Description:
EMCal work@Grenoble. For 7/11 EMCal Supermodules (3 done) Led test of delivered stripmodules (from Catania, Frascati, Nantes, WSU) Assembly (inserting stripmodules in SM crate) Cabling (US and EU SM signal cables are done @Grenoble) Calibration (Muons cosmic test bench) Crating - PowerPoint PPT Presentation
10
DCal meeting - CERN Dec 16-17 th ’09 1 LPSC / J.F Muraz EMCal work@Grenoble For 7/11 EMCal Supermodules (3 done) Led test of delivered stripmodules (from Catania, Frascati, Nantes, WSU) Assembly (inserting stripmodules in SM crate) Cabling (US and EU SM signal cables are done @Grenoble) Calibration (Muons cosmic test bench) Crating Shipping and Customs to CERN Design and production of the STU card Production of all EU Strap foils (3 SM)
Transcript
Page 1: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 1 LPSC / J.F Muraz

EMCal work@Grenoble

For 7/11 EMCal Supermodules (3 done)

Led test of delivered stripmodules (from Catania, Frascati, Nantes, WSU)

Assembly (inserting stripmodules in SM crate)

Cabling (US and EU SM signal cables are done @Grenoble)

Calibration (Muons cosmic test bench)

Crating

Shipping and Customs to CERN

Design and production of the STU card Production of all EU Strap foils (3 SM)

Page 2: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 2 LPSC / J.F Muraz

Infrastructure @Grenoble220 m² assembly building dedicated to the EMCal project -> DCal

Project

4 SM can be stored

(more if new platforms are made)

Page 3: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 3 LPSC / J.F Muraz

Assembly toolsAll needed tools are operationnal and can be re-used for DCal

SM

Strip Handling Tool

4 SM Platforms

Page 4: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 4 LPSC / J.F Muraz

Cosmic test bench

Page 5: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 5 LPSC / J.F Muraz

Cosmic test bench

2 SM can be sitted side by side for

combined Assembly / Calibration

Page 6: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 6 LPSC / J.F Muraz

Crating & ShippingProcedure for: Loading at Grenoble, shipping, customs, unloading at

CERN are validated and can be re-used for DCal SM

Page 7: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 7 LPSC / J.F Muraz

ScheduleAssembly, test and calibration for 1 SM: (based on 3 SM

experience)(under the hypothesis that the stripmodule are fully equipped (LED, APD etc …)

Strip delivery + first LED test (standalone) : 3 days (1 day / 1/3) Cabling : 3 days (1 day / 1/3)

LED driver system + fiber assembly : 1 day Electronics assembly and test : ~ 3 days Calibration measurement :

• 3 passes / 1/3rd 9 days

4 weeks minimum are required to assemble and calibrate a full Supermodule

Manpower (FTE): 1 Eng. + 2 Tech. + 4 physicists

Page 8: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 8 LPSC / J.F Muraz

- Assembly, cabling, calibration and shipping of DCal SModules

- Management of all DCal SM cables production at Grenoble.

- Production of strap foils for 2 (or more) DCal SM.

If green light from IN2P3. If no impact on EMCal schedule. If manpower support from D-Cal contributors. (SM Calibration)

More platforms must be produced to store EMCal-DCal SM @ Grenoble

Grenoble possible contribution to D-Cal

Page 9: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 9 LPSC / J.F Muraz

Page 10: EMCal work@Grenoble

DCal meeting - CERN Dec 16-17 th ’09 10 LPSC / J.F Muraz

Cosmics calibration

Test and calibration : Fix any hardware problems (LED, ADPs, cabling,

electronics …) Adjust the APD gain on the overall SM Calibration performed by 1/3rd of SM 3 passes required to achieve < 3% dispersion

(starting from 15%). 16 hours/pass (200 to 500 muons / tower

required

~15%

~2.3%


Recommended