ELECTRIFICATION INFRASTRUCTURE:
ASSESSING HOW INDIAN RAILWAYS OPTIMIZE T E N D E R I N G , C O N T R A C T I N G , D E S I G N A N D CONSTRUCTION PROCEDURES ACROSS ONE OF THE WORLD’S LARGEST NETWORK TO IDENTIFY COST REDUCTION LESSONS FOR GLOBAL INFRASTRUCTURE MANAGERS
Indian Railways-An Overview
Dedicated Freight Corridor Project
Project Over view Project at a Glance Unique Project Features Funding Arrangements Project Updates
Opportunities Contract Strategy Upcoming ICB - Procurements Road Ahead
Scope of Presentation
More than 64,600 kms( world’s third-largest rail network). Largest passenger carrier and the fourth-largest rail freight
carrier in the world. Runs 12,617 trains, carrying over 23 Million passengers
daily and connecting more than 7,172 stations. Runs more than 7,421 freight trains, carrying about 3
Million Tonnes of freight every day. Comprises 63,870 coaches, more than 240,000 wagons and
1.3 Million employees.
Indian Railways-An Overview
Indian Railways- An Overview
High%Density%Corridor%(Golden%Quadrilateral%+%Diagonals)%%
%
16%%of%route%Km%carries%52%%of%passenger%&%58%%%of%freight%
DELHI&
MUMBAI&
KOLKATTA&
CHENNAI&
Indian%Railways%–%An%Overview%
0%
100%
200%
300%
400%
500%
600%
700%
800%
900%
1000%
1950P51% 1960P61% 1970P71% 1980P81% 1990P91% 2000P01% 2010P11%
73.2%119.8%
167.9%195.9%
318.4%
473.5%
921.5%
Freight%Traffic%(MT)%
Freight&Traffic&(MT)&
Indian Railways – An Overview
MANIFOLD%GROWTH%OF%FREIGHT%TRAFFIC%
73.2%
473.5%
0&
100&
200&
300&
400&
500&
1950C51& 2000C01&
FREIGHT%TRAFFIC%(MILLION%TONNES)%
FREIGHT&TRAFFIC&(MILLION&TONNES)&
AN%INCREASE%OF%400.3%MT%OVER%50%YEARS%
473.5%
975.2%
0&
100&
200&
300&
400&
500&
600&
700&
800&
900&
1000&
2000P01% 2010P11%
Freight%Traffic%(MT)%
Freight%Traffic%(MT)%
2011P12%2000#01%
1950#51% 2000#01%
AN%INCREASE%OF%502%MT%FROM%2000P01%
Areas Of Concern
Falling market share (90% to 30%)
Capacity constraints on high density network.
Differential speeds of trains
Inadequate Ports / Mines connectivity
Inability to carry longer/heavier trains
Lower throughput / longer turn-around
DEDICATED FREIGHT CORRIDOR PROJECT
“DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LIMITED” (DFCCIL) WAS CREATED ON 30TH OCTOBER 2006 TO UNDERTAKE PLANNING, DEVELOPMENT, MOBILIZATION OF FINANCIAL RESOURCES AND CONSTRUCTION, OPERATION AND MAINTENANCE OF THE DEDICATED FREIGHT CORRIDORS.”
CHENNAI
KOLKATA
VIJAYAWADA VASCO
LUDHIANA
MUMBAI
DELHI
Sanc]oned%projects%
Unsanc]oned%projects%
Concept Plan of DFC Network
��������������
�����������������������
�����
������
�����������
���������
������������
��������
������������������
�����
�����������
NEW GANJKHWAJA
LUDHIANA
AMBALA
SAHARANPUR
MEERUT
HAPUR
KHURJA
ALIGARH HATHRAS
TUNDLA
ETAWAH BHAUPUR KANPUR
PREMPUR
ALLAHABAD
MUGHALSARAI
SONNAGAR
NEW KARWANDIYA
DANKUNI
EXISTING LINE
DFC LINE (PARALLEL)
(EXISTING STNS.
�������
Dedicated Freight Corridor - Eastern Corridor
�����������
��������������
��������������
��������
���������
�������
�����������
��������
VASAI
GOTHANGAM
MAKARPURA
SANAD
MAHESANA
PALANPUR
MARWAR
PHULERA
REWARI PIRTHALA REWARI
JNPT
NIM KA THANA
RINGAS
PHULERA
AJMER
SENDRA
MARWAR
SIROHI
ABU RD.
PALANPUR
MAHESANA
AHMADABAD
VADODRA
BHARUCH
SANJALI
SURAT
VALSAD
SANJAN DAHANU
PANVEL
VASAI
EXISTING LINE
DFC LINE (PARALLEL)
DFC LINE(DETOUR)
DFC JUNCTION STNS.
EXISTING STNS.
�������
Dedicated Freight Corridor - Western Corridor
Phas
e-2
Phase-2
DADRI
Objectives Of The Project
OBJECTIVES%
Create additional rail infrastructure to cater to high levels of transport demand
Reduce unit cost of transportation resulting in market competitive rail tariff for customer
Provide seamless end to end solution to the customers
Segregate freight infrastructure for focused approach on both passenger and freight business of Railways
Create rail connectivity to bulk customers not using rail network through PPP model
IT packaging of Freight Services
Increase rail share in freight market
Direct impacts :-
Transport capacity enhancement
Faster movement (Average speed to more than double)
Guaranteed transit time (freight trains to Time Table)
Special services (Automobile, RO-RO, etc.)
Asset utilization
Unit cost of transport
Greener Railway
POSITIVE IMPACTS
- 2.5 x - 6 x
Eastern Corridor (1975 Billion Tonne-Km)
Western Corridor (3241 Billion Tonne-Km)
Cumulative GHG emissions over 30 years
116
47.5
466
77
Source: Report on ‘Green House Gas Emission Reduction Analysis for DFC’ by Ernst & Young
Carbon Footprint of Dedicated Freight Corridor
Green DFC - to save 457 million-tonne CO2 over 30 years period.
Positive Impacts (Contd...)
Indirect impacts:-
Socio- Political
Economic – Not only regional but National
Employment generation
Released capacity on IR available for augmenting passenger services
Decongestion of major highways
Development of various industries/ancillaries
Development of industrial hubs
Positive Impacts contd..
Delhi%–%Mumbai%Industrial%Corridor%(DMIC)%–%An%Added%Feature
• Focus& is& on& ensuring& high& impact&
developments&within&150km&distance&on&
either&side&of&alignment&of&DFC&&
• Area&under&Project& Influence& is&14%&and&popula[on&is&17%&of&the&Country&
• Total&Popula[on& in& the&Project& Influence&Area&:&178Mn&
• Total& Workers& in& the& Project& Influence&
Area:&70.56Mn%%%%%%
As%per%CensusP2001%
DFC Alignment End Terminal
Haryana Dadri%
J.N.Port%
Rajasthan
Maharashtra
Gujarat Madhya Pradesh
Haryana
Uttar Pradesh
DFCC to manage train operation on DFC.
DFCC to have own stations and control centers.
Rolling stock ownership & its maintenance by IR.
Feeder Routes /Sidings to be upgraded by IR .
All LCs to be replaced by ROBs / RUBs.
Operating Aspects of DFCC
Height%
Width%
4.265&m& 7.1&m&
3200&mm& 3660&mm&
700&m& 700/&1500&m&
4,000&Ton& 15,000&Ton&
5.1m&&
Western&Corridor& Eastern&Corridor&
%%%%%%Moving%Dimensions%%%%%%%%%%%%%%%%%%%%%%%%%%%%%Container%Stack%%%%%%%%%%%%%%Train%Length%%%%%%%%%%%%%%%%%Train%Load%&&
% %Indian%Railway%%%%%% %DFC%Routes%
Western&Corridor& Eastern&Corridor&
Basic Design Features
www.dfccil.org
Heavier Axle Loads
Axle%Load%
Track%Loading%density%
22.9&t&/&25&t& 32.5t/25&t&
8.67&t/m& 12&t/m&
75&Kmph& 100&Kmph&
% %Indian%Railway%%%%%%%DFC%Routes%
Maximum%Speed%
Grade% Upto&1&in&100& 1&in&200&
Basic Design Features (Contd.)
% %%%%%%Indian%Railway%%%%%% %DFC%Routes%
Basic Design Features (Contd.)
Stations Every 7- 10 kms Every 40 kms
Electrification 25 KV AC 2x 25 KV AC (1 MVA /KM)
Signaling Absolute /Automatic with 1Km spacing
Automatic with 2 Km spacing
Communication Emergency sockets Mobile Train Radio
ELECTRIFICATION WORKS
Power density required to meet the projected traffic :1MVA/RKM
2x25 kV system has been adopted for
DFC
Flexible polygonal sagged simple catenary type OHE
Feeder wire along the track Protective earth wire Foundations – mechanized augering and concreting Steel structures –Higher size specially in WDFC (MMD
7.1 m) Flexible dropper
Contact wire(150 sqmm) :Copper Alloy Catenary wire(120 sqmm) : Copper Alloy
Feeder wire :AAAC
Protective Earth wire :GS Modular Cantilevers
Spacing of traction sub-station (60 km for DL and 90 to 100 km for SL)
Spacing of switching posts (15 to 17 km) Auto
transformer (8 MVA) Ratings of Scott/V-connected traction power
transformer (60/84 MVA)
SF-6 CB for HV side & VCB for 25 kV side Protection: Fast acting Intelligent Numerical
Protection – IEC 61850 Reactive Power Compensation: UPQC correction to
keep power factor harmonics and unbalance within limits. Dynamic Reactive compensation Appropriate C-R Device
TCP/IP based open protocol SCADA system (IEC- 60870-5-104) Video Wall display
Fault Locator of high accuracy
Execution
Functional independence to contractors to complete the project in time by
Proposing most optimal state of the art designs.
Adopt global standards.
Adopt globally prevalent construction methods with appropriate mix of human and machinery resources.
To protect the environment around the construction site.
Adopt energy efficient methods and equipment
Other Features
Higher MMD/SOD to result in high cost cargo transportation, e.g. automobiles, white goods, etc.
Multimodal logistic parks to fuel growth of industry and trade.
Paradigm shift in O&M methodology as a modern benchmark for railway networks.
• Project Completion Cost : USD 16 billion • Debt : Equity : 2:1 • Loans (Committed) : USD 10.930 billion (2.725 billion -
World Bank + 8.205 billion – JICA) • Loan Agreements Sanctioned/Signed : USD 10.28 billion
(2.1 Billion - World Bank + 8.205 billion – JICA)
• Loans under Approval : USD 625 million (World Bank)
• Eastern Corridor : World Bank (Ludhiana-Mughalsarai)
: GOI (Mughalsarai-Sonnagara)
: Sonnagar-Dankuni (546 km.) to be constructed through PPP. (Estimated Cost USD 2004 Million)
• Western Corridor : JICA Funded
Project Update
Over 98% land Acquisition completed under Railway Amendment Act, 2008.
All environmental and wildlife clearances in place.
Civil Contracts awarded for over 1000 route km length of corridor and works in progress.
Tenders for civil works for about 1250 km invited.
System contracts (Elect., Signalling & Telecom) also invited.
Mechanised Maintenance Contracts also planned.
Great opportunity for construction (equipment & machinery) and manufacturing industry.
Opportunities in public private partnership (PPP) in construction.
Developing more economic zones on the pattern of DMICDC.
High capacity Rolling stock for DFC. Setting up of logistic parks. Freight Business.
Mechanized Construction for faster progress and quality construction
Automated Mechanised & Concreting Machinery Major Bridge construction Machinery for Deep Friction Piles and End Bearing Piles Under-water Piling – Self Propelled Gantries
Mechanized Track Laying Cable / OHE laying . Mechanized Maintenance of Assets
Mechanised unwinding and anchoring of catenary and contact wires.
Scheduled Procurements* • Civil and Track Works 1250 route KM (Double Line) • Electrification Works 2250 route KM (Double Line) • Signaling & Telecom Works 2250 route KM (Double Line)
* Next one year
FIDIC Yellow Book customized for Design-Build railway infrastructure works.
Slice & Package System - enhanced competition.
PQ followed by one/two stage bidding- Pre-Qualification followed by two stage bidding – EDFC Pre-Qualification followed by single stage bidding – WDFC Engagement of consultant through Quality-Cum-Cost-Based-
System (QCBS)
New technology encouraged. Alternate technologies invited. Capitalization of Transformer losses for Bid evaluation
CAPITALISATION OF TRANSFORMER LOSSES K : Present worth of Transformer Losses in INR
K=D{(1+i)n-1} i(1+i)n D = Annual cost of combined No load and load losses in
INR i = Rate of compound interest on unit price of Transformer
@12% per annum n = Life of Transformer in years
Packaging and Slicing based on Road shows ICB based on WB Procurement Guidelines Design and Build LUMP SUM Completion Period: 3 to 4 yrs Defect Notification Period: 2 yrs
World Bank Funded Project: EDFC
• In accordance with Para 1.8 of the Guidelines: Procurement under IBRD Loans and IDA Credits, dated January 2011, the Bank permits firms and individuals from all countries to offer goods, works and services for Bank-financed projects.
JICA Funded Project: WDFC
• STEP Conditions
The eligible nationality of the supplier/applicant and all partners constituting the applicant shall be :- (i) Japan incase of the Prime Contractor (ii) All countries and areas incase of Sub-Contractors Incase where the Prime Contractor is a joint venture,
such joint venture will be eligible provided that the nationality of the lead partner is Japan and the nationality of the other partners is Japan and/or India and that the total share of work of Japanese partners in the JV is more than 50% of the contract amount.
Eligible Countries for Japanese ODA Loans
Performance Specification Based on EN, IEC or other International standard
Acceptance Criteria of PROVEN New Technology
Transfer of Technology for local sourcing
Three years of satisfactory performance Should have supplied equipment of 70% (min.) rating
of the equipment offered Should have supplied 50% quantity to be used in the
contract in last seven years Can supply two times( max.) the quantity supplied in
last seven years
50% quantity can be sourced locally through Technology Transfer to any Indian Company
Extended Guarantee for 3 years beyond DNP for
such items
TIMELINES
EDFC
BHAUPUR-KHURJA: 343 kms : Dec. ‘17
BHAUPUR-MUGHALSARAI: 402km. : June ‘18
DADRI-KHURJA-LUDHIANA: 447 km. : D*+5.5 yrs
MUGHALSARAI-SONNAGAR: 122 kms : Dec’16
WDFC
PHASE-1 REWARI-VADODARA (920 kms) : June’18
PHASE-2
VADODARA-JNPT (438 KMS) : Dec.’18
REWARI-DADRI (141 KMS) : Dec.’18
*D : Date of Loan approval by World Bank
ROAD AHEAD
Future Corridors
East – West Corridor (Kolkata–Mumbai) 2000 Kms. North-South Corridor (Delhi-Chennai) 2173 Kms. East Coast Corridor (Kharagpur-Vijayawada) 1100 Kms. Southern Corridor (Chennai-Goa) 890 Kms. RITES are conducting the study, to be completed by Dec 2014.
350 million cum of Earthwork / Subgrade 20 million cum of Stone Ballast Hundreds of thousand cum of RCC / PSC 11 million Sleepers/Ties Close to a million Tonne of Structural steel A million Tonne of Rail procurement /laying 7,000 small/big bridges More than 50 Rail to Rail Flyovers 1000 ROBs/RUBs
( All quantities are approximate )
54 Traction sub-stations. 162 Traction Switching Station (SP & SSP). 6000 Km of Contact & Catenary Wire ( Copper Alloy). 6000 Km of Aluminum (AAAC) Conductor. Over 3 Lacs Insulators. Over 100,000 MT of Steel Structures for OHE &
Switching Stations. Over 10,000 nos of ATDs 81 Traction Transformers. 600 Auto Transformers. TCP/ IP based SCADA.
( All quantities are approximate )
More than 100 Stations Signaling, complete with Electronic Interlocking and Track Detection.
More than 2000 Signals.
1 Master Switching Centre, 5 Base Switching Centre, 320 Base Transmitters and 1400 Cab Radios (OPH+GPH+GSM Hand Set) for GSM®.
More than 100 Telecom Facilities (Exchanges).
6000 Kms OFC and Quad Cables & Laying.
More than 100 OFC Nodes.
( All quantities are approximate )