+ All Categories
Home > Documents > Earthworks Completion Report

Earthworks Completion Report

Date post: 23-Feb-2018
Category:
Upload: mohd
View: 230 times
Download: 1 times
Share this document with a friend

of 70

Transcript
  • 7/24/2019 Earthworks Completion Report

    1/70

    EARTHWORKS COMPLETION REPORTELLEN STIRLING PARADE,

    ELLENBROOK

    Ellenbrook, W.A.Georgiou Group Pty Ltd

    GEOTPERT08050AZ-AH27 March 2013

  • 7/24/2019 Earthworks Completion Report

    2/70

    27 March 2013

    EARTHWORKS COMPLETION REPORTELLEN STIRLING PARADE,

    ELLENBROOK

    Ellenbrook, W.A.Georgiou Group Pty Ltd

    GEOTPERT08050AZ-AH27 March 2013

  • 7/24/2019 Earthworks Completion Report

    3/70

  • 7/24/2019 Earthworks Completion Report

    4/70

    CONTENTS

    1 INTRODUCTION 1

    2 PROPOSED DEVELOPMENT 1

    3 EARTHWORKS 1

    4 BACKGROUND INFORMATION 2

    5 INFORMATION SUPPLIED BY OTHERS 2

    6 COMPACTION CRITERIA 2

    7 CONTRACTORS TEST RESULTS 3

    8 COFFEY FIELD OBSERVATIONS AND TESTING 3

    8.1 Earthworks Monitoring 3

    8.2 Audi t Compaction Testing 3

    9 DISCUSSION 3

    9.1 General 3

  • 7/24/2019 Earthworks Completion Report

    5/70

    ATTACHMENTS

    Figures

    1 PSP Test Location Plan 13/12/2012

    2 PSP Test Location Plan 16/01/2013

    3 PSP Test Location Plan 08/02/2013

    Append ices

    A Cossill & Webley Earthworks Specification (14 pages)

    B Georgiou Group Pty Ltd Earthworks Confirmation Letter (1 page)

    C Georgiou Group Pty Ltd Site Compaction Records (14 pages)

    D Coffey PSP Field Test Results (10 pages)

    E Laboratory Test Results (6 pages)

  • 7/24/2019 Earthworks Completion Report

    6/70

    EARTHWORKS COMPLETION REPORT

    ELLEN STIRLING PARADE, ELLENBROOK

    1 INTRODUCTION

    This Earthwork Completion Report (ECR) presents the results of part time monitoring carried out by

    Coffey Geotechnics Pty Ltd (Coffey) of the earthworks for Georgiou Group Pty Ltd (Georgiou) for Ellen

    Stirling Parade located close to the town centre, Ellenbrook WA. Coffeys level of involvement is

    equivalent to Level 2 Geotechnical Investigation Authority of AS3798-2007.

    These services were provided and carried out in accordance with Coffeys proposal dated 7 November

    2012 (Ref: GEOTPERT08050AZ-AC-P) and were commissioned by Sinisa Rakovic of Georgiou via a

    completed and signed Consultancy Agreement form dated 31 October 2012.

    It should be noted however, that the requirements of the proposal related specifically to Level 1

    Inspection and Testing for the proposed Bunnings Store located on The Promenade and that

    subsequently works for the nearby Urbano residential development and Ellen Stirling Parade were

    included within this scope, though not the requirement for Level 1 Inspection and Testing.

    This work was carried out to provide an independent review of the compaction of bulk earthworksrequired to bring Ellen Stirling Parade and adjacent lots to design levels.

    2 PROPOSED DEVELOPMENT

    It is understood that the project involves bulk fill earthworks along the Ellen Stirling Parade alignment

    and adjacent lots to achieve design levels. Ellen Stirling Parade is aligned roughly east to west and is

    about 325m north of Urbano and being parallel to The Promenade, to the north, and The Parkway, to

    the south The extent of earthworks associated with Ellen Stirling Parade covered by this report is about

  • 7/24/2019 Earthworks Completion Report

    7/70

    EARTHWORKS COMPLETION REPORT

    ELLEN STIRLING PARADE, ELLENBROOK

    4 BACKGROUND INFORMATION

    Coffey has been involved with geotechnical investigation and earthworks monitoring during the ongoing

    development of Ellenbrook since its inception in 2000.

    Coffey has previously performed two site specific geotechnical investigations for the adjacent

    Ellenbrook Town Centre Retail and Middle School sites in November 2002 and April 2005 respectively.

    Prior to earthworks geotechnical investigation reports were prepared, dated 20 November 2002 (Ref:

    P2572/16-AB) and 18 April 2005 (Ref: P2572.60-AA Rev 1). The conclusions and recommendations of

    the reports have been reviewed during the preparation of this document.

    Fieldwork during the investigation for the Ellenbrook Town Centre Retail site comprised 27 test pits, 27

    Perth Sand Penetrometer (PSP) tests and 9 Electric Friction Cone Penetration (CPT) tests. The

    investigations identified that these areas were underlain by Bassendean Dune Sand. The sand was

    assessed as loose to medium dense within the top two metres of the natural ground surface.

    CPTs were carried out at 6 locations to depth varying from 4.0m to 5.0m below the existing groundsurface of the Middle School site. The ground conditions encountered during the investigation

    comprised medium dense to dense sand to a depth of 5.0m below the natural ground surface.

    It should be noted that cohesive fill materials have previously been placed within the footprint of Ellen

    Stirling Parade, as part of bulk earthworks for the adjacent Parkway road alignment in 2012. Details of

    these works are presented in Coffeys earthworks completion report, dated 23 September 2012 (Ref:

    GEOTPERT08050AY-AA) and letter, dated 13 June 2012 (Ref: GEOTPERT08050AY-AB), which

    should be read in conjunction with this report.

  • 7/24/2019 Earthworks Completion Report

    8/70

    EARTHWORKS COMPLETION REPORT

    ELLEN STIRLING PARADE, ELLENBROOK

    7 CONTRACTORS TEST RESULTS

    Georgiou performed compaction testing on the compacted sand fill during fill placement using a Perth

    Sand Penetrometer (PSP). The compaction testing was carried out between 24 November 2012 and 15

    January 2013. The PSP test results are attached in Appendix C and indicate that the compaction

    criteria has been achieved.

    8 COFFEY FIELD OBSERVATIONS AND TESTING

    8.1 Earthworks Monitoring

    Site visits were carried out by personnel from Coffey to observe topsoil stripping and bulk fill placement.

    Site visits were undertaken to assess earthworks Coffey personnel made site visits to assess topsoil

    stripping, subgrade suitability and bulk earthworks compaction for Ellen Stirling Parade between

    November 2012 and February 2013.

    8.2 Audi t Compaction Testing

    The results of the PSP testing confirm that the sand fill has been compacted sufficiently to achieve the

    requirements of the specification. Coffey PSP testing results are presented in Appendix D. Coffey PSP

    test locations are presented on Figures 1 3.

    9 DISCUSSION

  • 7/24/2019 Earthworks Completion Report

    9/70

    EARTHWORKS COMPLETION REPORT

    ELLEN STIRLING PARADE, ELLENBROOK

    Builder to ensure that footing designs and construction are compliant with the building foundation

    design for the lot in accordance with the Lot classification referenced to AS 2870-2011 and to carry out

    their own compaction checks on a lot by lot basis and compact any localised loose soil zones identified.

    The owner of the property has a requirement to maintain the property and foundations in accordance

    with AS 2870-2011, including but not limited to, maintaining adequate drainage away from the house

    foundations. Purchasers should be provided with a copy of the CSIRO Information Sheet BTF 18

    (Foundation Maintenance and Footing Performance: A Homeowner's Guide) available for download athttp://www.publish.csiro.au/pid/7076.htm

    10 IMPORTANT INFORMATION ABOUT YOUR COFFEY REPORT

    The readers attention is drawn to the important information about this report which follows the main

    text.

  • 7/24/2019 Earthworks Completion Report

    10/70

    As a client of Coffey you should know that site subsurface conditions cause more construction

    problems than any other factor. These notes have been prepared by Coffey to help you

    interpret and understand the limitations of your report.Your report is based on project specific criteria

    Your report has been developed on the basis of your

    unique project specific requirements as understood

    by Coffey and applies only to the site investigated.

    Project criteria typically include the general nature of

    the project; its size and configuration; the location of

    any structures on the site; other site improvements;the presence of underground utilities; and the additional

    risk imposed by scope-of-service limitations imposed

    by the client. Your report should not be used if there

    are any changes to the project without first asking

    Coffey to assess how factors that changed subsequent

    to the date of the report affect the report's

    recommendations. Coffey cannot accept responsibility

    f bl th t d t h d f t

    Your report will only give

    preliminary recommendations

    Y t i b d th ti th t th

    earth, rock and time. The actual interface between

    materials may be far more gradual or abrupt than

    assumed based on the facts obtained. Nothing can

    be done to change the actual site conditions which

    exist, but steps can be taken to reduce the impact of

    unexpected conditions. For this reason, ownersshould retain the services of Coffey through the

    development stage, to identify variances, conduct

    additional tests if required, and recommend solutions

    to problems encountered on site.

    Important information about your CoffeyReport

  • 7/24/2019 Earthworks Completion Report

    11/70

    Interpretation by other design professionals

    Costly problems can occur when other design professionals

    develop their plans based on misinterpretations

    of a report. To help avoid misinterpretations, retain

    Coffey to work with other project design professionals

    who are affected by the report. Have Coffey explain

    the report implications to design professionals affected

    by them and then review plans and specifications

    produced to see how they incorporate the report

    findings.

    Data should not be separated from the report*

    The report as a whole presents the findings of the site

    assessment and the report should not be copied in

    part or altered in any way.

    Logs, figures, drawings, etc. are customarily included

    in our reports and are developed by scientists,

    engineers or geologists based on their interpretation

    f fi ld l ( bl d b fi ld l) d

    Rely on Coffey for additional assistance

    Coffey is familiar with a variety of techniques and

    approaches that can be used to help reduce risks for

    all parties to a project, from design to construction. It

    is common that not all approaches will be necessarily

    dealt with in your site assessment report due to

    concepts proposed at that time. As the project

    progresses through design towards construction,

    speak with Coffey to develop alternative approaches

    to problems that may be of genuine benefit both in

    time and cost.

    Responsibility

    Reporting relies on interpretation of factual information

    based on judgement and opinion and has a level of

    uncertainty attached to it, which is far less exact than

    the design disciplines. This has often resulted in claims

    being lodged against consultants, which are unfounded.

    To help prevent this problem, a number of clauses

    h b d l d f i t t t d

    Important information about your CoffeyReport

  • 7/24/2019 Earthworks Completion Report

    12/70

    Figures

  • 7/24/2019 Earthworks Completion Report

    13/70

    PSP1

    PSP2

    PSP3

    PSP4

    PSP5PSP6

    PSP7

    PSP8

    PSP9

    PSP10 PSP11

    PSP12

    PSP13

    PSP14

    PSP15

    PSP16

  • 7/24/2019 Earthworks Completion Report

    14/70

    PSP1

    PSP2PSP3

    PSP4

    PSP5

    PSP6

    PSP7

    PSP8 PSP9

    PSP10

    PSP11

    PSP12PSP13

    PSP14

    PSP15

    PSP1

    P

  • 7/24/2019 Earthworks Completion Report

    15/70

    PSP1PSP2

    PSP3

    PSP4PSP5 PSP6

    PSP7

    PSP8

    PSP9

    PSP10

    PSP11

    PSP12

    PSP13

    PSP14PSP15

    PSP16PSP17

    PSP18

    PSP23

  • 7/24/2019 Earthworks Completion Report

    16/70

    Appendix AC ill & W bl E th k S ifi ti

  • 7/24/2019 Earthworks Completion Report

    17/70

  • 7/24/2019 Earthworks Completion Report

    18/70

  • 7/24/2019 Earthworks Completion Report

    19/70

  • 7/24/2019 Earthworks Completion Report

    20/70

  • 7/24/2019 Earthworks Completion Report

    21/70

  • 7/24/2019 Earthworks Completion Report

    22/70

  • 7/24/2019 Earthworks Completion Report

    23/70

  • 7/24/2019 Earthworks Completion Report

    24/70

  • 7/24/2019 Earthworks Completion Report

    25/70

  • 7/24/2019 Earthworks Completion Report

    26/70

  • 7/24/2019 Earthworks Completion Report

    27/70

  • 7/24/2019 Earthworks Completion Report

    28/70

  • 7/24/2019 Earthworks Completion Report

    29/70

  • 7/24/2019 Earthworks Completion Report

    30/70

  • 7/24/2019 Earthworks Completion Report

    31/70

    Appendix B

  • 7/24/2019 Earthworks Completion Report

    32/70

  • 7/24/2019 Earthworks Completion Report

    33/70

    Appendix C

  • 7/24/2019 Earthworks Completion Report

    34/70

  • 7/24/2019 Earthworks Completion Report

    35/70

  • 7/24/2019 Earthworks Completion Report

    36/70

  • 7/24/2019 Earthworks Completion Report

    37/70

  • 7/24/2019 Earthworks Completion Report

    38/70

  • 7/24/2019 Earthworks Completion Report

    39/70

  • 7/24/2019 Earthworks Completion Report

    40/70

  • 7/24/2019 Earthworks Completion Report

    41/70

  • 7/24/2019 Earthworks Completion Report

    42/70

  • 7/24/2019 Earthworks Completion Report

    43/70

  • 7/24/2019 Earthworks Completion Report

    44/70

  • 7/24/2019 Earthworks Completion Report

    45/70

  • 7/24/2019 Earthworks Completion Report

    46/70

  • 7/24/2019 Earthworks Completion Report

    47/70

  • 7/24/2019 Earthworks Completion Report

    48/70

    Appendix D

  • 7/24/2019 Earthworks Completion Report

    49/70

    PERTH SAND PENETROMETER

    Test Report No.AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 13/12/2012

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 1 2 3 4 5 6

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set Set Set

    150-300 2 2 3 3 3 2

    300-450 4 6 8 6 6 4

    450-600 8 11 13 13 11 10

    600-750 12 19 19 20 18 16

    750-900 14 20+ 20+ 20+ 20+ 20+

    900-1050 12

  • 7/24/2019 Earthworks Completion Report

    50/70

    PERTH SAND PENETROMETER

    Test Report No.AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 13/12/2012

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 7 8 9 10 11 12

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set Set Set

    150-300 3 3 4 3 3 3

    300-450 4 5 7 7 7 6

    450-600 9 10 12 13 12 9

    600-750 13 14 17 15 20+ 15

    750-900 17 15 20+ 20+ 18

    900-1050 19 17 20

  • 7/24/2019 Earthworks Completion Report

    51/70

    PERTH SAND PENETROMETER

    Test Report No.AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 13/12/2012

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 13 14 15 16

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set

    150-300 3 4 3 3

    300-450 7 8 5 8

    450-600 9 12 9 13

    600-750 14 18 12 20

    750-900 18 20+ 14 20+

    900-1050 19 15

  • 7/24/2019 Earthworks Completion Report

    52/70

    PERTH SAND PENETROMETER

    AS1289.6.3.3-1997

    SCALA PENETROMETER TEST

    AS1289.6.3.2-1997

    Test Report No.

    Job No: GEOTPERT08050AZ

    Office: Perth

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Urbano

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    Date: 16/01/2013

    Tested by: TC

    Hammer mass: 9kg

    Hammer drop: 600mm

    Penetrometer used: Coffey 1

    Test Location* 1 2 3 4 5 6

    Test Depth (mm) Blows/150mm

    0-150 SET SET SET SET SET SET

    150-300 3 4 4 3 7 4

    300-450 4 7 7 8 12 11

    450-600 7 11 11 14 16 17

    600-750 11 17 18 20+ 20+ 20

    750-900

  • 7/24/2019 Earthworks Completion Report

    53/70

    PERTH SAND PENETROMETER

    AS1289.6.3.3-1997

    SCALA PENETROMETER TEST

    AS1289.6.3.2-1997

    Test Report No.

    Job No: GEOTPERT08050AZ

    Office: Perth

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Urbano

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    Date: 16/01/2013

    Tested by: TC

    Hammer mass: 9kg

    Hammer drop: 600mm

    Penetrometer used: Coffey 1

    Test Location* 13 14 15 16 17 18

    Test Depth (mm) Blows/150mm

    0-150 SET SET SET SET SET SET

    150-300 2 3 3 3 4 2

    300-450 4 6 6 5 7 5

    450-600 6 11 10 9 11 6

  • 7/24/2019 Earthworks Completion Report

    54/70

    PERTH SAND PENETROMETER

    AS1289.6.3.3-1997

    SCALA PENETROMETER TEST

    AS1289.6.3.2-1997

    Test Report No.

    Job No: GEOTPERT08050AZ

    Office: Perth

    Client: Georgiou Group Pty Ltd

    Principal:Project: Ellenbrook Town Centre - Urbano

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    Date: 16/01/2013

    Tested by: TCHammer mass: 9kg

    Hammer drop: 600mm

    Penetrometer used: Coffey 1

    Test Location* 25 26

    Test Depth (mm) Blows/150mm

    0-150 SET SET SET SET SET SET

    150-300 4 3

    300-450 7 7

  • 7/24/2019 Earthworks Completion Report

    55/70

    PERTH SAND PENETROMETER Test Report No.

    AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 08/02/2013

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 1 2 3 4 5 6

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set Set Set

    150-300 3 3 4 3 2 2

    300-450 8 6 9 5 6 4

    450-600 12 8 16 10 9 8

    600-750 16 13 20+ 17 14 11

    750-900 20+ 19 20+ 20 18

    900-1050 20+ 20+ 20

  • 7/24/2019 Earthworks Completion Report

    56/70

    PERTH SAND PENETROMETER Test Report No.

    AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 08/02/2013

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 7 8 9 10 11 12

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set Set Set

    150-300 3 2 3 3 2 2

    300-450 6 4 5 5 5 4

    450-600 11 6 8 9 7 6

    600-750 20+ 11 10 16 10 8

    750-900 20 17 20+ 15 13

    900-1050 20+ 19 18 15

  • 7/24/2019 Earthworks Completion Report

    57/70

    PERTH SAND PENETROMETER Test Report No.

    AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 08/02/2013

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 13 14 15 16 17 18

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set Set Set

    150-300 3 2 4 2 3 4

    300-450 6 4 8 6 7 7

    450-600 10 6 15 13 14 8

    600-750 17 8 19 18 17 12

    750-900 19 10 20+ 20+ 20+ 18

    900-1050 20+ 13 20

  • 7/24/2019 Earthworks Completion Report

    58/70

    PERTH SAND PENETROMETER Test Report No.

    AS1289.6.3.3 - 1997 Job No: GEOTPERT08050AZ

    SCALA PENETROMETER TEST Office: Perth

    AS1289.6.3.2 - 1997

    Client: Georgiou Group Pty Ltd

    Principal:

    Project: Ellenbrook Town Centre - Ellen Stirling Parade

    Location: Ellenbrook, WA

    Soil type: Sand

    Soil moisture:

    Depth to water:

    date: 08/02/2013

    tested by: TC

    hammer mass: 9kg

    hammer drop: 600mm

    penetrometer used: Coffey 1

    Test Location* 19 20 21 22 23

    Test Depth mm Blows/150mm

    0-150 Set Set Set Set Set

    150-300 4 5 4 2 4

    300-450 9 10 7 6 7

    450-600 13 17 12 10 11

    600-750 16 20 17 18 14

    750-900 20+ 20+ 17 20+ 20

    900-1050 20 20+

  • 7/24/2019 Earthworks Completion Report

    59/70

  • 7/24/2019 Earthworks Completion Report

    60/70

  • 7/24/2019 Earthworks Completion Report

    61/70

  • 7/24/2019 Earthworks Completion Report

    62/70

  • 7/24/2019 Earthworks Completion Report

    63/70

  • 7/24/2019 Earthworks Completion Report

    64/70

  • 7/24/2019 Earthworks Completion Report

    65/70

  • 7/24/2019 Earthworks Completion Report

    66/70

  • 7/24/2019 Earthworks Completion Report

    67/70

  • 7/24/2019 Earthworks Completion Report

    68/70

  • 7/24/2019 Earthworks Completion Report

    69/70

  • 7/24/2019 Earthworks Completion Report

    70/70


Recommended