Date post: | 29-Jul-2015 |
Category: |
Documents |
Upload: | suzanne-chinner |
View: | 518 times |
Download: | 76 times |
EIC CONTRACTOR’S GUIDE TO THE FIDIC
CONDITIONS OF CONTRACT FOR EPC
TURNKEY PROJECTS (THE SILVER BOOK)
FRANK M KENNEDY
Carillion Plc and Chairman of the EIC 1 Conditions
of Contract Working Group
In October 1997, EIC received from FIDIC the first drafts of the 1999 First Editions of four new standard
forms of contract and were invited to comment. EIC gratefully accepted this opportunity and undertook a
comprehensive review of all of the new forms and submitted a large number of proposals for
amendment, clarification and improvement. A significant number of EIC proposals were incorporated in
the Test Editions of 1998 and, following further exchanges, in the First Editions of September 1999. In
common with a number of other reviewers of the draft forms, EIC’s objective was to try and ensure that
the new documents maintained the same balance and fairness between client and contractor that has
been the hallmark of FIDIC contracts. In our view the Silver Book falls a long way short of this objective.
The Silver Book will create problems for employers and contractors and is unlikely to achieve the
dispute free projects desired by FIDIC. It sets out to place almost every conceivable risk on the
contractor but within a framework of conventional FIDIC contract administration procedures. Such an
approach is a long way from good turnkey practice, which gives the contractor a fair degree of freedom
to decide how to achieve performance criteria unhindered by bureaucratic processes. Interestingly, it is
also contrary to FIDIC’s own recommendation in the Introductory Note to the Silver Book that the
“Contractor should be given freedom to carry out the works in his chosen manner”. It is this scope for
interference in the design and construction process along with the Employer’s right to unilaterally issue
instructions that so troubles contractors rather than any fundamental objection to the principle of risk
transfer. Regrettably, examples of turnkey projects falling behind programme whilst the contractor
attempts to satisfy the Employer’s engineer’s requests for further information before authority to
proceed with construction is permitted, are all too common. What could cause greater disagreement and
dispute however is the attempt to make the
1 European International Contractors was founded in 1970 and is a federation of construction industry trade
associations from 15 European countries. The value of international business carried out by members amounts to
around 30 billion Euro per annum. Copies of the Guide can be obtained from EIC at: European International
Contractors, Kurfurstenstrasse 129, D-10785 Berlin, Germany. Tel: ++49 30 21 286 244. Fax: ++49 30 21 286 285.
Email: [email protected]
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
505
contractor responsible for information provided by the employer who is not even responsible for the
accuracy of the Employers Requirements. It is difficult to understand the thinking behind such a
requirement.
In the Introductory Note to the Silver Book, FIDIC set out their rationale for preparing it, point out some
of the consequent obligations on Employers and even go so far as to warn against its use in certain
circumstances. A more imaginative solution would have been to create a form of contract which
establishes a fair balance of risk between the parties, based on their respective abilities to deal with risk.
This would provide the Contractor with the freedom to perform his obligations and give the Employer
confidence that he is getting what he is paying for.
In the past, contractors have taken comfort from the fact that contracts produced by FIDIC have laid
down a predictable and practical starting-point for negotiations between the parties based on equitable
and balanced risk sharing. It is the Silver Book’s departure from the traditional FIDIC contractual and risk
sharing philosophy, that has prompted EIC to publish a Contractor’s Guide and highlight many of the
potential pitfalls of the Silver Book. In preparing our guide we have tried to avoid the pitfall of only
arguing the case for the contractor and we have attempted to point out what we see as potential areas
of difficulty for both employer and contractor. Consequently, we welcome the opportunity offered by the
International Construction Law Review to publish the guide, open a debate with a wider audience and
test the validity of our arguments.
1. GENERAL PROVISIONS
1.4 Law and Language
Provides that “The Contract shall be governed by the law of the Country (or other jurisdiction) stated in
the particular conditions”. The Contractor should be aware that under certain Civil Law jurisdictions some
Silver Book conditions may be considered unfair trade terms and therefore inapplicable. Also there may
be mandatory laws which cannot be overridden by the Contract.
1.9 Confidentiality
Obligates both Parties to treat the details of the Contract as confidential. If the Contractor’s design
contains data which is commercially sensitive and which he does not wish to be placed in the public
domain, the second sentence of this Sub-Clause, referring to restrictions on publication or disclosure of
particulars, should also be an obligation on the Employer.
[2000
The International Construction Law Review
506
1.13 Compliance with Laws
The Contractor shall comply with all applicable laws. However the responsibility for obtaining permits,
licenses or approvals is not entirely clear when Sub-Clauses 1.13 (a) and (b) are compared:
Sub-Clause 1.13 (a) provides that “the Employer shall have obtained (or shall obtain) the planning,
zoning or similar permission for the Permanent Works”. Sub-Clause 1.13(b) states that “the Contractor
shall…obtain all permits, licences and approvals, as required by the Laws in relation to the design,
execution and completion of the Works and the remedying of any defects”.
Responsibility for obtaining permissions is ambiguous and should be clarified. For instance, what are
“similar permissions” for which the Employer is responsible pursuant to Sub-Clause 1.13 (a) and how do
they fit with the Contractor’s obligations under Sub-Clause 1.13(b)?
Ideally, the Contract should include a detailed schedule of the permits required and should identify the
responsible Party. In the event that the Contractor is responsible, then the Employer, under Sub-Clause
2.2(b) (e) [Permits, Licences and Approvals] “shall (where he is in a position to do so) provide reasonable
assistance to the Contractor”. Consequently, any delay in the issue of permits caused by the Employer’s
failure should entitle the Contractor to an extension of time in accordance with Sub-Clauses 8.4
[Extension of Time for Completion] and 8.5 [Delays Caused by Authorities] .
In particular, those permits that are required to allow the project to be developed at the Site of the
Works should be specifically identified in the Contract as being the responsibility of the Employer.
1.14 Joint and Several Liability
Where the Contracting Party is a joint venture or consortium, this Sub-Clause requires that, the parties to
such joint venture or consortium must be jointly and severally liable to the Employer.
Conversely, should the Employer consist of two or more legal entities then, in such a case the
obligation should be reciprocal.
2. THE EMPLOYER
2.3 Employer’s Personnel
This Sub-Clause relates to the Employer’s obligations in respect of his personnel and contractors
employed directly by him. It should be noted that there is no express obligation on the Employer to
secure generally that his other contractors co-operate with the Contractor other than in the respects
identified.
The effects of any delay or disruption caused by the Employer’s personnel
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
507
and contractors are dealt with under Sub-Clause 8.4 (c) [Extension of Time for Completion] which
provides only for granting a time extension for such events. There is no provision in the Contract to
recompense the Contractor for the consequential cost of delay and disruption caused by such events.
Contractors should carefully consider the possible effects of such events in light of the obligation under
Sub-Clause 4.12 [Unforeseeable Difficulties] where the Contractor is deemed to have foreseen all
difficulties and costs of successfully completing the Works.
2.4 Employer’s Financial Arrangements
FIDIC recognises the need for the Contractor to be satisfied that the Employer has the necessary
financial strength to undertake his obligations under the Contract. This Sub-Clause requires that “the
Employer shall submit, within 28 days after receiving any request from the Contractor, reasonable
evidence that financial arrangements have been made and are being maintained which will enable the
Employer to pay the Contract Price”.
This is a crucial obligation on the Employer, particular where funding is being provided by third parties.
Fundamentally, the Contractor should have the right to refuse to undertake any Variation if he believes
that the available funding is insufficient to cover the varied Works. (See also comments in respect of
Sub-Clause 13.1 [Right to Vary] ).
The Contractor should also have a right to be made aware of any terms, conditions or step-in rights
that exist in any agreement between the Employer and his Lenders. If any direct agreement with regard
to the project is to be made between the Lenders and the Contractor then the terms and conditions of
such an agreement should be provided to the Contractor prior to signature of Contract.
A powerful sanction is available to the Contractor should the Employer fail to furnish reasonable
evidence. The Contractor is entitled to suspend the work or terminate the Contract under Sub-Clauses
16.1 [Contractor’s Entitlement to Suspend Work] and 16.2 [Termination by Contractor] . However, what
constitutes “reasonable evidence” is undefined and the Contractor should establish this prior to
submitting a tender. Failure to do so could prejudice any attempt to obtain more detailed information
during the currency of the Contract, for example in the event of a major variation being instructed.
Contractors should give due consideration to the risk associated with continuing to work during the 28
day period available to the Employer to provide the required evidence and the further extended notice
periods required to comply with the suspension and termination provisions.
2.5 Employer’s Claims
This Sub-Clause offers some protection to the Contractor and obligates the Employer to follow a given
procedure if he “considers himself to be entitled
[2000
The International Construction Law Review
508
to any payment…and/or to any extension of the Defects Notification Period”.
The Employer must notify the Contractor “as soon as practicable” and give particulars of his claim,
after which the Parties may agree the claim or failing which the Employer may then make a
determination in accordance with Sub-Clause 3.5 [Determinations] .
The provisions of this Sub-Clause are also mandatory in the event that the Employer wishes “to set off
against or make any deduction from an amount due to the Contractor”.
A provision entitling the Contractor to claim against the Employer is found in Sub-Clause 20.1
[Contractor’s Claims], but is much more onerous on the Contractor compared with Sub-Clause 2.5. (See
comments under Sub-Clause 20.1.)
3. THE EMPLOYER’S ADMINISTRATION
3.1 The Employers Representative
The Employer is completely free to appoint any person to act as the Employer’s Representative and/or to
revoke any such appointment. Invariably it will be important for the Contractor to establish whether that
representative will be an independent Consulting Engineer or a member of the Employer’s personnel. It
is also important for the Contractor to be aware of the exact nature of the duties and authority assigned
to the representative (s).
Contractors should appreciate a fundamental difference between a two Party contract such as the
Silver Book and traditional FIDIC forms of contract. Under the Silver Book, the Employer’s Representative
acts directly for the Employer and is only responsible for looking after his interests. This is particularly
relevant when compared to the role traditionally carried out by the engineer which required the exercise
of discretion and impartiality even when fulfilling the role of Employer’s Representative.
Contractors should also take note that the powers of the Employer’s Representative are potentially
very comprehensive. “Unless and until the Employer notifies the Contractor otherwise, the Employer’s
Representative shall be deemed to have the full authority of the Employer under the Contract, except in
respect of Clause 15 [Termination by Employer]. ”
3.2 Other Employer’s Personnel
The Employer or the Employer’s Representative may delegate powers to assistants. The power to
delegate authority to these third persons is very broad, and the Contractor should be alert to the
possible confusion and
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
509
interference that might arise if too many assistants are appointed. The Contractor is entitled to receive a
copy of the written delegation which describes clearly the role of the assistant or the like and the
delegation does not become effective until received by the Contractor.
3.4 Instructions
This Sub-Clause is very specific in terms of what constitutes an instruction under the project and requires
that “Each instruction shall be given in writing and shall state the obligations to which it relates…”.
Contractors should ensure that all instructions comply with these requirements and should note that
verbal instructions would appear to have no validity under the Contract.
3.5 Determinations
Notwithstanding the fact that FIDIC has drafted the Silver Book as a two-party contract, the Employer is
given the unilateral right under this Sub-Clause to determine matters in respect of a broad range of
matters. The thinking behind this was presuambly to ensure that decisions are taken when required to
minimise delay. The Employer has such rights in respect of the Sub-Clauses listed below.
2.1 [Right of Access to the Site];
2.5 [Employer’s Claims];
4.19 [Electricity, Water and Gas];
4.20 [Employer’s Equipment and Free-issue
Materials];
4.24 [Fossils];
7.4 [Testing];
8.9 [Consequences of Suspension];
9.4 [Failure to Pass Tests on Completion];
10.3 [Interference with Tests on Completion];
11.4 [Failure to Remedy Defects];
11.8 [Contractor to Search];
12.2 [Delayed Tests];
12.4 [Failure to Pass Tests after Completion];
13.3 [Variation Procedure];
13.7 [Adjustments for Changes in Legislation];
14.4 [Schedule of Payments];
15.3 [Valuation at Date of Termination];
16.1 [Contractor’s Entitlement to Suspend Work];
17.4 [Consequences of Employer’s Risks];
19.4 [Consequences of Force Majeure];
20.1 [Contractor’s Claims] .
It may seem strange that one of the parties has the right to make
[2000
The International Construction Law Review
510
determinations regarding the respective rights of the parties. This was normally reserved for the truly
impartial engineer—a rare bird nowadays. However, the Contractor is not obliged to give effect to the
determination provided he gives notice of his dissatisfaction within 14 days in which case the
determination is not binding.
The fact that the Employer has the right to make a determination is not necessarily against the
interests of the Contractor. If no agreement is achieved and the Employer fails to make a fair
determination then this will be a breach of Contract and the Contractor may refer the matter to the
Disputes Adjudication Board.
No time limit is placed upon the Parties reaching agreement and the Sub-Clause does not define a
period in which the Employer is required to make a determination. It is suggested that a time limit of 28
days should be imposed on the Employer to reach agreement with the Contractor and that a further 14
days are provided for making a determination upon failure to reach agreement.
The Contractor must be aware that the Sub-Clause places no obligation of the Employer to label his
decision a determination. Conversely, the Contractor is required to “give notice, to the Employer, of his
dissatisfaction with a determination within 14 days of receiving it”. Consequently in cases of dispute as
to whether a communication was a determination or otherwise it would be very unusual and grossly
unfair for the Contractor to lose his rights simply as a result of a failure to comply with the obligation to
notify. However, every effort should be made to avoid dispute by establishing whether a communication
from the Employer constitutes a determination or not. Avoidance of doubt is the safest way of ensuring
that there is no loss of entitlement through any failure to lodge the required notice.
4. THE CONTRACTOR
Clause 4 [The Contractor] and Clause 5 [Design] set out the principal obligations and risks which are to
be carried by the Contractor and both are much more onerous than any imposed by previous FIDIC
Conditions of Contract. These two clauses intereact with each other on a number of very important
issues and should be studied together to ensure that the extent of a contractor’s potential exposure is
fully understood. The principal matters in Clause 4 which justify meticulous analysis and prudent
appraisal are:
Fitness for purpose, Sub-Clause 4.1 [Contractor’s
General Obligations],
Nominated subcontractors, Sub-Clause 4.5
[Nominated Subcontractors],
Setting out, Sub-Clause 4.7 [Setting Out],
Site Data, Sub-Clause 4.10 [Site Data],
Unforeseen difficulties, Sub-Clause 4.12
[Unforeseen Difficulties] .
Pt. 4]
ETC Contractor’s Guide to the Fidic Conditions
511
4.1 Contractor’s General Obligations
Fitness for purpose obligations are of particular concern where a contract is carried out under
jurisdictions based on English Law or Common Law. It may be less of an issue under other jurisdictions
where fitness for purpose obligations have been common practice for many years. However the issues
discussed below are relevant to both situations.
According to this Sub-Clause, “When completed, the Works shall be fit for the purposes for which the
Works are intended as defined in the Contract”.
Under Sub-Clause 5.1(b) [General Design Obligations] the Employer is responsible for the correctness
of the definition of intended purpose. Immediately however, we must consider the wider implications of
Sub-Clause 5.1, which requires the Contractor to satisfy himself as to the accuracy of the Employer’s
Requirements. Contractors must therefore ensure that the definition is clear and unambiguous and that
it is not open to reinterpretation at a later date. If a satisfactory definition is not available prior to tender
submission then it would be prudent in almost all circumstances to prepare a definition acceptable to
both Parties prior to contract signature. Failure to do so could lead to dispute later.
With regard to the full extent of the obligation to design for fitness for purpose it may not be possible
to pass the full liability on to any third party design consultant appointed by contractors. Current practice
is for consultants to accept only an obligation to design with “reasonable skill and care” because
insurance to cover the risk associated with fitness for purpose is not presently universally available and
is a particular problem for British consultants.
In a perfect world, it should be obvious to all concerned that contractors cannot, within their lump sum
price, be responsible for providing everything that an Employer later claims that he understood to be
included. In reality, some Employers will choose to use the Silver Book for that very reason. An
unscrupulous Employer could argue that the Contractor is responsible for an omission and refuse to issue
a variation order. The Contractor’s only protection against this type of behaviour is to prepare and agree
as comprehensive and as detailed a schedule, as it is possible to prepare, setting out exactly what it is
that is being provided.
Failure of the Works to be fit for purpose carries punitive sanctions limited only by the terms of Sub-
Clause 17.6 [Limitation of Liability] .
4.5 Nominated Sub-Contractors
The concept of an Employer nominating a subcontractor is hardly compatible with the obligations of
the Contractor in a Turnkey Contract. Whilst this Sub-Clause does contain a provision for the Contractor
to “raise reasonable objection…with supporting particulars”, it does not convey an absolute right to
reject a nomination. Manifestly, it is impossible to comply with such a requirement where the
Contractor’s concerns arise, say, from the
[2000
The International Construction Law Review
512
relationships that are perceived to exist between the Nominated Subcontractor and either the Employer
or his advisers. Contractors would be well advised to avoid or re-negotiate the terms of any contract that
envisages such an arrangement.
In the event that the Employer instructs the employment of a particular subcontractor despite the
Contractor’s reasonable objections then the Contractor will have a very strong case against the Employer
to recover all of his costs arising from the default of the Sub-contractor.
4.6 Co-operation
This Sub-Clause spells out the obligations of the Contractor. However, there is no equivalent or
corresponding obligation on the Employer to secure that his directly employed “other contractors” co-
ordinate or co-operate with the Contractor. In most contracts, but especially those where the Employer
intends to place significant other contracts, it would be prudent to ensure that the Employer assumes
clear and reciprocal obligations.
4.7 Setting Out
Taken at face value, the obligations under this Sub-Clause would appear to be fair and reasonable and in
accordance with normal practice. “The Contractor shall set out the Works…and shall be responsible for
the correct positioning of all parts of the Works, and shall rectify any error”. However, Sub-Clause 5.1
[General Design Obligations], which deals with the Contractor’s design obligations, makes the Contractor
responsible for the accuracy of the information provided by the Employer! There are some exceptions to
this general requirement, but they are at best, limited and somewhat confusing in their application. Two
courses of action are open to contractors:
If practicable, check the setting out data prior to
submission of the tender, or
Clarify the basis of the offer and propose that the
Employer retain responsibility under Sub-Clause
5.1.
The question of responsibility for data is discussed more extensively under Sub-Clause 4.10 [Site Data]
and Clause 5 [Design] .
4.10 Site Data
The obligations and risks to consider under this Sub-Clause are essentially similar to, but much more
wide-ranging than, those identified above under Sub-Clause 4.7 [Setting Out] . “The Employer shall have
no responsibility for the accuracy, sufficiency or completeness of such data, except as stated in Sub-
Clause 5.1 [General Design Obligations] .” Put simply, whatever the source, the Contractor is responsible
for verifying data. In particular, the Contractor
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
513
is responsible for verifying and interpreting all data on subsurface and hydrological conditions, including
environmental aspects. Such obligations are extremely onerous. The precise extent to which the
exceptions offered under Sub-Clause 5.1 are actually applicable to the data supplied to the Contractor is
debatable and it is recommended that the terms of the exceptions on offer in each individual contract be
carefully scrutinised.
Significantly, the disclaimer covers any information provided during the performance of the Works.
Consequently the Contractor cannot rely on information provided by the Employer during the execution
of the Contract and must always therefore establish its veracity unless the Employer retains liability
under Sub-Clause 5.1 [General Design Obligations] .
FIDIC recognise that, under certain circumstances, it will be impossible for contractors to comply with
these obligations and propose a way out of this particular dilemma. They suggest, in the Introductory
Note, that the Silver Book is not suitable for use where “there is insufficient time or information for
tenderers to scrutinise and check the Employer’s Requirements or for them to carry out their designs,
risk assessment studies and estimating”. FIDIC go on to state that, if contractors believe that such a
situation pertains then they are advised to draw the Employer’s attention to FIDIC’s own
recommendation which is to suggest a suitable alternative form of contract e.g. the Yellow Book! Instead
of admitting that the Silver Book is inadequate on this important issue and amending it, they leave the
Employer and the Contractor to choose a totally different form of contract at such a late stage in the
implementation process that their proposal cannot be considered a credible alternative! Inevitably, it
must be concluded that FIDIC have opted out and ducked the task of solving a difficult problem of their
own making.
4.12 Unforeseeable Difficulties
The language used in this Sub-Clause is uncompromising in the extreme and its scope and application
are much more wide-ranging than any previous clause covering unforeseen conditions. The
consequential effects of all unforeseen difficulties are passed to the Contractor, “Except as otherwise
stated in the Contract”. Sub-Clause 4.12(b) requires the Contractor to foresee and allow in the price for
every eventuality however unforeseeable! Presumably this is intended to include events that are
completely outwith the control of the Contractor. It is difficult to imagine a clause which would be more
threatening to contractors and which would leave them more open to unscrupulous Employers who could
allege that any difficulty, however inconceivable at tender stage, could be laid at the Contractor’s door
under this Sub-Clause. Contractors should beware!
4.15 Access Route
On certain projects there could well be an inconsistency between this Sub-Clause and Sub-Clause 2.1
[Right of Access to Site] which requires the
[2000
The International Construction Law Review
514
Employer to give the Contractor the “right of access” to the site. A matter to be clarified pre-contract.
4.21 Progress Reports
The requirements of this Sub-Clause are unnecessarily detailed and over prescriptive. Contractors would
be well advised to agree at tender stage a more appropriate format for the particular contract.
5. DESIGN
A number of references have already been made to Clause 5, largely because it deals with the
responsibility of the respective parties for the basic data, and it is for that same reason that it is
considered to be one of the most important in the Silver Book. As has already been explained, Clause 5
[Design] establishes the fundamental and crucial principle that the Contractor has wide responsibility for
the correctness of the Employer’s Requirements and there are only limited and inadequately defined
exceptions to this principle. It is in the Contractor’s interest to make all proposed exceptions clear and
precise.
5.1 General Design Obligations
This is a complex Sub-Clause with many potential pitfalls for the unwary and it is well worth having a
further look at the major disclaimer it contains. “The Employer shall not be responsible for any error,
inaccuracy or omission of any kind in the Employer’s Requirements as originally included in the
Contract.” The problem created by this statement is particularly evident when considering the important
matter of the Employer’s responsibility for design criteria. This would normally be the Employer’s
responsibility, yet the Silver Book fails to establish this as a fundamental principle and this should be
covered by the exceptions provided for in this Sub-Clause.
The Sub-Clause is equally vague on the likely content of the Employer’s Requirements. The whole case
for producing a turnkey form of contract such as the Silver Book was based on the thinking that the
Contractor must comply with the Employer’s Requirements and carry all risks in doing so. Yet the only
indication in the Silver Book of what the Employer’s Requirements might be or what they might contain
is contained in the Guidance Notes. According to FIDIC they are to be specifically prepared project by
project by “suitably-qualified engineers”, no doubt taking many months to do so! Notwithstanding all of
these considerations, the Contractor is expected, prior to submission of the Tender, to check the
Employer’s Requirements and to verify his design criteria and calculations. To do this properly and
establish a high degree of confidence in the Employer’s data would be an enormous undertaking.
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
515
Design criteria encompass many and varied technical matters that include amongst other things,
quality standards, process design, capacity, design life and, in the case of process and power plants,
equipment specifications. The Contractor must not only establish whether the design criteria are
factually correct but must also establish whether they are adequate to achieve the desired performance
and intended purpose, all in the limited time available during the tender period! Inevitably, it will be
prudent for contractors to establish their own design criteria to ensure compatibility with their own
design and to make this an integral part of the offer, even where design criteria have been provided by
the Employer.
Employers are likely to insist that performance criteria and definitions of intended purpose be complied
with even if the technical specification fails to produce satisfactory compliance. Contractors must
understand therefore that the Employer’s definition of intended purpose and his required performance
criteria will invariably take precedence over detailed technical specifications.
Paradoxically, it could well be that in situations where the performance criteria are vague or are
difficult to measure, then a statement of and compliance with a detailed technical specification could be
a more appropriate safeguard.
Whilst there is no specific declaration to limit the Contractor’s responsibility for omissions it should be
reasonably limited to the physical limits of the Works, especially if the alleged omission could not
reasonably be established by a careful study of the intended purpose or from legal requirements or
standards. To be on the safe side, proposals should be appropriately clarified.
The exceptions offered under Sub-Clause 5.1 are of fundamental importance to the Contract. They
would appear to mitigate many of the Contractor’s extremely wide responsibilities for the definition and
specification of the Works. It is crucial to keep sub-paragraphs (a) to (d) in mind when studying the
Employer’s Requirements and negotiating the Contract. They are important enough to consider one by
one.
Sub-Clause 5.1 (a) states that, “portions, data and information which are stated in the Contract as
being immutable”. This means that they are incapable of being changed and are, therefore mandatory
on the Contractor and must be the responsibility of the Employer. It is therefore very important to check
and confirm that the Employer’s Requirements state very specifically which parts are immutable. This is
such an important matter that it must not be left to post contract interpretation and argument. Of
particular importance is the need to identify any part of the Employer’s Requirements which uses the
term “the Contractor shall” in respect of any data or information, as this could well make the
requirement immutable, insofar as it is incapable of being changed by the Contractor.
Under Sub-Clause 5.1 (b), the Employer is responsible for the correctness of the definition of the
intended purpose and it is reasonable to conclude
[2000
The International Construction Law Review
516
therefore that the Employer also retains responsibility for ensuring that it actually fulfils his needs.
Unfortunately, the Silver Book does not deal with the situation where the Employer has provided no clear
and identifiable definition. If this important issue is left unresolved, it could well be that the definition
could only be established later by an interpretation of the Employer’s Requirements. Such a situation
would be unsatisfactory in the extreme and contractors would be well advised to insist that a definition
be provided in the Employer’s Requirements.
Criteria for testing and performance is normally the Employer’s responsibility and this is as stated in
Sub-Clause 5.1(c), so this issue should not be a problem. Again however, contractors would be well
advised to satisfy themselves that they are appropriate to their proposed design for the particular
project.
Sub-Clause 5.1(d) will undoubtedly give rise to a significant amount of discussion. According to this
Sub-Clause the Employer is responsible for “those portions, data and information which cannot be
verified by the Contractor, except as otherwise stated in the Contract”. This is, to put it mildly, an
interesting statement. The words “cannot be verified” are obviously open to interpretation but in this
context, probably mean that it is either impossible or impractical to verify. Nowhere in the Contract or
guidance notes is advice offered on how this is to be decided or against what yardstick it is to be
measured. It might be assumed that the available time would be a deciding factor and yet no comfort is
offered to the Contractor by including a statement such as “with reasonable regard to time and
economy”. However, in the event of dispute, commercial practicality could still be a reasonable defence
when interpreting the word “cannot”. In the long term, only arbitrators or the courts will establish where
the border lies between “can be verified” and “cannot be verified”.
It would certainly be sensible for contractors to state in their tenders which parts of the Employer’s
Requirements could not be verified. Such a statement should at least lead to a discussion to establish
who is to be responsible for which information. It is important that these matters are agreed before the
Contract is signed if dispute is to be avoided later.
5.2 Contractor’s Documents
Most contractors would agree that an orderly flow of technical information is critical to the success of a
turnkey project. Yet, the Silver Book does not specifically address this issue but, under the terms of Sub-
Clause 5.2, actually invites a situation where the Employer, or his adviser, can seriously disrupt and
delay the design and construction process by repeatedly reviewing documents before giving permission
for construction to proceed.
Regrettably, this is not uncommon in turnkey projects, especially those where the Employer has
appointed a consulting engineer, “independent” from his own organisation. To delay the commencement
of construction
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
517
until reviews of the contractor’s documents are completed to the satisfaction of the Employer is, to put it
mildly, a recipe for disaster. The provisions for review of documents are overly prescriptive and give the
Employer too much freedom to interfere with and disrupt the Contractor’s design.
The Contractor has total responsibility for achieving the performance criteria and must therefore have
total freedom to achieve this objective free of the Employer’s interference. Contractor’s Documents
should be given to the Employer for information and the Contractor should at his own risk, be entitled to
proceed with construction. To avoid potential conflict, contractors should set out in their tender
document a clear and practical programme for the submission of all data, design and technical
information required by the Employer and this should include a specific provision for work to proceed at
all times, at the Contractor’s risk. The Contractor’s offer should be clarified accordingly and, to avoid
dispute later, any differences of opinion on the procedure to be adopted should be resolved prior to
contract signature.
5.3 Contractor’s Undertaking
The apparently simple undertaking required by this Sub-Clause hides a potentially dangerous
inconsistency with Sub-Clause 5.1 [General Design Obligations] . Manifestly, “the documents forming the
Contract”, include the Employer’s Requirements and, subject to certain exceptions, Sub-Clause 5.1
makes the Contractor responsible for their accuracy. Notwithstanding this, Sub-Clause 5.3 requires the
Contractor to design and execute the Works to comply with the Employer’s Requirements even if they
are defective or deficient. Furthermore, the Contractor has no power to vary the Works without an
instruction from the Employer who is not bound to issue one! This obvious ambiguity should be resolved
pre-tender.
5.4 Technical Standards and Regulations
This Sub-Clause should ensure that there is no open-ended obligation on the Contractor to amend the
Works at his cost in order to comply with the very latest design standards even if published after the
tender has been submitted. The Contractor should check that the particular conditions do not amend or
override this Sub-Clause. However, there is no mechanism in the Contract to resolve any ambiguity
between the Country’s technical standards and the Employer’s Requirements. Yet another matter for
pre-contract discussions.
7. PLANT, MATERIALS AND WORKMANSHIP
7.6 Remedial Work
A surprising omission is the lack of any express provision that permits the Employer to order a repair as
opposed to removal, replacement or
[2000
The International Construction Law Review
518
re-execution and the Contractor should have the right to carry out repairs to render the Plant or
Materials acceptable and in accordance with the Contract. Should the Employer insist on a replacement
in such situations then he should bear the additional cost.
8. COMMENCEMENT, DELAY AND
SUSPENSION
8.3 Programme
This Sub-Clause obliges the Contractor to give advance warning, is a new feature of the FIDIC Conditions
and requires that, “the Contractor shall promptly give notice of specific probable future events or
circumstances which may adversely affect or delay the execution of the Works”.
Contractors should consider whether, if such warning is given, it could have an impact on the starting
point for calculating the notice periods under Sub-Clause 20.1 [Contractor’s Claims]. It would be only fair
if this obligation to give warning is made reciprocal and applies to the Employer as well.
8.4 Extension of Time for Completion
The Contractor’s entitlement to an extention of Time for Completion is limited by comparison with the
Yellow Book. A right to extension exists if the delay is due to a Variation Order, to a delay caused by the
Employer or his other contractors or if a right to extension exists under any other Sub-Clause of these
conditions, i.e.:
2.1 Failure by the Employer to give access to and
possession of the Site.
(Cost plus reasonable profit added to Contract
Price).
4.24 Discovery of fossils etc.
(Cost but no profit added to Contract Price).
7.4 Delayed testing caused by Employer (see also
Sub-Clause 10.3)
(Cost plus reasonable profit added to Contract
Price).
8.5 Delays caused by Authorities.
(Extension of time only).
8.9 Suspension initiated by Employer (see also
Sub-Clause 16.1)
(Cost but no profit added to Contract Price).
10.3 Interference with testing by Employer (see
also Sub-Clause 7.4).
(Cost plus reasonable profit added to Contract
Price).
13 The time consequences of variations are dealt
with in Sub-Clause 8.4(a).
13.7 Changes in Legislation.
(Cost but no profit added to Contract Price).
16.1 Suspension initiated by Contractor (see also
Sub-Clause 8.9).
(Cost plus reasonable profit added to Contract
Price).
Pt. 4]
EIC Contractor’s Guide to the
Fidic Conditions
519
17.4 Employer’s Risks.
(Cost but no profit added to Contract Price).
19.4 Force Majeure.
(Cost but no profit added to Contract Price)
The variable remedies open to contractors should be carefully noted i.e. time only, time and cost and
time, cost and profit. Here again, FIDIC’s logic is difficult to follow.
The Red and Yellow Books contain, in addition to those mentioned in the Silver Book, the right to an
extension of time in the following cases:
← (i) exceptionally adverse climatic conditions;
← (ii) unforeseeable shortages in the availability of
personnel or goods caused by epidemic or
governmental actions; or
← (iii) in the event of adverse physical conditions.
None of the new FIDIC Contracts contain the sweep-up clause found in the fourth Edition of the Red
Book which refers to “other special circumstances”.
It could be argued that the Force Majeure provision in Sub-Clause 19.1 [Definition of Force Majeure]
gives the Contractor a right to an extension of time in the events listed above under (i)–(iii). Manifestly,
exceptionally adverse climatic conditions should be a Force Majeure event, as should shortage in
personnel and goods albeit depending on the reason for such shortage. The difference between an
undisputed contractual right to an extension of time and claiming Force Majeure is that additional
requirements must be satisfied for the latter such as the delaying event could not have been provided
against before entering into the Contract nor avoided nor overcome when it happens. The existence of a
right to an extension of time is not dependent on these requirements.
8.6 Rate of Progress
If, in the opinion of the Employer, the Contractor is working too slowly he can instruct acceleration
measures. This applies not only when the agreed Time for Completion is at risk but also where “progress
has fallen (or will fall) behind the current programme under Sub-Clause 8.3 [Programme] ”.
This type of clause is normally found in construction contracts where the Employer or his engineer has
produced the design and therefore has know-how sufficient to follow closely the actual construction of
the works and construction methods. In a turnkey contract, the Employer has less detailed knowledge.
With the increased responsibility for the Contractor under the Silver Book it should follow that the
Contractor has more freedom to execute the Works at his own pace as long as he complies with the Time
for Completion or other contractually agreed dates. It is perfectly feasible to sustain a position which
maintains that it is for the Contractor to decide whether acceleration measures should be undertaken or
not, particularly if the Employer’s
[2000
The International Construction Law Review
520
justification for acceleration is that although the Contractor has not yet fallen behind he “will fall” behind.
Contractors should have a strong incentive to adhere to the programme in any event, as their right to
payment is normally tied to meeting programme milestones tied to a payment plan.
8.7 Delay Damages
The maximum amount of Liquidated Damages shall be stated in the Particular Conditions. However,
damages in the event of delay can exceed this amount e.g. if the Contractor has to pay the Employers
costs under Sub-Clause 8.6 [Rate of Progress] or the Contract is terminated.
It is not unusual for contracts to state that the Employer may not terminate the Contract before the
aggregate of liquidated damages has reached the maximum amount. The Silver Book does not contain
such limitation but, on the other hand, in accordance with Sub-Clause 15.2 [Termination by Employer]
there have to be qualified reasons for termination due to delay.
If the Contract is terminated due to delay then the Contractor will have to pay all losses and damages
suffered by the Employer (See Sub-Clause 15.4 [Payment after Termination] ). However, such loss and
damage may not include loss of profit or other indirect damages and the maximum liability is limited
under Sub-Clause 17.6 [Limitation of Liability] .
9. TESTS ON COMPLETION
9.2 Delayed Tests
The references in this Sub-Clause to Sub-Clause 7.4 [Testing] (fifth paragraph) and Sub-Clause 10.3
[Interference with Tests on Completion] are confusing because these sub-clauses provide relief to the
Contractor for the circumstances set out in those sub-clauses and not specifically for those set out in
Sub-Clause 9.2 [Delayed Tests] .
9.4 Failure to Pass Tests on Completion
If the Works fail to pass repeated Tests on Completion and the failure “deprives the Employer of
substantially the whole benefit of the Works or Section…” then the Employer has the right to reject the
Works, terminate the Contract, recover all sums paid for the Works, plus financing costs, costs for
dismantling the Works and clearing the Site.
It is obvious that the Contractor will suffer catastrophic financial consequences if the contract price has
to be repaid together with financing costs and the costs of dismantling the Works and reinstating the
Site.
It is conceivable that there could be contracts where such a severe remedy
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
521
is justified, where, for example the Contractor has developed a unique know-how for a complete
production process and it fails to perform as guaranteed and no other contractor is capable of putting it
into satisfactory working order. In such circumstances, it would be unreasonable to expect the Employer
to bear the consequences of the Contractor’s failure.
On the other hand, current practice in the event of termination is that the Contractor is entitled to
payment for the value of the Works completed at the date of termination. Thereafter, it is up to the
Employer to decide whether or not to complete the Works with another contractor. In both situations the
Contractor must pay the Employer’s additional costs. In circumstances where the Works contain
technology which is “in the public domain”, then the same principle should apply. However, it should be
recognised that in such a case design responsibility for the whole of the Works could rest with the new
Contractor and contractors faced with such a prospect should take due regard of the risks involved. It is
important to understand the implications of this requirement, as the Contractor could be in a very serous
situation in the event that Tests on Completion are not successful.
It is important, in relation to this Sub-Clause to consider the limitation of liability under Sub-Clause 17.6
[Limitation of Liability] .
10. EMPLOYER’S TAKING OVER
10.2 Taking Over of Parts of the Works
According to this Sub-Clause, “Parts of the Works…shall not be taken over or used by the Employer,
except…as may be agreed by the parties”. It fails to address the situation where the Employer uses the
Works or part of the Works without the agreement of the Contractor. Various difficulties and risks could
arise in such a situation none the least of which would be damage to the Works, which may not be
covered by insurance. The Yellow Book offers a way out in Sub-Clause 10.2 [Taking Over of Parts of the
Works] which states that “…if the Employer does use any part of the Works before the Taking-Over
Certificate is issued: (a) the part which is used shall be deemed to have been taken over as from the
date on which it is used…”
11. DEFECTS LIABILITY
11.2 Cost of Remedying Defects
The Contractor shall at his own cost remedy defects caused by the design of the Works.
[2000
The International Construction Law Review
522
Sub-Clauses 4.1 [Contractor’s General Obligations] and 5.1 [General Design Obligations] make it
absolutely clear that the Contractor is fully responsible for the design of the Works, including the
correctness of the information on which he bases the design subject only to the important exceptions in
Sub-Clause 5.1. As written this means that the Contractor takes responsibility for any design supplied by
the Employer.
No exception is made for the situation where part of the design is supplied by the Employer or the
defect in the design is due to incorrect information or design criteria for which the Employer remains
responsible in accordance with Sub-Clause 5.1. It is clearly a flaw in the Silver Book that such important
exceptions are not expressly referred to. This is an unsatisfactory state of affairs and the Contractor
should not be left to rely on a court or similar to establish that a reasonable interpretation is that a
responsibility allocated to the Employer under Sub-Clause 5.1 should also have the effect that the
Employer takes the risk and cost for remedying defects caused thereby. The Employer’s responsibility
under Sub-Clause 11.2 (a) should be entirely consistent with that set out in Sub-Clause 5.1.
It is therefore recommended that the Parties clarify this matter in the Particular Conditions. This will be
particularly important where the Employer has responsibility for supplying a wide range of information or
for important parts of the design. It is interesting to note that Sub-Clause 11.2 (a) in the Yellow Book has
specific wording to cover just this situation.
It should also be noted that a similar ambiguity exists and is highlighted under Sub-Clause 17.3
[Employer’s Risks] and underlines the importance of getting the exclusions under Sub-Clause 5.1
absolutely correct.
11.4 Failure to Remedy Defects
If the Contractor fails to remedy a defect and the defect or damage “deprives the Employer of
substantially the whole benefit of the Works or any major part of the Works…” then the Employer is
entitled to recover all sums paid for the Works, plus financing costs, costs for dismantling the Works and
clearing the Site. These are indeed punitive sanctions and contractors must carefully consider whether
the risks they carry under the Silver Book are commensurate with the likely reward for performing the
Contract.
This Sub-Clause is similar in effect to Sub-Clause 9.4 [Failure to Pass Tests on Completion] where more
comprehensive comments have been made.
13. VARIATIONS AND ADJUSTMENTS
13.1 Right to Vary
The Employer may initiate Variations prior to issuing the Taking Over Certificate for the Works, and the
Contractor has only limited grounds for refusing to undertake the instructed Variation, which are:
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
523
“(i) the Contractor cannot readily obtain the Goods required for the Variation, or (ii) it will reduce the
safety or suitability of the Works, or (iii) it will have an adverse impact on the achievement of the
Performance Guarantees.”
Notwithstanding any objections raised by the Contractor, the Employer may still confirm his instruction.
The Employer’s right to unilaterally issue Variations does not fit well within the concept of an EPC
Turnkey Contract and the grounds that permit the Contractor to object to a Variation are too restrictive.
It should be at the Contractor’s sole discretion to refuse or accept a Variation if he believes that the price
offered is wholly inadequate, the Variation will have an adverse effect on the undertaking of any of his
obligations under the Contract or, following a request by the Contractor under Sub-Clause 2.4
[Employer’s Financial Arrangements], the Employer is unable to provide evidence that satisfactory
financial arrangements are in place and being maintained to pay for the addition to the Contract Price
resulting from the Variation Order.
Should the Employer instruct the Variation despite the Contractor giving notice that he will not consider
himself bound by the Variation, then the only remedy open to the Contractor is to refer the matter to the
Dispute Adjudication Board.
13.2 Value Engineering
This Sub-Clause provides that the Contractor may, but is under no obligation to, make proposals to
amend the Works that will benefit the Employer.
Unreasonably, what is not provided is a process whereby the two Parties share the benefits of any
value engineering undertaken by the Contractor.
The Contractor may therefore wish to consider how he should be reimbursed for his additional efforts,
or agree a method of sharing the enhanced benefits to be enjoyed by the Employer.
13.3 Variation Procedure
This Sub-Clause represents a dramatic departure from normally accepted practices for dealing with the
valuation of variations and Contractors would be well advised to agree the price of all variations before
starting the additional work.
The procedure outlined places the onus on the Contractor to prepare the design and price and to re-
programme the Works to accommodate the proposed variation. The Employer may then approve,
disapprove or comment upon the Contractor’s submission. The procedure will involve the Contractor in a
great deal of additional effort and expenditure that may not be recoverable if the variation is not
approved or is substantially amended by the Employer. Accordingly, the Employer should be made aware
at the time of Tender that the Contractor will expect to recover such additional expenditure.
[2000
The International Construction Law Review
524
If the price of a variation is not agreed, then it shall be unilaterally determined by the Employer under
Sub-Clause 3.5 [Determinations], and ultimately, in the event of disagreement, by the Disputes
Adjudication Board or Arbitrator. “Reasonable” profit will be allowed but this does not necessarily mean
the same profit margin as is built into other contract rates or in prices for comparable works or that
comparable rates will apply.
13.5 Provisional Sums
It is not clear whether the Contractor is liable for any design associated with Provisional Sums. In the
absence of any express provision it may well be that the Contractor is held to be responsible under Sub-
Clause 5.1 [General Design Obligations] . Again, an issue to be sorted pre-contract. Attention is drawn to
the Guidance Notes which indicate that Provisional Sums should only be used for minor supplies.
13.7 Adjustments for Changes in Legislation
This Sub-Clause contains provisions in respect of the recovery of additional Costs associated with
changes in legislation.
Contractors should note however that the recovery of losses only applies to changes in legislation in
the country in which the Site of the Permanent Works is located.
14. CONTRACT PRICE AND PAYMENT
14.2 Advance Payment
Provision is made for the Contractor to receive an advance payment as an interest-free loan for his
mobilisation and design provided that the amount of the advance is stated in the particular conditions.
If an advance is specified in the Particular Conditions then its payment will only be made after receipt
by the Employer of “(i) a Statement (under Sub-Clause 14.3 [Application for Interim Payments], (ii) the
Performance Security in accordance with Sub-Clause 4.2 [Performance Security], and (iii) a guarantee in
amounts and currencies equal to the advance payment”. The advance payment may be paid in
instalments. However the number and timing must be stated in the particular conditions and the
Contractor will require the advance payment guarantee to recognise this.
Within Sub-Clause 14.7 [Timing of Payments], paragraph (a) states that the first instalment of the
advance payment shall be paid within 42 days after the date on which the Contract Agreement came
into full force and effect, or within 21 days after the Employer receives the documents in accordance
with
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
525
Sub-Clause 4.2 [Performance Security] and Sub-Clause 14.2, whichever is later. Contractors may
consider these periods too long before receipt of the advance and could indeed require payment of the
advance as a condition precedent to the commencement of work on Site.
14.3 Application for Interim Payments
To initiate the payment process the Contractor is to submit a Statement at the end of the period of
payment which period is to be stated in the Contract. If no period is stated, the submission is to be at the
end of each month.
To be valid, the Statement must include items detailed in Sub-Clauses 14.3 (a) to (f). It must also
include the progress reports which are defined within Sub-Clause 4.21 [Progress Reports], an onerous
precondition for the receipt of payment.
Sub-Clause (a) requires that the contract value of the Works executed be estimated unless defined in
accordance with Sub-Clause 14.4 [Schedule of Payments] . It does not detail how the estimate is to be
prepared in a manner that will be acceptable to the Employer. Accordingly, a suitable procedure should
be agreed with the Employer. The Statement should also contain the various additions and deductions to
be made to the contract value of the Works.
Sub-Clause 14.5 [Plant and materials intended for the Works] below, makes provision for payment to
be made in respect of certain plant and materials which are in the country in which the Works are
located but which are not yet on Site. However contractors should be aware that there are no provisions
to make payments in respect of any plant and materials which have not been included in the entitlement
under Sub-Clause 14.5, or for those which are either stored outside the Country of the Works or which
have been delivered to the Site but are not incorporated in the Permanent Works. It is recommended
that amended payment procedures be negotiated prior to Contract signature.
The amount of any Retention Money is to be stated in the particular conditions and the Contractor may
wish to include provisions that permit him to provide a retention guarantee in lieu of the Employer
retaining cash.
14.4 Schedule of Payments
The Contract may provide for payment to the Contractor based upon a Schedule of Payments and if so,
“the instalments quoted in the Schedule of Payments shall be the estimated contract values for the
purposes of sub-paragraph (a) of Sub-Clause 14.3 [Application for Interim Payments] ”.
If the instalments are not defined by reference to actual progress achieved then the Employer is
entitled to revise any payment instalment by making a determination under Sub-Clause 3.5
[Determinations] which will take into account any delay in progress. Equally, the Contractor could
request that,
[2000
The International Construction Law Review
526
when the Works are ahead of programme he is entitled to an appropriate increase in the scheduled
payment.
If it is intended that the schedule of payments be based on the achievement of specific milestone
events then this should be expressly stated. Otherwise, payments would be based on the actual value of
work done.
14.5 Plant and Materials intended for the
Works
This Sub-Clause provides for payment in respect of plant and materials provided they are in the Country
in which the works are located. To obtain payment, the Contractor is to mark the relevant plant and
material as being the property of the Employer or provide suitable insurance together with a guarantee
equal to the value of the payment to be made. (See also comment under 14.3 [Application for interim
Payments] above.)
14.6 Interim Payments
The provisions for withholding payment in this Sub-Clause are potentially harsh. For instance, if the
Contractor, in the Employer’s view, is allegedly proceeding without “due expedition”, in apparent breach
of Sub-Clause 8.1 [Commencement of Works], the Employer could maintain that the whole of the value
of the delayed works should be withheld. A most unsatisfactory and unacceptable situation.
14.7 Timing of Payments
This Sub-Clause details the periods within which payment is to be made by the Employer in respect of
the advance, interim and final payments. By comparison with well-established norms, the periods
proposed are excessive and contractors may wish to suggest more reasonable intervals.
14.9 Payment of Retention Money
The amount of any Retention Money will be defined within the particular conditions and this Sub-Clause
provides for the first half of the Retention Money to be released after the Taking-Over Certificate has
been issued provided that the Works have passed all specified tests, including any tests after
completion.
It is important to fix a date for any tests to be carried out after completion to avoid any delay to the
release of the moiety of the retention.
The outstanding balance of the Retention Money is to be paid “promptly” after expiry of the latest
expiry date of the Defects Notification Period (s). Sub-Clause 1.1.3.7 provides that if no such period is
stated in the Particular Conditions then the Defects Notification Period shall be 12 months and under
Sub-Clause 11.3 [Extension of Defects Notification Period] the period
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
527
could be extended by a maximum of two years. The release of the final tranche of Retention Money
could therefore be up to three years after completion. The full release of Retention Money may be further
delayed if any work remains to be completed, as the Employer may withhold the estimated cost of any
outstanding works.
The above restrictions, together with differing interpretations of the meaning of the word “promptly”
could result in a protracted period of delay before the Contractor is able to recover his Retention Money.
Pressure on contractor’s cash flow could be avoided if the Employer is prepared to accept a bank
guarantee in lieu of retention.
14.10 Statement at Completion
The Contractor is required to submit a statement at Completion with supporting documents within 84
days after receiving the Taking-Over Certificate following which the Employer may make an interim
payment to the Contractor. This statement means that all of the Contractor’s claims must be submitted,
along with all other documentation required or reasonably implied as required under the Contract. Sub-
Clause 14.10(b) and (c) refers. Failure to include claims would result in them being barred under Sub-
Clause 14.14 (b) [Cessation of Employer’s Liability] . Contractors should also have regard to the
extremely tight time limits laid down in Clause 20 [Claims, Disputes and Arbitration] for the submission
of detailed particulars.
14.12 Discharge
A written discharge is to be submitted by the Contractor with the final statement and should be worded
to provide for such discharge to become effective when the final payment has been received and all
bonds and guarantees returned.
14.14. Cessation of Employer’s Liability
This is a very important Sub-Clause in respect of any Contractor’s claims. If the Contractor fails to notify
them in the Final Statement and the Statement at completion required by Sub-Clause 14.10 [Statement
on Completion], then, with minor exceptions, they will be barred. The notifications under this Sub-Clause
are in addition to those required under Sub-Clause 20.1 [Contractor’s Claims] .
15. TERMINATION BY EMPLOYER
15.1 Notice to Correct
This Sub-Clause gives the Employer, in addition to the right to give instructions under Sub-Clause 3.4
[Instructions], an unlimited right to
[2000
The International Construction Law Review
528
require the Contractor by notice to make good any alleged failure to carry out any obligation under the
Contract. If the Contractor fails to comply with such notice, the Employer has the right to terminate the
Contract under Sub-Clause 15.2 [Termination by Employer] .
In circumstances where the Employer has given the Contractor a very brief and vague description of
the scope of work and the Contractor is responsible for the design and tied into a lump sum price, such a
provision would be very dangerous for the Contractor. In situations where the Parties have made
different interpretations of the Employer’s Requirements, then this provision enables the Employer to
impose his view on the Contractor by threatening termination of the contract if the Contractor will not
comply. Such a right should only apply in the event of material breach of contract.
15.2 Termination by Employer
As always the Employer has the right to terminate the Contract in certain circumstances. These
circumstances include breach by, and insolvency of, the Contractor as well as corruption.
Allowing the Employer the right to terminate the Contract in the event of corruption is a sound
principle. However, the definition of corruption as defined by this Sub-Clause is too wide. It extends to
the Contractor’s sub-contractors (over whom the Contractor does not have total control) and it covers
any act, however small, carried out by an individual. As a consequence, determination of the Contract for
the act of corruption under a sub-contract is too severe a remedy. The obligation should be limited to an
obligation on the Contractor to terminate the sub-contract and should not give the Employer the right to
terminate the Contract.
Sub-Clause 15.2 (a) could be applied to quite trivial faults since it relates to compliance with a Sub-
Clause 15.1 [Notice to Correct] notice which covers “any” failure by the Contractor to carry out “any
obligation”. Such a clause could be used oppressively by an employer.
This Sub-Clause should also be considered in the light of the comments on Sub-Clause 8.7 [Delay
Damages] above regarding damages payable by the Contractor in the event of delay.
16. SUSPENSION AND TERMINATION BY
CONTRACTOR
16.2 Termination by Contractor
The right of the Contractor to terminate the Contract is subject to notice periods that could extend to 84
days. In the case of failure to receive reasonable evidence with regard to the Employer’s financial
arrangements
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
529
(Sub-Clause 2.4 [Employer’s Financial Arrangement]) or failure to pay the Contractor amounts due (Sub-
Clause 14.7) the Contractor must allow 42 days to elapse to demonstrate non-payment. Thereafter he
must give a further 14 days notice before he may terminate the Contract.
These time limits are too long. The Contractor must continue working even if the Employer has failed to
pay. It would be more equitable if (similar to the other grounds for termination in Sub-Clause 16.2) the
Contractor were required to give 14 days’ notice, particularly in the case of suspension of work by the
Contractor.
The situation will be more complex where project finance is in place and a lender has step-in rights.
However, the same basic principles should apply.
17. RISK AND RESPONSIBILITY
17.1 Indemnities
This Sub-Clause is unnecessarily broadly drafted. It imposes the risk on the Contractor of injury etc and
damage to property (other than the Works) arising “in the course of the design or execution of the Works
even if not caused by the Works. This is a ridiculously wide risk for the Contractor to assume which, in its
defined terms, may not be insurable.
The last paragraph contains a reference to Sub-Clause 18.3(d)(iii) [Insurance against injury to Persons
and Damage to Property] according to which the Employer is not obliged to indemnify the Contractor to
the extent that insurance cover is available at commercially reasonable terms. Since it is arguable
whether or not insurance cover was available at commercially reasonable terms, it may be advisable
when negotiating a contract to exclude this exception in Sub-Clause 18.3 (d) (iii).
17.3 Employer’s Risks
The catalogue of Employer’s Risks does not include loss or damage due to the occupation of the Works,
or any Section thereof, by the Employer because Sub-Clause 10.2 [Taking Over of Parts of the Works]
does not allow the use of any parts of the Works, except if stated in the Contract or as agreed by both
Parties. Where these latter exceptions occur, the Contractor should either ensure that a Taking Over
Certificate is issued in respect of any such parts or the Yellow Book solution identified under the
comments previously made in relation to Sub-Clause 10.2 [Taking Over of Parts of the Works] is followed.
The Employer’s Risks does not contain the Employer’s Requirements, data and information for which
the Employer is responsible according to Sub-Clause 5.1 [General Design Obligations]. If any loss or
damage to the Works is caused by these responsibilities then the Employer must remain liable.
The operation of exceptional forces of nature has not been included as an
[2000
The International Construction Law Review
530
Employer’s Risk because it is intended that the Contractor bears the full risk. Omitting the operation of
(exceptional) forces of nature from the list of Employer’s Risks is very burdensome. Generally speaking,
their specific occurrence is unforeseeable even by an experienced Contractor, and an experienced
Contractor can not be expected to take adequate precautions against them.
In view of the Contractor’s inability to foresee such risks the Contractor cannot make any realistic risk
assessment. Accordingly, any estimate in respect of such events can only be speculative.
If the Contractor does not want to assume such risks the corresponding provision of the Yellow Book
Sub-Clauses (f), (g) and (h) should be adopted as a more appropriate risk allocation.
17.4 Consequences of Employer’s risks
If, and to the extent that, the Employer requires the Contractor to rectify the loss or damage to the
Works, Goods or Contractor’s Documents resulting from any of the Employer’s Risks, the Contractor is
entitled to time extension and payment of the Cost incurred, but not to any uplift for profit, for rectifying
the loss or damage.
The Contractor’s rights under this Sub-Clause are subject to his compliance with Sub-Clause 20.1
[Contractor’s Claims] .
17.6 Limitation of Liability
This Sub-Clause provides that there is no liability on either Party for loss of use of any Works, loss of
profit, loss of any contract or for any indirect or consequential loss or damage.
It should be noted that it is only in certain cases of breach of contract by the Employer that the Silver
Book entitles the Contractor to compensation for loss of profit (see Sub-Clauses 2.1 [Right of Access to
Site], 7.4 [Testing], 10.3 [Interference with Tests on Completion] ).
This is inequitable and the Contractor should always be entitled to compensation for loss of profit and
other indirect or consequential damages, in the event of a breach of contract by the Employer,
irrespective of whether or not there is a specific Sub-Clause in the Silver Book.
By excluding Sub-Clause 17.1 [Indemnities] from the limitation of liability both the Contractor and the
Employer are fully liable for the events outlined in Sub-Clause 17.1.
19. FORCE MAJEURE
19.1 Definition of Force Majeure
This Sub-Clause provides a definition of Force Majeure and provides a non-exhaustive catalogue of Force
Majeure events in the second paragraph
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
531
that includes natural catastrophes such as earthquakes, hurricane, typhoon or volcanic activity.
19.4 Consequences of Force Majeure
In the event that the Contractor is prevented from performing any of his obligations under the Contract
due to an event of Force Majeure, the Contractor can claim for time extension and the Cost incurred. The
claims for Cost are limited to the events listed in Sub-Clause 19.1 (i) to (iv) [Definition of Force Majeure] .
Such limitation is difficult to understand given the fact that the catalogue of Force Majeure events is not
exhaustive.
19.6 Optional Termination, Payment and
Release
In case of termination due to Force Majeure, the Contractor is entitled to be paid for the Works executed,
the Cost of Plant and Materials ordered, any other Cost incurred in the expectation of completing the
Works, the Cost of removal of Temporary Works and Contractor’s Equipment and the Cost of repatriation
of staff and labour. If the Contractor wants to receive profit on these Costs, a corresponding provision
would have to be included in the Contract.
20. CLAIMS, DISPUTES AND ARBITRATION
20.1 Contractor’s Claims
This Sub-Clause details the procedure that the Contractor must follow when he considers himself entitled
to an extension of Time for Completion and/or additional payment under any of the Clauses or otherwise
in connection with the Contract.
The Contractor is required to give notice of his claim as soon as practicable and not later than 28 days
after becoming aware, or when he should have become aware, of the event or circumstance giving rise
to the claim. Failure to comply with this notice provision would result in the Contractor forfeiting his right
to an extension of the Time for Completion and to additional payment and the Employer is then
discharged from his liability in connection with the event.
The penalty for failure to comply with a purely technical requirement to give notice of a claim is unduly
harsh. This is the first time that a FIDIC contract has removed the fundamental right of the Contractor to
make a claim merely as a result of a failure to comply with a fixed period of time to submit the required
notice. In certain circumstances the Contractor may
[2000
The International Construction Law Review
532
prejudice his entitlement by failing to comply strictly with a notice provision but he should certainly not
forfeit his rights altogether and neither should the Employer be discharged from any and all liability in
connection with an event. It is ironic that this provision would also apply when the event or circumstance
giving rise to the claim is caused by the Employer in the first case e.g. refer to Sub-Clause 8.9
[Consequences of Suspension] .
A comparison of the notice provisions under Sub-Clause 20.1 with the notice provisions under Sub-
Clause 2.5 [Employer’s Claims] where the Employer is required to give notice as soon as practicable after
becoming aware of the event or circumstance. This demonstrates an unfair imbalance between the
position of the Employer and that of the Contractor without any reason being offered for such imbalance.
In addition to the first 28 day notice period the Contractor is also subject to a 42 day period by which
he has to send to the Employer a fully detailed claim with full supporting particulars. (See also the
provisions for continuing claims.) Due to the complex nature of the Works in an EPC contract this could
prove to be extremely difficult and inevitably, the task of compiling and interpreting the relevant facts to
support and justify the claim will be a time consuming and long drawn out process. Such provisions could
be lead to intensive disputes and costly arbitration.
The sixth paragraph of this Sub-Clause requires the Employer to respond to a Contractor’s claim giving
his approval or disapproval within a fixed period of time whereas the eighth paragraph requires the
Employer to proceed in accordance wtih Sub-Clause 3.5 [Determinations] to agree or determine any
extension of Time for Completion and/or any additional payment. It is not clear why these two separate
procedures are required. However, it should be borne in mind that under Sub-Clause 3.5 there is no time
limit within which the Employer has to make a determination.
Contractors should read the Comments made under this Sub-Clause in conjunction with those under
Sub-Clauses 14.10 [Statement at Completion] and 14.14 [Cessation of Employer’s Liability] all of which
underline the importance of submitting all required notices in time to ensure that their rights are
protected and maintained.
20.2 Appointment of the Dispute
Adjudication Board
This Sub-Clause provides for the establishment of the Dispute Adjudication Board (DAB) comprising
either one or three members to be appointed by the Parties. The DAB is to be appointed by the date 28
days after a Party has given notice of its intention to refer a dispute to a DAB. The appointment of the
DAB expires after it has given a decision on the referred dispute, provided no other disputes have been
referred to it in the meantime. When the appointment expires a new DAB will have to be appointed to
deal with the next dispute.
It is very likely that adjudication by a DAB in large and complex EPC
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
533
Projects would be much more effective under a standing body rather than one convened on an ad hoc
basis. It would be particularly beneficial for the DAB to become conversant with the Contract and the
Works at an early stage and to familiarise itself with the progress of the Works on a regular basis.
Undoubtedly this will result in speedy and well informed judgments and consequently the procedures
and draft agreements set out in the Red Book are to be preferred for such projects. Under these rules the
DAB is appointed at the start of the Contract and remains in existence for the duration of the Contract
unless agreed otherwise by the Parties.
20.4 Obtaining Dispute Adjudication Board’s
Decision
It should be noted that, if the DAB has given its decision as required by this Sub-Clause and if neither
Party has given notice of dissatisfaction within 28 days after having received the DAB’s decision, the
decision becomes final and binding on both Parties. Even in the case of dissatisfaction by either Party it
would appear that the intention is that decisions of the DAB are binding on both Parties “unless and until
it shall be revised in an amicable settlement or an arbitral award”.
The Contractor is required to “continue to proceed with the Works” but the obligation of the Employer,
in so far as payment is concerned, is merely to comply with the normal process for Interim Payments.
There is no provision for any sanction against the Employer in the case of non-payment. Manifestly, any
payments due as a result of a DAB decision should be considered as Payments due under Clause 14
[Contract Price and Payment] but to be made with immediate effect. Any failure to pay would then give
the Contractor the right to Suspend the Works under Sub-Clause 16.1 [Contractor’s Entitlement to
Suspend Work], an appropriate sanction in such circumstances.
EXECUTIVE SUMMARY
In their Introductory Note to the Silver Book, FIDIC describe the benefits to the Employer of turnkey
project execution and state that passing responsibility for designing and constructing the works to the
Contractor will relieve the Employer of responsibility for close supervision of the design and construction
processes. FIDIC also maintain that there will be an increased certainty of the final price and fewer
disputes if the Contractor assumes responsibility for the wide range of risks set out in the Silver Book.
Regrettably, EIC cannot endorse this view and believe that the Silver Book falls a long way of short of
meeting the objectives which FIDIC set down for it.
Contractors accept that, by choosing a turnkey approach, Employers can reasonably expect the
Contract to transfer as much risk as practicable to the Contractor, offer a high degree of certainty on the
final price, facilitate the speedy completion of the Works and, in the event of dispute, provide for
[2000
The International Construction Law Review
534
their rapid resolution. Contractors on their part, are quite prepared to contract on a turnkey basis and
accept additional risk, provided that risks can be identified, priced and managed, design and
construction of the works is free of disruptive interference and disputes are resolved quickly and
equitably.
In a number of important respects, the Silver Book does not adequately satisfy the respective
aspirations of Employer and Contractor and its failure to do so is best illustrated by consideration of
those matters that most commonly give rise to disputes in turnkey projects;
← inadequate definition of the scope of work;
← disruption of the design and construction process,
← inequitable allocation of risk and
← claims and dispute resolution.
Definition of the scope of the works
It is stating the obvious to say that an offer to work on a fixed lump sum basis can only be made if the
Works are sufficiently well defined. This requires an adequate preliminary design, comprehensive
technical specifications and clear and unambiguous performance criteria. The Contractor will carry out
the majority of these tasks in a turnkey project. However, it is essential that the Employer fully
understands and accepts what is on offer and the required clarity of understanding will only be achieved
through detailed and lengthy negotiation between employer and contractor. Manifestly, this cannot
possibly be achieved during the tender period with all bidders and, until such time as agreement has
been reached, any offer should remain conditional.
The obligations placed upon contractors by the Silver Book are onerous, whereas the Employer’s most
significant responsibility is limited to providing a definition of the intended purposes of the Works and
setting criteria for testing and performance. The Employer is not even responsible for the accuracy of the
“Employer’s Requirements”! The Contractor is required to make all necessary investigations, verify
relevant information and carry out design in sufficient detail to price the Works. Such demands,
combined with the allocation of risks to the Contractor which may be impossible to predict or cost
accurately, may make it impossible for the Contractor to establish precisely the full scope and extent of
his liability. In particular, it will be practically impossible for the Contractor to fully comply with all of
these obligations during the tender period especially the full verification of the Employer’s Requirements
and the development of a fully detailed design. Contractors must decide whether it will be feasible to
clarify all of these matters following tender submission and prior to the signature of a binding contract. In
most circumstances, contractors will be well advised to submit an appropriately conditioned offer which
makes it clear that a full and binding offer will only be made (to the extent that this is practically
possible) following extensive and conclusive negotiations.
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
535
Arguably, the submission of a qualified bid might lead to disqualification of the Contractor’s tender
despite FIDIC’s recommendation in their Introductory Note that it should be used as a starting point for
negotiations. Clarification of the Employer’s position on qualified tenders should be established before
any decision is made to submit a bid.
In many instances, clauses in the Silver Book are in direct conflict with the obligations placed on
Contractors. Not only is the obligation to define the scope of the Works loosely defined, it is also subject
to reviews by the Employer who has the same power to interfere through instructions, approvals,
variations and determinations as the engineer in a conventional construct only contract. Paradoxically,
should any Employer exercise his right to interfere in this way it will inevitably undermine FIDIC’s primary
objective, certainty of the final price.
Disruption of the design and construction
process
Only the Employer can make the choice of a turnkey contract and should only do so if he has confidence
in the competence, resources and experience of his potential Contractor. To achieve this level of
confidence demands a serious and comprehensive pre-qualification and tendering process aimed at
selecting the best contractor for the project. Thereafter, there can be no justification for detailed
supervision and interference and clearly specified monitoring at defined milestone events should be
perfectly adequate. For a Contractor to enter into a contract of fixed time and price his obligations must
also be fixed and once the contract is signed, the Employer should not be able to unilaterally impose his
will on the design and construction process.
The extent to which the Employer might disrupt the design and construction process is the most
fundamental area of concern for contractors working on turnkey projects. FIDIC would appear to accept
this important principle by stating in the Introductory Note to the Silver Book,
“the Employer should exercise limited control over and should in general not interfere with the
Contractor’s work.”
Consequently, in the event that the Employer orders the Contractor to design or construct all or part of
the works in a particular way, then the Employer must accept full responsibility for the consequences of
his actions. Should the Contractor be responsible for the achievement of any performance criteria then
the Contractor must have the right to refuse an instruction, which, in his opinion, is likely to have an
adverse effect on the achievement of the performance criteria.
Allocation of risks and responsibilities
EIC accept that Contractors will bear considerably more risk under a turnkey contract compared to that
of a conventional construct only contract but EIC
[2000
The International Construction Law Review
536
cannot accept the extent to which Silver Book goes in attempting to make the Contractor responsible for
almost every eventuality however unforeseeable. EIC believe that the Employer cannot pass liability for
all risks to the Contractor and any contract signed under the Silver Book should clearly define where
liability lies to ensure that contractors are in a position to accurately identify, price and manage those
risks which are to be their responsibility.
The Contractor must be especially alert to uninsurable risks, risks that are completely out with his
control or risks that are likely to increase as a consequence of the actions of the Employer or third
parties. Contractors should also be wary of those clauses, which, as drafted, could leave the Contractor
at the mercy of an unscrupulous Employer.
However, it is probable that the greatest challenge and consequently the greatest risk will be the
difficulty of checking and confirming the accuracy or adequacy of the information and data supplied by
the Employer. Contractors who accept contracts under the Silver Book are responsible for the accuracy
and correctness of all information and data regardless of its source. Contractors are advised to take
particular care with clauses dealing with the definition of fitness for purpose and liability for
unforeseeable difficulties and adverse physical conditions.
Claims and disputes management
Despite FIDIC’s claims to the contrary, the Silver Book is likely to give rise to disputes between the
Parties unless several of its provisions are modified during negotiation. In particular, the time contraints
placed on the Contractor to submit a notice of an intention to claim are impractical and the sanctions for
non-compliance are unreasonably punitive. By contrast the Employer is neither required to observe
similar time limits nor suffer any sanction provided he gives notice as soon as practicable. This is yet
another example of an inequitable contract.
The Contractor should only be required to advise the Employer of an intention to claim as soon as
reasonably practicable and there should be no time deadline after which the contractor would lose his
rights. This should also apply to the procedure to be followed where details of the claim are to be
submitted. Events may have a continuing effect and it is not always possible to establish the final effect
resulting from an event until later.
A comparison of FIDIC’s Conditions of
Contract for Plant and Design-Build (the
Yellow Book) and EPC Turnkey Projects (the
Silver Book)
If further evidence is required to demonstrate EIC’s concerns regarding the Silver Book the following
comparison of these two books highlights how far FIDIC have departed from their normal fair-handed and
equitable distribution of risk and responsibility. Consequently, the Yellow Book provides a useful source
of reference when drafting an alternative allocation
Pt. 4]
EIC Contractor’s Guide to the Fidic Conditions
537
of risk and design responsibility. It is also extremely important to remember and to point out to clients at
every opportunity that FIDIC is well aware of the fact that the Silver Book is highly unsuitable for certain
types of turnkey projects. FIDIC makes this clear in the Introductory Note to the First Edition, by stating
that it is not suitable in the following circumstances and that the Yellow Book should be used:
← If there is insufficient time or information for
tenderers to scrutinise and check the Employer’s
Requirements or to carry out the necessary
designs, risk assessment studies and estimating
(taking particular account of Sub-Clauses 4.12
[Unforeseeable Difficulties] and 5.1 [General
Design Obligations]) .
← If construction will involve substantial work
underground or work in other areas which
tenderers cannot inspect.
← If the Employer intends to supervise closely or
control the Contractor’s work, or to review most
of the construction drawings.
← If the amount of each interim payment is to be
determined by an official or other intermediary.
EIC consider that the following circumstances could be added to the list;
← Where part of the design is made by the
Employer and is binding on the Contractor—see
also comments on Sub-Clause 5.1 [General
Design Obligations] in this Guide.
← In competitive bidding without negotiations.
As a final word the principal differences between the Yellow and Silver Books are worth highlighting:
The Yellow Book The Silver Book Responsibility for the design provided by the Employer and for providing specifications rests with the Employer.
Responsibility for all designs and specifications rests with the Contractor, including those provided by the Employer.
Responsibility for the correctness of information provided by the Employer remains with the Employer.
The Contractor is responsible for the correctness of information provided by the Employer.
The risk for unforeseen physical conditions is borne by the Employer.
The risk for all unforeseen difficulties, including unforeseen physical conditions is borne by the
The Yellow Book The Silver Book Contractor.
It should be noted however, that the above only describes the overall responsibilities of the parties and
that important exceptions apply in each particular case.
[2000
The International Construction Law Review
538
Comments on a number of individual clauses follow and deal with the matters referred to above in
greater detail. Where considered appropriate comparative references are made to the Yellow Book.
ACKNOWLEDGEMENTS
EIC would like to thank the FIDIC Contracts Committee for the time they devoted to explaining the
philosophy behind the publication of the Silver Book and for listening patiently to our arguments. We
would also like to thank the Organisme de Liaison Industries Métalliques Européennes (ORGALIME) and
Mr Robert Akenhead QC for the important contributions they made in reviewing the final draft of this
Guide and recommending improvements.
EIC would also like to express its appreciation of the work carried out by members of the Conditions of Contract Working Group who produced this Guide: Lidia Amadio, Astaldi; Louise Axton-Wilkins, Costain; Eric Eggink, Ballast Nedam; John Fenwick, Amec; Dr Joachim Goedel, Hochtief; Frank Kennedy (Chairman), Carillion; Andrew Lee, Balfour Beatty; Agne Sandberg, Skanska; Charles Shankland, Eiffage. Thanks also to the Working Group’s secretary Frank Kehlenbach and Martin Carrey