Energy Benchmarking with Xcel Energy Drew Quirk, Product Developer 12/9/2016
Transcript
Page 1: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Energy Benchmarking

with Xcel Energy

Drew Quirk, Product Developer

12/9/2016

Page 2: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

• Background Information

• Development Process

• Solution Itself

• Current Participation Statistics

• Integration within Xcel Energy’s DSM Portfolio

• Looking forward

Agenda

Energy Benchmarking with Xcel Energy

Page 3: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Drivers - Demand

Page 4: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Drivers – DSM Potential

Page 5: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Development of Solution

2013 2014 2015 2016

DOE Energy Data Accelerator

CO PUC Rulemaking

MN PUC Workgroup

Internal Development

Launch

Page 6: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

DOE Energy Data Accelerator

Page 7: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Best Practice #1: Aggregate

Page 8: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Best Practice #2: Streamline Consent Process

CO PUC Rule for Whole Building Access

Page 9: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Best Practice #3: Utility Auto-Upload

Page 10: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Solution Overview

Benchmarking Tool

Back-end Systems Web Portal

Page 11: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Current Participation Statistics

Number of

Buildings

Ave Elec

Tenants

Min Elec

Tenants

Max Elec

Tenants

Ave Gas

Tenants

Min Gas

Tenants

Max Gas

Tenants

MN MF Master Meter 9 1 1 1 1 1 1

MN MF Multi-Tenant 136 49 2 380 17 1 255

Page 12: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

• Benchmarking is used at the beginning of the

program to set energy baseline

• Service and building information are available to

building owners (Xcel Energy data only) after

program participation

• Building owners outside of program are always

eligible to participate in the Benchmarking

Service.

Integration with Xcel Energy’s MFBE Program

Page 13: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

• As outcome of recent PUC

hearing, initial plan is to continue

current practices

• Formalize with PUC and

stakeholders through filing after

order is issued.

MN Policy Landscape

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

0 5 10 15 20 25%

Bu

ildin

gs C

aptu

red

n Tenants

Multi-Family Buildings

Electric

Gas

Page 14: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

For more information:

www.xcelenergy.com/energybenchmarking

Questions? Email us at [email protected]

Page 15: Energy Benchmarking with Xcel Energy...•As outcome of recent PUC hearing, initial plan is to continue current practices •Formalize with PUC and stakeholders through filing after

Recommended