimates of plant

performance, output, and hence the duration of activities, fall short of the actual

situation once construction start. The purpose of this study is to study the

earthmoving operation in a private housing development project, to study the

earthmoving production in a private housing development project, to identify the

problems faced by the contractors during the earthmoving activities and to identify

the factors that influence the contractors pricing during bidding. Data was gathered

from the local construction organizations by means of a survey questionnaire which

was further analyzed using the average index computation to portray the ranking of

the associated factors. A comparison of earthmoving production using the average

cycle time based on earthmoving production estimating table and the motion and time

study conducted at one of the project site. The finding revealed that generally

earthwork procedure for private housing project does not emphasize on the

environmental and quality control and thus the works carried out do not follow the

standard JKR specification. It was apparent that there is not much variation from the

earthmoving production estimating table for the excavator cycle time as compare to

the excavator cycle time from the motion and time study during construction. The

main problems that the contractor faced stem from the client’s decision and

confirmation on the final platform levels of the projects, the design provided by the

consultant and the inaccurate survey information. The final pricing during bidding

was highly influence by the client’s reputation to pay and the financial status which

normally depends on the sale of the houses built.

Page 6: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

viii

TABLE OF CONTENTS

CHAPTER TITLE PAGE

CHAPTER I INTRODUCTION

1.1 Introduction 1

1.2 Background of study 4

1.3 Statements of problem 7

1.4 Objective of study 8

1.5 Scope of study 9

1.6 Significant of research 9

CHAPTER II EARTHMOVING IN HOUSING PROJECT

2.1 Introduction 11

2.2 Setting out 12

2.3 Erosion control 13

2.4 SITE CLEARING 14

2.4.1 Removal of structures, trees, bushes, etc 14

2.4.2 Removal of stumps, roots, etc. 14

2.4.3 Top soil 14

2.4.4 Disposal of Material 15

2.5 EXCAVATION 15

2.5.1 General 15

2.5.2 Over Excavation 16

2.5.3 Removal of Excavated Material From Site 16

Page 7: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

ix

2.5.4 Removal of Unsuitable Material 17

2.5.5 Excavation of Rock 17

2.5.6 Storage and Handling of Explosives 18

2.5.7 Blasting 18

2.5.8 Safety Measures 19

2.5.9 Insecure Material 19

2.6 EMBANKMENTS 20

2.6.1 General 20

2.6.2 Material 20

2.6.3 Placement of Fill Material 20

2.6.4 Rock Fill Embankment 21

2.7 COMPACTION 22

2.7.1 General 22

2.7.2 Compaction Trials 22

2.7.3 Degree of Compaction 23

2.7.4 Moisture Control 23

2.7.5 Rock Fill Compaction 24

2.7.6 Confined area 24

2.7.7 Dewatering and Drainage 24

2.7.8 The Permitted Deviations for General Site

Excavation / Filling Level and Slope Surface.

25

CHAPTER III ESTIMATING AND TENDERING

EARTHWORKS IN HOUSING PROJECT

3.1 Introduction 26

3.2 Methods Of Obtaining Tenders And Types Of Contract 27

3.3 The Importance of The Estimate 31

3.3.1 The Estimate and the Tender 31

3.3.2 Tender Evaluation 32

3.4 Bidding Strategy 33

3.4.1 Factors to Be Considered While Making Out 33

Page 8: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

x

Analysis for a Project

3.4.2 Preplanning 35

3.5 Method of Estimating 36

3.5.1 A Queuing Analysis 37

3.5.2 The Waiting Line Theory 38

3.5.3 Earthmoving Production Estimate From

Production Table

40

3.5.4 Construction Schedule 42

CHAPTER IV EARTHMOVING EQUIPMENTS, SELECTION,

MATCHING AND PRODUCTION OUTPUT

4.1 Introduction 43

4.2 Types of Earthworks Equipment Used in Housing

Project

44

4.2.1 Bulldozers 44

4.2.2 Excavators 45

4.2.3 Trucks 45

4.2.4 Scrapers 46

4.2.5 Motor graders 47

4.2.6 Earth Compactor 47

4.3 Earthmoving Production Estimate, Sizing And

Matching

48

4.3.1 Procedure for Equipment Design 48

4.3.2 Cycle Time 49

4.3.3 Corrections To Cycle Time 50

4.3.4 Production Estimates for Excavators And

Sizing Of Hauling Units

51

4.3.5 Time and Motion Studies on Earthmoving

Production

51

4.3.6 Sizing And Matching of Hauling Units 54

4.4 Job And Management Factors on The Output Rate 56

Page 9: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

xi

4.4.1 The Effect of Job Conditions on The Output

Rate

57

4.4.2 The Effect of Management Conditions on The

Output Rate

58

CHAPTER V

METHODOLOGY OF STUDY

5.1 General 60

5.2 Methodology Approach 61

5.2.1 Literature Review 61

5.2.2 Identifying problem statement 62

5.2.3 Survey Questionnaire 62

5.2.4 Time and Motion Recording Sessions 63

5.2.5 Interviews 63

5.2.6 Compilation of Findings, Analyses and

Conclusion

63

5.3 Methodology Work Flow and Time Frame 65

CHAPTER VI DATA ANALYSIS

6.1 General 68

6.2 Earthwork activities in a housing projects 76

6.2.1 Operation of earthmoving activities 76

6.2.2 Time and Motion Study 79

6.2.3 Significant problems that the contractor faced

during the earthmoving activities

82

6.2.4 Method of obtaining tenders 84

6.2.5 Factors that influence the pricing during

bidding

85

6.2.6 The project site detail information need to 87

Page 10: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

xii

consider during tendering

CHAPTER VII CONCLUSION AND RECOMMENDATIONS

7.1 General 89

7.2 Earthwork activities in a housing project 90

7.3 General Conclusion 93

7.3.1 Earthmoving Operation in a Housing

Development Project

94

7.3.2 The Earthmoving Production in a Private

Housing Project

95

7.3.3 Problems Faced by the Contractors during The

Earthmoving Activities

96

7.3.4 Factors that influence the pricing during

bidding

97

7.4 Recommendation for Improvements 97

7.5 Summation 99

REFERENCES 100

APPENDICES 103

Page 11: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

xiii

LIST OF TABLES

TABLE

NO

TITLE PAGE

4.1 Corrections to cycle time 50

4.2 Factors for job and management conditions 59

5.1 Allocation of Time for Undertaking the Study 67

6.1 Percentage distribution of respondent’s organization

registered with PKK

68

6.2 Percentage distribution of respondent’s organization

registered with CIDB

69

6.3 Percentage distribution of respondent’s organization

involvement in the building earthwork construction

70

6.4 Percentage distribution of respondent’s scale of

earthwork project

71

6.5 Percentage distribution of respondent’s scale of

earthwork project in terms of volume (M3)

72

6.6 Percentage distribution of respondent’s experience 73

6.7 Percentage distribution of respondent’s nature of projects

undertaken

74

6.8 Percentage distribution on respondent’s level of

agreement that Private Development Projects were more

preferred compared to Government Projects

75

6.9 The priorities in the ranking order for selecting the

sequence of earthwork activities

77

Page 12: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

xiv

6.10 Percentage distribution on the decision making during

the construction period

78

6.11 Earthmoving production base on production estimating

table

80

6.12 Time and Motion Study 81

6.13 Ranking of problems faced by the contractor during the

earthmoving activities

83

6.14 Type of tender practice by private developer 84

6.15 Ranking of factors that influence the contractors pricing

during bidding

86

6.16 Ranking of factors need to consider during bidding 88

Page 13: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

xv

LIST OF FIGURES

FIGURE

NO

TITLE PAGE

3.3 Schematic representation of excavator-truck operation 39

4.1 Time study for an excavator 53

4.2 Time study for a wheel-type scraper 55

5.1 Methodology Flow Chart 66

6.1 Percentage distribution of respondent’s organization

registered with PKK. and CIDB

69

6.2 Percentage distribution of respondent’s organization

involvement in the building earthwork construction

70

6.3 Scale of Earthwork Project undertaken by Respondent’s

Organization

71

6.4 Percentage distribution of respondent’s scale of

earthwork project in terms of volume (M3)

72

6.5 Percentage distribution of respondent’s experience 73

6.6 Percentage distribution of respondent’s nature of

projects undertaken

74

6.7 Determination if private development projects were

more preferred compared to Government projects

75

6.8 The lead role in making decision during the construction

period

78

Page 14: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

xvi

LIST OF APPENDICES

ITEM TITLE PAGE

A Production Estimating Table 104

B Time and Motion Observation Sheet for Hauling Unit 105

C Time and Motion Observation Sheet for Excavator 106

D Survey Questionnaire Sample 107

Page 15: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

CHAPTER I

INTRODUCTION

1.1 INTRODUCTION

The rapid development of the housing construction industry in Malaysia in

recent years and the magnitude of the present-day constructions involved the

movement of large amount of earth excavations, cuttings and embankments may

be a substantial part of the overall project. These operations are relatively

repetitive and machine-oriented, being performed under the pressure to improve

productivity, efficiency and safety. (Jagman Singh, 1980) described the

conventional procedures for equipment management involving selection,

performance, estimating, maintenance, repairs and replacements etc. are not

enough in view of their incapability of approximating the real life phenomena

closely. These procedures usually provide estimates that are quite off the true

values. As the problems of management become more complex, the divergence of

results as obtained through conventional procedures and actual results becomes

greater. To a housing developer time is of the essence and the duration for the

completion of the projects will be as short as possible. To achieve the success of

the project within cost and time will require adequate planning and

implementation of earthworks and earthwork activities.

Earthmoving operations in the Malaysian housing industries normally

consist of a continuous process of the following phases:

Page 16: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

2

Phase 1: Site preparation

Demarcation of site boundary

Clearing and grubbing – vegetation, and debris (e.g., tree, brush,

buried vegetation, trash, stumps, roots, etc.)

Stripping top soil

Phase 2: Bulk excavation and filling

Cutting and filling

Load, haul and dump

Spread and compact

Phase 3: Finish work

Formation of roads and building platforms

Grade and trim to finish level

Phase 1: Site preparation

The earthwork starts with the demarcation of the site boundary and

preparation for the materials to be moved. Site clearing consist of clearing,

grubbing and stripping topsoil in the area designated in the drawings. Clearing

consist of cutting and/or taking down, removal and disposal of everything above

ground level. Grubbing consist of the removal and disposal of surface

vegetation, the bases of stumps, roots, the underground parts of structures, and

other obstructions to a depth of at least 0.5 metre below ground level.

Stripping of top soil consist of the removal of topsoil to an average depth

of at least 150mm below ground level, from the areas within cuttings and

embankments and stockpiling for reuse for any purpose such as the soiling of

slopes of cuttings and embankment, and benches.

Page 17: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

3

Phase 2: Bulk excavation and filling

Bulk excavation consist of materials excavated from the designated high

areas to the required depths and levels in accordance with the drawings, for

formation of roads, open spaces and building platforms within the limits of the

contract area.

Filling, consist of the excavation of suitable materials from high areas and

other approved sources is used for filling up of designated low areas to the

required levels in accordance with the drawings for formations of roads, open

spaces and building platforms. Filling can only be carried out after the original

ground has been cleared and any trees or organic materials removed. All materials

used in embankments and as fill is then compacted as soon as practicable after

being placed and spread.

Phase 3: Finish work

Surface finish for the formations of roads and building platforms shall be

finished fair, free of potholes, gullies and depressions where water may

accumulate. The surface of slopes shall be trimmed to an even profile.

In Malaysian housing industry earthmoving operation, normally involve

excavators loading a fleet of trucks and their proper matching in size is quite

important. The current procedures for equipment management involving selection,

performance, estimating, maintenance, repairs and replacements etc. are not

enough in view of their incapability of approximating the real life phenomena

closely. These procedures usually provide estimates which are quite off the true

values. As the problems of management become more complex, the divergence of

results as obtained through current procedures and actual results becomes greater.

The sizing of the haul units and estimation of production of the team is done using

Page 18: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

4

average values of arrival rate of trucks at the loader and loading rate by the

excavator. Experience, however, indicates that this procedure does not give

accurate results, and the performance as estimated is usually on the higher side.

The reason is that the arrival and the loading of the trucks at the excavator are

random phenomena which cannot be approximated by working with average

values.

Some other procedures have, therefore, to be devised which would help

analyze the problems in a more realistic manner in order to complete the project in

time and within estimated cost. Motion and time study conducted at the start of

the project and by comparing it with the earthmoving production estimating table

offers the prospect of a useful management and monitoring tool.

1.2 BACKGROUND OF STUDY

In the earthmoving industry for a housing project is a constant challenge

to a contractor’s vision, ingenuity and to his experience and it has been termed the

biggest gamble in the business field. This is mainly due to a combination of

various factors which influence the operation performance, among them,

earthwork characteristics, job-site conditions, equipment characteristics, and

construction methods.

The operation performance can be measured by several performance

criteria, which can be classified into time (duration), cost, and safety. It is evident

that effective operations are a multi criteria problem. However, in this section, the

focus is on the duration and cost of operations.

The production rate can be calculated by dividing the number of units

produced by the duration of earthwork operations, and the minimization of project

duration is highly dependent on the production rate. There are a wide variety of

factors that affect the duration of earthwork operations. Considering the

significance of their influence, the affecting factors can be categorized into four

Page 19: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

5

groups (Automation in Construction 12 (2003) 1-13, Kim and Jeffrey), which are

closely correlated with each other:

Work characteristics

Magnitude of the job (quantity of earth to be moved)

Layout and space constraint

Job-site conditions

Weather

Soil types and conditions

Haul road and gradients.

Equipment characteristics

Capacity (production rate)

Efficiency

Cycle time (combination of excavators and trucks)

Unexpected breakdown rate of equipment.

Economic haul distance

Motion and path planning strategy

Management

Planning the sequence of work

Method of construction.

Select a proper number of equipment

Page 20: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

6

In the first group, Magnitude of the job (quantity of earth to be moved) is

directly related to the duration of earthwork operations. Obviously, different

magnitude of the job will result in different duration. Even the same type of work

will have different work durations due to the differences in work volume, site

conditions, construction methods, and so forth. The layout and space constrain

affects the productivity of equipment in the given project. Concurrent activities of

multi equipment interfere with each other because of their requirement for

workspace within a confined area.

There are several affecting factors associated with the job site conditions

which include weather, soil conditions, and road conditions. As for Malaysian

weathers which is unpredictable greatly affects the duration of the earthwork

operations. In general, bad weather decreases the efficiency of construction

equipment. Various types of soil create different levels of difficulty in stripping

and excavating soil, and are related to the rolling resistance that affects both

production rate and the financial investment of an earthwork contractor. The haul

road and gradient is related with the effectiveness of haul and return trip of

construction equipment.

Equipment is an important resource for earth moving construction projects

that require a large concentration of construction equipment. In housing project,

the selection of equipment is directly affected by the magnitude of the job. In an

equipment-intensive project, it is clear that the proper equipment selection will

result in the minimization of project duration and the maximization of output of

work tasks.

The last group, management of operations, includes construction method,

planning the sequence of work tasks, and allocating the proper amount of required

equipment. For example, if two or more equipment fleets are involved in

earthwork operations at the same time at a constrain area, to transport the stripped

Page 21: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

7

soil to the fill area, there will be space interference that will result in the decrease

of productivity. To avoid this problem, the combination and number of

equipments to be used for interference free sequence of work tasks should be

planned in advance. Depending on the work environment and hauling distance, a

variable amount of construction equipment should be assigned to each equipment

fleet rather than a fixed amount throughout the earthwork operation process.

Among various affecting factors, planning the sequence of work tasks,

equipment selection, and equipment motion and path planning are controllable

factors to minimize the duration of earthwork operations.

1.3 STATEMENTS OF PROBLEM

The common choices of machineries for bulk excavation in housing

projects are combination of excavators and dump trucks. Like many construction

activities, earthworks are planned using data from previous projects together with

manufacturer’s performance charts. In many instances, many unforeseen

circumstances that affect the estimates of plant performance, output, and hence the

duration of activities, fall short of the actual situation once construction start. To

understand the project the researcher conducted a study on the earth work

activities carried out in various projects by interviewing with the project site

people. From the interview the researcher found that most of the projects were

either delay or cost overrun and it was due to 1) low bid, 2) insufficient

knowledge of job conditions, 3) adverse weather conditions, 4) improper selection

of construction equipment and 5) inefficient management and supervision. How

far these factors given will affect the project, here a study will be conducted.

Consequently, the potential for contractors’ losses on earthwork is large: this will

lead to contractual claims to recover those losses. Staples et al. (1992) estimated

that the annual value of earthworks claims during the early 1990s ran into many

millions of pound.

Page 22: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

8

The selection of equipment is very important, for its selection and

operation determine both cost and time. Methods and equipment which give the

minimum unit cost within the construction schedule have to be adopted. A cubic

metre forms the basis of calculation. The contractor figures costs and profit on a

cubic metre basis. If his estimates are correct and his bid low, he clinches the

contract. But he should know that the simple cubic metres on the basis of which

he bids differ from the loose cubic metres which he actually hauls. It seldom

weights the same and expands when disturbed. When hauling the cubic metre, a

dump truck will need to overcome rolling resistance. The contractor should also

reckon the cost and time in loading and dumping accelerating, breaking and

shifting gears. Lastly he should remember that neither people nor machines work

60 minute hours and should make allowance for operation fatigue and routine

maintenance. All these considerations should determine the final time of cubic

metre. Experience and practical judgement, of course, play an important role and

the key to success.

Earthmoving operations are a major part of housing construction projects.

Because of their labour and plant intensity, the planning, estimating, monitoring

and control is crucial to both cost and duration of the project. Earthworks are the

first activity for a housing project and are considered by many to be indicators to a

success or failure of the project as a whole. The fact that quite often contractors

have gone bankrupt establishes that success is more elusive today in every area of

construction. This may be due to various reasons such as hard competition and

tighter economic conditions. But at many jobs contractors have lost mainly due to

bad management, wrong selection of equipment and unrealistic assumptions made

in the bids like work characteristics and job site condition.

1.4 OBJECTIVES OF THE STUDY

This study is to analyze and identify the different constrain that affect the daily

work output production rate and cost by earthwork contractors specialized in bulk

Page 23: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

9

excavation and filling platform for housing development in Malaysia. In this study

we shall only consider excavators and dump trucks.

The objectives of the study are:

1. To study the earthmoving operation in a private housing

development project.

2. To study the earthmoving production in a private housing

development project.

3. To identify the problems faced by the contractors during the

earthmoving activities.

4. To identify the factors that influences the contractors pricing

during bidding.

1.5 SCOPE OF STUDY

This study focuses on the bulk earthwork excavation for private housing

development projects which has either been completed or currently in progress.

One of the project sites will be selected to conduct a time and motion study to

study the excavator and truck cycle time. The targeted participants would

comprise of contractors involved in earthwork for private housing development

projects in the state of Johore, Selangor and Negri Sembilan.

1.6 SIGNIFICANCE OF RESEARCH

The earthmoving industry continues to challenge construction men,

possibly largely because no two earthmoving jobs are the same. Each present its

own problems; each differs from another; and each requires different (or at least,

‘modified’) approach. It has been rightly said that “earthmoving is the biggest

gamble in the construction world”. Proper emphasis should be given to a basic

Page 24: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

10

principle: “Reduce downtime, achieve optimum equipment utilisation and

increase production at minimum cost”.

The rapid development of the housing construction industry in Malaysia in

recent years and the magnitude of the present day constructions involved the

movement of large amount of earth excavations, cuttings and embankments may

be a substantial part of the overall project. The developers are more concerned

with time and cost and since time is of the essence it was also noted that the

duration is short and cost reduced. This study attempts to examine the sequence of

earthwork activities carried out in a private development project that will

influence the pricing during bidding and to complete the project in time. The study

aims to look at the effects of using the earthmoving production estimating table

and identify some of the problems that may arrive during construction using

motion and time study. The study also aims at identifying the problems faced by

the contractors during construction and the factors that will influence the pricing

during bidding. The researcher hope that the introduction of the motion and time

study of daily trips the contractors, engineers and client or developer will enhance

the awareness on the important of tracking the actual earthmoving production that

will have consequential influence to the duration and cost. Hence to improve and

strengthen their organization, in order to increase the awareness at an early stage

the actual project performance and to achieve the completion of the project

performance within time and cost for every construction development carried out

by them.

Page 25: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

100

REFERENCE

1. Jagman Singh, Art of Earthmoving (1980), Second Edition, Oxford & IBH

Publishing Co. (New Delhi, Bombay, Calcutta).

2. R.L.Peurifoy (1979), Construction Planning, Equipment, and Methods, Third

Edition, International Student Edition, McGraw-Hill Kogakusha, LTD.

3. Dr. Mahesh Varma (1981), Construction Equipment And Its Planning And

Application, Third Edition, Metropolitan Book Co. (P) LTD. 1, Netaji

Subhash Marg, New Delhi – 110002 India.

4. Jagman Singh (1993), Heavy Construction-Planning, Equipment And

Methods, A.A Balkema/Rotterdam.

5. Caterpillar Performance Handbook (1989) 20th. Edition, Caterpillar Inc,

Peoria, Illinois, U.S.A.

6. Caterpillar Performance Handbook (1992) 23th. Edition, Caterpillar Inc,

Peoria, Illinois, U.S.A.

7. David G. Carmichael (1986), ‘Shovel-Truck Queues: A Reconciliation Of

Theory And Practice’. Construction Management and Economics, 4, 161-

177.

8. Jonathan JingSheng Shi (1999), ‘A Neutral Network Based System For

Predicting Earthmoving Production’. Construction Management and

Economics, 17, 463-471.

Page 26: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

101

9. Smith, S.D et al (2000), ‘A New Earthworks Estimating Methodology’.

Construction Management and Economics, 18, 219-228.

10. Mohamed Marzouk et al (2002), ‘Simulation Optimization For Earthmoving

Operations Using Genetic Algorithms’. Construction Management and

Economics, 20, 535-543.

11. Sung-Keun Kim et al (2003), ‘Framework For An Intelligent Earthwork

System Part I. System Architecture’. Automation in Construction, 12, 1-13.

12. Sung-Keun Kim et al (2003), ‘Framework For An Intelligent Earthwork

System Part II. Task Identification/Scheduling And Resource Allocation

Methodology’. Automation in Construction, 12, 15-27.

13. Sanjiv Singh (1997), ‘State Of The Art In Automation of Earthmoving’.

American Society Of Civil Engineers.

14. Edwards, D.J et al (2002), ‘Predicting Down Time Costs Of Tracked

Hydraulic Excavators Operating In The UK Opencast Mining Industry’.

Construction Management and Economics, 20, 581-591.

15. Jonathan JingSheng Shi (2002), ‘Three Methods For Verifying And

Validating The Simulation Of A Construction Operation’. Construction

Management and Economics, 20, 483-491.

16. David, M. Wall (1997), ‘Distributions And Correlations In Monte Carlo

Simulation’. Construction Management and Economics, 15, 241-258.

17. Chau Kwong Wing (1997), ‘Monte Carlo Simulation of Construction Costs

Using Subjective Data: Response’. Construction Management and

Economics, 15, 109-115.

Page 27: Earthwork Activities in Private Housing Industryeprints.utm.my/id/eprint/3703/1/LamYuenSiongMFKA2005.pdf · yang dihadapi oleh pihak kontraktor semasa aktiviti permindahan tanah dan

102

18. Gross, D et al (1974), Fundamentals of Queueing Theory, John Wiley, New

York.

19. Leslie Black, 11th Edition, Builder’s Reference Book, Northwood Books,

London EC1V7QA.

20. Smith, G.C (1976), ‘Guide to Estimating-5, Cost Analysis of Excavation

Work in Various Soils’. Building Trades Journal, 1976, 22-31.

21. Bell, J. (1997). Doing Your Research Project. 2nd ed. Great Britain: Open

University Press.

22. Mc Niff, J. (1988). Action Research: Principle and Practice. Hong Kong:

Mc Millan Education Ltd.