+ All Categories
Home > Documents > East Monroe Garage

East Monroe Garage

Date post: 14-Apr-2018
Category:
Upload: kbernat3
View: 218 times
Download: 0 times
Share this document with a friend

of 23

Transcript
  • 7/30/2019 East Monroe Garage

    1/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

  • 7/30/2019 East Monroe Garage

    2/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Abstract

    The Repair and Preventative Maintenance

    o the East Monroe Parking Garage was a

    ast paced 15-month renovation project in

    the heart o downtown Chicago.

    The underground parking acility is located

    below Grant Park and covers a oot print

    o 760 eet wide by 1200 eet long. The

    parking garage is part o the largest

    parking system in the United States and

    has three levels with two underground

    parking levels accommodating 3,850

    vehicles.

    The garage has been in operation or

    almost our decades and has exterior and

    interior structural elements that were

    severely deteriorated. The entire garage

    received upgrades including extensive

    concrete repairs, new waterproofng

    systems, new elevator, escalators, HVAC,

    and renovations to the North Lobby.

    One o the most crucial aspects o the

    project was the hydro-demolishing o the

    concrete deck on the upper level o the

    parking garage and replacing the concrete.

    There are only a hand-ull o contractors

    in the country that specialize in hydro-

    demolition.

    PROJECT ABSTRACT

  • 7/30/2019 East Monroe Garage

    3/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Sustainability Initiative

    East Monroe Parking Garage project

    required the collection, treatment, and

    re-use o over 11 million gallons o water

    resulting rom the hydro-demolition

    process. The team hired an independent

    testing agency to treat and test the water

    to ensure compliance with any City o

    Chicago water quality standards prior to

    depositing any waste water into the storm

    or sanitary sewer system. Testing o the

    waste water was done every 14 calendar

    days. Prior to releasing waste water of-

    site, waste water was run through settling

    tanks and then ltered to remove particles

    in excess o 100 microns. Once the water

    had passed through the lter system, it

    was then be treated to reduce the PH level

    to meet discharge requirements. No water

    was released until tests indicated that the

    waste water met requirements stipulated

    by the City.

    SUSTAINABILITY INITIATIVE

  • 7/30/2019 East Monroe Garage

    4/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Description

    The East Monroe Parking Garage was

    originally constructed in 1974. It is a three

    level acility with two underground parking

    levels to accommodate 3,850 vehicles.

    The acility includes about 1,470,000

    square eet o garage space. Along with

    three other related parking acilities, they

    provide over 9,000 parking spaces beneath

    Chicagos Millennium and Grant Park in

    downtown Chicago and adjacent to Lake

    Michigan.

    The East Monroe Garage has a 753 x

    1179 ootprint. The top (roo lid) level

    supports Maggie Daley Park. This 20+

    acre park is currently under renovation

    and when completed in 2015, will eature

    multisensory landscaping, an ice skating

    ribbon, rock climbing sculptures, play

    gardens and multiple event spaces.

    STRUCTURE CHARACTERISTICS

    CAUSES OF DETERIORATION / PROBLEMS THAT PROMPTED REPAIRThe parking garage has been in operation

    or almost our decades. Exterior and

    interior structural elements were

    severely deteriorated rom seasonal and

    environmental exposure. This exposure

    caused corrosion damage to the concrete

    walls, columns, slabs, and ceilings.

    Structural condition surveys discovered

    that much o the concrete had extensive

    deterioration, delamination, and spallingon the suraces. The majority o the

    deterioration was due to corrosion o

    embedded top reinorcing steel and a

    chloride contaminated environment.

    The structural slab consists o 9-inches

    o conventionally reinorced concrete.

    There were a variety o traf c bearing,

    waterproong systems o dierent

    vintages on the top oor suraces.

    All existing top reinorcing steel was

    deteriorated and in need o replacement.

    Cracks in the concrete leaked severely,

    exposing portions o the structure to bothtopside and underside deterioration.

  • 7/30/2019 East Monroe Garage

    5/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Description

    INSPECTION/EVALUATION METHODS AND TEST RESULTS

    Preliminary recommendations included

    complete slab replacement in all areas

    o the structure. Indeed, extensive ull

    depth deterioration was noted in primary

    areas such as the entrance/exit lanes and

    primary drive lanes and ramps. However,

    the extent o the deterioration was visually

    less in parking module areas. Additional

    testing (chloride and corrosion hal cell

    potentials) at the underside o many

    slab areas revealed little or no chloride

    contamination or corrosion potentials.

    Accordingly, the engineering rm designed

    a unique approach that incorporated

    hydromilling to remove the chloride

    contaminated portions o the slabs. A

    combination o ull depth repairs and a

    partial depth overlay was adapted as a cost

    eective, long-term repair approach while

    updating the structure to meet the current

    requirements o the Chicago Building

    Code.

    A new, (dry) sprinkler re suppression

    system and re doors were installed. These

    new eatures provided an added benet

    in that it permitted the removal o every

    other re separation wall to create new

    open areas o 80,000 square eet versus

    the original 40,000 square eet, enhancing

    the parking experience rom a site visibility

    and security standpoint.

    SITE PREPARATION

    The original plan called or the

    underground garage to remain partially

    open during the restoration but, due

    to the ast-track nature o the project

    and the logistical dif culties in de-

    commissioning existing lie saety systems

    in an underground structure and bringing

    all new lie saety systems on line in re-

    opened areas, a dierent approach was

    pursued. It was decided that the acility

    would be closed and the work would

    proceed in the shortest possible time.

    The goal was to complete the project in

    approximately hal the original allotted

    time. Beore work could begin, all vehicles

    were cleared rom the acility. Additional

    site preparation measures included

    creating a detailed logistics plan, which

    was a challenge since crews needed

    to share an entrance with an adjacent

    garage that remained open at all times. All

    pumping equipment and trucks needed to

    saely stay out o the way o live traf c.

  • 7/30/2019 East Monroe Garage

    6/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Description

    DEMOLITION METHOD

    Hydro-demolition (milling) was chosen

    as the most ef cient approach. The

    combination o underground work

    and hydro-demolition posed distinct

    challenges not typically present in most

    projects. The roaring noise coming rom

    the specialized equipment was over

    100 decibels, creating a communication

    challenge. Furthermore, 36,000 psi o water

    pressure was used to selectively remove

    portions or all o the slab surace. Hand

    chipping was perormed around columns

    and drop head using 15 lb. air hammers.

    The use o hydro-demolition equipment

    required us to enorce special saety

    precautions. Faceshields, saety glasses,

    and walkie-talkies kept our crews sae and

    in constant communication.

    Since the garage consists o two parking

    levels (upper and lower levels), all hazards

    were prevalent on the upper levels

    due to holes that were a result o blow-

    throughs (a.k.a. ull depth removal). Nets

    were erected at areas adjacent to hydro-

    demolition work to separate and protect

    workers.

    SURFACE PREPARATION

    Ater the completion o the hydro-demolition, rebar was inspected to meet

    the criteria in the specications. Any bar

    that did not meet specs was removed.

    To ensure proper bonding, workers

    APPLICATION METHOD SELECTION

    Each ull depth area was ramed, and new

    epoxy-coated steel was installed in the

    top mat o reinorcing throughout as well

    as in the bottom mat in ull depth areas.Concrete was placed rom the top surace

    through air shats by truck pumps. A pipe

    system was brought in to be used once

    underground to transport the concrete to

    the placement area. From that point, the

    slabs were water cured according to the

    specications.

    sandblasted partial depth areas. Thesurace was then cleaned by blowing and

    vacuuming to eliminate any oreign matter

    that might interere with adhesion to the

    existing slab.

    To ensure the longevity o the new

    structure, low water-cement ratio concrete,

    epoxy coated steel and a polyester

    reinorced hot rubberized waterproongmembrane was placed over the water

    cured slabs. This high perormance

    waterproong system was then protected

    by a minimum 1 inch thick, asphalt

    paved driving surace. The new slab

    suraces were shot blasted clean to ensure

    proper bond o the membrane to the slab.

  • 7/30/2019 East Monroe Garage

    7/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Description

    REPAIR PROCESS EXECUTION

    Debris rom the demolition had to be

    moved in order to place the shoring or the

    rame work. The surace o partial depth

    areas were sandblasted and cleaned.

    The next step o the process was saturating

    the surace with water, covering it with wet

    burlap, and then covering it with plastic to

    retain the moisture or a minimum o 24

    hours. The plastic and burlap was peeled

    back one bay ahead o the pour on the day

    o placement. The slabs were poured in

    14-oot bays at an average o 18,000 SF per

    pour. The surace was then wet cured using

    the burlap and plastic rom the SSD.

    The north exterior wall showed severe

    deterioration rom years o exposure to

    moisture and de-icing slats that leaked

    through a ailed expansion joint rom

    the public sidewalk area above. The

    delaminated concrete was removed

    rom the wall, surace then sandblasted,

    inspected, and new reinorcement was

    placed. The wall needed to be ramed and

    saturated until placement. The concrete

    was placed mainly by truck pumping sel-

    consolidating concrete along with hand-

    mixed material into a ramed cavity. All the

    work was done o o swing stages.

    UNFORESEEN CONDITIONS FOUND

    Unexpected and unoreseen conditions

    that presented unique challenges to our

    team included re-shoring column drop

    heads due to the extensive amount o ull

    depth repairs which compromised the

    drop head connection to the existing oor.

    A complete re-design o re suppression

    systems was necessary based on the City

    o Chicago requirement o a two sourced

    water supply or the or the dry sprinkler

    system which involved direction boring to

    tap into the waterline rom Monroe Street.

    Another unique challenge special to

    the East Monroe Garage project is its

    ventilation, lighting, communication, and

    egress based on its underground location.

    The accelerated project schedule created

    a unique challenge. The schedule called

    or us to complete the project in 455 days

    so working through the winter months

    was a must. Additionally, working in the

    heart o the City o Chicago presented

    many logistical challenges. There was a

    time period during the winter months

    were we worked 24 hours a day due to

    cold and reezing temperatures which

    made job conditions extremely dif cult to

    manage. Controlling the water usage and

    collection while allowing proper drainage

    throughout the reezing temperatures was

    a challenge.

  • 7/30/2019 East Monroe Garage

    8/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Description

    The Repair and Preventative Maintenance

    at the East Monroe Street Parking Garage

    revitalized an essential commuter hub in

    downtown Chicago.

    This project was extremely unique due

    to the act it was entirely underground.

    Ventilation, temporary lighting, wireless

    phone usage, and ingress/egress to

    the site are typically not a cause or

    concern on most projects. But being

    underground is a dierent scenario.

    Maintaining proper ventilation and

    lighting were major concerns. Supply

    and exhaust ans surrounding the garage

    were monitored daily to ensure they

    were unctioning properly and carbonmonoxide levels were monitored regularly.

    Without proper ventilation, none o

    Other signicant unoreseen conditions include:

    Micro silica overlay on existing slab entrance required removal

    Amount o unreinorced and/or under reinorced drop heads

    Total area repaired on the North wall increased by thousands o SF

    UNFORESEEN CONDITIONS FOUND - continued

    SPECIAL FEATURES THAT MAKE THE PROJECT WORTHY OF AN AWARD

    the machines and equipment could be

    used. The main culprit, o course, was

    the hydro-demolition machine. Not only

    did it exhaust a large amount o carbon

    monoxide, it also emitted a lot o heat

    and introduced a tremendous amount o

    moisture into the air. When these machines

    were running at ull capacity, a mist ormed

    around it causing humidity and visibility

    concerns in the area and the water spray

    guns only made things worse. Blowers/

    ans were situated at these areas to combat

    these hazards. An ice box was provided to

    battle heat exhaustion among the workers.

    Also, additional land-lines were installed

    at various locations within the garage.

    All o these measures ensured a sae andsuccessul project.

  • 7/30/2019 East Monroe Garage

    9/23

    REPAIR AND PREVENTATIVE MAINTENANCE OF

    THE EAST MONROE PARKING GARAGE

    Chicago, Illinois

    Project Description

    Unique demolition and concrete repair to a below ground structure

    Restoration to a acility incorporating long-term solutions that will last the test o time

    Repair o corrosion and moisture damage to an entire concrete structure and exterior

    vertical walls

    Working under unique and hazardous conditions, on a scale that has never in history been

    seen on an underground parking structure

    Unique solutions to unexpected and unoreseen conditions

    Extradited work schedule that was completed in a short amount o time

    Replacement o concrete at the parking entrance where there was live traf c

    Volume o water and debris rom lower-level demolition completely removed

    Totals o 15,000 yards o concrete, over 600 tons o steel and pumping rom the top

    surace underground with pipe that runs as long as 1,200 eet

    As part o the park renovation project over the garage, a complete membrane tear o and

    re-waterproong o the top level was perormed

    WHAT SETS THIS PROJECT APART?

    Full Depth Replacement: 234,000 SF

    New Concrete Overlay Replacement: 800,000 SFOVER 1,000,000 SF

    Overhead Repairs: 5,000 SF

    Vertical Repairs to the North Wall: 13,000 SF

    Yards of Concrete: 15,000

    Pounds of Steel: 1,432,000

    East Monroe Garage is the largest of the four garage parking system that

    makes up the largest underground parking system in the world.

  • 7/30/2019 East Monroe Garage

    10/23

  • 7/30/2019 East Monroe Garage

    11/23

  • 7/30/2019 East Monroe Garage

    12/23

  • 7/30/2019 East Monroe Garage

    13/23

  • 7/30/2019 East Monroe Garage

    14/23

  • 7/30/2019 East Monroe Garage

    15/23

  • 7/30/2019 East Monroe Garage

    16/23

  • 7/30/2019 East Monroe Garage

    17/23

  • 7/30/2019 East Monroe Garage

    18/23

  • 7/30/2019 East Monroe Garage

    19/23

  • 7/30/2019 East Monroe Garage

    20/23

  • 7/30/2019 East Monroe Garage

    21/23

  • 7/30/2019 East Monroe Garage

    22/23

  • 7/30/2019 East Monroe Garage

    23/23


Recommended