© 2013 Aspen Technology, Inc. All rights reserved Economics across the Capital Project Lifecycle Collaborative Engineering Webinar March 12, 2013 Tom Fiske and Dan McCarthy Aspen Technology
Transcript
Page 1: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved

Economics across the Capital Project Lifecycle

Collaborative Engineering Webinar

March 12, 2013

Tom Fiske and Dan McCarthy

Aspen Technology

Page 2: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

2

Ongoing Series of Technical Webinars Engineering Webinars for education and best practices

UPCOMING WEBINARS OF INTEREST:

Melhorar a Modelagem do Projeto Conceitual com um Fluxo de Trabalho Integrado Usando o Aspen HYSYS - 13 de Março

The New Aspen HYSYS for Refining – March 21st

Optimize Energy Use in New Process Designs with aspenONE Analysis Tools featuring Maturus Optimi – March 27th

Optimize Specialty Chemical Processes with aspenONE Engineering – April 10th

Improve Performance of Solids Processes through Modeling Dryers and Granulators in Aspen Plus V8 – April 16th

ALSO UPCOMING:

Optimize 2013 Global Conference – May 6th-8th

Page 3: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

3

Common Models & Data

aspenONE Integration

Support

Manufacturing

& Supply Chain

Conceptual Engineering

Basic Engineering

Detailed Engineering

aspenONE Engineering Best-in-class engineering solutions in an integrated workflow

Aspen Simulation Workbook & Aspen Online

Deployment

Aspen Petroleum Downstream & HYSYS

Upstream

Aspen Equipment Design & Rating

Aspen Basic Engineering Aspen Capital

Cost Estimator (ACCE)

Aspen Plus Dynamics, ACM & Flare System & Energy Analyzer

Aspen Plus

Aspen HYSYS

Aspen Process Economic Analyzer

(APEA)

Detailed Engineering

Aspen Plus

Aspen HYSYS

Page 4: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

4

Economics across the Capital Project Lifecycle

Tom Fiske and Dan McCarthy

March 12, 2013

Page 5: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

5

Disclaimer

Aspen Technology may provide information regarding possible future product developments including new products, product features, product interfaces, integration, design, architecture, etc. that may be represented as “product roadmaps.”

Any such information is for discussion purposes only and does not constitute a commitment by Aspen Technology to do or deliver anything in these product roadmaps or otherwise.

Any such commitment must be explicitly set forth in a written contract between the customer and Aspen Technology, executed by an authorized officer of each company.

Page 6: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

6

Overview

• Business Overview and Challenges

• Economics in Modeling

• Templates

• Activated Economics

• Integrated Economics

• Authorization Estimation

• Aspen Capital Cost Estimator

• Revamp Estimation

• Aspen In-Plant Cost Estimator

Page 7: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

7

Business Overview and Challenges

Page 8: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

8

Business Challenge: Sound Capital Decisions Require Accurate Estimates Across the Lifecycle

Basic Engineering

Detailed Engineering

Construction/ Start-up

Operations/ Maintenance/

Asset Mgt

Finance Planning

R&D

Conceptual Design

Page 9: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

9

Economic Evaluation Provides the Answers

Integrate estimation with process

modeling

Analyze constructability

with labor, schedule and

resources

Automatic scope generation with volumetric

models

Standardize basis across project and enterprise

Megaproject with multiple

project partners

Improved predictability &

efficiency of conceptual estimating

Page 10: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

10

Activated and Integrated Modeling, Sizing and Economics

Page 11: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

11

Traditional Conceptual Engineering

Equipment Design Economic Evaluation Process Simulation

Takes Weeks!

Page 12: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

12

aspenONE Conceptual Engineering

Page 13: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

13

Templates

Using Templates

Template Library

Default Templates available for each of the 5 Country Cost and Design Basis available

Page 14: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

14

Activated and Integrated Economics in Process Simulation

Process Model

Economic Evaluation

Energy Analysis

Equipment Design

Flare Analysis

Page 15: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

15

Activated Economics

Page 16: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

16

Activated Economic Analysis

Page 17: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

17

Activated Economic Analysis Quickly evaluate relative cost

Relative Cost Estimates

Cost Breakdown

Page 18: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

18

Economics Ribbon to Facilitate Workflow

New status indicators for clarity

Auto-evaluate mode – automatically calculate costs

after each simulation run

Page 19: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

19

Relative Economic Evaluation Enter Cost Options & Activate

New:

Use templates to ensure consistency and to customize sizing and costing

Page 20: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

20

Relative Economic Evaluation Map Unit Operations to Equipment

Radfrac

Condenser

Receiver

Reflux Pump

Pump

Exchanger

Column

Vessel

Packing

Section 1

Packing

Section 2

Reboiler

Equipment Unit Operation

Page 21: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

21

Relative Economic Evaluation Map Unit Operations to Equipment

Page 22: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

22

Relative Economic Evaluation Enter Equipment Specifications

Enter geometry, material of

construction, etc.

Page 23: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

23

Relative Economic Evaluation Size Equipment & Evaluate Costs

The equipment tab shows weights and costs for each equipment item.

Page 24: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

24

Relative Economic Evaluation Size Equipment & Evaluate Costs

The summary tab provides an overview of

operating and capital costs.

These relative estimates are sufficient for comparing conceptual

alternatives.

Page 25: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

25

Business Challenge: Minimize Capital and Operating Costs

Capital Cost

Operating Cost Equipment

Design

Process Design

Page 26: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

26

Business Challenge: Minimize Capital and Operating Costs

Two alternative designs are under consideration for GOSP

Two stage separation

….or three stage separation with a stabilizer column

Page 27: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

27

Economic Evaluation Product Family

Conceptual Engineering

Front End Eng Design

(FEED)

Detailed Engineering

Construction/ Start-up

Operations/ Maintenance/ Asset Mgmt

Business /

R&D

Aspen Process Economic

Analyzer (APEA)

Aspen Capital Cost Estimator (ACCE)

Aspen In-Plant Cost

Estimator (AICE)

ONE Economic Model

Page 28: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

28

Authorization Estimation

Page 29: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

29

Overview

Five country basis available (US-Houston, UK-Northwest, EU-Rotterdam, JP-Tokyo, ME-Saudi Arabia Western region

Costs updated yearly based on 1st Quarter data collection

Flexible “engineered” estimate. Changing the Design Basis may change estimate quantities

Page 30: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

30

Open Project in ACCE

Page 31: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

31

Adjust Specifications

Estimators Review and Adjust

• Design Codes

• Seismic Requirements

• Soil Loadings

• Electrical Specifications

• Instrument Specifications

• Field Productivity and Wage Rates

• Constructability

Page 32: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

32

Merge Projects or Import Project Areas

Page 33: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

33

Add Components

Examples

• Cooling Water Systems

• Communication and Alarms

• Steel Structures

• Pipe Racks

• Site Works

• Buildings

Page 34: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

34

Estimate and Review

Page 35: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

35

Project Scaling and Relocation

Project size can be scaled up or down

Project Relocation available for 89 locations.

Modifies both costs and design

Page 36: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

36

Revamp Estimation

Page 37: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

37

Revamp and Maintain

Page 38: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

38

Economic Evaluation Provides the Answers

Integrate estimation with process

modeling

Analyze constructability

with labor, schedule and

resources

Automatic scope generation with volumetric

models

Standardize basis across project and enterprise

Megaproject with multiple

project partners

Improved predictability &

efficiency of conceptual estimating

Page 39: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

39

PEMEX Economics across the design lifecycle

Challenge Solution Result

Integration of simulation, estimation, and project control

Equipment and sizing data received from Aspen HYSYS via integrated economics

Cost estimation using ACCE

Monte Carlo risk assessment using Crystal Ball software

ACCE integrated with Primavera

PEMEX integrated work flow

Ref: : Olga Monterrubio, PEMEX, AspenTech Global Conference: OPTIMIZE 2011, Washington DC, June 2011

Page 40: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

40

PEMEX Improving estimating accuracy and project oversight

Challenge Solution

Achieving Class IV estimates within 21%

Achieving Class III estimates within 16%

Predictable and consistently superior results

Successful integration with project control phase

Benchmarking estimated and final installed capital costs

Ref: : Olga Monterrubio, PEMEX, AspenTech Global Conference: OPTIMIZE 2011, Washington DC, June 2011

Page 41: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

41

Optimize 2013 Global Conference

Technip Why to use Aspen Capital Cost Estimator in the estimation process

Pemex Using new refinery cost estimation procedures

SABIC Methanol to Chemicals – A Conceptual Approach with Aspen Engineering Suite (including integrated economics)

May 6-8, 2013

See these and over 50 additional presentations and training sessions

Suncor Use of Aspen Capital Cost Estimator for oil sands projects

Page 42: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

42

Registration Discount for Webinar Attendees!

$1,500 – a savings of 25% off the standard conference fee! For more information, visit www.optimize2013.com and use the promotional code WEB2013 to receive the discount. Offer Expires March 31!

OPTIMIZE 2013 6 – 8 May 2013 The Westin Waterfront Hotel Boston, MA USA

Page 43: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

43

What Next?

Get more information now

– Additional resources available at: http://www.aspentech.com/products/aspen-economic-eval.aspx

– Videos also available at: www.youtube.com/user/aspentechnologyinc

Contact info for today’s presenter and hosts – Tom Fiske [email protected]

– Dan McCarthy [email protected]

– Ron Beck [email protected]

– Luisa Herrmann [email protected]

Page 44: Economics across the Capital Project Lifecycle - · PDF fileEconomics across the Capital Project Lifecycle ... Basic Aspen Basic Engineering Detailed Engineering ... Technip Why to

© 2013 Aspen Technology, Inc. All rights reserved |

44

Questions?