+ All Categories
Home > Documents > Emerging Legal Issues Chuck Sensiba, Van Ness Feldman LLP Northwest Hydroelectric Association Annual...

Emerging Legal Issues Chuck Sensiba, Van Ness Feldman LLP Northwest Hydroelectric Association Annual...

Date post: 27-Dec-2015
Category:
Upload: hilary-murphy
View: 213 times
Download: 0 times
Share this document with a friend
Popular Tags:
19
Emerging Legal Issues Emerging Legal Issues Chuck Sensiba, Van Ness Feldman Chuck Sensiba, Van Ness Feldman LLP LLP Northwest Hydroelectric Association Annual Conference February 18, 2014
Transcript

Emerging Legal IssuesEmerging Legal IssuesChuck Sensiba, Van Ness Feldman LLPChuck Sensiba, Van Ness Feldman LLP

Northwest Hydroelectric Association Annual Conference Northwest Hydroelectric Association Annual Conference February 18, 2014

Key Cases and Orders

Simmons v. Sabine River AuthorityState of Louisiana, 732 F.3d 469 (5th Cir. 2013)

FFP Qualified Hydro 14, LLC,145 FERC ¶ 61,255 (2013)

Power Site Reservation Fees Group,142 FERC ¶ 61,196 (2013)

Simmons v. Sabine River AuthorityState of Louisiana, 732 F.3d 469

◘ In October 2013, the Fifth Circuit rules that state-law tort claims that seek to alter operations of a FERC-licensed hydro project are preempted by the Federal Power Act (FPA).

Simmons v. Sabine River AuthorityState of Louisiana, 732 F.3d 469

◘ Despite FPA § 10(c), which preserves state law claims for damages inflicted on the property of others, the Fifth Circuit held that state tort laws impeding FERC’s operational control over dam operations are preempted.

• Prior FERC proceeding

• FERC findings of fact

◘ Plaintiffs filed a Petition for a Writ of Certiorari with the U.S. Supreme Court on January 7, 2014.

FFP Qualified Hydro 14, LLC,145 FERC ¶ 61,255 (2013)

◘ FERC holds that municipal preference under FPA § 7(a) applies only to hydropower projects located in the “vicinity” of the municipality.

◘ Muni should receive preference to develop “nearby hydropower sites” but not in public interest to grant preference for project “far from the site of the municipality.”

◘ Muni in case was located almost 400 miles from the project site – deemed to be outside of vicinity.

FFP Qualified Hydro 14, LLC,145 FERC ¶ 61,255 (2013)

◘ Order ends FERC’s existing practice of applying muni preference to any state or municipal application for preliminary permit or original license without regard to location of project.

◘ Could significantly reduce the use of muni preference in future permitting and licensing decisions.

◘ Rehearing is pending. Project Nos. 13579 and 14491.

Power Site Reservation Fees Group,142 FERC ¶ 61,196 (2013)

◘ FERC holds that it will no longer assess annual charges for non-federal lands at hydropower projects that are subject to a federal power site reservation under FPA § 24.

◘ Changes longstanding FERC policy dating to 1981.

◘ Will result in significant reductions in federal land use annual charges for numerous projects, particularly in Alaska and other areas in the West.

Major Policy Initiatives

HREA Implementation

Columbia River Treaty Renewal

Implementation of Hydropower Regulatory Efficiency Act

◘ On August 9, 2013, the President signed into law H.R. 267, the Hydropower Regulatory Efficiency Act of 2013 (HREA).

◘ First energy law passed by Congress in more than 5 years.

◘ Significant update in FERC’s regulation of small hydropower development.

Implementation of Hydropower Regulatory Efficiency Act

◘ HREA provisions:• 2-Year Pilot Licensing Process: Mandated FERC to

investigate a 2-year licensing process for certain projects

• Qualifying Conduit Facilities: Created new class of 5 MW facilities that are excluded from FERC jurisdiction

• Extended Preliminary Permit Terms: Authorized FERC to extend by 2 years permit terms at its discretion

• Conduit Exemptions: Increased capacity limit (from 15 to 40 MW) for FERC conduit exemptions sought by non-municipalities

• Small Hydropower Exemptions: Increased the capacity limit (from 5 MW to 10 MW) for small hydro project exemptions

Implementation of Hydropower Regulatory Efficiency Act◘ Two-Year Licensing Process

◘ Eligible projects must:• (1) be located at a non-powered dam or be a closed-loop pump storage

project; • (2) cause little to no change to existing surface and groundwater flows and

uses; and • (3) be unlikely to adversely affect federally listed threatened and endangered

species.

◘ Additional Requirements for some projects: • Located at or will use a federal dam – include a letter from the dam owner that

the applicant’s plan of development is conceptually feasible• Use any public park, recreation area, or wildlife refuge established under state

or local law – include a letter from the managing entity indicating its approval of the site’s use for hydropower development

• Closed-loop pumped storage – not continuously connected to a naturally flowing water feature

Implementation of Hydropower Regulatory Efficiency Act

◘ Two-Year Licensing Process◘ Requests to use the 2-year licensing process must be filed between February 5 –

May 5, 2014.

◘ Requests must include:

• An adequate consultation record,• Pre-application document,• Proposed study plan,• Potential environmental impacts of the project, and• Process plan and schedule.

◘ Keys to Success:

• Solid project proposal• Early outreach to Federal and State regulators• Early outreach to FERC

◘ FERC staff has signaled a willingness to work with developers after the May 5th deadline to develop an efficient process.

Implementation of Hydropower Regulatory Efficiency Act

◘ Qualified Hydropower Conduit Facilities

• Qualifying Criteria Must use only the hydroelectric potential of a non-federally owned

conduit

Conduit must be operated for the distribution of water for agriculture, municipal, or industrial consumption and not primarily for the generation of electricity

Installed capacity does not exceed 5 MW

Facility is not licensed or exempted by FERC at time the law was enacted

Implementation of Hydropower Regulatory Efficiency Act

◘ Qualified Hydropower Conduit Facilities

• Statistics to Date: • 23 Notices of Intent to Construct Qualifying Conduit Facilities filed• 19 approved • 3 rejected (1 later re-filed and approved)• 1 is pending• FERC says average processing time is 63 days

Implementation of Hydropower Regulatory Efficiency Act

◘ Preliminary Permit Extensions• FERC may extend permits by two years (total of five years)

• Standard for extension (additional two years) is “good faith and with reasonable diligence”

No notice or opportunity for competing application, comment, or intervention

Issued very quickly Must be filed “not less than 30 days prior to the termination of the

permit.” 18 C.F.R. § 4.82

• FERC standard for successive permit “good faith and due diligence” Filed after expiration of existing permit Notice and opportunity for intervention and competing applications

Implementation of Hydropower Regulatory Efficiency Act

◘ Preliminary Permit Extensions• Appears as though FERC has applied same standard for extensions as

its long-standing standard for subsequent permits:• Case 1: In denying an extension, FERC found that the information

in progress reports was similar and doubts over economic viability of project.

• Case 2: In granting an extension, FERC noted that the permittee had conducted economic and financial analysis and filed its NOI, PAD, and request to use the TLP.

• It is unclear whether FERC will continue to issue successive permits, or whether it interprets the HREA to limit a permit term to no more than five years.

Columbia River BasinTreaty Renewal

◘ 1961 Treaty between United States and Canada.◘ Governs cooperative development and operation of

Columbia River basin water resources for flood control and power.

◘ Requires Canada to provide reservoir storage for flood control and generation, in exchange for one half of the downstream power benefits, delivered as energy and capacity, and currently valued between $250-350 million annually.

Columbia River BasinTreaty Renewal

◘ Either party can terminate Treaty on or after September 16, 2024, with minimum 10 years’ written notice (earliest notification date: September 16, 2014).

◘ On December 13, 2013, the U.S. Entity delivered its final recommendation to the U.S. Dept. of State.◘ Recommended renegotiation of a “modernized” Treaty that

addresses power production, flood risk management, and ecosystem-based function as the primary purposes of the Treaty.

◘ Next steps: Department of State coordinates federal, interagency review under direction of National Security Council on behalf of President.

For more information:For more information:

Chuck SensibaChuck [email protected]@vnf.com


Recommended