Date post: | 30-Dec-2015 |
Category: |
Documents |
Upload: | collin-day |
View: | 213 times |
Download: | 0 times |
Energy aspects of the North-European region
Presentation to the Northern Dimension Business Forum by CEO of Unified Energy Systems of Russia and Vice-President of BALTREL Anatoly B. Chubais
4 April 2001 Tallinn
2
Northern Dimension — active element of cooperation in the North of Europe
Northern Dimension must make its contribution into the cause of peace and security in the region
Northern Dimension may act as an instrument of complex spatial development of North-Western Russia
Russia
Finland
Poland
Iceland
Estonia
Latvia
Lithuania
Norway
Sweden
Kaliningrad
3
Establishment of well-balanced export of electricity - high priority task of RAO UES of Russia
RUSSIAN RUSSIAN FEDERATIONFEDERATION
Kazakhstan andCentral Asia
Baltic states
Belorussia
and
Ukraine
Transcaucasian republics
During Soviet times parallel operation was carried out within 11 USSR republics,4 Central Asian republics were interconnected with each other...
…the decision of RAO UES of Russia restored synchronous operation with 9 of the 12 CIS countries and all the Baltic states - former USSR members
4
Finland40%
Belarus
32%
Turkey5%
Poland4%
Latvia 6%
Georgia2% China
1%
Kazakhstan10%
Key markets for electricity deliveries from Russia
Presumptive electricity exports structure for 2001
Total: 15,525 mn kWh
Existing transmission capacity of RAO UES of Russia’s electricity connections with power grids of Latvia and Estonia allows to increase the exports by 3-4 TW per annum
Northern Dimension member countries account for 50% of Russia’s electricity exports
5
Exchange between power grids of Baltic countries
Exchange between power grids of Baltic countries in 2000 was 50-55 TWh per annum, in the future will be 65-70 TWh
0
10
20
30
40
50
60
70
2000 future
Russia’s share in the total volume of exchange with Baltic region countries is approximately 12 TWh per annum
12 TWh
38 TWh
6
Construction of the third 400 MW transmission line to Finland from the Vyborg transforming plant (Vyborg-Kymi)
Installation of DC connectors allowing export of electricity from the Kola power grid to Finland
Strengthening the 330 kV Lenenergo-Karelenergo-Kolenergo transit transmission line (1100 km)
Final putting into operation of the first stage of the North-Western thermal plant consisting of 2 CCGTs with capacity of 450 MW each
Construction of Kaliningrad No. 2 thermal plant based on the combined cycle technology with capacity of 900 MW
2000 saw continuation of efforts on several investment projects aimed at export expansion
7
Conditions and advantages of power grid integration
Conditions
- parallel operation of power grids according to agreed upon rules and technological standards
Advantages
- increase in energy security
- increase in reliability
- possibilities of regulation
- more even and therefore, more economical operation of power grids
8
Development of electricity exports from Russia to Western Europe has already begun. . .
Example:Contractual deliveries of electricity to Germany
RAO UES of Russia
Counterparty(Poland)
Counterparty(Germany)Deliveries
(transit via Belorussia)
Contract Contract
Framework agreement
Re-exports
Electricity deliveries to Turkey (transit via Georgia) already started
Patterns of electricity contractual deliveries to Hungary, Yugoslavia and Italy under development
9
. . . however the choice of further cooperation pattern determines the necessity of the grid development . . .
. . . However, if the strategic orientation towards parallel operation of power grids is adopted, the DC connectors are not needed
. . . However, if the strategic orientation towards parallel operation of power grids is adopted, the DC connectors are not needed
If it is decided to retain the existing situation it is necessary to develop the back-to-back stations
If it is decided to retain the existing situation it is necessary to develop the back-to-back stations
OUR STRATEGY IS RESTRUCTURING
OUR STRATEGY IS RESTRUCTURING
… and is determined by strategic plans of the partners
10
Russian power sector reform implies introduction of competition into generation and supply of power
Generation of power
Supply of power
Segments, where
development of competition is
possible
Natural monopolies
• Introduce free market pricing
• Stop cross-subsidisation
• Reorganise commercial/ technological infrastructure for functioning of power market
• Provide equal access to distribution network
Re-organise the regulatory system
Market rules
Regulated tariffs
Dispatching
High voltage grid
Distribution
11
Most countries have chosen a competitive model
Liberalisation
Priv
atis
atio
n
Private
State-owned
State regulation
Competitive market
Russia (2000)
France (2000)
Hungary (1999)
Thailand (1996)
Italy (1999)
California (1995)Great Britain (1990)
Ukraine (1997)
Skandinavia (1992)
EC Directive for Power
sector
Argentina (1990)
Brazil (1995)
South Africa (2000)
Greece (2000)
Kazakhstan (1998)
Moldova (1999)
12
Liberalisation of electricity generationand supply through implementationof competition
No constraints for third party access Community-wide
Unbundling and strict regulation of electricity transmission anddistribution systems
Gradual opening of electricity markets over a period of 6 years
Demonopolisation of generation and supply through restructuring of UES’ subsidiaries
Free access to customers
Separation and strict regulation of transmission; separation and regulation of distribution, third party access to the grid
Development of wholesale and retail electricity markets and conditions for private investments
EU Directive’s principles Principles of Russian reform
Basic principles of the Russian power sector reform correspond to key principles of EU Electricity directive (1996)
13
In spite of increase in the capex volume...
North-Western Co-Generation Plant
Late in 2000 the first unit of the North-Western Co-Generation Plant was commissioned - first CCGT plant in Russia
Total design capacity of the plant will be 1,800 MW
Its efficiency rate will amount to 51.5%, while at conventional steam plants this rate does not exceed 40%
Fuel consumption per 1 kW of generated power will fall by 20-25%
Construction of the plant is financed by RAO «UES»
In 2000 the amount of RAO «UES» investments in production was 1.4 times as high as it was in 1998 (RUR 34.9 bn against RUR 24.3 bn).
RUR 24.3 bn
RUR 34.9 bn
RUR 28.7 bn
823.9 MW
1,116 MW
836.5 MW
14
In particular, investments are needed for construction of units 3 and 4 of the North-Western Co-Generation Plant, Kaliningrad
Co-Generation Plant-2
…internal resources are not sufficient to solve the key problem
Assets of RAO «UES» have highly deteriorated
Over the last 15 years virtually no large power projects have
been commissioned
Annual retirement of capacities is 5 times as high as the
introduction of new ones
Annual amount of investments is 5-6 times lower than
required
15
«5,000 MW» Program: First stage of an investment breakthrough
Under the «5,000 MW» Program the capacities to be put in operation will provide for gas savings of up to 6.6 bn cub. nm per annum
Corresponding budgeted investments will amount to US$ 1,737.4 mn
Deadline for completion of pre-feasibility studies under the Program – 30 April 2001
16
Negotiations about possible attraction of investments are currently underway with largest international companies
0
10
20
30
40
50
60
70
80
30 largest electricity companies of the world by market capitalisationUS$ bn
Companies, with whom meetings have already been held
Second-tier strategic investors, with whom meetings are planned
On behalf of RAO UES of Russia the negotiations with 9 large electricity companies have been held, additional meetings are planned
*approximately, based on the expert estimates
17
Reform will open up new horizons for international co-operation in power sector
Investment opportunities in generation
Strengthening of European
electricity security
Asset swaps betweenRussian and Europeancompanies
New markets for power sector technologies
Expanded exportand import
of electricity
Russian power sector reform
THANK YOU FOR YOUR ATTENTION