EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout...

Date post: 29-Jan-2016
Category:
Upload: frederica-sparks
View: 219 times
Download: 0 times
Share this document with a friend
Popular Tags:
43
EMCal/DCal Electronics November 08, 2010 Outline: • EMCal Installation • DCal Preparations • Readout Upgrade - (Presentation by Hans)
Transcript
Page 1: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

EMCal/DCal ElectronicsNovember 08, 2010

Outline:• EMCal Installation • DCal Preparations• Readout Upgrade - (Presentation by Hans)

Page 2: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 2

EMCal Installation • Executive summary

– All readout hardware on SM is complete (at Grenoble)

• FEE crates, FEE cards, Cooling Manifolds, LED system, LV and HV cables, GTL buses, (RCUs)…

– All 6 SMs will be tested at P2 (SXL2) prior to installation

• Area has been prepared

– All cabling has been pre-installed on CalFrame• “Simply” need to connect SMs up after installation

– Main effort will be commissioning• Big task will be DCS work

– Should be relatively easy for SMA2 and SMC2 since they are on the same LV service group as SM0 and SM1

Page 3: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 3

EMCal Installation • SM Testing

– SM US#3 and US#5 delivered to B-167 • FEE cards installed

– (Modified FEE cards)

• LV, HV, T readout, trigger setup• DAQ station

– US#5 fully tested with LEDs• No bad channels! (1 weak signal/fiber)• Transported to P2 Nov. 5 for insertion tests

– US#3 to be tested with LEDs• This week probably.• Transport to P2 next week • Move DAQ setup next week

– EU#3 + US#4 arrive at P2 next week

Page 4: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 4

EMCal Installation • SM Testing @ SXL2

– All SMs will be re-tested at SXL2 with LEDs prior to installation

– Why re-test?• Plan to install “DTC” cards on all FEE cards prior to

installation– FEE cards of remaining 6 SMs have been modified with

installation of pins/sockets needed to mount DTC boards– Requires FEE cards to be removed to install DTC board

» DTC readout will be “ready” to use with “simple” cable connection after removing GTL bus and RCUs

– DTCs expected early December

• TRUs need to be installed and tested– TRUs expected in early December only– Installation of TRUs requires removal of DCS, GTL bus, etc.

Page 5: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 5

EMCal FEE Card Modification • FEE card modification for DTC

board – Insert and solder 4 pins and 4 sockets– Completed for 6 SMs to be installed– Plan to modify the FEE boards of 4

SMs already installed also (!)• Some channels suspected of no HV

bias to be repaired

Insert 4 pins

Insert 4 sockets

Page 6: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 6

EMCal FEE DTC Card• DTC board to be mounted on all FEE

boards – Passive while using GTL+RCU readout

• To enable DTC readout: – Reprogram FEE firmware

• 1-2 hrs/SM

– Connect cable to GTL bus (as shown)• Needed for FEE card enable and ALTRO

clock

– Connect RJ45 LVDS cable to SRU module – Free of RCU+DCS system!!!

• More later…

Page 7: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 7

EMCal Installation• Concerns?

– DTC cards• Mounting of the DTC boards prior to insertion of SMs is not essential,

– But it will be most convenient to do this prior to installation in L3

• Delivery expected by early December

– Removal of FEE boards from SMA0, SMA1, SMC0, SMC1 for modification, DTC installation, and any necessary repairs will be done as soon as DTC boards are available.

– TRUs • After testing in laboratory it still required some effort to debug TRUs in SMs.

– It will be most convenient to do this prior to installation in L3

– RCUs: This is the major concern…• We need 2x10 working RCUs to operate EMCal• Currently we have 37 RCUs in possession of EMCal, but only 12 confirmed to be

100% functional. – We will need to make a concerted effort at RCU repair– TPC has said there are no more spare RCUs available (to us)– This is one of the major reasons for the SRU readout upgrade…

• None of this will give reason to delay SM installation

Page 8: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 8

EMCal Installation• We want to be able to connect SM to services immediately after

insertion of each SM and test to confirm that the SM is fully functional

• All services are ready to connect to SM– Minor exception LED LV and trigger cables must be installed

• LED system was not finalized until after CalFrame was installed.• Can be installed in December

• Hardware– Service group A0-2 and C0-2 LV and HV ready– Need to install a LV module and 2 HV modules for service groups A3-4

and C3-4 (and finish a HV multi-pin connector) • Can be done in December - everything is at CERN

• DCS must be upgraded to configure and monitor new SMs– Jiro arrives in December to begin upgrade, Kithsiri also in January

• AMORE must be upgraded to provide monitoring histograms of all 10 SMs– Can be started immediately after end of run

• Francesco?

Page 9: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 9

EMCal DCS ModificationsSMA2 and SMC2 “simply” added to existing panels:

HV controlT monitoring

DCS Monitoring Panel for SM group A0,A1,A2 New Panels

and structure needed for SM groups A3,A4 and C3,C4.

Page 10: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 10

EMCal DCS Modifications

• Existing DCS control of FEE via scripts executed via ssh– 2 DCS boards per SM, with 10SM -> 20 DCS windows! + BusyBox

• Direct communication has been convenient for commissioning• During normal ALICE operation this is done “under the hood” of PVSS• EMCal functionally fully compliant, but technically not compliant as PVSS-DCS

communication should be done via DIM server – Jiro and Kirthsiri may work towards this in January

Page 11: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 11

EMCal Commissioning Schedule• December:

– Complete remaining hardware installations in P2: LV, HV modules, LED cables– Update DCS to be ready to control additional 6 SMs– Update AMORE to be ready to monitor pedestal and LED data from all 10 SMs and

check SMs as they are installed– Find/Fix sufficient RCUs for 10 SMs (starting now)– Complete TRU production– Complete DTC production– Install TRUs and DTCs on SMs and re-test SMs with LEDs in sequence of expected

installation– If DTCs available and time allows - Remove FEE cards from installed SMs to make

modifications and mount DTCs and fix any bad channels

• January:– Evenings(?): Connect each SM to services after installation. Test SM and full SM

groups.– Complete removal of FEE cards of installed SMs for repair, modification, DTC

installation.– Much etc, etc, etc to get everything functional for collisions.

Page 12: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 12

DCal Preparation Status

Page 13: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 13

SMA9SMA10 SMA11

SMC9SMC10

SMC11

C-side

A-side2

3

1

DCal Installation

• DCal is part of EMCal, but with shortened SMs– In DCS, DAQ and Trigger there will be no DCal distinction except by SM

number

• Sectors follow EMCal sector Numbering– EMCal Sectors 0-4 (5=1/3 SM, 6,7,8 empty)

1314

12

PHOS/EMCal do not follow ALICE Sector numbering

0

11

Page 14: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 14

DCal SM Readout• DCal same as EMCal,

but shortened– Fewer cables, fibers,

FEE cards

• 3 Shielded Ribbon Cables per Strip Module (48 total)– APD bias,

preamplifier LV, and signal

• 8 Temperature Sensors per SM – 2 sensors every 4th

strip module

• LED monitoring– One 3mm Fiber (1

LED) per Strip– 16 LEDs per SM

SM#2 @ Grenoble

Page 15: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 15

DCal Super Modules

DCal: 16 Strip ModulesRequires:• 24+1 FEE cards• 2 TRUs• 2 FEE Crates• 4 GTL Bus• 2 RCU+DCS+SIU• 1 LED Driver (doublet?)• 1 16xPhotodiode Reference

EMCal: 24 Strip ModulesRequires:• 36+1 FEE cards• 3 TRUs• 2 FEE Crates• 4 GTL Bus• 2 RCU+DCS+SIU• 1 LED Driver triplet• 1 24xPhotodiode Reference

Page 16: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 16

DCal FEE Crate - Option I

• Use two EMCal FEE crates but sparsely filled with FEE+TRU boards.– Each TRU connected to 12 FEE cards = 1 1/2 “rows” of DCal

• Option I: Keep FEE cards and TRUs in same location as for EMCal– ++ Connections on IPCB same -> cables same as EMCal

– -- FEE separated -> Longer FastOr cables

FEETRUEmpty

2 FEE Crates of SM

Page 17: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 17

DCal FEE Crate - Option II

• Option II. Move FEE cards closer to TRUs– ++ RCU1 GTL branch B not needed– ++ FastOR cables shorter– -- Different IPCB connector locations and FEE locations.

FEETRUEmpty

2 FEE Crates of SM

Page 18: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 18

DCal Electronics Status• All DCal electronics orders placed via ALICE-DCal CERN account (a

la ALICE-EMCAL account) set up April 14.• Highest priority was components for Strip Module assembly

– Strip Module components - all delivered and shipped to Catania, Nantes, and WSU

• APDs – 6000 for US EMCal @24.9euros/pc (4608 needed for 4 EMCal SM)

» 1392 available for US DCal (delivered@Houston)

– Tsukuba ordered 1200 PE APDs - all delivered @ Catania– 2500 PE APDs ordered @29.7euros/pc and (all?) delivered to Houston– With EMCal PE APD order, estimated 484 spare APDs

» ~500 APDs with epoxy problems (~1/2 recoverable)» Therefore 300 additional PE APDs ordered @29.7euros/pc (spares)

• 7000 Preamplifiers - all delivered– Total cost ~1.9 CHF/pc (cf. ~9 CHF/pc for original CSPs; 5.5CHF CSP )

• 3800 Molex cables (+EMCal extras) - all delivered– @2.25euros/pc (cf @1.6euros/pc)

• T-cards - all delivered (30 spares still to be delivered)– Total cost ~45 CHF/pc (cf. ~60 CHF/pc for original T-cards)

Page 19: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 19

Status: Strip Components• PE APD (4608 each)

– Same as used for last part of EMCal• 6000 for US EMCal @24.9euros/pc (4608 needed for 4 EMCal SM)

– > 1392 available for US DCal (delivered@Houston)

• 1200 ordered by Tsukuba @32.5euros/pc (already delivered@CERN)• 2500 additional ordered for DCal (to be delivered@Houston) @29.7euros/pc• Total = 5092 ==> 484 spares (399 missing?)

• Preamplifier (4608 each; modified)– Modified to use surface mount molex connector (and correct C7)– PCBs ordered and delivered– All components ordered and delivered– Production of 7000 CSPs may start this week

• Total cost ~1.9 CHF/pc (cf. ~9 CHF/pc for original CSPs; 5.5CHF CSP )

• Molex cables (4608 each)– 3800 ordered @2.25euros/pc (cf @1.6euros/pc)

• Transition Card (288 each; unchanged)– PCBs ordered and delivered– All components ordered– Order for production of 350 T-cards placed

• As well as 10 12-channel T-cards for LED reference system• Total cost ~45 CHF/pc (cf. ~60 CHF/pc for original T-cards)

Page 20: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 20

Status: Electronics • Signal cables (288 each; unchanged strips 0-35)

– To be ordered by Grenoble

• Intermediate PC Boards (6 (x4 PCBs) each; unchanged)– Produced and delivered to Grenoble (@~6000CHF)

• FEE Crate Mechanics (6 (x2) FEE crates; unchanged)– Rails & guides ordered and delivered (commercial Rittal) @1940CHF– Machined crate pieces produced at UT Austin and delivered to Grenoble– FEE Crate cover plates ordered and delivered @749CHF– Copper Cooling plates

• Material and Machining - done @9238CHF• Welding tubes on plates - done @ 6386 CHF• Manifold assembly & welding - done @ CERN @1770 CHF• Cleaning underway @ CERN @~1440CHF

• LED Drivers (6 (x3 PCBs) each; unchanged)– PCBs ordered @911CHF– Production underway, delivery in next weeks– LED Driver Box produced at UT Austin– Fiber connectors being modified at WSU

Page 21: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 21

Status: Electronics • LED Reference (6 each; unchanged)

– 144 Photodiodes delivered @ 10.3CHF/pc– Preamplifiers and12-channel T-cards (included above)– Fiber connectors being prepared at WSU – LED Reference support produced at UT Austin– Aluminum sheet metal pieces being produced in Grenoble

• LED Control Unit (LCU) (0 each; unchanged)– Use same unit as EMCal (+3 spares)

• Front End Electronics Card (150 each; unchanged)– Production version v1.1f

• We have ~80 extras from EMCal + 50 (JCal production), but only about 30 currently confirmed 100% working

– Needs a dedicated repair effort– Therefore plan to produce 150 new FEE boards

• 150 PCBs ordered to be delivered this week (@~110CHF/pc)• Some components ordered• Requested 600 ALTROs from CERN• Problem: GTL chips no longer in production - Need 1050; 300 from PHOS

– Phillips GTLP chips might be alternative - requires testing– Only 150 needed for use with Readout Upgrade

Page 22: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 22

Status: Electronics• Trigger Region Unit (12 each; unchanged)

– Jyvaskyla contribution (@~3600CHF)• Nothing ordered

• Summary Trigger Unit - STU (1 each; Grenoble)– Final production version

• Busy Box– DCal and EMCal use same BusyBox

• DCal is a part of EMCal detector system

• RCU: Readout Control Unit (6x2 each)– ALICE standard; “off the shelf”;

• If you can get them; Many “bad” RCUs; ~No spares; Insufficient stock for DCal– Will require a new RCU production for DCal – TPC group no longer responsible for RCU production

» RCUs require GTL chips - no longer in production

– Not needed with Readout Upgrade

• GTL bus (6 x2 (x4 types); unchanged)– Components ready, but order has not been placed – Not needed with Readout Upgrade

Page 23: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 23

Status: Electronics• DCS: Detector Control System card (6x2 each)

– ALICE standard; In hand– Not needed with Readout Upgrade

• DDL+DataReadOutReceiverCards (6x2 each)– ALICE standard; provided by DAQ group– Not needed for Readout Upgrade

• Need Gigabit Ethernet version of DRORC instead

• Local Data Collectors (PCs - 6 each)– ALICE standard; “Provided” by DAQ group

• Detector Control System (HV and LV control, FEE setup, Temperature readout, ethernet)– Incorporated into EMCal DCS

• Possibly need additional DCS Worker Node

• High Level Trigger– HRORCs + PCs

• Modification of HRORCs for Readout Upgrade?

Page 24: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 24

Trigger Considerations

• EMCal TRU to be used unchanged.– Jyvaskyla agrees to provide DCal TRUs

• EMCal STU to be used unchanged (probably), separate STU for DCal.– Case 1) PHOS TRU input to STU, DCal STU provides L1 shower

and Jet triggers from DCal+PHOS• Requires PHOS TRU to send FastOR data to STU

– PHOS TRUs cannot run as full 40MHz– PHOS TRU upgrade planned for 2011-2012 shutdown

• Requires 36 STU inputs for 3 sectors of DCal (12 TRUs) + PHOS (24 TRUs)

– Okay since STU has 40 inputs– Would require modified DCal TRU algorithm

– Case 2) DCal input only to DCal STU• STU provides L1 shower (and L0 OR) only to CTP

• EMCal and DCal triggers OR’d at CTP

Page 25: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 25

DCal Services

• DCal rack space defined– LV rack A13 (new)– HV rack (share with EMCal in

Y10 CR4)– DAQ LDC rack (3 LDCs)– HLT rack

• HV crate (share with EMCal)– 2 ISEG modules

• Delivered @15745CHF

• 2 LV multi-channel supplies in rack A13– Wiener (0-8V, and 0-16V)

• Delivered @27361 CHF

Rack O12 - EMC Rack Y10 - EMC/PHOS/CPV

5554 Turbine + Rack Monitoring535251 Heat Exchanger504948474645 Unused44434241

40 Netgear switch 4039 Netgear switch 3938 cable feedthrough 38 SY252737 37 (CPV)36 Turbine + Rack Monitoring 3635 35 Patch panel34 34 (CPV)33 Heat Exchanger 33 space for heat exchanger32 32 Cable feedthrough31 3130 3029 Wiener PL-500/F12 2928 +13.7 V OM21.0001 28 Iseg27 27 (PHOS)26 2625 Wiener PL-500/F12 2524 2-8V OM21.004 24 Patch Panel23 23 (PHOS)22 22 space for heat exchanger21 Wiener PL-500/F12 21 Cable feedthrough20 2-8V OM21.004 2019 1918 1817 Wiener PL-500/F12 17 Iseg16 2-8V OM21.003 16 (EMC)15 1514 1413 13 Patch Panel12 2x12 LV Patch Panel 12 (EMC)11 1110 10

9 98 87 2x12 LV Patch Panel 76 6 Unused5 54 43 32 21 Air Deflector 1 Air Deflector0 0

Rack A13 DCal

Page 26: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 26

DCal Services• Integration of DCal Electrical

“Services” within ALICE to SuperModule - Cables & Panels:– LV cables + distribution panels

(ordered)– HV cables + distribution(done)– Fiber optic + patch panels for trigger

and readout (DAQ group)– Temperature sensor MotherBoards

(requested) + cables to SM– Ethernet + patch panel (done)– Trigger cables

• Single cable tray will be sufficient – Located below SMs on support

• Layout by Stefane (done)

– DCal cables on support permanent

Primary LV(to 3 SM)

Secondary LV(to SM)

Page 27: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 27

DCal Services - Cables

• All DCal Cables/Patch Panels functionally specified (since January)

Spreadsheet from Didier Gabriele, based on spreadsheet from TA for entry to ALICE Cable DB

Page 28: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 28

DCal Services - Cables

• DCal SM services labeled as additional EMCal SMs. • Cable/fiber routing essentially finalized (Stephane Maridor) and ready to fix lengths, then

ready to commit to ALICE DB and produce cables.

Spreadsheet from Didier Gabriele, based on spreadsheet from TA for entry to ALICE Cable DB

Page 29: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 29

EMCal/Dcal Readout Upgrade

Page 30: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 30

EMCal/Dcal Readout Upgrade• Concerns with the existing EMCal GTL Bus based Readout

– GTL chips no longer in production• Likely insufficient supply for DCal FEE production

– Limitation of Serial Readout• Single FEE GTL problems can disable full GTL Bus (1/4SM) or RCU (1/2SM)• Readout time 10x FEE readout

– Minimum deadtime for p+p with Zero Suppression on FEE = 250 s– Minimum deadtime for Pb+Pb likely to be >625 s (1.6kHz max.)

– EMCal trigger• EMCal L0 Trigger must be inhibited (in TRU) during FEE readout due to noise

induced on FastOR lines

– RCU support• Production and RCUs no longer supported by TPC

– Insufficient RCU supply -> New RCU production will be required for DCal» Sufficient GTL chips for DCal RCU production?

• Firmware not under EMCal control– Requires TPC support for EMCal/PHOS versions

– Complexity • Requires 4 GTL boards, 2 RCUs, 2 DCS, 2DDL, + associated cables per SM

Page 31: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 31

FEE Upgrade Design

• Replace 2 RCU+DCS+SIU + 4 GTL with single SRU – Replace serial readout of 10 cards/GTL bus with parallel readout of all

FEE/TRU boards• Minimum readout speed ~30s, maximum readout speed (HI) ~100s

– FEE-SRU communication via LVDS serial lines a la TRU-STU• LCU was effectively a prototype SRU to test all functionality

– SRU-LDC communication via gigabit ethernet• Planned ALICE upgrade path• Compatible with existing DDL readout fibers

• New FEE (and FEE upgrade daughter card) must add LVDS communication channel– TRU already has this capability

2 x

Page 32: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 32

EMCal/DCal Readout Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

SRS project lead by Hans

Page 33: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 33

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

EMCal LED Control Unit

Page 34: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 34

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

Page 35: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 35

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

Page 36: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 36

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

Page 37: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 37

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

For EMCal:1 clock line2 data lines1 trigger line@80 MHz

Page 38: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 38

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

-> Est. rate limit ~300kHz p+p; 5kHz Pb+Pb

Page 39: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 39

EMCal/DCal SRS Upgrade

QuickTime™ and a decompressor

are needed to see this picture.

== EMCal LCU module

Page 40: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 40

EMCal/DCal SRS Upgrade• Plan & progress:

– Upgrade existing FEE boards with “small cheap” daughter card (DTC) to allow all FEE & TRUs to be readout with SRUs rather than RCUs.

• Prototype DTC board was made in March 2010– Tested with EMCal LCU as SRU emulator to demonstrate concept and necessary

performance of DTC-SRU link

• First pre-production DTC boards (shown) installed on FEE and tested with LCU– DTC PCBs expected next week, all components@CERN to start full DTC production

immediately - expect delivery end of November.

SRU

Page 41: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 41

EMCal/DCal SRS Upgrade• Plan & progress:

– SRU pre-production underway• 11 SRU PCBs produced in China (Wuhan)• Full SRU order has been placed (need 16 SRUs EMCal+DCal)

– All components for 8 SRUs at CERN

– Two SRUs will be produced and tested immediately (perhaps next week)

» If okay production of 8 SRUs will be completed (end of November)

» If layout problem, then modify PCB layout for new production

– Order PCBs, components for production of remaining SRUs (ready early 2011)

SRU

Page 42: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 42

EMCal/DCal SRS Upgrade• Plan & progress:

– DTC-SRU Firmware development (&TRU-SRU) is a major task• Fan Zhang (Wuhan) @ CERN for 1 year to work on this project (as part of SRS

for RD51)• FEE and TRU Board Controller firmware must be upgraded to use new protocol

for Data, Control, and Trigger via DTC board– Fan is also author of EMCal FEE board controller firmware

– TRU BC firmware will need to be upgraded by Jiri

• Plan for shutdown (ambitious!):– All DTCs to be installed on FEE

boards by end of 2010-11 installation

– Switch one EMCal Group (e.g. SMC3& SMC4) over to SRS readout by end of 2010-11 installation

• Insanely ambitious!• DTC(TRU)-SRS system must be fully

functional– Firmware development is already

underway

Page 43: EMCal/DCal Electronics November 08, 2010 Outline: EMCal Installation DCal Preparations Readout Upgrade - (Presentation by Hans)

November 8, 2010 EMCal & DCal Electronics, T.Awes 43

EMCal/DCal Readout Upgrade

• Plan:– EMCal to switch from RCU to SRS readout in groups of “quadrants”

(LV groups)• This can be done in about 2 days per group

• Can be done throughout 2011 run during Machine Stop periods– EMCal operated with mixed readout methods– Perhaps start 2011 run with one group in SRS readout mode

• Requires:– Removal of GTL+RCU+DCS– Installation of SRS module: mounting, cabling– Connection of DTC boards to GTL bus and SRS, and TRU to SRS– Reprogramming of FEE and TRU Board Controllers– Switch from ALICE DDL readout to Gigabit ethernet @ LDC– Switchover of FEE&TRU control from DCS board to Gigabit ethernet