EARTHWORKS COMPLETION REPORTELLEN STIRLING PARADE,
ELLENBROOK
Ellenbrook, W.A.Georgiou Group Pty Ltd
GEOTPERT08050AZ-AH27 March 2013
7/24/2019 Earthworks Completion Report
2/70
27 March 2013
EARTHWORKS COMPLETION REPORTELLEN STIRLING PARADE,
ELLENBROOK
Ellenbrook, W.A.Georgiou Group Pty Ltd
GEOTPERT08050AZ-AH27 March 2013
7/24/2019 Earthworks Completion Report
3/70
7/24/2019 Earthworks Completion Report
4/70
CONTENTS
1 INTRODUCTION 1
2 PROPOSED DEVELOPMENT 1
3 EARTHWORKS 1
4 BACKGROUND INFORMATION 2
5 INFORMATION SUPPLIED BY OTHERS 2
6 COMPACTION CRITERIA 2
7 CONTRACTORS TEST RESULTS 3
8 COFFEY FIELD OBSERVATIONS AND TESTING 3
8.1 Earthworks Monitoring 3
8.2 Audi t Compaction Testing 3
9 DISCUSSION 3
9.1 General 3
7/24/2019 Earthworks Completion Report
5/70
ATTACHMENTS
Figures
1 PSP Test Location Plan 13/12/2012
2 PSP Test Location Plan 16/01/2013
3 PSP Test Location Plan 08/02/2013
Append ices
A Cossill & Webley Earthworks Specification (14 pages)
B Georgiou Group Pty Ltd Earthworks Confirmation Letter (1 page)
C Georgiou Group Pty Ltd Site Compaction Records (14 pages)
D Coffey PSP Field Test Results (10 pages)
E Laboratory Test Results (6 pages)
7/24/2019 Earthworks Completion Report
6/70
EARTHWORKS COMPLETION REPORT
ELLEN STIRLING PARADE, ELLENBROOK
1 INTRODUCTION
This Earthwork Completion Report (ECR) presents the results of part time monitoring carried out by
Coffey Geotechnics Pty Ltd (Coffey) of the earthworks for Georgiou Group Pty Ltd (Georgiou) for Ellen
Stirling Parade located close to the town centre, Ellenbrook WA. Coffeys level of involvement is
equivalent to Level 2 Geotechnical Investigation Authority of AS3798-2007.
These services were provided and carried out in accordance with Coffeys proposal dated 7 November
2012 (Ref: GEOTPERT08050AZ-AC-P) and were commissioned by Sinisa Rakovic of Georgiou via a
completed and signed Consultancy Agreement form dated 31 October 2012.
It should be noted however, that the requirements of the proposal related specifically to Level 1
Inspection and Testing for the proposed Bunnings Store located on The Promenade and that
subsequently works for the nearby Urbano residential development and Ellen Stirling Parade were
included within this scope, though not the requirement for Level 1 Inspection and Testing.
This work was carried out to provide an independent review of the compaction of bulk earthworksrequired to bring Ellen Stirling Parade and adjacent lots to design levels.
2 PROPOSED DEVELOPMENT
It is understood that the project involves bulk fill earthworks along the Ellen Stirling Parade alignment
and adjacent lots to achieve design levels. Ellen Stirling Parade is aligned roughly east to west and is
about 325m north of Urbano and being parallel to The Promenade, to the north, and The Parkway, to
the south The extent of earthworks associated with Ellen Stirling Parade covered by this report is about
7/24/2019 Earthworks Completion Report
7/70
EARTHWORKS COMPLETION REPORT
ELLEN STIRLING PARADE, ELLENBROOK
4 BACKGROUND INFORMATION
Coffey has been involved with geotechnical investigation and earthworks monitoring during the ongoing
development of Ellenbrook since its inception in 2000.
Coffey has previously performed two site specific geotechnical investigations for the adjacent
Ellenbrook Town Centre Retail and Middle School sites in November 2002 and April 2005 respectively.
Prior to earthworks geotechnical investigation reports were prepared, dated 20 November 2002 (Ref:
P2572/16-AB) and 18 April 2005 (Ref: P2572.60-AA Rev 1). The conclusions and recommendations of
the reports have been reviewed during the preparation of this document.
Fieldwork during the investigation for the Ellenbrook Town Centre Retail site comprised 27 test pits, 27
Perth Sand Penetrometer (PSP) tests and 9 Electric Friction Cone Penetration (CPT) tests. The
investigations identified that these areas were underlain by Bassendean Dune Sand. The sand was
assessed as loose to medium dense within the top two metres of the natural ground surface.
CPTs were carried out at 6 locations to depth varying from 4.0m to 5.0m below the existing groundsurface of the Middle School site. The ground conditions encountered during the investigation
comprised medium dense to dense sand to a depth of 5.0m below the natural ground surface.
It should be noted that cohesive fill materials have previously been placed within the footprint of Ellen
Stirling Parade, as part of bulk earthworks for the adjacent Parkway road alignment in 2012. Details of
these works are presented in Coffeys earthworks completion report, dated 23 September 2012 (Ref:
GEOTPERT08050AY-AA) and letter, dated 13 June 2012 (Ref: GEOTPERT08050AY-AB), which
should be read in conjunction with this report.
7/24/2019 Earthworks Completion Report
8/70
EARTHWORKS COMPLETION REPORT
ELLEN STIRLING PARADE, ELLENBROOK
7 CONTRACTORS TEST RESULTS
Georgiou performed compaction testing on the compacted sand fill during fill placement using a Perth
Sand Penetrometer (PSP). The compaction testing was carried out between 24 November 2012 and 15
January 2013. The PSP test results are attached in Appendix C and indicate that the compaction
criteria has been achieved.
8 COFFEY FIELD OBSERVATIONS AND TESTING
8.1 Earthworks Monitoring
Site visits were carried out by personnel from Coffey to observe topsoil stripping and bulk fill placement.
Site visits were undertaken to assess earthworks Coffey personnel made site visits to assess topsoil
stripping, subgrade suitability and bulk earthworks compaction for Ellen Stirling Parade between
November 2012 and February 2013.
8.2 Audi t Compaction Testing
The results of the PSP testing confirm that the sand fill has been compacted sufficiently to achieve the
requirements of the specification. Coffey PSP testing results are presented in Appendix D. Coffey PSP
test locations are presented on Figures 1 3.
9 DISCUSSION
7/24/2019 Earthworks Completion Report
9/70
EARTHWORKS COMPLETION REPORT
ELLEN STIRLING PARADE, ELLENBROOK
Builder to ensure that footing designs and construction are compliant with the building foundation
design for the lot in accordance with the Lot classification referenced to AS 2870-2011 and to carry out
their own compaction checks on a lot by lot basis and compact any localised loose soil zones identified.
The owner of the property has a requirement to maintain the property and foundations in accordance
with AS 2870-2011, including but not limited to, maintaining adequate drainage away from the house
foundations. Purchasers should be provided with a copy of the CSIRO Information Sheet BTF 18
(Foundation Maintenance and Footing Performance: A Homeowner's Guide) available for download athttp://www.publish.csiro.au/pid/7076.htm
10 IMPORTANT INFORMATION ABOUT YOUR COFFEY REPORT
The readers attention is drawn to the important information about this report which follows the main
text.
7/24/2019 Earthworks Completion Report
10/70
As a client of Coffey you should know that site subsurface conditions cause more construction
problems than any other factor. These notes have been prepared by Coffey to help you
interpret and understand the limitations of your report.Your report is based on project specific criteria
Your report has been developed on the basis of your
unique project specific requirements as understood
by Coffey and applies only to the site investigated.
Project criteria typically include the general nature of
the project; its size and configuration; the location of
any structures on the site; other site improvements;the presence of underground utilities; and the additional
risk imposed by scope-of-service limitations imposed
by the client. Your report should not be used if there
are any changes to the project without first asking
Coffey to assess how factors that changed subsequent
to the date of the report affect the report's
recommendations. Coffey cannot accept responsibility
f bl th t d t h d f t
Your report will only give
preliminary recommendations
Y t i b d th ti th t th
earth, rock and time. The actual interface between
materials may be far more gradual or abrupt than
assumed based on the facts obtained. Nothing can
be done to change the actual site conditions which
exist, but steps can be taken to reduce the impact of
unexpected conditions. For this reason, ownersshould retain the services of Coffey through the
development stage, to identify variances, conduct
additional tests if required, and recommend solutions
to problems encountered on site.
Important information about your CoffeyReport
7/24/2019 Earthworks Completion Report
11/70
Interpretation by other design professionals
Costly problems can occur when other design professionals
develop their plans based on misinterpretations
of a report. To help avoid misinterpretations, retain
Coffey to work with other project design professionals
who are affected by the report. Have Coffey explain
the report implications to design professionals affected
by them and then review plans and specifications
produced to see how they incorporate the report
findings.
Data should not be separated from the report*
The report as a whole presents the findings of the site
assessment and the report should not be copied in
part or altered in any way.
Logs, figures, drawings, etc. are customarily included
in our reports and are developed by scientists,
engineers or geologists based on their interpretation
f fi ld l ( bl d b fi ld l) d
Rely on Coffey for additional assistance
Coffey is familiar with a variety of techniques and
approaches that can be used to help reduce risks for
all parties to a project, from design to construction. It
is common that not all approaches will be necessarily
dealt with in your site assessment report due to
concepts proposed at that time. As the project
progresses through design towards construction,
speak with Coffey to develop alternative approaches
to problems that may be of genuine benefit both in
time and cost.
Responsibility
Reporting relies on interpretation of factual information
based on judgement and opinion and has a level of
uncertainty attached to it, which is far less exact than
the design disciplines. This has often resulted in claims
being lodged against consultants, which are unfounded.
To help prevent this problem, a number of clauses
h b d l d f i t t t d
Important information about your CoffeyReport
7/24/2019 Earthworks Completion Report
12/70
Figures
7/24/2019 Earthworks Completion Report
13/70
PSP1
PSP2
PSP3
PSP4
PSP5PSP6
PSP7
PSP8
PSP9
PSP10 PSP11
PSP12
PSP13
PSP14
PSP15
PSP16
7/24/2019 Earthworks Completion Report
14/70
PSP1
PSP2PSP3
PSP4
PSP5
PSP6
PSP7
PSP8 PSP9
PSP10
PSP11
PSP12PSP13
PSP14
PSP15
PSP1
P
7/24/2019 Earthworks Completion Report
15/70
PSP1PSP2
PSP3
PSP4PSP5 PSP6
PSP7
PSP8
PSP9
PSP10
PSP11
PSP12
PSP13
PSP14PSP15
PSP16PSP17
PSP18
PSP23
7/24/2019 Earthworks Completion Report
16/70
Appendix AC ill & W bl E th k S ifi ti
7/24/2019 Earthworks Completion Report
17/70
7/24/2019 Earthworks Completion Report
18/70
7/24/2019 Earthworks Completion Report
19/70
7/24/2019 Earthworks Completion Report
20/70
7/24/2019 Earthworks Completion Report
21/70
7/24/2019 Earthworks Completion Report
22/70
7/24/2019 Earthworks Completion Report
23/70
7/24/2019 Earthworks Completion Report
24/70
7/24/2019 Earthworks Completion Report
25/70
7/24/2019 Earthworks Completion Report
26/70
7/24/2019 Earthworks Completion Report
27/70
7/24/2019 Earthworks Completion Report
28/70
7/24/2019 Earthworks Completion Report
29/70
7/24/2019 Earthworks Completion Report
30/70
7/24/2019 Earthworks Completion Report
31/70
Appendix B
7/24/2019 Earthworks Completion Report
32/70
7/24/2019 Earthworks Completion Report
33/70
Appendix C
7/24/2019 Earthworks Completion Report
34/70
7/24/2019 Earthworks Completion Report
35/70
7/24/2019 Earthworks Completion Report
36/70
7/24/2019 Earthworks Completion Report
37/70
7/24/2019 Earthworks Completion Report
38/70
7/24/2019 Earthworks Completion Report
39/70
7/24/2019 Earthworks Completion Report
40/70
7/24/2019 Earthworks Completion Report
41/70
7/24/2019 Earthworks Completion Report
42/70
7/24/2019 Earthworks Completion Report
43/70
7/24/2019 Earthworks Completion Report
44/70
7/24/2019 Earthworks Completion Report
45/70
7/24/2019 Earthworks Completion Report
46/70
7/24/2019 Earthworks Completion Report
47/70
7/24/2019 Earthworks Completion Report
48/70
Appendix D
7/24/2019 Earthworks Completion Report
49/70
PERTH SAND PENETROMETER
Test Report No.AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 13/12/2012
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 1 2 3 4 5 6
Test Depth mm Blows/150mm
0-150 Set Set Set Set Set Set
150-300 2 2 3 3 3 2
300-450 4 6 8 6 6 4
450-600 8 11 13 13 11 10
600-750 12 19 19 20 18 16
750-900 14 20+ 20+ 20+ 20+ 20+
900-1050 12
7/24/2019 Earthworks Completion Report
50/70
PERTH SAND PENETROMETER
Test Report No.AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 13/12/2012
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 7 8 9 10 11 12
Test Depth mm Blows/150mm
0-150 Set Set Set Set Set Set
150-300 3 3 4 3 3 3
300-450 4 5 7 7 7 6
450-600 9 10 12 13 12 9
600-750 13 14 17 15 20+ 15
750-900 17 15 20+ 20+ 18
900-1050 19 17 20
7/24/2019 Earthworks Completion Report
51/70
PERTH SAND PENETROMETER
Test Report No.AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 13/12/2012
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 13 14 15 16
Test Depth mm Blows/150mm
0-150 Set Set Set Set
150-300 3 4 3 3
300-450 7 8 5 8
450-600 9 12 9 13
600-750 14 18 12 20
750-900 18 20+ 14 20+
900-1050 19 15
7/24/2019 Earthworks Completion Report
52/70
PERTH SAND PENETROMETER
AS1289.6.3.3-1997
SCALA PENETROMETER TEST
AS1289.6.3.2-1997
Test Report No.
Job No: GEOTPERT08050AZ
Office: Perth
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Urbano
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
Date: 16/01/2013
Tested by: TC
Hammer mass: 9kg
Hammer drop: 600mm
Penetrometer used: Coffey 1
Test Location* 1 2 3 4 5 6
Test Depth (mm) Blows/150mm
0-150 SET SET SET SET SET SET
150-300 3 4 4 3 7 4
300-450 4 7 7 8 12 11
450-600 7 11 11 14 16 17
600-750 11 17 18 20+ 20+ 20
750-900
7/24/2019 Earthworks Completion Report
53/70
PERTH SAND PENETROMETER
AS1289.6.3.3-1997
SCALA PENETROMETER TEST
AS1289.6.3.2-1997
Test Report No.
Job No: GEOTPERT08050AZ
Office: Perth
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Urbano
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
Date: 16/01/2013
Tested by: TC
Hammer mass: 9kg
Hammer drop: 600mm
Penetrometer used: Coffey 1
Test Location* 13 14 15 16 17 18
Test Depth (mm) Blows/150mm
0-150 SET SET SET SET SET SET
150-300 2 3 3 3 4 2
300-450 4 6 6 5 7 5
450-600 6 11 10 9 11 6
7/24/2019 Earthworks Completion Report
54/70
PERTH SAND PENETROMETER
AS1289.6.3.3-1997
SCALA PENETROMETER TEST
AS1289.6.3.2-1997
Test Report No.
Job No: GEOTPERT08050AZ
Office: Perth
Client: Georgiou Group Pty Ltd
Principal:Project: Ellenbrook Town Centre - Urbano
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
Date: 16/01/2013
Tested by: TCHammer mass: 9kg
Hammer drop: 600mm
Penetrometer used: Coffey 1
Test Location* 25 26
Test Depth (mm) Blows/150mm
0-150 SET SET SET SET SET SET
150-300 4 3
300-450 7 7
7/24/2019 Earthworks Completion Report
55/70
PERTH SAND PENETROMETER Test Report No.
AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 08/02/2013
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 1 2 3 4 5 6
Test Depth mm Blows/150mm
0-150 Set Set Set Set Set Set
150-300 3 3 4 3 2 2
300-450 8 6 9 5 6 4
450-600 12 8 16 10 9 8
600-750 16 13 20+ 17 14 11
750-900 20+ 19 20+ 20 18
900-1050 20+ 20+ 20
7/24/2019 Earthworks Completion Report
56/70
PERTH SAND PENETROMETER Test Report No.
AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 08/02/2013
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 7 8 9 10 11 12
Test Depth mm Blows/150mm
0-150 Set Set Set Set Set Set
150-300 3 2 3 3 2 2
300-450 6 4 5 5 5 4
450-600 11 6 8 9 7 6
600-750 20+ 11 10 16 10 8
750-900 20 17 20+ 15 13
900-1050 20+ 19 18 15
7/24/2019 Earthworks Completion Report
57/70
PERTH SAND PENETROMETER Test Report No.
AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 08/02/2013
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 13 14 15 16 17 18
Test Depth mm Blows/150mm
0-150 Set Set Set Set Set Set
150-300 3 2 4 2 3 4
300-450 6 4 8 6 7 7
450-600 10 6 15 13 14 8
600-750 17 8 19 18 17 12
750-900 19 10 20+ 20+ 20+ 18
900-1050 20+ 13 20
7/24/2019 Earthworks Completion Report
58/70
PERTH SAND PENETROMETER Test Report No.
AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ
SCALA PENETROMETER TEST Office: Perth
AS1289.6.3.2 - 1997
Client: Georgiou Group Pty Ltd
Principal:
Project: Ellenbrook Town Centre - Ellen Stirling Parade
Location: Ellenbrook, WA
Soil type: Sand
Soil moisture:
Depth to water:
date: 08/02/2013
tested by: TC
hammer mass: 9kg
hammer drop: 600mm
penetrometer used: Coffey 1
Test Location* 19 20 21 22 23
Test Depth mm Blows/150mm
0-150 Set Set Set Set Set
150-300 4 5 4 2 4
300-450 9 10 7 6 7
450-600 13 17 12 10 11
600-750 16 20 17 18 14
750-900 20+ 20+ 17 20+ 20
900-1050 20 20+
7/24/2019 Earthworks Completion Report
59/70
7/24/2019 Earthworks Completion Report
60/70
7/24/2019 Earthworks Completion Report
61/70
7/24/2019 Earthworks Completion Report
62/70
7/24/2019 Earthworks Completion Report
63/70
7/24/2019 Earthworks Completion Report
64/70
7/24/2019 Earthworks Completion Report
65/70
7/24/2019 Earthworks Completion Report
66/70
7/24/2019 Earthworks Completion Report
67/70
7/24/2019 Earthworks Completion Report
68/70
7/24/2019 Earthworks Completion Report
69/70
7/24/2019 Earthworks Completion Report
70/70