INDEXCHECK LISTS FOR SITE ACTIVITIES
SR. NO.
CHECK LIST FOR CHECK LIST NUMBER
PAGE NUMBER
1 Checks while receiving drawings CL – 01 052 Demarcation and Plot layout CL – 02 083 Land Development Works CL – 03 094 Layout of the Buildings on site CL – 04 105 Lineout of Individual Building with side
railCL – 05 11
6 Plum Concrete CL – 06 127 Plain Cement Concrete CL – 07 138 Mix Design & Weigh Batching CL – 08 149 Slump Test, Cube Casting and Cube
Testing CL – 09 16
10 Concreting of Footings CL – 10 1911 Concreting of Columns CL – 11 2012 Concreting of Plinth Beams CL – 12 2113 Concreting of Lift Raft & Lift Pardi CL – 13 2214 Concreting of Staircase CL – 14 2315 Concreting of Beams / Slabs CL – 15 2416 RCC of Lift Machine Room & O.H.W.T. CL – 16 2617 Filling in Plinth & Anti-Termite
Treatment CL – 17 27
18 Rubble Soling CL – 18 2819 Uncoursed Rubble Masonry CL – 19 2920 Brick Masonry CL – 20 3021 External Plaster CL – 21 3122 Internal Plaster CL – 22 3223 Expansion and Construction Joints CL – 23 3324 Curing CL – 24 3525 Concealed Plumbing CL – 25 3626 Water Supply – Rising Mains and
Distribution CL – 26 37
27 Building Drainage system up to the Vertical Stack
CL – 27 38
28 C.P. and Sanitary Fittings CL – 28 3929 Sewage System from Vertical Stack to
Septic Tank / DrainCL – 29 40
SR. CHECK LIST FOR CHECK LIST PAGE - 1 -
NO. NUMBER NUMBER30 Septic Tank CL – 30 4131 External Water Supply – Rising Main CL – 31 4232 Electrical Wiring, Fittings & Fixtures CL – 32 4333 External Electrical M.S.E.D.C.L. supply CL – 33 4434 External Electrical Generator supply CL – 34 4535 Street Light Work CL – 35 4636 Water-proofing of Toilets, Dry Balcony
and Terrace CL – 36 47
37 Tiling Work CL – 37 4938 Kitchen Platform CL – 38 5039 Aluminum Windows and Doors CL – 39 5140 Door Shutters CL – 40 5241 Internal Painting for Walls & Ceiling CL – 41 5542 External Painting CL – 42 5643 Fabrication Work CL – 43 5744 Handing over of flat – Check List CL – 44 5945 Passenger Lift CL – 45 6446 Fire Fighting System CL – 46 6647 Road Work CL – 47 6748 Landscape Works CL – 48 6949 Cleaning of Water Tank CL – 49 7050 Cleaning of Drain Line CL – 50 7151 Collection and Disposal of Dry Garbage /
Wet GarbageCL – 51 72
52 Lift Maintenance CL – 52 7353 Working and Maintenance of Fire
Fighting Equipments CL – 53 74
54 Cleaning of Swimming Pool CL – 54 7555 Safety Measures at Site CL – 55 7656 Rain Water Harvesting CL – 56 77
INDEX- 2 -
CHECK LISTS FOR FIELD TESTSR. NO.
FIELD TEST FOR FIELD TEST NO.
PAGE NO.
1 Receiving, Inspection & Testing : Cement FT – 01 862 Receiving, Inspection & Testing : Steel FT – 02 873 Receiving, Inspection & Testing : Binding Wire FT – 03 884 Receiving, Inspection & Testing : Sand
(Fine Aggregate)FT – 04 89
5 Receiving, Inspection & Testing : Stone Metal (Coarse Aggregate)
FT – 05 90
6 Receiving, Inspection & Testing : Murum FT – 06 917 Receiving, Inspection & Testing : Flush Door FT – 07 928 Receiving, Inspection & Testing : Bricks FT – 08 939 Receiving, Inspection & Testing : Instant Sunla FT - 09 9410 Receiving, Inspection & Testing : M.S. Windows FT – 10 9511 Receiving, Inspection & Testing : Glass Fixing FT – 11 9612 Receiving, Inspection & Testing : Rolling Shutter FT – 12 9713 Receiving, Inspection & Testing : Aluminum
WindowsFT – 13 98
14 Receiving, Inspection & Testing : Plumbing G.I. Pipes and Fittings
FT – 14 99
15 Receiving, Inspection & Testing : Plumbing C.I. Pipes and Fittings
FT – 15 100
16 Receiving, Inspection & Testing : Plumbing PVC Pipes and Fittings
FT – 16 101
17 Receiving, Inspection & Testing : Hume Pipes FT – 17 10218 Receiving, Inspection & Testing : Mosaic Tiles FT – 18 10319 Receiving, Inspection & Testing : Ceramic /
Glazed TilesFT – 19 104
20 Receiving, Inspection & Testing : Granite / Marble / Kotah / Tandoor Stones
FT – 20 105
21 Receiving, Inspection & Testing : Wood / Timber / Plywood / Block Board / Laminates
FT – 21 106
22 Receiving, Inspection & Testing : Shingle FT – 22 10723 Receiving, Inspection & Testing : Stone Dust FT – 23 10824 Receiving, Inspection & Testing : Crushed Sand FT – 24 10925 Receiving, Inspection & Testing : Fly Ash FT – 25 11026 Receiving, Inspection & Testing : Fly Ash Bricks FT – 26 111
SR. NO.
FIELD TEST FOR FIELD TEST NO.
PAGE NO.
27 Receiving, Inspection & Testing : Citadel Blocks FT – 27 11228 Receiving, Inspection & Testing : CPVC Pipes
and FittingsFT – 28 113
- 3 -
29 Receiving, Inspection & Testing : RCC Door Frames
FT – 29 114
INDEXOTHER ENGINEERING INFORMATION
SR. NO.
SUBJECT PAGE NO.
1 Handling, Storage and Preservation 822 Sampling Plan 843 Durocrete Mix Design Manual and Mix Deign for M15 to
M35 Grade of concrete115-131
4 Tables of Engineering Information 132-1555 List of I.S. Codes 156
- 4 -
CHECKS WHILE RECEIVING DRAWINGS CL - 01
Before we start any constructionPlease took info following in the drawings with you.
Check List
a) P.M.C. approved drawings with commencement letter :1. Area of plot.2. Available F.S.I.3. Consumed F.S.I.4. Number of Buildings5. Number of stories of each building.6. Set-Back / side margins shown.
b) Layout drawings (project): check the following :1. Name plate as per specified form.2. Project name, Drawing Title, Sub-Title and Scale.3. North direction.4. Boundaries as per site demarcation.5. Existing Tree location, Well, Bore well, Electric Poles, Telephone Poles,
Overhead Lines, Both Lt. and H.T. and Hutments / Structures.6. Building setback, other buildings of structure obstructing existing
structures, Sufficient set back for septic tank. Etc.7. Road, Septic Tank, UGWT, Bore well, Pump Room, Garden,
Transformer Room, Security Office location etc.8. R. L. of road top, LT room plinth, society office, top of UGWT, main
entrance road, TBM location etc.9. Location of Compound wall, Front Gates, and Types of Compound Wall.
c) Working Drawings :1. North direction and name plate as per specified form.2. Project name, Drawing Title, Sub-Title and Scale.3. Whether sizes are as per printed broachers.4. Flat number as per printed broachers.5. Brick / Block walling convention.6. Chajja at terrace level shown in dotted on all plan.7. Level with respect to T.B.M. for all plan on Plinth, Parking, Landing
and Mid-Landing etc.8. All room door opening sides with Bath W.C.9. Duct dimension and open area dimension.10. Column reduction arrows.11. Centre line checking such as size of column at footing level, all open
ducts, space and staircase details direction, room sizes as per broachers & wall thickness.
- 5 -
12. Dotted lines for Chajja, Rolling Shutter’s pardi, drop etc.13. Kitchen Otta position with sink size14. Lift position and size.15. Balcony, W.C. and Bath drop.16. All windows, door frames opening rolling shutters, R.C.C. grill sizes,
Schedule, exhaust for opening and balcony grill opening.17. Specification in brief.18. W.C. / Bath / Toilet / Terrace sunk line shown shaded. 19. Terrace drain, shopping patterns and rain water pipe opening locations 20. Lift shaft sizes, O.H.W.T. / Lift room positions.21. Staircase pardi thickness, riser thread details.22. Parking drawing.23. Extract details for plinth side flats.24. Meter cabinet locations.
d) Following points be seen while checking R.C.C. Drawings :1. To be read as per working drawings.2. Check the structure at contour level.3. Sunk slabs W.C. toilet bath.4. Head room at specific level (beam depth & change in beam depth)5. Dowel for adjacent structure.6. Details of column below O.H.W.T.7. Check Elevation features.8. Inverted beams for W.C. bath etc.9. Loft details to be taken along with beam.10. Floating column details.11. Terrace level chains slab details.12. Reinforcement at critical points.
e) Following points be seen while checking Plumbing Drawings :1. Location of UGWT / OHWT / Septic Tank / STP / WTP.2. Drawings to support with size and design calculations for capacities of
above.3. Arrangements of Rain-Water Harvesting.4. Slope / Flow of drainage to suit site terrain.
f) Following points be seen while checking Electrical Drawings :1. Location and size for transformer room, meter room for individual
buildings and location of feeder pillars2. Route for electrical cabling to be done.3. Location and size of electrical duct.4. Load calculations for transformer.5. Detailed electrical conduiting for each flat / building.6. Detailed meter room layout.
- 6 -
g) Following points be seen while checking Landscape Drawings :1. Detailed layout of open space area.2. Check weather amenities provided are as per broacher / specifications.3. Check for structural feasibility.
DEMARCATION AND PLOT LAYOUT CL – 02
Check List :
1. Approved demarcation plan with North direction.2. Plane table survey (Map)3. Contour Survey (Map) – Contour Survey also to include R.L.’s of
approach road near the points of entry and at regular intervals if the road runs along the perimeter of the plot.
4. Survey for underground electrical / telephone cables, water supply lines, drainage lines, nala structures etc.
5. Soil Investigation Report – for deciding type of foundation.- 7 -
6. Physical verification of the plot with reference to demarcation plan, existing structure, nala, boundries, H.T. lines approach road etc.
7. Verification of above by Architect and Technical Cell.8. Road widening markings at site from authorized agency.
Records :
1. Demarcation Plan.2. Plane table survey plan3. Contour Map.4. Verification Certificate of Architect and Technical Cell.
LAND DEVELOPMENT WORKS CL - 03
Check List :
1. Architect to give details of following to all Consultants and Technical Cell a) Layout of all building.b) Location and size of U.G.W.T.c) Location and size of Septic Tank and S.T.P.d) Location and size of Transformer, L.T. room and Generator room.e) Design of Compound Wall and Entrance Gate and Security Cabin.f) Design and location of any other amenities ( W.T. Plant, Club House, Garden, Lawn, Swimming Pool, S.T.P., Use of Solar Energy etc )g) Location of E.S.R. if applicable.h) Developed Ground Level.i) Developed Plinth level of all Building and Amenities (preliminary)
- 8 -
j) Developed first slab levelk) Basement level if applicable l) Layout and Location of Rain-water Harvesting with Storm water arrangements.m) Location for Vermiculture / Bio-gas Plant.
2. Existing G.L. with respect to T.B.M.3. Surface cleaning, dressing and leveling.4. Trial Pits for each building for foundation strata.5. Mass Excavation / Pit Excavation – balance cutting and filling. 6. Disposal and Reuse of Excavated earth. 7. Try to maintain natural slope of ground.8. Excavated GL9. Approval by RCC consultant for foundation strata. 10. Bore well locations and water yield reports.11. Provision for proper arrangements of Labour Hutments, GI Sheet
fencing, curing work, electrical lines and plantation. 12. Verification all above by Architect and Technical Cell at site.
Records :
1. Developed plan showing all above amenities and their respective levels.2. Verification Certificate by Architect / RCC consultant and Technical
Cell.
LAYOUT OF THE BUILDINGS ON SITE CL – 04
Check List :
1. As per CL – 02 approved layout showing North direction, Plot Boundaries of all building, Amenities Area, Open Parking, Compound Wall, Gates, Roads, U.G.W.T., Electrical Substation, etc.
2. Marking the Buildings and Structures, Roads on ground with lime powder and check for fouling if any.
3. Check set-backs required for all structure as per rules and regulations 4. Clearance from Architect, Technical Cell for individual building lineout.
Reference : Approved layout plan.
Records : Approved drawings Certificate from Architect and Technical Cell.
- 9 -
LINEOUT OF INDIVIDUAL BUILDING WITH SIDE RAIL CL – 05
Check List :
1. Latest approved centre line plan of the building showing North Direction, adjoining structures, expansion joint if any & reference point with distances.
`2. Verify the center line with respect to RCC foundation plan, Architectural Floor plans and service drawings.
3. Establish T.B.M. near each building.4. Fixing four corners of building and check diagonals.5. Fixing side rails & all center lines, including lift pit position on rails,
diagonals checking part wise.6. Making pits for footings & lift on ground with lime powder and check
for fouling of footings etc.7. Consent from architect, RCC designer and Technical Cell for proceeding
ahead with concrete works.
Reference: Latest approved Center line plan from Architect.
Record : Certificate from Technical Cell and Architect on verification of lineout.
- 10 -
PLUM CONCRETE CL - 06
Check List :
1. Plum concrete is generally used – a) When in the same pit some portion of pit is excavated more for required strata, to level this pit plum concrete is used.b) If two adjacent footings are at different levels, elevate one footing by proving plum concrete.
2. Grade of concrete for plum concrete is M15.3. Plum concrete is to be done in layers 230 mm to 300 mm. After each
layers plums (boulders) to be inserted in concrete. After that next layer of concrete is to be done.
4. Size of plums to be used 6” to 12”5. Percentage of plums with respect to concrete – maximum 40 % 6. PCC below footing is to be done above plum concrete as per specified
thickness.7. Curing for 07 days (minimum)
Records : Consumption statement
- 11 -
PLAIN CEMENT CONCRETE CL – 07
Check List :
1. Refer To : a) Architect drawing.b) RCC drawing and revision.c) Strata for foundation approved by RCC consultant.d) Any service lines passing below PCC or above PCC.
2. Check whether rubble soling below PCC preferred / anti termite treatment below PCC is necessary.
3. PCC top level as per RCC drawing and also with reference to developed ground level or road level.
4. Size, depth and diagonals of the pit size is more than required PCC size; provide side shuttering to get required size.
5. Grade of concrete and thickness of concrete. 6. Placement of concrete and compaction.7. Top of PCC must in level.8. Curing for 7 days (minimum)
Records : Consumption statement`
- 12 -
MIX DESIGN AND WEIGH BATCHING CL – 08
Check List :
1. Use of Weigh Batcher :a) For all major concreting works of RCC like column, beams, slabs, lift
Shaft and water tank, retaining walls, basement raft and walls weigh batcher should be used.
b) Whenever weigh batcher is under repair or not available due to unforeseen reasons, weigh batching converted into volume batching can be adopted
c) The weights should be marked, weighted on an electronic balance & the same is to be recorded in register by site engineer before first operation.
d) For RCC normal – volume batching by standard pharmas can be done.
2. Before starting concrete :a) Design mix data required from site e.g. brand of cement, samples of materialsb) Sieve analysis of stone metal.c) Sieve analysis of natural sand.d) Sieve analysis of crushed sand.e) Moisture content in sand.f) Bulk density of sand.
3. Weigh batcher operations :a) Weigh batcher installed in level.b) Calibration – Once in six months.c) Adjust weigh scale for error.d) Weights should be washed and cleaned.e) The design mix of concrete should be displayed prominently near the weigh batcher.f) Weights of a particular weigh batcher should not be used for any other weigh batcher.
- 13 -
4. During Concreting :a) Type of cement, grade of cement, approved mix design.b) Exact weight of each type of material i.e. cement, coarse aggregate, and fine aggregate and – fly ash, shingle, crushed sand if to be used.c) Check workability of concrete by relating to the slump.d) Casting of cubes and identification marks – min. 6 cubes.e) Check weight in pan and marker of weight on scale as these get disturbed due to vibration.
5. After Concreting :a) Record actual consumption of material.b) Compare actual consumption with theoretical consumption.c) Cube test results with related slump for 7 days and 28 days strengths d) Curing for 10 days.e) De-shuttering period with respect to type of cement used and consultant’s notes on drawings.
Records : 1) Approved design mix
2) Consumption statement.
- 14 -
SLUMP TEST, CUBE CASTING & CUBE TESTING CL -09
A) SLUMP TEST :This test is conducted for determining consistency of concrete where nominal size of aggregate does not exceed 38 mm.Apparatus Used :i. Slump Cone : Top Diameter 100 mm
Bottom Diameter 200 mm Height 300 mm
ii. Tamping Rod : Diameter 16 mm Length 600 mm
Rod rounded at one end.Procedure :The internal surface of the slump cone shall be thoroughly cleaned before commencing the test. Slump cone shall be placed on a carefully leveled metal plate, the slump cone being firmly held in place while it is being filled. The slump cone shall be filled in four layers, each approximately one- quarter of the height of the cone. Each layer shall be tamped with twenty-five strokes of the rounded end of the tamping rod. The strokes shall be distributed in a uniform manner over the cross-section of the cone and for the second and subsequent layers shall penetrate into the underlying layer. The bottom layer shall be tamped throughout its depth. After the top layer has been rodded, the concrete shall be struck off level with a trowel or the tamping rod, so that the mould is exactly filled. Any mortar which may have leaked out between the mould and the base plate shall be cleaned away. The mould shall be removed from the concrete immediately by raising it slowly and carefully in a vertical direction. This allows the concrete to subside and the slump be measured immediately by determining the difference between the height of the mould & that of the highest point of the specimen being tested. The above operation shall be carried out at a place free from vibration or shock, and within a period of two minutes after sampling.
B) CASTING OF CUBES :Cubes of concrete should be cast regularly to estimate the strength of concrete. Concrete for filling the cubes should be taken from the middle discharge of concrete mixer. Concrete from beginning or at the end of discharge should be avoided. Cubes should be filled in 3 equal layers. Each layer should be uniformly tampered at least 35 times with a 16 mm blunt rod. Cubes should be properly leveled and finished using hand trowel. Cubes should be de-molded after 24 hours and immersed in water for curing. It is important to keep the cubes away from the shocks or vibrations especially for initial 3 days of casting.
- 15 -
We recommend that minimum 6 cubes should be taken every day and the batch of 3 cubes be tested for 7 days and 28 days respectively.
As per IS 456 – 2000 minimum frequency of sampling is as follows :
Volume of Concrete Number of Samples1 – 5 m3
6 – 15 m3
16 – 30 m3
31 – 50 m3
51 and above
1234
4 plus one additional for each additional 50 m3
Each sample comprises of 3 cubes.Size of test specimens cubical in shape shall be 15 cm x 15 cm x 15 cm
C) TESTING OF CUBES FOR COMPRESSIVE STRENGTH :Cube testing is done at specified age i.e. on 7th and on 28th day.Age of cubes is calculated from the time of addition of water to the dry ingredients.Test specimens stored in water shall be tested immediately on removal from water and while they are still in the wet condition. Surface water and grit shall be wiped off the specimens and any projecting fins removed. The dimensions of the specimens to the nearest 0.2 mm and their weight shall be noted before testing. The bearing surfaces of testing machine shall be cleaned before placing test specimen. The side faces (faces other than top & bottom) of specimen shall be placed between bearing surfaces. The load shall be applied without shock & increased continuously at a rate of approximately 140 kg / sq.cm / minute until the resistance of the specimen to the increasing load breaks down & no grater load can be sustained. The maximum load applied to the specimen shall then be recorded.
Calculation :
The measured compressive strength of the specimen shall be calculated by dividing the maximum load applied to the specimen during the test by the cross-sectional area, calculated from the mean dimensions of the section and shall be expressed to the nearest kg per sq.cm. Average of
- 16 -
three values shall be taken as the representative of the batch provided the individual variation is not more than +/- 15 percent of the average. Otherwise repeat test shall be made.
Grade of Concrete
28 day’sRequired Strength
03 day’s Indicative Strength
07 day’s Indicative Strength
14 day’s Indicative Strength
M 10 13.5 N / mm2 05.4 N/mm2 09.05 N/mm2 11.47 N/mm2
M 15 18.5 N / mm2 07.4 N/mm2 12.40 N/mm2 15.73 N/mm2
M 20 24.0 N / mm2 09.6 N/mm2 16.08 N/mm2 20.40 N/mm2
M 25 29.0 N / mm2 11.6 N/mm2 19.43 N/mm2 24.65 N/mm2
M 30 35.0 N / mm2 14.0 N/mm2 23.45 N/mm2 29.75 N/mm2
M 35 40.0 N / mm2 16.0 N/mm2 26.80 N/mm2 34.00 N/mm2
M 40 45.0 N / mm2 18.0 N/mm2 30.15 N/mm2 38.25 N/mm2
CONCRETING OF FOOTINGS CL – 10
NOTE : CENTRING / SHUTTERING DESIGN SHOULD BE GOT APPROVED BY CONSULTANT FOR ANY R.C.C. ACTIVITY
Check List : 1. Latest approved center line drawing 2. Latest approved RCC drawings.3. Footing size and respective column number.4. Placement of steel with reference to drawings.5. Orientation of footings and column.6. Cover blocks for reinforcement.7. Grade of concrete and mix design.8. Concrete placement and mechanical vibration.9. Surface finishing.10. Cubes with identification marks and related slump – min. 6 cubes.
- 17 -
11. Testing of cubes for 7 days and 28 days strength.12. Consumption records.13. Curing ( minimum 10 days )
Records : Cube test reports with related slump
Consumption statement
CONCRETING OF COLUMN CL – 11
Check List :
1. Marking of centers for columns to be done before starting any work for above floor.
2. Starters to be casted with minimum height 6” & with vibrated concrete.3. Starters to be casted at least 2 days in advance before erecting the
column shuttering.4. Check for orientation as per RCC and Architectural drawings.5. Column reinforcement, links, and their arrangement as per drawings 6. Fixing cover blocks to reinforcement.7. Checking of shuttering materials.
a) Quality of shuttering material.b) Apply shuttering oil to plywood and planks.c) To close the gaps / gabdies with mud paste to prevent cement slurry flowing out.
8. Column to cast up to bottom of beams. 9. Concrete with mixer should be insisted, if mixer is not used 10% extra
cement is to be used.- 18 -
10. Checking of column while concreting, for plumb.11. Type of cement, grade of cement, grade of concrete and design mix.12. Six cube mould are kept ready to cast cubes from different batches and
slump test for each.13. Compaction by needle vibrator and poking / tamping. 14. Check for lap length above top of concreting of columns.15. Checking of columns after concreting
a) De-shuttering of column after 24 hours.b) Finishing of honeycombing immediately after de-shuttering.c) Hacking of columns within 3 days from de-shuttering.
16. Cube testinga) Remove cubes next day and keep for curing.b) Cover the column by gunny bags.c) Testing of cubes on due dates ( 7th day and 28th day )
Records : Consumption Statement
Cube test results and related slumps
CONCRETING OF PLINTH BEAMS CL – 12
Check List :
1. PCC below plinth beams as per the requirement.2. Out to out measurements and right angles and internal dimensions.3. Provision of foundation of stairs from plinth beams.4. Check for dimensions of Plinth Beams.5. Check reinforcement details as per RCC drawing and schedule.6. Ducting if required for all services lines.7. Quality of shuttering materials.8. Gaps and joints of shuttering 9. Covering for all sides of beams.10. Grade of concrete and design mix.11. Concrete placement and mechanical vibrator / tamping and surface
finishing.12. Marking and finishing of top level of plinth beams.13. Cubes with identification marks and related slump test.14. Curing for minimum 10 days.
Records : Consumption record
Cube test and related slump
- 19 -
CONCRETING OF LIFT RAFT AND LIFT PARDI CL – 13
Check List :
1. Architectural drawing showing lift shaft size and orientation of shaft with reference to manufacturers requirements and required depth of pits.
2. Latest approved RCC drawings.3. Check whether base water proofing is done.4. Check size, diagonal, plumb, support and depth below level required by
lift manufacturers.5. Check grade of concrete and reinforcement.6. Centers of raft, pardi, covering for raft and pardi.7. Check for lift door opening to be provided in lift pardi wall.8. Water proofing on sides of lift pardi up to plinth level.9. Hacking to concrete surface.10. Cubes with identification marks.11. Curing for minimum 10 days.12. Cube tests on 7 and 28 days with related slump.
Records : Consumption Statement
- 20 -
CONCRETING OF STAIRCASE CL - 14
Check List :
1. Scrutiny of RCC Drawing with respect to latest revised Architectural Drawing and details of staircase such as riser, trade and thickness of waist slab.
2. Ensure height of riser is within specified limit (not to exceed 175 mm)3. Before erecting formwork for staircase check by marking on plain
ground, whether arrangement given in drawing is suitable or not.4. Check whether slab / floor level landing top is provided with sunk slab
(50 mm) or not ?5. The sunken (50 mm) provided should be distributed among all risers at
parking floor.6. Check quality of shuttering and staging material.7. Shuttering plates should be well supported by chavi’s for full length. 8. All props supporting chavi’s must in plumb. Top of mundha to cut at an
required angle. 9. Check reinforcement is laid as per RCC drawing or not.10. Mark top of mid-landing / slab level on shuttering sides.11. Check shuttering provided to steps is of plywood finish or not ?12. Check size of risers and trades is as per drawing.13. Check verticality of risers.14. Check thickness of waist slab as per drawing.15. Check dowel provided for upper flight or not ?16. Concreting as per design mix and proper grade of concrete.17. Proper compaction of concrete with vibrator and hand pocking.18. Casting of cubes with related slumps.19. Curing for minimum 10 days.
Records :
- 21 -
Consumption StatementCube Test Results and related slumps.
CONCRETING OF BEAMS / SLABS CL – 15
Check List :
1. Scrutiny of structural drawing with respect to latest revised architectural drawing and details of staircase such as riser, thread, thickness of waist slab, sunk for landing flooring, lift size and opening.
2. Level of each bay of the slab and internal panel measurement beam to beam & diagonals.
3. Location and depth of sunken slab.4. Proper laps for reinforcement of columns, beams and slab and Lift pardi.5. Check reduction of columns and reinforcement is done as per above floor
requirements as per RCC drawings.6. Check for expansion joint details and the same should be provided as per
RCC details. 7. Chairs for reinforcement with 8 mm.8. Dowels for future columns if any in slab and beams.9. Quality of Centring and Shuttering and staging materials.10. Shuttering plates should be well supported by chavis at 3-0” c/c for the
full length.11. Provide camber for cantilever beams as specified by structural
consultant. 12. Cross bracing should be provided for vertical supports (wooden & M.S.
both) for slab and beams at maximum 4’00” interval.13. Make the top of concrete on sides of beam / slab shuttering around14. Making of required GHODI of various thickness of slab.15. Concealed conduit / junction boxes / fan hooks as per electrical
drawings.16. Require number of sleeves opening for RWP, drainage pipe etc.17. Inform well in advance to Architect, RCC designer, Technical Cell for
checking of slabs.18. Provide sufficient cover blocks for beams, columns and slabs.19. Keep six numbers of cubes and one slump cone ready.20. Type of cement, grade of cement and grade of concrete / design mix.21. Proper compaction of concrete with vibrator hand pocking
- 22 -
22. Control of W/C ratio in the concrete to be checked frequently as per the slump desired.
23. Add water proofing compound for sunken slab and terrace slab.24. Finishing of slab to the required line and level without honeycombing.25. For curing ensure water ponding minimum 2” depth with maximum size
of 6-0” X 6-0” between bunds for minimum 7 days.26. Cross-Bracing should not be removed before 03 days after casting.27. De-shuttering of slabs after 7, 10 or 15 days and beams 14 or 21 days
depending upon span and type of cement used, also refer notes on consultant’s drawing and instructions of Technical Cell.
28. Cube tests with related slump for 7 days and 28 days strength.
STAGEWISE VERIFICATION SHOULD BE DONE AS BELOW :
STAGE VERIFICATION BY1. Centring / Shuttering but before
laying reinforcement Project In-Charge2. After Laying reinforcement
but before concreting RCC Consultant,Tech. Cell, Architect
3. During Concreting Project In-Charge4. After concrete for curing
& before de-shuttering Project In-Charge
Records : Consumption statement
Cube test results and related slump
Verification certificate from Architect, RCC consultant, Technical Cell
- 23 -
RCC OF LIFT MACHINE ROOM AND O.H.W.T. CL – 16
Check List :
1. Lift Machine Room :
a) Check for latest approved drawings from lift manufacturer / and architect.b) Check the size of machine room, height, access, ventilation etc.c) Check for the sleeves in the bottom slab as per drawings.d) Check for lifting hook in the top slab as per designed capacitye) Grade of concrete and thickness of concrete.f) Cube test results related with slump.g) Curing for minimum 10 days.
2. For O.H.W.T. :
a) Check the capacity as per Architect or Consultants drawings for domestic, potable water and fire fighting water and treated water for flushing.b) Check for Sleeves for washout, inlet, outlet overflow, fire fighting and treated water for flushing etc.c) Check for chamfer in concrete for bottom slabd) Check for chamber cover openings.e) Grade of concrete and design mix.f) Water proofing compound.g) Cube test results with related slumps.h) Curing for minimum 10 days.
Records : Consumption StatementCube test result and related slumpVerification Certificate from Architect, RCC consultant & Technical Cell
FILLING IN PLINTH AND ANTI TERMITE TREATMENT CL – 17
- 24 -
Check List :
1. Sub ground level and top of filling level.2. Check for laying underground pipelines, cables, etc.3. Material used for filling either murrum or black cotton soil mixed
murrum or lime, filling should be done in layers not exceeding 1’6”4. Flooding with water through holes made in filling.5. Ramming at every layer.6. Top 1’6” layer just below the soling shall be of murrum, watered and
rammed thoroughly with compactor.7. Check necessity of Anti Termite Treatment, if required, then follow pre-
treatment as given below :
Stages :
Stage i) For filling around column footings and plinth beams.Stage ii) For filling in plinth all surface area.Stage iii) For filling around external perimeter of building.
Emulsion Spray :
Mix chemical with water ( 1 part of chemical, 30 parts of water ), make the holes by crowbar at two feet center and two feet deep and spray the emulsion with pressure pump, consumption 5 liters per Sq. meter.
Records :
Levels of sub ground and final levels
RUBBLE SOLING CL – 18
Check List :
1. Filling and compaction of surface.2. Soling thickness as directed by Technical Cell. (minimum 230 mm)
- 25 -
3. Voids filled with murrum.4. Watering and Compaction.5. Ensure
a) Ducting line for electrical cable, TV cable, Water Supply, Drain pipe etcb) Anti termite treatment after filling murrum.c) Top of soling.
Records : Consumption statement
UNCOURCED RUBBLE MASONRY CL – 19
Check List :
1. Architectural drawings.2. Stage wise / thickness wise bottom and top levels of masonry.3. Proportion of cement mortar (not more than 1:6) and raking of joints for
specific type of pointing (proportion of mortar not more than 1:2)4. Provision of one header for every 5 Sq.Ft., staggered horizontally and
vertically. - 26 -
5. Check whether weep holes required in case of retaining walls.6. Curing ( for 10 days minimum )7. Ensure there should not be voids in UCR masonry wall.8. Ensure that only 3 ft height of wall is constructed in one day.9. Provide pins for boundary of upper level masonry work for every 5 rft.
Records : Consumption statement
BRICK MASONARY CL – 20
Check List :
1. Latest approved architectural drawings showing thickness of walls, door windows and other openings.
2. Customer changes / NOC3. Cleaning the entire floor, stacking of bricks on either side of beam.4. Cleaning of slab conduits and passing GI wire through conduits before
brickwork starts.5. Soaking of bricks.6. Preparation of mortar in proper proportion in M.S. Tray, check whether
cement mortar or any other ready mixed mortar is to be used. Prefer for design mix and use of mixer for BBM mortar.
- 27 -
7. Confirm diagonals and dimensions of room after first layer.8. Check right angle, plumb lines, levels, joints ( max ¾” ) at sill and lintel
level.9. Plumb for external wall to be taken from outside and for internal walls
from side flush with beam / column. 10. Not more than 4’-00” masonry in day’s time.11. In case of long walls (exceeding 4.5 m length), provision of horizontal /
vertical RCC bands should be considered 12. Provide ¾” metal chip at the junction of RCC and BBM (insert by thumb
pressure)13. Provide RCC band, if 4” thick brick wall above 3.0 m and if 6” brick
wall above 4.0 m with nominal reinforcement and M15 grade of concrete.
14. Racking of Joints.15. Provide sufficient number of hold fast embedded in concrete for all
frames property covered.16. Cleaning the working area.17 Curing for minimum 10 days.18. Check the line and plumb of door frame.
Records : Consumption Statement
EXTERNAL PLASTER CL – 21
Check List :
1. Latest approved drawing to be referred for elevation features before plastering.
2. Soaking of brick wall surfaces well in advance for minimum 3 days before plaster from both sides.
3. The surface to be plastered shall be cleaned for algae growth, salt effloresces and dust accumulation.
4. Check for electrical conduiting and switch box fixing for terrace and dry balcony light points.
5. Type and texture of finished plaster and thickness of plaster (single or double coat) to be decided before hand.
6. Thiyyas of minimum thickness to be taken two days before plaster.7. Hacking to concrete and filling between concrete and BBM joints.8. Ensure the position of all the concealed sleeves for water supply,
sanitary, rain water, electrical pipes etc.- 28 -
9. Ensure covering of plaster side by tadpatri or plastic at least 3 days before plastering and 7 days after completing of plaster.
10. Verticality and lines of frames.11. Provide chicken mesh at joints of RCC and BBM wherever required.12. Gunny bags spreading near walls to avoid wastage and mortar can be
reused.13. Check proportion of mortar for base coat and finishing coat mixing to be
done in M.S. trays. Also whether cement mortar or ready mortar to be used. Prefer for design mix and use of mixer for plaster mortar.
14. For single coat plaster with rubdi coat for sponge finish – thk. 12 + 6 = 18 mm. both coats to be done simultaneously. For double coat plaster – thk. 19 + 6 = 25 mm. Second coat is to be done 03 days after first coat is completed.
15. Check for line, level and plumb of plaster, check right angles for all openings.
16. Cleaning of working area to be done on the same day, especially railings, RCC grills, door and window frames etc.
17. Curing for 10 days minimum.
Records : Consumption Statement
INTERNAL PLASTER CL – 22
Check List :
1. Soaking of brick-wall surface well in advance for minimum 03 days before plastering.
2. Ensure horizontal and vertical electrical conduits laid chiseling with cutter.
3. Patching up of chiseling area with rich mortar and ¾” metal 2 days before.
4. Sufficient hacking to all RCC work.5. Making thiyyas of minimum thickness 2 days before plater.6. Conduiting of plumbing, electrical and other service lines.7. Customer changes / NOC8. Check electrical conduiting with reference to electrical points, switch
boxes with DB box. 9. Chicken mesh at joints of RCC and BBM, Excess conduiting locations
etc.10. Verticality and alignment of all doors and windows frames.11. Proportion of mortar and mixing in tray, check whether prefer cement
mortar or ready mix mortar to be used with type of finishing coat. Prefer for design mix and use of mixer for plaster.
- 29 -
12. Ensure plumb, right angle, dhar corners, window jam levels, position of electrical boxes etc.
13. Ensure finishing of loft top.14. Ensure application of neeru in proper proportion and finish except dado
position.15. Check for finishing of joints between internal and external plaster.16. Smooth trowelling of neeru finish on next day.17. Cleaning of all working area.18. Check all electrical points and switch boxes are open and cleaned.19. Curing for minimum 10 days.20. Donga (white wash) to be applied after 03 weeks.
Records : Consumption Statement.
PROVIDING EXPANSION / CONSTRUCTION JOINTS CL – 23
Expansion Joint :These joints are provided to accommodate the expansion of adjacent building parts and to relieve compressive stresses that may otherwise develop.The joints formed by providing an initial gap between the adjacent building parts which gets widened or shortened while accommodating the contraction or expansion of the building. The width of the gap should be sufficient to accommodate the maximum thermal-induced moment likely to be encountered. Normally it varies between 10 mm to 40 mm. There should be complete discontinuity of masonry, reinforcement or concrete at the joint and the gap should permit unobstructed movement of the adjacent parts. Expansion joint should start from the top of footing (in case of combined footing for adjacent columns) tip topmost point of structure.
Spacing of Expansion Joints :1. Framed Structures : i) For long uniform structures at 30.0 meter interval
ii) Corners of L,H,T and C shaped structures 2. Walls : i) Load bearing walls with cross walls at intervals
at 30.0 m interval ii) Walls without cross walls – at 30.0 m interval. Control joints over center of openings may be given at half the spacing of expansion joints.
Material used to treat expansion joints :- 30 -
i) Joint Filler : A strip of compressible material used to form and fill the expansion joints in structure. Joint fillers can be made out of a variety of materials such as bitumen, bitumen containing cellular material, cork strips, natural or cellular rubber, expanded plastic, mineral fiber, coconut, pith etcii) Ceiling Compound : A material of plastic consistency applied to the joint in the form of liquid or paste. The function of the ceiling compound is to prevent the ingress of water or foreign matter. Mastic or hot-applied bituminous compound is commonly used for this purpose.iii) Water Bar : A strip which is placed across the joint during construction so as to form an impervious diaphragm. Water bars may be of natural and synthetic rubber, polyvinyl chloride or metal.
Construction Joints :Joints installed at location where construction stops for any reason is known as construction joint. If it is possible to plan construction in such a way that the days work ends at expansion or contraction joint, then there is no necessity of construction joint. But many times it is not possible to complete the concreting work in one operation. Therefore special measures are necessary to be taken to achieve perfect continuity in old and new concrete. For structural stability, it is necessary to ensure that construction joints are provided at pre-determined locations.
Location of Construction Joints for different members :1. Slabs : For simply supported one-way slab Construction joint should be
vertical and parallel to main reinforcement. It can also be provided at the ¼ part part of span at right angles to main reinforcementIn case of two-way slab, the joint can be provided ¼ th part of either span.
2. Beams : In case of beams construction joint should be vertical and located at ¼ th part of span.
3. Columns : 75 mm below beam bottom. 4. R.C.C. Walls : At suitable location where erection of formwork,
compaction of concrete and supervision is convenient.
Old concrete should be treated as below : 1. If the new concrete is to be laid within 48 hours, the face of the old
concrete is cleaned with wire brush and water and a coat of cement mortar (of the same composition as that of concrete) is applied before placing new concrete.
2. If the new concrete is to be laid after 48 hours, the face of the old concrete is first roughened by chiseling. It is then cleaned of scum, loose
- 31 -
aggregates and other foreign matter, wetted and a coat of cement mortar (of the same composition as that of the concrete) is applied before placing new concrete.
CURING CL – 24
Curing is the process of preventing the loss of moisture from the concrete / mortar. Curing should be done for minimum 07 days for 43 / 53 Grade cement.Curing should be done for minimum 10 days for blended cement, but recommended to continue for 14 days.
Installation of Hydro-pneumatic system for curing is recommended.
Following procedure should be adopted for curing.
S. No.
Type of Work Procedure for Curing
1 P.C.C. Sprinkling of water2 Footings Should be covered by wet gunny bags & by
intermittent sprinkling of water. 3 Columns Should be covered by wet gunny bags & by
intermittent sprinkling of water.4 Plinth Beams Should be covered by wet gunny bags & by
intermittent sprinkling of water.5 Slabs & Beams Slabs : Water Ponding of minimum 2”
depth & maximum size 6’ X 6’ between bunds.Beams : Outer side should be covered by wet gunny bags and intermittent sprinkling of water.Beams & Slabs : Sprinkling of water from bottom side of slab & beams after de-shuttering.
6 Brickwork Intermittent sprinkling of water.7 Internal / External Intermittent sprinkling of water.
- 32 -
Plaster8 Water-proofing By ponding9 Tiling Intermittent sprinkling of water.10 External Painting Intermittent sprinkling of water.
CONCEALED PLUMBING CL – 25
Check List :
1. Latest approved plumbing layout.2. Waterproofing requirements.3. Customer changes / NOC.4. Chasing with cutter.5. Ensure type and approved brand of materials ( pipe & fittings ) for
concealed piping work.6. Coaltar painting to all concealed lines / insulation if any for hot water
lines.7. Ensure all taps position at tile joints. All fittings to be flush with tiles.8. Proper filling with mortar.9. Testing with required pressure and its record. To be tested at 10 kg / cm2
for GI / CPVC pipe line and 07 kg / cm2 for Copper pipe line. 10. Identification marks of PMC & Domestic water.11. Provision of nahani tarp, P-trap, CI bends outlets below waterproofing.12. Fixtures levels.13. Provide escape spouts at top coat level.
Records : Pressure test.Consumption Statement.
- 33 -
WATER SUPPLY - RISING MAINS AND DISTRIBUTION CL – 26
Check List :
1. Consultant’s approved drawings / specifications for materials and pumps / work order.
2. Ensure the provision of valve and NRV, PRV3. Position of delivery pipes, air vent pipes, over flow pipes, wash out drain
pipes.4. Joining and alignment of pipes near overhead tank.5. Installation of water pumps of required capacity its Earthing and
Electrical connection.6. If auto control system is provided, then ensure
a) Quality of the sensors of the system.b) Display panel for water tank.c) Cabling used for system.d) Protection for dry run.
7. Proper clamping for pipes.8. Adopt telescopic arrangement in down take pipe lines and check the
plumb and alignment.9. Pressure of water to each floor.10. Identification marks on pipes PMC / wash water supply.
Records : Consumption Statement.
- 34 -
BUILDING DRAINAGE SYSTEM UPTO THE VERTICAL STACK CL – 27
Check List :
1. Check sequence of waterproofing before starting work.2. Procurement of material as per approved drawing and changes in outlet
of sanitary wares.3. Ensure the provision for bends, branch pieces etc.4. Ensure the verticality of the stack before joining internal branches5. Ensure leak proof joints6. Ensure sufficient slope to horizontal drain pipes. 7. Introduce plug socket for cleaning.8. Ensure inspection eye provided wherever necessary.9. Ensure the position, levels of sanitary ware from the floor levels.10. Ensure provision of anti siphon age pipes and elongated length of vent
pipe above the roof level.11. Clamping the pipes rigidly to maintain verticality, plumb, line level, and
slopes.12. Ensure the free flow of drainage for the desired discharge by testing all
the lines.13. Do not mix rain water outlets in to sewage or sullage drains.14. Rain water outlets to connect to rainwater harvesting system.
Records : Consumption Statement
C.P. AND SANITARY FITTINGS CL – 28
Check List :- 35 -
1. Refer to specification and schedule of fittings, fixtures and sanitary ware and type of outlet trap of W.C.
2. Customer changes and NOC3. Free flow of water at least 15 minutes by removing plugs and then fixing
fittings / sanitary wares.4. C.P. fixtures should be fixed with cloth packing while using the
spanners.5. Check all the fittings for free flow of water, leakages if any ( to be
rectified )6. Fix the identification mark on domestic and PMC water connection.7. Ensure the sanitary fitting before fixing for colour code, defects if any.8. Ensure proper grouting of EWC / WB brackets.9. Ensure the proper functioning of flush tank / half turn valve / PVC
connection for colour code, defects if any.10. Seat cover of correct size and matching colour.11. Check for cleaning of tiles and sanitary ware, C.P. fiitings12. Ensure that the plugs for boiler connections are easy to remove but at the
same time the plug is non-leaking.
STANDARD HEIGHTS OF PLUMBING FITTINGSSr. No. Fittings Height from FFL
1 Open Mixer 30”2 Shower 78”3 Tumbler Cock 12”4 Wash Basin 33”5 Angle Cock for Wash Basin 18”6 Angle Cock for Flush Tank 24’7 Bottle Trap Outlet 18”8 Low level Cistern height 36”9 Urinal 24”10 Soap Dish 36”11 Kitchen Sink Cock 39”12 Kitchen Platform 31”13 Flush Valve 41”14 Fourway Divertor / Single Lever Divertor 39”
SEWAGE SYSTEM FROM VERTICAL STACK TO SEPTIC TANK / DRAIN CL – 29
Check List :
1. Approved drawing / work order / specifications for materials.2. Sewage line to be 5 m away from UGWT
- 36 -
3. Ensure all invert levels and proper slope.4. Ensure the alignment of the line.5. Record initial ground level.6. Record excavated ground level.7. Lay pipe in the upgrade direction of the slope and ensure all branches are
connected with proper slope.8. Fill the joints as specified.9. Sufficient time before backfilling (2 days)10. Ensure minimum interval of chambers and provision of chambers at
turnings. Ensure drop in invert level in each chamber between incoming and outgoing pipes.
11. Ensure that all the chambers / manholes are plastered from inside & outside with footsteps.
12. Ensure free flow in the pipe line till connecting drain to septic tank or Municipal chamber.
Records : Consumption Statement / as built drawing
SEPTIC TANK CL – 30
Check List :
1. Approved drawing 2. Invert level of incoming sewer.3. Record initial ground level.4. Record final excavated ground level.5. PCC / RCC, BBM, Water-proofing to be done as per respective check
list.6. Inlet – Outlet levels of tank.
- 37 -
7. Free board.8. All the documents, Size of the compartments and the baffle walls.9. Filler media materials and filling procedure.10. Water tightness of septic tank.11. Vents are provided.12. Connected effluent to sock pit or nearest drain or STP
Records : Consumption Statement / as built drawing
EXTERNAL WATER SUPPLY – RISING MAIN CL – 31
Check List :
1. Approved drawing / work order / specification for materials.2. Whether automatic level control system is to be provided.3. Pump HP head, discharge and quality of foot valve.4. Pump foundation.5. Proper earthing for electrical supply.6. Union joint on suction and delivery side of pump for easy maintenance.7. Motor testing8. Dry run protection.9. Quality of sensors.10. Quality of control panels.11. No air is trapped on suction side.
- 38 -
12. All joints are watertight / leakages to be repaired.13. NRV and sluice / gate valves on rising main.14. Identification for drinking water, wash water and recycled water for
flushing.15. Record the time required to fill the OHWT16. Ensure that the NRV flap closes as soon as pump stops.17. Ensure that no water is stagnant on the pump room floor.18. As built drawing to be prepared.
Records :
Consumption Statement
ELECTRICAL WIRING, FITTINGS AND FIXTURES CL – 32
Check List :
1. Refer to schedule and specifications of fittings and fixtures2. Customer changes / N.O.C.3. The quality gauges and the brand name of the wires, as per the approvals,
before starting the works.4. Check the colour code and specification of the wire for points and avoid
joints wiring.5. Fix the accessories on the boards, as required with line and level and of
approved brand.6. Terminate the wire in accessories, considering an extra length for
looping.7. Connect the wires in accessories, considering an extra length for looping.8. After starting the supply, switch on the main switch and check all the
points with megar and test lamp.
WIRES AND THEIR COLOURS- 39 -
1.5 mm2 Point Wiring Yellow2.5 mm2 Sub Main and 16 A Point Red4 mm2 Boiler and AC Point Blue
COLOUR PURPOSERed, Yellow, Blue Phase WiresBlack NeutralGreen Earthing
EXTERNAL ELECTRICAL M.S.E.D.C.L. SUPPLY CL – 33
Check List :
1. Civil instrument work of LT room and transformer yard based on approved layout of M.S.E.D.C.L. and electrical inspector and detailing by Architects and RCC consultants.
2. M.S.E.D.C.L. approved layout of transformer, four pole structure, LT / HT panels, earthing provision switchgear, feeder pillars, cable layout from transformer to meter board including sizing.
3. Work order for transformer, LT / HT panels, switchgear, cables, steel structure, feeder pillar and all accessories required.
4. Electrical contractors scope of work, his work order, installation schedule.
5. Approvals from M.S.E.D.C.L. and electrical inspector after erection.6. M.S.E.D.C.L. supply from outside mains for charging transformer,
testing and commissioning of the total system.
Records : Approved drawing from M.S.E.D.C.L., Architect and Consultant.
Material Consumption
- 40 -
EXTERNAL ELECTRICAL GENERATOR SUPPLY CL – 34
Check List :
1. Civil construction work as per manufacturer’s requirement, detailing by architect and RCC consultant.
2. Approved layout of generator foundation, AMF and switching panels, diesel stock provision, ducting and ventilation, chimney for smoke disposal, earthing, canopy etc by the approved suppliers and erection contractor.
3. Schedule for erection, testing and commissioning. 4. Approval from electrical inspector concerned.5. Maintenance Manual.6. Maintenance contract.
Records : Approved Drawings
Fuel consumption records
- 41 -
STREET LIGHT WORK CL – 35
Check List :
1. Approved drawings / work order / specification for materials 2. Poles of street lights shall not disturb other services and access.3. Street light cables shall be laid in pipe or GI pipe with proper cushioning.4. Provision of earthing (GI wire) for feeder pillar and each pole.5. Ensure colour code of wires and distribution, connections from pole
junctions to each point.6. Ensure the intensity of street lights in night ( it shall be uniform )
Records :
Consumption Statement / As built drawing
- 42 -
WATERPROOFING OF TOILETS,DRY BALCONY, TERRACE, LIFT PIT AND BASEMENT CL – 36
Check List :
A) TOILETS :
1. Fixing of reference levels / bench mark for every floor.2. Removal of debris ( cleaning of surface with wire brush )3. Making of holes required for all types of outlets.4. Base coat to cover all junctions. 5. Fix finished floor levels to ensure proper and sufficient slope towards
outlet pipes with cushioning mortar above those pipes.6. Proportion of mix for waterproofing treatment at various layers to be
ensured. Use appropriate waterproofing chemicals.7. Brick bat coba with proper slope.8. Finishing coat with smooth finishing bottom surface and same carried
over on vertical surfaces for one foot.9. Escape outlets after top coat.10. Curing for every coat.11. Testing by ponding of water for minimum 10 days.
B) TERRACE AND DRY BALCONY :
1. Fixing of reference levels / bench mark for every floor.2. Removal of debris ( cleaning of surface with wire brush )3. Provision of rainwater outlets.4. Base coat to cover all junctions. 5. Fix finished floor levels to ensure proper and sufficient slope towards
outlet pipes with cushioning mortar above those pipes.6. Proportion of mix for waterproofing treatment at various layers to be
ensured. Use appropriate waterproofing chemicals.7. Brick bat coba with proper slope.8. Finishing coat with smooth finishing bottom surface and same carried
over on vertical surfaces for one foot.- 43 -
9. Curing for every coat.10. Testing by ponding of water for minimum 10 days.
C) LIFT PIT AND BASEMENT :
1. Fixing of machine cut rough shahabad below raft slab with waterproof plaster.
2. Fixing of machine cut rough shahabad for RCC pardi from outside with waterproof plaster up to plinth level.
3. In case of basement encasing column and footings with machine cut rough shahabad is necessary.
4. Curing for 10 days minimum.
Records : Consumption Statement
- 44 -
TILING WORK CL – 37
Check List :
1. Customer changes / NOC2. Customer supplied material if any.3. Drawing for adjusting cut pieces.4. Sorting of tiles for size, colour and pattern.5. Removing of all loose mortar from slab and cleaning the surface
thoroughly (Ghadai)6. Tiles soaking and sorting before fixing. (Use appropriate farma for
sorting)7. Any service line below flooring, especially electrical conduits. 8. Finishing floor levels to be fixed with respect to toilets, terraces and
entrance lobby.9. Ensure slope for flooring in toilets, terraces and dry balcony towards
outlet / nahani trap.10. Use of sand-cement mortar for fixing skirting and dado tiles. 11 Proportion of lime / cement mortar – proper mixing of mortar dry as well
as wet mortar.12 Right angles and plumbs for dado and skirting.13 Fixing of tiles neatly with sufficient slurry backing ensuring no
hollowness behind tiles.14 Ensure cutting of dado tiles to the exact size of switch box.15 Hole cutting for taps, traps, outlets.16 Fixing of skirting by machine cut tiles.17 Proper Butt finishing for skirting and dado tiles.18 Filling of joints with matching colour cement paste on same day.19 Curing / Curing compound for on joints / Butt.20. Polishing coat / cleaning with detergent powder.21. Ensure for gaps / voids by knocking.
Records :
Consumption Statement
KITCHEN PLATFORM CL – 38
- 45 -
Check List :
1. Latest approved drawings (considering drain location).2. Check for vertical and horizontal partitions below platform for kitchen
cabinet.3. Customer changes / N.O.C.4. Customer supplied material.5. Ensure slope towards sink.6. Proper bearing in the walls.7. Position and size of built in sink / S.S. sink / drain board.8. Ensure cutting of dado tiles to the exact size of switch box.9. Connection of sink to vertical stack.10. Sharp edges to be rounded off.11. Coloured cement for joints.
Records :
Consumption Statement
ALUMINUM WINDOWS AND DOORS CL – 39
Check List :
1. Latest approved drawings and specifications.
- 46 -
2. Check position of M.S. Grill of windows, whether from inside or outside before fixing windows.
2. Customer changes / N.O.C.3. Aluminum material section weights, use medium gauge material.4. Aluminum sections to be used, number of tracks and shutters.5. Base frame if necessary; anodizing / powder coating for base frame and
window.6. Right angels of frames, sizes of shutters, bearing, handles, locking
arrangement, provision of mosquito net etc.7. Verify details of tracks, exhaust fan, a/c openings.8. Type, Thickness, Quality of Glass and PVC molding around glasses.9. Removing packing sheet on member and clean all surfaces.10. Holes from outside at bottom truck for draining out rain water.
DOOR SHUTTERS CL – 40
Check List :
1. Refer to approved drawings / work order / schedule of fittings and fixtures.
2. Customer changes / NOC3. Type size, thickness and quality of shutter.4. Door frame should be checked for plumbs and alignment.
- 47 -
5. All the slots for hinges properly provided.6. All the screws fitted with the help of screw driver and not hammered.7. Leaping to be provided as per required.8. Door fittings and fixtures as per approved schedule / work order.9. Painting / Polishing to frame and shutters by protecting and fixtures by
proper covering.10. Flat owner’s name plate on entrance door shutter.11. Use waterproof shutters.12. Use minimum 32 mm thick door shutter if Cylindrical Lock is provided
and 30 mm thick if Al-Drop / Tadipatti are provided.13. Use 35 mm thick door shutter for entrance door.14. Provide minimum 4 hinges for entrance door and 3 hinges for internal
doors.15. Table for levels of different fittings and fixtures. 1. STANDARD HEIGHT’S FITTINGS FOR BALCONY DOOR :Sr. No.
Recommended Fittings Details
Recommended Heights from FFL
Position Of Fittings
1 Balcony Door Inside a) Handle ‘D’ type
bottom95 cm (38”) 6.5 cm (2 ½”) from
opening edge of shutter.
b) Cylindrical Lock / Tadi Patti
100 cm (40”) / 82.5 cm (33”)
Opening Edge
c) Tower bolt 15 cm (6”) Top flush to top of shutter
5 cm (2”) from opening edge of shutter.
d) Door Stopper As per requirement 5 cm (2”) 7.5 cm (3”) at opening edge
2. STANDARD HEIGHT’S OF FITTINGS FOR INTERNAL DOOR :Sr. No.
Recommended Fittings Details
Recommended Heights from FFL
Position Of Fittings
1 Internal Door : Insidea) Tower Bolt 15 cm
(6”)Top flush to top of shutter
5 cm (2”) from opening edge of shutter.
b) Handle ‘D’ type (bottom)
95 cm (33”) 6.5 cm (2 ½”) from opening edge of shutter
c) Baby Latch 82.5 cm (33”) Opening Edged) Rubber Gattu 7.5 cm (3”) 7.5 cm (3”) at opening
edge
- 48 -
2 Outside a) Handle ‘D’ type
bottom95 cm (38”) 7.5 cm (3”)
b) Cylindrical Lock / Tadi Patti
100 cm (40”) / 85 cm (34”)
At opening edge
c) Door stopper As per requirement 5 cm (2”) 7.5 cm (3”) at opening edge.
3. STANDARD HEIGHT’S OF FITTINGS FOR W.C. / BATHROOM DOOR :
Sr. No.
Recommended Fittings Details
Recommended Heights from FFL
Position Of Fittings
1 W.C. / Bath. (Inside)a) Handle (Bottom) 95 cm (38”) 6.5 cm (2 ½”) from
opening edge of shutter.
b) Baby Latch 82.5 cm (33”) Opening edge c) Hook 160 cm (64”) Center of shutter d) Rubber Gattu 7.5 cm (3”) 7.5 cm (3”) from
opening edge of shutter
2 W.C./Bath. (Outside )a) Handle (Bottom) 95 cm (38”) 7.5 cm (3”) from
opening edge of shutter
b) Cylindrical Lock / Tadi patti
100 cm (40”) / 85 cm (34”)
Opening Edge of shutter
4. STANDARD HEIGHT’S OF FITTINGS FOR MAIN DOOR :
Sr. No.
Recommended Fittings Details
Recommended Heights from FFL
Position Of Fittings
1 Main Door Insidea) Tower Bolt 15 cm
(6”)Top flush to top of door
5 cm (2”) from opening edge of shutter
b) Safety Chain 145 cm (58”) 5 cm from opening edge of shutter
c) Eye Piece 145 cm (58”) At center of shutter.d) Handle ‘D’ type
bottom of shutter120 cm (48”) 6.5 cm (2 ½”) from
opening edge e) Night Latch 100 cm (40”) Opening edge of
shutterf) Tadi Patti 85 cm (34”) At the opening of edgeg) Rubber Gattu 7.5 cm (3”) 7.5 cm (3”) from
- 49 -
opening edge of shutter
2 Outsidea) Unit number place 175 cm (70”) Center to shutterb) Name Plate 167.5 cm (67”) Center to shutterc) Decorative handle
(bottom)110 cm (44”) 7.5 cm (3”) from
opening edge of shutter
d) Al-drop 90 cm (36”) 5 cm (3”) from opening edge of shutter
e) Door Stopper As per requirement At the opening edge
INTERNAL PAINTING FOR WALLS AND CEILINGS CL – 41
Check List :
1. Approved colour scheme and check customer’s changes, if any, regarding paint.
2. Wall has been scraped for all unwanted material like excess cement, mortar nails, dust etc.
3. Donga has been removed completely and the wall surface is rubbed by the fine sand paper, wide cracks completely opened and filled with crack seal compound.
4. Mix, preparation and application of primer.5. Primer has been allowed to dry for at least 24 hours before application of
putty.6. All the undulations of minor nature, dents and cracks in proper way are
filled up with putty and surface is smooth to receive paint.7. Surface has been rubbed with fine paper to get smooth finish after 24
hours of application of putty.8. Check any brush marks bristles from the brush stick to the wall.9. Mix, preparation and application of second coat shall be done only after
drying 1st coat.
- 50 -
10. Check for floor, door, windows fittings cleaned properly.11. Check all cement mortar, unwanted welding burr etc. are removed before
application of primer polishing properly.12. Check for free movement of hinges, fittings and fixtures of door and
windows before application of primer.13. Application of zinc cromite metal primer before application of first coat
of oil paint to the steel works.14. Application of first coat of oil paint and proper finish, fill up putty
whenever necessary, application for second coat of oil paint after 24 hours drying of first coats.
Records : Colour Scheme.Consumption Statement
EXTERNAL PAINTING CL – 42
Check List :
1. Approved specifications for materials to be used.2. Approved colour scheme and ensure external wall surface is cleaned
properly before painting is taken up.3. All the electrical plumbing holes are finished properly before application
of first coat.4. The surface is watered for 12 hours before application of priming coat /
first coat. 5. Ensure cleaning by scrapping patti before application of first coat.6. Priming coat / first coat to be applied with proper mix, application and
finishing of surface as per the manufacturers instructions for use.7. Second coat with proper mix, application and finishing of surface as per
the manufacturers instructions for use.8. Cleaning the surfaces, windows glass, terrace, floor, pipes, doors,
fixtures, electrical switches etc.9. Curing as per manufacturers instructions.
Reference : Colour Scheme.
Records : Consumption Statement
- 51 -
FABRICATION WORK CL – 43
Check List :
1. Check the approved drawings, customer changes with NOC2. Check the material as per approved drawing prior to indenting.3. Check the material as per specification.4. Check for :
a) Diagonal / Angles.b) Plumb.c) Design.d) Joints welding.e) Grinding of joints.f) Scrapping by sand paper.
5. Check for painting primer coat.6. Check for painting of oil paints as per specification7. Check for any damages created during erection, rectify it.8. Final point touchup.
Records :
Consumption Statement
- 52 -
CUSTOMER CHANGES
Changes within acceptable norms :
1. Deleting of internal wall.2. Change from EWC (Commode) to IWC (Indian type) with stepped
platform. 3. Change from IWC (Indian type) to EWC (Commode).4. Increase in dado tiles height.5. Door and window grills as per our approved patterns.
Changes beyond acceptable norms :
1. Shifting of internal walls and addition of walls2. Additional loft or change in position / location of loft.3. Changes which will affect external elevation.4. Washing machine / wash basin on terrace.
- 53 -
HANDING OVER OF FLAT - CHECK LIST CL – 44
NOTE : ENSURE THAT COMPLIANCE OF FOLLOWING ARE DONE. REFER TO SPECIFICATION APPROVED FOR FINISHING AND FIXTURE OF ALL TYPES.
A) WALLS AND CEILINGS :( of all the rooms including bathroom and W.C. )
1. Are all cracks in wall are properly filled ?2. Are all signs of dampness / leakage on wall removed ?3. Are all patches or black stripes observed in painting attended ?4. Are loose patches (if any) in ceiling and walls rectified ?5. Are all corners sharp and finished ?6. Are the fan hook in ceiling are proper ?7. Are the overall finishing proper ?
B) TILING :1. Is the floor in proper level ?2. Is the floor and skirting properly polished and cleaned ?3. Is the skirting in one line and at right angles ?4. Are the floor tiles of one type ?5. Is the mosaic / ceramic tiles in the room continued up to outer edge of
main door frame ?6. Is the butt joint properly finished ?7. Is the skirting and butt properly inline level and right angle around the
column ?8. Are cracked tiles replaced and finished properly ?9. Are glazed tiles cleaned and finished properly ?10. Are all glazed tiles cleaned and finished properly ?11. Are the glazed tile dado in right angle and level ?12. Is the gap between glazed tile dado and room ceiling / flooring filled
properly ?13. Are jams of windows properly finished with glazed tiles ?14. Are you sure that there is not a single cracked tile in dado ?15. Are the glazed tile around W.C. pan properly fixed ?16. Are you sure that no water accumulates on flooring of W.C. ?
- 54 -
17. Have you confirmed by knocking each tile that there are no loose patches left in the dado ?
18. Is there proper slope towards nahani trap and no water accumulates in between ?
19. Is there proper slope given to bathroom ?20. Is there bath and W.C. floor down than room floor ? Is boundary edge
finished properly ?21. Is the slope properly given to the balcony towards water spout ?22. Is the terrace or balcony floor level minimum 1” down than floor ? If not
check whether threshold ( Umbra Patti ) has been provided ?23. Is the gap between terrace, toilet, dry balcony floor and room floor filled
properly with white cement.24. Are water spouts in balcony fitted properly and cleaned properly ?25. Is there any necessity to provide threshold fixed to bath and W.C. ?26. Is the kitchen platform finished properly ?27. Is the kitchen platform leak proof ?28. Are the edges of granite around kitchen sink and fascia patti polished
properly and edges soft chamfered ? 29. Is there proper slope given to kitchen platform top ?30. Are the glazed tiles near water taps properly cut and fixed ?31. Is the hole for gas provided with pvc bend above the kitchen otta ?32. Is polishing of kitchen otta cuddappa verticals and shelves done ?33. Is edge polishing and rounding done ?34. Flooring below kitchen platform to be in level with the room floor ?35. Check whether skirting below kitchen platform provided ?36. Is the space for gas cylinder ok to put cylinder freely /37. Are you sure that hole for gas pipe is not chocked with cement / debris ?38. Is the finishing and painting of walls below kitchen platform done
properly ?
D) DOORS AND WINDOWS :1. Are all doors / windows, opening and closing smoothly ?2. Is gap between door / windows frame and shutter within tolerance limit ?3. Are drain holes in aluminum window track from outside provided ?4. Are the aluminum window tracks cleaned with air blower ? 5. Are all doors / windows properly painted / polished /6. Are all fitting’s like locks, tower bolts, stoppers, hinges etc working
smoothly ?7. Are all glass properly fitted, cleaned and crack free ?8. Is the sealant applied it fill in the gaps between windows and wall ?9. Is the polishing of main door proper ?10. Is the no / name plate of the main door fixed ? along with flat no. put on
it ?11. Are all gaps between window / door frames and walls properly fixed ?
- 55 -
12. Is the gap between sill and aluminum window frame sealed with white cement / sealant.
13. Are the door / windows shutters free from bend or any defect ?14. Is the whether shed properly provided to all external door / window with
pani patti in plaster ?15. Is eye piece provided ?16. Check whether laminated sheet has been provided for bath / w.c. doors if
so specified ?17. For protection from rainwater for terrace, door, check whether chajja is
provided ?18. Are screws to all fittings provided ?19. Are tadipatti to door shutters fixed correctly for locking arrangement ?20. Cover molding patti to all door frames fixed or not with proper corner
finishing and painting ?21. Is finishing of lipping patti to door shutter proper with respect to joints ?22. Are the hinges of windows, free and out of plaster of window jam ?23. Are you sure that no windows / door shutter is touching to chajja / loft
plaster.24. Is the rubber gattu fixed sturdy with 7 cm screw each ?25. Are all the doors fittings clean and free from screws each ?
E) LOFTS :1. Are the lofts finished by I.P.S. from top ?2. Are the ceilings and walls around loft properly painted and finished ?3. Is the loft properly cleaned and no rabit / debris left out ?4. Is the finished thickness of loft maintained all over ?
F) PLUMBING AND SANITATION :1. Are all fixtures like bibtaps, mixers etc fixed properly and at proper
height from floor level.2. Is there any leakage from taps / other c.p. fixtures /3. Is there proper pressure to all the taps ?4. Is there half turn cock or flush tank operating properly ?5. Is there continuous flow of water through w.c. when half turn cycle or
flush tank is kept open.6. Is ‘P’ – trap of w.c. properly cleaned to be without any lump.7. Is there continuous flow of water without any chock-up through nahani
trap when tested for at least 5 minutes. A check for finishing of watta below nahani trap cover.
8. Is the hot / cold operation proper.9. Are boiler connections properly plugged, non leaking & easy to remove ?10. Is the low level flushing water tank operation of commode proper ?11. Is the seat cover of commode fixed properly and cleaned ?12. Check whether provision for soap dish mode ?13. Are the mirror over w.h.b. and tile dado filled with sealant ?
- 56 -
14. Is height of mirror (Bottom) 1.25 m from toilet floor ?15. Is proper cleaning done for all sanitary fixtures ?16. Are the brackets of basin painted with oil paint ?17. Are open GI pipe connected to w.c. painted ?18. Is basin and counter if any fitted properly ? is the sturdy ?19. Are all the sanitary fittings in proper condition without any leakage or
crack ?20. Are the CI or PVC lines (7.5 cm / 10 cm) found leak proof when tested
for at least 15 min. with continue water flow ?21. Is the fixing of GI / CI / a.c. or PVC lines inline and proper clamping ?22. Are you sure there is no chock-up in the drainage chamber ?23. Are the main inlet and outlet GI lines of water tanks leak proof ?24. Is the white cement filled between w.h.p. and wall smooth, without ay
crack.25. Is PVC outlet pipe for w.h.b and kitchen sink fixed properly ?26. Is there any convention marked for municipal water tap and wash water
tap and also respectively GI pipes with colour bads.
G) ELECTRIFICATION :1. Is the individual meter allotted to flat ?2. Is the main switch fixed in meter cabinet ?3. Is there any testing report of electrical points given by electrical
contractor ?4. Are all the kitkat / fuses fitted properly ?5. Are all electrical switches working properly ?6. Is the earthing connection tested for working condition ?7. Are all the fan hooks in fan boxes ?8. Are all the switch boards fitted in line and level ?9. Is the position and quality of electrical points as per working drawings ?10. Are all extra amenities provided as per customer changes ?11. Is the colour of switches and accessories same as provided initially ?12. Are the battens / casing capping in perfect line and right angles ?13. Are the wires on batten fixed with proper clipping ?14. Are you sure there is no gap between wall and batten ?15. Are you sure that no screw is left from boards / switches / plugs etc ?16. Is the type of bell same as approved initially ?17. All the fittings fixed on board are inline and level or not ?
H) PAINTING :1. Is the painting properly done for walls and ceiling ?2. Is the oil painting done properly for doors and windows ?3. Are all the windows glasses cleaned by painter /4. Are all the door / windows fixtures cleaned by painter ?5. Is the painting done on lofts ?
- 57 -
6. Are all the paint stains cleaned properly ?7. Are all painting of battens / wires done properly throughout ?
I) MISCELLANEOUS :1. Is the letter box with owners name provided ?2. Are the keys for all doors and letter box tagged and their numbers
recorded ?3. Is the flat number displayed on electrical meter ?4. Is the electrical meter number and initial reading recorded ?
SALES EXECUTIVE AT SITE SITE IN-CHARGE SIGN & DATE SIGN & DATE
CERTIFICATETO,THE DIRECTOR __________________
I HEREBY CERTIFY THAT FLAT NO. ………………… IN BUILDING NO ……………................. AT PROJECT …………………………………….. IS HANDED OVER TO ME, INCLUDING OF ALL CONTRACT AMENMENTS AND IS TO THE SATISFACTION OF MYSELF.I HAVE NO COMPLAINT WHATSOEVER ABOUT ANYTHING IN THIS MATTER.
NAME OF SALES EXECUTIVE NAME OF THE FLAT OWNER(SIGN & DATE) (SIGN & DATE)
PASSENGER LIFT CL – 45
Check List :
1. Lift pit and lift shaft size as per lift manufacturers specifications and the work order.
2. Waterproofing to the lift pit and top of the machine room slab.3. Size of the shaft, size of the all door openings, floor levels and height of
machine room as per manufacturers requirements.4. Cleaning of lift pit, ducts and shafts.
- 58 -
5. All material produced is as per the specifications. (Refer work order)6. Angels and channels in the lift shaft / duct.7. Fixing of template.8. Scaffolding is made in the lift shaft is steardy and approved by the lift
erector.9. Electrical cabling and light points in shaft as per manufacturer’s
requirement.10. All the door frames (except ground floor) are fixed in the plumb line
fixed by the erector.11. Rope hole in the bottom slab of machine room and pockets are made in
the side walls for clamping of angles.12. Grouting of brackets and check rigidity.13. Whitewash in the lift shaft.14. For the machine room
a) I.P.S. flooring b) Ventilation and Exhaust fan.c) Shutter fixing d) Painting of machine room.e) Provide electrical points as per manufacturers requirement.
15. Angles (rails) fixing and roping.16. Machine of the lift is fixed with proper bolting, grouting, and anti
vibration pads are fixed below it.17. Flooring in the landing is done as per levels fixed previously and slope of
the flooring is away from the lift.18. Button box holes are marked and made properly.19. Ensure three phase meter exclusively for lift.20. Ensure the safety arrangement as
a) Ladder for pit.b) Weld mesh guard to the motor.c) Weld mesh guard to the window to avoid entry of the birds.d) All safety indicators working properly.e) Effectiveness of electrical switches.f) Emergency key operations.g) Instruction plates for the usefulness of the passengers guidance.h) Earthing done properly.
21. Ensure while the trial run of the lift that there are no jerks and sudden stops, floor levels matching to lift level at all floors.
22. Ensure about the guarantee period and certification from P.W.D.23. Instructions for users from manufacturer should be displayed inside lift
cabin.24. Maintenances :
a) Ensure local agency for A.M.C. with full address, telephone numbers of contractor and engineer.b) Frequency of Maintenance.c) Lubrication of wire ropes and guide rails.
- 59 -
d) Levels of machine oil.e) Greasing to the motor.f) Cleaning of all the equipment.g) Adjustment in electrical circuits, leading gate locks, lift car switches etc.h) Inspection of hoist way switches.
Records : Lift manufacturers name, address, telephone numbers.
Site representative attending the job.
Lift erection period lift handling over date.
Lift inspection report.
FIRE FIGHTING SYSTEM CL – 46
Check List :
1. The capacity of U.G.W.T. and O.H.W.T. with provision in that for fire fighting storage.
2. Other requirement as per municipal authorities in provisional N.O.C.3. Authorized agency for fire fighting installation work.4. Quality of material supplied by the contractor refers work order.5. Civil work like excavation, making holes to the bricks, wall, concrete
and refinishing of the same is done properly as per the requirements of working agency.
6. Scaffolding fixed in such a way that no work in fire fighting is disturbed.7. Testing done before inspection by Municipal authorities. 8. All G.I. / M.S. pipe line for straightness, level plumb, etc for perfect
ness.9. G.I. / M.S. line painted in red colour.
- 60 -
10. Check all required electrical connections are provided and are in working condition.
11. Check that all fire extinguishers are working and installed at proper location.
12. Fire hydrant located is easily accessible.
ROAD WORK CL – 47
Check List :A) GENERAL :1. Approved cross-section for road work.2. Demarcation of road on the layout plan and type of road to be provided.
Distinguish roads, ramps, open parking areas, paving etc. 3. Preparation of longitudinal and cross-section of the existing ground level
with respect to TBM4. Decide the layers in foundation (subgrade) and base course and wearing
surface thickness ( for bituminous road 2” and for concrete road min 4” ) 5. Decide the formation level with respect to plinth of buildings and
approach road.6. Balancing of cutting and filling area.7. Decide the longitudinal slope, camber, super elevation etc.
B) SUB GRADE :1. Initial ground level.2. Excavated final ground level.3. Murrum filling in layers and rolling by 8 to 10 ton roller.4. Record final sub grade levels.
- 61 -
C) BASE COURSE : By Soling 1. Record initial levels laid.2. Ensure the pipes are laid for cross-drain, electrical, drainage, water line
and any other service line.3. Soling with stone laid on their edges and chips filled in voids properly of
minimum 9” thickness.4. Width of soling 1’00” more than the width of road.5. Rolling of the road by 8 to 10 ton roller.6. Record final formation levels.7. Soling and WBM should be completed minimum 2 months before for
concrete roads.
D) BITUMINOUS ROAD (ON BASE COURSE) :1. Record initial levels. 2. Spreading the grit as per specification.3. Proper slope, gradient, camber.4. Decide grouting pattern (semi grout, full grout) and weight of bitumen
per square meter area.5. Ensure spreading of grit when bitumen is hot. Ensure the compaction by
roling.6. Final levels.E) TACK COAT, CARPET AND SEAL COAT (ON BASE COURSE) :1. Record initial levels.2. Decide weight of bitumen / sq.m. to be used.3. Mixing of 20 mm & 12 mm metal with bitumen.4. Spreading the mixture in uniform thickness.5. Rolling when mix is hot.6. Same procedure is to be adopted for seal coat (metal size smaller ¼”)7. Record final level.
F) CONCRETE ROAD (ON BASE COURSE) :1. Initial level about base course.2. Drawings showing layout of slabs panels, expansion joints, construction
joints.3. Proper cleaning.4. Channel thickness to match concrete thickness.5. Grade of concrete / mix design.6. Concreting in alternate bays. Area of each bay not to exceed 36 sq.meter.7. Filler for expansion joints.8. Needle vibrator and screed vibrator.9. Mechanical trovelling and vacuum dewatering.10. Broom finish.11. Curing by ponding for minimum 10 days.12. Filling bitumen 25 mm thick and deep in joints13. Provision for speed breakers.
- 62 -
G) PAVING BLOCKS :1. Approved drawings.2. Levels to be decided.3. Pattern of fixing to be decided.4. Block fixed in proper line, level and pattern.
H) STORM WATER SYSTEM :1. Approved drawings.2. Ensure that the storm water drain is not connected to sewage line in any
case.3. Ensure that no turbulence is created at junctions.4. Periodic cleaning / Pre monsoon precautions.
Records : Consumption Statement
LANDSCAPE WORKS CL – 48
Check List :
1. Latest approved layout of total landscape works from landscape consultant and parent architect.
2. For location and size of building and structures as Club House, Swimming Pool, Tennis Court, Garden, Library Hall, Gymnasium, Other Games, Children’s Park, Entrance Gate, Open Parking Place, Plantation refer to approved detail drawings of landscape of landscape consultants and RCC
3. Civil construction works to be completed with reference to other check list of construction activities.
4. Work order for specialized equipment along with, manufacturer’s specification, catalogues.
5. Work order for horticulture contractor, his scope of work, schedule of completion.
6. Arrangement for cutting, developing, manufacturing and watering of plants, lawns, and shrubs area.
7. Maintainace contracts for swimming pools water purification plants play game equipment, gymnasium equipment etc.
Records : Consumption Statement
- 63 -
CLEANING OF WATER TANK CL - 49
Check List :
1. Empty the water tank before starting any work.2. Arrange scraping by wire brush on the internal wall surface of the tank.3. Spray the liquid, bleaching with water by jet gun.4. Clean the entire tank surface by using water twice and then ensure there
is no wash water inside.5. Ensure there is no foreign particle inside the tank and then clear the tank
for use.6. Ensure that the person who is cleaning the tank uses the rubber gloss
during the cleaning.7. Enter the details of work done along with date and time in the water tank
cleaning register.8. A.M.C. may be given to approved agency.
Records : Water tank cleaning register.
- 64 -
CLEANING OF DRAIN LINE CL - 50
Check List :
1. Ensure that the person who is cleaning the drainage line uses the rubber gloss, mask & helmet.
2. Chamber to chamber cleaning by using steel rod.3. Ensure that the chamber should be cleaned by wire brush & hand broom.4. Clean the entire tank surface by using water twice and then ensure there
is no wash water inside.5. Ensure that this procedure follows quarterly every year.6. A.M.C. may be given to approved agency.
Records : Drain Line Cleaning register.
- 65 -
COLLECTION AND DISPOSAL OF DRY GARBAGE / WET GARBAGE CL - 51
Check List :
1. For 100 kg wet garbage per day (approximately half kg / family / day), construct 7 bins of size 8’ x 4’ x 2’6” (plastering is optional) over ground level along suitable part of the compound wall.
2. Bins should be marked “Monday, Tuesday,…..” for efficient disposal.3. Spread broken piece of bricks evenly at bottom of bins.4. On the layer of bricks spread coconut fiber, dry leaves. 5. Instruct every flat owner to collect wet and dry garbage in separate bags
or buckets.6. Ensure that the person is appointed for collecting wastage from every
house.7. Ensure that the person collects wet and dry garbage separately.8. Spread wet garbage inside bin (of respective day)9. Sprinkle rock-dust on it. 10. On these layers sprinkle vermi ++ Biosanitizer (Biosanitizer is an
enzyme used to process biodegradable waste in simple and efficient manner).
11. Cover it with thin layer of garden waste. 12. Sprinkle ‘Sujala Biosanitizer’ water with a watering can evenly over
entire bins. (Packet of ‘Sujala Biosanitizer’ to be left in watering can permanently)
13. Repeat the process in the next bin for next day.14. Spread the waste wet in every day in the respective bin only, but every
day sprinkle ‘Sujala Biosanitizer’ water in all bins. 15. Ensure that the dry wastage is separate like paper and plastic for
recycling and remaining garbage dump into the PMC separate dust bin for dry garbage.
16. Ensure that the PMC container comes and collects all the wastage and dump into the depot everyday.
17. A.M.C. may be given to approved agency.
Records : Waste Collecting Register.
- 66 -
LIFT MAINTENANCE CL – 52
Check List :
1. Ensure the annual maintenance contract is done.2. Ensure that the quarterly servicing is done for each lift.3. Ensure that the inspection of lift machine like (oil, breaks, setting & etc)
is done time to time.
Records : Lift Maintenance Register.
WORKING AND MAINTENANCE OF FIRE FIGHTING EQUIPMENTS CL –53
- 67 -
Check List :
1. Ensure that OHWT capacity 10,000 liters serve for fire fighting.2. Ensure that UGWT capacity 50,000 liters serve for fire fighting if
applicable.3. Ensure that 4” dia pipeline for each building in each one main valve &
NRV at OHWT & 3 HP with back up pump is connected to the line. Hydrant valve with lugs for every floor to attach delivery hose & branch pipe fire alarm system with control panel pill box & siren at ground floor.
4. Ensure that the oiling to lungs assembly, Female coupling hydrant Spindles, Gate Valves Spindle & pump checking for inner gaskets of hydrant valve & coupling.
5. Ensure that the Portable extinguisher for each building servicing fire extinguisher quarterly done and yearly refilling and demonstration before refilling.
6. Ensure that Fire Drill System is done quarterly.
Records : Fire Fighting Maintenance Register.
CLANING SWIMMING POOL CL – 54
Check List :
1. Ensure display of instructions for use to maintain hygienic condition of swimming pool.
- 68 -
2. Ensure that the water sample is tested by test kit from pool for Ph & Chlorine content. Ph = 7.6 > 7.2 & Chlorine = 2.00 > 1.5
3. Ensure that the materials for cleaning swimming pool are Chlorine = TCC Granules, Alum = Normal – Powder or Cub’s,Hypo (liquid chlorine) = 12 %, Cooper Sulphate = Granules.
4. Ensure that the brushing is done to bottom of pool and all impurities are collected to deep end of pool.
5. Ensure that the trolley pump section is done & outlet is connected to overflow trap which goes to filtration plant & all impurities are collected in filtration plant & clean water goes to pool.
6. Ensure that the back wash is done to filtration plant & filter is cleaned. 7. Ensure that the Risen of filter is done.
Dose for cleaning : Chlorine = 250 gm per day, Alum = 1.5 to 2.0 kg per four day, Hypo = 7 lit. Per day, C.S. = 1 kg per 15 days.
Records : Swimming Pool Cleaning Register.
SAFETY MEASURES AT SITE CL – 55
A) Following type of accidents may occur at site.i. Falling down, Slipping from height.ii. Falling of material from top.iii. Fireiv. Structural Collapse.v. Electrical Shocks.vi. Any other injuries.
- 69 -
B) Why accidents occur ?i. No use of Safety tools i.e. Helmets, Safety Belts, Safety Shoes, Hand
Glows, Goggles, Safety Nets, etcii. Not following of safety instructions.iii. Electricity misuse.iv. Negligence & Ignorance in following general safety rules
C) First Aidi. First Aid kit should be readily available.ii. Administration of First-Aid.iii. Information to ambulance.iv. Shifting to nearby hospital.v. Information to corporate office.vi. Information to other concerned agency.vii. Police, Fire Brigade etc
D) Following Corrective/Preventive Actions should be initiated by Project In-Charge
i. Proper training for allii. Contractor’s / Supplier have to be properly educated about safety.iii. Mock-Drills to be regularly conducted.iv. E.P.R. team to be alert at all times.v. Role of Security Supervisor is to make people use safety tools.vi. All are informed about the importance of safety and basic safety safe
practices.vii. Contractor’s / Supplier’s are educated about importance of safety.viii. Fire-Fighting equipments should be available at site and should be
regularly checked.ix. Electrical overloading or unauthorized connections should be avoided.x. Avoid working in night time.
RAIN WATER HARVESTING CL - 56
Due to unlimited use, sub-soil water level decreased. Due to building, roads, footpaths and concreting deposition of rain water to subsoil water is reduced. To reinstate this water bank rain water harvesting is absolutely necessary. This can be done by
a) Percolation Pit Method :Constructed in the open space at required intervalsSize : 1 m x 1 m x 1.5 m Filled with broken bricks / pebbles.Suitable for sandy sub-soil area.One unit for 250 sq.ft. area (approximately)
- 70 -
b) Bore Well Method :Roof top rain. Water may also be diverted to a bore well.A settlement / filter tank of required size to be provided.Overflow water may be diverted to a percolation pit nearby.Recharge through bore well is less effective than open wells.Defunct bore wells may also be used.
c) Open Well Method :Rain water from the terrace is diverted to the existing open well using PVC pipes through a filter chamber.The minimum size of filter chamber is 2’ x 2’ x 2’ filled with broken bricks in the bottom and sand on the top.
- 71 -
The chamber may be covered with RCC slab
d) Recharge Well Method (Shallow / Small) :Meant for large areas with heavy run-offSize : 3’00” diameter with 5’0” – 10’0” depth.Constructed with Brick / Concrete rings.Side walls must be perforated.Bottom (1’0”) is filled with brickbats.Covered with RCC slab / manhole.Suitable for sandy sub-soil area.
- 72 -
Note :1. For area with clay / hard formations recharge wells with
diameter (5’0”) / depth (10’0” – 15’0”) has to be constructed.2. Run-off water diverted through a filter media preferably.3. One wall is sufficient for areas with one ground extent.4. Rainwater from the open spaces may be diverted through mall
trenches.
e) Recharge trench with bore method :Along the recharge trench boreholes has to be drilled.Borehole interval, 10’0” – 15’0”Suitable for clay area.
- 73 -
Notes :1. Above structures are meant for area with large catchments like
Apartments / Big Complexes.2. RCC slab cover is optional.3. Top (1’00”) portion may be filled with sand.
f) Recharge Trench Method :Similar to recharge pit but longitudinal in shape.Size : 0.5 – 1.0 m wide / 1.0 – 1.5 m depth.Length may vary from 1.0 m – 5.0 mFilled with broken bricks / pebbles.Suitable for sandy sub-soil area.
- 74 -
g) Percolation Pit with Bore Method :A borehole is to be drilled at the bottom of the percolation pit.Bore hole size 150 – 300 mm diameter with 10’0” -15’0” depth. (approx.)Filled with broken bricks / pebbles.Suitable for clay area.
Note :1. Above structures are
meant for area with small catchments like individual houses.
2. RCC slab cover is optional.
3. Top (1’00”) portion may be filled with sand.
HANDLING, STORAGE AND PRESERVATION
A) For Cement, Lime, Sanla :1. 6” raised platform.
- 75 -
2. Water tight compartment with minimum ventilation.3. First in first out should be followed.4. Date of receipt to be displayed to avoid storage beyond one month.5. Maximum 10 bags should be stored in each stack.6. Separate stock for each brand stock position and tables.
B) For Steel :1. To be stacked on concrete block in different diameter stacks, diameter
wise stock and labels.2. Steel yard should have proper Access / Space for Vehicles, Fitters
movement.
C) For Sand, Metal, Dust, Grit, Bricks, Concrete Blocks :1. All above material should be stacked separately with avoiding direct
contact with soil.2. Should be stacked systematically for easy use and minimizes wastage.
D) For Door Frames and Shutters :1. Store in water tight compartment and lockable arrangement with firm
and leveled platform.2. Stack the material in different sizes and not more than 10 nos in each
stack 3. Wooden door frames shall be applied Black Japan on top and side and
primer for inside surface.4. Door Frame should be stacked in vertical manner and shutter in
horizontal manner.5. Stock position, Size wise, Labels.
E) For Door Fittings, C.P. Fittings, Sanitary ware, Plumbing Material : 1. Store in Lockable arrangement and free from dampness.2. Fittings should be store in racks in cupboards. 3. To avoid accidental breakages store in separate places.
F) For Rolling Shutter, Aluminum Window, MS Grill, MS Window, Wooden Panels :
1. Store in water tight components with lockable arrangement.2. Stack in such a manner to avoid bends, scratches and breakages.3. Material wise labelsG) For Flooring Material :1. Should be stacked on leveled floor with locking arrangement and free
from dampness.2. Store separately, Quality Wise, Colour wise, Size wise 3. Store position and labels.
Note : All rejected materials should be kept separately with identification tags.
- 76 -
Records :
1. All material inward and outward registers.2. Identification marks as per each consignment.3. Physical stock verification at every month end.
SAMPLING PLANSr. No.
Material Frequency Sampling Plan
Reference / Criteria
Remarks
1 Cement Every truck load
01 bag for every 100 bags. Random selection
For all criteria’s given in field test.Format MT-01
Instructions for use of specific brand of cement to be obtained from purchase dept..
2 Tor-steel For each delivery & every dia of steel, if wt
03 nos of 1 m length cut piece for each dia of
For all criteria’s given in field test.Format MT-02
If fields test results are not satisfactory send the samples for Laboratory test with
- 77 -
of each dia is 500 kg
steel received.
the approval of purchase department
3 Binding Wire
Every Delivery
01 bundle For all criteria’s given in field test. Format MT-03
----
4 Bricks Every truck load
03 bricks for every 1000 nos random selection
For all criteria’s given in field test.Format MT–8
If supplier and source is same for more than one truck load in a single day, then sampling from one truck load is enough.
5 Sand Every truck load
Sample from central part of the truck. Random selection
For all criteria’s given in field test.Format MT-04
If supplier and source is same for more than one truck load in a single day, then sampling from one truck load is enough.
6 Stone Metal
Every truck load
Sample from central part of truck
For all criteria’s given in field test.Format MT-05
If supplier & source is same for more than one truck load in a single day, then sampling from one truck load is enough.
7 Sanla Every delivery
01 bag for every 50 bags. Random selection
For all criteria’s given in field test.Format MT-09
If supplier & source is same for more than one truck load in a single day, then sampling from one truck load is enough.
Sr. No.
Material Frequency Sampling Plan
Reference / Criteria
Remarks
8 Ceramic / Glazed Tiles
Every delivery / 2 boxes for each 150 boxes for each brand & for each size.
05 tiles from each Random selection.
For all criteria’s given in field test Format MT-19
As per sample approved by Purchase Department
9 Kota / Kadappa/Tandur/ Granite/Marble
Every Delivery
Each Piece For all criteria’s given in field test.Format MT-20
As per sample approved by Purchase Department
- 78 -
10 Mosaic Tiles & Chequered Tiles
Every Delivery
05 tiles from every 100 numbers.Random selection.
For all criteria’s given in field test. Format MT-18
As per sample approved by Purchase Department
11 M.S. Door Frame
Every Delivery
Each Frame As specified in work order & criteria’s given in field test.
----
12 Timber / Wood
Every Delivery
Each member
For all criteria’s given in field test. Format MT-21
----
13 Flush Doors
Every Delivery
Each Shutter For each criteria given in field test Format MT-07
----
14 Rolling Shutter
Every Delivery
Each Shutter As specified in work order& criteria’s in field test Format MT-12
----
15 Aluminum windows & doors
Every flat and common area
One piece of each section used, including glass & gasket
As specified in work order & criteria’s given in field test. Format MT-13
As per sample approval by purchase department.
RECEIVING, INSPECTION AND TESTING :CEMENT FT - 01
Sr. No.
Field Test Details Required Result
1 Grade and Brand 33 / 43 / 53 Grade as indented of approved brand.
2 FRESHNESS TESTa) Manufacturing date from the date of manufacture. Older than 90 days should not be used.b) Lump Test
Printed Week, Month and Year
No lump should be present.3 FINENESS TEST
a) Feeling the fineness after rubbing in the fingures.b) When hand immersed in the bag
Should feel silky
Should feel hot / warm.
4 FLOATING TEST Should float on water before sinking
- 79 -
5 TYPE OF BAG Jute / Polythene / Paper Bag6 HANDLING & STORAGE a) Should be stacked / stored on
raised platformb) Flooring should be damp proof c) First in first out should be followed.d) Max 10 bags should be stored in each stacke) Receipt date of cement should be displayed.f) Period of storage : Ensure use within 3 months avoid storage more than 2 months.
RECEIVING, INSPECTION AND TESTING :STEEL FT -02
Sr. No.
Field Test Details Required Results
1. TYPE OF STEELa) Tor Steelb) Mild Steel
As indented Tor/CTD/Round bars, J round bars, TMT
2 COLOUR Steel Gray3 WEIGHT PER METER LENGTH
a) 6 mm diameter bar b) 8 mm diameter barc) 10 mm diameter bard) 12 mm diameter bare) 16 mm diameter barf) 20 mm diameter bar
Criteria for Acceptance
Weight = 2% tolerance
4 RUSTING SHOULD NOT BE FOUND5 DIAMETER AS PER INDENT6 BENDING TEST FOR HARDNESS
IF FELT NECESSARYIT SHOULD BEND SMOOTHLY & SHOULD NOT DEVELOP ANY CRACK
- 80 -
WHILE BENDING
RECEIVING, INSPECTION AND TESTING :BINDING WIRE FT – 03
Sr. No.
Field Test Details Required Results
1 GUAGE OF WIRE AS INDENTED (NORMAL GUAGE 17 S.W.G.)
2 BENDING TEST FOR HARDNESS
SHOULD BE SOFT FOR TWISTING
- 81 -
RECEIVING, INSPECTION AND TESTING :SAND (FINE AGRREGATE) FT – 04
Sr. No.
Field Test Details Required Results
1 SILT CONTENT IT SHOULD NOT BE MORE THAN 7% BY VOLUME
2 TYPE OF SAND COARSE OR FINE3 ORGANIC IMPURITIES SHOULD BE WITHIN LIMITS &
SHOULD BE IDENTIFIED BY VISUALISATION (SUCH AS MIXED QUALITY OF SHELU/SHINGLE & OTHERS)
4 STORAGE HANDLING 1) AREA TO BE MARKED FOR STORING TO ENABLE TRACEABILITY AFTER CONSUMPTION 2) DIRECT CONTACT OF MATERIALS WITH SOIL AVOIDED.3) STORED FOR EASY ACCESS FOR CONSUMPTION.
- 82 -
RECEIVING, INSPECTION AND TESTING :STONE METAL ( COARSE AGGREGATE ) FT – 05
Sr. No.
Field Test Details Required Result
1 SHAPE ANGULAGE NOT FLACKY, HARD
2 SIZE AS PER INDENT3 QUALITY OF STONE BLACKISH / GREY AND HARD 4 STORAGE HANDLING 1) AREA TO BE MARKED FOR
STORING TO ENABLE TRACEABILITY AFTER CONSUMPTION.2) DIRECT CONTACT OF MATERIALS WITH SOIL AVOIDED3) STORED FOR EASY ACCESS FOR CONSUMPTION.
- 83 -
RECEIVING, INSPECTION & TESTING :MURRUM FT – 06
Sr. No.
Field Test Details Required Result
1 QUALITY IT SHOULD NOT GET MUDDY2 SIZE SHOULD BE ACCEPTABLE3 HARDNESS PARTICLE SHOULD BE HARD
ENOUGH
- 84 -
RECEIVING, INSPECTION & TESTING :FLUSH DOOR FT – 07
Sr. No.
Field Test Details Required Result
1 TYPE SOLID CORE / BOILING WATER-PROOF
2 BONDING MATERIAL PHENOL BONDED3 DEFECTS FREE FROM BEND, TWISTING &
WARPING4 EDGES SHOULD BE SHARP, STRAIGHT
AND NO DAMAGES IN TOP LAYER
5 STIRAGE AND HANDLING 1) FLOOR TO BE DAMP PROOF2) SHOULD BE PLACED HORIZONTALLY3) ROOF SHOULD BE LEAK PROOF4) STORED IN LOCKABLE ARRANGEMENT
- 85 -
RECEIVING, INSPECTION & TESTING :BRICKS FT – 08
Sr. No.
Field Test Details Required Result
1 COLOUR REDDISH AND UNIFORM2 SIZE & MARK
1) ORDINARY BRICK2) THOKLA / GATTU BRICK
AS PER REQUIREMENT225 X 100 X 80 MM TOLERANCE 5MM225 X 150 X 100 MM TOLERANCE 5MM
3 FROG SHOULD NOT BE LESS THAN 1 CM & SHOULD NOT BE MORE THAN 2 CM
4 WATER ABSORPTION SHOULD BE BETWEEN 25 % TO 30 % BT WEIGHT
5 SOUNDNESS SHOULD GIVE CLEAR METTALIC SOUND
6 OVERBURNT BRICKS SHOULD NOT BE MORE THAN 5 % 7 BROKEN BRICKS SHOULD NOT BE MORE THAN 5 % 8 STRENGHT SHOULD NOT BREAK WHEN
THROWN TO THEIR FLAT FACE FROM A HEIGHT OF 60 CM (24”)
9 STORAGE & HANDLING 1) AREA TO BE MARKED FOR EASY TRACEABILITY AFTER CONSUMPTION 2) BRICKS SHOULD NOT BE THROWN 3) STACKED FOR EASY COUNTING 4) GROUND TO BE FAIRLY LEVELLED 5) STACKING SHALL BE DONE IN SUCH A PLACE WHERE DEBRIS, SCRAP, THROWN FROM THE BUILDING DOES NOT FALL ON THE STACK.
RECEIVING, INSPECTION & TESTING :INSTANT SANLA FT – 09
Sr. Field Test Results Required Results
- 86 -
No.1 COLOUR EVEN & UNIFORM (PINKISH OR
WHITE), BRAND AS PER ORDER2 STRENGTH IT SHOULD HARDEN WITHIN 12
HOURS AFTER APPLICATION ON WALLS.
3 CONSISTENCY IT SHOULD BE CONSISTENT & CAN BE JUDGE BY VISUAL OBSERVATION.
4 FRESHNESS NO LUMPS SHOULD BE OBSERVED
5 WEIGHT OF BAG AS PER ORDER6 STORAGE / HANDLING 1) SHOULD BE STORED ON
RAISED PLATFORM2) ROOFS & FLOORING SHOULD BE WATERPROOF3) STACKED IN LOCKABLE ARRANGEMENT
RECEIVING, INSPECTION & TESTING :M.S. WINDOWS FT – 10
Sr. No.
Field Test Results Required Results
1 A) CHECK FOR SECTION TRADE MARK EMBOSSED ON SECTION AT EVERY LENGTH @ 12 / 18 METER.
- 87 -
B) WEIGHT OF SECTION AHEMDABAD SECTION’S STANDARD WEIGHTS
2 ACCESSRIES PROVIDED AS PER ORDER3 CHECK WINDOW FOR
DIAGONAL SIZE / PLUMBBOTH DIAGONALS SHOULD BE SAME & CORRECT.
4 CHECK RED OXIDE & WELDING OVERALL FINISHING QUALITY
RED OXIDE SHOULD BE UNIFORM OVER WELD PORTION TO BE GRINDED.
5 OPENING OF SHUTTERS / LOUVERS
AS PER ORDER
6 LOCKING SYSTEM TOWER BOLTS
AS PER ORDER
7 HINGES BOX TYPE, SMOOTH WORKING8 STORAGE / HANDLING 1) STACKED AT AN ANGLE TO
THE WALL2) FLOOR & ROOF TO BE LEAK PROOF TO AVOID RUSTING3) TO BE LOCKED WITH M.S. CHAIN4) STAYS AND HANDLES TO BE STORED SEPERATELY.
RECEIVING, INSPECTION & TESTING :GLASS FIXING FT - 11
Sr. No.
Field Test Details Required Results
1 CHECK OVERALL SIZE, THICKNESS & TYPE OF GLASS
AS PER ORDER
2 CHECK FOR WAVYNESS, CRACKS, CAVITY
SHOULD BE FREE FROM ALL DEFECTS
3 CHECK FOR STRAIGHTNESS & RIGHT
SHOULD BE PERFECT
- 88 -
ANGLES4 SCRATCHES NO SCRATCHES5 CHECK FOR OVERALL
FIXING WORKSHOULD BE RIGID AND WELL PACKED ALLROUND
6 CHECK FOR PUTTI / GLAZING CLIP
AS PER ORDER / UNIFORM FIXING OF CLIP AT REQUIRED SPACING
7 TOLERANCE FOR THICKNESS BETWEEN 4 MM TO 7 MM THICK GLASS SHEET
= 1 %
RECEIVING, INSPECTION & TESTING :ROLLING SHUTTERS FT – 12
Sr. No.
Field Test Details Required Results
1 TYPE OF SHUTTER PULL AND PUSH TYPE / GEAR TYPE
2 GUAGE OF BOTTOM LOCK PLATE & LOCKING ARRANGEMENT
AS PER ORDER
3 TYPE OF SECTION USED FOR LATHS WITH GUAGE
18/20 GUAGE OR SHOULD BE AS PER ORDER.
4 CHECK SHUTTER LATHS IN 30 CMS LENGTHS
4 TO 4 ½ NUMBERS
5 TOP COVER IN ONE PIECE WITH CENTRALLY SUPPORTED
IN ONE PIECE OF 20/22 GUAGE
- 89 -
PLATE & ITS GUAGE6 BALL BEARING & SPRING CHECK FOR SMOOTH
OPERATION7 M.S. PIPE SHAFT DIAMETER MINIMUM 40 MM8 BRACKET PLATES & GUIDE
RAILAS PER ORDER
9 STOPPER ON EACH SIDE AS PER ORDER10 HANDLE 2 NOS RIVETTED OR AS PER
ORDER11 HOLD FAST AT EQUAL
DISTANCE30 CM IN LENGTH & 3 NOS ON EACH SIDE OR AS PER ORDER
12 RED OXIDE UNIFORM ON COAT13 EXTRA LOCIKING
ARRANGEMENT1 NO IN CENTER AS PER ORDER
14 OVERALL FINISHNG / FIXING SHOULD BE GOOD LOCKING OPERATION
15 GREASING FOR SPRINGS AND GUIDE
SUFFICIENT FOR EASY AND SMOOTH OPERATION
RECEIVING, INSPECTION & TESTING :ALUMINUM WINDOWS FT – 13
Sr. No.
Field Test Details Required Result
1 SIZE AS PER DRAWING / INDENT2 DIAGONAL AND PLUMB SHOULD BE PERFECT3 SECTION / ACCESSORIES
USED FOR TRACK, SHUTTER, INTER LOCKING ETC
AS PER ORDER
4 ASSEMBLY SHOULD BE PROPER WITH SCREW
5 CHECK FOR ACCESSORY POSITION & RUBBER / PVC PACKING FOR GLASS
AS PER ORDER
6 CHECK FOR QUALITY OF GLASS
AS PER ORDER
7 ANNODISING / COLOUR OF POWDER COATING
AS PER ORDER
8 MAKE ALUNIMUM SECTION AS PER ORDER
- 90 -
USED9 SLIDING OF GLASS PANELS ON ROLLERS & SMOOTH 10 SCRATCHES / BENDS /
CRACKS IF ANYFREE FROM ALL DEFECTS
11 PROVISION OF FLY PROOF SHUTTER
AS PER ORDER
12 PROVISION OF DRAIN HOLES IN WINDOW BOTTOM CHANNEL
ENSURE NO STAGNATION OF WATER
13 STORAGE / HANDLING 1) STACKED PROPERLY2) FREE FRO DAMPNESS & LEAKAGES3) STORE IN LOCKABLE AREA4) IN COUNTABLE POSITION
RECEIVING, INSPECTION & TESTING : PLUMBING G.I. PIPES & FITTINGS FT – 14
Sr. No.
Field Test Details Required Results
1 CLASS SEE COLOUR BAND FOR B OR C CLASS – REFER ORDER
2 DEFECTS FREE FROM ANY CRACKS3 LENGTH & SIZE STANDARD LENGTH & DIA.4 PIPE DIA. & WEIGHT AS PER CLASS OF PIPE5 PIPE FITTINGS ALL ISI MARKS6 STORAGE & HANDLING G.I. PIPES :
1) STORED IN STEEL RACK DIAWISE / CLASSWISE2) THREADED ENDS OF GI PIPES TO BE PROPERLY PROTECTED.3) TO BE STACKED IN COUNTABLE POSITIONG.I. PIPES FITTINGS :STORED IN WOODEN RACKS.(PIGEON HOLE TYPE DIAMETERWISE, PROPERLY CLASSIFIED LIKE ELBOW, TEE, ETC)
- 91 -
RECEIVING, INSPECTION & TESTING : PLUMBING C.I PIPES & FITTINGS FT – 15
Sr. No.
Field Test Details Required Results
1 CLASS SEE IS 1230-1979 MARK FOR RW PIPE & IS 1729-1979 MARK FOR SOIL PIPE.
2 DEFECTS FROM INSIDE PIN HOLES / ROUGH SURFACE3 PIPE FITTINGS VERY SMOOTH SURFACE FROM
INSIDE / CHECK MATCHING WITH PIPES.
4 LENGTH & SIZE REFER ORDER
STANDARD LENGTHS & DIA.
5 STORAGE & HANDLING STORED IN STACKS HORIZONTALLY, DIAWISE SEPERATELY ON WOODEN MEMBERS.
- 92 -
RECEIVING, INSPECTION & TESTING : PLUMBING PVC PIPES & FITTING FT – 16
Sr. No.
Field Test Details Required Results
1 CLASS MEDIUM (FOR PRESSURE 4 KG PER SQ.M.) HEAVY (FOR PRESSURE 6 KG PER SQ.M.)
2 DEFECTS SHOULD BE FREE FROM CRACKS, BEND, PIN HOLES
3 PIPE FITTINGS VERY SMOOTH SURFACE FROM INSIDE.NO BUR FROM INSIDE.CHECK JOINTING SYSTEM FOR USING LUBRICANT, RUBBER RING & SOLUTION.
4 LENGTH & SIZE REFER ORDER
STANDARD LENGTHS & DIA
5 STORAGE & HANDLING STORED IN PIGEON HOLE RACKS, DIAWISE, HORIZONTALLY WITH TAGSFITTINGS, LUBRICANTS, RUBBER RINGS / SOLUTION VERY CAREFULLY
- 93 -
RECEIVING, INSPECTION & TESTING : HUME PIPES FT – 17
Sr. No.
Field Test Results Required Results
1 LENGTH & SIZE LENGTH & DIA AS PER ORDER2 TYPE SPIGGOT END / COLLERED JOINT
AS PER ORDER3 CLASS
CLASS PIPES
PRESSURE P1 / P2 ETC OR NON PRESSURE NP2 CLASS FOR GRAVITY FLOW WE USE NP2
4 DEFECTS SHAPE – NOT EXACTLY CIRCULAR NO RINGING SOUND WHEN STUCK WITH LIGHT HAMMER CHECK DAMAGED ENDS & HOLES ON SURFACE.
5 STORAGE & HANDLING DIAWISE SEPERATELY ON WOODEN SLEEPERS HORIZONTALLY.AVOID ENDS ABUTTING EACH OTHER.
- 94 -
RECEIVING, INSPECTION & TESTING : MOSAIC TILES FT – 18
Sr. No.
Field Test Result Required Result
1 SIZE 25 CM X 25 CM (10” x 10”) 20 MM THK.30 CM X 30 CM (12” x 12”) 25 MM THK.
2 COLOUR GRAY / WHITE 3 NO. OF CHIPS & ITS
PROPORTION 0 TO 5 NOS SIZE OF CHIPS OR AS PER ORDER.
4 DIAGONAL OF TILE BOTH DIAGONAL SHOULD BE PERFECT
5 TOP LAYER THICKNESS NOT LESS THAN 6 MM 6 WATER ABSORPTION LESS THAN 10 %7 TOP SURFACE &
SHARPNESS OF EDGES SHOULD BE SMOOTH WITH SHARP EDGES
8 CRACKS, CAVITIES IN THE TILE
SHOULD BE FREE FROM ALL DEFECTS
9 STORAGE / HANDLING 1) STORED AGAINST THE WALL AT ANGLE.2) LOT WISE STORING IS MAINTAINED 3) TO BE STACKED IN COVERED AREA & NOT EXPOSED TO SUN 4) STACKED PERIOD SHALL BE MINIMUM 5) ARRANGED COLOURWISE 6) FLOOR SHALL BE FREE FROM DAMPNESS
- 95 -
RECEIVING, INSPECTION & TESTING : CERAMIC / GLAZED TILES FT – 19
Sr. No.
Field Test Details Required Results
1 SIZE, COLOUR, QUALITY AS PER ORDER2 DIAGONAL OF TILE BOTH DIAGONAL SHOULD BE
PERFECT3 EDGES / RIGHT ANGLES SHOULD BE CORRECT & PERFECT4 EVENESS OF TOP LAYER SHOULD BE SMOOTH & EVEN 5 STRAIGHTNESS OF TILES SHOULD BE STRAIGHT 6 CRACKS / CAVITIES,
HOLESTOP LAYER SHOULD BE FREE FROM ANY DEFECTS
7 CORNERS SHOULD BE STRAIGHT & NOT BRACKEN
8 THICKNESS NOT LESS THAN 5 MM9 TOP FINISHING & GLAZE UNIFORM & GOOD10 STORAGE / HANDLING 1) STACKING DONE LOTWISE,
COLOURWISE & SIZE WISE 2) FLOOR TO BE IN LEVEL3) 1ST / PREMIUM & 2ND / COMMERCIAL QUALITY SHALL BE STACKED SEPERATELY.4) STORED WITH LOCKING ARRANGEMENTS5) FLOOR SHALL BE FREE FROM DAMPNESS
RECEIVING, INSPECTION & TESTING :GRANITE/MARBLE/KOTAH/TANDOOR STONES FT – 20
Sr. Field Test Results Required Results
- 96 -
No.1 SIZE, COLOUR, QUALITY SHOULD BE UNIFORM COLOUR,
SIZE AS PER ORDER, SOUND & TOUGH
2 CHECK FOR POLISHING QUALITY & CUTTING
ONE FACE SHOULD BE POLISHED WITH FOUR SIDE MACHINE CUT, REFER ORDER
3 EDGES / DIAGONAL EDGES SHOULD BE STRAIGHT & AT RIGHT ANGLES TO EACH OTHER & DIAGONAL SHOULD BE PERFECT
4 PERFORMANCE OF TOP LAYER
SHOULD BE FREE FROM CRACKS
5 STAIGHTNESS OF TILES SHOULD BE STRAIGHT 6 THICKNESS UNIFORM THICKNESS AS PER
ORDER7 STORAGE / HANDLING 1) FLOOR TO BE IN LEVEL
2) LOTWISE VERTICAL STACKING TO BE DONE.
RECEIVING, INSPECTION & TESTING :WOOD/TIMBER/PLYWOOD/BLOCK BOARD/LAMINATE FT–21
Sr. No.
Field Test Details Required Results
1 TYPE OF WOOD REFER ORDER2 WETNESS & SEASONING AIR DRY & SEASINED WOOD3 TEXTURE UNIFORM
- 97 -
4 FREE FROM SPOTS SAPWOOD / OPEN SHAKES SPONGY HOLLOW CRACKS
5 AREA OF KNOTS OF SURFACE AREA
SHOULD NOT BE MORE THAN 15 %
6 GRAINS PARALLEL & NATURAL
RECEIVING, INSPECTION & TESTING :SHINGLE FT – 22
Sr. No.
Field Test Results Required Results
1 SIZE OF PARTICLES 100 % PASSING THROUGH 20 MM SIEVEPASSING THROUGH 10 MM SHOULD BE MORE THAN 80 %PASSING THROUGH 4.75 MM SHOULD NOT BE MORE THAN 30 %PASSING THROUGH 2.36 MM
- 98 -
SHOULD NOT BE MORE THAN 10 %2 IMPURITIES SHOULD NOT CONTAIN MUD
LUMPS CALCIUM, SHELLS3 STORAGE SEPARATE CLEAN AREA
AVOID DIRECT CONTACT WITH SOIL
RECEIVING, INSPECTION & TESTING :STONE DUST FT – 23
Sr. No.
Field Test Details Required Results
1 SIZE OF PARTICLES PASSING THROUGH 4.75 MM & 2.36 MM SIEVE – 100 % PASSING THROUGH 600 MICRON NOT MORE THAN 60 %PASSING THROUGH 150 MICRON NOT MORE THAN 20 %
2 IMPURITIES SHOULD NOT CONTAIN FLACKY PARTICLES
3 STORAGE SEPARATE CLEAN AREA.AVOID DIRECT CONTACT WITH SOIL
- 99 -
RECEIVING, INSPECTION & TESTING : CRUSHED SAND FT – 24
Sr. No.
Field Test Details Required Results
1 SIZE OF PARTICLES STANDARD GRADATION PASSING THROUGH 150 MICRON NOT MORE THAN 20 %PASSING THROUGH 75 MICRON NOT MORE THAN 15 %
2 IMPURITIES SHOULD NOT CONTAIN FLACKY PARTICLES
3 STORAGE SEPARATE CLEAN AREA.AVOID DIRECT CONTACT WITH SOIL
- 100 -
RECEIVING, INSPECTION & TESTING :FLY ASH FT – 25
Sr. No.
Field Test Details Required Results
1 SIZE AND PARTICLES PASSING THROUGH 75 MICRON 90 % RETAINED ON 75 MICRON NOT MORE THAN 10 %
2 IMPURITIES SOURCE FROM STAGE 4 OR ABOVE FROM THERMAL PLANT
3 STORAGE SEPERATE CLEAN AREAAVOID DIRECT CONTACT WITH SOIL.
- 101 -
RECEIVING, INSPECTION AND TESTING :FLY ASH BRICKS FT – 26
Sr. No.
Field Test Details Required Result
1 COLOUR UNIFORM2 SIZE & MARK
1) ORDINARY BRICK
2) THOKLA / GATTU BRICK
AS PER REQUIREMENT230 X 100 X 80 MM TOLERANCE 5MM230 X 150 X 100 MM TOLERANCE 5MM
3 FROG SHOULD NOT BE LESS THAN 1 CM & SHOULD NOT BE MORE THAN 2 CM
4 WATER ABSORPTION SHOULD BE BETWEEN 15 % TO 20 % BT WEIGHT
5 BROKEN BRICKS SHOULD NOT BE MORE THAN 1-2 %
6 STRENGHT SHOULD NOT BREAK WHEN THROWN TO THEIR FLAT FACE FROM A HEIGHT OF 60 CM (24”)ABOUT 12.5 N / MM2 AT 28 DAYS.
7 STORAGE & HANDLING 1) AREA TO BE MARKED FOR EASY TRACEABILITY AFTER
- 102 -
CONSUMPTION 2) BRICKS SHOULD NOT BE THROWN 3) STACKED FOR EASY COUNTING 4) GROUND TO BE FAIRLY LEVELLED. 5) STACKING SHALL BE DONE IN SUCH A PLACE WHERE DEBRIS, SCRAP, THROWN FROM THE BUILDING DOES NOT FALL ON THE STACK.
RECEIVING, INSPECTION AND TESTING :CITADEL BLOCKS FT – 27
Sr. No.
Field Test Details Required Result
1 COLOUR GREYISH WHITE2 SIZE & MARK AS PER REQUIREMENT
625 X 250 X 100 -300 MM(25 MM INCREMENT)TOLERANCE +/- 1.5 MM
3 FROG NOT REQUIRED4 BROKEN BRICKS SHOULD NOT BE MORE THAN 1-2
% 5 STRENGTH SHOULD NOT BREAK WHEN
THROWN TO THEIR FLAT FACE FROM A HEIGHT OF 60 CM (24”)ABOUT 35.0-40.0 KG / CM2
6 STORAGE & HANDLING 1) AREA TO BE MARKED FOR EASY TRACEABILITY AFTER CONSUMPTION 2) GROUND TO BE PERFECTLY LEVELLED. 3) STACKING SHALL BE DONE IN SUCH A PLACE WHERE DEBRIS, SCRAP, THROWN FROM THE BUILDING DOES NOT FALL ON THE STACK.4) SHOULD BE PROTECTED
- 103 -
AGAINST RAIN FALL / SNOW FALL.
RECEIVING, INSPECTION AND TESTING :CPVC PIPES FT - 28
Sr. No.
Field Test Details Required Result
1 SIZE DIAMETER OF PIPES & FITTINGS AS PER ORDER.
2 DEFECTS SHOULD BE FREE FROM CRACKS, BEND, PIN HOLES
3 PIPE FITTINGS SHOULD BE SMOOTH FROM INSIDE.CHECK FOR JOINING SYSTEM AND JOINING MATERIAL RECEIVED
4 STORAGE & HANDLING SHOULD BE STORED IN A RACK, DIAMETER-WISE.FITTINGS TO BE STORED DIAMETERWISE AND TYPEWISE SEPEARTELY.ALL MATERIALS TO BE PROPERLY TAGGED.
- 104 -
RECEIVING, INSPECTION AND TESTING :R.C.C. DOOR FRAMES MT – 29
Sr. No.
Field Test Details Required Result
1 APPEARANCE ON UNPACKING NO CRACKS SHOULD BE FOUND AND ALL EDGES INTACT.ALSO CHECK NUT BOLTS FOR HOLD FAST FIXING.
2 SIZE AND SHAPE WIDTH AND HEIGHT OF DOOR FRAME AS PER ORDER.CROSS SECTION AS PER ORDERON ASSEMBLY ALL SIDES SHOULD BE AT RIGHT ANGLES TO EACH OTHER.
3 FIXING ARRANGEMENT ARRANGEMENT FOR FIXING HINGES, HOLDFAST AND LOCKING ARRANGMENTS FOR ALL DOOR FITTINGS AS PER REQUIREMENTS
4 STORAGE / HANDLING TO BE STORED CAREFULLY ON LEVELLED GROUND, SEPERATE AS PER SIZE.TO BE STORED WITH LOCKING ARRANGEMENT
- 105 -
DUROCRETE MIX DESIGN MANUAL
What is Mix Design ?Like any structural member concrete needs to be designed for strength and workability. Mix design consists of determining relative quantities of cement sand, metal, water to achieve the desired strength & workability.
Advantages of Mix Design1. Mix design aims to achieve good quality concrete at site economically,
quality concrete means.Better Strength Better Durability Dens & Homogeneous Concrete
2. Economy in Cement Consumption :It is possible to save upto 15 % of cement for M20 grade of concrete with the help of concrete mix design. Savings in cement consumption increases with the grade of concrete. Lower cement content also results in lower heat of hydration & reduces shrinkage cracks.
Design Variables in Mix Design :A. Water Cement RatioB. Cement ContentC. Proportion of Fine & Coarse aggregate.D. Use of Admixtures.
Water Cement RatioWater cement ratio (W/C ratio) is the single most important factor governing the strength of concrete. Strength of concrete depends upon W/C ratio rather than the cement content. Higher the water cement ratio lower is the strength of concrete. As a thumb rule every 1 % increases in quantity of water added reduces the strength of concrete by 5 %. A water cement ratio of only 0.38 is required for complete hydration of cement. Water added for workability over & above this water cement ratio of 0.38 evaporates leaving cavities in the concrete. They reduces the strength and durability of concrete. Hence it is very important to control the water cement ratio on site.
Cement ContentCement is the core material in concrete which acts as a binding agent and imparts strength to the concrete. From durability considerations cement content should not be reduced below 290 kgs / m3 considering moderate conditions of exposure. IS 456 recommends higher cement contents for more severe conditions of
- 106 -
exposure of weathering agents to the concrete. It is not necessary that higher cement content would result in higher strength. Higher cement content helps us in getting the desired workability at a lower water cement ratio.
Gradation of Aggregates : Are two typesA. Coarse aggregates (Metal) : These are particles retained on standard IS
4.75 mm sieve.B. Fine Aggregate (Metal) : These are particles passing through IS 4.75 mm
sieve.
Proportion of fine aggregate to coarse aggregate is decided with the help of the gradation curves.The coarse aggregate of 20 mm & 10 mm are generally used for concreting. 20 mm coarse aggregate is defined as the one, which passes through 20 mm sieve and is retained on 10 mm sieve. While 10 mm metal should pass the 10 mm IS sieve and should be retained on 4.75 mm sieve. Some common problems to metal available in Pune are as follows :1. The metal has considerable proportion of over-size aggregates varying from 20 mm to 40 mm size. Generally when the sand is fine, smaller proportion of it is enough to get a cohesive mix, while coarser the sand, greater has to be its proportion in the concrete.Excess sand increases the water requirement of concrete & reduces the strength, while under – sandy mix results in segregation and honey combed concrete.Generally sand available in Pune is very coarse (FM > 3.2) and needs to be blended with fine particles (like stone dust) to get a cohesive mix.
Use of AdmixturesNow a day’s admixtures are rightly considered as a fourth ingredient of concrete. Use of plasticizers is essential to control the water cement ratio on site. Plasticizers help us in increasing the workability of concrete at lower water cement ratio. Hence we can achieve much higher strength at the same cement content. Use of plasticizers is economical as the cost incurred on them is less than the cost of cement saved. This is made possible by mix design.
IMPLEMENTATION OF MIX DESIGN ON SITE Items necessary on site for Mix Design. 1. Set of 12 cube moulds.2. A slump cone, tamping rod, and a scale.3. Weighing balance of 5 kg with accuracy of 2 gms.4. Spring balance of 50 kgs5. Buckets of known capability for addition of water preferably 5 to 7 liters
in capacity 6. 250 ml measuring cylinder.7. Forms of various sizes.
- 107 -
Capacity in Liters Nos L B H Size (in cms)353025201510
112112
40 * 25 * 3540 * 25 * 30 40 * 25 * 2540 * 25 * 2040 * 25 * 1540 * 25 * 10
B. Measuring pan & Stove for heating the sand.
3. IMPORTANT FOR IMPLEMENTATION OF MIX DESIGN
1. Cement brands to be used should be standardized in advance.2. Make regular corrections on the proportions of mix design for
a) Moisture in sandb) Absorption by metalc) Bulk density of sandd) Changes in fineness of sand
3. Regularly check the weight of cement bags.4. The water cement ratio on the site should be strictly controlled. The
water cement ratio can be controlled by maintaining the slump as per the design specifications.
5. The slump readings should be taken after every 25 bags of concreting. The slump readings should be specially taken for the batches from which cube casting is done.
6. Cement bags to be used should not be older than one month. Cement used should not have lumps and should give a cool feel on hand.
7. Extremely coarse sand or silty sand should not be used.
Note : If any of the above conditions are not satisfied a trial mix should be conducted at laboratory to determine fresh proportions.
4. STANDARD CORRECTIONS FOR IMPLEMENTING MIX DESIGN
3.1 Corrections for surface moisture in sand.Sand contains some fraction of water as surface moisture. This moisture affects he water cement ratio of concrete. Water cement ratio takes into account the total water available for hydration of cement.
- 108 -
Water cement ratio = (water added per batch + Surface moisture in sand – absorption of coarse aggregate) / 50
Finding surface moisture of sandTake 500 gms of sand & hat it in tray gently till sand is dry and starts flowing freely. Surface dry sand is weighed again to find the loss in weight.Surface Moisture = W / (500 - w)
Note : It is important not to over heat the sand
To get a rough estimate of surface moisture following thumb rule may be used when sand is not extremely wet.
Moisture in Sand Bulkage
1 %2 %3 %4 %5 %
Medium Sand8 %16 %22 %27 %29 %
Coarse Sand6 %12 %15 %17 %18 %
Water to be added per batch = (water cement ratio * 50) – Surface moisture * wt. of sand per batchIf moisture content = 4 %
Wt of sand = 135 kgs
Water-cement ratio = 0.55
Water to be added per batch = 0.55 * 50 – 4 % * 135
= 27.5 – 5.4
= 22.11 liters
Weight of sand per batch should be increased correspondingly by wt. of
surface moisture in sand e.g. 5.4 kgs
Moisture content in sand will vary from day to day and also with
different lots of sand. It is therefore very important to make corrections
for moisture in sand to maintain w/c ratio. If slump on site is kept under
control, the water cement ratio is automatically controlled.
FINDING AGGREGATE ABSORPTION :
- 109 -
For any mix design, the coarse aggregate is considered to be in saturated surface dry condition. Whereas the metal on sites is often in bone dry condition (especially in summers). This dry aggregate often absorbs the water added in concrete & reduces the workability of concrete. Correction for surface absorption is necessary to maintain the water cement ratio. A correction of 1 % to 2 % of coarse aggregate may be made in case of bone dry condition of aggregate. For example if the aggregate absorption is 2 % and water and total weight of aggregates is 180 kgs thenAggregate absorption = 0.02 * 180
= 3.6 liters.Hence quantity of water added (from previous example) = 22.1 + 3.6
= 25.7
CORRECTION FOR BULK DENSITY :Every mix design is always done considering weights of different ingredients. In case volume batching is done on site, the weights of aggregates need to be converted into volumes. This is done with the help of bulk densities of aggregates.Bulk density = weight of material in kgs
----------------------------- volume in liters
Bulk density can be measured on site by filling a standard 35 liters pharma with aggregate & weighing the aggregate filled in the form.e.g. wt. of sand in 35 liters pharma = 58 kgsBulk density = 58 / 35 = 1.66 kgs / liters.Volume of sand per batch = wt. of aggregate per batch
------------------------------ Bulk density
VOLUME BATCHINGFor example, if weight of sand per batch = 135 kgs.Volume of sand = 135 / 1.66 = 81.3 liters, say 80 liters.Hence use 2 forms of 25 liters & one form of 30 liters. Bulk density of sand changes with bulkage. Hence correction for bulk density of sand should be made every day.Bulk density of metal is between 1.4 kg / lit to 1.5 kg / lit whereas bulk density of sand varies with bulkage and usually lies between 1.6 to 1.8 kg / lit.
CORRECTION FOR BULKAGE :This is done in case of volume batching of concrete. When sand is moist it bulks i.e. it occupies greater volume. Hence, less weight of sand is taken in the given volume. In other words, the bulk density of sand
- 110 -
changes. If correction of bulk density is done. Otherwise, volume of sand needs to be increased in proportion of bulkage.
Measuring bulkage on siteTake 100 mls of sand in 250 ml. Baker and add water so as to completely submerge the sand. Shake the beaker well and keep it steady for some time. Note the level to which it settles.Bulkage % = Original Level - New Level * 100
------------------------------------------New Level
CHECK THE SILT CONTENT :Excessive silt in sand affects the bond between cement and sand. This reduces the strength of concrete. This problem is quite severe during monsoon.Measuring silt content on site.Take 50 ml of water in 250 ml beaker and add some salt to it. Add sand to it till 100 ml mark is reached. Again add water up to 150 ml. Stir the sand well to wash it in salt water. Keep the beaker still for 3 hours. Observe the thickness of silt layer.Silt content = Height of Silt Layer (ml) * 100
------------------------------------Height of Sand
Sand with silt content greater than 7 % calculated by above method should not be used for concreting.
CORRECTIONS FOR CHANGES IN GRADATION OF SAND :Sand shows lot of variation on sites because of changes in source of supply. The fineness module of sand in Pune varies from 3.2 to 3.8. The IS specifies a limit of 2.2 (fine sand) to 33.2 (coarse sand) for fine aggregate. This means that sand available in Pune is extremely coarse. This is partly because of absence of fines in the sand and 10 % to 15 % is retained on 4.75 mm sieve as chal or shingle present in the sand. Hence, in case of extremely coarse sand, use of stone dust up to liters is recommended. If sand available on site is coarser than the one used for mix design, following correction may be made.
A. WEIGHT BATCHING i. Increase in the weight of sand up to 15 kgs and reduce the weight of metal by equal quantity. Total weight of aggregate going per batch
should remain constant.ii. If the mix does not improve with above correction, replace up to 15 kgs of sand by dust in the weights mentioned in the design.
- 111 -
B. VOLUME BATCHING i. Increase the volume of sand by 10 liters and reduce volume of metal by 10 lit. ii. If the mix does not improve with above correction replace 10 liters of sand in mix design proportion by 10 lits of dust.
Following precautions should be taken when stone dust is to use.
Stone dust should not be too fine or powdery ( FM should be between 2.0 to 2.5 )
It should be used used in limited quantity as mentioned above unless, higher quantity is recommended by the laboratory.
Strict control on water cement ratio should be kept. Stone dust reduces the workability; hence the water cement ratio is likely to increase. The slump may be maintained 2 cms below the value given in the mix design.
Note : If above corrections in the proportion do not yield satisfactory mix, fresh trial should be conducted at the laboratory for a revised mix design.
DUROCRETEEngineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005Telefax - 25520456, 25534335
Date : 29 Jan. 2005MIX DESIGN SHEET
Name : Purpose of Experiment : Mix design for M15 grade of concreteSite : Brand of Cement : Ultratech 43 Grade.
PROPOSED MIX PROPORTIONS :
CEMENT FLY ASH
CRUSHED SAND
20 MM
WATER ADMIXTURES
By Wt. (Kg)
50 9 183 224 33.04 ---- ml
Wt. in Kg
255 45 869 1151 174.90 ---- ml
- 112 -
/ m3
Water Cement Ratio = 0.56 Total Cementetious Material 300 kg/m3 Cement Used = Ultratech 43 Grade (W-47, M-11, Y-04)Fly Ash used = Pozzocem 63 TM * Slump not to exceed 50 mm
Observations of Laboratory Trial :Plastic Density = 2547 kg / m3
Compaction factor = 0.94Average 28 days Compressive strength = 27.39 N/mm2
* Corrections for moisture content in sand & aggregate absorption in metal should be made on water / cement ratio (Refer our mix design manual)* Any change in material like cement, plasticizer, sand or aggregate would require re-validation of design.* The volumetric proportion are rounded of to nearest 5 liters, however, in case of volume batching, weight to volume conversion should be done on the basis of Dry Loose Bulk Density of ingredients actually found out at site.* The above mix design requires certain control practices on site to ensure results.
Target Mean Strength = fck N / mm2 + (K x Std. Deviation)K = Himsworth Constant which is 1.65 for 5 % results to fall below the characteristic strength.Standard Deviation Assumed = 3.5 N / mm2 (As per IS 456 – 2000 )Table 8, Clause 9.2.4.2Target Mean Strength = 15.00 + 1.65 x 3.5 = 20.78 N/mm2
- 113 -
DUROCRETEEngineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005Telefax - 25520456, 25534335
Date : 22 Oct. 2004 MIX DESIGN SHEET Name : Purpose of Experiment : Mix design for M20 grade of concreteSite : Brand of Cement : Vasavadatta 43 Grade
PROPOSED MIX PROPORTIONS :
CEMENT FLY ASH
CRUSHED SAND
20 MM
WATER ADMIXTURES
By Wt. (Kg)
50 12 164 217 33.00 ---- ml
Wt. in Kg / m3
265 65 869 1151 174.90 ---- ml
Water Cement Ratio = 0.53 Total Cementetious Material 330 kg/m3
Cement Used = Vasavadatta 43 Grade Fly Ash used = Super Pozz* Slump not to exceed 45 mm
Observations of Laboratory Trial :Plastic Density = 2525 kg / m3
- 114 -
Compaction factor = 0.97Average 7 days Compressive Strength = 20.03 N/mm2
Average 28 days Compressive strength = 32.28 N/mm2
* Corrections for moisture content in sand & aggregate absorption in metal should be made on water / cement ratio (Refer our mix design manual)* Any change in material like cement, plasticizer, sand or aggregate would require re-validation of design.* The volumetric proportion are rounded of to nearest 5 liters, however, in case of volume batching, weight to volume conversion should be done on the basis of Dry Loose Bulk Density of ingredients actually found out at site.* The above mix design requires certain control practices on site to ensure results.
Target Mean Strength = fck N / mm2 + (K x Std. Deviation)K = Himsworth Constant which is 1.65 for 5 % results to fall below the characteristic strength.Standard Deviation Assumed = 4 N / mm2 (As per IS 456 – 2000 )Table 8, Clause 9.2.4.2Target Mean Strength = 20.00 + 1.65 x 4 = 26.60 N/mm2
- 115 -
DUROCRETEEngineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005Telefax - 25520456, 25534335
Date : 22 Oct. 2004MIX DESIGN SHEET
Name : Purpose of Experiment : Mix design for M25 grade of concreteSite : Brand of Cement : Vasavadatta 43 Grade
PROPOSED MIX PROPORTIONS :
CEMENT
FLY ASH
CRUSHED SAND
10 MM
20 MM
WATER
ADMIXTURE
By Wt. (Kg)
50 12 140 34 168 30.41 ---- ml
Wt. in Kg / m3
290 70 813 198 971 176.40 ----- ml
Water Cement Ratio = 0.49 Total Cementetious Material 360 kg/m3
Cement Used = Vasavadatta 43 Grade Fly Ash used = Super Pozz* Slump not to exceed 50 mm
Observations of Laboratory Trial :Plastic Density = 2519 kg / m3
Compaction factor = 0.97Average 7 days Compressive Strength = 21.31 N/mm2
Average 28 days Compressive strength = 32.01 N/mm2
* Corrections for moisture content in sand & aggregate absorption in metal should be made on water / cement ratio (Refer our mix design manual)* Any change in material like cement, plasticizer, sand or aggregate would require re-validation of design.
- 116 -
* The volumetric proportion are rounded of to nearest 5 liters, however, in case of volume batching, weight to volume conversion should be done on the basis of Dry Loose Bulk Density of ingredients actually found out at site.* The above mix design requires certain control practices on site to ensure results.
Target Mean Strength = fck N / mm2 + (K x Std. Deviation)K = Himsworth Constant which is 1.65 for 5 % results to fall below the characteristic strength.Standard Deviation Assumed = 4.0 N / mm2 (As per IS 456 – 2000 )Table 8, Clause 9.2.4.2Target Mean Strength = 25.00 + 1.65 x 4.0 = 31.60 N/mm2
- 117 -
DUROCRETEEngineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005Telefax - 25520456, 25534335
Date : 15 Sept. 2006MIX DESIGN SHEET
Name : Purpose of Experiment : Mix design for M30 grade of concreteSite : Brand of Cement : Coromandal 43 Grade
PROPOSED MIX PROPORTIONS :CEMENT FLY
ASHCRUSHED SAND
20 mm
WATER ADMIXTURES
By Wt. (Kg)
50 08 100 178 24.94 ---- ml
Wt. in Kg / m3
355 60 708 1259 178.45 ---- ml
Water Cement Ratio = 0.42 Total Cementetious Material 415 kg/m3 Cement Used = Coromandal 43 Grade (W-27, M-07, Y-06)Fly Ash used = Star Ash* Slump not to exceed 70 mm
Observations of Laboratory Trial :Plastic Density = 2561 kg / m3 Compaction factor = 0.91Average 7 days Compressive strength = 28.08 N / mm2
Average 28 days Compressive strength = 40.55 N / mm2
* Corrections for moisture content in sand & aggregate absorption in metal should be made on water / cement ratio (Refer our mix design manual)* Any change in material like cement, plasticizer, sand or aggregate would require re-validation of design.* The above mix design requires certain control practices on site to ensure results.* Given mix proportions will be confirmed on achieving satisfactory 28 day’s compressive strength at our laboratory.* You are requested to take a site trial and give us a feedback, which will enable us to give you the corrections in the mix, before your actual casting.Target Mean Strength = fck N / mm2 + (K x Std. Deviation)K = Himsworth Constant which is 1.65 for 5 % results to fall below the characteristic strength.Standard Deviation Assumed = 4.0 N / mm2 (As per IS 456 – 2000 )
- 118 -
Table 8, Clause 9.2.4.2Target Mean Strength = 25.00 + 1.65 x 4.0 = 31.60 N/mm2
DUROCRETEEngineering Services Pvt. Ltd.
1160 / 5, Shivaji Nagar, Gharpure Colony, Pune – 411 005Telefax - 25520456, 25534335
MIX DESIGN SHEET Name :
- 119 -
Purpose of Experiment : Mix design for M35 grade of concreteSite : Brand of Cement : Vasavadatta 43 Grade
PROPOSED MIX PROPORTIONS :
CEMENT CRUSHED SAND
20 MM WATER ADMIXTURES
By Wt. (Kg)
50 84 137 20.00 400 ml
Wt. in Kg / m3
430 724 1182 172.00 3440 ml
Water Cement Ratio = 0.40Cement Used = Vasavadatta 43 Grade Fly Ash used = Super PozzAdmixture Used = Dr. Fixit Pidiproof LW
* Slump not to exceed 50 mm Observations of Laboratory Trial :Plastic Density = 2508 kg / m3
Compaction Factor = 0.92* Corrections for moisture content in sand & aggregate absorption in metal should be made on water / cement ratio (Refer our mix design manual)* Any change in material like cement, plasticizer, sand or aggregate would require re-validation of design.* The above mix design requires certain control practices on site to ensure results.* Given mix proportions will be confirmed on achieving satisfactory 28 day’s compressive strength at our laboratory.* You are requested to take a site trial and give us a feedback, which will enable us to give you the corrections in the mix, before your actual casting.* The above mix proportions are based on 3 day’s compressive strength achieved at our laboratory = 24.37 N /mm2
Crushed Sand Moisture Content = 4.56 % Loose Bulk Density = 1.29 kg / lit (for conversion to volumetric)Water Absorption = 3.37 %Specific Gravity = 2.500
Sieve Sizes Wt. Retained Wt. Retained Cumu. Wt. Cumu.
- 120 -
(gm) % Retained % Passing %10 mm 3 0.30 0.30 99.704.75 mm 19 1.90 2.20 97.802.36 mm 233 23.30 25.50 74.501.18 mm 200 20.00 45.50 54.50600 micron 191 19.10 64.60 35.40300 micron 100 10.00 74.60 25.40150 micron 85 8.50 83.10 16.9075 micron 100 10.00 93.10 6.90Pan 69 6.90 100.00 0.00Total 1000
F.M. = 2.958
20 mm MetalSpecific Gravity = 2.872Water Absorption = 1.21 %Flakiness Index = 21.05 %Loose Bulk Density = 1.44 kg / lit (for conversion to volumetric)Sieve Size Wt. (gm)
Retained Wt. Retained %
Cumu. Wt. Retain %
Cumu. Passing %
IS Passing % Limits
40 mm 0 0.00 0.00 100.00 10025 mm 0 0.00 0.00 100.00 ----20 mm 290 14.50 14.50 85.00 85 to 10016 mm 806 40.30 54.80 45.20 ----12.5 mm 689 34.45 89.25 10.75 ----10 mm 191 9.55 98.80 1.20 0 to 20Pan 24 1.20 100.00 0.00 ----Total 2000
- 121 -
- 122 -
- 123 -
- 124 -
EQUIVALENT UNITS / CONVERSION TABLESA) LINEAR MEASUREMENTS :Sr. No. Unit Equivalent Unit1 1 Kilometer 1000 Meter
- 125 -
2 1 Kilometer 0.62 Miles3 1 Meter 100 Centimeters4 1 Meter 3.28 Feet5 1 Meter 1.093 Yards6 1 Centimeter 10 Millimeter7 1 Centimeter 0.393 Inch8 1 Mile 8.00 Furlong9 1 Furlong 220 Yards10 1 Yard 3 Feet11 1Mile 5280 FeetB) WEIGHT MEASUREMENTS :Sr. No. Unit Equivalent Unit1 1 Tonne 1000 Kilogram2 1 Kilogram 1000 Grams3 1 Kilogram 2.205 Pounds 4 1 Quintal 100 Kilogram5 1 Gram 0.086 Tola6 1 Ounce 28.35 GramsC) AREA MEASUREMENTS :Sr. No. Unit Equivalent Unit1 1 Sq. Kilometer 106 Sq. Meter2 1 Sq. Kilometer 0.386 Sq. Miles3 1 Sq. Meter 10000 Sq. Centimeter4 1 Sq. Meter 10.76 Sq. Ft.5 1 Acre 40 Guntha6 1 Guntha 1089 Sq.Ft.7 1 Acre 43560 Sq.Ft.8 1 Acre 4047 Sq. Meter9 1 Hector 100 Are10 1 Are 100 Sq. Meters11 1 Hector 10000 sq. Meters12 1 Hector 2047 Acre13 1 Brass 100 Sq.Ft.14 1 Brass 9.29 Sq. Meter15 1 Acre 4840 Sq. YardsD) VOLUME MEASUREMENTS :
Sr. No. Unit Equivalent Unit1 1 Cu. Meter 106 Cu. Centimeter2 1 Cu. Meter 35.28 Cu. Ft.3 1 Cu. Meter 220.14 Gallon4 1 Cu. Meter 1000 Liters5 1 Cu. Feet 6.24 Gallon
- 126 -
6 1 Gallon 4.546 Liters7 1 Cu. Feet 28.315 Liters8 1 Brass 100 Cu. Ft.9 1 Brass 2.83 Cu. Meter
WEIGHT’S OF MATERIALS
Sr. No. Material Weight Kg. / cum1 Cement 14402 Steel 78503 Sand a) Dry
b) River16001840
4 Stone (Basalt) 2850 to 29605 Water 10006 PCC 22407 RCC (2 % steel) 24208 Bricks 1600 to 19209 Brick Masonry 192010 Soil 176011 Cement Concrete Blocks (Solid) 180012 Cement Mortar 208013 Lime Mortar 176014 Lime 64015 Glass 253016 Teak Wood 670 to 83017 Sal Wood 99018 Marble Stone 262019 Granite Stone 2460 to 280020 Cuddappah 272021 A.C. Sheet (Corrugated) 16 kg / sqm22 Bitumen 1040
USEFUL NOTES ON CEMENT
1 Ton of Portland Cement = 20 bags1 cu.ft. of Portland Cement weights 90.94 lbs. when loosely filled.
Average weight of 1:2:4 concrete :1) Coke bricks aggregate 100 lbs per cu.ft.2) Clinker aggregate 110 lbs per cu.ft.3) Brick aggregate 125 lbs per cu.ft.4) Ballast aggregate 145 lbs per cu.ft.
Average weight of 1:2:4 reinforced concrete is 150 lbs per cu.ft.
- 127 -
1 cu.ft. of loose Portland Cement paste will make about :4.1 cu.ft. of concrete mixed 1:2:45.1 cu.ft. of concrete mixed 1:2.5:55.8 cu.ft. of concrete mixed 1:3:67.5 cu.ft. of concrete mixed 1:4:81 cu.ft. of loose Portland Cement neat as cement paste will cover 9.5 sq.ft. 1” thk.
1 cu.ft. of 1 loose Portland Cement with 1 part of sand will cover 16.8 sq.ft. 1” thick1 cu.ft. of 1 loose Portland Cement with 2 part of sand will cover 29 sq.ft. 1” thk.1 cu.ft. of 1 loose Portland Cement with 3 part of sand will cover 35.7 sq.ft. 1” thick
1 cu.ft. of loose Portland Cement with 6 parts of sand will lay about 410 bricks with 3/8” joints and 527 bricks with 1/4” joints
STANDARD MATERIAL CONSUMPTION CONSTANTS ON BUILT-UP AREA BASIS
Sr. No.
Material Item of Work Quantity / Sq.M.
Quantity / Sq.Ft.
1 Cement For RCC workFor Masonry WorkFor Plaster WorkFor Other WorkTotal
1.94 bags0.43 bags1.18 bags0.32 bags3.87 bags
0.18 bag0.04 bag0.11 bag0.03 bag0.38 bag
2 Steel For RCC work 24.25 kg 2.25 kg3 Sand For RCC work
For Masonry workFor Internal PlasterFor External Plaster
0.21 cum0.05 cum0.23 cum0.15 cum
0.70 cft0.16 cft0.75 cft0.50 cft
- 128 -
For TilingFor Water-ProofingFor OthersTotal
0.04 cum0.03 cum0.01 cum0.72 cum
0.13 cft0.09 cft0.02 cft2.35 cft
4 Metal For RCC work 0.27 cum 0.90 cft5 Rubble For Plinth Soling 0.06 cum 0.20 cft6 Murrum For Plinth Filling 0.23 cum 0.75 cft7 Bricks 6”
(Thokla)For Ext. Wall (6” thk.)For Int. Wall (6” thk.)Total
43 nos32 nos75 nos
04 nos03 nos07 nos
8 Sunla For Internal Plastering 0.27 bag 0.025 bag9 Flooring
TilesFor all rooms and balcony/terrace flooring
0.75 sqm 0.75 sq.ft
10 Skirting For all rooms and balcony/terrace flooring
0.25 rm 0.25 rft
11 Bath/Toilet For Flooring Dado
0.05 sqm0.20 sqm
0.05 sq.ft.0.20 sq.ft.
12 Kitchen Platform
---- 0.04 rm 0.012 rft
13 Parking Flooring
Parking Area 0.15 sqm 0.15 sq.ft.
14 Staircase stone flooring
For RisersFor TradesFor LandingsTotal
0.014 sqm0.028 sqm0.022 sqm0.084 sqm
0.014 sq.ft.0.028 sq.ft.0.022 sq.ft.0.084 sq.ft.
Sr. No.
Material Item of Work Quantity / Sq.M.
Quantity / Sq.Ft.
15 Brick bats For Water-Proofing 0.03 cum 0.10 cft16 Door
Frames---- 0.09 nos 0.0085 nos
17 Door Shutters
---- 0.14 sqm 0.14 sq.ft
18 Concrete Grills
For Staircase 0.03 sqm 0.03 sq.ft
CONSTRUCTION MATERIALS WASTAGE : PLANNING NORMS
SR. NO. TYPE OF MATERIALS PLANNED WASTAGE1 Cement 2 %2 Sand 10 %3 Aggregate 5 %4 Concrete Structural 2 %5 Concrete Blinding (Lean) 10 %6 Reinforced Steel Bars 3 %
- 129 -
7 Reinforced Steel Mesh 10 %8 PVC Sheeting 15 %9 Timbering in Trenches 5 %10 Stone Masonry 5 %11 Marble Lining 20 %12 Wood for Door Frame 5 to 7.5 %13 Wood for Shutters 10 %14 Wood for Flooring / Walling 5 to 10 %15 Sheet Roofing 2 %16 Tile Roofing 5 %17 Floor Tiling 2 to 5 %18 Wall Tiling 3 %19 Pigments 5 %20 Paints 5 %
PERCENTAGE BREAK-UP FOR DIFFERENT CONSTRUCTION ACTIVITIES (RESIDENTIAL) :
Activity Percentage Cost Break-Up(Material + Labour)
Work up to Plinth (Excl. RCC) 2 %RCC 28 %Masonry and Plaster 21 %Aluminum Windows 4 %Door Frames and Shutters 5 %Railing 1 %Water Proofing 3 %Flooring and Tiling 15 %Painting 3 %Lift 4 %Fire Fighting 1 %Entrance Lobby and General 1 %Plumbing / Sanitation 5 %Electrical Work 7 %TOTAL 100 %
Activity Percentage Cost Break-Up (Material)Cement 14 %Sand 11 %
- 130 -
Metal 3 %Steel 12 %Bricks 4 %Tiles 17 %Doors and Windows 10 %Plumbing and Sanitation 6 %Electrical Work 12 %Painting 6 %Other Miscellaneous 5 %TOTAL 100 %
Activity Percentage Cost Break-Up (Labour)RCC 37 %Brick work and Plaster 21 %POP 7 %Tiling 12 %Plumbing and Sanitation 3 %Doors 1 %Water Proofing 3 %Painting 8 %Electrical 8 %TOTAL 100 %
Note : For general Residential Building,
Material cost = 76 %Labour Cost = 24 %
Cost Break-Up for RCC :Steel = 56 %Concrete = 44 %
Cost Break-Up for Masonary & Plaster :BBM = 15 %Internal Plaster = 32 %External Plaster = 21 %POP = 32 %
- 131 -
Plumbing and Sanitation Break-Up :G.I. Pipes and Fittings = 26 %C.I. / PVC = 18 %Sanitary = 15 %C.P. Fittings = 41 %
STANDARD MATERIAL CONSUMPTION CONSTANTSFOR VARIOUS ITEMS
(A) CONCRETE ITEMS : (INCLUDING WASTAGES)SR. NO.
DESCRIPTION UNIT PER
CEMENT SAND METAL
1 P.C.C. (1:3:6) M10
100 cft 12.00 bags 60 cft 85 cft1 cum 4.24 bags 0.60 cum 0.85 cum
2 P.C.C. (1:2:4) M15
100 cft 17.00 bags 60 cft 85 cft1 cum 6.00 bags 0.60 cum 0.85 cum
3 R.C.C. (1:1.5:3) M20
100 cft 22.00 bags 60 cft 85 cft1 cum 7.77 bags 0.60 cum 0.85 cum
4 R.C.C. (1:1:2) M25
100 cft 32.00 bags 60 cft 85 cft1 cum 11.47 bags 0.60 cum 0.85 cum
(B) MASONARY ITEMS : S. N.
Description Unit Per
Cement Sand Rubble Bricks23x10x7
cm
Bricks23x15x9
cm1 U.C.R.
MasonryIn C.M. 1:6
100 cft1
cum
4.5 bags
1.6 bags
40 cft
0.4 cum
125 cft
1.25 cum
-- --
2 23 cm (9”)B.B.
Masonry In C.M. 1:5
100 sft1
sqm
2.5 bags
0.27 bag
20 cft
0.06 cum
--
--
1000 nos
110 nos
--
--
3 15 cm (6”) B.B.
MasonryIn C.M. 1:5
100 sft1
sqm
1.5 bags
0.16 bag
15 cft
0.05 cum
--
--
--
--
400 Nos
45 Nos
- 132 -
4 10 cm (4”)B.B.
Masonry In C.M. 1:4
100 sft1
sqm
1 bags
0.11 cum
8 cft
0.025 cum
--
--
475 nos
50 nos
--
--
(C) PLASTERING ITEMS :Sr.No. Description Unit Per Cement Sand Neeru
(30 kg bag)1 NEERU FINISH PLASTER
12.5 MM (1/2” THK.)a) in C.M.1:4 100 sft 1.5 bags 11.00 cft 0.60 bags
1 sqm 0.60 bags 0.03 cum 0.07 bagsb) in C.M. 1:5 100 sft 1.2 bags 11.00 cft 0.60 bags
1 sqm 0.13 b02ags 0.03 cum 0.07 bagsc) in C.M. 1:6 100 sft 1.00 bag 11.00 cft 0.80 bags
1 sqm 0.11 bags 0.03 cum 0.07 bags2 NEERU FINISH PLASTER
20 MM (3/4” THK.)a) in C.M. 1:4 100 sft 2.4 bags 18.00 cft 0.60 bags
1 sqm 0.26 bags 0.06 cum 0.07 bagsb) in C.M. 1:5 100 sft 1.90 bags 18.00 cft 0.60 bags
1 sqm 0.21 bags 0.06 cum 0.07 bagsc) in C.M. 1:6 100 sft 1.6 bags 18.00 cft 0.60 bags
1 sqm 0.17 bags 0.60 cum 0.07 bags3 SAND FACED PLASTER
SINGLE COAT 15 TO 20 MM THK.a) in C.M. 1:4 100 sft 2.25 bags 17 cft ---
1 sqm 0.24 bags 0.05 cum ---b) in C.M. 1:5 100 sft 1.80 bags 17 cft ---
1 sqm 0.19 bags 0.05 cum ---c) in C.M. 1:6 100 sft 1.50 bags 17 cft ---
1 sqm 0.16 bags 0.05 cum ---4 SAND FACED PLASTER
DOUBLE COAT 20 TO 25 MM THKa) in C.M. 1:4 100 sft 3.75 bags 28 cft ---
1 sqm 0.41 bags 0.09 cum ---b) in C.M. 1:5 100 sft 3.00 bags 28 cft ---
1 sqm 0.32 bags 0.09 cum ---c) in C.M. 1:6 100 sft 2.50 bags 28 cft ---
1 sqm 0.27 bags 0.09 cum ---- 133 -
(D) FLOORING & TILING :Sr. No.
Description Unit Per
Cement Sand Lime30 kg bag
Tiles White Cement
1 Mosaic Tile / Ceramic Tile Flooring
100 sft1 sqm
1.0 bag
0.11 bag
16 cft
0.05 cum
2.0 bag0.2 bag
As Per Size
5 kg
0.55 kg
2 Mosaic Tile / Ceramic Tile Skirting
100 rft10 rm
2.0 bags
0.65 bag
2 cft0.017 cum
----
As Per Size
2 kg
0.65 kg3 Stone Flooring
40 x 55 cm cut45 x 60 cm cut
100 sft1 sqm
2.0 bags
0.22 bag
16 cft
0.05 cum
--
--
43 nos
5 nos
2 kg
0.22 kg
4 Rough Shahabad Stone Flooring45 x 80 cm uncut40 x 55 cm cut
100 sft1 sqm
0.75 bag
0.08 bag
18 cft
0.06 cum
2.0 bags0.2 bag
40 nos
4 nos
--
--
5 Chequered Tile Flooring(25 x 25 cm)
100 sft1 sqm
1.25 bag
0.13 bag
16 cft
0.05 cum
2 bags
0.2 bag
150 nos16 nos
--
--
6 I.P.S. Flooring 100 sft1 sqm
3.5 bags
0.38 bag
16 cft
0.05 cum
--
--
--
--
--
--
7 Glazed Tile Dado( 15 cm x 15 cm )
100 sft1 sqm
3.5 bags
0.38 bag
--
--
--
--
420 nos45 nos
2.0 kg
0.22 kg
- 134 -
(E) WATER PROOFING :Sr. No.
Description Unit Per Cement Sand Brickbat
1
2
Brickbat Coba Water Proofing in W.C. / Bath / Toilet EtcBrickbat Coba Water Proofing to Terrace
100 sft1 sqm
100 sft1 sqm
6.00 bags0.65 bags
4.00 bags0.43 bags
30 cft0.09 cum
30 cft0.09 cum
30 cft0.09 cum
30 cft0.09 cum
(F) RECOMMENDED CEMENT MORTAR MIXESSr. No.
Purpose Cement43 Grade
(Kg)
Fly Ash(Kg)
Natural Sand / Crushed
Sand(Kg)
W/C Ratio
Remark
1 BBM 5050
5025
629472
0.650.65
M/C MixingHand
Mixing2 Internal
Plaster5050
5025
550412
0.700.70
M/C MixingHand
Mixing3 External
Plaster5050
5025
473355
0.650.65
M/C MixingHand
Mixing
Notes : 1) Crushed Sand and Natural sand should confirm to RCC acceptance criteria 2) Mortar to be used within 45 minutes of addition of water.
WEIGHT PER METER IN KG. FOR ROUND & SQUARE BARS
- 135 -
Size inMm
For Round Bars For Square BarsArea cm2
WeightKg / m
Length (m) / Ton
Area cm2
WeightKg / m
Length (m) / Ton
6 0.283 0.222 4510 0.36 0.283 35358 0.503 0.395 2532 0.64 0.502 199210 0.785 0.617 1621 1.00 0.785 127412 1.131 0.888 1125 1.44 1.130 88514 1.539 1.208 829 1.96 1.539 65016 2.011 1.578 633 2.56 2.010 49818 2.545 2.000 500 3.24 2.543 39320 3.142 2.466 405 4.00 3.140 31822 3.801 2.980 336 4.84 3.799 26325 4.909 3.854 200 6.25 4.906 20428 6.157 4.830 207 7.84 6.154 16232 8.042 6.313 159 10.24 8.038 12436 10.179 7.990 125 12.96 10.200 9840 12.566 9.864 101 16.00 12.560 8050 19.365 15.410 65 25.00 19.625 51
Notes :1. For Round Bars Weight of Steel in Kg./ meter = d2 / 162 (where ‘d’ is diameter of bar in mm)2. Density of Steel = 7850 kg / meter3
3. Weight of Steel = Density x cross-sectional area of bar (in mm2) e.g. For 20 mm square bar : Wt. = (7850 x 10-6) x 400 = 3.140 kg / meter
WEIGHT / RUNNING METER OF G.I. PIPESDiameter
(mm)Class ‘A’ Class ‘B’ Class ‘C’Weight
(Kg)Weight
(Kg)Weight
(Kg)15 (1/2”) 1.01 1.28 1.5120 (3/4”) 1.48 1.65 1.9725 (1”) 2.10 2.54 3.08
32 (1 ¼”) 2.72 3.27 3.9740 (1 ½”) 3.40 3.76 4.5850 (2”) 4.32 5.31 6.38
65 (2 ½”) 6.10 6.81 8.2080 (3”) 7.20 8.85 10.51
ROLLED STEEL BEAMSDesignation Wt. Sectional Depth of
/ m Area Section‘W’ kg ‘a’ cm2 ‘h’ mm
Flange Thk. of Width Flange‘b’ mm ‘tf’ mm
Thk. of Web‘tw’ mm
ISJB 150 7.1 9.01 150 50 4.6 3.0ISJB 175 8.1 10.28 175 50 4.8 3.2
- 136 -
ISJB 200 9.9 12.64 200 60 5.0 3.4ISJB 225 12.8 16.28 225 80 5.0 3.7ISLB 75 6.1 7.71 75 50 5.0 3.7ISLB 100 8.0 0.21 100 50 6.4 4.0ISLB 125 11.9 5.12 125 75 6.5 4.4ISLB 150 14.2 18.08 150 80 6.8 4.8ISLB 175 26.7 21.30 175 90 6.9 5.1ISLB 200 19.8 25.27 200 100 7.3 5.4ISLB 225 23.5 29.92 225 100 8.6 5.8ISLB 250 27.9 35.53 250 125 8.2 6.1ISLB 275 33.0 42.02 275 140 8.8 6.4ISLB 300 37.7 48.08 300 150 9.4 6.7ISLB 325 43.1 24.9 325 165 9.8 7.0ISLB 350 49.5 63.01 350 165 11.4 7.4ISLB 400 56.9 72.43 400 165 12.5 8.0ISLB 450 65.3 83.14 450 170 13.4 8.6ISLB 500 75.0 95.5 500 180 14.1 9.2ISLB 550 86.3 109.97 550 190 15.0 9.9ISLB 600 99.5 126.69 600 210 15.5 10.5ISMB 100 11.5 14.60 100 75 7.2 4.0ISMB 125 13.0 16.60 125 75 7.6 4.4ISMB 150 14.9 19.00 150 80 7.6 4.8ISMB 175 19.3 24.62 175 90 8.6 5.5ISMB 200 25.4 32.3 200 100 10.8 5.7ISMB 225 31.2 39.72 225 110 11.8 6.5ISMB 250 37.3 47.35 250 125 12.5 6.9ISMB 300 44.2 56.26 300 140 12.4 7.5ISMB 350 52.4 66.71 350 140 14.2 8.1ISMB 400 61.6 78.46 400 140 16.0 8.9ISMB 450 72.4 92.27 450 150 17.4 9.4ISMB 500 86.90 110.74 500 180 17.2 10.2ISMB 550 103.7 132.11 550 190 19.3 11.2ISMB 600 122.6 156.21 600 210 20.8 12.0
INDIAN STANDARD ROLLED STEEL CHANNELS
Sectionh x b
(mm x mm)
Thickness of Flange
Tf (mm)
Thickness of Web
Tw (mm)
Sectional Area
Sq.Cm.
Weight / MeterW (kg)
75 x 40 7.3 4.4 8.67 7.1100 x 40 7.5 4.7 11.70 9.56125 x 65 8.1 5.0 16.19 13.1150 x 75 9.0 5.4 20.88 16.8175 x 75 10.2 5.7 24.38 19.6
- 137 -
200 x 75 11.4 6.1 28.21 22.3250 x 80 12.4 6.4 33.01 30.60300 x 90 13.6 7.6 45.64 36.3350 x 100 13.5 8.1 53.66 42.7400 x 100 15.3 8.6 62.93 50.1
INDIAN STANDARD ROLLED STEEL EQUAL ANGLESDESIGNATION SIZE
h X bmm X mm
THICKNESS OF FLANGE ‘t’
mm
WEIGHT / METER‘w’ (Kg)
ISA 2020 20 x 20 3.04.0
0.901.1
ISA 2525 25 x 25 3.04.05.0
1.11.41.8
ISA 3030 30 x 30 3.04.05.0
1.41.82.2
ISA 3535 35 x 35 3.0 1.6
- 138 -
4.05.06.0
2.12.63.0
ISA 4040 40 x 40 3.04.05.06.0
1.82.43.03.5
ISA 4545 45 x 45 3.04.05.06.0
2.12.73.44.0
ISA 5050 50 x 50 3.04.05.06.0
2.33.03.84.5
ISA 5555 55 x 55 5.06.08.010.0
4.14.96.47.9
ISA 6060 60 x 60 5.06.08.010.0
4.55.47.08.6
ISA 6565 65 x 65 5.56.08.010.0
4.95.87.79.4
DESIGNATION SIZEh X b
mm X mm
THICKNESS OF FLANGE
‘t’ mm
WEIGHT / METER‘w’ (Kg)
ISA 7070 70 x 70 5.06.08.010.0
5.36.38.310.2
ISA 7575 75 x 75 5.06.08.010.0
5.76.88.911.0
ISA 8080 80 x 80 6.08.010.012.0
7.39.611.814.0
ISA 9090 90 x 90 6.08.0
8.210.8
- 139 -
10.012.0
13.415.8
ISA 100100 100 x 100 6.08.010.012.0
9.212.114.917.7
ISA 110110 110 x 110 8.010.012.015.0
13.416.519.624.2
ISA 130130 130 x 130 8.010.012.015.0
15.919.723.428.9
ISA 150150 150 x 150 10.012.015.018.0
22.827.233.639.9
ISA 200200 200 x 200 12.015.0
36.645.5
DIMENSION AND WEIGHTS OF HOT-ROLLED STEEL FLATS
WIDTHMm
THICKNESSmm
WEIGHT(Kg / Meter)
10.0 3.04.05.06.0
0.2360.3140.3930.471
14.0 3.04.05.06.0
0.3300.4400.5500.659
20.0 3.04.05.06.0
0.4710.6280.7850.942
25.0 3.04.05.06.0
0.5890.7850.9811.18
30.0 3.0 0.707
- 140 -
4.05.06.0
0.9421.181.41
35.0 3.04.05.06.0
0.8241.101.371.65
40.0 3.04.05.06.0
0.9421.261.571.88
Weight of MS Flat = 7850 x 10-6 x W x T (Kg / m)Where, W = width of flat in mmT = thickness of flat in mm
MS PLATES (PLAIN)THICKNESS
mmWEIGHT
KG / SQ.M.5.0 39.256.0 47.108.0 62.810.0 78.512.0 94.214.0 109.916.0 125.618.0 141.320.0 157.0022.0 172.7025.0 196.25
MS PLAIN BLACK SHEETSTHICKNESS
mmWEIGHT
KG / SQ.M.0.40 3.140.50 3.930.63 4.950.80 6.300.90 7.051.0 7.851.12 8.80
- 141 -
1.25 9.801.40 11.001.60 12.601.80 14.101.90 14.902.0 15.702.24 17.602.50 19.602.80 22.003.15 24.703.55 27.864.0 31.404.30 33.754.65 36.50
STEEL TUBES FOR STRUCTURAL PURPOSE
Nominal Bore (mm)
Outside Dia.(mm)
Class Thickness(mm)
Weight(Kg / meter)
15 21.3 LightMediumHeavy
2.02.653.25
0.9621.221.45
20 26.9 LightMediumHeavy
2.352.653.25
1.421.581.90
25 33.7 LightMediumHeavy
2.653.254.05
2.042.462.99
32 42.4 LightMediumHeavy
2.653.254.05
2.613.153.86
40 48.3 LightMediumHeavy
2.93.254.05
3.273.614.43
50 60.3 Light 1Light 2MediumHeavy
2.93.253.654.5
4.144.575.16.17
65 76.1 LightMediumHeavy
3.253.654.50
5.846.537.92
80 88.9 LightMediumHeavy
3.254.054.85
6.868.4810.10
90 101.6 Light 3.65 8.82- 142 -
MediumHeavy
4.054.85
9.7511.6
100 114.3 LightMediumHeavy
3.654.505.40
9.9712.114.5
110 127.0 LightMediumHeavy
4.504.855.40
13.614.616.2
BARBED WIRE 2 PLY
Gauge of Ply Gauge of Barbs
Gap between two Barbs
Approx. Wt.Kg. / meter
Approx. Length in
25 Kg. bundle (m)
12 12 75 mm (3”) 0.166 15114 14 75 mm (3”) 0.083 30012 14 100 mm (4”) 0.119 21012.5 12 75 mm (3”) 0.135 18512.5 14 75 mm (3”) 0.119 210
GAUGE CONVERSION TO MM
Gauge no. Diameter in mm08 4.06410 3.25112 2.64214 2.03216 1.62618 1.21920 0.91424 0.55926 0.457
- 143 -
LIST OF IMPORTANT I.S. CODES : (Available at H.O. for reference)
I.S. CODE TITLE269-1989 Ordinary and Low Heat Portland Cement383-1970 Coarse and Fine Aggregate from Natural Sources for
Concrete 432-1982 (Part D) Mild Steel and Medium Tensile Steel bars 455-1989 Portland Slag Cement456-2000 Code of Practice for Plain and Reinforced Concrete516-1959 Methods of Test for Strength of Concrete800-1984 Code of Practice for Structural Steel in General
Building Constructions875-1987 (Part I, II, III, IV, V)
Loading code
1077-1992 Common Burnt Clay Building Bricks1199-1959 Method of Sampling and Analysis of Concrete1200 (Part I to XXVIII)
Method of Measurement of Building and Civil Engineering Works.
1489-1991 (Part I & II) Portland Pozzolana Cement1542-1992 Sand for Plaster1597-1992 (Part I & II) Code of Practice for Construction of Stone Masonry 1786-1985 High Strength Deformed Steel bars & Wires for
Concrete Reinforcement1893-2002 (Part I) Design of Earthquake Structures2065-1983 Code of Practice for Water Supply in Building2116-1980 Sand for Masonry Mortars2386-1963 (Part I to VIII)
Method of Test for Aggregates for Concrete
2470-1985 (Part I & II) Code of Practice for Septic Tanks2502-1963 Code of Practice for Bending and Fixing of bars for
Concrete Reinforcement2751-1979 Code of Practice for Welding of Mild Steel bars used
for Reinforcement Cement Concrete Construction 2911 (Part I to IV) Code of Practice for Design and Construction of Pile
and Pile Foundations 3370 (Part I to IV) Liquid Retaining Structures3414-1968 Expansion Joints
- 144 -
3696 (Part I & II) Safety Code for Scaffolds and Ladders3764-1992 Safety Code for Excavation workI.S. CODE TITLE3812-1981 Fly Ash for use as Pozzolana and Admixture4082-1996 Storage of Materials 4326-1993 Ductile Design for Earthquake Structures4925-1968 Battening of Concrete4926-2003 Ready Mixture Concrete6313 (Part I to III) Anti-termite Measure in Building 7969-1975 Safety Code for Storage and Handling of Building
Materials8041-1990 Rapid Hardening Portland Cement8112-1989 43 Grade Ordinary Portland Cement9103-1999 Admixtures11817-1986 Construction Joints12089-1987 Ground Granulated Blast Furnace Slag12269-1987 53 Grade Ordinary Portland Cement13311-1992 (Part I & II) Non-Destructive Testing 13920-1993 Ductile Design for Earthquake Structures14687-1999 Formwork Design and Detailing
- 145 -