Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv .com
Transcript
Page 1: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

Eelco KruizingaProject Manager

The European CCS Demonstration Project NetworkLessons on public engagement

eelco,[email protected]

Page 2: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 2 | | | 10 Apr 2023

Our Network

Members have concrete plans to demonstrate operation of the full CCS value chain:

by end of 2015

on a minimum power plant capacity of 250 MW, or equivalent industrial output (500 kt avoided CO2 emissions per year)

with at least 85% capture rate of the treated flue gas stream

Supporting first movers

26 May2011

Page 3: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 3 | | | 10 Apr 2023

Membership

Page 4: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 4 | | | 10 Apr 2023

Reports

26 May2011

Page 5: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 5 | | | 10 Apr 2023

Public engagement 2010: methodologies

National Energy Technology Laboratory (NETL) best practice guide for Public Outreach and Education for Carbon Storage Projects (Dec 2009)

1. Integrate Public Outreach into Project management

2. Establish a strong outreach team3. Identify key stakeholders4. Conduct and apply social characterisation5. Develop an outreach strategy and

communication plan6. Develop key messages7. Develop outreach material tailored to

audience8. Actively oversee the outreach throughout the

life of the CO2 storage project9. Monitor the performance of the programme

and changes in public perceptions and concerns

10. Be flexible, refine the outreach

26 May2011

Page 6: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 6 | | | 10 Apr 2023

Public engagement 2011: issues

Page 7: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 7 | | | 10 Apr 2023

Journey

Less of More of

Broad technology communication Compelling (local) value propositions

Climate Economy

Disseminating knowledge on CCS Fundamental understanding of CO2

Sending Dialogue

One message Messaging frameworks

Technology works Implementation works

Individual approaches Collaborative approaches

Page 8: Eelco Kruizinga Project Manager The European CCS Demonstration Project Network Lessons on public engagement eelco,kruizinga@dnv.com.

| 8 | | | 10 Apr 2023

Thank you for your attention