of 27
8/10/2019 ENEVA Corporate Presentation ? October 2014
1/27
October, 2014
8/10/2019 ENEVA Corporate Presentation ? October 2014
2/27
8/10/2019 ENEVA Corporate Presentation ? October 2014
3/27
One of the largest private sector power generators in Brazil
ENEVA currently operates 2.4GW in coal and gas-fired power plants (2.9 GW until the end of year)
Integrated energy platform, with privileged access to natural resources
Only private power generator in Brazil with access to onshore gas
Ongoing restructuring initiatives
- Reorganization of the companys structure and continuous TPPs operation stabilization
- Strengthening of the companys capital structure
Competitive greenfield portfolio
Licensed coal, gas and wind power generation projects
Company overview
8/10/2019 ENEVA Corporate Presentation ? October 2014
4/27
A Brazilian thermal generator with asset exposure to energy fossil fuels (natural gas and coal)
ENEVA at a glance
2.9GW inflation-protected, long-term PPAs
o 2.4GW in operation
o 518MW under construction
Long-term PPAs guarantee R$2.2 billion in annual inflation-adjustedcapacity payments
PPAs provide hedge against commodity price exposure
Integrated gas E&P assets supply up to 8.4MM m/day to ENEVAs powerplants
Competitive portfolio of licensed greenfield wind, coal and gas firedcapacity
Company Description
ENEVA ownership structure
Geographic Footprint
Amapari EnergiaENEVA 51% / Eletronorte 49%
Diesel - 23MWItaquENEVCoal -
Natural GasExploratory
blocksContracted production
of 8.4MM m 3 /day
Free Float (37.1%)
42.9% 20.0%
Other
ENEVA ParticipaesENEVA/E.ON
Joint Venture
50%
50%
BNDES
8.6%
EikeBatista
Controlling Block
28.5%
Note: 1) Ownership structure assumes future ENEVA Participaes (JV ENEVA/E.ON) incorporation, as disclosed on the Material Fact Notice as of July 3, 2013
8/10/2019 ENEVA Corporate Presentation ? October 2014
5/27
Pecm I
Capacity: 720MW
Fix. Rev.: R$600.3MM /year
CVU: R$99/MWh
Auction: A-5/2007
COD: Dec, 2012
Capacity: 360MW
Fix. Rev.: R$317.3MM/year
CVU: R$103/MWh
Auction: A-5/2007
COD: Feb, 2013
Itaqui
Note: (1) Fixed revenues are indexed to i nflation index IPCA (Database: Nov, 2013)
Capacity
Fix. Rev.
CVU: R
Auction:
COD: O
Coal generation portfolio overview1.4 GW of installed capacity in full operation
8/10/2019 ENEVA Corporate Presentation ? October 2014
6/27
Parnaba II2 GE GTs x 168,8MW+ 1 GE ST x 181MW
Parnaba I4 GE GTs x 168,8MW
Parnaba III1 GE GT x 168,8MW
+ 1 Wrtsil GM x 7,3MWParnaba IV3 Wrtsil GMs x 18MW
Capacity: 56MW
46% efficiency
Fix. Rev: R$54MM/year
CVU: R$69/MWh
Free market
COD: Dec, 2013
Capacity: 178MW
38% efficiency
Fix. Rev: R$98MM/year
CVU: R$160/MWh
Auction: A-5/2008
COD: Dec, 2013
Capacity: 676MW
37% efficiency
Fix. Rev: R$443 MM/year
CVU: R$114/MWh
Auction: A-5/2008
COD: Apr, 2013
Parnaba IV Parnaba III Parnaba I
Notes: (1) Bertin project developed by ENEVA; (2) Fixed revenues indexed to infl ation index IPCA (Database: Nov, 2013)
Parnaba Complex overviewA unique case in Brazil power generation sector with 910MW already in operation
8/10/2019 ENEVA Corporate Presentation ? October 2014
7/27
Cambuhy/E.ON investment in Parnaba Gs NaturalSecuring ENEVAs power plants gas supply
In 2H2013, ENEVA and E.ON led efforts to rescue PGN fromOGPs judicial recovery process and secure the gas supply forENEVAs power plants
o Cambuhy Investimentos was brought onboard to replace OGP inthe shareholding structure of PGN
o Reinforcing its commitment to Brazil, E.ON agreed to join thecontrol group of PGN
In Feb, 2014, Cambuhy and E.ON carried out a CapitalIncrease at PGN amounting to R$250MM, guaranteeing funds
to cover PGNs capex needs in 2014o Additional R$750MM in LT financing were secured
Cambuhy also entered into a share purchase agreement tobuy OGPs remaining stake at PGN for R$200MM
o This last step of the transaction will be completed as part ofOGPs judicial recovery process
ENEVA and E.ON have the right for a 2-year term to increasetheir joint participation at PGN to 33.3%
After execution of the sale and purchase a
18.2%
Parnaba Gs Natural
9.1%
Controlling Block (100%)
18.2% 9.1% 36.4%
Controlling Block (63.7%)
Current
Successful rescue plan of PGN
GasBTG 30%
Shareholding Structure
8/10/2019 ENEVA Corporate Presentation ? October 2014
8/27
Only part of Parnaba Basin is yet l icensed and explore
Declaration of commerciality for 3 gas fields: GaviAzul and Gavio Branco
o Santa Vitria discovery in Jan, 2014 (well OGX-121)
New management team led by Pedro Zinner (ex-BG di
o New COO Hubert Mainitz (E.ON E&P)
Challenges
o High dispatch scenario increases draw on existinganalysis on optimization of reservoir management
o Additional investment may be required to keep productio
Overview
Parnaba Gs Natural (PGN)3 commercial gas fields fully committed to supply ENEVA power plants
8/10/2019 ENEVA Corporate Presentation ? October 2014
9/27
Operating & Financial Performance of Power Plants
2
8/10/2019 ENEVA Corporate Presentation ? October 2014
10/27
8/10/2019 ENEVA Corporate Presentation ? October 2014
11/27
Operational performance (Parnaba I)
EBITDA (R$MM)
Availability Variable Revenue X Variable Cost
Sources: ONS & Company OBS: Dispatch margin captured by Parnaba Gs Na
Operating costs per MWh followed Henry Hub prices decrease and reflected lower unavailabilitycosts
NOTE: 1) Does not include Depreciation & Amortization.
Operating Costs
1Q14
Operating Costs 1 (R$ million) 221.9 19
Gross Energy Generated (GWh) 1,411 1
Operating Costs per GrossEnergy Generated (R$/MWh) 157.2
N.A.
91% 97% 96%99% 98%
1Q13 2Q13 3Q13 4Q13 1Q14 2Q14
44.8
-20.6 25.3
0.7
50.3
EBITDA 1Q14 Net OperatingRevenues
OperatingCosts
OperatingExpenses
EBITDA 2Q14
77 74 65 75 80 68 77 78 74 79
80 82 9499 100 96 93 99 95 92
Variable Cost Gross Vari
8/10/2019 ENEVA Corporate Presentation ? October 2014
12/27
Operating Costs
Operational performance (Pecm I)
Availability
NOTES: 1) Figures consider 100% of Pecm I; 2) Does not include Depreciation & Amortization; 3) 1Q14 unavailability figure considers ONS review (previously 71%).
Variable Revenue X Variable Cost
Lower Operating Costs per MWh mainly offset by higher fuel and unavailability costs
Sources: ONS & Company
1Q14
Operating Costs 2 (R$ million) 230.2 25
Gross Energy Generated (GWh) 1,014 1
Operating Costs per GrossEnergy Generated (R$/MWh) 227.1
EBITDA 1 (R$MM)
72%
41%
66%
51%
83%3 77%
1Q13 2Q13 3Q13 4Q13 1Q14 2Q14
48.8
9.6
-26.1
0.3
32.5
EBITDA 1Q14 Net OperatingRevenues
OperatingCosts
OperatingExpenses
EBITDA 2Q14
71% 151127 118
136154
117139 138
109 119 107
111 105 104 100 99 99 97 102 105 106110
Variable Cost Gross Variab
8/10/2019 ENEVA Corporate Presentation ? October 2014
13/27
Operational performance (Pecm II)
Variable Revenue X Variable CostAvailability
Sources: ONS & Company
EBITDA negatively impacted by higher outsourced services and unavailability costs
EBITDA (R$MM) Operating Costs
1Q14
Operating Costs (R$ million) 99.4 10
Gross Energy Generated (GWh) 720.8 7
Operating Costs per GrossEnergy Generated (R$/MWh) 137.9
N.A. N.A. N.A.
85%97% 96%
1Q13 2Q13 3Q13 4Q13 1Q14 2Q14
46.3
-7.1
-6.0 0.3
33.5
EBITDA 1Q14 Net OperatingRevenues
OperatingCosts
OperatingExpenses
EBITDA 2Q14
NOTES: 1) Figures consider 100% of Pecm II; 2) Does not include Depreciation & Amortization.
92 99111 99 106
114 118 122 125 125
Variable Cost Gross Varia
8/10/2019 ENEVA Corporate Presentation ? October 2014
14/27
Operating Costs
Operational performance (Parnaba III)
NOTES: 1) Figures consider 100% of Parnaba III; 2) Does not include Depreciation & Amortization.
Availability Variable Revenue X Variable Cost
Sources: ONS & Company
OBS: Dispatch margin captured by Parnaba Gs Na
Operational dispatch adjustment impacted Operating Costs
1Q14
Operating Costs 2 (R$ million) 61.9 6
Gross Energy Generated (GWh) 344
Operating Costs per GrossEnergy Generated (R$/MWh) 179.6
EBITDA 1 (R$MM)
N.A. N.A. N.A.
100% 99%
77%
1Q13 2Q13 3Q13 4Q13 1Q14 2Q14
14.4 -19.6
-3.30.04
-8.4
EBITDA 1Q14 Net OperatingRevenues
OperatingCosts
OperatingExpenses
EBITDA 2Q14
75 71 69 69
161 161 161 161 161
Variable Cost Gross Varia
8/10/2019 ENEVA Corporate Presentation ? October 2014
15/27
Regulatory Update
3
8/10/2019 ENEVA Corporate Presentation ? October 2014
16/27
Background: Delayed 450MW PPA, with initial supply date as of
Mar, 2014
Successful 6-month negotiation with Aneel, preserving plants
PPA and mitigating potential high regulatory/contractual penalty
Agreement main conditions:
o Conclude plants construction in Dec, 2014
o 20-year PPAs start date postponed to Jul, 2016
o Penalty amounting to R$333MM, to be paid:
In installments as of 2022Through the partial reduction in annual fixed revenues over theterm of PPAs
o Commitment to close the cycle of Parnaba I OCGT in next 5 years
(renewable for +5 years by Aneel), subject to certain conditions
precedent, such as:
Sale of energy in the regulated marketSecure long-term financing for the project
Parnaba II Agreement with Aneel
Pecm II and Parnaba I & III
Successful regulatory achievements (1)Parnaiba II PPA restructuring
Gas optimization of Parnaba Thermoelectric
by Aneel: Parnaba III and 2 gas turbintemporally substituted by Parnaba II, as so
available.
All plants PPAs terms and conditions fulfille
gas production, as recommended by A
development of other gas areas (4.4-4.8 million
Parnaba Gas Optimization
8/10/2019 ENEVA Corporate Presentation ? October 2014
17/27
8/10/2019 ENEVA Corporate Presentation ? October 2014
18/27
Financial Stabilization Update
4
8/10/2019 ENEVA Corporate Presentation ? October 2014
19/27
May 12, 2014 2Q14 / 3Q14
Signing of term-sheet with banks for: R$1.5Bi capital increase
o Phase I: R$316.5MM cash-only; and
o Phase II: R$1.5Bi minus funds raised on
Phase I (cash or asset capitalization or
debt conversion)
HoldCo. Debt renegotiationo R$600-700MM debt drop-down to
ENEVAs subsidiaries/projectso 5-year maturity extension of remaining
HoldCo. debt (approx. R$1.5Bi), with
amortization starting only in Jun, 2017
Sale of Pecm IIo Backstop guarantee by E.ON of up to
R$400MM for 50% of the asset
R$100MM short-term bridge financingto Pecm II disbursed
Capital Increase Phase I concluded,raising R$174MM (R$120MM by E.ON)
Shareholding Structure after CI I
Pecm II partial sale by executingE.ON backstop guarantee (R$408MM)
Successful regulatory outcomes
o Parnaba II Agreement with Aneel
o All plants protected from hourly-based
unavailability charges
42.9% 20.0%
FreeFloat
EikeBatista
Controlling Block
37.1%
Financial Stabilization on course
4Q14
R$300MM long-termPecm II approved by
Launch of Capital Inccomprising of
o Cash;
o Debt conversion;
o Asset capitalizatio
Execution/effective ofdown/roll over
8/10/2019 ENEVA Corporate Presentation ? October 2014
20/27
Brazilian Power Market and Greenfield Portfolio
5
8/10/2019 ENEVA Corporate Presentation ? October 2014
21/27
Southeast Reservoirs
~70% of total storage capacity
Source: ANEEL
Brazils Generation Capacity: 136 GW
Breakdown by source April, 2014
Brazil is highly dependent on hydro generation with increasingly faster depletion of reservoirs
Brazilian energy matrix
63.5%10.5%
2.5%1.5%2.2%
19.8%
Hydro Gas Coal Nuclear Wind Others
Dry Seas
67%
76%
38%
40%
35% 36%39%
20%
30%
40%
50%
60%
70%
80%
90%
Jan Feb Mar Apr May Jun Jul Aug
Average 2007-2011 2012
8/10/2019 ENEVA Corporate Presentation ? October 2014
22/27
Source: ONS
Autonomy = Storage Capacity / (Load Thermal Generation)
Economic growth will boost power deleading to a supply deficit in 20
Water storage capacity has stagnated,leading to decreased system autonomy
65
65
60
65
70
75
80
85
90
2013 2014 2015 2016 2017
G W a v g
2016-on: New generation require~8 GWavg required until 2020
Electric system reliabilityNew thermal plants are necessary to guarantee reliable power supply
0
5
10
15
20
25
30
1 9 7 0
1 9 7 2
1 9 7 4
1 9 7 6
1 9 7 8
1 9 8 0
1 9 8 2
1 9 8 4
1 9 8 6
1 9 8 8
1 9 9 0
1 9 9 2
1 9 9 4
1 9 9 6
1 9 9 8
2 0 0 0
2 0 0 2
2 0 0 4
2 0 0 6
2 0 0 8
2 0 1 0
2 0 1 2
R e s e r v o
i r s
A u t o n o m y
( M o n
t h s )
2 0 1 3
Current reservoirautonomy ~6 months
f f
8/10/2019 ENEVA Corporate Presentation ? October 2014
23/27
ParnabaComplex
Integrated to natural gas resources
Located in a tax-advantaged region
Ventos WindComplex
Located in one Brazils best wind resource areas
Attractive load factor
Just 30km from grid connection
Land ownership assured
Au(Coal + Gas)
Located at a port with a regasification terminal buildlicense
150km from Campos Basin natural gas accumulations
Environmental licensed to both coal and gas operations
Sul & SeivalIntegrated to the Seival Mine (proven reserves: 152 M ton)
Low operation costs
Powersupply-demand
unbalanced
Hydropowerconcentrated
matrix
Spot prices athistorical highs
Demand for base-load generation2 3 4 51
Sul727 MW
ParnabaComplex2,166 MW
Sei600
Solar Ta1 MW
ENEVAs greenfield portfolio Attractive licensed greenfield projects in various development stages
8/10/2019 ENEVA Corporate Presentation ? October 2014
24/27
P b I Cl i f th l (2)
8/10/2019 ENEVA Corporate Presentation ? October 2014
25/27
Net power output: 352,8 MW
Plants upside efficiency: 51% (previously 37%)
Additional gas consumption: zero
Contractor: TBD (first phase performed by Duro Felguera)
Implementation schedule: 36 months
CAPEX: approx. R$1.75 billion
Target capital structure: 70/30, with BNDES financing
Target IRR: 15% realMain equipment/delivery time
o Steam Turbine + Generator: 18 months
o Heat Recovery Steam Generator (boilers): 14 months
o Cooling Tower: 13 months
o Pumps (feed water, condensate, cooling water): 13 months
New equipment
Parnaba I: Closing of the cycle (2)Highly competitive expansion to existing site
Di l i
8/10/2019 ENEVA Corporate Presentation ? October 2014
26/27
The material that follows is a presentation of general background information about ENEVA S.A. and its subsidiaries (collectively, ENEthe date of the presentation. It is information in summary form and does not purport to be complete. No representation or warranty, express or implied, is madeconcerning, and no reliance should be p laced on, the accuracy, fairness, or completeness of this information.
This presentation may contain certain forward-looking statements and information relating to ENEVA that reflect the current views and/or expectations of theCompany and its management with respect to its performance, business and future events. Forward looking statements include, without limitation, any statementthat may predict, forecast, indicate or imply future results, performance or achievements, and may contain words like
may
,
p
expect
,
envisages
,
will likely result
, or any other words or phrases of similar meaning. Such statements are subject to a number of risks, uncer tainties anassumptions. We caution you that a number of important factors could cause actual results to differ materially from the plans, objectives, expectations, estimatesand intentions expressed in this presentation. In no event, neither the Company, any of its affiliates, directors, officers, agents or employees nor any of the
placement agents shall be liable before any third party (including investors) for any investment or business decision made or action taken in reliance on theinformation and statements contained in this presentation or for any consequential, special or similar damages.
This presentation does not constitute an offer, or invitation, or solicitation of an offer, to subscribe for or purchase any securities.
Neither this presentation nor anything contained herein shall form the b asis of any contract or commitment whatsoever.
Recipients of this presentation are not to construe the contents of this summary as legal, tax or investment advice and recipients should consult their own advisorsin this regard.
The market and competitive position data, including market forecasts, used throughout this presentation were obtained from internal surveys, market research, publicly available information and i ndustry publications. Although we have no reason to believe that any of this information or these reports are inaccurate in anymaterial respect, we have not independently verified the competitive position, market share, market size, market growth or other data provided by third parties orby industry or other publications. ENEVA, the placement agents and the underwriters do not make any representation as to the accuracy of such information.
This presentation and its contents are proprietary information and may not be reproduced or otherwise disseminated in whole or in part without ENEVA
written consent.
Disclaimer
8/10/2019 ENEVA Corporate Presentation ? October 2014
27/27
Thank you. www.eneva.com.br