EFFECTIVEJANUARY 1, 2013

CHANGES THEY ARE HERE!

Page 3: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Introduction / Background

Summer 2012 – Long session of legislature received report from Legislative Study Committee recommending changes to Article 3, Chapter 44A

Bill known as House Bill 1052 addressed double payment in Little Miller Act projects, the “bankruptcy fix” for liens, false lien waivers, and “necessary and proper parties”

Page 4: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Background

An outgrowth of the North Carolina Bar Association’s Construction Law Section’s initial efforts to overhaul Articles 2 and 3 of Chapter 44A to modernize the processes in lien and bond claims.

Page 5: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

May 10, 2012 An Open Letter to Approved Attorneys of Chicago Title, Commonwealth Land Title, and Fidelity National Title Dear Approved Attorney: Chicago Title, Commonwealth Land Title, and Fidelity National Title announce that we will be curtailing mechanics' and materialmen's lien coverage in situations posing a significant risk of broken priority under applicable NC law at the time of their closing, effective for commitments issued after Friday, June 15, 2012.  Historically, North Carolinians could be assured they had some of the lowest rates, the lowest closing costs and the lowest claims losses in the Country, -- but no longer. Unfortunately, in recent years, we have paid increasing and significant losses from mechanics' lien coverage in North Carolina, creating a significantly higher claims ratio than the national average.  The claims submissions continue unabated in the current market. To address this problem, for the past several years, our companies and others have made extensive efforts, negotiating in good faith on a multitude of proposals and investing substantial amounts of time in attempts to create a legislative framework whereby innocent purchasers and lenders could be protected by law. Our goal was to provide protection for buyers purchasing and lenders extending loans on properties with recent or contemplated construction.  Unfortunately, thus far, our attempts have been thwarted or ignored. Unless and until this priority protection for these innocent parties under the law is provided, the risk is uncontrollable and unacceptable. Situations affected will include commercial and residential properties with recent construction or construction loans or both, i.e. those for which potential lien claimants may have the ability to file timely lien claims under N.C.G.S. Chapter 44A, Article 2, and for which the proposed purchaser and/or lender cannot obtain legal priority of record over those potential liens not yet filed at time of closing.   These are typically referred to as "broken priority" situations because priority cannot be assured at law and of record.  We recognize that, due to current law, this will have a significant impact on: Owners who are not protected by the current law and who may be unable to obtain this protection on new construction, residential or

commercial Lenders who are similarly unprotected by the current law and may be unwilling to provide loans for construction on or purchase of these

properties without this coverage Owner-builders who may be unable to provide assurance of the coverage to construction lenders, purchasers or their lenders Contractors and suppliers who may no longer be able to assume title insurance policy coverage is available if they are not paid by the

appropriate party with whom they contracted Attorneys representing all of the above, whether in closing transactions or mechanics' lien litigation We have negotiated in good faith for a reasonable solution to this "broken priority" or "hidden lien" problem in North Carolina in the hopes of avoiding this eventuality. We continue to stand ready to participate in any constructive meaningful negotiations to that end. However, because no such solution has been reached and there appears to be no prospect of a solution in the near future, we are no longer in a position to provide this coverage with no means of effectively and reliably assessing and managing the risk, for ourselves or our insureds. We would be remiss in our fiscal responsibilities to all of our insureds to continue to provide this coverage in these high risk situations. Please feel free to contact your local Chicago Title, Commonwealth Land Title, or Fidelity National Title counsel to discuss any questions.

Page 6: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Relocated Definitions :Moved within the Statute

Owner: “A person who has an interest in the real property improved and for whom an improvement is made and who ordered the improvement to be made.”

Contractor: “A person who contracts with an owner to improve real property.”

First tier subcontractor: “A person who contracts with a contractor to improve real property”

Second tier subcontractor: “A person who contracts with a first tier subcontractor . . .”

Third tier subcontractor: A person who contracts with a second tier subcontractor . . .”

N.C.G.S. § 44A-7 (1-2, 6, 8-9)

Page 7: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

House Bill 1052

Part of Bankruptcy “Fix”Section 44A-11 now clarifies that a claim of

lien upon real property is perfected when served upon the record owner, and filed under 44A-12

Page 8: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Previous LawEffective January 1, 2013

At the time of filing at the Clerk’s Office

Only after filing and service upon the owner N.C.G.S. § 44A-11(a)

Within 120 days of last furnishing N.C.G.S. § 44A-12(b)

New Perfection Requirements for Claims of Lien on Real Property

Page 9: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Previous LawEffective January 1, 2013

At the time of filing at the Clerk’s Office

Only after filing and service upon the owner and the contractor N.C.G.S. § 44A-11(1)

Within 120 days of last furnishing N.C.G.S. § 44A-12(b)

New Perfection Requirements AffectSubcontractor Subrogation Liens

Page 10: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Certification of Service

Section 44A-12 now requires the claim of lien on real property to include certification of service of the name parties. The amended claim of lien on real property form provides:

“I hereby certify that I have served the parties listed in paragraph (2) above in accordance with the requirements of G.S. 44A-11.”

Page 11: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

METHOD SERVICE ADDRESS

Personal Delivery (hand delivery)

Deposit for delivery with USPS; or

Deposit with specified overnight delivery services N.C.G.S. § 44A-11(b)

Address listed on building permit

Address listed on county tax rolls; or

Address for the party’s registered agent (published with the Secretary of State)

Complying with the NewService Requirements

Page 12: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Necessary or Proper Parties

Section 44A-13 now specifies that former or subsequent purchasers of real property are not necessary or proper parties to lien enforcement actions, if no additional relief is sought from those parties.

Page 13: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Bankruptcy Fix (Part 2)

Section 44A-18 states that a notice of claim of lien upon funds is immediately effective upon the first furnishing of labor, material or services.

The modification protects subcontractors of all tiers when a party above them in the contractual chain files for bankruptcy

Page 14: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

First and Last Dates of Contractors

Section 44A-23 (subrogation liens for subcontractors) permits subcontractors to use the dates of first and last furnishing of a higher-tier contractor – including the general contractor.

(NOTE: wording of statute is or – as in “either” “or” claimant’s first/last date or higher-tier contractor’s)

Page 15: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Bankruptcy Fix Part 3: “Disconnecting”

The amended Section 44A-23 removes the requirement that a notice of claim of lien upon fund be attached to the subrogated claim of lien on real property.

(NOTE: Does not prohibit it being attached, just does not require).

Page 16: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

False Lien Waivers

Amended 44A-24 adds a provision that the signing of a false lien waiver shall constitute “deceit and misconduct” subject to disciplinary action by contractor licensing board

Continues to be a criminal misdemeanor

Page 17: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Elements of Criminal Misdemeanor

False written statement,With knowledge it was false, andReceipt of payment for labor or materials by:

Person signing false statement, Person directing another to sign, or Any person or entity for whom the document was

signed

Page 18: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Everyone Is At Risk

Applies to all persons and entities licensed under Chapter 87 of North Carolina General Statutes Contracting entity and qualifiers General Contractors

Building, highway, public utilities, grading Plumbing, heating contractors Electrical contractors Other persons or entities covered by Chapter 87

Page 19: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Licensed Contractors or Qualifiers

Constitutes deceit and misconduct subject to disciplinary action under Chapter 87 of the General Statutes,

Sanctions: Revocation, suspension, or restriction of a license Ability to act as a qualifying party for a license

DON’T EXECUTE FALSE LIEN WAIVERS!!!CONFIRM ALL CERTIFICATIONS ARE

TRUE!!!

Page 20: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

THE ISSUE: STATE AND LOCAL PAYMENT

BOND CLAIMS

In The Beginning: Why Change What Was Working Well?

Page 21: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

2012 Amendment to North CarolinaLittle Miller Act

Enacted to avoid “double payment” by contractors on state and local public projects

For projects with building permits issued on or after January 1, 2013

If no permit, for projects commenced after January 1, 2013

Page 22: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Why Pre-Notice?

Truism: Under existing law, subs and suppliers were entitled to recover whether the tier above them had been paid or not.

Only requirement of sub or supplier was to give timely notice within 120 days and file suit within one year

Reality: As the economy tightened, so did sureties – lawsuits and delays increased changing economics of payment bond claims

Page 23: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Purpose of Pre-Notice

Wave a flag without a threatLet those from whom the money flows know

who is on the project and expects paymentOpen lines of communication while

preserving rightsProviding more accurate information to subs

and suppliers earlier in a project

Page 24: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

HB 1052: What stays the same?

Notice of claim on bond still must be given to contractor within 120-days of last performance if unpaid and still cannot file a lawsuit until at least 90-days after last performance

Must file action to enforce within one year

Page 25: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

What is new?

Contractor’s Obligations: MUST provide a copy of the payment bond within 7

days of receiving written request from sub/supplier

Page 26: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Subcontractor/Supplier’s Duty

Must provide a Notice of Public Subcontract within 75 days of date of first performance

HINT: Early is always better than late

Page 27: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Bail-out Provision for Delayed Notice

What if you miss the 75-day deadline? Look back 75-days from date notice is actually given

(recovery via bond for sum of invoices accrued in the 75-days prior to date of notice, and additional balance cannot be claimed)

If contractor fails to provide bond, then old law still applies

$20,000 maximum recovery if notice not provided by sub/supplier

Page 28: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

How to Serve Notices?

Rules apply to both request for bond and to serving Notice of Public Subcontract Certified mail Signature confirmation To contractor at office “regularly maintained for the

transaction of business”; or to agent identified in Contractor’s Project Statement

Or any method allowed for service of Summons – adds overnight courier with signature; private process server in certain circumstances

Page 29: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

New FORM: Notice of Public Subcontract

Name and address of subcontractor giving notice

General description of property on which work performed: street address, tax map lot and block number, reference to recorded instrument; any description that reasonably identifies the real property

General description of sub/supplier’s contract, including names and address of parties (who is up the chain from you to contractor); and

Page 30: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Notice of Public Subcontract (continued)

General description of the labor and/or material performed and/or furnished

Page 31: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Safety Net

If total billed for project is less than $20,000 then no notice required

If you blow the notice provisions (even the 75-day look back), still can claim up to $20,000

Page 32: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Contractors Project Statement

Only on State and Local Public Projects where Payment Bond required

Contractor responsible for preparing Project Statement N.C.G.S. §44A-27(f)

Page 33: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

How do I know who to serve?

Contractor’s Project Statement: Name of the Project Physical address of the Project Name of the contracting body (governmental agency) Name of the Contractor

AND

Page 34: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Contractor’s Project Statement (CPS) (Continued)

Name, phone number, and mailing address of agent authorized by Contractor to accept service of requests for payment bond, Notice of Public Subcontract, and Notice of Claim on Payment Bond

Name and address of the principal place of business of the surety issuing the payment bond

Page 35: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

How does one find the CPS?

Contractor required to provide to first tier subs

Failure to do so negates the protection from double payment

Subcontractors are then obligated to provide to each of their subs (1st Tier to 2nd Tier; 2nd Tier to 3rd, presumably no farther since lower tiers not entitled to bond claim)

No harm in requesting it in order to be proactive

Page 36: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Subcontractor Fails to Provide CPS

If 1st Tier fails to provide to 2nd Tier, then 2nd Tier not obligated to perform contract and cannot be sanctioned for failing to provide in timely manner (you have a right to protect yourself and can explain to the Contractor why you are not providing)

Important to establish this practice because right to claim against bond will most likely be cut if Contractor did what it was supposed to do and a sub failed – protection is non-performance

Page 37: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Reminders

Nothing changes with federal projectsThese changes apply solely to North Carolina

state and local projectsBecome effective for projects which begin on

or after January 1, 2013

Page 38: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Point to Ponder

No service mechanism specified for CPS, so if you are a first or second tier think about how you are going to prove receipt or delivery of a CPS

If a year later your 1st Tier testifies that he/she handed someone from your company the CPS how do you refute if it was not received, especially if you went ahead and delivered on the project. Once delivery is made, presumption is going to be against supplier

Page 39: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

Another Reminder

120-day Notice of Claim on Payment Bond not changedStill must be served as currently requiredStill must bring the lawsuit in the one year period

Page 40: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

QUESTIONS ON PAYMENT BONDS AND PRE-NOTICE?

Page 41: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

What about the other changes?

Page 42: EFFECTIVE JANUARY 1, 2013 CHANGES THEY ARE HERE!

More to come

Senate Bill 42Lien AgentSubject to “technical revisions” prior to April

1, 2013 effective dateWill be subject of future Webinar once it

becomes clearer what happens with the proposed revisions