+ All Categories
Home > Documents > energizeEASTSIDE · energizeeastside Spring 2018 Puget Sound Energy, P.O. Box 97034, Bellevue, WA...

energizeEASTSIDE · energizeeastside Spring 2018 Puget Sound Energy, P.O. Box 97034, Bellevue, WA...

Date post: 24-May-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
2
energizeEASTSIDE project newsletter Spring 2018 pse.com/ energizeeastside Environmental review complete. The extensive, multi-year environmental review process wrapped up with publication of the Partner Cities’ Final Environmental Impact Statement (EIS). The nearly 5,000-page Final EIS affirms that the project can be safely built and operated and that by replacing poles and wires along the existing corridor, we limit impacts on Eastside communities. To learn more about the Final EIS, visit EnergizeEastsideEIS.org. Making plans for trees and envisioning the future. Spring is here, and we’re meeting with property owners along the existing corridor to develop landscape and tree replacement plans! These plans illustrate how we’ll restore yards and replace trees once the project is complete. Our goal is for there to be more trees when the project is complete, not fewer. Permitting process is underway. Permit applications for the southern portion of the project, which includes the new Richards Creek substation and the upgraded transmission lines in south Bellevue, Newcastle and Renton, are already under review by their respective cities. The next major permit applications to be submitted are for the northern portion of the project in Bellevue and Redmond. Once we have permits, construction will follow. Project construction will start with the southern portion, which is anticipated to begin later this year. Once the southern portion is complete, we’ll continue with construction of the northern portion. We’ll keep property owners and the community up to date on project progress. Conceptual Project Energize Eastside will replace poles and upgrade transmission lines along the existing utility corridor. To view more photo simulations of the current conditions and proposed project, visit our website. Existing Conditions Photo simulation in Bellevue 2018 is a big year for upgrading the Eastside's electric grid Energize Eastside uses the existing transmission line corridor that has served the Eastside for nearly a century. Detailed maps are available on our website. Redmond Bellevue Newcastle Renton Existing substation New substation Final route LEGEND N Map for illustrative purposes only.
Transcript

energizeEASTSIDEproject newsletter

Spring 2018pse.com/energizeeastside

Environmental review complete. The extensive, multi-year environmental review process wrapped up with publication of the Partner Cities’ Final Environmental Impact Statement (EIS).

The nearly 5,000-page Final EIS affirms that the project can be safely built and operated and that by replacing poles and wires along the existing corridor, we limit impacts on Eastside communities. To learn more about the Final EIS, visit EnergizeEastsideEIS.org.

Making plans for trees and envisioning the future. Spring is here, and we’re meeting with property owners along the existing corridor to develop landscape and tree replacement plans! These plans illustrate how we’ll restore yards and replace trees once the project is complete. Our goal is for there to be more trees when the project is complete, not fewer.

Permitting process is underway. Permit applications for the southern portion of the project, which includes the new Richards Creek substation and the upgraded transmission lines in south Bellevue, Newcastle and Renton, are already under review by their respective cities. The next major permit applications to be submitted are for the northern portion of the project in Bellevue and Redmond.

Once we have permits, construction will follow. Project construction will start with the southern portion, which is anticipated to begin later this year. Once the southern portion is complete, we’ll continue with construction of the northern portion.

We’ll keep property owners and the community up to date on project progress.

Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review

Existing Conditions

8/4/2017

Conceptual Project

Time

Viewing Direction

Date

Address

2:21 PM

Northwest

7/24/2017

13233 SE 51st Pl, Bellevue

Existing Pole Heights ~55 feet

Proposed Pole Heights ~65 feet

2KOP

SEGMENTCENTRAL 38

Conceptual Project

Energize Eastside will replace poles and upgrade transmission lines along the existing utility corridor. To view more photo simulations of the current conditions and proposed project, visit our website.

Photo simulations are for discussion purposes only and may change pending public, regulatory and utility review

Existing Conditions

8/4/2017

Conceptual Project

Time

Viewing Direction

Date

Address

2:21 PM

Northwest

7/24/2017

13233 SE 51st Pl, Bellevue

Existing Pole Heights ~55 feet

Proposed Pole Heights ~65 feet

2KOP

SEGMENTCENTRAL 38

Existing Conditions

Photo simulation in Bellevue

2018 is a big year for upgrading the Eastside's electric grid

Energize Eastside uses the existing transmission line corridor that has served the Eastside for nearly a century. Detailed maps are available on our website.

Redmond

Bellevue

Newcastle

Renton

Existing substation

New substation

Final routeLEGEND

NMap for illustrative purposes only.

Spring 2018pse.com/energizeeastside

Puget Sound Energy, P.O. Box 97034, Bellevue, WA 98009-9734

pse.com/energizeeastside

[email protected]

1-800-548-2614

Thank you for your interest in Energize Eastside.

Upgrading the grid to keep up with growthThe backbone of the Eastside’s electric grid was last upgraded in the 1960s. Since then, our population has grown eight-fold, and now the grid is being pushed beyond its capacity.

PSE’s Energize Eastside project will build a new substation and upgrade existing transmission lines in the existing transmission line corridor. With continued electric conservation, Energize Eastside will keep the lights on for years to come.

• For information about the project, including maps and photo simulations, visit pse.com/energizeeastside.

• To learn more about the Bellevue, Kirkland, Newcastle, Redmond and Renton Final Environmental Impact Statement (EIS), visit EnergizeEastsideEIS.org.

6945 04/18

As Energize Eastside continues through permitting and moves into construction this year, I want to thank the community for engaging with PSE on this critical project.

PSE’s core mission is to efficiently deliver safe, dependable electricity to homes, businesses and communities. Four years ago, our studies — confirmed by independent experts — revealed our transmission grid is strained today under peak conditions, just at the time when our customers need reliable power the most.

Community feedback has helped us understand customer concerns, shaped the project design, and guided our route decision. This engagement continues today through property owner conversations, stakeholder briefings and permitting meetings.

We appreciate the extensive dialogue and understand that building an infrastructure project of this magnitude has an impact on our communities. Yet, an unreliable electric grid affects everyone, including hospitals, first responders, schools, businesses and residents.

Energize Eastside will ensure reliable power for the Eastside’s innovative, growing communities.

Sincerely,

Booga GilbertsonSenior Vice President of Operations, PSE

Thank you to our customers

A reliable transmission grid is vital for:

• Critical services

• Quality of life

• Economic development

• Modern, digital world


Recommended