Dick Loveless Upgrade report 12 Oct 2012 1
EMU Upgrade Report
Dick LovelessUniversity of Wisconsin
12 October 2012
Dick Loveless Upgrade report 12 Oct 2012 2
ME4/2 Chambers• Chamber factory is operating reliably
• Chamber production rate ~1/week• Completed 19 chambers (out of 67 needed)• Chambers 211 – 218 in 2 month HV test• Chambers 219 and 220 in assembly area
211
212
213
216
214
215
217
218 219220
Dick Loveless Upgrade report 12 Oct 2012 3
Final Assembly & Testing• Final Assembly
• Add on-chamber electronics and cables• Assembly going well - ~1-2 days per chamber
• Testing• All CSCs go through a 2-month HV test (up to 4KV –
nominal HV is 3.6 KV)• On-chamber electronics tested -- 14 different tests
including trigger, gas gain, cosmic ray data• Completed 10 chambers – rate limitation is
production, not testing
Dick Loveless Upgrade report 12 Oct 2012 4
Chamber production chart
5/1/2012
5/18/2012
6/4/2012
6/21/2012
7/8/2012
7/25/2012
8/11/2012
8/28/2012
9/14/2012
10/1/2012
10/18/2012
11/4/2012
11/21/2012
12/8/2012
12/25/2012
1/11/2013
1/28/2013
0
5
10
15
20
25
30
35
producedexpected
Showing production rates for the 1st endcap (31 CSCs)
Dick Loveless Upgrade report 12 Oct 2012 5
ME1/1 Electronics I• ME1/1 Test Stand in B904
• 7 prototype DCFEBs have been installed & powered• Prototype LVDB board working fine• Cooling operational• Currents high - - roughly 50 amps per CSC• On-board temperatures ~30 C (reasonable)
• Currently reading DCFEBs using copper skewclear cables and old DMB (can only read 5 boards)
• Reading new TMB boards using optical fibers
Dick Loveless Upgrade report 12 Oct 2012 6
ME1/1 Electronics II• DCFEB boards
• Most firmware operational - - currently working on the firmware for ODMB to enable data transfer to ODMB
• FF_EMU ASIC• Currently does not work• Decision to focus effort on backup solution via Cu
• ODMB• Prototype board exists at CERN, needs firmware
• TMB• Received new firmware enabling full functionality
Dick Loveless Upgrade report 12 Oct 2012 7
ME1/1 Low Voltage
Design of LV system finalized• ME1/1 prototype test
working well• Layout of cables & power
supplies• Junction box prototype
under construction• 8 Maraton power supplies
ordered