+ All Categories
Home > Documents > ENEVA Corporate Presentation ? October 2014

ENEVA Corporate Presentation ? October 2014

Date post: 02-Jun-2018
Category:
Upload: mpxeri
View: 221 times
Download: 0 times
Share this document with a friend

of 27

Transcript
  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    1/27

    October, 2014

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    2/27

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    3/27

    One of the largest private sector power generators in Brazil

    ENEVA currently operates 2.4GW in coal and gas-fired power plants (2.9 GW until the end of year)

    Integrated energy platform, with privileged access to natural resources

    Only private power generator in Brazil with access to onshore gas

    Ongoing restructuring initiatives

    - Reorganization of the companys structure and continuous TPPs operation stabilization

    - Strengthening of the companys capital structure

    Competitive greenfield portfolio

    Licensed coal, gas and wind power generation projects

    Company overview

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    4/27

    A Brazilian thermal generator with asset exposure to energy fossil fuels (natural gas and coal)

    ENEVA at a glance

    2.9GW inflation-protected, long-term PPAs

    o 2.4GW in operation

    o 518MW under construction

    Long-term PPAs guarantee R$2.2 billion in annual inflation-adjustedcapacity payments

    PPAs provide hedge against commodity price exposure

    Integrated gas E&P assets supply up to 8.4MM m/day to ENEVAs powerplants

    Competitive portfolio of licensed greenfield wind, coal and gas firedcapacity

    Company Description

    ENEVA ownership structure

    Geographic Footprint

    Amapari EnergiaENEVA 51% / Eletronorte 49%

    Diesel - 23MWItaquENEVCoal -

    Natural GasExploratory

    blocksContracted production

    of 8.4MM m 3 /day

    Free Float (37.1%)

    42.9% 20.0%

    Other

    ENEVA ParticipaesENEVA/E.ON

    Joint Venture

    50%

    50%

    BNDES

    8.6%

    EikeBatista

    Controlling Block

    28.5%

    Note: 1) Ownership structure assumes future ENEVA Participaes (JV ENEVA/E.ON) incorporation, as disclosed on the Material Fact Notice as of July 3, 2013

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    5/27

    Pecm I

    Capacity: 720MW

    Fix. Rev.: R$600.3MM /year

    CVU: R$99/MWh

    Auction: A-5/2007

    COD: Dec, 2012

    Capacity: 360MW

    Fix. Rev.: R$317.3MM/year

    CVU: R$103/MWh

    Auction: A-5/2007

    COD: Feb, 2013

    Itaqui

    Note: (1) Fixed revenues are indexed to i nflation index IPCA (Database: Nov, 2013)

    Capacity

    Fix. Rev.

    CVU: R

    Auction:

    COD: O

    Coal generation portfolio overview1.4 GW of installed capacity in full operation

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    6/27

    Parnaba II2 GE GTs x 168,8MW+ 1 GE ST x 181MW

    Parnaba I4 GE GTs x 168,8MW

    Parnaba III1 GE GT x 168,8MW

    + 1 Wrtsil GM x 7,3MWParnaba IV3 Wrtsil GMs x 18MW

    Capacity: 56MW

    46% efficiency

    Fix. Rev: R$54MM/year

    CVU: R$69/MWh

    Free market

    COD: Dec, 2013

    Capacity: 178MW

    38% efficiency

    Fix. Rev: R$98MM/year

    CVU: R$160/MWh

    Auction: A-5/2008

    COD: Dec, 2013

    Capacity: 676MW

    37% efficiency

    Fix. Rev: R$443 MM/year

    CVU: R$114/MWh

    Auction: A-5/2008

    COD: Apr, 2013

    Parnaba IV Parnaba III Parnaba I

    Notes: (1) Bertin project developed by ENEVA; (2) Fixed revenues indexed to infl ation index IPCA (Database: Nov, 2013)

    Parnaba Complex overviewA unique case in Brazil power generation sector with 910MW already in operation

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    7/27

    Cambuhy/E.ON investment in Parnaba Gs NaturalSecuring ENEVAs power plants gas supply

    In 2H2013, ENEVA and E.ON led efforts to rescue PGN fromOGPs judicial recovery process and secure the gas supply forENEVAs power plants

    o Cambuhy Investimentos was brought onboard to replace OGP inthe shareholding structure of PGN

    o Reinforcing its commitment to Brazil, E.ON agreed to join thecontrol group of PGN

    In Feb, 2014, Cambuhy and E.ON carried out a CapitalIncrease at PGN amounting to R$250MM, guaranteeing funds

    to cover PGNs capex needs in 2014o Additional R$750MM in LT financing were secured

    Cambuhy also entered into a share purchase agreement tobuy OGPs remaining stake at PGN for R$200MM

    o This last step of the transaction will be completed as part ofOGPs judicial recovery process

    ENEVA and E.ON have the right for a 2-year term to increasetheir joint participation at PGN to 33.3%

    After execution of the sale and purchase a

    18.2%

    Parnaba Gs Natural

    9.1%

    Controlling Block (100%)

    18.2% 9.1% 36.4%

    Controlling Block (63.7%)

    Current

    Successful rescue plan of PGN

    GasBTG 30%

    Shareholding Structure

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    8/27

    Only part of Parnaba Basin is yet l icensed and explore

    Declaration of commerciality for 3 gas fields: GaviAzul and Gavio Branco

    o Santa Vitria discovery in Jan, 2014 (well OGX-121)

    New management team led by Pedro Zinner (ex-BG di

    o New COO Hubert Mainitz (E.ON E&P)

    Challenges

    o High dispatch scenario increases draw on existinganalysis on optimization of reservoir management

    o Additional investment may be required to keep productio

    Overview

    Parnaba Gs Natural (PGN)3 commercial gas fields fully committed to supply ENEVA power plants

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    9/27

    Operating & Financial Performance of Power Plants

    2

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    10/27

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    11/27

    Operational performance (Parnaba I)

    EBITDA (R$MM)

    Availability Variable Revenue X Variable Cost

    Sources: ONS & Company OBS: Dispatch margin captured by Parnaba Gs Na

    Operating costs per MWh followed Henry Hub prices decrease and reflected lower unavailabilitycosts

    NOTE: 1) Does not include Depreciation & Amortization.

    Operating Costs

    1Q14

    Operating Costs 1 (R$ million) 221.9 19

    Gross Energy Generated (GWh) 1,411 1

    Operating Costs per GrossEnergy Generated (R$/MWh) 157.2

    N.A.

    91% 97% 96%99% 98%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    44.8

    -20.6 25.3

    0.7

    50.3

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    77 74 65 75 80 68 77 78 74 79

    80 82 9499 100 96 93 99 95 92

    Variable Cost Gross Vari

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    12/27

    Operating Costs

    Operational performance (Pecm I)

    Availability

    NOTES: 1) Figures consider 100% of Pecm I; 2) Does not include Depreciation & Amortization; 3) 1Q14 unavailability figure considers ONS review (previously 71%).

    Variable Revenue X Variable Cost

    Lower Operating Costs per MWh mainly offset by higher fuel and unavailability costs

    Sources: ONS & Company

    1Q14

    Operating Costs 2 (R$ million) 230.2 25

    Gross Energy Generated (GWh) 1,014 1

    Operating Costs per GrossEnergy Generated (R$/MWh) 227.1

    EBITDA 1 (R$MM)

    72%

    41%

    66%

    51%

    83%3 77%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    48.8

    9.6

    -26.1

    0.3

    32.5

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    71% 151127 118

    136154

    117139 138

    109 119 107

    111 105 104 100 99 99 97 102 105 106110

    Variable Cost Gross Variab

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    13/27

    Operational performance (Pecm II)

    Variable Revenue X Variable CostAvailability

    Sources: ONS & Company

    EBITDA negatively impacted by higher outsourced services and unavailability costs

    EBITDA (R$MM) Operating Costs

    1Q14

    Operating Costs (R$ million) 99.4 10

    Gross Energy Generated (GWh) 720.8 7

    Operating Costs per GrossEnergy Generated (R$/MWh) 137.9

    N.A. N.A. N.A.

    85%97% 96%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    46.3

    -7.1

    -6.0 0.3

    33.5

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    NOTES: 1) Figures consider 100% of Pecm II; 2) Does not include Depreciation & Amortization.

    92 99111 99 106

    114 118 122 125 125

    Variable Cost Gross Varia

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    14/27

    Operating Costs

    Operational performance (Parnaba III)

    NOTES: 1) Figures consider 100% of Parnaba III; 2) Does not include Depreciation & Amortization.

    Availability Variable Revenue X Variable Cost

    Sources: ONS & Company

    OBS: Dispatch margin captured by Parnaba Gs Na

    Operational dispatch adjustment impacted Operating Costs

    1Q14

    Operating Costs 2 (R$ million) 61.9 6

    Gross Energy Generated (GWh) 344

    Operating Costs per GrossEnergy Generated (R$/MWh) 179.6

    EBITDA 1 (R$MM)

    N.A. N.A. N.A.

    100% 99%

    77%

    1Q13 2Q13 3Q13 4Q13 1Q14 2Q14

    14.4 -19.6

    -3.30.04

    -8.4

    EBITDA 1Q14 Net OperatingRevenues

    OperatingCosts

    OperatingExpenses

    EBITDA 2Q14

    75 71 69 69

    161 161 161 161 161

    Variable Cost Gross Varia

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    15/27

    Regulatory Update

    3

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    16/27

    Background: Delayed 450MW PPA, with initial supply date as of

    Mar, 2014

    Successful 6-month negotiation with Aneel, preserving plants

    PPA and mitigating potential high regulatory/contractual penalty

    Agreement main conditions:

    o Conclude plants construction in Dec, 2014

    o 20-year PPAs start date postponed to Jul, 2016

    o Penalty amounting to R$333MM, to be paid:

    In installments as of 2022Through the partial reduction in annual fixed revenues over theterm of PPAs

    o Commitment to close the cycle of Parnaba I OCGT in next 5 years

    (renewable for +5 years by Aneel), subject to certain conditions

    precedent, such as:

    Sale of energy in the regulated marketSecure long-term financing for the project

    Parnaba II Agreement with Aneel

    Pecm II and Parnaba I & III

    Successful regulatory achievements (1)Parnaiba II PPA restructuring

    Gas optimization of Parnaba Thermoelectric

    by Aneel: Parnaba III and 2 gas turbintemporally substituted by Parnaba II, as so

    available.

    All plants PPAs terms and conditions fulfille

    gas production, as recommended by A

    development of other gas areas (4.4-4.8 million

    Parnaba Gas Optimization

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    17/27

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    18/27

    Financial Stabilization Update

    4

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    19/27

    May 12, 2014 2Q14 / 3Q14

    Signing of term-sheet with banks for: R$1.5Bi capital increase

    o Phase I: R$316.5MM cash-only; and

    o Phase II: R$1.5Bi minus funds raised on

    Phase I (cash or asset capitalization or

    debt conversion)

    HoldCo. Debt renegotiationo R$600-700MM debt drop-down to

    ENEVAs subsidiaries/projectso 5-year maturity extension of remaining

    HoldCo. debt (approx. R$1.5Bi), with

    amortization starting only in Jun, 2017

    Sale of Pecm IIo Backstop guarantee by E.ON of up to

    R$400MM for 50% of the asset

    R$100MM short-term bridge financingto Pecm II disbursed

    Capital Increase Phase I concluded,raising R$174MM (R$120MM by E.ON)

    Shareholding Structure after CI I

    Pecm II partial sale by executingE.ON backstop guarantee (R$408MM)

    Successful regulatory outcomes

    o Parnaba II Agreement with Aneel

    o All plants protected from hourly-based

    unavailability charges

    42.9% 20.0%

    FreeFloat

    EikeBatista

    Controlling Block

    37.1%

    Financial Stabilization on course

    4Q14

    R$300MM long-termPecm II approved by

    Launch of Capital Inccomprising of

    o Cash;

    o Debt conversion;

    o Asset capitalizatio

    Execution/effective ofdown/roll over

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    20/27

    Brazilian Power Market and Greenfield Portfolio

    5

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    21/27

    Southeast Reservoirs

    ~70% of total storage capacity

    Source: ANEEL

    Brazils Generation Capacity: 136 GW

    Breakdown by source April, 2014

    Brazil is highly dependent on hydro generation with increasingly faster depletion of reservoirs

    Brazilian energy matrix

    63.5%10.5%

    2.5%1.5%2.2%

    19.8%

    Hydro Gas Coal Nuclear Wind Others

    Dry Seas

    67%

    76%

    38%

    40%

    35% 36%39%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    Jan Feb Mar Apr May Jun Jul Aug

    Average 2007-2011 2012

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    22/27

    Source: ONS

    Autonomy = Storage Capacity / (Load Thermal Generation)

    Economic growth will boost power deleading to a supply deficit in 20

    Water storage capacity has stagnated,leading to decreased system autonomy

    65

    65

    60

    65

    70

    75

    80

    85

    90

    2013 2014 2015 2016 2017

    G W a v g

    2016-on: New generation require~8 GWavg required until 2020

    Electric system reliabilityNew thermal plants are necessary to guarantee reliable power supply

    0

    5

    10

    15

    20

    25

    30

    1 9 7 0

    1 9 7 2

    1 9 7 4

    1 9 7 6

    1 9 7 8

    1 9 8 0

    1 9 8 2

    1 9 8 4

    1 9 8 6

    1 9 8 8

    1 9 9 0

    1 9 9 2

    1 9 9 4

    1 9 9 6

    1 9 9 8

    2 0 0 0

    2 0 0 2

    2 0 0 4

    2 0 0 6

    2 0 0 8

    2 0 1 0

    2 0 1 2

    R e s e r v o

    i r s

    A u t o n o m y

    ( M o n

    t h s )

    2 0 1 3

    Current reservoirautonomy ~6 months

    f f

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    23/27

    ParnabaComplex

    Integrated to natural gas resources

    Located in a tax-advantaged region

    Ventos WindComplex

    Located in one Brazils best wind resource areas

    Attractive load factor

    Just 30km from grid connection

    Land ownership assured

    Au(Coal + Gas)

    Located at a port with a regasification terminal buildlicense

    150km from Campos Basin natural gas accumulations

    Environmental licensed to both coal and gas operations

    Sul & SeivalIntegrated to the Seival Mine (proven reserves: 152 M ton)

    Low operation costs

    Powersupply-demand

    unbalanced

    Hydropowerconcentrated

    matrix

    Spot prices athistorical highs

    Demand for base-load generation2 3 4 51

    Sul727 MW

    ParnabaComplex2,166 MW

    Sei600

    Solar Ta1 MW

    ENEVAs greenfield portfolio Attractive licensed greenfield projects in various development stages

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    24/27

    P b I Cl i f th l (2)

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    25/27

    Net power output: 352,8 MW

    Plants upside efficiency: 51% (previously 37%)

    Additional gas consumption: zero

    Contractor: TBD (first phase performed by Duro Felguera)

    Implementation schedule: 36 months

    CAPEX: approx. R$1.75 billion

    Target capital structure: 70/30, with BNDES financing

    Target IRR: 15% realMain equipment/delivery time

    o Steam Turbine + Generator: 18 months

    o Heat Recovery Steam Generator (boilers): 14 months

    o Cooling Tower: 13 months

    o Pumps (feed water, condensate, cooling water): 13 months

    New equipment

    Parnaba I: Closing of the cycle (2)Highly competitive expansion to existing site

    Di l i

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    26/27

    The material that follows is a presentation of general background information about ENEVA S.A. and its subsidiaries (collectively, ENEthe date of the presentation. It is information in summary form and does not purport to be complete. No representation or warranty, express or implied, is madeconcerning, and no reliance should be p laced on, the accuracy, fairness, or completeness of this information.

    This presentation may contain certain forward-looking statements and information relating to ENEVA that reflect the current views and/or expectations of theCompany and its management with respect to its performance, business and future events. Forward looking statements include, without limitation, any statementthat may predict, forecast, indicate or imply future results, performance or achievements, and may contain words like

    may

    ,

    p

    expect

    ,

    envisages

    ,

    will likely result

    , or any other words or phrases of similar meaning. Such statements are subject to a number of risks, uncer tainties anassumptions. We caution you that a number of important factors could cause actual results to differ materially from the plans, objectives, expectations, estimatesand intentions expressed in this presentation. In no event, neither the Company, any of its affiliates, directors, officers, agents or employees nor any of the

    placement agents shall be liable before any third party (including investors) for any investment or business decision made or action taken in reliance on theinformation and statements contained in this presentation or for any consequential, special or similar damages.

    This presentation does not constitute an offer, or invitation, or solicitation of an offer, to subscribe for or purchase any securities.

    Neither this presentation nor anything contained herein shall form the b asis of any contract or commitment whatsoever.

    Recipients of this presentation are not to construe the contents of this summary as legal, tax or investment advice and recipients should consult their own advisorsin this regard.

    The market and competitive position data, including market forecasts, used throughout this presentation were obtained from internal surveys, market research, publicly available information and i ndustry publications. Although we have no reason to believe that any of this information or these reports are inaccurate in anymaterial respect, we have not independently verified the competitive position, market share, market size, market growth or other data provided by third parties orby industry or other publications. ENEVA, the placement agents and the underwriters do not make any representation as to the accuracy of such information.

    This presentation and its contents are proprietary information and may not be reproduced or otherwise disseminated in whole or in part without ENEVA

    written consent.

    Disclaimer

  • 8/10/2019 ENEVA Corporate Presentation ? October 2014

    27/27

    Thank you. www.eneva.com.br


Recommended