+ All Categories
Home > Documents > EGR 599 Principles of Lean Systems Standard Work...

EGR 599 Principles of Lean Systems Standard Work...

Date post: 15-Aug-2018
Category:
Upload: lykhuong
View: 213 times
Download: 0 times
Share this document with a friend
14
1 EGR 599 Principles of Lean Systems Standard Work Overview 1 Learning Objectives Provide overview of standardized work concepts, tools and methods Importance of standardized work for managing in a lean environment Awareness of how to utilize this information to identify waste and plan opportunities for improvement 2 Definition of Standardized Work The written current best method for safe and efficient work that meets the required quality and provides the standard for continuous improvement 3 1 2 3 4
Transcript

1

EGR 599 Principles of Lean Systems

Standard Work Overview1

Learning Objectives

• Provide overview of standardized work concepts, tools and methods

• Importance of standardized work for managing in a lean environment

• Awareness of how to utilize this information to identify waste and plan opportunities for improvement

2

Definition of Standardized Work

The written current best method for safe and

efficient work that meets the required quality

and provides the standard for continuous

improvement

3

1

23

4

2

Standardized Work Is Not . . .

• Created by a supervisor or engineering

• Static; it is ever changing as workers continually improve the operation

• Buried in some desk• Merely worksheets; it is a system for

closely checking the actual performance of the production operations

4

The Role of Standardized Work

• Tool to build in quality at each process

• Manufacture only what sells and avoid over-production

• Produce at lowest cost

• Improve operations and minimize waste

• Centered around human motion

5

Categories of Work Motion6

Focus on waste identification

and reduction

WasteValueAdded

Necessary

Non-value Added

Work

Motion/Work??

Motion/Work??

3

Waste Defined7

WasteValueAdded

Work

Waste is anything that

takes • time• resources• effort• or space

but does not add value to

the product or service

delivered to the customer

Waste is anything that

takes • time• resources• effort• or space

but does not add value to

the product or service

delivered to the customerNecessary

Non-value Added

Motion/Work??

Motion/Work??

Necessary Non-Value Work Defined8

Necessary Non-Value

Work is any activity that

is necessary under the

current operating

conditions, but adds no

value to the product.

Necessary Non-Value

Work is any activity that

is necessary under the

current operating

conditions, but adds no

value to the product.

Waste

ValueAdded

Work

Necessary

Non-value Added

Motion/Work??

Motion/Work??

Waste

ValueAdded

Work

Value-Added Defined9

Value-added activities are

those which add form, fit or

function to the product. Any

activity that does not add form

or function is considered non-

value-added waste.

Value-added activities are

those which add form, fit or

function to the product. Any

activity that does not add form

or function is considered non-

value-added waste.

Necessary

Non-value Added

Motion/Work??

Motion/Work??

4

Seven Major Wastes

• Defects• Waiting• Motion• Over Production• Inventory• Over Processing• Conveyance

10

Pre-Requisites for Standardized Work

• Work Point Of View• Centered around human movements

• Work done the same way each time

• Equipment Point Of View• Minimal trouble with machinery or equipment

• Minimal fluctuation in the operation of equipment or production time

• Quality Point Of View

• Minimal trouble in processing quality

11

What Are The Benefits?

• Clear accessible documentation of the current best method

• Reduces variation, same way between job rotations and shifts

• Reduces costs from variation• Consistent quality results• Consistent quality increases • Competitiveness, customer satisfaction, job

security.• New workers/operators learn quicker

12

5

What Are The Benefits? (cont’d)

• Learning from others’ experiences (shared learning)

• Organizational knowledge• Easier to spot problems• Base for problem solving• Base for improvement• Expertise reflected in standard work

Results inPROCESS STABILITY

13

Standardized Work is a Baseline

• It serves as a foundation for continuous

improvements

• Basis for problem solving

• All workers use standardized work once it is

implemented

• Post at line side, naming the (current) best

method for “doing the job”

14

Standard Work Forms15

Part No.

& Name

Process

Name

No. Man. Auto Walk 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

Totals

RequiredPer Shift

TaktTime

Time

Operation

Date

Dept.

QPS WorkAnalysis Sheet

ManualAutomaticWalking

Part No.

Part NamePcs

Step

No.

Manager Supervisor ProducitonCapacity Sheet

Complete

Name

Current OutputPerson / Day

Base Time Tools

Max DailyOutput

Process Name Machine No.

Totals

Date

TimeMachine

TimeManual ChangeTime To

Group

frequencyTime tochange

Remarks

Line name

ProcessingCapacity

Standard Work Sheet Combination Time Table

Capacity Sheet

6

Three Elements of Standardized Work16

1. Takt Time

3. (Standard Work-in-Process -(SWIP))

2. Work Sequence

1

2

34

5

6

1

2

3

6

5

4

Standard Work in‐Process

#

Approved by: MC Champ

Cell / Workstation Layout

Takt Time: 

180

SWIP: 0

Operation Number: 15 Written by: Luther Cottrell Date: 01/07/2010

Tooling RequiredManual Auto WalkTime

Standard Work Sheet

1 Collect cup and return 4

Step No Work Elements

Operation Name: Brew Tea

4Spoon

6

2

3

3

2 Collect spoon and return 3

3 Collect tea and sugar and return 6

4 Collect milk and return 3

5 Collect teapot and return 2

6 Place teabags in teapot 8

58 Return kettle and boil water 5 180

7 Fill kettle with water 10

39 Fill teapot with hot water 8

210 Return kettle 2

411 Allow tea to brew 120

12 Pour tea into cup 4

13 Add milk 3

14 Add sugar 3

15 Stir with spoon 5

3266 300

Total Process Time

Safety 

Concern

Quality 

Concern

In Process 

StockKey Point

Health & Safety Points

5

Spoon

Cold Water

1

3

4

Work Area

Cups

Tea/Sugar

Milk

Tea Pot

Kettle

12 1 14

6 9 11

2

7

11 8

Standardized Work Sheet

17

4. SWIP

2. Work SequenceTimes

3. Takt Time

5. Area Layout

1. Work Sequence 6. Work Movement

7. Safety & Quality Checks

***Perform all work according to applicable 1E specs***

TAKT Time18

Total available production timedivided by total customerrequirements

7

TAKT Time19

Note: Takt time makes no allowances for machine inefficiency (e.g. breakdowns, changeovers. In real life, the target cycle time is used instead of the takt when inefficiencies have to be taken into account in the production planning

Takt time is the time in which one part needs to be produced to satisfy customer demand

Takt time = total time available* total customer demand

Clocked time from operators

Lunch or breaks

5’s Team meetings

Total time available

Management allowances

1 shifts / day

8.0 hrs/shift

8.0 hours/day 3/4h/day

5 min/day

10 min/day

7.0 h/day

Includes machine inefficiencies/ breakdowns

Cycle Time20

The actual time it takes to process 1 unit

• includes human & machine work and

walking & waiting time.

• Measured by taking the average time

measured over a representative sample

size.

TAKT & Cycle Time Relationship

• If TAKT Time and Cycle Time are not equivalent, an

imbalance exists in the operating system

• When TAKT Time and Cycle Time are equivalent,

overproduction is prevented by maintaining the

cycle

21

Operators

TAKT Time (1 min.)

A B C D E

1 min.

CycleTime

8

Work Sequence

Work Sequence is the order in which the work elements are done in a given process

22

Note: When work sequence is not clear process steps vary, some may be omitted and defects occur.

1

2

3

6

5

4

Standard workingsequence

Work Sequence

Work Sequence

• Work occurs in a sequence of fixed steps

• Sequence steps are always followed

• Failure to follow work sequence can:

• Compromise Safety

• Cycle time fluctuation

• Defects generated

• Steps in process overlooked

• Machinery may be improperly used and

subsequently damaged

23

Standard Work In-Process

The Standard Work In-Process (SWIP) is the minimum number of unfinished components necessary for the smooth completion of a work sequence.

24

1

2

3

6

5

4

Standard Work in‐Process

9

Controlling Standard In-Process Stock

• Why is Standard In-Process stock determined?

• Minimizes the amount of in-process inventory between manufacturing steps in the same work station

• Determines the minimum amount of stock required to keep the process running

• Sets maximum stocking level

25

Reflection

• What is the difference between TAKT Time

and Cycle Time?

• Why is a standard work sequence

necessary?

• What is Standard In-Process Stock?

26

Production Capacity SheetPart No.

Part NamePcs

StepNo.

Manager Supervisor ProducitonCapacity Sheet

Complete

Name

Current OutputPerson / Day

Base Time Tools

Max DailyOutput

Process Name Machine No.

Totals

Date

TimeMachine

TimeManual ChangeTime To

Group

frequencyTime tochange

Remarks

Line name

ProcessingCapacity

Used in processes that incorporate machines

Lists the production capacity of each process

Shows the bottleneck process

Provides the focus for Continuous Improvement activities

Becomes the basis for Standardized Work Combination Tables

27

10

Production Capacity Sheet28

OPERATIONAL TIME PER SHIFT (SECS)PRODUCTION CAPACITY =

TIME TO COMPLETE +INTERVAL OF CHANGE

SETUP TIME

e.g. 26,400

PRODUCTION CAPACITY = 607 units

43 300150

+

Part No.

WR2A N 24631 AD

Part Name 593#8 Pinnion 26400 Secs

Step

No.

1 Gear - Rough Cutitng GC-614 5 38 43 300 150 607

2 Gear- Edge Chamfering CH-228 6 7 13 2000 60 2026

3 Gear - Front Finishing GC-1444 6 38 44 300 150 593

4 Gear - Rear Finishing GC-1445 6 30 36 300 230 718

5 Check TS-1100 7 3 10 - - 2640

Group

frequencyTime tochange

Remarks

Line name

Date

TimeMachine

TimeManual ChangeTime To

Max Daily

Output

Process Name Machine No.

Totals

Manager Supervisor ProducitonCapacity Sheet

Complete

Name

Total Available

Time (seconds)Base Time Tools

ProcessingCapacity

29

Standardized Work Combination Table30

• The Standardized Work Combination Table is the result of examining the range of work a single work group member can cover.

• It is based on the Takt Time.

11

Standardized Work Combination Table

• Why do we need to use SWCT?

• Combines human and machine movement based

on Takt Time

• Determines the range of work for which an

employee is responsible and the work sequence

• Allows for judgment of the impact of a change in

Takt or other operating parameter changes

31

Standardized Work Combination Table Example

32

32

Importance of People

People

are the focus of standardized work

33

12

Importance of People

• Defines safe work practices

• Creative thinking leads to significant

improvements in quality and

productivity

• Affects how workers efficiently

interact with machinery

• Assists in training new workers

34

Role of Team Leader/ Members

• Define and complete std. work forms

• Update SWS forms following continuous

improvement activities

• Maintain SWS forms.

• Ensure conformance to the agreed

standardized work sequence

35

Role of Production Management

• Ensure consistency of approach across all

work groups

• Ensure that operators are conforming to the

standardized work sequence

• Provide appropriate guidance and support

for continuous improvement and re-balance

activity

36

13

Methods for Monitoring Sustainability37

• Standardized work must be updated each time there is a process or machine change

• Management should review the operators standardized work (go and see) on a regular basis

Why do We Need to Audit Standardized Work Sheets?

• Maintain safety at the job site

• Maintain quality at the job site

• Maintain correct work sequence

• Insures training consistency and

efficiency

• Highlights problem solving

opportunities

38

Key Points

• Standardized Work Sheets for every

production job function

• Standardized work is fostered and

understood by all employees

• Workers are the focal point of standardized

work

39

14

Standardized Work Summary

“…High production efficiency has been maintained by preventing the recurrence of defective products, operational mistakes, and accidents, and by incorporating workers’ ideas. All of this is possible because of the inconspicuous standard work sheet.”

- Taiichi Ohno

40

41


Recommended