ENERGY RECOVERY OF HIGH PRESSURE COLD INCOMING WATER IN DEEP LEVEL MINES

Date post: 24-Feb-2016
Category:
Upload: tobias
View: 32 times
Download: 0 times
Share this document with a friend
Description:
ENERGY RECOVERY OF HIGH PRESSURE COLD INCOMING WATER IN DEEP LEVEL MINES Presented by Danie le Roux August 2012. Conventional water reticulation of deep level mines. Opportunities for energy recovery. Three Chamber Pump System (3CPS) Displaces hot water with incoming cold water - PowerPoint PPT Presentation
Popular Tags:
81
ENERGY RECOVERY OF HIGH PRESSURE COLD INCOMING WATER IN DEEP LEVEL MINES Presented by Danie le Roux August 2012
Transcript

ENERGY RECOVERY OF HIGH PRESSURE

COLD INCOMING WATER IN DEEP LEVEL MINES

Presented by Danie le RouxAugust 2012

Conventional water reticulation of deep level mines

Opportunities for energy recovery

• Three Chamber Pump System (3CPS)• Displaces hot water with incoming cold

water• Consists of six high pressure and six low

pressure valves• Dissipater bypass system• Control system

How does a 3CPS work?

How does a 3CPS work?

How does a 3CPS work?

Principles of a 3CPS?

Control System of a 3CPS?

Opportunities for energy recovery

• Pump as Turbine (PaT)• Pump running in reverse• Powered through incoming cold water• Maintains back pressure• Generates electricity

Principles of a Pump as a Turbine

FT

MV1

MV1

CV1

CV1

MV2

MV2Existing PRVCONTROL VALVEMANUAL

VALVE

MAG-FLOW METER

REVERSE –RUNNING PUMP

HIGH PRESSURE

BYPASS LINE

VARYING DEMAND

Switch gear

Electricity at 50Hz

Conventional water reticulation of deep level mines

Ideal mine – all incoming pressure recovered

• Three x 3CPS being installed in Gold Mines (2 completed, 1 in process of completion)

• Eskom funded 50% • Payback to client reduced from 6 years to 3 years.

• Operating Specifications:• Designed flow rate 240 – 380l/s• Operating pressure 11 – 19MPa• Pump energy saving 3.5 + 4.3 + 5.8 = 13.6MW

Case Studies

Case Studies – 3CPS installed

Case Studies – Eskom site visit

• Significant opportunity to recover pressure of incoming cold water in deep level mines

• Higher Levels: a 3CPS or Pelton Turbine• Lower Levels: a PaT • There is no mine in SA where all the pressure

is currently recovered• Large savings are possible

Conclusion