Electrical District No. 2 APA Presentation Presented by: Thomas Martin General Manager
Transcript

Electrical District No. 2APA Presentation

Presented by:

Thomas Martin

General Manager

Electrical District No. 2, Pinal CountyOrganized in 1923

First Electrical District in ArizonaService Area – 120,000 Acres

ED2 System Map

ED2 Office – Constructed 1961

Irrigation Wells Number 2011 Usage355 95,367,459 kWh

Dairies Number 2011 Usage

12 17,245,699 kWh

Cotton Gins Number 2011 Usage

2 7,950,986 kWh

Casa Grande Water Reclamation Plant

12 Million Gallons per Day Capacity

Casa Grande Promenade Shopping Center

Farm Residence

ED2 Substation – One of six substations in theDistrict

Arizona Water Company - Domestic Water FacilityED2 serves 15 wells that provide domestic water for thegreater Casa Grande Valley

Pinal County Fairgrounds

Farm Equipment Dealer

ELECTRICAL DISTRICT NO. 2

ENERGY SALES AND HYDRO POWER PURCHASES - KWHs

YEAR 2011

SALES

AGRICULTURAL USE

COTTON GINS 7,950,986

DAIRIES 17,245,699

IRRIGATION 95,367,459

OTHER - GOLF COURSES 772,965

TOTAL AGRICULTURAL USE 121,337,109

STREET LIGHTS 816,057

WATER PUMPS FOR RESIDENTIAL, COMMERCIAL, INDUSTRIAL, ETC. 9,482,329

SEWAGE TREATMENT FACILITIES 8,650,970

RESIDENTIAL SERVICE - FARM 5,156,151

RESIDENTIAL SERVICE - NONFARM 40,177,371

COMMERCIAL SERVICE 32,322,292

INDUSTRIAL SERVICE 38,797,109

ED2 USE 346,694

TOTAL ENERGY SALES 257,086,082

PURCHASES

HYDRO POWER DELIVERED

HOOVER 57,703,000

CRSP 45,560,121

TOTAL 103,263,121

LESS: LINE LOSSES @ 7.8% (8,054,523)

NET HYDRO POWER 95,208,598

Possible Uses of Hydo Power (2011)

Agricultural and Related Uses : 120,564,144 kWhMunicipal Uses: 10,239,992AZ Water Co. Wells: 9,331,081

Associated Distr. Losses @ 5%: 7,375,537Total Ag and Muni Use: 147,510,754

Hoover Energy: 55,971,000CRSP Energy: 45,560,121

Total Hydro Energy: 101,531,121

Shortfall of Hydro Energy forAgricultural and Municipal Uses: 45,978,935 kWh

* All hydro is allocated to agricultural loads

Future Agricultural EnergyRequirements

Hohokam Irrigation and Drainage District, which isentirely within ED2’s boundaries, will begin toexperience reductions in its water supply starting in2013. By 2030, it is anticipated that all CAPagricultural water deliveries will end. Pinal Countyagriculture will then be almost entirely reliant onpumped water for irrigation purposes.Consequently, it is expected that ED2’s energyrequirements to serve irrigation loads will increasesignificantly above current levels.