+ All Categories
Home > Documents > ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil...

ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil...

Date post: 29-Dec-2015
Category:
Upload: tyler-craig
View: 216 times
Download: 0 times
Share this document with a friend
Popular Tags:
12
ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Example 2 nd Semester 2010/2011 Eng: Ismail Zakaria Al Daoor 1
Transcript

ECCS5209

Project Planning & Control

Faculty of Applied Engineering and Urban Planning

Civil Engineering Department

Example

2nd Semester 2010/2011

Eng: Ismail Zakaria Al Daoor

1

2

Project Crashing

3

Example

The durations and direct costs for each activity in the network of a small

construction contract under both normal and crash conditions are given in

the following table. Establish the least cost for expediting the contract.

Determine the optimum duration of the contract assuming the indirect cost

is LE 125/day.

Time-Cost Trade-Off ( Project Crashing )

4

0 12

0 12

A(0)

2@100

12 20

14 22

B(8)

2@150

20 25

22 27

E(5)

1@50

27 47

27 47

G(20)

5@60

47 59

47 59

I(12)

2@75

12 27

12 27

C(15)

3@200

27 32

29 34

F(5)

1@300

32 45

34 47

H(13)

2@40

20 12

24 12

D(23)

Act. N.D C.D ∆.D C.C. N.C ∆.C Slop

A 12 10 2 7200 7000 200 100

B 8 6 2 5300 5000 300 150

C 15 12 3 4600 4000 600 200

D 23 23 0 5000 5000 0 0

E 5 4 1 1050 1000 50 50

F 5 4 1 3300 3000 300 300

G 20 15 5 6300 6000 300 60

H 13 11 2 2850 2500 350 175

I 12 10 2 3150 3000 150 75

CPM = A-C-G-I

5

1. The activity on the critical path with the lowest cost slope is G, this

activity can be crashed by 5 days, but if it is crashed by more than 2 days

another critical path will be generated. Therefore, activity G will be

crashed by 2 days only. Then adjust timing of the activities.

A new critical path will be formed, A-C-F-H-I.

New contract duration is 57 days.

The cost increase is 2 x 60 = LE 120.

Time-Cost Trade-Off ( Project Crashing )

6

2. At this step the activities that can be crashed are listed below:

Either A at cost LE 100/day

Or C at cost LE 200/day

Or I at cost LE 75/day

Or F & G at cost LE 360/day

Or H & G at cost LE 100/ day

Activity I is chosen because it has the least cost slope, and it can be crashed

by 2 days. Because this is last activity in the network, it has no effect on other

activities.

New contract duration is 55 days.

The cost increase is 2 x 75 = LE 150.

Cumulative cost increase = 120 + 150 = LE 270

Time-Cost Trade-Off ( Project Crashing )

7

3. Now, we could select A or both H & G, because they have the same cost

slope. Activity A is chosen to be crashed. This will change the timings for

all activities, but no new critical path will be formed.

New contract duration is 53 days.

The cost increase is 2 x 100 = LE 200.

Cumulative cost increase = 270 + 200 = LE 470

Time-Cost Trade-Off ( Project Crashing )

8

4. Now, activities H & G can be crashed by 2 days each. A new critical path

A-B-D-I will be formed.

New contract duration is 51 days.

The cost increase is 2 x 100 = LE 200.

Cumulative cost increase = 470 + 200 = LE 670

Time-Cost Trade-Off ( Project Crashing )

9

5. At this stage, the network have three critical paths. The activities that

can be crashed are listed below:

Either C & B at cost LE 350/day

Or F, G & B at cost LE 510/day

Activities C & B are chosen because they have the least cost slope.

New contract duration is 49 days.

The cost increase is 2 x 350 = LE 700.

Cumulative cost increase = 670 + 700 = LE 1370

Now, there is no further shortening is possible.

Time-Cost Trade-Off ( Project Crashing )

10

The contract duration and the corresponding cost are given in the table below.

Time-Cost Trade-Off ( Project Crashing )

Time-Cost Trade-Off ( Project Crashing )

Question

12


Recommended