8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 1/8
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 2/8
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 3/8
3
Notes:
The flow rate in each pipe above is the assumed value and we wanted the ACTUAL Q. The
correction for the assumed value can be calculated by using following formula:
∑
∑
Thus, we need to find summation of h for each pipe and the ratio of h/Q.
Also,
The signage value of δQ obtained is referred to magnitude. Meaning, if you are getting a –ve
value of δQ. Then, the ACTUAL value of Q is actually less than your assumed value.
DO NOT CONFUSE with Q.
***************************************************************************
STEP 2: Calculate the K for all pipe in both Loop 1 and 2. K can be calculated from
following formula:
K= fL3.03D5
Comment: I think calculation of K is straight forward.
***************************************************************************
STEP 3: Calculate energy losses due to friction, h by applying following formula:
h=KQ
Comment: Bit tricky as you already successfully making me confused. Do rememberthat, -ve value of Q is referring to direction of Q (anti-clock wise) and thus, for –Q, the
value of h also would be –ve. We can say that head loss, h are the same direction with
flow (That why –Q would have –h). Also, the unit for h is m & thus Q needed to be in
m3 /s.
***************************************************************************
STEP 3: Calculate the ratio h/Q.
Comment: All should be +ve value. As h and Q for EACH pipe should be in the same
direction.
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 4/8
4
Step 4: Started with Iteration 1
By now, you should be able to developed table something like this:
LOOP PIPE
D L
K
Assumed Q h
h/Q Q new
mm m L/s m
1
AC 500 3000 317 400 50.7 126.7 420.1
CD 350 2000 1257 50 3.1 62.0 94.0
DB 350 3000 1885 ‐150 ‐42.4 282.7 129.9
BA 500 2000 211 ‐400 ‐33.8 84.5 379.9
SUMMATION: ‐22.4 556.8
2
CE 250 3000 10139 150 228.1 1520.8 126.1
EF 250 2000 6759 50 16.9 338.0 26.1
FD 250 3000 10139 ‐100 ‐101.4 1013.9 123.9
DC 350 2000 1257 ‐50 ‐3.1 62.8 ‐94.0
SUMMATION:
140.6 2935.4
Notes:
1)
The corrected assumed value, Q NEW = Q (initially assumed) + δQ
2) The equation above applicable for all pipes in Loop 1 and 2, except for pipe CD (or
DC). For this pipe, the corrected value δQ has to be considered for both loops as the
pipe was in both loops. The formula for calculation as follow:
δQCD = δQ1 - δQ2
3)
Then you should proceed with the Second Iteration by using your new Q obtained inthe First Iteration as your newly assumed Q.
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 5/8
5
4) The method above should be repeated until δQ = 0 for both loop (or at least 3 iteration
during the final). Your friend asked me, what happened if after 1st iteration, we already
got δQ=0 for both loops. Answer: It is quite impossible for us to correctly guess the
flow rate on our first assumption. BUT, if this happened, I would do at least up to 2
iterations.
Kindly refer to the following for marking scheme.
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 6/8
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 7/8
7
2
CE 250 3000 10139 150 228.1 1520.8 126.1
EF 250 2000 6759 50 16.9 338.0 26.1
FD 250 3000 10139 ‐100 ‐101.4 1013.9 123.9
DC 350 2000 1257 ‐50 ‐3.1 62.8 ‐94.0
SUMMATION: 140.6 2935.4
Iteration 2
LOOP PIPE
D L
K
Q h
h/Q Qnew
mm m L/s m
1
AC 500 3000 317 420.1 55.9 133.1 416.0
CD 350 2000
1257 94.0 11.1 118.2 89.7
DB
350
3000
1885
129.9 ‐
31.8
244.9 ‐
134.0
BA 500 2000 211 379.9 ‐30.5 80.2 ‐384.0
4.7 576.4
2
CE 250 3000 10139 126.1 161.1 1278.2 126.3
EF 250 2000 6759 26.1 4.6 176.2 26.3
FD
250
3000
10139 123.9 ‐155.7 1256.5 ‐123.7
DC
350
2000
1257 ‐94.0 ‐11.1 118.2 ‐89.7
‐1.1 2829.0
8/10/2019 Eat 239 (Pipe Network) Example 4 Solution
http://slidepdf.com/reader/full/eat-239-pipe-network-example-4-solution 8/8