Date post: | 03-Jun-2018 |
Category: |
Documents |
Upload: | humaid-shaikh |
View: | 216 times |
Download: | 0 times |
of 17
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
1/17
Electricity Distribution
System
Jasjit Singh Jolly
EEE-7thsem
0311324908
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
2/17
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
3/17
Distribution system layout
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
4/17
The generation generally takes place at
voltages around 3.3kV to around 22kV which
is medium voltage.
The voltage is then stepped up to a level of
110kV or 220 kV (high voltage) or even 400kV
(extra high voltage) depending on the amount
of power to be transmitted .
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
5/17
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
6/17
Saket D-block substation
Total no. of transformers: 2
Oil immersed step down delta/star transformers
Capacity : 1250kVA
Rated Primary Voltage : 11KVSecondary Voltage : 416/240V
Input HT lines: 11kV from Malviya Nagar grid
& 11kV from Lado Sarai
Integral part of the ring main distribution system
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
7/17
RMU: Ring Main Unit
RMU panel generallyforms ring system inwhich distributor issupplied from more than1 feeders as input to RMUso that in case of failurefrom any one feeder,power can be feduninterruptedly fromother feeders at thesame point. Now a days itis of SF6 gas insulatedtype.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
8/17
Contd
RMU is used for HT side and it has a
total number of 3 switches
(Circuit Breakers or Isolators),
it is used for two inputsand one outgoing to the load or
one input with two outgoings.
Primarily used for feeding purposes .
Also protects secondary side transformer from the occasionaltransient currents.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
9/17
Electricity supply to consumers
The secondary winding of
the transformer is mostly
of wye connection type.
This supply system with a
neutral wire is termed as 4
wire 3 phase supply.
4 wire supplies are normally
used to distribute domestic
supplies since they canprovide an earthed neutral.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
10/17
Contd
The three phase wires
together give a 3-phase 3-wire
supply (240x1.73=415Volts)
suitable or heavy machinery
such as 3-phase motors.
Three single phase supplies
are available between each
phase line and the neutral wire.
The three phase single phase 415V supplies are available between
any of the three phases.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
11/17
Contd
For distribution to consumers either overhead or
underground lines are used.
The underground system is much expensive as
compared to overhead system and is only used inareas where safety and good appearance are of
prime importance.
For domestic users a phase and a neutral connection
is supplied whereas for those with heavy load
requirements 3 wire connection is supplied.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
12/17
Faults in distribution lines
Transient Faults: A transient fault is a fault thatis no longer present if power is disconnectedfor a short time. For eg - momentary tree or
bird contact. Persistent Faults: A persistent fault does not
disappear when power is disconnected. Faultsin underground power cables are oftenpersistent. These occur due to some externaldamage.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
13/17
Contd
Faults can further be classified as symmetric
or asymmetric faults.
Symmetric faults: Equal fault currents in line with
120 deg displacement. Rare in nature. Eg - (L-L-L)
or (L-L-L-G) faults.
Asymmetric faults: Unequal fault currents with
unequal phase displacement. Most likely to occur.Eg (L-L) or (L-L-G) or (L-G) faults.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
14/17
Fault detection
To detect the exact location of a high
resistance fault in underground transmission
lines Arc Reflection Method (ARM) is used.
LSG 300 surge generator manufactured by
sebaKMT is use to testing purposes.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
15/17
Contd
LSG 300 along with a surge
generator and TDR teleflex
helps in detection of thelocation of fault.
In a first step, a TDR Teleflex does a low voltage reflection measurement
of the cable, not seeing the high resistive fault. This picture is stored as
reference. In a second step the energy of a surge generator is released
into the faulty cable, passing through the arc stabilising filter LSG 300.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
16/17
Contd
This surge causes a flashover at
the weak spot in the cable.
Simultaneously, the
LSG 300 triggers the TDR Teleflex .
The TDR can now see the lowresistive arc at the weak spot as a
short-circuit. This picture is stored
as fault-picture and compared
with the previously measured
reference picture. The point of
separation of the two traces is the
fault location and the TDR Teleflex
will indicate the distance to the
fault.
8/12/2019 electricitydistributionsysteminindia-110925005751-phpapp01
17/17
Thank You