Date post: | 19-Dec-2015 |
Category: |
Documents |
Upload: | tomaz-filho |
View: | 3 times |
Download: | 0 times |
energydesignresources
AUTOMATED MONITORING AND FAULT DETECTION
design brief
Summary
Commissioning, retro-commissioning, re-commissioning, and
automated monitoring and fault detection (also referred to as automated
commissioning) are all systematic methods of ensuring that a building
and its hardware perform to the level intended by the owner and design
team. Buildings that are running properly benefit from reduced
maintenance, quality indoor environments, and lower energy costs.
Using only energy savings, the median payback for retro- and re-
commissioning is less than a year and approximately five years for new
construction commissioning.6
As sensor technology, building control networks, and building
supervisory software have evolved into building automation systems
(BAS), better information about building performance has become
available to building operators. Most modern BAS offer alarm filters
that may be set for out-of-range conditions and detecting critical
component faults. An emerging use of these capabilities is the
application of sophisticated algorithms to detect hidden problems that
are usually discovered in a formal commissioning process. However,
commissioning and retro-/re-commissioning lack the advantage of
continuing to monitor and identify issues, which automated monitoring
offers. The automated process can be as simple as helping building
operators gather data or as powerful as actively testing the hardware and
conducting reprogramming and recalibrations. This Design Brief
discusses developments in research and commercially available
automated monitoring systems.
C O N T E N T S
Introduction 2
Benefits of Automated Monitoring 5
Fault Detection andDiagnostics 9
FDD Detailed Example 14
Automated MonitoringPackages 17
The Future of AutomatedMonitoring 23
Conclusion 24
Glossary 25
For More Information 26
Notes 27
Automated monitoring provides
continuous monitoring of building
energy systems and can alert a
facility manager to performance
or comfort issues, saving time
and money.
PAGE 2 AUTOMATED MONITORING AND FAULT DETECTION
Introduction
Building commissioning is the systematic process of ensuring that a
building’s systems are designed, installed, and tested to perform
according to the design intent and the building owner’s operational
needs. The commissioning process can be applied to new and existing
buildings and covers the building envelope, plumbing, and all energized
systems (lighting, HVAC, refrigeration, life-safety, occupant transport,
and specific processes). Commissioning is an iterative process of
communication, observation, actively testing components and systems,
and recording results. Traditionally, it has been conducted over a set
time period by a team of specialists who understand the design,
installation, and operation of these systems. If applied to existing
buildings, it is often called retro-commissioning (first application) or re-
commissioning (second and subsequent applications).
The commissioning of new buildings is most effective when considered
throughout the planning, design, construction, and post-occupancy
stages. Integrating commissioning into a new building project provides
the opportunity for the best initial performance, which the owner can
use as a guideline throughout the life of the building.
Post-occupancy commissioning (including retro-commissioning and re-
commissioning) usually are performed because some aspect of building
performance, such as occupant comfort or energy use, has exceeded the
baseline performance that should be achieved. Post-occupancy
commissioning is the process of systematically re-evaluating the
performance of the building systems. Simply tuning the building
controls is often a cost-effective means of returning the building to its
design performance. But commissioning of existing buildings often
identifies components or systems that should be repaired or replaced.
Repair and replacement offer the opportunity to install higher efficiency
equipment or improve operations by improving the controls for systems.
Often comfort is improved, and energy use or demand is reduced.
A key limitation to commissioning and retro-/re-commissioning is that
each one is a periodic service, and building performance usually tends to
drift away from the design baseline over time. Also, retro-/re-
PAGE 3AUTOMATED MONITORING AND FAULT DETECTION
commissioning are usually not considered until a problem is significant
enough to warrant action. Over time, the slow deterioration in
equipment and changes in control systems, specifically the HVAC
system, adds up to higher energy costs and degrading comfort. Changes
in building use, including increases in occupant density, personal
computers, copiers, and other energy-consuming office equipment, may
also adversely affect performance.
Degradation in performance is often due to budget shortfalls for
equipment repair and replacement, and shortages of trained operators.
In turn, equipment life may be shorter than expected because operators
must spend a greater portion of their time addressing problems that
cause comfort complaints rather than underlying equipment problems.
They simply don’t have enough time to manually analyze trend data and
inspect equipment on a routine basis. And, since it’s not practical to
have a commissioning team on hand at all times, an outsider’s
perspective on performance degradation and how changes in building
use affect energy use and comfort is not available.
As mentioned, due to the evolution of BAS, better information about
building performance has become available to building operators. Most
modern BAS offer alarm filters for detecting critical component faults
and sophisticated algorithms for finding hidden problems that are
usually discovered in a formal commissioning process. Some in the
industry have called this “auto-commissioning” because it automates
some, but not all, of the processes in traditional commissioning.
Automated commissioning is continuous or periodic monitoring of
building sensor and control points, applying algorithms that detect
faults in building systems, and notifying operators that faults exist.
However, it does not necessarily involve commissioning experts and
relies on traditional commissioning functional tests.
To acknowledge these differences, this paper has adopted “automated
monitoring” to describe technologies that are more reliant on BAS.
Table 1 shows trends in the evolution of building automation systems
and the resulting higher quality information.
PAGE 4 AUTOMATED MONITORING AND FAULT DETECTION
Source: Architectural Energy Corporation
“Faults” are conditions that are outside of design intent and may include
conditions that waste energy, increase electric or natural gas demand,
and may result in comfort complaints. In addition to detecting faults,
automated monitoring systems may also diagnose faults and provide
information about possible causes.
Automated monitoring can provide operators with information that
allows them to focus on the root causes of comfort complaints and energy
waste. It also can be a very valuable adjunct to retro-/re-commissioning
projects by providing insight into equipment deficiencies at the
beginning of the project. Table 2 summarizes the key characteristics
associated with commissioning, retro-commissioning, re-commissioning,
and automated monitoring.
Level Building ControlDescription
Control Access(Local, Remote)
Control SystemCharacteristics
Operator InteractionWith Controls
Commissioning Technology
1 Independent,separate control ofcomponents and/orsystems
Local No or little datastorage
Manual control ofcomponent andsystem operations
On-site personal observation;use of pre-functional checklists and functionalperformance tests
2 Integration ofcontrol under on-site supervisorysoftware
Local Ability to store anddisplay data
Automated control ofon/off schedules andsetpoints
Level 1 plus local humananalysis of displayed data tofind operations problems
3 Level 2 plusconnection viaphone line
Local and RemoteComputerTerminals
Level 2 plus abilityto apply filter rule-sets to generateautomatic alarms
Level 2 plus simplealarms and remoteaccess
Level 2 plus remote access andautomatic alarms forequipment protection and/oroccupant comfort
4 Level 3 plusInternet technology
Level 3 plusalarms to remotepagers, cellphones, andemail
Level 3 plusembeddeddiagnostics in localcontrollers and/ordiagnostics atsupervisory level
Level 3 plusinformation to assessmaintenancerequirements
Level 3 plus diagnostic reportsfor fault detection atcomponent and/or system level
5 Level 4 withoutside input forutility demandresponse (weatherand loadinformation)
Same as Level 4 Level 4 plus built-inoptimization basedon internal loadsand externaldemand response
Level 4 plusautomatic loadmanagement andinformation to assesspredictivemaintenance
Level 4 plus predictive loadand maintenance models
Table 1. Evolution of Building Automation Systems
PAGE 5AUTOMATED MONITORING AND FAULT DETECTION
Benefits of Automated Monitoring
Automated monitoring systems can provide information that benefit
building performance in the areas of indoor air quality, thermal
comfort, energy cost savings, labor savings, and risk mitigation.
Incorporating automated monitoring features in a building also may
qualify for credits under the U.S. Green Building Council’s (USGBC)
Leadership in Energy and Environmental Design (LEED) Green
Building Rating System™.
Indoor Air Quality and Thermal Comfort
When a component fails in the HVAC system, often the building
operators and occupants are not aware that anything has changed. For
Table 2. Matrix of Commissioning Characteristics
Commissioning Retro-Commissioning Re-Commissioning Auto-Monitoring
Application New Construction Existing buildings that havenever been previouslycommissioned, or if buildingage or modifications render commissioning plans obsolete
Existing buildings thathave beencommissioned orretro-commissioned
All applications
Timing As early as possiblei.e. pre-design
Occurs in response tounder-performance orproblems in the buildingsystems
Occurs periodically orin scheduled intervalsas part of the O&M, orin response to specificoperating issues
Any time afterbuilding systems areinstalled andoperational
Purpose Ensures buildingsystems will performoptimally
Solves problems thatprevents buildings fromperforming optimally
Ensures building isstill performingoptimally, maintainslevel of previouscommissioning
Continuouslymaintains optimalperformance
Frequency Once during theinitial design andconstruction
Once, as needed due toage; 10-15yrs
Every 3-5yrs Once installed,provides continualcommissioning for thelife of the building
Cost6 Varies with size andcomplexity of systems:$0.50 to $3.00/ft2,median is $1.00/ft2
$0.05-$0.40/ft2, median is $0.27/ft2
Costs will be similarto retro-commissioning
Too large a range offunctions and costs tocurrently compare. Haspotential to be mostcost effective method.
Benefit6 $1.00/ft2 energysaving with a medianpayback of 4.8 yrs.One time non-energybenefit = $1.24/ft2
$0.27/ft2 for 15% energysavings and payback of0.7 yrs, one time non-energy benefits = $0.18/ft2
Similar to retro-,depending onfrequency
Similar to retro- andre-commissioning withcontinuous benefits forthe length of operation.
Source: Architectural Energy Corporation
PAGE 6 AUTOMATED MONITORING AND FAULT DETECTION
example, if an outdoor supply air (OSA) damper seized in the closed
position or was closed by a technician to address an occupancy
complaint, fresh air would not be delivered to occupied spaces. This
condition may reduce energy costs because the proper amount of outside
air would have not been heated or cooled, but this is clearly at the
expense of good indoor air quality. Also, during periods when the outside
air temperature is within the economizer range, free cooling would not
be available. Automated monitoring can detect this problem quickly and,
in some cases, provide a diagnosis of what caused the problem.
Energy Cost Savings
Automated monitoring can expose a problem long before a serious
malfunction occurs. If an outdoor supply air (OSA) damper seized in
the open position, during cooler weather the boiler or heater would
compensate for the added cold air and the indoor air temperature would
remain within setpoint limits. During winter months, however, the
ambient temperature would drop and the hot water coil or heater might
not have enough capacity to maintain the set point, creating
uncomfortable room temperatures. At this point, occupants would
complain and building maintenance staff would eventually become
aware of the problem. During extremely cold temperature conditions, it
is possible that coils might even freeze. Significant energy waste can
occur for months without automated monitoring.
For existing buildings, retro- or re-commissioning typically results in a
reduction in energy use of 10 percent to 30 percent (see retro-
commissioning sidebar) with payback periods that are often less than
one year. The energy saved using automated monitoring is predicted to
be similar to retro- or re-commissioning. The initial hardware, software,
and setup costs for an automated monitoring system may be equivalent
to that of a retro- or re-commissioning project.
An automated monitoring system, if used properly, enables building
operators to create persistence in savings for energy, labor, and
maintenance during the life of the facility. Finally, indoor environments
for building occupants can be more reliably maintained, which help
mitigate indoor air quality (IAQ) issues and associated costs.
Retro-Commissioning Cost SavingsRetro-commissioning of existing
buildings reduces energy use by
anywhere from a few percent to
more than 60 percent of pre-retro-
commissioning consumption, with
most savings falling into the range
of 10 percent to 30 percent.1
In 2004, Lawrence Berkeley National
Laboratory, Portland Energy
Conservation Inc., and the Energy
Systems Laboratory at Texas A&M
University developed the largest survey
to date on the costs associated with
commissioning on commercial buildings.
The reseachers reported, “For existing
buildings, we found median
commissioning costs of $0.27/ft2,
whole-building energy savings of
15 percent, and payback times of
0.7 years.
These results are conservative insofar
as the scope of commissioning rarely
spans all fuels and building systems in
which savings may be found, not all
recommendations are implemented, and
significant first-cost and ongoing non-
energy benefits are rarely quantified.”6
PAGE 7AUTOMATED MONITORING AND FAULT DETECTION
Labor Savings and Risk Mitigation
The most tangible benefit of automated monitoring is energy cost
savings, but there are other benefits that are not as obvious. One such
benefit is labor cost savings, in the form of more efficient diagnosis and
maintenance. Automated monitoring systems have the potential to not
only find a problem with minimal or no human intervention, but to also
detect problems earlier. When problems are detected early, maintenance
staff are able to directly address faults before they have existed for long
periods, which results in better performing systems.
Constantly monitoring the energy systems also may mitigate the risk
that a major failure will occur, because some catastrophic failures result
from malfunctions going unnoticed. In some cases, major equipment
failures can be completely avoided, or downtime can be scheduled for
repairs or replacements instead of being forced into emergency outage
situations. Long term equipment condition can be tracked by an
automated monitoring system, allowing equipment replacements and
maintenance work to be forecasted.
LEED Accreditation
For building owners pursuing accreditation under the USGBC LEED®
rating systems, automated monitoring systems may help qualify projects
for credits under the Energy and Atmosphere (EA) and Indoor
Environmental Quality (EQ) categories. For the New Construction
(LEED-NC) rating system, automated monitoring systems could apply
to the following.
� EA prerequisite #1: Fundamental Commissioning of Building
Energy Systems and EA credit #3: Enhanced Commissioning -
designing and implementing an automated monitoring system
should support the commissioning activities for a new facility and
help qualify for this prerequisite and credit.
� EA credit #5: Measurement and Verification - an automated
monitoring system may support on-going accountability of energy
consumption (required for at least one year) under this credit.
� EQ credit #1: Outdoor Air Delivery Monitoring - if carbon dioxide
and air flow data points are permanently monitored and provide
continual feedback into the automated system, a credit is achievable.
A visual or audible alert is required when conditions vary by more
than 10 percent.
The Existing Buildings (LEED-EB) rating system has similar credits
under the EA and EQ categories.
� EA prerequisite #1: Existing Building Commissioning - designing
and implementing an automated monitoring system as part of retro-
commissioning an existing facility supports this prerequisite.
� EA credit #3.3: Building Operations and Maintenance - Building
Systems Monitoring – this requires continuous monitoring, alarms
that identify issues, and a system for responding to repairs. These
requirements align with the primary goals of automated monitoring
systems.
� EA credit #5.1-5.3: Performance Measurement - Enhanced Metering
– this requires continuous metering during a selected performance
period of various building energy and water consumption with
measures in place to show improved performance. Automated
monitoring systems can be designed to monitor the performance of
most systems listed in the checklist including cooling loads, chilled
water system efficiency, air volume, air and water economizers, and
variable frequency drive operation.
� EA credit #6: Documenting Sustainable Building Cost Impact -
information from automated monitoring systems also can be used to
meet the requirements listed for this credit.
� EQ credit #1: Outdoor Air Delivery Monitoring - if carbon dioxide
and air flow data points are permanently monitored and provide
continual feedback into the automated system, credit under the EQ
credit #1 is achievable.
PAGE 8 AUTOMATED MONITORING AND FAULT DETECTION
PAGE 9AUTOMATED MONITORING AND FAULT DETECTION
� EQ credit #7.2: Thermal Comfort: Permanent Monitoring System -
this credit requires measurement and trending of temperatures,
relative humidity, and CO2 or air speed at locations selected
according to the impact on occupant comfort. Automated
monitoring systems can be designed to handle these tasks.
Fault Detection and Diagnostics
Considered the cornerstone of automated monitoring, fault detection
and diagnostics (FDD) is the process by which malfunctions,
degradations, and broken equipment is recognized and diagnosed by
software. A system that has chronically high supply air temperatures
during the summer might have a stuck damper. In the absence of FDD,
a technician must visually inspect the outside air dampers or review the
time series plots of the outside, return, mixed, and supply air
temperatures and reach a correct diagnosis. FDD software can run the
same data through an algorithm and reach the same conclusion quicker.
Unlike traditional commissioning where a building is monitored for a
discrete amount of time, automated FDD is continuous and can ensure
the proper function of building systems as long as it is in place. Human
intervention is still needed to carry out repairs and maintenance.
However, once a repair is completed, the FDD system will automatically
verify that it is functioning correctly.
Although not yet commercially available, FDD tools with active control
could further react to the fault by taking action. Most malfunctions are
minor and either reduce efficiency or cause poor IAQ. If the problem
can be fixed through the BAS, such as an out-of-calibration sensor, the
FDD controller could recalibrate the sensor and report the adjustment.
If a fix through the BAS is not possible, an alternative may be to bypass
the malfunctioning sensor and run the system at a slightly reduced
efficiency until the problem is corrected. The last scenario would occur
when either safety is compromised or the HVAC system could suffer
catastrophic failure. In this case, the FDD controller would take the
appropriate action and issue an alarm to the building operator. Figure 1
shows a generic FDD process decision tree.
PAGE 10 AUTOMATED MONITORING AND FAULT DETECTION
Detecting Faults
Regardless of the fault detection method used, faults are detected when
the comparison residual (actual value minus predicted value), exceeds a
predefined threshold. Not all values come directly from readings, some
variables are either calculated or characteristic values, such as outside air
quantity or coefficient of performance for an air conditioner. Regardless
of the source of the variable, it is important to use a dynamic model for
predicted values. HVAC systems are inherently dynamic due to
changing indoor and outdoor conditions. Using a fixed value as a
comparison will result in either too many or too few faults being
reported. For example, if facility staff were measuring efficiency and
comparing it to a fixed minimum value, the result would not be accurate
because efficiency changes with input conditions. For this reason, the
detection algorithm should run a dynamic model. This could be as
simple as using a formula to change the threshold based on inputs or a
real time simulation of the whole system.
Building System/Component
Fault Detection
Passive FaultDiagnosis/Isolation
Fault Evaluation
• Safety• Availability• Energy/Cost Impact• Comfort• Environmental• Impact
No ActionRequired
Decision
Request a Repairand Continue
Reconfigure the Controls
Tolerate?
ReconfigureControls?
Continue toOperate?
Alarm/Shutdown
Fault
Fault Diagnosed
No Fault
ProactiveDiagnosis
Mea
sure
men
ts
Pro-ActiveDiatnosis for
Fault Isolation
Tolerate
No
No
No
Operate
Reconfigure
Figure 1. Generic Automated FDD Process Tree
Source: Portland Energy Conservation, Inc.
PAGE 11AUTOMATED MONITORING AND FAULT DETECTION
Diagnosing Faults
Diagnosing faults is a much more sophisticated process than detection.
Detection is as simple as fault or no fault, diagnosis may require an
analysis of multiple faults (passive diagnosis), or require manipulation of
the system itself (active diagnosis). Many times a fault is detected but its
cause cannot be determined without observing the system through a
wide range of conditions or modes. Using the proactive measure, modes
can be forced and a conclusion reached in a relatively short amount of
time. Passive diagnostics may take considerable time for the system to
cycle through the required conditions or modes on its own.
The cause of some faults can be determined as soon as they are
discovered. For example, if a large pressure drop is found across the air
filter, the diagnosis would be a clogged air filter (assuming the sensor is
functioning properly). On the other hand, triggered faults that are a
result of calculated values typically need further testing to determine
their origin. For example, the monitoring system might detect a
potential sensor error, but is unable to pin point the error among three
different sensors – return air, mixed air, and outside air. A proactive
system could wait until the building is unoccupied to force modes that
reveal the diagnosis. Through the BAS, the diagnostics program could
initiate 100 percent outside air and compare both mixed air and outside
air, then switch the dampers for 100 percent return air, and compare the
return air and mixed air. By isolating the different sensors and
comparing them, the faulty sensor should reveal itself. Figure 2 shows a
proactive FDD decision tree for a faulty sensor.
PAGE 12 AUTOMATED MONITORING AND FAULT DETECTION
A malfunctioning sensor does not always need to be replaced. Sensors
may be un-calibrated, drifting, or installed incorrectly. By reviewing the
backlog of data on the sensor, the actual issue can sometimes be
determined and the appropriate action taken. A fully automated
monitoring system may be able to recalibrate the sensor and give a
report without ever needing the assistance of a technician.
Proactive DiagnosticsTemperature Sensor Problem
TemperatureSensor
Problem
SequentialOperation
Close Outdoor-AirDamper Completely
Shut (100%Recirculation)
Close Return-AirDamper Completely
Shut (100% Outdoor Air)
Wait for Conditionsto Reach
Steady-State
Wait for Conditionsto Reach
Steady-State
Is Mixed-Air Temperature =Return-Air Temperature
Is Mixed-Air Temperature =Outdoor-Air Temperature
Equal Equal
NoNoMixed-Air andReturn-Air
Temperature Sensors OK
Mixed-Air andOutdoor-Air
Temperature Sensors OK
If BothTests Fail
Problem: Outdoor-AirTemperature Sensor
Problem
Problem: Return-AirTemperature Sensor
Problem
Problem: Mixed-AirTemperature Sensor
Problem
Figure 2. Possible Decision Tree to Isolate Faulty Temperature Sensor
Source: Portland Energy Conservation, Inc.
PAGE 13AUTOMATED MONITORING AND FAULT DETECTION
Verifying HVAC Programming and Schedules
Automated tools can monitor system schedules over long periods of
time and detect changes that waste energy. It is not uncommon for
operational schedules to be manually overridden for special events or
maintenance. If the BAS does not have a function to return the schedule
to normal operation, the over-ride condition may persist for weeks or
months. Simply reporting each over-ride condition may save significant
amounts of energy by allowing a supervisor to see and correct changes
that could be overlooked.
Data Handling and Documentation
Apart from the labor saving benefits that fault detection and diagnosis
provides, valuable time is also saved on data management. Part of the
automation process involves the management and conversion of data into
a comprehensible format. This can be as simple as interpreting and
exporting into a spreadsheet or as complex as a graphical interface capable
of performing many advanced functions with the data. Data storage and
data mining are key features that allow for easy review of historical trends.
Additionally, many of the current automated monitoring systems provide
access to building information via the Internet, which produces time
savings for facility managers and staff, especially when multiple building
locations or campus-wide sites are involved.
Automated documentation is another advantage of automated
monitoring. Automated tools are capable of creating performance and
maintenance reports as well as managing some types of commissioning
documents. Performance reports can track deficiencies and report
improvements. A major survey of commissioning providers suggested
that key aspects for automated monitoring systems were tracking and
creating standardized commissioning reports through automation.8
PAGE 14 AUTOMATED MONITORING AND FAULT DETECTION
FDD Detailed Example
Diagnose Faulty Outside Air Damper
Faulty dampers and valves in air-handling units (AHU) are difficult to
identify. A leaky hot water valve will increase the temperature of the air
entering the cooling coil, but this is compensated for by increased
mechanical cooling. The same thing occurs with damper problems: an
incorrect mixed air temperature due to excessive or inadequate outside
air can most times be compensated for by increased heating or cooling.
Since IAQ is generally not affected, faults in these components can go
unnoticed for years. Valves and dampers consist of many different
components and it is beyond the capabilities of current software to
distinguish what type of malfunctions occurred. Simply identifying a
fault will alert users to a damper or valve malfunction.
One way to diagnose a faulty outside air damper is to monitor either the
fan power or pressure drop across the damper. The pressure drop and fan
power will be different for every AHU, so an initial “training” period is
required to characterize the operation. Using this method, a simple look-
up table could be created that relates outside air fraction, damper position,
and fan power or pressure drop across the damper. Data for this table
would be collected by first setting the system to normal operation mode
with the outside air damper (OSAD) fully closed. Then, allow the return
air and exhaust air dampers to operate normally and the system to reach
equilibrium, and record the three inputs. The next step is to record the
measurement again, this time with the damper open 10 percent and repeat
the process in 10 percent increments until the damper is 100 percent open.
The next stage is to characterize the system for a stuck open and stuck
closed damper. To do this, the process is repeated as before with the system
operating normally except the damper is forced open or shut. The return
air and exhaust air dampers should operate as if the OSAD was in the
correct position. For instance, if the system was calling for full outside air,
the return damper would be shut and the fan would be working against a
large pressure drop causing more power to be drawn. If the damper was
stuck open, then the power draw would be lower. The system must be
characterized first to be able to determine the exact meaning of the power
differences. A typical look-up table might look like Table 3.
PAGE 15AUTOMATED MONITORING AND FAULT DETECTION
As shown in Figure 3, the first step in diagnosing a potential damper
problem is to validate the sensors to ensure they are reading correctly.
Then, confirm that the damper position is correct by comparing it to
the expected damper position. The expected damper position can be
determined based on outside air temperature and the mode of the AHU.
If the system is operating appropriately, the next step is to use the look
up table to confirm that the fan power corresponds to normal operation.
If it is not, a higher power draw in this example corresponds to a stuck
closed damper, and a lower draw corresponds to an open damper.
Once the FDD system has made a diagnosis, it can react in different
ways depending on how sophisticated and well integrated it is with the
HVAC system. If the FDD system is capable of being active, it can make
changes, such as changing schedules or recalibrating sensors. Some
faults, like the damper example, cannot be fixed through the controller
and require a physical repair. In a system where the FDD cannot make
changes, creating a fault alarm is the only response.
Table 3: Lookup Table for Diagnosing Damper Faults, Created by Actively Calibrating the Damper System8
10 0.15 1,550 0.05 1,560 0.15 1,500
20 0.25 1,450 0.08 1,600 0.25 1,400
30 0.40 1,350 0.15 1,625 0.40 1,300
50 0.60 1,250 0.20 1,650 0.60 1,200
70 0.75 1,150 0.40 1,750 0.75 1,100
100 1.00 1,000 0.70 1,800 1.00 1,000
Source: Portland Energy Conservation, Inc.
Outdoor AirDamperSignal
(% Open)
Normal Operation Outdoor Air DamperStuck Fully Closed
Outdoor Air DamperStuck Fully Open
Outdoor AirFraction
Supply FanPower
Consumption(Watts)
Outdoor AirFraction
Supply FanPower
Consumption(Watts)
Outdoor AirFraction
Supply FanPower
Consumption(Watts)
PAGE 16 AUTOMATED MONITORING AND FAULT DETECTION
Is Actual Pressure
Drop and Power Consumption = Expected
Pressure Dropand Power
Consumption?
No
No
Yes
No
Correct
Good
Equal
No
Yes
Validate SensorMeasurements
Are SensorMeasurements
Good?Problem: Sensor Problem
Is Outdoor-AirDamper Signal
Correct?
Lookup Table forNormal Operation
Lookup Table forFaulty Operation
Is Actual Pressure
Drop and Power Consumption = Expected
Pressure Dropand Power
Consumption?
Is Actual OAF =Expected OAF?
No
Problem: Unknown DamperProblem
Problem: Damper Problem
OK: OA Damper Operation OK
Problem: Control orControl Code
OAF is OK, but not the
Pressure Dropand Power
Consumption
Figure 3. Decision Tree to Detect and Diagnose Outdoor Air Damper Faults
Source: Portland Energy Conservation, Inc.
PAGE 17AUTOMATED MONITORING AND FAULT DETECTION
Automated Monitoring Packages
A number of public and private organizations have been actively
working to develop semi- and fully automated monitoring packages.
Summaries of several programs are provided. It is important to note that
some are available commercially, some are under development, and
others are under research. Additional information about the
organizations is shown in the For More Information section or by
footnote references provided in the Notes section.
ABCAT
The Automated Building Commissioning Analysis Tool (ABCAT),
developed by the Energy System Laboratory at Texas A&M University,
uses existing hardware in a fully commissioned building to achieve a
baseline measurement for operational energy use. During the calibration
period, the program is running its own simulation model; at the end of
that period, the mean error is subtracted to further calibrate the model.
It then monitors the building and compares the actual inside air quality
and energy use to the calibrated model. When the two values are not
synchronized, a fault is reported by the system.4
ACRx® Sentinel
Field Diagnostics Services Inc. created the ACRx® Sentinel package to
diagnose faults in small commercial air-conditioning units. The Sentinel
uses custom hardware installed in packaged-HVAC units to monitor
and transmit data to a web server via a wireless modem. The software
analyzes refrigeration and air-side data on a daily basis and reports faults
on a web page, including estimated wasted energy costs.9 The Sentinel
is available for retrofit applications and is likely to be available as an
OEM (original equipment manufacturer) feature that is sold to HVAC
companies within the next few years.
PAGE 18 AUTOMATED MONITORING AND FAULT DETECTION
APAR and VPACC
The Air-handling unit Performance Assessment Rules (APAR) is an
expert set of rules for fault detection in air handling units developed and
published by National Institute for Standards and Technology (NIST)
(ASHRAE, 2001). The rules apply to single duct, variable- or constant-
volume air-handlers with hydronic heating and cooling and economizers.
APAR uses control signals and occupancy schedules to identify the mode
of AHU operation. Each mode has a subset of performance rules that are
evaluated using BAS sensor data. These modes of operation include
heating, cooling with outdoor air, mechanical cooling with 100 percent
outdoor air, mechanical cooling with minimum outdoor air, and
“unknown”, where the condition of the valves and dampers do not
correspond to an identified mode. The rules are suitable for
incorporation into AHU-controller hardware or use in a BAS supervisory
computer. The rules have been tested in hardware manufactured by
Alerton, Automated Logic, Johnson Controls, Delta Controls, and
others. An expanded version of the rules is used in the ENFORMA‚
Building Diagnostics software, which is referenced in this section.
The VAV-box Performance Assessment Control Chart (VPACC) method
was also developed and published by NIST. This method is based on a
widely used statistical method used in manufacturing to detect anomalies
in manufacturing processes. The VPACC algorithms are compact and
may be embedded in VAV-box controllers or used in supervisory control
software. The rules have been tested in hardware manufactured by
Alerton, Automated Logic, Johnson Controls, Delta Controls, and others.
CITE-AHU
CITE-AHU is a retro-commissioning tool developed from a joint effort
between NIST and CSTB, the French Scientific and Technical Centre
for Building. Designed specifically for AHUs, the program uses APAR
algorithms. CITE-AHU depends on the existing hardware in a building
and taps into the BAS for its interface. By connecting directly to the BAS,
CITE-AHU can perform active tests to force different modes. This
allows the program to more aggressively pursue faults without waiting for
them to happen.3
PAGE 19AUTOMATED MONITORING AND FAULT DETECTION
DABO
Diagnostic Agent for Building Operators (DABO) was developed at the
CANMET Energy Technology Centre-Varennes in Canada. DABO
requires a BAS because it actively monitors and controls the HVAC
system with four different modules.
Currently, the Diagnostic Agent module is the only part available for
commercialization. The Diagnostic Agent uses expert systems and
pattern recognition to monitor, diagnose, and report faults. The
Adaptive Controller monitors and controls the sub-systems of the
HVAC system, such as VAV boxes and AHUs at optimal levels. The
Building Energy Agent uses inputs from the Diagnostic Agent and the
Adaptive Controller to predict performance and optimize set points.
The Building Maintenance Agent uses outputs from the Diagnostics
Agent to create a maintenance schedule report. The last module in the
circle is the Building Commissioning Agent, which is the active part of
DABO. Using the information from the Diagnostic Agent, it runs a
series of tests and actively changes settings based on the results.5
EffTrack
EffTrack, developed by Efficiency Technologies, Inc. is an automated
efficiency and diagnostic web-based service focused on chiller, boiler,
and plate exchanger efficiency and trending. EffTrack uploads data from
an existing BAS and/or additional monitoring equipment to its servers
and processes the data to provide facility managers the ability to
document, monitor, evaluate, and manage chiller system performance.
Efficiency Technologies has announced plans for future enhancements
that will include advanced chiller charting, internationalization (metric
units), diagnostics, and automated data collection for boilers and plate
exchangers, water treatment analysis, screw chillers, steam driven
chillers, evaporator condensers, air-cooled and rooftop units, air
handling units, and tower systems.
PAGE 20 AUTOMATED MONITORING AND FAULT DETECTION
ENFORMA® Building Diagnostics
ENFORMA Building Diagnostics (BD), developed by Architectural
Energy Corporation, is automated fault detection and diagnostics
software that runs on Tridium’s NiagaraAX BAS platform. The
ENFORMA software uses trend data from the underlying BAS,
processes it once a day, and stores and reports the faults for air-handlers,
chillers, cooling towers, and related equipment. The results can be
accessed using commonly available web browsers. ENFORMA BD
capabilities include a customizable graphical display of the data to
confirm faults detected by the system. Based on the duration of the
faults, the urgency level is displayed as red, yellow, or green in a graphic
maxtrix with days of the week in columns and building components in
rows. The program can be installed on a local or remote NiagaraAX
system, allowing managers and service personnel to remotely track
multiple building locations.
Information Monitoring and Diagnostic System (IMDS)
IMDS is a research system developed by Lawrence Berkeley National
Laboratory. The IMDS archives measurements from high-quality
sensors every minute. It includes a powerful data-visualization tool,
which can be used on-site or accessed via the Internet. The IMDS has
been used to identify and correct a series of control problems in a
demonstration building. It has also allowed the operators to make more
effective use of the building control system, freeing up time to take care
of other tenant needs. The operators believe they have significantly
increased building comfort, potentially improving tenant health and
productivity. The reduction in the time required to operate the building
is worth about $20,000 per year. A control system retrofit based on
findings from the IMDS is expected to reduce annual energy use by 20
percent, saving more than $30,000 per year. The project has also
evaluated simple chiller models for fault detection, concluding that they
can be used as references to monitor operation and detect faults. The
ability of the IMDS to measure cooling load and chiller power to within
one percent accuracy and with a one-minute sampling interval permits
the detection of faults that would otherwise be missed.
PAGE 21AUTOMATED MONITORING AND FAULT DETECTION
INFOMETRICS
Infometrics, developed by Cimetrics, is a remote monitoring service
using hardware and software that access data from the underlying BAS.
Cimetrics personnel analyze the data to find and diagnose faults.
Quarterly reports are created for the client with an energy use analysis,
mechanical system performance analysis, and a set of operational
recommendations prioritized by savings.2
PACRAT
Performance and Continuous Re-Commissioning Analysis Tool
(PACRAT) is an automated monitoring tool created by Facility
Dynamics. PACRAT taps into the existing BAS trend logs to monitor
and analyze the performance of the HVAC system. PACRAT has
three modules:
� Bass (data collection module)
� Expert (analysis and diagnosis module)
� Viewer (user interface)
The Bass module’s purpose is to connect to the building and to create
trend logs of appropriate data on a local server. The data are downloaded
periodically and analyzed using the Expert module. The Expert module
completes the analysis and diagnosis, and passes the processed
information on to the Viewer. The Viewer is a user-friendly interface
where the faults are categorized by importance. Faults with high
estimated energy waste are at the top of the list of suggested repairs.
Along with fault detecting and reporting, PACRAT can meter energy
use to maintain two running baselines for before and after comparison
of savings based on current utility rate schedules. Users are provided
with a real time reading of energy and unrealized energy savings.7
Rooftop Diagnostician
Developed at Pacific Northwest National Laboratory (PNNL), which is
operated by Battelle for the U.S. Department of Energy, this tool allows
facility staff to determine the cause of a malfunction in a rooftop unit or
to monitor performance in order to optimize regularly scheduled
PAGE 22 AUTOMATED MONITORING AND FAULT DETECTION
maintenance. Rooftop Diagnostician provides fast and effective
diagnostics for HVAC units in commercial buildings, allowing staff to
better monitor the HVAC system to provide optimal performance.
The Rooftop Diagnostician attaches directly onto the HVAC unit and
provides real-time web-based performance information. The Rooftop
Diagnostician is available for licensing from Battelle and provides the
following. 10
� Supports heat pumps and dual fuel systems
� Detects low fresh air supply to prevent “sick” buildings
� Features a web-enabled display so no special software is needed
� Detects high energy use and control failures
� Provides real-time information that permits service analysis
� Collects performance data from three months to five years.
Whole Building Diagnostician
The Whole Building Diagnostician (WBD) was created by PNNL,
which is operated by Battelle for the U.S. Department of Energy.
WBD uses a building’s own data collection capabilities, when possible,
to funnel data into one of two modules: the Whole-Building Energy
module (WBE) and the Outside Air Economizer (OAE) diagnostics
module. The WBE monitors energy consumption and displays the
results on a graph in the form of an energy index. The index represents
the ratio of expected energy use to actual energy use. The expected
value comes from an internal empirical model that takes into account
factors such as time of day and weather. The OAE uses a limited
number of the sensor and control outputs on the air handling unit to
detect roughly 20 common errors. The errors are then color coded
based on severity and reported to the user. It is available for licensing
from Battelle.11
PAGE 23AUTOMATED MONITORING AND FAULT DETECTION
The Future of Automated Monitoring
Areas for Improvement
Automated monitoring and specifically FDD are still under substantial
development. Current products have already proven to be valuable
commissioning and maintenance tools, though installed systems are
few. One of the reasons for the lack of market presence is public
awareness, although technical information and case studies on
automated monitoring are becoming more prevalent. With increased
awareness and usage, automated tools and systems will become more
sophisticated and cost effective.
In five to 10 years, it is foreseeable that FDD tools will be integral to
building energy and control systems. Similar types of self-diagnostics are
standard equipment in the aerospace industry, power plants, and most
modern vehicles. One way to accelerate market adoption of this technology
is to embed the FDD software into the HVAC component controllers or
the BAS. Since most new buildings already use some sort of BAS, including
FDD on all new systems would lower the prices considerably.
Tools also could be developed to make automated monitoring and FDD
fully comprehensive across all building systems. The current focus is on
HVAC systems because the faults are most prevalent and the hardest to
detect. Lighting also provides an opportunity for FDD, because it has a
significant impact on energy consumption and many lighting systems
rely on control strategies to ensure efficiency. A comprehensive FDD
system could monitor the HVAC, lighting, water, and other essential
building systems that depend on programs or schedules to control use.
Current Development
As noted above, many different organizations are developing automated
monitoring tools, each with a slightly different focus. Most products are
focused on one or more major HVAC components, with the intent of
expanding the scope to create a comprehensive analysis tool that can be
used to detect and diagnose faults throughout the whole HVAC system.
The details of research and development by private organizations are
closely guarded. However, public groups such as CANMET Energy
Technology centre in Canada, NIST, and Annex 40 readily announce
current progress and future development.
PAGE 24 AUTOMATED MONITORING AND FAULT DETECTION
Conclusion
Lack of proper commissioning, inexperienced operators incapable of
handling complicated building controls, and insufficient maintenance,
lead to reduced equipment life and increased operating costs.
Commissioning, re-commissioning, and retro-commissioning require
qualified commissioning personnel for periodically gathering, reviewing,
and documenting performance data. After traditional commissioning has
been completed, the beneficial effects often begin to dissipate.
On the other hand, automated monitoring provides continuous
feedback on building performance and affords the opportunity to
reduce labor requirements and create energy savings. Whether the
installed automated monitoring system is an active or passive FDD
system, nearly all HVAC systems will realize better performance.
Many hurdles still exist for this industry. Public awareness may be the
most significant. Many organizations are investing in this technology
with the hope that these products will be a common part of building
systems in the future. For now, only a few commercial and government
buildings utilize automated monitoring, and these few cases have shown
the concept to be viable. It is only a matter of time before automated
monitoring is installed as a common HVAC tool, and is expanded to
encompass other building systems.
PAGE 25AUTOMATED MONITORING AND FAULT DETECTION
Glossary
ABCAT Automated Building Commissioning and Analysis Tool
AEC Architectural Energy Corporation
AFDD Automated Fault Detection and Diagnostics
AHU/RTU Air Handler Unit/Roof Top Unit
APAR Air handling unit Performance Assessment Rules
ASHRAE American Society of Heating, Refrigeration andAir-conditioning Engineers
BAS Building Automation System
DABO Diagnostics Agent For Building Operators
FDD Fault Detection and Diagnostics
HVAC Heating Ventilating and Air Conditioning
IAQ Indoor Air Quality
LEED® Leadership in Energy and Environmental Design
NIST National Institute of Standards and Technology
O&M Operations and Maintenance
OSA Outside Air
OSAD Outside Air Damper
OAE Outside Air Economizer
PACRAT Performance and Continuous Re-commissioningAnalysis Tool
PECI Portland Energy Conservation Inc.
PNNL Pacific Northwest National Laboratory
USGBC United States Green Building Council
VAV (box) Variable Air Volume
VFD Variable Frequency Drive
WBD Whole Building Diagnostician
PAGE 26 AUTOMATED MONITORING AND FAULT DETECTION
FOR MORE INFORMATION
ASHRAE (American Society of Heating, Refrigeration, and Air Conditioning
Engineers) established the APAR set in 2001. www.ashrae.org
Architectural Energy Corporation developed ENFORMA diagnostic software.
www.archenergy.com
CANMET Energy Technology Centre is Canada’s leading science and
technology organization with a mandate to develop and demonstrate energy-
efficient, alternative, and renewable energy technologies and processes.
www.nrcan.gc.ca
CTSB focuses on four major areas: research, advanced engineering, quality
assessment, and dissemination of knowledge. international.cstb.fr/default.asp
Efficiency Technologies, Inc. developed EffTrack. www.efftec.com
Energy Laboratory at Texas A&M University developed ABCAT.
esl.eslwin.tamu.edu/
Facility Dynamics created PACRAT. www.facilitydynamics.com
Field Diagnostics developed the Sentinel. www.fielddiagnostics.com
International Energy Agency Annex 40 Commissioning – HVAC
Commissioning of Buildings and HVAC Systems for Improved Comfort and
Energy Savings. The objective of Annex 40 was to develop, validate, and
document tools for commissioning of buildings and building services.
These tools include guidelines on commissioning procedures and
recommendations for improving commissioning processes, as well as
prototype software that could be implemented as stand-alone tools and/or
embedded in Building Energy Management Systems (BEMS). The work
performed in the Annex is focused on HVAC systems and their associated
control systems. www.commissioning-hvac.org/default.asp
NIST is the National Institute of Standards Technology, developer of APAR
and VPACC and co-developer of CITE-AHU. www.nist.gov
Pacific Northwest National Laboratory (PNNL), operated by Battelle for the U.S.
Department of Energy, is the developer of the Whole Building Diagnostician
and the Rooftop Diagnostician. PNNL’s mission is to provide basic and applied
research to deliver energy, environmental, and national security for the nation.
www.pnl.gov/
Tridium is the developer of the Niagara Framework®, a software framework
that integrates diverse systems and devices into a unified platform that can
be managed and controlled in real time over the Internet. www.tridium.com/
PAGE 27AUTOMATED MONITORING AND FAULT DETECTION
Notes
1. Brambley, Michael, and Srinivas Katipamula. “Beyond Commissioning.” The Role of Automation. Feb. 2005. Pacific Northwest National Laboratory.www.automatedbuildings.com/news/feb05/articles/pnl/pnl.htm
2. “Building Accountablity.” Cimetrics.www.cimetrics.com/home/infometrics/
3. Castro, Natascha S., and Hossien Vaezi-Nejad. CITE-AHU, an Automated Commissioning Tool for Air-Handling Units. National Conference on Building Commissioning, 2005.
4. Claridge, D.E. Engineering and Software Requirement of theAutomated Building Commissioning and Analysis Tool. Energy Systems Laboratory (ESL) at Texas A&M University. ESL, Texas A&M, 2005.txspace.tamu.edu/bitstream/1969.1/2081/1/ESL-TR-05-01-02.pdf
5. Intelligent Building Operating Technologies. CANMET EnergyCentre. Varennes: CANMET Energy Technology Centre, 2004.cetc-varennes.nrcan.gc.ca/fichier.php/codectec/En/2004-044/2004-044e.pdf
6. Mills, Evan. “Cost-Effectiveness of Commercial-BuildingCommissioning.” Dec. 2004. Lawrence Berkeley NationalLaboratory, Portland Energy Conservation, Energy SystemLaboratory. eetd.lbl.gov/emills/PUBS/Cx-Costs-Benefits.html
7. “PACRAT.” Facility Dynamics.www.facilitydynamics.com/Pacwho.pdf
8. Portland Energy Conservation, Inc. Methods for Automated andContinuous Commissioning of Building Systems. ARTI: 21-CR.Springfield: US Dept. Commerce, 2003.
9. Rauch, Christopher A. “Field Diagnostics Services, Inc.”Acrx.Com. 2002. www.acrx.com/FieldDiagnosticServicesIncCompanyDescription.pdf
10. Rooftop Diagnostician.availabletechnologies.pnl.gov/technology.asp?id=58
11. “Whole Building Diagnostician.” Building Systems Program. 20 Oct. 2005.www.buildingsystemsprogram.pnl.gov/fdd/wbd/index.stm
Energy Design Resources provides information and design tools toarchitects, engineers, lighting designers, and building owners anddevelopers. Our goal is to make it easier for designers to createenergy efficient new nonresidential buildings in California. EnergyDesign Resources is funded by California utility customers andadministered by Pacific Gas and Electric Company, SacramentoMunicipal Utility District, San Diego Gas and Electric, SouthernCalifornia Edison, and Southern California Gas Company, under theauspices of the California Public Utilities Commission. To learn moreabout Energy Design Resources, please visit our Web site atwww.energydesignresources.com.
This design brief was prepared for Energy Design Resources byArchitectural Energy Corporation.
09/2007