Description:
EMU Upgrade Report. Dick Loveless University of Wisconsin. 12 October 2012. ME4/2 Chambers. Chamber f actory is operating reliably Chamber production rate ~1/week Completed 19 chambers (out of 67 needed) Chambers 211 – 218 in 2 month HV test Chambers 219 and 220 in assembly area . 211. - PowerPoint PPT Presentation
Popular Tags:
7
Dick Loveless Upgrade report 12 Oct 2012 1 EMU Upgrade Report Dick Loveless University of Wisconsin 12 October 2012
Transcript
Page 1: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 1

EMU Upgrade Report

Dick LovelessUniversity of Wisconsin

12 October 2012

Page 2: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 2

ME4/2 Chambers• Chamber factory is operating reliably

• Chamber production rate ~1/week• Completed 19 chambers (out of 67 needed)• Chambers 211 – 218 in 2 month HV test• Chambers 219 and 220 in assembly area

211

212

213

216

214

215

217

218 219220

Page 3: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 3

Final Assembly & Testing• Final Assembly

• Add on-chamber electronics and cables• Assembly going well - ~1-2 days per chamber

• Testing• All CSCs go through a 2-month HV test (up to 4KV –

nominal HV is 3.6 KV)• On-chamber electronics tested -- 14 different tests

including trigger, gas gain, cosmic ray data• Completed 10 chambers – rate limitation is

production, not testing

Page 4: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 4

Chamber production chart

5/1/2012

5/18/2012

6/4/2012

6/21/2012

7/8/2012

7/25/2012

8/11/2012

8/28/2012

9/14/2012

10/1/2012

10/18/2012

11/4/2012

11/21/2012

12/8/2012

12/25/2012

1/11/2013

1/28/2013

0

5

10

15

20

25

30

35

producedexpected

Showing production rates for the 1st endcap (31 CSCs)

Page 5: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 5

ME1/1 Electronics I• ME1/1 Test Stand in B904

• 7 prototype DCFEBs have been installed & powered• Prototype LVDB board working fine• Cooling operational• Currents high - - roughly 50 amps per CSC• On-board temperatures ~30 C (reasonable)

• Currently reading DCFEBs using copper skewclear cables and old DMB (can only read 5 boards)

• Reading new TMB boards using optical fibers

Page 6: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 6

ME1/1 Electronics II• DCFEB boards

• Most firmware operational - - currently working on the firmware for ODMB to enable data transfer to ODMB

• FF_EMU ASIC• Currently does not work• Decision to focus effort on backup solution via Cu

• ODMB• Prototype board exists at CERN, needs firmware

• TMB• Received new firmware enabling full functionality

Page 7: EMU Upgrade Report

Dick Loveless Upgrade report 12 Oct 2012 7

ME1/1 Low Voltage

Design of LV system finalized• ME1/1 prototype test

working well• Layout of cables & power

supplies• Junction box prototype

under construction• 8 Maraton power supplies

ordered