+ All Categories
Home > Documents > Emergency Response Preparedness Program (Cris)

Emergency Response Preparedness Program (Cris)

Date post: 03-Apr-2018
Category:
Upload: alvin-garcia-palanca
View: 217 times
Download: 0 times
Share this document with a friend

of 107

Transcript
  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    1/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAM

    Document Title

    01 3/1/2011 EMS 2004 1 of 97

    Rev No. Start Date Doc No. Page

    REVISION HISTORY

    Ref. No.Doc.

    Rev. No.Page No.Affected

    Originator Date Details of Changes

    N/A 00 N/A ESDeonaldo 3/01/2010 originate

    IMPORTANT:THIS COVER SHEET FORM IS PART OF THE FOLLOWING DOC SHEETS AND IS NOTTO BE DISCARDED UNLESS SUPERCEDED BY A REVISED ISSUE. UNAUTHORIZEDREPRODUCTION IS STRICTLY PROHIBITED.

    Name Department Date

    Originator :

    CD Era Safety / TDEM

    Checked by :ES Deonaldo Safety / TDEM

    Approved by :

    M. Kawata Plant Manager NOTE : USE BLACKPEN FOR SIGNING

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    2/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 2 of 97

    Rev No. Start Date Doc No. Page

    TABLE OF CONTENTS

    1 INTRODUCTION............................................................................................7

    1.1 GENERAL INTRODUCTION..........................................................................71.2 SCOPEOFTHE PLAN.................................................................................71.3 AUTHORITY STATEMENT............................................................................91.4 PLAN DISTRIBUTION..................................................................................9

    1.4.1 LOCATION AND PLAN IDENTIFICATION NUMBERS..............................91.4.2 PLAN INFORMATION AND CONTACT PERSON...................................10

    1.5 PLAN UPDATING PROCEDURES................................................................111.6 PLAN TRAINING.......................................................................................11

    1.6.1 BASIC TRAINING PROGRAMS...............................................................111.6.2 OTHER TRAINING...................................................................................121.6.3 EMERGENCY RESPONSE TEAM MEMBERS........................................121.6.4 TRAINING FREQUENCY.........................................................................12

    1.7 PLAN DRILLSAND EXERCISES.................................................................131.7.1 EXERCISE DOCUMENTATION...............................................................13

    2 GENERAL INFORMATION..........................................................................14

    2.1 ORGANIZATIONAND PERSONNEL RESPONSIBILITIES.................................142.1.1 EMERGENCY RESPONSE TEAM...........................................................14

    2.1.2 KEY PROJECT PERSONNEL AND OUTSIDE GROUPS........................152.1.3 MEDIA RELATION POLICY......................................................................16

    2.2 EMERGENCY ALERTING PROCEDURES.....................................................172.3 EVACUATIONAND PERSONNEL ACCOUNTABILITY......................................17

    2.3.1 EMERGENCY RESPONSE TEAM HEAD (PLANT MANAGER)..............182.3.2 OPERATION TEAM..................................................................................182.3.3 FIRE FIGHTING AND FIRST AID TEAM..................................................192.3.4 UTILITIES/ENGINEERING TEAM............................................................192.3.5 GUIDANCE AND PUBLIC RELATIONS TEAM........................................192.3.6 MONITORING TEAM................................................................................202.3.7 MEDICAL TEAM.......................................................................................202.3.8 LOG RECORDER.....................................................................................21

    3 EMERGENCY PROCEDURES....................................................................21

    3.1 H2S GAS LEAK.......................................................................................213.1.1 EMERGENCY EQUIPMENT.....................................................................223.1.2 ALARM SYSTEM......................................................................................223.1.3 H2S GAS LEAK AT THE H2S HOLDER...................................................223.1.4 H2S GAS LEAK AT THE AREA OTHER THAN THE H2S HOLDER.......283.1.5 CLEARANCE/ LIFTING OF THE EMERGENCY......................................293.1.6 H2S EMERGENCY PROCEDURES - NIGHT SHIFTAND HOLIDAYS....30

    3.2 ACID LEAK..............................................................................................313.2.1 ACID LEAK FROM THE PIPELINE (PLANT SITE)..................................31

    3.2.2 ACID LEAK FROM THE PIPELINE (PIER SITE)......................................32

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    3/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 3 of 97

    Rev No. Start Date Doc No. Page

    3.2.3 ACID LEAK FROM THE LORRY (PLANT SITE)......................................343.2.4 ACID LEAK FROM THE LORRY (PIER SITE).........................................363.2.5 ACID LEAK FROM THE LORRY (MACADAM ROAD).............................38

    3.3 POWER FAILURE.....................................................................................403.4 AIR FAILURE...........................................................................................433.5 FIRE.......................................................................................................46

    3.5.1 COAL FIRE (AT PIER COAL STOCKYARD)............................................463.5.2 METHANOL FIRE (PIER SITE)................................................................473.5.3 METHANOL FIRE (PLANT SITE).............................................................493.5.4 SULFUR FIRE (PIER SITE)......................................................................513.5.5 SULFUR FIRE (PLANT SITE)...................................................................52

    3.6 TRAFFIC ACCIDENTS...............................................................................543.6.1 SULFURIC ACID LORRY.........................................................................55ESTIMATEOFQUANTITYSPILLEDANDRATEOFRELEASEIFCONTINUING;...............56

    CAUSEOFTHEACIDSPILL;..................................................................................56SOURCEOFTHEACIDSPILL;AND.........................................................................56LOCATIONOFSPILLANDDIRECTIONOFSPREADIFMOVING...................................56IFTHEREISDANGEROFSPILLSPREAD, COORDINATEWITHCONCERNEDEMPLOYEESON:..........56LAY-OUTOFADDITIONALSPILLBOOMS;AND.........................................................56BLOCKINGOFFOFCHEMICALSPREAD..................................................................56AFTERLEAKHASBEENSTOPPEDANDSLICKCONTAINED, EFFECTAPPROPRIATECHEMICAL

    RECOVERYPROCEDURES......................................................................................573.6.2 METHANOL TRUCK.................................................................................573.6.3 CHEMICAL/MS PRODUCT TRUCK.........................................................601. ESTIMATEOFQUANTITYSPILLEDANDRATEOFRELEASEIFCONTINUING;............612. SOURCEANDCAUSEOFTHECHEMICALTRUCK SPILL;AND................................613. LOCATIONOFSPILLANDDIRECTIONOFSPREADIFMOVING................................614. IFTHEREISDANGEROFSPILLSPREAD, COORDINATEWITHCONCERNEDEMPLOYEESON:.......615. LAY-OUTOFADDITIONALSPILLBOOMS;AND......................................................616. BLOCKINGOUTOFCHEMICALSPREAD...............................................................61SPILLSRECOVERYPROCEDURE:..........................................................................611. FORSOLIDSPILLAGES (SULFUR, SLAKEDLIME, CAUSTICSODA,ANDFLOCCULANT)612. CLEANSPILLSINAMANNERTHATFINEPARTICLESWILLNOTDISPERSEINAIR.....613. CONTAINSPILLAGESANDTRANSFERTOACONTAINERFORRECOVERY...............614. WASHTHEAREA, WHERECHEMICALSPILLSHAPPENED, WITHWATERANDCOLLECTTHEWASHINGSUSINGPUMP, VACUUMTRUCK, ORANYOTHERMEANS...........................627. COORDINATEWITHEMO FORPROPERDISPOSAL..............................................62

    IFLARGEQUANTITYOFSPILL, CLEANUPPROMPTLYBYPUMP, VACUUMPUMPORANYOTHERMEANS. 62KEEPTHERECOVEREDSPILLSINACLOSEDCONTAINER........................................62COORDINATEEMO FORPROPERDISPOSAL..........................................................62

    A. RESPONDSTOTHEREPORTED CHEMICALSPILLANDDIRECTSTHEACTIONSOFTHEOTHERMEMBERSOFTHEEMERGENCYRESPONSETEAM..................................................62B. GETSUPDATEFROMTHECHEMICAL SPILL TEAMLEADER(PRODUCTIONMANAGER) OFTHEPRESENTCONDITIONOFTHECHEMICALSPILL........................................................62C. ENSURESCHEMICALSPILLHASCOMPLETELYBEENCONTROLLED.......................62

    3.7 TYPHOON, FLOOD, HEAVY RAINAND LANDSLIDES....................................623.7.1 PLANT SITE OPERATION.......................................................................623.7.2 LANDSLIDES AND FLOODING...............................................................65

    EXACTLOCATIONOFTHELANDSLIDE....................................................................66

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    4/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 4 of 97

    Rev No. Start Date Doc No. Page

    ESTIMATEDVOLUMEOFSOILERODED..................................................................66ESTIMATEDAREAAFFECTED................................................................................66STATUSOFMOVEMENTS (ACTIVEORINACTIVE)....................................................663.7.3 QUARTERS, HOUSING AND SCHOOL...................................................67GENERALCLEAN-UPHOUSEKEEPING. THISMUSTBEDONEWHILEONEISINCOMPLETECONTROL

    OFCONDITIONI.E., BEFORETHETYPHOONARRIVALS.............................................67BREAKABLEOBJECTSSHOULDBEPLACEDINSIDECUPBOARDS..............................67HOUSES/QUARTERSSHOULDBEVENTILATEDBYOPENINGWINDOWS. THEWINDOWSATTHESIDE

    AWAYFROMTHEWINDSHOULDBEOPENEDTOEQUALIZEAIRPRESSURE. WHENWINDCHANGESDIRECTIONASTYPHOONMOVESALONGITSPATH, THEWINDOWSTHATAREOPENEDONTHELEEWARDSIDEWILLENDURETHEMOSTOFTHEWINDCHANGE. THESEWINDOWSMUSTTHENBECLOSEDANDTHESEONTHEOPPOSITESIDESHALLBECRANKEDOPEN...................67ALLLOOSEOBJECTSOUTSIDEHOUSES/QUARTERSSHOULDBEPICKEDUP, EITHERSTORED

    UNDERCOVERORSECURED.................................................................................67

    REMEMBERTHATANYOBJECTLIFTEDANDHAULEDBYTREMENDOUSWINDCANBEDEADLYINSTRUMENTTOINJUREORKILL............................................................................67WITHOUTTHESLIGHTESTDOUBTELECTRICALPOWERWILLBELOSTVERYSOONAFTERTHE

    TYPHOONBEGINS. THISWILLTHENREQUIREPLANNINGFORLIGHTANDALTERNATEMETHODOFCOOKINGANDHEATINGFOOD...............................................................................67LANTERNSSUCHAS PETROMAXWITHSUFFICIENTFUELANDAFEWEXTRAMANTLESMUSTBE

    ATHAND. BATTERYPOWEREDLANTERNSSHOULDBECONSIDEREDASTHEYPREVENTLOSSOFAFIREHAZARD. ALSOEXTRABATTERIESANDABULBORTWOFORPOSSIBLEREPLACEMENT........68FLASHLIGHTWITHADEQUATEBATTERIESANDEXTRABULB....................................68CANDLESSHOULDONLYBEUSEDASALASTRESORT...........................................68OPENEDFLAMESNOMATTERHOWSMALLPOSEHAZARDS.....................................68BESURETOHAVEANADEQUATESUPPLYOFFOOD...............................................68

    WATER 68HAVECONTAINERSFILLEDWITHWATERAGAINSTTHEPOSSIBILITYTHATTHESUPPLYMAYFAIL.

    68BUCKETSORPAILSMUSTBEAVAILABLEINTHEEVENTOFFIRE.............................68MAINTAINADEQUATESUPPLYOFCANNEDFOODSTHATMAYBESERVEDCOLD.......68EMERGENCY.......................................................................................................68KNOWLOCATIONOFMAINCIRCUITBREAKERFORALLELECTRICALPOWERENTERING

    HOUSE/QUARTERFORSWITCHINGOFFWHEREANDWHENNECESSARY...................68

    3.8 ACCIDENTSAT CBNC COMPLEX.............................................................683.8.1 MEDICAL EMERGENCY RESPONSE.....................................................683.8.2 RESPONSES ON OCCUPATIONAL FATALITIES ..................................703.8.3 WHEN A FATALITY HAPPENS................................................................71

    3.9 TAILINGS DAM EMERGENCY.....................................................................723.9.1 SAFE ACCESS ROUTES TO THE TAILINGS DAM................................723.9.2 AREAS THAT MAY BE IMPACTED.........................................................723.9.3 CONDITIONS THAT WILL CALL FOR A DAM EMERGENCY.................733.9.4 LEVEL 1 (IMPENDING DAM FAILURE)...................................................743.9.5 LEVEL 2 (DAM FAILURE; NEARBY FACILITIES IMPACTED)................763.9.6 LEVEL 3 (DAM FAILURE; IMPACTING THE COMMUNITY)...................773.9.7 SPECIAL EQUIPMENT AND RESOURCES REQUIRED........................783.9.8 TESTING AND REVISION OF THE PLAN...............................................78

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    5/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 5 of 97

    Rev No. Start Date Doc No. Page

    LIST OF TABLES

    TABLE 1 ERPP DISTRIBUTION...................................................................10

    TABLE 2 COMPOSITION OF THE EMERGENCY RESPONSE TEAM (ERT)14

    TABLE 3 KEY PROJECT PERSONNEL TO BE CONTACTED DURINGEMERGENCIES..............................................................................................15

    TABLE 4 LOCAL AND NATIONAL ORGANIZATIONS AND SERVICE PROVIDER....16

    TABLE 5 EMERGENCY EQUIPMENT...........................................................22

    TABLE 6 PHASES/STAGES DURING LEAK AT THE H2S HOLDER.........22

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    6/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 6 of 97

    Rev No. Start Date Doc No. Page

    THIS PAGE INTENTIONALLY LEFT BLANK

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    7/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 7 of 97

    Rev No. Start Date Doc No. Page

    1 INTRODUCTION

    1.1 General Introduction

    The Coral Bay Nickel Corporation - Emergency Response and Preparedness

    Program (ERPP) is intended to handle emergencies of a particularly serious nature,

    which are likely to involve hazards to personnel, damage to equipment and cause

    serious inconvenience to the general public. This plan also aims to prevent injury

    and the loss of lives and property during emergencies. This is attained by

    instructing employees and management what to do for every conceivable

    emergency.

    1.2 Scope of the Plan

    An advance emergency planning, therefore, should be intensified to be able to

    handle emergencies effectively such as:

    I. H2S Gas Leak

    II. Acid Leak

    a. Acid Leak from the Pipeline (Plant site)

    b. Acid Leak from the Pipeline (Pier site)

    c. Acid Leak from the Lorry (Plant site)

    d. Acid Leak from the Lorry (Pier site)

    e. Acid Leak from the Lorry (Macadam Road)

    III. Chemical Spills

    a. Chemical Spills (Laboratory)

    b. Oil Spills (Plantsite)

    IV. Power Failure

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    8/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 8 of 97

    Rev No. Start Date Doc No. Page

    V. Air Failure

    VI. Fire

    a. Coal Fire (Pier Coal Stockyard)

    b. Methanol Fire

    i. Pier site

    ii. Plant site

    c. Sulfur Fire

    i. Pier site

    ii. Plant site

    VII. Traffic Accident

    a. Sulfuric Acid Lorry

    b. Methanol Truck

    c. Chemical Truck

    VIII. Typhoon/Flood/Heavy Rain/Landslides

    IX. Accidents at the CBNC Complex

    X. Tailings Dam Emergency

    XI. Emergency on Nuclear Equipments and Devices

    XII. Earthquake

    XIII. Medical Emergencies/Outbreaks

    The Emergency Response and Preparedness Program is designed to handle such

    emergencies on a planned and orderly manner. It is intended that everyone who

    has a part to play in disaster control should know his/her responsibilities.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    9/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 9 of 97

    Rev No. Start Date Doc No. Page

    1.3 Authority Statement

    The Emergency Response and Preparedness Program, upon approval by the

    CBNC Plant Management, grants the authority to company officials to implement

    the plan in order to terminate any emergency. The Emergency Coordinator is

    authorized to perform the coordination and overall implementation of the said plan.

    The emergency coordinator will be designated depending on which area the

    emergency or incident occurred. All other employees and persons concerned are

    enjoined to cooperate fully with the designated personnel in carrying out the

    appropriate response called for by an emergency.

    1.4 Plan Distribution

    An electronic copy of the Emergency Response and Preparedness Program shall

    be made available for easy access by CBNC employees at the File Server in PDF

    format. The master copy shall be maintained by the Document Control Custodian.This plan shall be made available for review by all employees. Likewise, a copy

    shall be submitted to Mines and Geosciences Bureau (Central Office) and

    Department of Labor and Employment (Bureau of Working Conditions).

    1.4.1 LOCATION AND PLAN IDENTIFICATION NUMBERS

    Since CBNC electronic file will be made readily available through the

    Common File Server, printed hard copies shall be made available for the

    following personnel who do not have a direct access to the file server. The

    plan shall be identified with a number on the binder spine to control its

    dissemination. Table below indicates the distribution and location of the said plan.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    10/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 10 of 97

    Rev No. Start Date Doc No. Page

    Table 1 ERPP Distribution

    Plan

    NumberDepartment Location

    ERPP-1 Office of the Plant

    Manager

    Office of the Plant Manager , CBNC

    ERPP-2 RTNMC Management Office of the Res. Mine Manager,

    RTNMC

    ERPP-3 RTNMC Safety Office Safety Engineers Office, RTNMC

    ERPP-4 JGC/JMAINT JGC/ JMAINT Office

    ERPP-5 SMCC Management Office of the Project Manager, SMCC

    ERPP-6 MANNJ Trading MANNJ Manager s Office

    ERPP-7 DCR MPS DCR MPSs Managers Office

    ERPP-8 PCBSI Office of the Branch Manager

    ERPP-9 Barangay Rio Tuba Office of the Barangay Chairman

    ERPP-10 RTNFI Hospital Office of the Medical Director

    ERPP-11 CBNC SAFETY Safety Office

    ERPP-12 Office of the President CBNC Makati Office

    These plans shall be kept in their designated locations at all times so that they

    can easily be obtained when needed. The Emergency Response and

    Preparedness Program shall always be updated.

    1.4.2 PLAN INFORMATION AND CONTACT PERSON

    The plan may be obtained from the Department Managers and Safety Section

    upon the approval of the Plant Manager.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    11/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 11 of 97

    Rev No. Start Date Doc No. Page

    1.5 Plan Updating Procedures

    The Safety and Health Committee will review the ERPP once a year, every time an

    emergency occurs, or when new and revised legislation affecting it as promulgated.

    The addition, revisions and modifications formulated by this committee shall be

    incorporated in the plan. The Plant Manager, in collaboration with the Central

    Safety and Health Committee, shall be responsible for the dissemination of these

    changes.

    In case of revision, the history revision page shall be indicated with the revision

    number,date revised, and the revised items. The revised section will be printed in

    its entirety. All pages of the revised section will bear the revision date and

    designated reference numbers, that is, mm/dd/yy. This procedure ensures that

    there will be no confusion between current and obsolete portions of the manual.

    1.6 Plan Training

    The Plant Manager is responsible for the design and conduct of training programs

    for employees. The training needs of employees shall depend on their functions

    and vulnerability to accidents and emergencies. Current skills of employees in

    relation to emergency situations shall likewise be considered. Based on these

    factors, the employees will be classified into groups. The training program shall

    focus on the following:

    Roles and Responsibilities of the employees

    Emergency Plan Procedures

    Evacuation Procedures

    1.6.1 BASIC TRAINING PROGRAMS

    Regardless of designation, each employee shall be provided with training on the

    following:

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    12/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 12 of 97

    Rev No. Start Date Doc No. Page

    A. Emergency Plan Procedures

    B. Emergency Evacuation Procedures

    C. Basic Fire Fighting Procedures (Fire Extinguishers)

    D. Basic First Aid, and

    E. Basic Cardio Pulmonary Resuscitation (CPR) Procedures

    The training program will enable all employees to identify conditions, which might

    lead to an emergency situation. Immediate identification of a potentially

    dangerous situation will be most helpful in damage control.

    1.6.2 OTHER TRAINING

    Additional training will be given to supervisors and other personnel responsible for

    the safety of other people, operation of various kinds of equipment, and

    undertaking of activities that may expose employees and visitors to certain risks.

    The training includes, but not limited to Basic Occupational Safety And Health,

    Loss Control Management, Basic Safety Auditing, and Advanced Safety

    Management. Other training may be considered as determined by the Safety

    Office.

    1.6.3 EMERGENCY RESPONSE TEAM MEMBERS

    An Emergency Response Team shall be created for certain emergencies. This

    team shall be headed by the Emergency Response Team Head and to be

    assisted by Sub Head.

    1.6.4 TRAINING FREQUENCY

    All employees shall undergo the basic training program upon joining the company.

    When employees are transferred to other departments, an appropriate training

    course or orientation regarding their new duties, responsibilities and work

    procedures shall be provided by the Department concerned._______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    13/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 13 of 97

    Rev No. Start Date Doc No. Page

    The frequency of training for the supervisors and members of the Emergency

    Response Team shall be determined by the Safety and Health Committee.

    1.7 Plan Drills and Exercises

    Emergency drills for various emergencies shall be conducted regularly for all work

    shifts to ensure employees emergency preparedness skills. The Safety and Health

    Committee shall determine the frequency of these exercises. Specific areas to be

    monitored during these exercises are:

    Evacuation and accountability of personnel

    Proper operation of alarms, sirens and other systems

    Response Time of the Emergency Response Team members

    and plant personnel

    Adherence to Plan Procedures.

    1.7.1 EXERCISE DOCUMENTATION

    The exercises shall be documented using the Emergency Response Exercise

    Evaluation Form (Please see Appendix 3) which shall be completed by the

    Safety Section after the evaluation meeting which shall be conducted immediately

    after the exercise to be attended by Department Managers and Department

    Supervisors who are present. The report shall discuss the results of the exercise,

    problems encountered during the execution of the plan and any recommendations

    for improvement and modifications of the existing plan which shall be applied in

    the next exercises. The report shall be signed by the attendees to signify their

    approval.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    14/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 14 of 97

    Rev No. Start Date Doc No. Page

    2 GENERAL INFORMATION

    2.1 Organization and Personnel Responsibilities

    In an emergency, the Emergency Response Team Head (Plant Manager) is

    responsible for implementing appropriate action to ensure the safety of the

    employees and visitors in the operating premises. Management authorizes him to

    carry out the tasks and functions laid down in the plan.

    If he is not present in the event of an emergency, the assigned Sub Head/s will

    assume his responsibilities. The contact numbers of the Emergency Response

    Team Head (Plant Manager), his Sub Heads and all members of the Emergency

    Response Team shall always be available and shall be prominently displayed in

    strategic areas within the operating premises.

    2.1.1 EMERGENCY RESPONSE TEAM

    Table below is the composition of the Emergency Response Team. The team will

    be directly under the direction of the Plant Manager.

    Table 2 Composition of the Emergency Response Team (ERT)

    Name Position Team DesignationContact

    Numbers

    Mr. Koji Sakamoto Plant Manager Head, ERT 09175404666

    Mr. Arturo T.Manto

    Vice President forEnvironment and

    External Affairs

    Sub Head, ERT 09178219754

    Mr. Isao NishikawaManager, ProductionDept.

    Head, Operation Team at Plantsite (Production)Sub Head, ERT

    09175810551

    Mr. DiosdadoParaiso

    Asst Manager,Production Dept.

    Sub Head, Operation Team atPlantsite (Production)

    09178064635

    Mr. HidehikoHarada

    Manager, General AffairsDept.

    Head, Guidance and PublicRelations TeamSub Head, ERT

    09155384172

    Mr. Warlito B.Tabanag

    Manager, PersonnelSect

    Sub Head, Guidance and PublicRelations Team

    09178551271

    Mr. Ernesto A. Manager, Comrel Sect Sub Head, Guidance and Public 09165718013

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    15/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 15 of 97

    Rev No. Start Date Doc No. Page

    Llacuna Relations Team

    Mr. ShigeruOnozaki

    Manager, MaintenanceDept.

    Head, Maintenance TeamSub Head, ERT

    09178036079

    Mr. Takao NiiyamaManager, Purchasingand Logistics Dept.

    Head, Operation Team atPlantsite and Pier site (PLD)Sub Head, ERT

    09178540446

    Mr. Yuji Tange Manager, Utilities Dept.Head, Operation Team atPlantsite (Utilities)Sub Head, ERT

    09178544843

    Mr. Erwin S.

    DeonaldoHead, Safety Section

    Head, Firefighting and First AidTeamsSub Head, ERT

    09178551271

    Mr. Briccio Abela Head, EMQC UnitHead, Monitoring TeamSub Head, Guidance and PublicRelations Team

    09178506099

    Mr. Reginaldo Z.Mia

    Medical Director, RTNFIHospital

    Head, Medical Team 09273195984

    Ms. RaquelTantoco

    Safety Coordinator,Safety Section

    Log Recorder / Documentation

    2.1.2 KEY PROJECT PERSONNEL AND OUTSIDE GROUPS

    Key Project Officers shall be informed during major emergencies. Their names,

    designations and contact numbers are indicated below:

    Table 3 Key Project Personnel to be contacted during Emergencies

    Name PositionContact

    Numbers

    Mr. Takanori Fujimura President, CBNC 09175384488

    Mr. Koji Sakamoto Plant Manager, CBNC 09175404666

    Mr. Arturo T. Manto

    Vice President for Environment and

    External Affairs 09178219754Mr. Isao Nishikawa Manager, Production Dept. 09175810551

    Mr. Hidehiko Harada Manager, Gen. Affairs Dept. 09155384172

    Mr. Shigeru Onozaki Manager, Maintenance Dept. 09178036079

    Mr. Takao Niiyama Manager, PLD 0917540446

    Mr. Yuji Tange Manager, Utilities Dept. 09178544843

    Mr. Erwin S. Deonaldo Head, Safety Section 09178551271

    Mr. Briccio Abela Head, EMQC Section 09178506099

    Mr. Bernardo M. Dacyon,Jr.

    Resident Mine Manager, RTNMC 09178937267

    Hon. Bgy. Capt. GomerMiano

    Bgy. Capt. , Rio Tuba 09214028419

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    16/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 16 of 97

    Rev No. Start Date Doc No. Page

    Other individuals and groups not connected with the company may be calledduring an emergency. The contact numbers of these entities shall likewise beprominently displayed in strategic areas within the operating premises.

    Table 4 Local and National Organizations and Service Provider

    Organization Contact Person Contact Numbers

    RTNFI Hospital Dr. Reginaldo Z. MiaHospital Director

    09273195984

    Rio Tuba Barangay Disaster CoordinatingCouncil

    Gomer MianoBarangay Captain

    09214028419

    Municipal Disaster Coordinating CouncilBureau of Fire Protection Bataraza

    Philippine Air ForceRio Tuba Detachment

    1Lt. Romar CatotalComm. Officer2Lt. Elias GarryGregorioAsst. Comm. Officer

    Philippine National Red Cross (PNRC)Puerto Princesa City, Palawan Chapter

    Miss Arsenia TadiqueAdministrator

    (048) 4336362

    Philippine National Red Cross (PNRC)-ManilaNational Headquarters, Bonifacio Drive, PortArea, Manila

    Mrs. Lourdes GenatoManager, SafetyServices

    (02) 5279979

    Mines and Geosciences Bureau (MGB-Central)

    Horacio C. RamosDirector

    (02) 9288642

    Mines and Geosciences BureauRegion IVB MIMAROPA

    Mario A. CatarrojaOIC, Office of theRegional Director

    Bureau of Working Conditions (BWC)-Occupational Health and Safety Division,OSHC Complex, North Avenue, Cor. Scienceroad, Diliman, Quezon City

    Dir. Ma. Brenda L.VillafuerteDirector

    (02)920-2585(02)920-2381

    Bureau of Working ConditionBWC-DOLE, Region IVB

    Josefino I. TorresRegional Director

    PNP Western Command

    Puerto Princesa, Palawan

    Tirso R. Danga

    Vice Admiral

    2.1.3 MEDIA RELATION POLICY

    In the event of an emergency, only the President or his designated spokesperson

    is authorize to give information to the public in behalf of the company. No other

    person is allowed to disseminate information regarding the incident.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    17/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 17 of 97

    Rev No. Start Date Doc No. Page

    2.2 Emergency Alerting Procedures

    The Coral Bay Nickel Corporation High Pressure Acid Leach Project maintains a

    state-of-the-art system to alert the employees and other people concerned in an

    emergency.

    In case of Fire, the fire alarm system will be automatically activated. The sound will

    immediately warn people of the fire and signal the start of evacuation procedures.

    Fire fighting team will be activated.

    Notification procedures vary depending on the magnitude of the situation. Bigger

    events will call for more people involvement. In case of a serious or facility-wide

    emergency, the appropriate means of notification is through the paging system and

    the activation of the siren.

    In case of gas leakage, detectors located at strategic locations activates the gas

    alarms to warn all personnel of the emergency. Corresponding announcementsthrough paging system follows.

    Reporting of any other type of emergency shall be done using telephones or mobile

    phones and handheld radios. , Telephone directories shall likewise be placed in

    strategic areas accessible to all employees.

    For handheld radios, channel 9 is designated as emergency channel.

    2.3 Evacuation and Personnel AccountabilityCertain emergencies may require the evacuation of all or part of the facility. An

    early warning system will effect a safe and timely evacuation and will communicate

    the perilous situation to all personnel concerned.

    The following procedures apply to all evacuations.

    The Hydrometallurgical Processing Plant site complex area has designated three

    (ABC) Safety Zone Headquarters depending on the wind direction. One is located

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    18/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 18 of 97

    Rev No. Start Date Doc No. Page

    at the northwest portion of the plant site (A), another is at the Southwest portion (B)

    and at the Northeast portion (C). Announcement thru the paging system will be

    done three times to inform everybody of the designated safety zone headquarters.

    In case of evacuation, employees are to leave the area by the designated route to

    the designated evacuation point.

    Upon arrival at the designated evacuation point, the employee reports directly to his

    supervisor. The supervisor does a head count of all employees under his

    supervision and reports missing personnel and location last seen to the Department

    Managers who will then report to the Plant Manager.

    2.3.1 EMERGENCY RESPONSE TEAM HEAD (PLANT MANAGER)

    a. Immediately after confirming any emergency call from the Department

    Manager concerned or from the Safety Section Head, ERT Head shall

    immediately order the various team leaders to gather pertinent data and other

    information necessary for an investigation. The team shall lay out plans to

    control the situation.

    b. The team shall inspect and report on hazards to personnel, particularly the

    possibility of explosion, fire, leakage, presence of harmful gases or liquids and

    collapsing structures.

    c. All employees shall be informed of hazardous situations immediately on orders

    of the ERT head.

    d. Assist in the evacuation of personnel from hazardous situations.

    2.3.2 OPERATION TEAM

    a. Coordinates with the ERT Head, pertaining to the emergency.

    b. Takes full responsibility on operational emergency procedures

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    19/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 19 of 97

    Rev No. Start Date Doc No. Page

    c. Provide heavy equipment such as wheel loaders, bulldozers, and

    backhoes for clearing and emergency rescue work

    2.3.3 FIRE FIGHTING AND FIRST AID TEAM

    a. Immediately proceeds to the assembly area upon the first call for instructions.

    b. Stays at assembly area and wait for further instruction depending on the

    situation.

    c. Fire fighting team to be activated only should there be fire.

    d. First aid team to be readied all the time in any type of emergency.

    2.3.4 UTILITIES/ENGINEERING TEAM

    a. Provide temporary electrical lighting and power as required.

    b. To maintain electrical power supply necessary at the disaster areas.

    c. Clear or barricade weakened structures, which pose danger.

    d. Coordinate with Emergency Response Team.

    e. Supply engineering information such as plant layout, piping and wiring

    drawings as required.

    f. Conduct thorough investigation of disaster and record all pertinent

    information.

    2.3.5 GUIDANCE AND PUBLIC RELATIONS TEAM

    a. Provide transportation as required.

    b. Should transport injured persons, without any delay, to a designated first aid

    station for treatment.

    c. Maintain enough number of service vehicles available for use anytime.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    20/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 20 of 97

    Rev No. Start Date Doc No. Page

    d. Coordinates with the nearby communities and persons affected for proper

    evacuation

    e. Determine the status of all personnel affected by the disaster. Gather

    information on injured personnel or any fatalities.

    f. Notify promptly the next of kin of all affected employees.

    g. Under supervision from the Plant Manager, maintain exclusive channel of

    communication with public news media. Deal with all inquiries from the general

    public.

    h. Accommodate evacuees at Evacuation Center and provide food services as

    may be required.

    i. Coordinates with the Medical Team in case victims are to be brought to the

    hospital.

    2.3.6 MONITORING TEAM

    a. Makes communication with ERT Head with regards to the affected areas in

    the vicinity of the plant and the other impact areas.

    b. Assists the Public Relations Team in the efficient evacuation of nearby

    residents

    c. Reports from time to time the situation at different monitoring areas until it

    is proclaimed safe.

    2.3.7 MEDICAL TEAM

    a. Provides medical treatment to the injured.

    b. Arranges hospitalization of seriously injured persons.

    c. Coordinates in the operation of Rescue Team on First Aid procedures

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    21/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 21 of 97

    Rev No. Start Date Doc No. Page

    2.3.8 LOG RECORDER

    a. Records the sequence of events of the occurrence of an emergency.

    b. Keep records of the account of the emergency for future references.

    c. Documents emergency drills and exercises.

    3 EMERGENCY PROCEDURES

    3.1 H2S Gas Leak

    Hydrogen sulfide gas (H2S) handling is one of the most deadly occupational

    hazards. When H2S gas is inhaled, it is rapidly absorbed by the lungs into the

    blood, which initially induces rapid breathing. This is followed by respiratory

    inactivity. At higher concentration, H2S exerts an immediate paralyzing effect on the

    respiratory centers. Death due to asphyxia is a certain outcome, unless artificial

    respiration is promptly provided. This sequence of events represents the mostimportant toxic effect of H2S.

    Hydrogen sulfide in low concentrations is easily recognized by its characteristic foul

    odor similar to rotten eggs. However, continued exposure will temporarily deaden

    ones ability to smell the gas. This leads to the person believing that the gas is

    gone when probably it is still there. Therefore, a person should always check with

    the gas detectors for actual gas concentration in the atmosphere.

    To determine the presence of H2S within the plant site complex area, thirty

    four (34) H2S Gas detectors were strategically installed and linked to the DCS

    at the Central Building.

    PPEs must be maintained in good working condition and made available at all

    times. These include self-contained air breathing apparatus (SCABA), half mask

    respirators, safety glasses, safety gloves, safety boots, safety shoes, and water

    washing equipment. The mask must have good fit with all face types.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    22/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 22 of 97

    Rev No. Start Date Doc No. Page

    3.1.1 EMERGENCY EQUIPMENT

    Table 5 Emergency Equipment

    EquipmentGOB

    No. of Units

    PSO

    No. of Units

    Bullhorn or Megaphone 2 3

    H2S Portable Meter 1

    Badge Type H2S Meter 2 8

    First Aid Kit 2 5

    Radio Transceivers 12 1

    Self-Contained Air Breathing Apparatus

    (SCABA) with Cylinders12

    Air Line Mask 2

    First Aid Kit 3 3

    White Board 3 9

    3.1.2 ALARM SYSTEM

    If there is H2S Gas leakage detected by the H2S Gas detectors, the alarm

    in the DCS room and the siren are automatically activated. A continuous loud

    siren sound will be heard all over the plant site area (see Appendix 9 for the

    location of the paging speakers)

    3.1.3 H2S GAS LEAK AT THE H2S HOLDER

    Table 6 Phases/Stages during Leak at the H2S Holder

    H2S Gas Concentration Description/ Activities

    Process Area: 5 ppmOutside Proc. Area: 1ppm

    DCS Alarms.The Production Manager per DCS operators information informsthe Plant manager.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    23/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 23 of 97

    Rev No. Start Date Doc No. Page

    H2S Gas Concentration Description/ Activities

    Plant site1st Stage:Process Area: 5- 29 ppmOutside Proc. Area:1- 9 ppm2nd Stage:Process Area:>30ppmOutside Proc. Area >10ppm(Local Dectector Alarm)

    1st Stage : Emergency Procedure activated. Each EmergencyResponse Team on standby.

    2nd Stage: All personnel evacuate from the buildings to the SafetyZone

    RTNMC WS/Upper Kinurong> 1 ppm

    1. The local community residents (Kinurong) are evacuated toRTNMC Town site

    2. RTNMC employees,Radar Personnel and BCI / PSSIcompound personnel are evacuated to Town site

    1. For DCS Operator

    a. Informs MS Supervisor of the detected gas concentration inside the

    H2S Holder through the DCS monitors.

    b. The DCS operator announces through the paging system that H2S gas

    leaked at the H2S gas holder and instructs all employees at the MS and

    H2S plant areas to evacuate their respective areas immediately upon

    instruction from the Production Supervisor. This announcement is

    repeated 3 times (English and Filipino).

    c. The DCS operator reports the situation to the Production Supervisor.

    He feeds back actual gas concentration per DCS Monitor regularly

    d. At a concentration of 10ppm, the DCS operator, upon receiving order

    from the Production Supervisor who went to the H2S Gas holder to get

    actual reading, will then push water spray switch to on position.

    e. The DCS Operator (Production) initiates the operation of the following

    upon order from Production Supervisor

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    24/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 24 of 97

    Rev No. Start Date Doc No. Page

    1. Decrease or put flow at necessary rate to empty H2S gas

    holder the soonest time possible.

    2. H2S plant emergency shutdown bypassing emergency

    switch for H2S compressors

    f. The DCS Operator (Utilities) upon receiving order from the Utilities

    Superviso, puts operation to hot standby status.

    g. DCS Operator announces through the paging system the plant

    situation upon order form the Production Supervisor. This

    announcement is repeated three times.

    h. Upon order from Fire Fighting and First Aid Team Head, DCS operator

    calls attention of the members of firefighting and first aid teams to

    assemble at designated area.

    i. At a concentration of 30ppm, the DCS operator upon receiving the

    instruction of the Production Supervisor, announces to all employees

    and contractors through the paging system to evacuate to safety zone,

    which is to be determined depending on the wind direction. Emergency

    response teams are then advised to switch to channel 9, designated as

    emergency channel. This announcement shall be repeated three times

    in English and Tagalog.

    j. The DCS Operator wears his SCABA and proceeds to the Safety

    Zone for the Roll Call after emptying H2S Holder and putting operation

    to shutdown mode.

    2. For MS Shift Foreman and H2S Operator

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    25/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 25 of 97

    Rev No. Start Date Doc No. Page

    a. Upon getting information from the DCS Operator that H2S leak occurred

    at the H2S gas holder, the H2S operator immediately evacuates to the

    H2S Utility DCS Room. The MS Shift Foreman brings a radio

    transceiver, together with the H2S Operator, immediately wears their

    SCABA, proceeds to the H2S gas holder, and checks the H2S gas

    holder concentration.

    b. At a concentration of 10ppm, the MS Shift Foreman confirms it to the

    DCS Operator and informs Production Manager

    c. At a concentration of 30ppm, the Production Supervisor confirms to the

    DCS operator and informs Production Manager.

    d. The Production Supervisor, upon instruction of the Production Manager,

    activates the NaOH spray and evacuates to Central Building with H2S

    Operator.

    e. Upon hearing the announcement to evacuate to safety zone, Production

    Supervisor and H2S Operator proceed to safety zone and reports for

    the roll call.

    3. For Production Manager

    a. Upon getting information from Production Supervisor, Production

    Manager immediately proceeds to the Central Building DCS Room or

    advises Production Supervisor of necessary actions to be done.

    b. At a concentration of 10ppm, Production Manager informs the Plant

    Manager.

    c. Production Manager instructs the DCS Operator to announce first

    step emergency procedures.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    26/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 26 of 97

    Rev No. Start Date Doc No. Page

    d. At a concentration of 30ppm, the Production Manager instructs

    Production Supervisor to activate the NaOH spray and evacuate to

    safety. He then reports the situation to Plant Manager. After this, he

    instructs the DCS Operator to announce Emergency Evacuation.

    e. Upon establishing the Safety Zone Headquarters, the Production

    Manager instructs the MS Shift Foreman and DCS Operator to monitor

    gas concentration at the Utility building.

    f. Upon the report of the Guidance and Monitoring Team Head that the

    Upper Kinurong gas concentration is greater than 1ppm, the Production

    Manager immediately reports information to the Plant Manager.

    4. For General Affairs Manager and Guidance Team Members

    a. At a gas concentration of 10ppm, the General Affairs Manager

    proceeds to the Central Building DCS Room.

    b. Upon the announcement by the DCS Operator, that the first stage

    emergency procedure effects, the guidance and monitoring team

    assembles at the General Office Building.

    c. At a gas concentration of 30ppm, the Plant Manager instructs the

    monitoring team to proceed to assigned monitoring stations. Monitoring

    team head dispatches members to assigned monitoring stations

    d. Each member of the Guidance and Public Relations Team and

    Monitoring Team proceed to their respective stations and reports to

    respective team heads upon reaching their posts.

    e. The Monitoring Team Head instructs the personnel assigned at the

    RTNMC WS to get reading of H2S gas concentration.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    27/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 27 of 97

    Rev No. Start Date Doc No. Page

    f. Upon receiving the information that the gas concentration at RTNMC

    Warehouse is over 1ppm, the Monitoring Head Team reports the

    information to the Plant Manager who also instructs the Guidance and

    Public Relations Team Head to instruct RTNMC management and the

    Radar Station to evacuate their personnel immediately to the RTNMC

    Town site.

    g. Upon receiving the information that the gas concentration at the Upper

    Kinurong is over 1ppm, the General Affairs Manager instructs the

    Guidance and Public Relations Team to evacuate residents of BCI and

    PSSI compounds to RTNMC Town site.

    h. Using CBNC Service Bus, the assigned Guidance and Public Relations

    team member supervises the transport of residents to RTNMC Town

    site and upon arrival, reports to the Guidance and Public Relations

    Team Head that all residents have already been evacuated.

    5. For Plant Manager

    a. Upon hearing the siren and the announcement of the Production

    Manager, the Plant Manager immediately proceeds to the General

    Office Building.

    b. At a gas concentration of 10ppm, the Plant Manager instructs all

    managers to initiate emergency procedures.

    c. At a gas concentration of 30ppm, the Plant Manager instructs all

    managers to evacuate all personnel.

    d. Upon establishing the Safety Zone Headquarters, the Plant Manager

    observes proper monitoring of personnel at the evacuation site.

    e. Upon knowing that the gas concentration at RTNMC WS is over 1ppm,

    the Plant Manager instructs the General Affairs Manager to instruct

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    28/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 28 of 97

    Rev No. Start Date Doc No. Page

    RTNMC management and the Radar Station to evacuate their

    personnel immediately to the Town site.

    f. Upon knowing that the gas concentration at the Upper Kinurong is over

    1ppm, the Plant Manager instructs the General Affairs Manager to

    evacuate residents to RTNMC Town site.

    6. For Members of the Fire Fighting and First Aid Team

    a. Upon the declaration of the Emergency Procedures, the fire fighting and

    first aid team proceeds to the designated assembly area.

    b. Stay at the site and wait for further instruction, or depends on actual

    situation. Fire fighting team is to be activated if fire occurs and first aid

    team is to be activated if injured person/s is/are noticed.

    7. Maintenance Team Head

    a. Coordinates with maintenance contractors in case of evacuation.

    8. For All Other Employees

    a. At a gas concentration of 30ppm and upon the announcement to

    evacuate to safety zone, all employees evacuate to the evacuation

    area.

    b. Stay at the headquarters and to be counted during the employee roll

    call.

    3.1.4 H2S GAS LEAK AT THE AREA OTHER THAN THE H2S HOLDER

    (Similar procedure for H2S Gas Leak at H2S Gas Holder)

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    29/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 29 of 97

    Rev No. Start Date Doc No. Page

    3.1.5 CLEARANCE/ LIFTING OF THE EMERGENCY

    If H2S gas in Upper Kinurong Area is no longer detected

    a. If H2S gas concentration at the Upper Kinurong, RTN Assay Lab area can

    no longer be detected, the Monitoring Team assigned to get the reading

    reports the information to the Monitoring Team Head, who also reports the

    information to the Plant Manager.

    b. The Plant Manager, upon getting the information tells the Guidance and Public

    Relations Team to inform evacuated residents that the emergency is cleared.

    c. The Guidance and Public Relations Team upon getting this instruction informs

    the residents to go home, in coordination with the Barangay officials. CBNC

    service bus available transports back the residents.

    If H2S gas in RTNMC Workshop Area is no longer detected

    a. If H2S gas concentration at the RTNMC Workshop area can no longer be

    detected, the Monitoring Team member assigned to get the reading reports

    the information to the Plant Manager.

    b. The Plant Manager, upon getting the information declares that the emergency

    is over and orders the emergency headquarters to be disbanded.

    c. Guidance and Public Relations Team informs RTN Management of the

    situation.

    d. The fire fighting team returns the fire truck to the firefighting equipment-parking

    area.

    e. Other employees who evacuated to the Safety Zone Headquarters return to

    their respective work areas.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    30/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 30 of 97

    Rev No. Start Date Doc No. Page

    3.1.6 H2S EMERGENCY PROCEDURES - NIGHT SHIFT and HOLIDAYS

    DCS operator, upon the alarm of the DCS Monitor, shall follow the following

    procedures:

    a. With the corresponding stages of the gas concentration, follow the established

    procedures as if it happens during the day shift.

    b. Using the radio, the DCS Operator shall call the concerned Shift Supervisor forimmediate information and for immediate information to the Production

    Manager.

    c. Production Manager informs Plant Manager who will then inform also other

    department managers.

    d. If the gas concentration persists to rise reaching 10ppm, members of the

    Emergency Organization are immediately notified through their cellular phones

    and proceeds to the plant site for the next step following the established

    procedures.

    1. Plant Manager (Station at JTA), town site.

    a. Upon receipt of the report, gives instruction and dispatches emergency

    response team

    b. Maintains communication links

    c. Proceeds to Plant site/General Office Building for the next procedure to

    follow

    2. Guidance and Public Relations Team

    a. Upon receiving the information from DCS Operator, proceed to JTA

    to secure vehicle

    b. Receive instruction from the Plant Manager

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    31/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 31 of 97

    Rev No. Start Date Doc No. Page

    c. Proceed to Plant site for the next step following the established

    procedure

    3.2 Acid Leak

    Sulfuric Acid (H2SO4) is the main acid utilized in the HPAL operations of CBNC.

    Hazardous materials like this acid can cause unreasonable risks to health, safety or

    property when it leaks.

    3.2.1 ACID LEAK FROM THE PIPELINE (PLANT SITE)

    1. DCS Operator

    a. Obtain from the caller the exact location and nature of the problem.

    b. Inform shift supervisor for possible stoppage of acid pumps

    c. Inform the Operation Team Head (Production Manager) as reported by

    the caller.

    2. Operation Team Head (Production Manager)

    a. Upon receiving the information from the DCS operator, he informs the

    HPAL Foreman to proceed to the location where the leak was reported.

    b. He directs actions of the Acid Leak Response Team members.

    c. Provide for the proper clean-up and removal of spilled chemicals.

    d. He informs the ERT Head (Plant Manager) of the present condition of

    the leak.

    3. Acid Leak Response Team members

    a. Proceeds immediately to the location where the leak was reported with

    complete personal protective equipment and necessary equipment

    needed including but not limited to pH paper, vacuum trucks, sand

    bags, shovels, etc.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    32/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 32 of 97

    Rev No. Start Date Doc No. Page

    b. Upon arrival, report by radio and give an initial assessment of the

    situation such as:

    o Estimate of quantity spilled and rate of release if continuing

    o Source and cause of the acid leak

    o Location of leak and direction of spread if moving

    o Securing the area by installing barricade and/or sandbags if canals

    are affected.

    c. For small spills, cover with lime or limestone to neutralize the acid and

    prevent corrosion of metals and formation of hydrogen gas while for

    large spills, dikes or ditches must be closed before the spills reach to

    the dikes or ditches.

    d. Wash the spills with water to a proper drain.

    e. After leak has been stopped and spill contained, effect appropriate acid

    recovery procedures.

    4. ERT Head (Plant Manager)

    a. Responds to the reported acid leak and direct the actions of the other

    members of the Emergency Response Team.

    b. Ensure that the necessary actions such as leak stoppage, containment

    and recovery are initiated.

    c. Gets update from the Operation Team Head (Production Manager) of

    the present condition of the leak.

    d. Ensures proper clean-up and removal of acid spill.

    3.2.2 ACID LEAK FROM THE PIPELINE (PIER SITE)

    1. The Person who discovers the Acid Leak_______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    33/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 33 of 97

    Rev No. Start Date Doc No. Page

    a. Informs unloading leader to stop the acid pump.

    b. Informs Pier Site Logistics Section Head (Acid Leak Team Sub-leader)

    the exact location and nature of the problem.

    2. The Acid Leak Team Sub-Leader

    a. Assesses the extent of the leak and inform the Acid Leak Pier Site

    Team Head (Purchasing and Logistics Manager).

    3. Acid Leak Response Team members

    a. Upon receiving the information from the Acid Leak Team Sub-Leader,

    proceeds immediately to the location where the leak was reported.

    b. Upon arrival, report by radio and give an initial assessment of the

    situation such as:

    a. Estimate of quantity spilled and rate of release if continuing

    b. Source and cause of the acid leak

    c. Location of leak and direction of spread if moving

    c. For small spills, cover with lime or limestone to neutralize the acid and

    prevent corrosion of metals and formation of hydrogen gas while for

    large spills, dikes or ditches must be closed before the spills reach to

    the dikes or ditches.

    d. Wash the spills with water to a proper drain.

    e. After leak has been stopped and spill contained, effect appropriate acid

    recovery procedures.

    4. Acid Leak Pier Site Team Head (Purchasing and Logistics Manager)

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    34/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 34 of 97

    Rev No. Start Date Doc No. Page

    a. Upon receiving the information from the Acid Leak Team Sub-Leader,

    he directs actions for the reinforcement of the Acid Leak Response

    Team members (from plant site), if needed.

    b. Provide for the proper clean-up and removal of spilled chemicals.

    c. He informs the ERT Head (Plant Manager) of the present condition of

    the leak.

    5. ERT Head (Plant Manager)

    a. Responds to the reported acid leak and direct the actions of the other

    members of the Emergency Response Team.

    b. Ensure that the necessary actions such as leak stoppage, containment

    and recovery are initiated.

    c. Gets update from the Acid Leak Pier Site Team Head (Purchasing and

    Logistics Manager) of the present condition of the leak.

    d. Ensures for the proper clean-up and removal of spilled acid.

    3.2.3 ACID LEAK FROM THE LORRY (PLANT SITE)

    1. DCS Operator

    a. Obtain from the caller the exact location and nature of the problem.

    b. Inform the Operation Team Head (Production Manager) as reported by

    the caller.

    2. Operation Team Head (Production Manager)

    a. Upon receiving the information from the DCS operator, he informs the

    HPAL Foreman to proceed to the location where the leak was reported.

    b. He directs actions of the Acid Leak Response Team members.

    c. Provide for the proper clean-up and removal of spilled chemicals._______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    35/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 35 of 97

    Rev No. Start Date Doc No. Page

    d. He informs the ERT Head (Plant Manager) of the present condition of

    the leak.

    3. Acid Leak Response Team members

    a. Proceeds immediately to the location where the leak was reported.

    b. Upon arrival, report by radio and give an initial assessment of the

    situation.

    c. Prepare containers beside the Acid Lorry and contain the acid leaking

    towards the containers.

    d. If there is danger of the spill spread, coordinate with other members of

    the Acid Leak Team to layout additional spill booms and blocking of

    acid spread.

    e. After leak had stopped and contained, effect appropriate acid recovery

    procedure.

    f. For small spills, cover with lime or limestone to neutralize the acid and

    prevent corrosion of metals and formation of hydrogen gas while for

    large spills, dikes or ditches must be closed before the spills reach to

    the dikes or ditches.

    g. Wash the spills with water to a proper drain.

    In case leak at the acid lorry is noted at Plantsite, it will then not be allowed

    to travel back to piersite. Instead, it will be referred to Maintenance

    Department for repair. Basically, a round check after unloading is conducted

    before giving go signal to travel back to Piersite.

    4. ERT Head (Plant Manager)

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    36/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 36 of 97

    Rev No. Start Date Doc No. Page

    a. Responds to the reported acid leak and direct the actions of the other

    members of the Emergency Response Team.

    Emergency Response Team are as follows:

    First Aid Team - will immediately attend to the victim by giving first aid

    treatment and prepare the victim for transport for on the RTNFI Hospital.

    Acid Leak Team will immediately cordon the area affected while other

    member prepare the necessary equipments for the clean-up.

    Public Relation Team will immediately coordinate to the local barangay

    regarding the up to date situation and will ask assistance to the barangay

    to assist them in crowd control.

    Fire Fighting Teamwill be on stand-by status in the area in case the need

    arises.

    b. Ensure that the necessary actions such as leak stoppage, containment

    and recovery are initiated.

    c. Gets update from the Operation Team Head (Production Manager) of

    the present condition of the leak.

    d. Ensures proper clean-up and removal of spilled acid.

    3.2.4 ACID LEAK FROM THE LORRY (PIER SITE)

    1. The Person who discovers the Acid Leak

    a. Informs the Pier Site Logistics Section Head (Acid Leak Team Sub-

    leader) the exact location and nature of the problem.

    b. Requests to stop loading activity as needed.

    2. The Acid Leak Team Sub-Leader

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    37/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 37 of 97

    Rev No. Start Date Doc No. Page

    a. Assesses the extent of the leak and inform the Operation Team Head

    (Procurement and Logistic Manager). In addition, the latter will inform

    Plant Manager.

    b. Directs action of acid leak response team member

    3. Acid Leak Response Team members

    a. Proceeds immediately to the location where the leak was reported.

    b. Upon arrival, report by radio and give an initial assessment of the

    situation.

    c. Prepare containers beside the Acid Lorry and contain the acid leaking

    towards the containers. Acid can also be transferred to empty lorry.

    d. If there is danger of the spill spread, coordinate with other members of

    the Acid Leak Team to layout additional spill booms and blocking of

    acid spread.

    e. After leak had stopped and contained, conduct appropriate acid

    recovery.

    f. Cover small spills with lime or limestone to neutralize the acid and

    prevent corrosion of metals and formation of hydrogen gas.

    g. Wash the spills with water to a proper drain.

    4. ERT Head (Plant Manager)a. Responds to the reported acid leak and direct the actions of the other

    members of the Emergency Response Team.

    Emergency Response Team are as follows:

    First Aid Team - will immediately attend to the victim by giving first aid

    treatment and prepare the victim for transport for on the RTNFI Hospital.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    38/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 38 of 97

    Rev No. Start Date Doc No. Page

    Acid Leak Team will immediately cordon the area affected while other

    member prepare the necessary equipments for the clean-up.

    Public Relation Team will immediately coordinate to the local barangay

    regarding the up to date situation and will ask assistance to the barangay

    to assist them in crowd control.

    Fire Fighting Teamwill be on stand-by status in the area in case the need

    arises.

    b. Ensure that the necessary actions such as leak stoppage, containment

    and recovery are initiated.

    c. Gets update from the Operation Team Head (Production Manager) of

    the present condition of the leak.

    d. Ensures proper clean-up and removal of spilled acid.

    3.2.5 ACID LEAK FROM THE LORRY (MACADAM ROAD)

    1. The person who discovers the leak shall:

    a. As much as possible call the attention of the acid lorry driver or thedriver of the escort truck.

    b. Immediately informs guards at the nearest location of thesituation.

    2. The escort truck driver

    a. Informs RTN Supervisor of the situation

    b. Calls the attention of the acid lorry driver.

    c. Dumps limestone to affected area.

    3. Acid lorry driver

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    39/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 39 of 97

    Rev No. Start Date Doc No. Page

    a. Parks the lorry at the side of the road where there are less pedestrians.

    b. Informs RTN MH Supervisor

    c. Makes initial barricading of the area.

    d. Assists in the traffic situation.

    4. RTN MH Supervisor

    a. Immediately informs PLD Supervisor of the situation

    b. Proceeds to the area to assist.

    5. PLD Supervisor / Manager

    a. Immediately informs PLD Manager, who immediately informs the Plant

    Manager and other department managers.

    b. Proceeds to the area to assess the situation

    c. Calls Safety Office to assist in barricading the area.

    6. The Acid Leak Team Sub-Leader

    a. Assesses the extent of the leak and inform the Operation Team Head

    (Procurement and Logistic Manager). In addition, the latter will inform

    Plant Manager.

    b. Directs action of acid leak response team member

    7. Acid Leak Response Team members

    a. Proceeds immediately to the location where the leak was reported.

    b. Upon arrival, report by radio and give an initial assessment of the

    situation.

    c. Prepare containers beside the Acid Lorry and contain the acid

    leaking towards the containers. Acid can also be transferred to empty

    lorry.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    40/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 40 of 97

    Rev No. Start Date Doc No. Page

    d. If there is danger of the spill spread, coordinate with other

    members of the Acid Leak Team to layout additional spill booms and

    blocking of acid spread.

    e. After leak had stopped and contained, conduct appropriate

    acid recovery.

    f. Cover small spills with lime or limestone to neutralize the

    acid and prevent corrosion of metals and formation of hydrogen gas.

    g. Wash the spills with water to a proper drain.

    8. ERT Head (Plant Manager)

    a. Responds to the reported acid leak and direct the actions of the other

    members of the Emergency Response Team.

    b. Ensure that the necessary actions such as leak stoppage, containment

    and recovery are initiated.

    c. Gets update from the Operation Team Head (PLD Manager) of the

    present condition of the leak.

    d. Ensures proper clean-up and removal of spilled acid.

    3.3 Power Failure

    The Coral Bay Nickel Corporation Hydrometallurgical Processing Plant in any

    eventuality may experience power failure due to tripping of the Steam Turbine

    Generator (STG) or any other possible causes.

    To be able to address this kind of an emergency situation, there is a need to

    establish emergency procedures to continue the operation of important plant

    facilities while some other lesser important facilities are sequentially shut

    down.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    41/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 41 of 97

    Rev No. Start Date Doc No. Page

    As soon as the electric power is cut off, emergency generators automatically start.

    After 40 seconds from power cut-off, the first emergency generator supplies power

    and then the second generator synchronizes to the first generator.

    During power failure, the following procedures shall be adopted:

    1. Utility DCS Room Operator shall:

    a. Immediately informs the Production Department through the Production

    DCS Operator that power failure has occurred. He then informs the Utility

    Superintendent about the situation.

    b. Check the starting condition of the emergency Generating Sets by

    confirming that the air compressors, raw water pump, cooling tower

    pump, cooling tower fan are in normal operating condition.

    c. Check the instrument air pressure, plant air pressure and raw water

    through the DCS. He coordinates with Production.

    d. Instructs key personnel to proceed to RTNMC Power Plant and start the

    emergency generating sets to restore electric power supply to RTNMC

    Town site.

    e. Opens the hand blow valve (HV-132) manually through the DCS and

    adjusts the pressure of the steam drum to 5 MPA or less. The High

    Pressure Steam of the boiler is likewise reduced.

    f. Instructs the Utility Operator to proceed to the local panel. Utility Operator

    will do the manual tripping of the turbine by pushing the Remote Trip

    button on the TCP.

    g. Instructs the Utility Operator to check the DC Oil Pump of the Steam

    Turbine Generator. Also to be checked are the following:

    1. Turbine Rotation (or RPM) has decreased.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    42/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 42 of 97

    Rev No. Start Date Doc No. Page

    2. Auxiliary Lube oil pump and the control oil pump have started

    automatically.

    3. The DC oil pump has already started at the Turbine Building.

    4. Lube oil pressure and control oil pressure are in normal operating

    condition.

    h. Instructs the operator to turn the Steam Turbine Generator. The Utility

    operator checks that the turning motor operates immediately after the

    turbine rotation has decreased. The turbine shaft shall also rotate slowly.

    He further checks on the lube oil pump pressure and control oil pressure

    are operating normally. The Utility Operator then closes the entrance

    valve of the Steam Turbine Generator and opens the drain valve.

    2. Production DCS Room Operator

    a. The DCS operator informs the Production Manager that Power failure

    occurred.

    3. Production Foremen and Shift Leaders

    a. The Foreman and Shift Leader see to it that water flushing of the

    pipeline from Ore Thickener Underflow pump to 02TK01 / 202TK01 is

    done. (Ore Preparation Area)

    b. The autoclave is boxed. (HPAL Area)

    c. Water flushing of suction and discharge line of each thickener underflow

    pump by using self-circulation line is done. (CCD/NTRL Area)

    d. Confirms scrubber operation (De-Zn / MS Areas)

    e. Confirms discharge valve of the Geho Pump (to tailings dam) is closed.

    (FNTRL)

    f. Inspects leakages that can cause environmental hazards. (Chemical)_______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    43/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 43 of 97

    Rev No. Start Date Doc No. Page

    g. Confirms H2S gas supply valve to the H2S Reactor is closed. (H2S

    Plant)

    4. Field Operators

    a. Inspect each equipment and/ or facilities. Inspect for spillages/ leakages

    (General)

    b. Conducts water flushing of the slurry feed pump. (HPAL)

    c. Confirms the valve for each reactor on the H2S Gas injection line is

    closed. (De-Zn/MS)

    5. Production Manager/ Utility Manager

    a. Informs the Plant Manager that the necessary measures to be taken

    during power failure are properly carried-out.

    3.4 Air Failure

    The CBNC Hydrometallurgical Processing Plant may experience air failure thereby

    affecting valve operations in the MS plant.

    To be able to address this kind of an emergency, there is a need to establish

    emergency procedures.

    When the air pressure goes down immediately reaching to 560KPaG of L alarm

    level, the following procedures shall be adopted:

    1. Utility DCS Room Operator

    a. Immediately informs the Production Department through the Production

    DCS Operator that plant air pressure is going down to 560KPaG of Low

    Alarm Level and requires production to reduce consumption. He then

    informs the Utility Superintendent about the situation.

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    44/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 44 of 97

    Rev No. Start Date Doc No. Page

    b. The supply of the Neutralization (NTRL) basin bubbling air shall be

    stopped when during the time of air pressure reduction, it is being used.

    c. If air pressure reaches to 500KPaG, the Utility DCS operator shall

    advise Production to stop their operation. However, in this shutdown

    operation, Production shall still proceed following standard operating

    procedures.

    d. If air pressure reaches to 400KPaG, the operator shall inform

    Production Dept. that Utility Section will stop Boiler and Turbine

    Operation. Operator stops the turbine manually. Production will proceed

    with the SOPs being followed properly. After such instructions,

    Production shall inform Utility that the shutdown operations were

    completed.

    2. Production DCS Room Operator

    a. The DCS operator informs Foreman or Shift Leader, and Production

    Manager that Air Failure occurred.

    3. Production Foremen and Shift Leaders

    a. The Foreman and Shift Leader see to it that valves on the Low

    Pressure and High Pressure water line closes. Stop ore feed to prevent

    ore clogging. To prevent clogging of ore thickener drain line, water flush

    the pump and stop. Confirm that there are no air leaks (Ore Prep

    Area).

    b. The autoclave is boxed. All feed types shall be stopped. Since some

    acid in the lance and feed slurry in the pipes can remain, once air

    pressure recovers, Nitrogen (N2) purging or raw ore water flushing as

    well as autoclave cooling shall be implemented. Since

    02HV130/202HV130 is closed, the vent line shall be opened and

    _______________________________________________________________________________________

    Printed versions are UNCONTROLLED except when stamped CONTROLLED COPY in blue

  • 7/28/2019 Emergency Response Preparedness Program (Cris)

    45/107

    Coral BayNickel Corporation

    EMERGENCY RESPONSE AND PREPAREDNESSPROGRAMDocument Title

    01 3/1/2011 EMS - 2004 45 of 97

    Rev No. Start Date Doc No. Page

    autoclave temperature is decreased to discharge pressure. While

    adjusting the manual valve for plant air to scrubber, decrease air

    volume. Pressure is set at 180 to 90KPaG to minimize effect on other

    areas (HPAL Area).

    c. When instrument air pressure decreases, there will be no problem

    indicated in the Pre-Neutralization Area. If limestone is needed, the by-

    pass line can be used. If flash tank overflow decreases and

    03TK13/203TK13 level drops, stop operation of 03PU08/203PU08.

    Check if air leaks occur. (Pre-NTRL Area)

    d. Control Valves must be closed and since there is a possibility of

    overflow from 03TK08/203TK03, the following measures are taken:

    Secure 03TK08/ 26TK01/ 26 PD01 lines; Close CCD overflow line

    valves starting from CCD 7. CCD 7 drain is the same as previously

    indicated but discharging operations to F- NTRL is stopped. When Pre-

    Neutralization slurry is stopped, CCD Underflow (U/F) pumps are

    stopped in order. Check for air leaks. (CCD Area)

    e. Discharge from the CCD and Chemical addition line is stopped, thus,

    NTRL needs to be stopped with the following measures: Flocculant

    supply is stopped. Coagulant supply is also stopped. Seed from CCD is

    also stopped. NTRL slurry discharge is adjusted to the barest minimum.

    Check for air leaks. (NTRL Area)

    f. H2S supply line valve is closed and the following measures are taken:

    Stop the flow from 04PU01/204PU01. Check for air leaks (De-Zn Area).

    g. The feed line to the reactor (including seed), H2S supply line, NaOH

    addition line to scrubber, gas and effluent discharge line and barren

    liquor discharge line will be closed. On the other hand, 06TH01 /


Recommended