El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May...

Date post: 01-Jan-2016
Category:
Upload: dwight-adams
View: 217 times
Download: 0 times
Share this document with a friend
Popular Tags:
13
El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer Middle Rio Grande Conservancy District
Transcript
Page 1: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

El Vado Dam Corrective Action Study

New Mexico Watershed and Dam Owners Coalition

Conference – May 12, 2015Presented by

Mike A. Hamman, Chief EngineerMiddle Rio Grande Conservancy District

Page 2: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

El Vado DamQuarter Inch Faceplate

Page 3: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Early Construction Photo

Page 4: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

El Vado Dam Spill

Page 5: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Intake Structure for SJC Project

Page 6: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

View of Expansion Joints and Patches looking up to the Crest

Page 7: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Expansion Joint Separation

Page 8: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Failed Expansion Joint

Page 9: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Patched Spillway Wall

Page 10: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Failed Bracing on Spillway Wall

Page 11: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Backfill Behind Spillway Wall

Page 12: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Complete designs for concrete spillway, gate and emergency spillway dike and related reports by 12/2015

Complete abutment and faceplate assessments by 2/2016

NEPA Compliance by 5/2016 Construction start by 2/2017 ??

CAS Status

Page 13: El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Questions?