+ All Categories
Home > Documents > Energy101 Module 21

Energy101 Module 21

Date post: 04-Jun-2018
Category:
Upload: luis-emprendedor
View: 215 times
Download: 0 times
Share this document with a friend

of 21

Transcript
  • 8/13/2019 Energy101 Module 21

    1/21

    Energy 101Energy Technology and PolicDr. Michael E. WebberThe University of Texas at Austin

    Module 21: Electricity IV--Energy Pricing

  • 8/13/2019 Energy101 Module 21

    2/21

    Power Plants are Dispatche

    by Price and Availability

  • 8/13/2019 Energy101 Module 21

    3/21

    A Load Duration Curve Shows the

    Distribution of Load Throughout the YCourtesy: Sand

  • 8/13/2019 Energy101 Module 21

    4/21

    ERCOT Dispatches Power Plants

    in the Order of Least Marginal Cos

    Power plants dispatched so

    that supply = demand

    Marginal Cost =

    VOM + HR x FC

    !VOM = Variable Operations and

    Maintenance Costs ($/MWh)

    !HR = Heat Rate (MMBTU/ MWh)

    !FC = Fuel Cost ($/MMBTU)

    Capacity (MW)

    Example: If demand MW, all power plants

    the line are dispatch

  • 8/13/2019 Energy101 Module 21

    5/21

    Decreasing Natural Gas Prices Have Sh

    The Merit Order For ERCOT Dispatch

    [Sanders, Blackhurst, andWebber 2013]

  • 8/13/2019 Energy101 Module 21

    6/21

    The Prices at Which Power Plants B

    Determined by Power Plant Econo

  • 8/13/2019 Energy101 Module 21

    7/21

    There are Two Types of Costs

    for Power Plants

    Variable Costs: Spent

    when running the plant

    !Fuel

    !Variable Operations &

    Maintenance (O&M)

    Fixed Costs: Must be

    spent, even if plant is off

    !Fixed O&M, Taxes, and Insuranc

    !Capital costs (building the powe

    plant)

  • 8/13/2019 Energy101 Module 21

    8/21

    Variable Costs are a Function

    of Several Parameters

    Variable Costs (VC) are a function of:!Heat Rate (HR): expressed in [BTU/kWh]

    !Capacity (CAP): expressed in [MW]

    !Fuel Costs (FC): expressed in [$/BTU]

    !O&M costs (OM): expressed in [$/kWh]

    !Capacity Factor (CF): expressed in %

    Variable costs are typically expressed as

    !$/yr, $/kWh, $/MWh

  • 8/13/2019 Energy101 Module 21

    9/21

    Nuclear has the Highest Average Capacity

    Nuclear

    Coal

    Natural Gas CC

    Hydroelectric

    Renewable

    Natural Gas

    PetroleumAll Sources

    0% 25% 50% 75% 100%

    Average Capacity Factor

    Capacity factor is a f1. Reliability

    2. Use

    3. Fuel availability

    Actual Output [MWh]

    365 days( )! 24 hours/day( )! Rated Capacity MW[ ]( ) = Capacity Factor

    Mich

    aelE.Webber

    2009 U.S. Average Capacity Factors by Energy SourceSource: U.S. Energy Information Administration / Electric Power Annual 2009 Graphic: Michael E. Webber, The University of Texas at Austin

  • 8/13/2019 Energy101 Module 21

    10/21

    Calculating Variable Costs Requires Infor

    About the Power Plant and Fuel

    VC $kWh

    !"

    #$

    = FC% HR +OM[ ]

    VC $kWh

    !"

    #$

    = FC $BTU

    !"

    #$%HR BTU

    kWh!"

    #$ +OM

    $!"

    !"&

    Variable costs [$/kWh] are a function of fuelcosts, heat rate and O&M expenses

  • 8/13/2019 Energy101 Module 21

    11/21

    Calculating Variable Costs Requires Infor

    About the Power Plant and Fuel

    Variable costs [$/yr] are a function of fuel costs, hrate, O&M expenses, capacity and capacity factor

    VC $

    yr

    !

    "#

    $

    %&

    = FC' HR +OM[ ]' e(

    VC $yr

    !"#

    $%&= FC' HR +OM[ ]' CAP ' CF ' 87[

  • 8/13/2019 Energy101 Module 21

    12/21

    Calculating Variable Costs Requires Infor

    About the Power Plant and Fuel

    VC $ yr!"# $%&= FC' HR+OM[ ]'e(

    VC $yr

    !"#

    $%&

    = FC $BTU

    !"

    $%'HR BTU

    kWh!"

    $%+OM

    $kWh

    !"

    $%

    !"#

    $%&'e( kWh

    y!"#

    VC $ yr!"# $%&= FC' HR+OM[ ]' CAP' CF' 8760[ ]

    VC $yr

    !"#

    $%&

    = FC $BTU

    !"

    $%'HR BTU

    kWh!"

    $%+OM

    $kWh

    !"

    $%

    !"#

    $%&' CAP [kW]' CF' 8!

    "#

  • 8/13/2019 Energy101 Module 21

    13/21

    There are also Capital Costs for Power P

    Cost for Capacity: $/W or $/kW

    ! Overnight price

    !akaCapital Cost (CC)

    Rule of thumb 19902007:

    ! Capacity:

    ! ~$1/W

    ! ~$1000/kW

    ! ~$1,000,000/MW

    ! A power plant capable of generating 1000 MW (1 GW)

    power would cost $1 billion

    2010 CAPEX costs for new capacity from Black & Veatch (Feb 2012)

    Fuel

    Capacity

    p

    Natural Gas (Turbine)

    Natural Gas

    (Combined Cycle)$

    Wind $

    Solar PV $

    Coal (Pulverized) $

    Coal (IGCC) $

    Nuclear $

  • 8/13/2019 Energy101 Module 21

    14/21

    Solar CAPEX Costs Have Been Fallin

    EPC = E

    Procure

    BOP = B

    (other s

    infrastru

  • 8/13/2019 Energy101 Module 21

    15/21

    Capital Costs Are Usually Amortized O

    Decades, NOT overnight

    n= term of the loan (yrs) = planned life ofthe system

    i= interest rate (%/yr)

    P= principal amount of loan ($)

    A= annual loan payment ($)

    M= monthly loan payment ($)

    T= total payment ($) = nx A= 12 x nx M

    A = P !i(1+ i)

    (1+ i)n"

    M = P ! ( i

    12 )(1+

    1

    (1+ in)12n

  • 8/13/2019 Energy101 Module 21

    16/21

    Annualized Capital Costs Depend

    on the Lifetime of the Power Plant

    Question: What is the lifetime of a power plant?

    Answer:Its like my grandfathers axe. Its had 6 new heads

    new handles, but its still my grandfathers axe.

    !Source: HoffStauffer

    Power plants last as long as the owner continues to invest i

    Typical periods are 20 to 40 years

  • 8/13/2019 Energy101 Module 21

    17/21

    The Total Costs Include the

    Variable and Capital Costs

    Total Cost (TC) = Variable Cost (VC) + Cap Cost (CC)

    Fixed & Variable [$/kWh], [$/yr]

    Someday there might also be additional costs

    !Emissions: [$/tonNOx, $/tonSOx, $/tonCO2]

    !Water: [$/gallon]

    TC $yr

    !"#

    $%&= VC $

    yr!"#

    $%&+CC $

    yr!"#

    $%&

  • 8/13/2019 Energy101 Module 21

    18/21

    Costs can be Normalized and Compare

    the Levelized Cost of Electricity (LCO

    LCOE $kWh[ ]=Total Cost $yr!" #$

    Annual Electricity Generation kWyr!"

    LCOE $kWh[ ]= VC+CC[ ] $yr!" #$

    CAP% CF% 8760[ ] kWhyr!" #$

  • 8/13/2019 Energy101 Module 21

    19/21

    The Price for Electricity Generatio

    Depends on the Costs Plus Other Fact

    Cost of Electricity: /kWh!Includes capital charge, fuel costs, O&M costs

    Price of Electricity

    !Regulated: Historically, prices are fixed for consumers regardless of fuel

    costs, time of day, season, or location

    !Market-Based:price depends on markets (supply & demand, profits, etc.

    !Moving towards smart meters and real-time pricing

    !Typically ~$0.10-14/kWh for commercial/residential

  • 8/13/2019 Energy101 Module 21

    20/21

    Prices listed in $/MWhValues include installed capacity

    LCOE of Installed and Planned Fleet Va

    From $0.06 to $0.275/kWh

  • 8/13/2019 Energy101 Module 21

    21/21

    Dr. Michael E. Webber


Recommended