• Welcome, Introductions and Purpose of the Meeting
• Overview of EchoWater Project
• Current Construction
• Overall Site
• Plant Access and Security
• Project Features
• Upcoming Project Details
• EchoWater Projects
• Regional San Projects
• Upcoming Pre-Qualifications
• 3-D Model/Schedule Integration
• Contractor Input
BNRTTF
$25M
$20M
$15M
$10M
$5M
2015 2016 2017 2018 2019 2020 2021 2022 2023
FEQ
SP
Program Expenditures by Project
Sacramento Regional County Sanitation District
EchoWater Site Plant Access and Security
• Construction
Access and
Deliveries via
Dwight Road
• Dedicated
Access Security
Facility
EchoWater Project Features
• Multiple Contractors
• OCIP
• PMIS (web-based)
• Stringent P6 Scheduling
Requirements
• On-Site Batch Plant
(Teichert Ready Mix)
• Materials Testing
– Onsite District Lab
– Supplement where
necessary
Sacramento Regional County Sanitation District
EchoWater Projects
• Channel Air Blower System (CAB)
• Bradshaw Equalization Structure Pipeline (BES)
• Tertiary Treatment Facilities (TTF)
Upcoming Projects
Sacramento Regional County Sanitation District
Channel Air Blower System (CAB)
• New Blower
Building
• New Air Piping
• Bid
Advertising
• 1st Qtr. 2018
• Construction
Cost Estimate
- $10M
Sacramento Regional County Sanitation District
Bradshaw Equalization Structure
Pipeline (BES)
• 1,200 LF 8-inch PVC or
HDPE
• 1,000 LF 8-inch pipe
inside 36” & 60” SD
• Bid Advertising 2/16/2018
• NTP 5/17/2018
• Completion by 11/1/2018
• Construction Cost
Estimate $650K
Sacramento Regional County Sanitation District
TTF Overview
DCPF
DCSDCBGMF
SBIS
FIPS
FAP & COAG
ELECT
Sacramento Regional County Sanitation District
Importance of Timely Decision
Milestone Date
DS3 October 15, 2017
Bid Set January 5, 2017
Approval to Advertise January 10, 2018
Bid Opening March 1, 2018
Contractor NTP May 11, 2018
GMF Construction Complete March 28, 2022
Completion of Commissioning August 8, 2022
Permit Compliance May 9, 2023
Sacramento Regional County Sanitation District
Project Elements:
Filter Influent Pumping Station (FIPS) Pumps up to 343 MGD of Secondary Effluent
from the Secondary Settling Tanks (SSTs) to
Filters
One drum screen (and channel for future) for
bird and algae removal
3 duty and 1standby pump (6 pumps for buildout)
Sacramento Regional County Sanitation District
Project Elements: Granular Media
Filtration (GMF) Facility
Chemical mixing (coagulant, filter aid),
20 granular media filters,
During winter months (November-April) flows in excess of the filtration capacity
of 217 MGD will be diverted around filtration.
Seasonal Flow Diversion Structure
(SFDS),
Sacramento Regional County Sanitation District
Project Elements: Granular Media
Filtration (GMF) Facility
Filters are dual media, composed of anthracite and sand
Backwash supply system, and
Spent backwash equalization
tanks and pumps.
FTE Flash Mix Moved to South End of GMF• Filtered effluent (FTE) flash mix
was relocated to the south side of
GMF
– Based on flow separation (TM9)
– Flash Mix is now at 96” lines
near the flow meter vault
Sacramento Regional County Sanitation District
Project Elements:
Disinfection Contact Basins (DCB) Filtered effluent will be mixed with disinfectant (sodium hypochlorite) at filters and
conveyed to the DCBs.
One dedicated DCB (#4) will produce Title 22 effluent year-round for unrestricted reuse
DCBs (#1-3) will disinfect filtered and seasonal secondary effluent for river discharge
Unfiltered secondary effluent that is diverted during winter high flow events will be blended
with the filtered water and disinfected through DCBs (#1-3).
Sacramento Regional County Sanitation District
Upcoming Projects (Continued)
Regional San Projects – Near-Term
PROJECT SUMMARY EST. COST ADVERTISE DATE
Near-Term Projects
Digesters 5, 6, & 7 Rehab Rehabilitation, repair, and/or replacement of structural,
mechanical, and electrical components associated with
each digester and the systems that support them.
$7M July 2017
Water Reclamation Facility
(WRF) Storage Tank
Coating
Repair/Replacement
Replace and repair failing coating on the WRF’s 2 MG
treated water storage tank interior.
$375k July 2017
Gas Management System
Improvements and Rehab
Implementation of system modifications to the existing
Digester Gas Management System to improve
performance and reliability. Includes work on GMS
piping, valves, burners, flares, and system controls.
$750K March 2018
Primary Deck Structural
Repairs and Rehab
Rehabilitation, repair, and/or replacement of deteriorated
concrete, access hatches, steel cover plates and frames,
isolation gates, and other components associated with
the concrete deck that covers the Primary Process
area. Expected to be a multiple season project due to
operational constraints.
$1.6M March 2018
Sacramento Regional County Sanitation District
Upcoming Projects (Continued)
Regional San Projects – Near-Term
PROJECT SUMMARY EST. COST ADVERTISE DATE
Extended Forecast
ESB-D Liner Replacement Replace existing membrane liner on Emergency Storage
Basin D. Anticipate new liner will be concrete, similar to
EchoWater FEQ project.
$22M 2019
RTP I/O Controller
Replacement
Replace old, obsolete plant control system
components. Design will follow system architecture
established for EchoWater processes, which is local
PLC controllers. This is expected to be a multi-year
project due to operational constraints.
$15M 2019
South County Ag Recycled
Water, Phase 1Construct new pump station and conveyance pipeline to
deliver tertiary treated wastewater to agricultural
interests in south Sacramento County. Anticipate
multiple contracts for first phase improvements.
$140M 2020
Sacramento Regional County Sanitation District
Contractor Pre-Qualifications
Tertiary Treatment Facility - TTF
General Contractors – Similar qualification
requirements as previous BNR pre-qualifications.
Expected RFP in June, 2017
Electrical Subcontractors
Pre-Qualifications will be required for TTF and CAB. One List will be created.
Expected RFP in June, 2017
I & C Subcontractors
No Pre-Qualification Required
Sacramento Regional County Sanitation District
EchoWater Projects are Designed
using BIM
• BIM files may be available for
4-D (schedule) and 5-D (cost)
management.
• Responsibility for maintaining
model files to reflect changes,
and “as-built” conditions,
during construction TBD.
• Use of asset database for
submittals (shop drawings,
O&M information, etc.) TBD.
Sacramento Regional County Sanitation District
Synchro Contact Information
Jon Berkoe │Director, Virtual Design & Construction
+1 415-706-6371
2120 University Avenue│ Berkeley, CA 94704 │ USA
Construct safe, productive and trusted projects
Sacramento Regional County Sanitation District
Contact Information
• Web site:
http://www.srcsd.com/business-opportunities.php
• PMO CM Lead:
– Ron Perkins
EchoWater Project Program Management Office