    The purpose of this procedure is to outline the sequence in

    preparing and handling Cost Request to solicit market prices of

    materials, equipments, sub-contract quotation needed to base

    competitive pricing of bid estimates.

    The procedure is also intended to generate information regarding

    current prices for major MMG supplied plant permanent materials,

    and equipment and to determine the availability, whether it is

    locally available or a foreign source.

    This procedure will also provide evaluation data to be used in theselection of proposed Subcontractors.

    The scope covers preparation of Cost Requests by the Engineering

    Department, requesting Central Purchasing Department Cost

    Request Section to solicit prices of materials and equipment.

    Contracts Department for securing quotations from possible

    subcontractors.

  • 7/30/2019 END 3 007 Cost Request

    3/13

    COST REQUEST

    Are forms originated by Engineering Estimating Sectionaddressed to Central Purchasing Department (CPD) Cost

    Request Section (Form No. END-4-007A) requesting to solicit

    current prices of identified Contractor Supplied materials or

    equipments from Suppliers not available in Engineering Files.

    Cost Request Form No. END-4-007D is used to requestquotation for subcontracted items addressed to Contracts

    Department.

    Product Data are material technical literature,

    specifications, brochures or other manufacturers material

    references.

    REFERENCES

    Engineering Estimating Procedure

    Procedure No. END-3-009

  • 7/30/2019 END 3 007 Cost Request

    4/13

    CHIEF ENGINEER

    Overall management of the Engineering Departmentfunctions.

    PROPOSAL MANAGER / ESTIMATING MANAGER

    Supervise the Bid development and Engineering

    Estimating, Approval of Cost Request.

    CENTRAL PURCHASING DEPARTMENT

    Solicit prices for materials and equipment.

    CONTRACTS DEPARTMENTSolicit subcontract quotation for requested

    subcontracted items from approved Subcontractors.

  • 7/30/2019 END 3 007 Cost Request

    5/13

    (continuation)

    ESTIMATING SUPERVISING ENGINEER

    Supervise respective engineering estimating

    discipline, Identify major contractor supplied material

    and subcontracted items.

    Check Cost Request and analyze quotations from CPD& Contracts.

    ESTIMATING ENGINEER

    Determine the material, equipment and subcontract

    item with no available current prices or quotations, andprepare the Cost Request.

  • 7/30/2019 END 3 007 Cost Request

    6/13

    Estimating Engineer prepares the Cost Request prior

    forwarding to the approval by the concerned Proposal

    Manager or Estimating Manager.Approved Cost Requests are forwarded via the Document

    Controller for recording in the Cost Request Transmittal

    Control Sheet (Form No. END-4-015C). The Document

    Controller prepares Transmittal Form No. QAD-4-202 and

    attached to the Cost Request, then it is forwarded to eitherCPD (for materials) or to Contracts Department (for

    Subcontractor)

    CPD then make the necessary communication with Material

    Suppliers to obtain material quotations or prices as

    requested in the Cost Request, Likewise, the ContractsDepartment make necessary contact with MMG or Client

    approved subcontractors to obtain quotations for the

    proposed subcontracted items described in the Cost

    Request.

  • 7/30/2019 END 3 007 Cost Request

    7/13

    (continuation)

    CPD if possible, to solicit three (3) Material Suppliers

    quotation for major MMG supplied permanent materials.Contracts Department to obtain, if possible at least three (3)

    quotations for Subcontracted items from approved

    Subcontractors.

    A minimum of five (5) days and maximum of ten (10) days is

    allotted to CPD or Contracts Department to process the CostRequest.

    Material price quotations from the Suppliers received by CPD

    or Work Quotations from Subcontractors received by Contracts

    Department are immediately forwarded to Engineering

    Department through the Engineering Document Controller. TheDocument Controller receives the above information, stamp

    date, and record in the control log book and subsequently

    forward the same to the concerned discipline Supervising

    Engineer and finally gven to the originator Estimating Engineer.

  • 7/30/2019 END 3 007 Cost Request

    8/13

    (continuation)

    As required by the Customer or where the Bid Contract

    specify for a ten (10) days period after the receipt ofNotice to Proceed on awarded project for Contractor to

    submit material Product Data for Customer approval, prior

    to purchase of Contractor supplied permanent materials,

    the following action should be made.

    Discipline Estimating Engineers during the bid estimateprepares the Proposed Product Lists using Form No. END-4-

    007B, for identified MMG supplied permanent materials for

    the specific project.

    The proposed Product List includes the detailed

    description of the material, material quantity, unit of

    measure and instructions, if required to obtain

    manufacturers or material product data for major

    permanent materials,

  • 7/30/2019 END 3 007 Cost Request

    9/13

    (continuation)

    The Proposed Product List is then forwarded to CPD to start

    soliciting the required product data for the anticipatedpotential projects.

    All Product Data obtained by CPD is forwarded to Engineering

    Department through the Engineering Document Controller who

    will then keep all the Product Data on his file until needed,

    until award of Contract for the specific project requirement.Upon award of Contract, the Engineering Department will

    immediately endorse all available product data to the assigned

    Engineering Project Task Force Supervising Engineer.

    The Engineering Supervising Engineer through the Project

    Manager will then submit the product data for all majorContractor supplied permanent materials to the Customer for

    approval within the ten (10) days period, subsequent to

    Contract award in conformance with the requirement of the

    Contract Document.

  • 7/30/2019 END 3 007 Cost Request

    10/13

    ENGINEERING DEPARTMENT

    TASK TITLE

    COST REQUEST

    (END-3-007)

    ESTIMATING ENGINEERS

    Prepare Cost Request for Material/ Subcontract Price Quotation

    (END-4-013A)

    Assign CR Control Number andprepare Transmittal

    (QAD-4-202 / END-4-015C)

    START

    A1End

    CPDDOCUMENT CONTROLLER

    DOCUMENT CONTROLLER

    Transmit Cost Request

    (END-4-007A-D)

    Prepare Cost Request(END-4-007B)

    If requires only

    ESTIMATING ENGINEERS

    CTD

    CPD / CTD

    Forward all solicitedQuotations and Technical

    Data to END

    Solicit Material PriceQuotation from approved

    material Suppliers

    CPD CTD

    Forward Quotation / TechnicalData to Estimating Engineers

    DOCUMENT CONTROLLER

    Solicit Subcontract PriceQuotation from approved

    Subcontractors

  • 7/30/2019 END 3 007 Cost Request

    11/13

    PROCEDURE FOR COST REQUEST =

    SOLICITING CURRENT MARKET PRICES FOR MMG SUPPLIED MATERIAL

    AND SUBCONTRACT ITEMS DURING BID DEVELOPMENT STAGE.

    PREPARATION OF COST REQUEST

    Estimating Engineers prepares Cost Request (CR) Form No. END-4-007A for

    MMG supplied material and/or Form No. END-4-007D for Subcontract Work

    Item requiring current market price estimate. The format shall include

    material or work description, quantity, unit of measure, date submitted, date

    required, referenced transmittal number, name & signature of originator, The

    provision for product data, Suppliers or Subcontractors brochures or

    company profile/date is specified in the CR (Form No. END-4-007B) will be

    submitted if required.

    Review / check the CR before forwarding to the approval by the concerned

    Proposal / Engineering Manager / Supervising Engineer.

    Approved CR is forwarded to Engineering Department (END) Document

    Controller (DC) for assigning of CR Control Number, Prepare Transmittal

    Form No. QAD-4-202 and record in Cost Request Transmittal Control Sheet

    (END-4-015C)

    END Document Controller transmits CR for MMG supplied material Form

    No. END-4-007A to CPD Cost Request Section.

    END Document Controller transmits CR for Subcontract Work Item Form

    No. END-4-007D to Contracts Department (CTD)

  • 7/30/2019 END 3 007 Cost Request

    12/13

    QUOTATION & TECHNICAL DATA

    COMING FROM CPD COST REQUEST SECTION

    Quotation and Technical Data to ENDEND Document Controller receives the Quotation &

    Technical Data and record in the Cost Request File.

    END Document Controller forward the Quotation and

    Technical Data to the Engineering Section Estimatorwho initiated the Cost Request.

    Receives the Quotation & Technical Data for his

    estimating requirement.

  • 7/30/2019 END 3 007 Cost Request