Date post: | 07-Apr-2018 |
Category: |
Documents |
Upload: | rummankabir |
View: | 220 times |
Download: | 0 times |
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 1/17
Economic Dispatch Calculation
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 2/17
Introduction
` Rumman Kabir
` MohnishTuladhar
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 3/17
Economic Dispatch
` What is ED` Sharing load between Generators to minimize total cost
required to supply the loads
` If Gen A costs more to produce power than Gen B, Gen A will be
controlled to produce less power than Gen B
` The Generators also have to meet all the constraints in the
system
` Energy Policy Act 2005, section 1234(b)
` ´the operation of generation facilities to produce energy at the lowest
cost to reliably serve consumers, recognizing any operational limits of
generation and transmission facilities.´
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 4/17
Savings of $3/MWh
Gen A
Gen B
$2/MWh
$5/MWh
Cost
MWhIncrease
1MW
Reduce
1MW
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 5/17
Benefits
` Cost Effective` Saves cost by dispatching the cheapest combination allowable
by the system
` Saves Natural Resources
` Newer combined-cycle gas turbines (CCGT) costs less toproduce 1MWH (ERCOT showed $15/MWH savings)
` Less fuel is burned (30% less in ERCOT Example)
` Less Emissions
` Not only more efficient, less emissions per-unit fuel used (50-90% less emissions per unit fuel)
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 6/17
Constraints
` Fuel` Coal
` Natural Gas
` Hydro
` Nuclear
` Wind/Solar
` Startup/Shutdown Cost
` Ramp Rate
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 7/17
Constraints
` Minimum/maximum generation limits
` Minimum Up/Down time
` Transmission Limits
` Emission Constraints
` Transmission Losses
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 8/17
Challenges
` Forecasting` Loads
` Natural resources
` Dynamic load changes.
` Generators take longer to startup
` Rate Curtailment programs can help
` Frequency of Dispatch affect level of costs (If you re-
dispatch every 5-10 mins rather than hours)
` EDC between multiple providers/regions
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 9/17
EDC calculation
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 10/17
Analysis of the Program
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 11/17
Analysis continued
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 12/17
Analysis continued
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 13/17
Analysis continued
Total Load= 210MW
Iteration Pgen Qgen Generator cost( $/hr)
1 217.875 179 3.04E+03
2 216.699 176.07 3.14E+03
3 216.702 176.087 3.13E+03
4 216.7 176.083 3.13E+03
Matpower 216.7 176.08 3126.36
Total Load= 231MW
Iteration P Gen Qgen Generator cost( $/hr)
1 241.55 209.141 3.27E+03
2 239.404 202.391 3.43E+03
3 239.373 202.392 3.41E+03
4 239.389 202.383 3.42E+03
Matpower 239.4 202.4 3399.29
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 14/17
Analysis continued
Total Load= 252
Iteration P Gen Qgen Generator cost ($/hr)
1 265.32 226.877 3.71E+03
2 262.252 202.391 3.71E+03
3 262.18 227.574 3.67E+03
4 262.185 227.086 3.69E+03
Matpower 262.2 229.6 3680.06
Total Load= 279
Iteration P Gen Qgen Generator cost($/hr)1 297.734 290.817 3.80E+03
2 292.407 266.727 4.11E+03
3 292.239 268.465 4.01E+03
4 292.153 266.837 4.07E+03
Matpower 292.1 260 4082.07
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 15/17
L MP (EDC Program) vs L ambda (MatpowerOPF
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 16/17
Journal Paper review:A new formulation of Generator Penalty Factors ² Q.C L u
` A new algorithm for calculation of transmission loss penaltyfactors for generators, suitable for real time application
` Previously published techniques for generator penalty factorcalculation were derived from the power flow model withbasis upon reference bus location or internal-externalinterchange, disregarding the electrical distance betweengeneration and load
`
The new method is based purely upon the physical definitionof a penalty factor that is losses resulting from deliveringpower across the transmission network from a generator busto the loads.
8/6/2019 Economic Dispatch Latest
http://slidepdf.com/reader/full/economic-dispatch-latest 17/17
Journal Paper Review
` Because of changing nature of a power system network, aneffective implementation of real-time penalty factor is basedupon periodic state estimator solutions in real time.
` Little attention devoted to real time penalty factor formulationin the literature in recent years.
` A generator·s penalty factor should be dependent upon the
electrical distance from the generator the load; rather in thisformulation it is dependent upon its location with respect tothe reference bus. Selection of a different reference bus wouldyield a different penalty factor.