+ All Categories
Home > Documents > Engineering Service-Learning in Ghana Biogas Project … · Engineering Service-Learning in Ghana...

Engineering Service-Learning in Ghana Biogas Project … · Engineering Service-Learning in Ghana...

Date post: 05-Jun-2018
Category:
Upload: duongtruc
View: 218 times
Download: 0 times
Share this document with a friend
49
Engineering Service-Learning in Ghana Biogas Project Team Pre-Trip Report Kave Anderson Meng Cheng Victor Haynes Kan Liu In collaboration with Dr. Roger Dzwonczyk, Mariantonieta Gutierrez Soto and the Engineering Education Department, Columbus, Ohio, The Ohio State University December 3, 2015
Transcript

Engineering Service-Learning in Ghana

Biogas Project Team Pre-Trip Report

Kave Anderson

Meng Cheng

Victor Haynes

Kan Liu

In collaboration with Dr. Roger Dzwonczyk, Mariantonieta Gutierrez Soto

and the Engineering Education Department, Columbus, Ohio,

The Ohio State University

December 3, 2015

Table of Contents

1. Introduction ............................................................................................................................................... 1

1.1 Definition of Terms ........................................................................................................................... 1

1.2 Executive Summary .......................................................................................................................... 1

1.3 Team Members and Other Participants ............................................................................................. 2

1.4 Project Location ................................................................................................................................ 3

2. Background ............................................................................................................................................... 3

3. Scope of Work .......................................................................................................................................... 3

3.1 Problem Statement ............................................................................................................................ 3

3.2 Customer Identification ..................................................................................................................... 4

3.3 Needs Assessment ............................................................................................................................. 4

3.4 Specific Objectives ........................................................................................................................... 6

3.5 Deliverables ...................................................................................................................................... 6

3.6 Sustainability Assessment ................................................................................................................. 7

4. Background Research ................................................................................................................................ 9

5. Representation ......................................................................................................................................... 10

6. Prototyping .............................................................................................................................................. 15

6.1 Prototyping Details .......................................................................................................................... 15

6.2 Testing and Results ......................................................................................................................... 16

6.3 Evaluation ....................................................................................................................................... 17

7. List of Materials ...................................................................................................................................... 18

8. In Country Schedule ................................................................................................................................ 20

Table 4. In-country Pre-Trip Schedule .................................................................................................... 20

Table 5. In-country Post-Trip Schedule .................................................................................................. 21

9. Post-Trip Results..................................................................................................................................... 22

9.1 Objectives Achieved ....................................................................................................................... 22

9.2 Project Diagram .............................................................................................................................. 22

9.3 Issues Encountered ......................................................................................................................... 23

9.4 Sustainability Statement ................................................................................................................. 23

10. In-Country Project Evaluation ............................................................................................................ 24

10.1 Success ............................................................................................................................................ 24

10.2 Weakness ........................................................................................................................................ 24

10.3 Improvements in the Future ............................................................................................................ 24

10.4 Cost Analysis for Research & Development .................................................................................. 25

10.5 Cost Analysis in Ghana ................................................................................................................... 26

11. Conclusion .......................................................................................................................................... 27

12. Recommendation ................................................................................................................................ 27

13. References ........................................................................................................................................... 29

14. Acknowledgements ............................................................................................................................. 30

15. Appendices .......................................................................................................................................... 31

15.1 Extra Figures ................................................................................................................................... 31

15.2 Biogas Technology Team Agreement ............................................................................................ 33

15.3 Meeting Notes ................................................................................................................................. 36

15.4 Maintenance & Use ......................................................................................................................... 41

15.5 Overall Gantt Chart ......................................................................................................................... 43

1

1. Introduction

1.1 Definition of Terms CCO Chief Communication Officer

CFO Chief Financial Officer

GO ENGR Global Option in Engineering

GSC Ghana Sustainable Change

LPG Liquefied Petroleum Gas

ONDA Offinso North District Assembly

1.2 Executive Summary

The human race’s increased use of fossil fuels has led to much speculation regarding the

well-being of the planet. These speculations have led to a new paradigm in thinking. Over the

past decade, increased focus has been placed on sustainability throughout many avenues. Solar

energy, wind energy, and geothermal heating are a few of the many developments that have

arisen. While these new “clean” energies are better for the environment, they are still rather

expensive and inefficient. One such energy that is more feasible to use is Biogas Technology.

Biogas Technology is a fairly recent development in the worlds of engineering and

academics. The main product of biogas is methane gas, which is a cleaner, more efficient fuel for

cooking than commonly used firewood. Because of its low cost, ease of construction and

environment friendly, this option is the most popular in underdeveloped countries. One such

country, Ghana, is the focus of the International Engineering Service-Learning Program. The

team will travel to Akomadan, Offinso North District Assembly, Ghana in order to construct a

Biogas Digester for the community residents to use. Residents will be able to use the bio-digester

to generate biogas to use primarily for cooking when wood had previously been used.

For the pre-trip biogas project testing, the group has built a 5 gallon digestion tank

prototype to test the possibility of producing, filtering and collecting the biogas. With the

experience from the prototype, the group decided to build a 1000L digestion tank with steel wool

filter and larger floating water trap for the in country project. The team hopes this can bring

Ghanaian partners lower cost energy and better life.

2

1.3 Team Members and Other Participants

Table 1. Team members and participants

Members Roles Major (Minor) Phone Email

Kave

Anderson

Team

Leader, CCO

Biological

Engineering (GO

ENGR)

(404) 468 - 2806 [email protected]

du

Kan Liu Co-Leader,

Director of

Testing,

Logistics

Manager

Aerospace

Engineering

(GO ENGR)

(917) 250 - 9768 liu.1891 @osu.edu

Meng Cheng Primary

Documenter

Mechanical

Engineering

(Math, Russian)

(614) 254 - 9351 cheng.643 @osu.edu

Victor

Haynes

CFO, Lead

Design,

Multimedia

Civil

Engineering

(Design, GO

ENGR)

(815) 302 - 3242 haynes.249 @osu.edu

Other

Participants

Title Phone Email

Roger

Dzwonczyk

Resident Director (614) 570 - 2073 [email protected]

u

Mariantonieta

Gutierrez Soto

Resident Director (614) 315 - 4988 gutierrez-

[email protected]

Honorable

Kojo

Appiah-Kubi

District Chief Executive (020) 922 - 2222 [email protected]

m

Augustine

Yeboah

Electrical Technician (024) 816 - 5422 Augustineyeboah22@

gmail.com

3

1.4 Project Location

During the fall semester, the initial research, design, and prototyping was one at The Ohio

State University located in Columbus, Ohio, United States of America. Prototype building is

conducted in Smith Laboratory and testing is carried out in the Agricultural Engineering

Building. The in-country portion of the project is conducted in the Offinso North District

Assembly (ONDA), which is located in Akomadan, Ghana.

2. Background

Ghana implemented a Liquefied Petroleum Gas (LPG) promotion program in 1989. Since

then, LPG has grown in popularity as a source of clean cooking fuel among Ghanaian

communities and households. The National Energy Policy of 2010 indicates that, “the

Government intend to increase the access of households to LPG as main cooking fuels to 50%

by 2015.” (Ghana Energy Action Plan, 2012). The growing demand of LPG brought not only

fast development but also challenges. The Ghana Energy Action Plan overestimated the speed

of LPG use in households; only 18% of the households were actually using LPG.

There is a huge demand among the Ghanaian population for a clean cooking fuel that is

not being met. Without the LPG, the current economically cooking fuel left for Ghanaian

people is wood. However, the side products of burning wood like CO and ashes are harmful

for the environment and human.

In order to protect Ghanaian people’s health, save the environment, and satisfied the

huge demand of cooking fuel, the group need to find an economical, clean and easy to use

fuel. One of the most suitable energy sources available is naturally occurring methane gas

harnessed by biogas digester technology.

3. Scope of Work

The following section clearly documents the project requirements, milestones,

deliverables, end products, documents and reports that are expected to be provided by the bio-gas

technology group.

3.1 Problem Statement

Methane gas is a cleaner, more efficient fuel for cooking than commonly used firewood.

In 2013, Ghana Sustainable Change (GSC) introduced biogas technology as a means to

produce methane gas. However, the bio-digester that was created is currently inoperable. The

current situation calls for renovation of the existing bio-digester and/or the implementation of

more updated technology--possibly in the form of completely new bio-digesters.

4

3.2 Customer Identification

This project is a collaboration of The Ohio State University students and Ghana partners,

ONDA to deliver sustainable biogas technology to Ghanaian people.

3.3 Needs Assessment

The prototype completed before departure was operable; it created methane gas in its

closed system as intended. Because it was built from the ground up, the prototype served its

secondary purpose of identifying unanticipated complications in the engineering design process.

The current issues with the entire scope of the biogas project are divided into two categories:

binary (simple) problems, and open-ended problems.

Binary Problems:

● Addition of valve(s):

○ An open and shut valve (i.e. a ball valve) is needed somewhere in the piping

between the septic tank and the water trap. The addition of this valve would help

coax the trapped gas to flow in the proper direction. This would be especially

helpful in the early stages of gas production due to the minimal internal pressure.

● Slurry and excess waste liquid pipe:

○ A slurry and or excess liquid runoff pipe with an open and shut valve needs to be

added. Emptying the contents of the septic tank or over filling it were controlled

variables that were removed from our focused design and the scope of our testing.

In country, there will need to be a way to remove excess liquid from the system

without exposing the contents of the tank to too much oxygen. A simple runoff

pipe solves this.

Open-ended Problems:

● Necessity of water trap:

○ The efficacy and salience of the water trap needs to be assessed. The water trap

makes the design process markedly more complicated. There is reason to believe

that a digester without a water trap would be serviceable, comparably efficacious,

and much easier to design.

● Weak internal flow:

○ While the prototype did produce methane gas, the gas did not flow into the

designed capture bag as intended. The gas either stayed in the septic tank, in the

steel wool filter, or in the water trap. This is a point of contention because it is not

5

clear as to why this system had very poor flow. It is probably due to the fact that

this very small scale digester is not generating substantial amounts of internal

pressure. The lack of flow is a major motivating factor for the possible removal of

the water trap--the gas would collect directly above the waste in this design.

● Minimizing the introduction of oxygen introduced through routine use:

○ The feedline design for the septic tank needs to be slightly more robust and

sophisticated. Quasar Energy Group recommended that the feedline be kept full

so oxygen cannot reach the fermenting bacteria, only the top of the waste that is

being added.

● Carbon dioxide filtering (with calcium hydroxide as the primary agent):

○ The efficacy and design-feasibility of using soda lime, calcium hydroxide, or

limewater (calcium hydroxide and water) to filter the gas and absorb harmful and

useless carbon dioxide gas (which is an occurring byproduct) needs to be

determined.

● Bonding with glue and materials in country:

○ Because the materials in country are not precisely known, there is a question of

which types of plastics will be available (for the septic tank, various fixings,

piping etc.). Not all types of plastic easily bond together. Working with PVC

would be ideal but it is unknown if all the necessary components will be made out

of PVC.

● Safety of the gas capture bag(s):

○ The materials for the in country capture bag(s) or equivalent storage unit(s) are

not precisely known. In the prototype, a thick standard material trash bag was

used along with PVC fixings. There were no clear issues with the design. The

capture bag needs to be robust and airtight if they are going to be used. For safety

reasons, at the cost of convenience, they can easily be removed from the

deliverables if necessary.

● Wide possible array of fuel sources in country:

○ Having a more precise idea of methane potential would be ideal. Unfortunately,

knowing precisely largely depends on the fuel sources. However, there are known

general figures, current design features in place and known techniques that

generally increase the amount of gas generated whilst filtering out unwanted

gases (i.e. carbon dioxide, hydrogen sulfide).

6

3.4 Specific Objectives

● The team will build a biodigester with all parts entirely from Ghana at an affordable cost

to ensure the sustainability of the program.

● The team will make the biodigester serviceable, fitting for use, and fit to produce enough

methane for daily cooking.

● The team will teach the Ghanaian people operation and maintenance procedures of the

biodigester.

● The team will simplify the usage and maintenance procedure of the biodigester and leave

operation manual to Ghanaian households.

● The team will focus on the sustainability aspect of the bio-digester, the delivered product

should be easy to maintain and replacement parts should be accessible in Ghana.

● The team will ensure the biodigester be durable and usable for an extended period of

time.

● The team will investigate the local community and find the possibility of installing biogas

electricity generators in the future.

3.5 Deliverables

At the end of a two week implementation and evaluation period in Ghana, the following

will be delivered to the Offinso North District

● A Biogas Digester will be deployed to one residence following the recommendations of

our in country hosts (primarily: Isaac Tenkorang, Augustine Yeboah, Honorable Kojo

Appiah-Kubi, and Andrews Bediako).

● Training will be given to the community residents who will receive and/or use the

Biogas Digester for cooking.

● Training will take the form of an educational presentation, a brochure detailing

procedures, and a “One-Point Lesson” to be attached to the Biogas Digester.

● Pending the approval of our in-country hosts, one or several community residents will

help with the implementation gaining expanded knowledge which will aid in

maintenance and upkeep.

The following points detail aspects of the project that are “Out of Scope” or that will not be

included in our implementation of the Biogas Digester:

● A Biogas Digester will be implemented that supplies biogas used for cooking. This

does not include a cooking stove or any related paraphernalia.

● There will be no evaluation of the Biogas Digesters that may have been constructed

during previous trips unless requested by residents.

● There was a request to investigate the possibility of generating electricity from

biogas. After research it was decided that this venture would be too expensive.

Almost all Biogas systems that create electricity have a generator available.

7

3.6 Sustainability Assessment

There are several factors that keep effective programs sustained over time. The ultimate

goal of the Ghana International Engineering Service-Learning curriculum is to implement

projects that take into account the needs of the community. An important aspect of this is that the

residents must find the deliverables to be something that they can use and will make life a little

easier. There are several elements that we believe will aid in the ability to maintain the benefits

of the Biogas Digester over time. Those elements include: Environmental Support, Funding

Stability, and Communication/Partnership,

Environmental Support:

● Waste Management

○ As long as maintenance is kept up, a biogas digester can last as long as 10 years.

○ End of life disposability could be tricky however. Because the contents of the

digester are flammable and chemical hazards, the contents must be disposed of

properly and the materials used must be sanitized.

○ A Biogas Digester is extremely useful for waste management because the fuel for

the biogas product is literally waste. Manure, food wastes, and cooking greases

are all viable fuels for the digester. A Biogas Digester runs off of organic material

which makes it highly efficient.

● Energy Efficient

○ A Biogas Digester is highly sustainable. There is no gasoline, electricity, or any

materials other than organic waste needed to run it.

● Safety

○ The purpose of the Biogas Digester being implemented in Ghana is to generate

gas to be used for cooking. Currently, most Ghanaians use biomass like wood for

cooking. Cooking with wood is dangerous because chemicals like carbon

monoxide, formaldehyde, and sulfur dioxide are abundant. The smoke from wood

interferes with lung development in children and can cause cancer (The Health

Effects of Wood Smoke). Because of this a Biogas Digester is a cleaner, healthier

way to cook.

Funding Stability:

● Cost to build, operate, and maintain;

○ The cost of a Biogas Digester is relatively inexpensive.

○ For details regarding costs and materials, refer to Section 8.

8

● Scalability

○ For prototyping, the group experimented with a smaller version of the plug flow

biodigester that was built in Ghana in 2011. The prototype used a five gallon

bucket as the holding tank. In Ghana the biodigester was constructed with a 250L

tank.

○ A Biogas Digester is extremely scalable and the simple construction can be

duplicated to build multiple units for each home.

Partnership:

● Entrepreneurial potential

○ One point that was emphasized at the very beginning of the curriculum was the

aspect of entrepreneurial potential. Dr. Dwonczyk stressed that the class keep

entrepreneurship in mind during research and implementation of the projects.

○ Biogas Digesters have moderately low entrepreneurial potential. The most

obvious venture would be for restaurants, diners, and other food services. Biogas

can be used to cook and sell meals in the community.

○ On a more technical level, the biogas can be harnessed and sold to families to heat

their homes. But because Ghana is closer to the equator and therefore hotter than

countries like the United States there is little use for the excess heat.

● Ownership

○ As previously mentioned, one of the most important aspects of sustainability is

ownership. If there is no one available to learn to construct and maintain the

Biogas Digester then the project will be useless.

○ In order to prevent this from happening, education has to be a point of emphasis.

○ Please see Section 3.5 for further information about training and ownership

9

4. Background Research

In order to build a biogas digester that fills all the previous requirements, the team began

background research in the 5th week. The information was collected mainly through three

resources: construction videos online, research papers, and an interview with the professor.

Videos:

The team focused on three videos found on Youtube. The team confirmed the first

prototype construction process based on the video “How to make a Bio-gas Digester”5. From the

video, the group decided to use large poly tank with one inlet and two outlets as digestion tank.

And the PVC glue should be used to fix and seal the connection between parts.

Based on the video “Biodigester - Methane as fuel”1, the team learnt that the side product

of digestion process, H2S can be removed by a steel wool filter. The reaction between iron and

H2S will form FeS. So, the team added a steel wool filter in order to remove the H2S, which is

harmful to user.

Based on the video “Storing biogas in a plastic trash bag”10, the team learnt that the

biogas can be easily collected in a seal trash bag. And the pressure caused by the weight of

blanket on the bag is proper for burning usage. The team the installed a gas storage bag on the

prototype.

Research Papers:

The team learned that the biogas digestion process is actually the anaerobic digestion of

the organic by certain stereotypes of microbes.8 During the process, methane as the gas fuel as

well as side products like CO2 , H2S will be produced.4 In order to keep the microbes active, the

temperature, pH and C/N ratio of the rough materials should be kept in a proper range.4

Interviews:

The team scheduled an interview with Dr. Yebo Li, a specialist on biogas digester aspect.

Dr. Li shared a lot of his own experience like accelerating the process by using “seeds” and oil;

adjusting the pH by adding buffer or stop feeding. He also shared some maintenance skills with

the team

10

5. Representation

For more information see: Prototyping 7.1. The pictures listed below represent various preliminary design

ideas and concepts.

Preliminary Photos and Sketches

Figure 1. Concept of a water trap

The first drawing made. It depicts the concept of a water trap. Biogas containing methane enters from the

left and exits from the bottom of the pipe immersed in water. The gas bubbles up through the surface and

escapes through its only route on the right.

11

Figure 2. A birdseye view of the lid of the septic tank

The black marks indicate the size and location of the necessary cuts for tubing and the feedline.

Figure 3. The underside of a plastic bucket

It is the top face of the water trap. The black marks indicate holes for tubing. Gas enters on the right and

exit on the left.

12

Figure 4. Drilling the tubing hole (Kave) The water trap being assembled. The holes depicted in Figure 3 are being drilled through. On the table,

the lid of the septic tank can be seen.

Figure 5. Assembling the prototype. Left: the septic tank with the feedline, a rubber plug/lid for the feedline, a threaded adapter.

Right: the top of the water trap, a threaded adapter, tubing through the adapter (this is on both sides. See:

Figure 3 and Figure 4)

13

Figure 6. The underside of the septic tank lid with adaptor installed. This piece along with tubing that will be attached to it will allow the gas to escape from the septic tank.

These pieces greatly simplify the building process.

Figure 7. A drawing of the idealized prototype design

From left to right: a capture gas bag, tubing, a valve, more tubing, the water trap, tubing, a valve, steel

wool filter and tubing, septic tank, waste feedline. Circled components are possible improvements.

14

Figure 8. The steel wool filter being stuffed (white pipe with lid

removed).

15

6. Prototyping 6.1 Prototyping Details

Figure 9. Prototype Design Diagrammatic Sketch

Details:

● The aforementioned depicts a closed-system anaerobic biogas digester.

● Aside from instructions, the final prototype consists of:

A. Biogas digester

The container where the digestion process happened inside. The biogas production part.

B. Water trap (optional)

Used to store the gas when gas bag not available, and control the pressure inside.

Stop the possibly gas reverse flow.

C. Steel wool filter (optional)

Fix toxic H2S gas.

D. Gas capture bag (optional)

For convenience and short to medium term storage.

16

6.2 Testing and Results

After two weeks of digestion process, the prototype was tested on three aspects: the gas

production, the toxic filtering and the gas storage.

Of the gas production:

Method: Flame test. The team held a burning object at the end of the tube and checked whether

the emission gas will accelerate the burning process.

Observation: The bubbles came out from the mixture and released gas. The area on the object

contacted with gas was ignited suddenly and formed larger flame.

Result: The burning phenomenon above shows that the flammable biogas was produced and

stored in the tank at a proper concentrate.

Of the toxic filtering:

Method: Steel observation. The team took the steel wool out from the filter and checked the

color. The iron atom will react with H2S and form dark brown FeS compound.

Observation: Compared with original steel wool, the steel wool in the filter did not appear to

have color change.

Result: There is not enough evidence show that the hydrogen sulfide was fixed on the steel

wool. The immeasurable color change may due to the short usage period and the small

amount of H2S. A further acid test will give clear answer.

Of the gas storage:

Expected Result: Based on the calculation. Around 1.5lb of the cow manure, dry grass and palm

oil mixture should produce around 20L of biogas within two weeks. The storage

bag should be around ⅛ full.

Observation: The gas storage bag was completely flat.

Result: The flat bag means there was no gas in the bag. After detailed examination,

the team found a leak between the flexible tube and the PVC adaptor. The leak reduced

the maximum pressure in the tank. The gas cannot pass through water trap but is emitted

into air.

17

6.3 Evaluation

Successes

The prototype verified the assumption that the seeds and oil can accelerate the digestion

process. For the in-country project, the group is going to keep on using seed to accelerate the

process.

The design of the inlets/outlets positions can be applied in the in-country project.

The team used PE pipes when transferring the biogas increased the flexibility and mobility

of the gas tank.

Failures and Experiences

The sealing problem is the most serious failure in the prototype design. The team used

two kinds of plastic which are PE & PVC, and the sealing between two different materials is a

big difficulty. The contact area between tank and leaked even after sealing two times. Based on

the previous lesson and the larger tank used in the in-country project, the team decided to use

pure hard PVC tube connection in the in-country project and seal every connection tightly with

PVC glue.

18

7. List of Materials

Table 2: Prototype 1 Material List

Part Description Quantity Cost (USD) Consumed

5 gallon blue lid 2 2.54 2/2

5 gallon blue bucket 2 5.96 2/2

2 gallon blue bucket 1 3.58 1/1

3" PVC tube 1 x 2 ft 4.98 2/2ft

3" plug 1 4.99 1/1

1/2" PVC adaptor 2 0.77 2/2

#5 o-ring 10 2.49 1/104/10

super fine steel wool 1 x 4 3.97 2/4

5.5 oz fast dry 1 2.78 2.5/5 oz

3"/4" PVC closet flange 2 7.36 2/2

3/8" ball valve 1 7.77 0/1

3/4" to 1/2" adaptor 4 3.88 0/4

1/2" out (3/8" in) flexible tube 13 ft 3.77 13/13 ft

3/4" 90° PVC elbow 4 1.88 0/4

3/4" PVC ball valve 2 14.66 0/2

3/4" insert combination 1 1.21 0/1

8 oz PVC cement 1 4.98 2/8 oz

1/4" PVC tubing 1 x 3 ft 0.48 0/3 ft

1/2" PVC pipe 1 x 5 ft 2.79 1/5

3/4" to 1/2" adaptor 1 0.97 0/1

duct tape 1 x 75 ft 8.98 12/75 ft

3/4" to 1/2" PVC coupler 1 0.24 0/1

1/2" PVC ball valve 1 6.2 1/1

42-gal trash bag 24 12 1/24

palm oil 10oz Provided by Victor 9.5/10 oz

lime juice 2.5oz Provided by Victor 2.5/2.5 oz

19

Table 3: In-Country(Ghana) Project Material/Tool List

Part Description Quantity Purchase Location

3' PVC tube 1 x 2 ft Ghana

3" test plug 1 Ghana

1/2" PVC adaptor 1 Ghana

#5 o-ring 10 Ghana

super fine steel wool 1 Ghana

5.5 oz fast dry 1 Ghana

3"/4" PVC closet flange 2 Ghana

3/8" ball valve 1 Ghana

3/4" to 1/2" adaptor 4 Ghana

1/2" out (3/8" in) flexible tube 13 ft Ghana

3/4" 90° PVC elbow 4 Ghana

3/4" PVC ball valve 2 Ghana

3/4" insert combination 1 Ghana

8 oz PVC cement 1 Ghana

1/4" PVC tubing 3 x 1 ft Ghana

1/2" PVC pipe 1 x 5 ft Ghana

3/4" to 1/2" adaptor 1 Ghana

1/2" PVC adaptor 1 Ghana

duct tape 1 x 75 ft Ghana

3/4" to 1/2" PVC coupler 1 Ghana

1/2" PVC ball valve 1 Ghana

42-gal trash bag 24 Ghana

palm oil 10oz Ghana

lime juice 2.5oz Ghana

20

8. In Country Schedule

The overall project timeline is presented in the Overall Gantt Chart section of the

Appendix. The in-country pre-trip schedule is presented in table 4. The in-country post-

trip schedule is presented in table 5.

Table 4. In-country Pre-Trip Schedule

Date Goals

Saturday, December 26th 0700: Depart from Columbus

Sunday, December 27th 0750: Arrive in Accra

Monday, December 28th

Morning:

Site visit

Implement project plan Afternoon: Supplies shopping

Tuesday, December 29th

Morning:

Start bio-digester building Measure

and drill connection holes Measure and

cut PVC pipes

Afternoon:

Supplies shopping Searching

for cow manure Wednesday, December 30th

Morning: Supplies shopping( if needed) Install and connect PVC pipes

Afternoon: Sealing gaps Obtain cow manure

Thursday, December 31th

Morning: Extra time for bio-digester building

Afternoon: Extra time for obtaining cow manure and supplies shopping

Friday, January 1st

Morning: Extra time for biodigester building

Afternoon: Extra time for obtaining cow manure and supplies shopping

Saturday, January 2nd Rest day (other activities)

Sunday, January 3rd Rest day (other activities)

Monday, January 4th

Morning: Finish up bio-digester building

Afternoon: Start collecting data (if possible)

Tuesday, January 5th

Morning: Test bio-digester (if possible)

Afternoon: Troubleshooting

Wednesday, January 6th

Morning: Make bio-digester instructions/manual

Afternoon: Extra time for troubleshooting

Thursday, January 7th

Morning: Extra time for troubleshooting

Afternoon: Education/teaching time

Friday, January 8th

Morning: Time reserved for extra event

Afternoon: Time reserved for extra event

Saturday, January 9th 2200: Depart from Accra

Sunday, January 10th 2238: Return to Columbus

21

Table 5. In-country Post-Trip Schedule

Date Goals

Saturday, December 26th Departed from Columbus

Sunday, December 27th Arrived in Accra

Monday, December 28th Morning: Project supplies purchasing (PVC parts)

Afternoon: Meet and greet with ONDA staff

Tuesday, December 29th Morning: Met with Augustine and project discussion

Afternoon: Purchased poly tank

Wednesday, December 30th Morning: Obtained cow manure Biodigester building (80% completion)

Afternoon: Purchased project supplies (PVC parts and connectors)

Thursday, December 31th Morning: Purchased project supplies (PVC sealing parts and steel wood)

Afternoon: Visited Techiman Processing Complex Biodigester building (95% completion)

Friday, January 1st Morning: Waterfall visit

Afternoon: Monkey sanctuary visit

Saturday, January 2nd Visited the hospital and Nana’s village

Sunday, January 3rd Rest day and football

Monday, January 4th Morning: Finished biodigester building (100%)

Afternoon: Filled up the water tank Took pictures

Tuesday, January 5th Morning: Searched for gas bags

Afternoon: Obtained more cow manure

Wednesday, January 6th Morning: Put in the last batch of cow manure

Afternoon: Augustine showed us his work and company

Thursday, January 7th Morning: Interviewed by the radio station Presented the biodigester to Kojo and other OSU teammates

Afternoon: Presented the biodigester to ONDA staff

Friday, January 8th Morning: Traveled to Cape Coast

Afternoon: Ghana national forest visit

Saturday, January 9th Cape Coast Elmina Castle visit Departed from Accra

Sunday, January 10th Returned to Columbus

22

9. Post-Trip Results 9.1 Objectives Achieved

Upon reaching the worksite, the team found that the biogas tank would only be used by

Augustine’s family. So, the scale of the design had been changed. After investigating the wasted

biogas tank built by the previous 2012 team, the group concluded that their failure was caused by a

defective design. However, the wasted tanks were still good to use. In order to save the cost and

protect the environment, the group decided to recycle the wasted tanks from previous design.

While In Country, the team competed the following tasks:

The team built a 1000L biogas digester with all parts entirely from Techiman and

Akomadan, Ghana.

Biogas digester was built at a relatively affordable cost ($226 US dollars) to ensure the

sustainability of the program.

The team made the biogas digester serviceable, fitting for use, and fit to produce enough

methane for daily cooking.

The team collaborated closely with Augustine Yeboah and Isaac Tenkorang to ensure

someone was knowledgeable about the operation and maintenance procedures of the biogas

digester.

The team left a simple operation manual with ONDA.

The team focused on sustainability of the bio-digester to ensure the delivered product was

easy to maintain and replacement parts were accessible in Ghana.

The team investigated the local community and found examples of biogas electricity

generators. A partnership between ONDA and Techiman Processing Company (TEPCO)

was established to explore future projects in this field.

9.2 Project Diagram

Figure 10. Overall Diagram for the In-Country Project

23

9.3 Issues Encountered 1. Budget

The budget for the whole project was $400 ($100 for each team member). After the prototype

testing, the team brought around $250 budget for the In-Country Project. And the final total budget

is $394.31 (hardly anything left). The polytank was really expensive and worth 540 Ghana cedi

(about $142). So the team used two wasted tanks from previous group project to save cost. Even

though, the team was out of budget for the short term gas storage bag design.

2. Material

Most of the materials were bought from Techiman which is about 30 min from the

construction site. When the team forgot to buy some parts, it took over 1 hour to buy and bring it

back. It wasted a lot of time.

The team cannot find heavy duty plastic bags in Ghana. Plastic bags on market were too thin

and leaking. This is another reason why the team gives up short term gas storage bag design.

3. Vehicle Arrangement

Ghana is not a developed country and the vehicles resources are limited. Usually, the team

need to wait until the vehicles sent two other teams to the site and came back. The room of the

vehicle is also limited. Most of the time, team members need to sit in the trunk of the pickup. When

the pickup was full loaded with materials/water/manure, the team members also need to keep the

loadings fixed.

4. Sealing

The sealing was still a problem in the In-Country Project. As the size of the project increased,

the water level inside the tank increased. In this case, the high pressure in the water tank can cause

leaking easily. In order to solve the problem, the team used epoxy to seal between plastic; Teflon

tape to seal between threads; silicon to fill the leakages.

9.4 Sustainability Statement The ultimate goal of the Ghana International Engineering Service-Learning curriculum was

to implement projects that take into account the needs of the community. An important aspect of

this is that the residents must find the deliverables to be something that they can use and will make

life a little easier. There are several elements that we believe aided in the ability to maintain the

benefits of the biodigester over time.

Waste Management

The biodigester is extremely useful for waste management because the fuel for the biogas

product is literally waste. Manure, food wastes, and cooking greases are all viable fuels for the

digester. A biodigester runs off of organic material which makes it highly efficient.

Safety

The purpose of the biodigester being implemented in Ghana is to generate gas to be used

for cooking. Currently, most Ghanaians use biomass like wood for cooking. Cooking with wood is

dangerous because chemicals like carbon monoxide, formaldehyde, and sulfur dioxide are

abundant. The smoke from wood interferes with lung development in children and can cause

24

cancer (The Health Effects of Wood Smoke). Because of this a Biogas Digester is a cleaner,

healthier way to cook.

Entrepreneurial potential

Biogas Digesters have entrepreneurial potential, but this is primarily on a large scale.

Restaurants, diners, and other food services could use Techiman Processing Company as an

example. In their production of tomatoes, Techiman Processing Company is using wastes to go into

a biodigester that would provide natural gas and electricity for the company to use at its leisure. In

addition, Biogas can be used to cook and sell meals in the community.

10. In-Country Project Evaluation 10.1 Success

Compare with the prototype, the in-country project is a more successful project. In the project

construction, the team improve design; saved cost; simplified usage and maintenance; achieved

requirements.

In the previous design, digestion tank was open to the air. Oxygen in the air will dissolve in

the water and kills anaerobic bacteria which producing methane. Of the new project, the digestion

tank was separated from the water trap and seal tightly.

In order to save the cost, the team recycled the wasted tanks from previous group and

transformed them into a storage water trap. The new water trap can store around 400L of biogas

and adjust pressure in a small range. It saved the team at least 1000 Ghana cedi (around $263) by

recycling the two tanks.

All of the parts were bought in Techiman and Akomadan. This means it’s convenient for user

to replace any broken parts.

The biogas digester tank is 1000L and will start producing enough biogas for a family

cooking usage after 3 months.

10.2 Weakness

Similar to the prototype, sealing problem still appears. When recycling the wasted tank,

most of the sealing parts are too old to be used. Although the team replaced them with new parts,

the leaking still happens because of the uneven surface between connections. The team should

clean the surface of the sealing parts before replacing.

10.3 Improvements in the Future

There are still some aspects can be improved on this project and similar projects in the

future. Three important parts are: production rate measurement; gas tank pressure adjustment

measurement and CO2 filter.

For the production rate measurement:

Since the production of the biogas depends on ingredient type, outdoor temperature,

humidity and many other factors. It’s really hard to calculate how much biogas will be produced

daily instead of testing. If the production rate can be measured, it will be easier to choose the size

of the digestion tank and the ingredients amount based on the demand. To measure the production

rate, label volume marks on the gas tank based on the height and the inside diameter of the tank.

Then let the digestion tank run out of ingredients and use up all biogas in the tank. Finally, measure

25

the amount of the ingredients injected and the volume of the biogas produced daily.

For the gas tank pressure adjustment:

To use the biogas at stove, the pressure need to be controlled at a proper range. For the project,

the user can adjust the pressure with stones. However, a quantified standard will be better for

operation. The relationship between the weight of stone and the pressure can be calculated from the

inside diameter of the gas tank. Based on the calculation, the user could know the proper weight of

the stone should be put on the gas tank.

For the CO2 filter:

The raw biogas usually contains up to 40% of inflammable CO2, which reduced the

combustibility of the biogas. In order to improve the performance, a CO2 filter can be added if the

budget available.

10.4 Cost Analysis for Research & Development

Table 6. Cost Analysis for Research & Development

Vender Description Cost

Agent of Duraplast Plumbing parts $34.74

Lowe's 3/4'' X10FT CPVC pipe $5.89

Lowe's 3"* 2' PVC tube $4.98

3" test plug $4.99

5 gallon blue lid $1.27

5 gallon bucket (2) $5.96

1/2" PVC adaptor $0.77

3/4" to 1/2" adaptor (3) $2.91

3/4" 90°PVC elbow (4) $1.88

3/4" PVC ball valve (2) $14.66

3/4" insert combination $1.21

8 oz PVC cement $4.98

1/4" *1 ft PVC tubing (3) $0.48

2 gallon blue bucket $3.58

Others $3.58

Lowe's Plumbing parts $30.38

Lowe's Plumbing parts $34.35

OSU Bookstore Educational materials $11.24

In U.S. Research & Development Cost $167.85

26

10.5 Cost Analysis in Ghana

Table 7. Cost Analysis in Ghana

Vender Description Cost

God's Power Paint & Hardware Valve and PVC glue $15.79

God's Power Paint & Hardware PVC plumbing items $20.79

Kwao Electrical Tubing $8.42

ASPET Rambo 100 Tank $136.84

Awurade Okoye Woko 2'' Plugs (2) $1.31

1/2'' Valve socket (7) $1.84

1/2'' Air valve $5.27

Angle valve $5.27

1/2'' F28 (2) $2.63

1/2'' K2 $1.32

1/2'' Bends (7) $1.84

1'' Valve socket (2) $1.58

1/2'' Pipe $2.63

Others $8.02

Winnax Age Company 1'' Tank connector $2.63

1'' Valve socket (2) $1.05

1'' Bend (2) $1.05

Nasa Frimpong Provisions Palm oil $5.53

Winnax Age Company 1'' Tank connector $1.58

1'' Thread plug $0.53

Akomadan roadside store Soap $0.53

Tools(Provided by Augustine)

Shovels $0.00

Saw $0.00

Tools(Provided by Roger, brought from

Columbus)

Power drill $0.00

Plumbers putty $0.00

Wrench $0.00

Teflon tape $0.00

USD to Cedi Conversion (January 2016) 1 : 3.79746

In Ghana Cost $226.46

27

11. Conclusion As previously mentioned, methane gas is a cleaner, more efficient fuel for cooking as

commonly used firewood. In 2013, Ghana Sustainable Change (GSC) introduced biogas

technology as a means to produce methane gas. However, the bio-digester that was created was

inoperable. After in country assessment it was determined that the underlying cause of failure for

the previous design was lack of education about the biodigester. The Ghanaian owners of the

biodigester (primarily Augustine Yeboah) started to use the biogas after a 7-day wait period. This

allowed the biogas to be exposed to oxygen for long periods of time which decimated the anaerobic

bacteria culture needed for fermentation. From research, we understand that it takes about 1-3

months to obtain a sustainable amount of biogas. All in all, in 2 weeks the team renovated the

existing bio-digester and implemented updated technology.

This project was a collaboration of The Ohio State University students and Ghana partners,

ONDA to deliver sustainable biogas technology to Ghanaian people. More specifically, the team

collaborated with Augustine Yeboah and Isaac Tenkorang to deliver the final product.

Some of the issues encountered in-country were centered on Budget, Material, and sealing.

After using 98.5% of our budget for prototyping and in-country materials, the team was unable to

construct a short term gas storage bag. In addition to the budget, the team struggled to find heavy

duty plastic bags in Ghana that were thick and nonporous enough to prevent leaking. Sealing the

biodigester system was also a major problem. In order to solve the problem, the team used epoxy to

seal between plastic; teflon tape to seal between threads; and silicon to fill the leakages.

12. Recommendation Overall, the design and implementation was a success. However, there are delicate details that

need to be communicated to future teams. Many improvements can also be made. The

recommendations below are listed in terms of priority.

Remain consistent with construction materials. PVC, for example, is a desirable

construction material in low-tech biodigesters because of its availability, affordability,

durability, and ability to be cut. While PVC is very compatible with other PVC parts such

elbows, valves, PVC glue, and various fixings, it is not easily compatible with most other

materials. Bonding PVC with other types of plastics or materials is challenging and must

be done with skill and care. The success of a biodigester is largely dependent on the quality

of its seals and bonds. Also, low pressure pipes can certainly be used and are widely

available. They are flexible, but they further complicate bonding issue.

Carbon dioxide gas can be eliminated from the final product. Calcium Hydroxide

[Ca(OH)2] reacts with carbon dioxide [CO2], creating a harmless precipitate calcium

carbonate [CaCO3] and water. All of these reactions and byproducts occur in equal

amounts. Carbon dioxide is a harmful gas and byproduct of biogas digestion--up to 25 to

40%. The [CO2] can be removed by running the gas through a liquid filter (most

commonly a “U tube”) comprised of water and dissolved calcium hydroxide or calcium

oxide13. Calcium oxide [CaO] can also be used to achieve a similar effect with a similar

absorption rate. Calcium oxide and carbon dioxide yields the same precipitate and oxygen

instead of water.

28

These findings come from the literature on biogas and carbon dioxide scrubbing.

Experimental, and therefore practical, results were not obtained. Because of this, the design

of the carbon dioxide scrubber must be robust enough to be effective while also being able

to be removed from the system for occasional desludging.

Be certain to design a feedline or feeding system that can be utilized whilst simultaneously

minimizing the introduction of oxygen from the outside air. Preferably, the level of the

sludge inside the main tank should rise above the opening of the feedline. The feedline

should be backed up with newly fed waste or some sludge from the main tank. This

prevents oxygen from interacting with the primary sludge whenever the tank is fed. The

design implemented could be appropriate. An angled or more complicated feeding system

is likely better but this complicates the building process and durability.

Create a steel wool or iron or iron shavings filter. The filter (iron [Fe] is the agent) removes

hydrogen sulfide [H2S] from the product which is a harmful gas that occurs in small

amounts. A steel wool filter can easily and cheaply be created.

Create a short term gas storage mechanism. The design featured previously can be made

affordably and relatively easily. Because of prototyping errors and the inability to obtain a

strong enough bag in country, the design was not fully tested (it did past a leakage test

when filled with water).

Create the water trap inexpensively. In general, the water trap is a very helpful design

feature because it gives a clear visual representation of how much gas is ready for use.

While respecting the first priority, the water trap can be built very inexpensively. In

country, two polytanks were utilized and recycled from the previously implemented

digester. Something so expensive and robust is not at all necessary for a water trap.

Requirements for the water trap construction in the future:

o Be penetrated by a pipe and sealed water tight.

o Generally not have any leaks; be solid (it is a container of water).

o Have a slightly smaller upside container for the gas to be stored. This upside down

container will also need an air tight seal for a gas line; the gas is forced out of this

container.

o Be durable enough to hold large amounts of water for long periods of time.

Thoroughly research feedstock options and ways to optimize methane creation. For about

as free as the primary feedstock (animal or human waste), various substances such as

cooking oil waste and rice straw can be added to the primary sludge to increase the gas

output. In general, high lipid food wastes and various natural grown products and farm

waste increase gas output11. Too much of either can be added, however. Reference No.11

provides an excellent breakdown of these details.

29

13. References 1Biodigester - Methane as Fuel. Accessed December 3, 2015.

https://www.youtube.com/watch?v=xAkIKxA3Jm0.

2“Biogas Production and Applications,” n.d. Accessed December 3, 2015.

3Foodwaste Biogas Generator. University of Malaya, n.d.

https://www.youtube.com/watch?v=KpYdHXvQ50g.

4“Fundamentals of Anaerobic Digestion,” n.d. Accessed December 3, 2015.

5How to Make a Bio-Gas Digester, n.d. https://www.youtube.com/watch?v=mWefbc1spd0.

6Lansing S, Botero RB, and Martin JF. Wastewater Treatment and Biogas Production in

Small-Scale Agricultural Digesters. Bioresour Technol, 2008.

7Lansing S, Vı´quez J, Martı´nez H, Botero R, and Martin J. Optimizing Electricity

Generation and Waste Transformations in a Low-Cost, Plug-Flow Anaerobic

Digestion System. Ecol Eng, 2008.

8Mamun, Muhammed Rashed et. al. Methane Enrichment of Biogas by Carbon Dioxide

Fixation with Calcium Hydroxide and Activated Carbon. Journal of the Taiwan

Institute of Chemical Engineers 58 (2016): 476-81. Accessed December 30,

2015.http://www.sciencedirect.com/science/article/pii/S1876107015003132 9Peter Weiland. “Biogas Production: Current State and Perspectives.” Appl Microbiol

Biotechnol, 2010.

10Rajabapaiah P, Jayakumar S, and Reddy AKN. Biogas Electricity. 1993rd ed. Renewable

Energy: Sources for Fuels and Electricity. Washington DC: Island Press, n.d.

11Storing Biogas in a Plastic Trash Bag. Accessed December 3, 2015.

https://www.youtube.com/watch?v=fZJ6mu7O3c8.

12The Health Effects of Wood Smoke. Accessed December 3, 2015

http://www.ehhi.org/woodsmoke/health_effects.shtml 13Xiaohua W, Li J. Influence of Using Household Biogas Digesters on Household Energy

Consumption in Rural Areas. 2005th ed. A Case Study in Lianshui County in

China. Renewable Sustainable Energy, n.d.

30

14. Acknowledgements

The authors would like to thank resident directors Dr. Roger Dzwonczyk and

Mariantonieta Gutierrez Soto for their the advice and planning. Thanks to Nana Odeneho,

Andrew Bediako, and other Ghana in-country partners for their help and patience. Thanks to Dr.

Yebo Li for technical advice, Dr. Scott Shearer for providing prototyping facility in Agricultural

Building, Aleksandr Yakhnitskiy from Quasar Energy Group, and the Waterman farm for

providing project related materials. Thanks to Anne Christy, Michael Lichensteiger for proving

the laboratory to test the prototype.

For the Ghana trip, the authors would also like to thank to Kojo Appiah-Kubi for

providing the service learning program. Thanks to Augustine Yeboah for his great help during

whole construction. Thanks to Wil Aparloo Ofori for showing the huge biogas digestion in

Techiman Processing Complex. Thanks to Andrew Bediako, Evans Kwame for their help during

the trip. Thanks to Mahadi Annor for proving pick up service. Thanks to all ONDA partners for

their patience and help.

31

15. Appendices

15.1 Extra Figures

Figure 11. Flame test. Figure 12. Steel wool condition.

Figure 13. The team replaced the sealing part on old tank

32

Figure 14. Team member (Kave) was injecting manure into the digestion tank

Figure 15. The completed final project

Figure 16. Business Card of Wil

33

15.2 Biogas Technology Team Agreement

Biogas Technology Team Agreement

Identifying the project:

● Term of contract: 09/13/2015 ­ 05/01/2016

● Team members and contact information:

Victor Haynes: (815) 302­3242 [email protected]

Major: Civil Engineering

Minor: Design

Kan Liu: (917) 250 9768 [email protected] Major:

Aerospace Engineering

Minor: Global Option in Engineering

Meng Cheng: (614) 254­9351 [email protected]

Major: Mechanical Engineering

Minor: Russian & Math

Kave Anderson: (404) 468­2806 [email protected]

Major: Biological Engineering

Minor: Global Option in Engineering

Teamwork Criteria:

1. Team Leadership Roles:

● Kave Anderson: Team Leader, CCO (Chief Communications Officer)

● Kan Liu: Co­leader, Director of Testing, Logistics Manager.

● Meng Cheng: Primary Documenter/Scribe/Recording Secretary.

Victor Haynes: CFO (Chief Financial Officer) Accountant, Photographer,

Videographer.

2. Preferred Methods of Communication:

● Email, phone communication, and Whatsapp.

● Information will be stored on a Google Drive.

● Project timeline will be created and edited with Excel on Google Doc.

3. Meeting Guidelines:

34

● There will be a regularly scheduled meeting on Wednesday at 8 P.M. at SEL

weekly.

● Before every meeting, an agenda will be written and followed.

● Every meeting will be documented by recording secretary.

● Attendance is required for every team member unless communicated 24 hours in

advance.

● All members should arrive no later than five minutes after meeting time.

● All members should stay on task during the meeting.

● Meetings will be arranged at times when all members are available.

● At the end of each class session/meeting, members will define tasks required for

next class session/meeting.

4. Participation:

● Project partners will put forth effort to complete all tasks and participate as much as

possible.

● All are free and encouraged to equally participate in meetings.

● All members should perform the tasks described in the team agreement.

5. Responsibilities:

The project is a partnership. All members are equally responsible for completing the

project.

● Team members will hold each other accountable during all aspects of the project.

● The Chief Communications Officer will be in charge of communicating with

Ghana partners and anyone else involved in developing the project.

● The Chief Financial Officer is responsible for maintaining financial records of

project expenses and budgeting.

● The Logistics Manager is responsible for creating a project timeline and maintaining

the schedule throughout the duration of the project.

● The Primary Documenter is responsible for submitting documents on time and

assembling any written reports required for the project. Any documents should be

checked by all members before submitting. The receipt should be forwarded to all

members after submitting.

6. Approaches to conflict resolution:

● Conflicts will be resolved internally on a flexible, case­to­case basis.

● For conflicts that cannot be resolved internally, group members will seek help from

one of the instructors to serve as a mediator.

35

7. Approaches to problem solving:

● All team members will have equal opportunity to solve a problem. All ideas will be

considered.

● After all possible solutions have been proposed, team members will discuss further

options for solving the problem.

8. Approaches to decision making:

● Decisions will be made as a team as often as possible.

● Decisions will be made by majority vote by team members.

● In the case that team members cannot agree on a decision, efforts will be made to try

all ideas given that the circumstances permit trying more than one.

9. Signatures (dated) of all team members, thereby agreeing to abide by this contract

36

15.3 Meeting Notes

Bio-gas team meeting notes.

1st Meeting

Location: SEL underground

Date: Sept. 13th 2015

Time: 8 P.M.

Main purpose: Writing the Team Agreement.

Based on the Team Agreement template provided on Carmen, a detailed and strict Agreement

had been approved and signed. Major improvements includes task assignment, regularly meeting

weekly, strict on time rule and majority vote rule.

P.S.

(An Email will be sent on Tuesday before every regularly meeting with discussing topics as

reminders.)

(Remind: Add Augistine and other technicians on Whatsapp)

(Updated on Sept. 14th)

2nd Meeting

Location: SEL underground

Date: Sept. 16th 2015

Time: 8 P.M.

Main purpose: Writing the Project Proposal

The team was confused on the goal of the project. Should the biogas electricity generator be

considered during the program? The team decided to discuss with Roger on next lecture.

The Proposal version 1.0 was finished during the meeting. The team decided to bring a hard copy

and ask for Roger’s opinion on the following lecture. More detailed information or correction

may be applied based the advices from instructor.

(Updated on Sept. 16th 9:54 P.M.)

The proposal was fixed according to comments from Roger and Mariant, and the latest version

was uploaded to carmen on 8:10PM. Sept. 23rd.

3rd Quick Meeting

Location: Smith lab

Date: Sept. 22nd 2015

Time: 5:20 P.M.

Due to the career fair and the complement of proposal, the team decided to call off the next

regularly meeting on Wednesday (Sept. 23rd).

The team will start the research work and try to build the first prototype in the following classes.

Each team member needs to collect information and learn about bio-digester before next class.

37

On Thursday, the team member will brainstorm the bio-digester design and draw out the

timeline. Kave (CCO) will reach Augustine within the week in order to discuss prototype design.

(Updated on Sept. 23rd 8:27 P.M.)

4th Meeting

Location: Smith lab

Date: Sept. 24th 2015

Time: 4:20 P.M.

Main purpose: Draw out the Gantt Chart

Pre-Trip Technical Report Contains:

SOW- stated needs

deliverable list- include sustainability and ownership (Owner: Kave)

description of research, design, prototyping, testing (Owner: Meng)

cost analysis of project (Owner: Vic)

lists of tools, equipment and supplies (Owner: Vic & Kave)

timeline of design, development, prototyping, implementation (Owner: Kan)

The SOW has already roughly down during the previous proposal. The 4 terms need to be

considered about are researching, designing, prototyping & testing. From this meeting to the

final report due, there are ten weeks. The team decided to spend 2 weeks on researching, 2 weeks

on designing, 3 weeks on prototyping and 2 weeks on testing. The rest week is going to be used

as analyzing and documenting week. The team also going to list the tools and supplies will be

used in Ghana during the last week. The time can be flexible based on the project process.

Team will start the research process since next week.

The research progress includes reading articles, connecting with professors at OSU experienced

with bio-digester, investigating the experimental bio-digester at Waterman Farm and collecting

local informations(ingredients source, local soil, etc.) at Ghana from Adam and Agustine.

The team will also research different methods of generating electricity with biogas.

5th Meeting

Location: Smith lab

Date: Sept. 29th 2015

Time: 4:20 P.M.

Main purpose: Research Report

38

Kave:

● Emailed 7 professors and received 3 responses. Get contact information.

Yibo Li: Can be contact with video/audio chat. Oct. 2nd ,6th- 9th.

Will schedule a remote meeting on Oct. 9th at 10:10 A.M.

Rest of the professors suggested Dr. Li on the issue.

● One video instruction and one website on how to build bio-digester.

● Need more research on the usage of “steel wool”.

Kan:

● Video: how to build bio digester.

● Listed the materials to build a prototype.

● Need to stir the tank after a period of using. (Need a string rod inside?)

● Trolley to move the biodigester.

Victor:

● The amount of the solid “bad waste” will leave in tank. How long do we need to clean it?

Meng:

● Ingredients to use in the digester.

● Ph, Temp in the digester and the pressure to keep for the natural gas.

More Q:

● What kind of ingredients or catalysts can speed up the progress?

● What are the mainly maintenance procedure? Can we make it easier? Charging time?

● Should have one man in the community shadowing with the group to learn most of the

procedure and principle.

● How long does it take for the gas work?

● Source of ingredients for the prototype testing.

● What is the container made out of?(What type of plastic, PVC or PET?)

● What is the gas output?(The percentage of the methane for the 1st time and normally

works.)

● What issues/complications generally arise? (In your experience, if any)

● Do we need to have a mechanism for stirring the contents?

Actions to do Next:

● Schedule meeting with Dr. Li. and Dr. Martin. Contact with Dr. Micheal. (Kave)

● Finish the Gantt Chart. (Kan)

● Complete the work updated.(Meng)

● Schedule a meeting room.(Victor)

● Finish the Capstone quizzes. (Meng, Kave, Victor)

39

10 OCTOBER 15

(Class Workday)

● Kave’s idea: look into different types of oil for testing (palm oil?)

○ Ask Augustine about the kinds of cooking oil that are available

■ Frytol, palm oil?

● Look at articles 38-42 in Kave’s link (figure out which oils work best/lipids?)

● Continue research

Meeting with Dr. Li

Of usage:

o At least 500 kWh or electricity it’s not econ.

o The usage amount for cooking is actually not much.

Of maintenance:

o Too much dirt or ashes my precipitated at the bottom.

Of food waste:

o It doesn’t matter. Any organic things can be used.

Of mixing:

o Small size of the digester don’t need to be stirred but can add a slope.

Of materials:

o The materials are mainly choose by cheaper materials

Of time:

o It’s all depends on the seeds (bacteria). Better get from another bio-digester local.

Of Steel Wool:

o It’s really useful from avoiding loss of heat.

Of gas amount:

o Need to be calculated from the ingredients’ potential specific heat.

Of pH

o The ph mainly caused by fatty acid added.

o If the ph is lower than 6, stop feeding. If the pH is even low at 5, add things to

bring pH up.

6th Meeting

Location: Smith lab

Date: Oct. 13th 2015

Time: 4:20 P.M.

Main purpose: prototype progress.

Based on the discussion result, the team canceled the second prototype test with a 200 L plastic

drum due to time reason. The team also canceled the tour to the Quasar Company because of

lacking storage place. The team will go contact Quasar first to find out can we get the seed from

40

them. According to Adam’s experience, the team will go contact with waterman farm later for

digestion ingredients.

P.S.

A email from Quasar was received on 19th which confirmed that they can offer seeds.

The tour is scheduled on Friday.

Oct 27th update

1. The team get the place but need permission.

2. Farm tour canceled and will be re-scheduled

3. Received reply from Andy.

4. Prototype Connection issue. The flexible tube will be replaced by PVC tube in the real project.

Nov 3rd update

1. Contacting Techiman Processing Complex

2. Confirmed lab place at AG 150

3. Scheduled visit to Quasar & Waterman Farm

4. Pre-trip Report

5. Put limes in water to reduce the concentrate of CO2

41

15.4 Maintenance & Use

Operation: When to inject?

The bio-digestion process is a long term process. Feeding too frequently may cause failure.

The right time to inject the ingredients is when the pressure in the floating gas tank begin to

decrease. This means the production amount of biogas is less than the usage amount, and the

digestion tank need more materials.

What to Inject?

Many kinds of organic waste can be used as ingredients for the digester, including animal and

human manure, kitchen waste and straw. However, the user should control the humidity and the

C/N ratio of the ingredients injected. The best C/N ratio is from 20 to 30, the water and dry

ingredients ratio is 1:3.

The following is a C/N ratio table.

For example, using the common ingredients cow manure and straw, the ratio of manure to

straw should be 2:1 in order to give 25 C/N ratio.

How to inject?

Open both injection tubes, put the ingredients in the vertical tube and push it in through

horizontal tube. Other time, keep the injection tubes closed.

When to collect fertilizer?

At the same time of injecting new ingredients. The materials inside has already undergone

digestion process and turned into fertilizer. It’s a good time to take these fertilizer out.

How to collect fertilizer?

Just open the fertilizer valve and collect with a bucket.

When to replace steel wool?

Since the concentrate of H2S in the biogas is really small, the steel wool does not need to be

replaced frequently. Check the condition of the steel wool every 3 months. If most part the steel

wool turned into dark brown, then we need to replace the steel wool.

How to replace steel wool?

Close the two valves on each side of the steel wool filter. Open the top lid of the filter and take

the old one out. Tear the new steel wool to make it fluffy, then full fill the filter. Close the top lid

and open two valves.

How much water should be added?

42

Due to the leakage and evaporation, the water in the water tank is losing all the time. User

need to add more water in order to keep the water trap working. The water level should never

higher than the alert mark on the PVC pipe. (Or the water may flow back through the gas tube.)

How to control a proper pressure?

The pressure inside the equipment is controlled by the weight on the gas tank. Increase the

weight to increase the pressure or vice versa.

Maintenance: What if there’s no biogas?

Check all the connections and make sure there’s no leakage. Take some fertilizer out and

exam the pH level. The proper pH level inside the digestion tank is around neutral. If the pH is

lower than 6, stop feeding and wait it until it turns back.

How to deal with leaking?

The leaking may happened as time goes by. Clean the leaking part and keep it dry, then seal

the leakage with PVC glue or silicon for the PVC tube or poly tank.

Caution: The biogas is a highly flammable gas fuel. Do not smoke or burn around the

equipment.

The equipment need to be kept in tightly sealed condition. Do not use sharp object

scratch the equipment.

The oxygen burning ratio of biogas and LPG are different. Do not use biogas to cook

with the stove for LPG.

43

15.5 Overall Gantt Chart

44

45

46

47


Recommended