Date post: | 21-Mar-2018 |
Category: |
Documents |
Upload: | truongtuyen |
View: | 229 times |
Download: | 4 times |
© 2013 Aspen Technology, Inc. All rights reserved
Economics across the Capital Project Lifecycle
Collaborative Engineering Webinar
March 12, 2013
Tom Fiske and Dan McCarthy
Aspen Technology
© 2013 Aspen Technology, Inc. All rights reserved |
2
Ongoing Series of Technical Webinars Engineering Webinars for education and best practices
UPCOMING WEBINARS OF INTEREST:
Melhorar a Modelagem do Projeto Conceitual com um Fluxo de Trabalho Integrado Usando o Aspen HYSYS - 13 de Março
The New Aspen HYSYS for Refining – March 21st
Optimize Energy Use in New Process Designs with aspenONE Analysis Tools featuring Maturus Optimi – March 27th
Optimize Specialty Chemical Processes with aspenONE Engineering – April 10th
Improve Performance of Solids Processes through Modeling Dryers and Granulators in Aspen Plus V8 – April 16th
ALSO UPCOMING:
Optimize 2013 Global Conference – May 6th-8th
© 2013 Aspen Technology, Inc. All rights reserved |
3
Common Models & Data
aspenONE Integration
Support
Manufacturing
& Supply Chain
Conceptual Engineering
Basic Engineering
Detailed Engineering
aspenONE Engineering Best-in-class engineering solutions in an integrated workflow
Aspen Simulation Workbook & Aspen Online
Deployment
Aspen Petroleum Downstream & HYSYS
Upstream
Aspen Equipment Design & Rating
Aspen Basic Engineering Aspen Capital
Cost Estimator (ACCE)
Aspen Plus Dynamics, ACM & Flare System & Energy Analyzer
Aspen Plus
Aspen HYSYS
Aspen Process Economic Analyzer
(APEA)
Detailed Engineering
Aspen Plus
Aspen HYSYS
© 2013 Aspen Technology, Inc. All rights reserved |
4
Economics across the Capital Project Lifecycle
Tom Fiske and Dan McCarthy
March 12, 2013
© 2013 Aspen Technology, Inc. All rights reserved |
5
Disclaimer
Aspen Technology may provide information regarding possible future product developments including new products, product features, product interfaces, integration, design, architecture, etc. that may be represented as “product roadmaps.”
Any such information is for discussion purposes only and does not constitute a commitment by Aspen Technology to do or deliver anything in these product roadmaps or otherwise.
Any such commitment must be explicitly set forth in a written contract between the customer and Aspen Technology, executed by an authorized officer of each company.
© 2013 Aspen Technology, Inc. All rights reserved |
6
Overview
• Business Overview and Challenges
• Economics in Modeling
• Templates
• Activated Economics
• Integrated Economics
• Authorization Estimation
• Aspen Capital Cost Estimator
• Revamp Estimation
• Aspen In-Plant Cost Estimator
© 2013 Aspen Technology, Inc. All rights reserved |
7
Business Overview and Challenges
© 2013 Aspen Technology, Inc. All rights reserved |
8
Business Challenge: Sound Capital Decisions Require Accurate Estimates Across the Lifecycle
Basic Engineering
Detailed Engineering
Construction/ Start-up
Operations/ Maintenance/
Asset Mgt
Finance Planning
R&D
Conceptual Design
© 2013 Aspen Technology, Inc. All rights reserved |
9
Economic Evaluation Provides the Answers
Integrate estimation with process
modeling
Analyze constructability
with labor, schedule and
resources
Automatic scope generation with volumetric
models
Standardize basis across project and enterprise
Megaproject with multiple
project partners
Improved predictability &
efficiency of conceptual estimating
© 2013 Aspen Technology, Inc. All rights reserved |
10
Activated and Integrated Modeling, Sizing and Economics
© 2013 Aspen Technology, Inc. All rights reserved |
11
Traditional Conceptual Engineering
Equipment Design Economic Evaluation Process Simulation
Takes Weeks!
© 2013 Aspen Technology, Inc. All rights reserved |
12
aspenONE Conceptual Engineering
© 2013 Aspen Technology, Inc. All rights reserved |
13
Templates
Using Templates
Template Library
Default Templates available for each of the 5 Country Cost and Design Basis available
© 2013 Aspen Technology, Inc. All rights reserved |
14
Activated and Integrated Economics in Process Simulation
Process Model
Economic Evaluation
Energy Analysis
Equipment Design
Flare Analysis
© 2013 Aspen Technology, Inc. All rights reserved |
15
Activated Economics
© 2013 Aspen Technology, Inc. All rights reserved |
16
Activated Economic Analysis
© 2013 Aspen Technology, Inc. All rights reserved |
17
Activated Economic Analysis Quickly evaluate relative cost
Relative Cost Estimates
Cost Breakdown
© 2013 Aspen Technology, Inc. All rights reserved |
18
Economics Ribbon to Facilitate Workflow
New status indicators for clarity
Auto-evaluate mode – automatically calculate costs
after each simulation run
© 2013 Aspen Technology, Inc. All rights reserved |
19
Relative Economic Evaluation Enter Cost Options & Activate
New:
Use templates to ensure consistency and to customize sizing and costing
© 2013 Aspen Technology, Inc. All rights reserved |
20
Relative Economic Evaluation Map Unit Operations to Equipment
Radfrac
Condenser
Receiver
Reflux Pump
Pump
Exchanger
Column
Vessel
Packing
Section 1
Packing
Section 2
Reboiler
Equipment Unit Operation
© 2013 Aspen Technology, Inc. All rights reserved |
21
Relative Economic Evaluation Map Unit Operations to Equipment
© 2013 Aspen Technology, Inc. All rights reserved |
22
Relative Economic Evaluation Enter Equipment Specifications
Enter geometry, material of
construction, etc.
© 2013 Aspen Technology, Inc. All rights reserved |
23
Relative Economic Evaluation Size Equipment & Evaluate Costs
The equipment tab shows weights and costs for each equipment item.
© 2013 Aspen Technology, Inc. All rights reserved |
24
Relative Economic Evaluation Size Equipment & Evaluate Costs
The summary tab provides an overview of
operating and capital costs.
These relative estimates are sufficient for comparing conceptual
alternatives.
© 2013 Aspen Technology, Inc. All rights reserved |
25
Business Challenge: Minimize Capital and Operating Costs
Capital Cost
Operating Cost Equipment
Design
Process Design
© 2013 Aspen Technology, Inc. All rights reserved |
26
Business Challenge: Minimize Capital and Operating Costs
Two alternative designs are under consideration for GOSP
Two stage separation
….or three stage separation with a stabilizer column
© 2013 Aspen Technology, Inc. All rights reserved |
27
Economic Evaluation Product Family
Conceptual Engineering
Front End Eng Design
(FEED)
Detailed Engineering
Construction/ Start-up
Operations/ Maintenance/ Asset Mgmt
Business /
R&D
Aspen Process Economic
Analyzer (APEA)
Aspen Capital Cost Estimator (ACCE)
Aspen In-Plant Cost
Estimator (AICE)
ONE Economic Model
© 2013 Aspen Technology, Inc. All rights reserved |
28
Authorization Estimation
© 2013 Aspen Technology, Inc. All rights reserved |
29
Overview
Five country basis available (US-Houston, UK-Northwest, EU-Rotterdam, JP-Tokyo, ME-Saudi Arabia Western region
Costs updated yearly based on 1st Quarter data collection
Flexible “engineered” estimate. Changing the Design Basis may change estimate quantities
© 2013 Aspen Technology, Inc. All rights reserved |
30
Open Project in ACCE
© 2013 Aspen Technology, Inc. All rights reserved |
31
Adjust Specifications
Estimators Review and Adjust
• Design Codes
• Seismic Requirements
• Soil Loadings
• Electrical Specifications
• Instrument Specifications
• Field Productivity and Wage Rates
• Constructability
© 2013 Aspen Technology, Inc. All rights reserved |
32
Merge Projects or Import Project Areas
© 2013 Aspen Technology, Inc. All rights reserved |
33
Add Components
Examples
• Cooling Water Systems
• Communication and Alarms
• Steel Structures
• Pipe Racks
• Site Works
• Buildings
© 2013 Aspen Technology, Inc. All rights reserved |
34
Estimate and Review
© 2013 Aspen Technology, Inc. All rights reserved |
35
Project Scaling and Relocation
Project size can be scaled up or down
Project Relocation available for 89 locations.
Modifies both costs and design
© 2013 Aspen Technology, Inc. All rights reserved |
36
Revamp Estimation
© 2013 Aspen Technology, Inc. All rights reserved |
37
Revamp and Maintain
© 2013 Aspen Technology, Inc. All rights reserved |
38
Economic Evaluation Provides the Answers
Integrate estimation with process
modeling
Analyze constructability
with labor, schedule and
resources
Automatic scope generation with volumetric
models
Standardize basis across project and enterprise
Megaproject with multiple
project partners
Improved predictability &
efficiency of conceptual estimating
© 2013 Aspen Technology, Inc. All rights reserved |
39
PEMEX Economics across the design lifecycle
Challenge Solution Result
Integration of simulation, estimation, and project control
Equipment and sizing data received from Aspen HYSYS via integrated economics
Cost estimation using ACCE
Monte Carlo risk assessment using Crystal Ball software
ACCE integrated with Primavera
PEMEX integrated work flow
Ref: : Olga Monterrubio, PEMEX, AspenTech Global Conference: OPTIMIZE 2011, Washington DC, June 2011
© 2013 Aspen Technology, Inc. All rights reserved |
40
PEMEX Improving estimating accuracy and project oversight
Challenge Solution
Achieving Class IV estimates within 21%
Achieving Class III estimates within 16%
Predictable and consistently superior results
Successful integration with project control phase
Benchmarking estimated and final installed capital costs
Ref: : Olga Monterrubio, PEMEX, AspenTech Global Conference: OPTIMIZE 2011, Washington DC, June 2011
© 2013 Aspen Technology, Inc. All rights reserved |
41
Optimize 2013 Global Conference
Technip Why to use Aspen Capital Cost Estimator in the estimation process
Pemex Using new refinery cost estimation procedures
SABIC Methanol to Chemicals – A Conceptual Approach with Aspen Engineering Suite (including integrated economics)
May 6-8, 2013
See these and over 50 additional presentations and training sessions
Suncor Use of Aspen Capital Cost Estimator for oil sands projects
© 2013 Aspen Technology, Inc. All rights reserved |
42
Registration Discount for Webinar Attendees!
$1,500 – a savings of 25% off the standard conference fee! For more information, visit www.optimize2013.com and use the promotional code WEB2013 to receive the discount. Offer Expires March 31!
OPTIMIZE 2013 6 – 8 May 2013 The Westin Waterfront Hotel Boston, MA USA
© 2013 Aspen Technology, Inc. All rights reserved |
43
What Next?
Get more information now
– Additional resources available at: http://www.aspentech.com/products/aspen-economic-eval.aspx
– Videos also available at: www.youtube.com/user/aspentechnologyinc
Contact info for today’s presenter and hosts – Tom Fiske [email protected]
– Dan McCarthy [email protected]
– Ron Beck [email protected]
– Luisa Herrmann [email protected]
© 2013 Aspen Technology, Inc. All rights reserved |
44
Questions?