i
ENVIRONMENT
MANAGEMENT
or
CONCEPTUAL PLAN
ii
Table of Contents
Sl. No. Contents Page
Nos.
A INTRODUCTION 1
1.1 Proposal of project details 1
1.2 Project proponent 1
1.3 Site Location 1
B ENVIRONMENTAL IMPACTS ON PROJECT LAND AND IT’s
SURROUNDING DEVLOPMENTS
10
2.1 Environment Settings of project site are as follows. 10
2.2 Environmental Impacts of Proposed Project Activity 11
2.3 Air Quality Impacts 11
2.3.1 Construction Phase Impacts 11
2.3.2 Mitigation Measures proposed 12
2.3.3 Occupation Phase Impacts 13
2.3.4 Mitigation Measures Proposed 13
C WATER REQUIREMENT AND SUPPLY SYSTEM(Water
Balance)
14
3.0 Water Supply During Construction Stage 14
3.1 Water Supply During Operation Phase 14
3.2 Wastewater Treatment System 16
D EXTERNAL SEWERAGE 19
E GROUND WATER POTENTIAL/HYDROGEOLOGY 19
4.1 Storm Water drainage and Rain water harvesting 20
F SOLID WASTE MANAGEMENT DURING CONSTRUCTION
PHASE AND OPERATION PHASE
21
5.0 Construction Phase 21
5.1 Solid Waste Collection / Disposal Plan during Operation Phase: 22
G AIR QUAITY AND NOISE LEVELS IMPACTS & MITIGATION
MEASURES
24
6.1 Air Quality Impacts 24
6.1.1 Construction Phase Impacts 24
6.1.2 Mitigation Measures proposed 24
6.1.3 Occupation Phase Impacts 25
6.2 Noise Level Impacts 26
6.2.1 Impact during Construction 26
6.2.2 Mitigation Measures 26
6.2.3 Noise Impacts during Occupation phase 26
6.2.4 Mitigation Measures 26
iii
H ENERGY & POWER REQUIREMENT, ELECTRICAL,
BUILDING & FIRE SAFETY ,DG SETS DETAILS
28
7.1 General 28
7.2 Design standards & codes 28
7.3 Design criteria for energy efficiency 28
7.4 Electrical load estimates 29
7.5 Source of Power 29
7.6 Backup power supply 30
7.7 Lighting & power requirement 30
7.7.1 Earthing System 30
7.7.2 Fire Alarm System 31
7.8 Street lighting 31
I TRAFFIC CIRCULATION SYSTEM AND CONNECTIVITY
(PARKING REQUIREMENTS AND PROVISIONS)
32
J GREEN BELT /GREEN COVER AND THE LANDSCAPE PLAN 35
K DISASTER/ RISK ASSESSMENT AND MANAGEMENT PLAN 38
L SOCIO-ECONOMICS/ DEMOGRAPHY IMPACTS OF THE
PROJECTS
38
M ENVIRONMENT MANAGEMENT PLAN 40
9.0 Project Monitoring 40
9.1 Monitoring Stratergy 40
9.2 Ambient Air Monitoring 40
9.3 Noise Monitoring 41
9.4 Water Quality Monitoring 41
9.5 Sewage Treatment Plant 41
9.6 Budget for EMP 41
9.7 Manpower requirement 42
9.8 Environment Management plan 42
9.9 Environment Management Cell 45
N. PROJECT BENEFITS
46
List of Tables
Sl. No. Tables Page
Nos.
1 Proposed Activities hereunder 1
2 List of NOC’s obtained for the Site 3
3 Landuse Breakup 6
4 Breakup of Net plot Area 6
5 Environment Settings 10
6 Details of DG set and Stack Height Calculations 13
7 Air Pollution Control Measures 13
iv
List of Figures
Sl. No. Figures Page
Nos.
1 Google Imagery of project site 2
2 Photographs Of Proposed Project Site 3
3 Topographical Map showing 10 km radius 4
4 Master layout plan 5
5 Elevation Plan 7
6 Floor Plans of Building 8
7 Water Balance Chart 15
8 Proposed Tentative STP Layout Plan with MBBR Technology 18
9 General process diagram of STP plan 19
10 Typical Rain Water Harvesting Pit Design 20
11 Solid Waste Management plan during operation phase 23
12 Design criteria for energy effiency 28
13 Power requirement 29
14 Basement Parking 1, 2 & 3 34
17 Land scape Plan 36
List of Annexures
S. No. Name of Annexure Page
no.
1 Highrise Clearance from Airport Authority of India, Begumpet 49
2 Land Documents 51
8 Daily Water Requirement 14
9 Wastewater Calculations 15
10 Estimated Wastewater Characteristics 16
11 Calculation for Storm Water Load 22
12 Solid Waste Generation during operation phase 28
13 Design criteria for Energy Efficiency 29
14 Power Requirement 32
15 Parking Requirement. 37
16 List of plants identified for greenbelt and plantations 41
17 EMP Budget 42
18 Manpower Requirement 43
19 Proposed Environmental Mitigation Measures 43
20 Environmental Monitoring Plan – Operation Phase 44
21 Environment Management Cell 45
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 1
ENVIRONMENT MANAGEMENT PLAN
A. BRIEF DESCRIPTION OF PROJECT IN TERMS OF LOCATION AND SURROUNDINGS
1.1 PROPOSAL OF PROJECT DETAILS
M/s. Green House Plantations Pvt. Ltd. is proposing to construct a New Commercial Building project at
Survey No. 45, 46, 47 & 53, Raidurg Nawkhalsa(Village), Serilingampally(Mandal), Ranga Reddy (Dist),
Telangana state-500008.
Total Land Area : 1.23 Acres or 4988.67Sq.mts
Road widening Area : 212.65 sq.mt
Net Plot Area : 4776.02sq.mt
Proposed Built up area: 29,159.33 sq.mt.
Proposed Height of Buildig : 49.7meters (High-rise NOC obtained from Airport Authority of India)
Estimated Project cost : 40 crores
EMP budget (Capital cost) : 1.5 crores Recurring Cost : 30 Lakhs.
Table 1 : Proposed Activities hereunder
S.no Type of Buildig Units
Built Up Area
(in Sq.mt)
1
Podium Building
(In 2 Floors) Ground +1st floor 4547.17
2
Commercial Offices
(11 Floors)
3rd
to 12th
Floor
(2 units per floor) 17528.54
Parking Area
3 Basement-1 (Regular parking) 3494.49
4 Basement-1
(Mechanical
parking)
1056.00
5 Basement-2 (Regular parking) 3494.49
6 Basement-3 (Regular parking) 3585.81
Total Proposed Built-up Area 29159.33
1.2 PROJECT PROPONENT
Sri. Allaka Satyanarayana (Director)
Address.D.No.1-1-380/20/A/2, V.V. Girinagar, Gandhinagar, Beside Jagadambha Hospital, Hyderabad 500080
1.3 SITE LOCATION:
Survey No. 45, 46, 47 & 53, Raidurg Nawkhalsa(Village), Serilingampally(Mandal), Ranga Reddy (Dist),
Telangana state-500008.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 2
Fig.1. Key Location map
Fig.2 Google Imagery of project site
Proposed Project Site
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 3
Table2- Lat-Longs of the Site Area
Features of the Project Site:
The project site is plain and covered by sparse vegetation of shrubs and few trees. The terrain of the
project site and its surrounding area is plain. The site is devoid of any rocky outcrops and is not
covered by any notified forests.
Fig 3: PHOTOGRAPHS OF PROJECT SITE
S.no Lattitude Longitude
1 17°25'14.61"N 78°23'04.44"E
2 17°25'13.94"N 78°23'05.65"E
3 17°25'10.95"N 78°23'03.42"E
4 17°25'11.56"N 78°23'02.21"E
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 4
FIG 4: TOPOGRAPHICAL MAP- 10 KM RADIUS OF PROJECT LOCATION
Project Site Project Site
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 5
FIG 5 : MASTER LAYOUT PLAN
STP Plant
Organic
waste
conveerter
Green
Belt
Podium
Commercial
Tower
7m
setback
Exit Entrance Garbage
storage area
RWH
pits
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 6
Table3.LANDUSE BREAKUP
Table 4. Breakup of Builtup Area Floorwise
Name of the Floor Built-UP Area in
Sq.mt
Ground Floor 2188.65
1st Floor 2358.52
3rd Floor 1176.27
4th Floor 1176.27
5th Floor 1176.27
6th Floor 1197.47
7th Floor 1176.27
8th Floor 1176.27
9th floor 1176.27
10th floor 1197.47
11th floor 1176.27
12th Floor 1176.27
Total Built-up area of the Towers (A) 17528.54
Basement-1(Regular Parking) 3494.49
Basement-1(Mechanical Parking) 1056
Basement-2 3494.49
Basement-3 3585.81
Total Parking Area provided (B)
11630.79
(Which is
66.3% of BUA)
Total Built-Up Area of Entire Building 29159.33 sq.mt
S.No Landuse Area in Sq.mt Percentage
1 Road widening 212.65 4.2
2 Green Area 478.81 9.7
3 Plinth Area 1176.27 23.6
4 Parking area 3120.94 62.5
Total Land Area 4988.67Sq.mt 100%
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 7
FIG 6 : ELEVATION PLAN
FIG 7 : Prospective View of the Building
Podium
(G+1 Floors)
Tower of 11
floors with
commercial
Offices
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 8
Fig.8: Floor Plans of Building
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 9
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 10
B.ENVIRONMENTAL IMPACTS ON PROJECT LAND AND IT’s SURROUNDING DEVLOPMENTS
2.1 Environment Settings of project site are as follows.
Table 5: Environment Settings
Particulars Details
Location of Project Survey No. 45, 46, 47 & 53, Raidurg Nawkhalsa(Village),
Serilingampally(Mandal), Ranga Reddy (District),
Telangana state-500008
Temperature(0C) 45
0C (max), 18
0C (min)
Nearest Railway station Hyderabad Deccan Railway station is 9.2km in SE direction.
Nearest Airport Begumpet Airport is at 9.8km(North East)
Rajiv Gandhi International Airport: 20km(South)
Other Historical / Religious
places
None
Defence installations No
Ecologically sensitive areas
(National Parks / Wild life
sanctuaries / bio-sphere
reserves, migratory routes
within).
None
Reserved / Protected Forest 1. Kottaguda Reserve Forest ---5.0km [NW]
2. Chilkur Protected Forest ---7.2km[SW]
Nearest Water Bodies Water Bodies
1.Malaka cheruvu -------------200 meters [SE]
2.Durgam cheruvu -----------1.0km [North]
3.Kajaguda cheruvu ----------1.5km [NW]
4.Suraram cheruvu ------------4.5km[North]
5.Musi River ------------------5.5km [South]
6.Kamunoni Cheruvu ---------6.1km[NNW]
7.Maisamma cheruvu ---------6.7km [NW]
8.Hussain Sagar ---------------9.7km [East]
9.Osman Sagar ----------------9.8km [SW]
The proposed project falls within 10km radius of Osmansagar lake.
But Rai durg Nawakhalsa village is not listed in the 84 List of
villages within 10km catchment area of Himayatsagar and
Osmansagar Lakes as mentioned in GO MS.No.111 Act
dated.08.03.1996 issued by MA&UD Dept. Govt. of A.P (Combined
state)
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 11
2.2 Environmental Impacts of Proposed Project Activity
The purpose of the impact assessment study is to provide information on the nature and extent of
environmental impacts arising from the proposed project during construction and occupation. This
information shall contribute decisions on the following;
Overall acceptability of any adverse environmental consequences that are likely to arise as a result of
the proposed project.
Conditions and requirements for the detailed design, establishment and operation of the proposed
project to mitigate against adverse environmental consequences wherever practicable and
Acceptability of minimized impacts after the proposed mitigation measures is implemented.
The environmental impact assessment of the proposed activity shall cover all developments within the
proposed project site and any other works associated with these developments outside the project area. The
impact prediction shall include specific impacts namely; air quality impact, water pollution impacts, noise
impacts, ecological impact and socio-economic impacts. The impact assessment is carried out for the
construction phase and operation phase.
2.3 Air Quality Impacts
An assessment of air quality impacts associated with the construction and occupation of the proposed project
has been carried out. Worst case impacts on the representative receivers have been assessed. Three major
sources of air pollution have been identified namely construction dust emission, road traffic emissions and
DG set emissions.
a. Construction Phase: Construction works include site clearance, site formation, building works,
infrastructure provision and any other infrastructure activities. The major air pollution source during this
activity is dust generation as a result of the above activities.
b. Occupational Phase: The major sources of air pollutants are the vehicle emissions from traffic on roads
internal and neighboring roads, air pollutants emitted from operation of DG sets and other mechanical
equipments used for day to day activities proposed at these project.
The representative air sensitive receivers within the study area represent the future and existing sensitive
receivers likely to be affected by the project.
2.3.1 Construction Phase Impacts
The principal potential source of air quality impact arising during construction period is fugitive dust
generation. The dust, measurable as PM 2.5 & PM 10 would be generated as a result of construction activities.
The construction program of the project shall commence immediately after obtaining statutory clearances.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 12
The potential dust sources associated with construction activities are loading and unloading of the materials,
top soil removal, travel over unpaved roads and wind erosion etc. The construction works associated with the
proposed development are broadly given below.
1. Site development and foundation works
2. Dust generation due to vehicles bringing raw materials
3. Un loading of raw materials, removal of un wanted waste material from site
4. Civil constructions and provision of infrastructure required for various activities proposed at each
project.
Among all the construction activities, site formation has the highest potential for causing dust nuisance to the
nearby air sensitive locations. During the construction of the project, existing houses nearby may be subject to
the potential dust impacts.
2.3.2 Mitigation Measures proposed
For the proposed project, site leveling and grading will be carried out for construction apartments and club
house, where ever possible natural elevations will not be disturbed, only leveling activity will be carried out
for providing roads, sewage network, storm water system, and places required for providing buildings.
According to the engineering assessment; most of the excavated material (for providing basements) shall be
reused within the project boundary, if any excess will be disposed through local contractors for filling low
lying areas or road laying purposes, etc. The movement of cut and fill material will be limited. Broad
estimation shows that there would not be more than 10 vehicles from the construction site within a day, since
all the excavated material shall be reused at the site itself.
The control measures proposed to be taken up are in-line with Construction and demolition waste
management rules 2016:
Regular water sprinkling on internal roads in the project area, this activity will be carried out at least
twice a day, if need arises frequency will be increased on windy days, in this way around 50% reduction
on the dust contribution from the exposed surface can be achieved.
The duration of stockpiling will be as short as possible as most of the material will be used as backfill
material for the open cut trenches for road development.
Temporary tin sheets of sufficient height (3m) will be erected around the site of dust generation or all
around the project site as barrier for dust control.
All the vehicles carrying raw materials will be covered with tarpaulin / plastic sheet, unloading and
loading activity will be stopped during windy period.
To reduce the dust movement from civil construction site to the neighborhood the external part of the
building will be covered by plastic sheets
Vehicles having pollution under control certificate will be allowed.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 13
Drivers of the Vehicles will be instructed to follow speed limits (<20 kmph), reducing the speed of
the vehicle will reduce generation of dust to large extent.
Speed limit boards will be displayed at entrance gate, speed breakers will be provided if needed.
Given the implementation of proper control measures for dust suppression, no adverse impacts are
expected and compliance with the Ambient Air Quality is achieved at all time.
2.3.3 Occupation Phase Impacts
As the proposed project is a construction project there are no major point source emissions like industries. The
major air pollutants associated with this project is from incoming and outgoing vehicles. In addition to this the
other source is use of DG set during power failure as back up source for lighting and other emergency needs.
The proposed Construction activity is proposing 2*150KVA DG set. The use of DG set will be as minimum
as possible as it is used during power failure as a backup. The Details of the DG set stack height calculation,
stack provided, pollutants expected is given in Table 6.
Table- 6
Details of DG set and Stack Height Calculations
DG SET CALCULATION
Capacity 150 KVA
Diesel requirement 18 LPH
Diesel requirement 16.2 kg/h
Sulphur 0.05 %
Sulphur 0.0162 Kg/h
SO2 0.0045 g/s
NOx 0.02295 g/s
Height of Building 49.7 m
Proposed stack height( in meters) 52.1 m
2.3.4 Mitigation Measures Proposed
In addition to the mitigation measures proposed above which will be extended for occupation phase, the other
air pollution control measures suggested are listed in Table 7
Table 7
Air Pollution Control Measures
Sources Air pollutant Control
DG set SO2, NOx Adequate stack height for proper dispersion of pollutants
Vehicles Dust, SO2, NOx,
CO, HC.
Black carpeted roads will be maintained properly to reduce dust
All vehicle owners will be informed to follow the emissions
standards fixed by the government authorities
General Measures
Provision of minimum of 2 rows of plantation with 1m wide greenbelt along the road sides
Provision of minimum of 1m wide around the STP area
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 14
C. WATER REQUIREMENT AND SUPPLY SYSTEM(Water Balance)
Water is an essential component of the basic infrastructure for urban settlements. Besides domestic use, water
is also required for fire fighting and other miscellaneous purposes. The water requirements have been
calculated as per IS: 1172 - 1993 Code of basic Requirements for Water Supply, Drainage and Sanitation (4th
Revision) by Bureau of Indian Standards (BIS), considering the needs for Indian town and cities.
3.0 Water Supply During Construction Stage
During construction stage, water will be sourced primarily through tankers from local Suppliers or Bore
wells to be laid with permission from local authorities.
3.1 Water Supply During Operation Phase:
Total water requirement has been calculated during operation phase as per the standards given below.
Table 8 : Daily Water Requirement calculation
S.No. Description Occupancy Demand
(lpcd)
Total requirement in
KLD
1
Water requirements 10sq.mt per person,
running 3 shifts at max
Commercial Office Area
(12981.37 sq.mt) 1300 45 175
Podium Building
(G+1st Floor)
(4547.17Sq.mt)
50 45 5
Visitors 200 15 3
Area liter/sqm
2 Greenbelt 478.81sq.mt 3 2
KVA lt/KVA/hr
3 DG set cooling
(2*150KVA) 300 0.9 1
Total water requirement 186
Source of Fresh water during operational phase: HMWSSB
Total Water Requirement for the project in initial Phase 183KLD
Daily Net Fresh Water Requirement
(Total Water requirement -Flushing Water) 183-55 =128KLD
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 15
Fig 9. Water Balance Chart
Table.9. Wastewater calculation
Wastewater Generation & Treatment
Total Sewage/wastewater Generation (Approximately) 158KLD
Proposed STP Capacity 180KLD
Recycled water from treated water tank (Flushing +Greenbelt+ DG set cooling) 88KLD
Excess water released into the Public sewer line 37KLD
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 16
3.2 WASTEWATER TREATMENT SYSTEM
Total wastewater generation from the proposed project activity will be 158KLD. The sewage generated
during the operation phase will be treated up to the tertiary level in a STP setup proposed in the site having
capacity of 180KLD. The treated sewage quantity of 88KLPD (80% treatment efficiency) is recycled/ reused
for toilet flushing and horticulture in the project site. Remaining water will be discharged into Municipal
Sewer line after STP treatment. The detailed water balance is given in Water Balance Table no 7
WASTEWATER TREATMENT TECHNOLOGY:
Section – I : Design basis, Treatment Scheme & Treatment Process
Flow rate : 150-180 m3/day
Nature of wastewater: Combined Sewage
Characteristics of inlet/outlet of STP: (Assumed)
Table No.10 : Estimated Wastewater Characteristics
S.
No.
Parameters Inlet Sewage
water
Characteristics
After
Biological
treatment
After
Tertiary
treatment
1. PH 7.0-8.5 7.0-8.0 7.0-8.0
2. COD, mg/l 550-700 < 100 < 60
3. BOD, 5 days @ 20 deg.
C, mg/l
250-350 < 20 < 10
4. Suspended solids, mg/l 200-250 < 100 < 10
5. Oil & grease, mg/l Up to 50 < 10 < 10
Mode of disposal of treated water: - Recycling in irrigation, horticulture, Landscaping
Treatment scheme:
Screening, Oil & Grease removal, collection, equalization and transfer of wastewater to FAB
reactor through anoxic tank
Biological treatment of wastewater using MBBR Technology.
Secondary Clarification of biologically treated wastewater using Tube Deck Media.
Disinfection of treated water using sodium hypochlorite.
Filtration of Chlorinated treated water through DMF & ACF.
Reuse of treated water in horticulture & plantation & Tertiary Treatment.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 17
Sludge treatment through Filter bag Mechanism.
Section – II: Technical notes
STP shall be compact, smell free and shall consume less power.
Bar Screen: The Bar Screens of SS 304 material is considered in the scope for better life. Two
bar screens of 10 mm spacing followed by 8 mm spacing are considered in series. The screens
can be easily removed & cleaned as required.
Oil & Grease Removal: We have proposed manually cleaned oil & grease trap with baffle
arrangement for removal of oil & grease coming from kitchen/cafeteria for better & smell free
biological process.
Equalization Tank: We have proposed collection cum equalization tank in RCC below the
ground level. All other tanks of STP in RCC can be built fully/partly above the ground as
required. The tanks can be covered from the top, if required and access manholes can be
provided. The tank is provided with air distribution piping with adequate number of Coarse
Bubble diffusers.
MBBR: MBBR reactor tank consists of a tank filled with specially developed media which are
made of special material of suitable density that can be fluidized by providing aeration with the
help of blowers through diffusers. This helps to develop a bio-film on the media, which move
along the effluent in the reactor. The movement within the reactor is generated by providing
aeration with the help of diffusers placed at the bottom of the reactor. The thin film on the media
enables the bacteria to act upon the bio-degradable matter in the effluent and reduce BOD/COD
content in presence of oxygen from the air used for fluidization.
Tube Deck Media Clarifier: The overflow of MBBR tank is taken in to the Tube Deck Media
Clarifier. Here Tube Deck media in PVC is arranged to facilitate solid liquid separation.
Clarified/Clear Water Tank: The clear water from Tube Deck Media Clarifier flows in to this
tank.
Media Filtration & Carbon Filtration System: The clarified water is pumped to Media Filter
followed by Carbon Filter to further polish the treated effluent. The Sand filter removes the
suspended solids and the Carbon Filter removes color & odor. treated effluent passes through
Ozonation and Ozone is a very reactive gas that can oxidise bacteria, moulds, organic material
and other pollutants found in water.
Sludge Collection Tank: We have proposed sludge collection tank to store the sludge. This
Sludge tank is provided with Sludge Transfer pumps. The sludge can be transferred to filter
Press mechanism for dewatering the sludge. The biologically treated sludge can be used as
manure
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 18
Fig 10: Proposed Tentative STP Layout Plan with MBBR Technology (180KLPD) capacity
(It may vary during construction as per the site conditions)
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 19
Fig.11.GENERAL PROCESS DIAGRAM OF STP PLANT
D. EXTERNAL SEWERAGE
There are no alterations in the natural slope and drainage pattern of the project site. Sewage lines will be laid
along the natural slope of ground with a self cleansing design velocity of 0.75mtr. /sec. Minimum 150mm dia.
RCC NP2 pipe will be provided with a slope.
E.GROUND WATER POTENTIAL/HYDROGEOLOGY
Hyderabad receives 700 mm average rainfall annually, considering GHMC area of 600 sqkm accounts to 4200
Million Cum. More than 90% of rain water goes into drains and gets carried away from city as infiltration into
ground varies between 3% to 8% only under natural conditions & this further reduces with increased urbanisation.
Natural replenishment of ground water reservoir is a slow process and is often unable to keep pace with this
incessant downpour, concrete jungles/ roads, reducing open/ public places and excessive exploitation of ground
water. The city receives abundant rains, gets flooded with every rain and many of the borewells go dry between
January to June but with improvised rain water harvesting (RWH) methods the infiltration rate can be increased to
10%. Hyderabad is situated on Deccan Plateau which is mainly underlain by rocks. Regular methods of recharge
pits are not very successful at all places because we can find sheet rock/ boulders beneath the proposed RWH pit
or sometimes due to clay soil also where the percolation is minimum or not possible. The rainwater reaching the
deep aquifers vertically is more important at present times than travelling horizontally through the weathered
zone.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 20
The effluents/sewage coming out of the complex should be monitored regularly. Ground water is recommended to
be monitored in at least two points in the direction of ground water flow to keep surveillance on the ground water
quality.
M/s Green House Plantations Pvt Ltd has proposed Storm water Drainage system, Rainwater Harvesting pit
construction etc for water conservation. Rainwater harvested from the surface and rooftop runoff is used to
recharge the sub soil.. We are proposing 14 no.of rectangular Recharge pits with sizes 1.25 m x 1.25 m 1.0 m
4.1 STORM WATER DRAINAGE AND RAIN
WATER HARVESTING
All along the road network of the proposed project, storm
water drains would be provided to collect water during
rains. They would be adequately sized to prevent
flooding of the site. It is proposed to have rainwater
harvesting structures for recharge of roof top rainwater
and rain water of paved surface at respective apartment
and villas. Treatment for silt, oil & grease removal will
be provided to rainwater harvesting recharging pit.
Overflow from the harvesting pit and storm water of
road/ open space will be collected through road side
storm water drains. For better infiltration of rainwater
into ground, storm water drains will be provided. The
storm water drains are connected to nearby natural drain.
The details of rainwater harvesting calculation is given in
Table 10. Typical Rain water harvesting pit design is
given in Figure 10
The rainwater harvesting pits will be provided adjacent
to the apartment blocks, so that the roof water can be
directly sent to nearest Rainwater harvesting pit. The
excess water if any from the rainwater harvesting pits is
diverted to storm water drains & STP plant.
Figure 12
Typical Rain Water Harvesting Pit Design
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 21
F.SOLID WASTE MANAGEMENT DURING CONSTRUCTION PHASE AND OPERATION
PHASE
5.0. Construction Phase:-
Solid waste would be generated both during the construction as well as during the operation phase will be
disposed strictly as per Solid Waste Management Rules 2016 and Construction and Demolition waste
management rules 2016. The solid waste expected to be generated during the construction phase will
comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps
are to be followed for the management solid waste:
All construction waste shall be stored within the site itself. A proper screen will be provided so that
the waste does not get scattered.
Attempts will be made to keep the waste segregated into different heaps as far as possible so that their
further gradation and reuse is facilitated.
Materials, which can be reused for purpose of construction, levelling, making roads/ pavement will
also be kept in separate heaps from those which are to be sold or land filled.
The local body or a private company may be arranged to provide appropriate number of skip
containers/ trolleys on hire.
The use of the construction material basically depends on their separation and conditions of the separated
material. A majority of these materials are durable and therefore, have a high potential for reuse. It would,
however, be desirable to have quality standards for the recycled materials. Construction waste can be used in
the following manner.
Reuse of bricks, tiles, stone slabs, timber, piping railings etc to the extent possible and depending upon
their conditions.
Sale/ auction of materials which cannot be used at the site due to design constraint
Plastics, broken glass, scrap metal, used cement bags, etc can be sent for recycling in the industries.
Rubble/ brick bats can be used for building activity, such as levelling, under coat of lanes where the
traffic does not constitute heavy moving loads.
Larger unusable pieces can be sent for filing up low laying areas.
Fine material such as sand, dust, etc can be used as cover material
The unearthed soil can be used for levelling as well as for lawn development
The broken pieces of the flooring material can be used for levelling in the building or can be disposed
off
The unused or remaining paints/varnishes/wood can either be reused or can be disposed off.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 22
5.1 Solid Waste Collection / Disposal Plan during Operation Phase:
The operations phase of the project the refuse generation rate as 0.5kg/Capita/day for residents, 0.25
Kg/Capita/day for staff in commercial shops/offices and 0.15 Kg/Capita/day for visitors have been
considered. Collection systems comprise waste containers at ground floor of the building. The solid waste
shall be disposed to the appropriate site as per municipal authority. The generated solid waste shall be first
segregated as plastic, glass, paper and other waste separately and disposed off as per MSW Rules, 2016. The
inert solid waste will be transported to a govt. designated landfill site.
Table 11. SOLID WASTE GENERATION DURING OPERATION PHASE
Solid Waste Calculation
Sl
No. Description occupancy kg/capita/day
Total solid waste
generated in kg
1 office staff in Commercial
Tower 1300 0.15 195
2 Shopping Area in podium 50 0.15 8
Total solid waste generated 203
Bio-Degradable waste
Biodegradable: 40% 80kg/day (Waste vegetables and foods etc.)
Recyclable 50% 100kg/day (Papers, cartons, thermocol, plastics, glass etc.)
Inerts 10% 23kg/day
Total: 203 kg/day
A. Estimated total quanity of Non-biodegradable waste will be 123kg/day.
B. An e-waste quantity of 0.4Ton/annum will be estimated to be generated, which will be sold to
authorized e-waste recyclers. The detailed breakup calculation has been given in EMP Plan.
Biodegradable waste Management :
Bio-degradable waste will be collected in the secondary processing area and fed to an
Organic Convertor the compost will be used as manure.
STP sludge is to be used for horticultural purposes as manure.
Horticultural Waste is to be composted and will be used for gardening purposes.
Non bio degradable - Sent to Authorized Vendors.
Recyclable waste
The segregated recyclable waste will be sold off to vendors
Inert waste
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 23
The inert waste collected at site will be sent to landfill through the municipal waste
handling system.
Fig 13. Solid Waste Management plan during operation phase
Municipality
Solid Waste
Biodegradable Non-Biodegradable Recyclable
Sold to
Local vendors Small Collection Bins
Block Collection Points
Main Collection Points
Municipal Solid Waste
Management Facility
Small Collection Bins
Block Collection Points
Main Collection Points
Organic converter
/ Vermicompost
Manure
Inerts
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 24
G. AIR QUAITY AND NOISE LEVELS IMPACTS & MITIGATION MEASURES
6.1 Air Quality Impacts
An assessment of air quality impacts associated with the construction and occupation of the proposed project
has been carried out. Worst case impacts on the representative receivers have been assessed. Three major
sources of air pollution have been identified namely construction dust emission, road traffic emissions and
DG set emissions.
1.Construction Phase: Construction works include site clearance, site formation, building works,
infrastructure provision and any other infrastructure activities. The major air pollution source during this
activity is dust generation as a result of the above activities.
2. Occupation Phase: The major sources of air pollutants are the vehicle emissions from traffic on roads
internal and neighboring roads, air pollutants emitted from operation of DG sets and other mechanical
equipments used for day to day activities proposed at these project.
The representative air sensitive receivers within the study area represent the future and existing sensitive
receivers likely to be affected by the project.
6.1.1 Construction Phase Impacts
The principal potential source of air quality impact arising during construction period is fugitive dust
generation. The dust, measurable as PM 2.5 & PM 10 would be generated as a result of construction activities.
The construction program of the project shall commence immediately after obtaining statutory clearances.
The potential dust sources associated with construction activities are loading and unloading of the materials,
top soil removal, travel over unpaved roads and wind erosion etc. The construction works associated with the
proposed development are broadly given below.
1. Site development and foundation works
2. Dust generation due to vehicles bringing raw materials
3. Un loading of raw materials, removal of unwanted waste material from site
4. Civil constructions and provision of infrastructure required for various activities proposed at each project.
Among all the construction activities, site formation has the highest potential for causing dust nuisance to the
nearby air sensitive locations. During the construction of the project, existing houses nearby may be subject to
the potential dust impacts.
6.1.2 Mitigation Measures proposed
For the proposed project, site leveling and grading will be carried out for construction apartments and club
house, where ever possible natural elevations will not be disturbed, only leveling activity will be carried out
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 25
for providing roads, sewage network, storm water system, and places required for providing buildings.
According to the engineering assessment; most of the excavated material (for providing basements) shall be
reused within the project boundary, if any excess will be disposed through local contractors for filling low
lying areas or road laying purposes, etc. The movement of cut and fill material will be limited. Broad
estimation shows that there would not be more than 20 vehicles from the construction site within a day, since
all the excavated material shall be reused at the site itself.
The control measures proposed to be taken up are given below:
Regular water sprinkling on internal roads in the project area, this activity will be carried out at
least twice a day, if need arises frequency will be increased on windy days, in this way around
50% reduction on the dust contribution from the exposed surface can be achieved.
The duration of stockpiling will be as short as possible as most of the material will be used as
backfill material for the open cut trenches for road development.
Temporary tin sheets of sufficient height (3m) will be erected around the site of dust
generation or all around the project site as barrier for dust control.
All the vehicles carrying raw materials will be covered with tarpaulin / plastic sheet, unloading
and loading activity will be stopped during windy period.
To reduce the dust movement from civil construction site to the neighborhood the external part
of the building will be covered by plastic sheets
Vehicles having pollution under control certificate will be allowed.
Drivers of the Vehicles will be instructed to follow speed limits (<20 kmph), reducing the
speed of the vehicle will reduce generation of dust to large extent.
Speed limit boards will be displayed at entrance gate, speed breakers will be provided if
needed.
Given the implementation of proper control measures for dust suppression, no adverse impacts are expected
and compliance with the Ambient Air Quality is achieved at at all time.
6.1.3 Occupation Phase Impacts
As the proposed project is a construction project there are no major point source emissions like industries. The
major air pollutants associated with this project is from incoming and outgoing vehicles. In addition to this the
other source is use of DG set during power failure as back up source for lighting and other emergency needs.
The use of DG set will be as minimum as possible as it is used during power failure as a backup. The Details
of the DG set stack height calculation, stack provided, pollutants expected along with Mitigation measures
have been given in Table no 4.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 26
6.2 Noise Level Impacts
Sound pressure level generated by noise source decreases with increasing distance from the source due to the
wave divergence. An additional decrease in sound pressure level with distance from the source is due to
atmospheric effect or interaction with the objects in the transmission path. It is also affected by the
environmental conditions.
The noise generation during construction phase and occupation phase will be different. The construction
phase will be temporary in nature where during occupation phase it will be continuous.
6.2.1 Impact during Construction
The major activities which produce periodic noise, during construction phase are as follows:
Foundation laying
Fabrication of structures
Operation of construction equipment
Movement of vehicles
6.2.2 Mitigation Measures
All noise generating equipment will be used during day time for brief period of its requirement. Proper
enclosures will be used for reduction in noise levels, where ever possible the noise generating equipment will
be kept away from the human habituation. Therefore, impact on noise environment due to proposed project
would be insignificant.
All vehicles entering into the project will be informed to maintain speed limits, and not blow horns unless it is
required.
6.2.3 Noise Impacts during Occupation phase
The major noise expected at the site is due to traffic movement and operation of DG set during power failure.
6.2.4 Mitigation Measures
To minimize the noise due to vehicular movement all the vehicles will be advised to get serviced regularly so
that the noise due to movement of vehicles will be minimum, they will also be advised not to blow horns
unless it is required. All noise generating machines like pumps, compressors, etc will be properly serviced and
mounted on anti-vibration pads to reduce the noise generation. The DG set will be provided by Acoustic
enclosure.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 27
In addition to this, the entire open areas along the boundary, along the main road and internal roads shall be
provided with adequate green belt to diffuse the noise dispersion.
Trees with heavy foliage will be planted along the project boundary to absorb the noise, shrubs and creepers
will be planted for additional protection between tree trunks.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 28
H. ENERGY & POWER REQUIREMENT, ELECTRICAL, BUILDING & FIRE
SAFETY ,DG SETS DETAILS :
7.1 GENERAL:
The Proposed Commercial building of M/s. Green House Plantations Pvt. Ltd mainly consists of following
major areas:-
Associated amenities are being provided with building.
7.2 DESIGN STANDARDS & CODES:
Electrical system design shall be in confirmation to the requirement of:
Indian Electricity Rule 1956.
Standards & Code Practice of Bureau of Indian Standard for various equipments & Systems.
National Building Code of India -2005 (Part -8)
National Electricity Code of India
7.3 DESIGN CRITERIA FOR ENERGY EFFICIENCY: Table 12: DESIGN CRITERIA FOR ENERGY EFFICIENCY
Design
Criteria
Proposal to Achieve Same
Energy
Efficiency
Use of energy efficient light fittings, ballast and transformers. T5 fixtures Solar and
LED fixtures shall be considered for Common Area.
Provisions of alternate circuits to serve common area light fittings to allow energy
saving in off-peak operation.
Safety of the
occupants and
end users
Strict compliance with Indian Electricity Rules & other safety code requirements.
All lighting and power circuits shall be protected by the circuit breakers and ELCBs.
Surge Arrestor shall be provided at the Main Panel and other SDBs/FDBs which has
external in/out cable connections.
Building shall be protected by the Lightening Protection System.
Reliability of the
Installation
Double Feeder with multiple Transformers from mall transformers thru separate mall
main panels.
Emergency generators to support 100% equipment / services in case of non-
availability of grid supply from mall common generators.
Flexibility and
Adaptability
Use of appropriate Cables to meet constant changes and needs in hotel businesses/
Utilities.
Planning shall be in such a way that distribution system will not have major change
in case of change in usage of area.
Expandability Sufficient spare capacity (about 20-25%) in the design of switchboard and
distribution network to meet future load growth.
Maintainability Space planning shall be done with consideration of regular service, maintenance;
and future replacement.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 29
Following design parameters are considered while estimating the electrical loads:-
S.NO. DESCRIPTION LIGHT CONVENIENC
E POWER UPS/EQUIPMENT
1 Stair case 0.4 Watt/Sqft. - -
2
Common Area
Toilets, Elec. Room, AHU Room,
Corridors, Lift Lobby
1.0 Watt/Sqft. 0.7 Watt/Sqft. -
3 Hall 2.0 Watt/Sqft. 0.7 Watt/Sqft.
4 Bed room 0.5 Watt/Sqft. 0.5 Watt/Sqft.
5 Kitchen 1.0 Watt/Sqft. 4.0 Watt/Sqft.
6 Bank 3.0 Watt/Sqft. 5.0 Watt/Sqft. 5.0 Watt/Sqft.
7 Drg. hall 2.0 Watt/Sqft. 0.7 Watt/Sqft.
8 Dining hall 2.0 Watt/Sqft. 0.7 Watt/Sqft.
9 Living/Dining Area 0.5 Watt/Sqft. 5.0 Watt/Sqft.
10 Parking 0.2 Watt/Sqft. 0.2 Watt/Sqft. -
11 Office /Reception /Manager Room 2.5 Watt/Sqft. 5.0 Watt/Sqft. 5.0 Watt/Sqft.
12 Entrance /Attrium 3.0 Watt/Sqft. 4.0 Watt/Sqft. 2.0 Watt/Sqft.
13. Electrical Room 1.0 Watt/Sqft. 1.0 Watt/Sqft. 1.0 Watt/Sqft.
7.4 ELECTRICAL LOAD ESTIMATES:
Based on the above parameters and design brief for Mechanical & Electrical services, the load requirement of
whole Building project works estimated out as below Table no 13.POWER REQUIREMENT
Power Requirement In Kilo wats
Total Requirement(KW) for Commercial Tower and
podium blocks 345KW
Site services, Lift and other amenities 55KW
Total Power Requirement 400KW
Total Requirement KVA 500KVA
7.5 Source of Power:-
Overall maximum demand estimated for Commercial building project is approximately was 400KW or
500KVA. The source of Electricity will be Telangana State Electricity Board. The billing from TSEB shall be
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 30
on single point basis and submitting charges shall be collected from individual resident (by sub meter) spaces
by building management team.
7.6 BACKUP POWER SUPPLY:-
DG Sets of 2 x 125 KVA capacity for Commercial Building are proposing for power backup. DG Sets shall
have heat exchanger and silent type with canopy water cooled with AMF panel planned.
DG Plant Room shall be acoustically treated to arrest the noise pollution as per CPCB Norm.
Exhaust piping for the DG Sets shall be taken up to the highest point of 52meters as per CPCB guidelines.
Power is reliable in Raidurg village, Serilingampally area where site is located therefore continuous operation of
DG Sets may not arrive.
7.7 LIGHTING & POWER REQUIREMENT:
All common areas lightning will be by using the LED source.
PVC insulated copper conductor cable will be used for wiring purpose.
Solar Landscape lighting in open sunlit areas and Solar Water Heating is proposed as per
MNRE guidelines.
Roof insulation is planned to conserve energy.
Capacitor banks shall be planned for improving the power factor of the power supply.
7.7.1 EARTHING SYSTEM:
Safety in using electrical energy is of paramount importance considering its dangers. The earthing system will
be in conformity with the IS: 3043. All non-current carrying metal parts forming part of the electrical system
shall be connected to the grounding system. The requirement of Indian Electricity Rules and statutory
requirement of local Electricity authority shall also be met fully.
a. The Earthing System is divided into Two Sections:
i. Substation earthing
(Copper)
a. Transformer neutral earthing solidly earthed
b. DG sets neutral earthing solidly earthed
c. Bank buildings, server/ATM solidly earth
d. VCB solidly earth.
ii. Protective earthing
(GI)
a. LT panel body earthing.
b. Trans & DG set body earthing
c. Emergency Panel
d. Equipment's(DB’s)
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 31
7.7.2. FIRE ALARM SYSTEM:
An Independent Analogue Addressable Fire Alarm System for the Commercial Floors in 6th
and 10th
with
refuge area is proposed to be installed. The main fire alarm panel shall be installed in the Fire command
center cum security control room and repeater panels shall be installed at the appropriate locations viz.
Security Room at the Main Gate.
The addressable smoke and heat detectors are proposed to be installed in all areas. All detectors installed in
air conditioned areas will be linked to the specific AHU or FCU for alarm and controls. The hooters shall be
strobe cum hooters wherever the noise level is high. The whole system design shall be in accordance with
NFPA. The detectors shall be provided as per relevant national and international standards. The fire alarm
system will comply with the requirement of MDS14.
7.8 Street lighting:-
Proper illumination is necessary for safety, systematic movement of vehicles and
pedestrian. The roads will be lighted using energy efficient Solar or LED street lighting.
It is proposed to meet the desired illumination by mounting the luminaries on poles with
appropriate mounting height. The pathways shall be illuminated using bollards and post top
lantern. The power to street lights is proposed through cable laid directly buried in ground &
outdoor control-pillars. Control Pillars shall have lighting contactor with integral
Astronomic 24hrs Programmable Timer and auto manual switch for automatic ON & OFF
operation, thus reducing the energy consumption. Control Pillars shall have lighting
contactor with integral Astronomic 24hrs Programmable Timer and auto manual switch for
automatic ON & OFF operation, thus reducing the energy consumption.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 32
I. TRAFFIC CIRCULATION SYSTEM AND CONNECTIVITY (PARKING REQUIREMENTS AND
PROVISIONS)
Adequate parking provision is allocated for vehicles parking at the campus. Total Parking area as per
GO.168 of Municipal Administration and Urban Development Department, Govt. of Telangana and
NBC code, Proposed parking for the Commercial building project is 66% of the Built-up area. i.e
11,630.79sq.m
Table 14. Proposed Parking
Parking Calculation
Type Area(sq.m) No.of ECS Car 2-Wheelers
Basement 1(Regular) 3494.49 100 80 60
Basement 1(mechanical) 1056 30 24 18
Basement 2 3494.49 100 80 60
Basement 3 3586 103 83 62
11630.79 sq.mt 333 267 200
Total ECS we are providing is 333ECS which Occupies 267 Cars and 200 Two-wheelers which is Adequate.
5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian
pathways, footpaths etc., with areas under each category.
Circulation
The access to the site is predominantly from North 65meter wide Road of Old Mumbai Highway from
Tolichowki towards Gachibowli. There is a proposed 23meter wide drive way provided.
a) For Podium (G+1st Floor), All around Set back areas shall be 7m wide.
b) For Commercial Tower block , the coverage and all around setbacks shall be minimum 50% of
the podium block and shall be atleast 3m from the podium edge on all the sides.
c) The fire safety and fire escape measures for the tower block shall be independent of the
podium block.
The Entry and Exit gates has 7m width left and Internal drives of 4.5m are provided. 3 Basement
parkings are provided for the building. Parking plan is strictly adhered as per the norms of NBC and
Municipal Administration standards. Fire refugees are present in 6th
and 10th
Floors as per the norms.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 33
Fig 14: Basement Parking-1 Fig 15 : Basement Parking-2
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 34
Fig 16 : Basement Parking-3
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 35
J. GREEN BELT /GREEN COVER AND THE LANDSCAPE PLAN
Green belt development is one of the most effective environmental pollution control measure. Trees play vital
role in the environment in preventing the horizontal dispersion of the pollutants to the surrounding areas.
They are very effective in trapping the pollution causing agents viz. dust and gaseous pollutants. They are also
considered to be excellent indicators of excessive ground level concentrations. The greenbelt is being
proposed for the following objectives.
Mitigation of fugitive dust emissions
Noise pollution control
Prevention of soil erosion
Balancing eco environment
Aesthetics
The green belt will be covered along the site boundary and along the roads. Apart from the bulk plantation in
vacant areas, Roadside avenue plantations will also be taken up. The placement of the plants would be
designed as follows:
Trees growing up to 10 m or more in height with thick canopy cover and perennial foliage would be
planted along the boundary.
Planting of trees would be done in rows with minimum three rows encircling perimeter of the project.
While planting the trees care would be taken that the buildings would be difficult to see through foliage
when seen from a point outside the green envelope. For preventing the horizontal dispersion of pollutants,
if any, the trees planted in alternate rows would fall in straight line.
Trees would be planted on roadside for containment of vehicular traffic emissions and fugitive emissions
due to the movement of vehicles.
Tree trunk being free foliage up to a height of 2 to 3 m, it is proposed to grow shrubs in front of trees so as
to give coverage to the open portion.
Sensitive species like Mangifera indica would be planted in patches along the entire green belt to work as
an indicator of pollution potential.
Landscape Plan
Total Green belt area proposed for the project = 478.81sq.mt which is 10.1% of the Net plot area.
Apart from this, there is a beautiful Tot-lots will be developed in the podium spaces.
Curtain Plantation: A green belt along the outer periphery of the premises and around yards;
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 36
Lung Plantation: At the free and empty places around the Office blocks, Stores, Shops, Raw material
Storage area etc.
Ornamental Plantation: Flowering trees and shrubs around the Office block, road dividers and lawns
to improve the landscape of the area.
FIG 17: LANDSCAPE PLAN
Green belt All along the border Lung plantation in commercial offices
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 37
Table 15: List of plants identified for greenbelt and plantations
A) Tree Species planted all along the road side/boundary wall of the project site
Tree
Common name
Scientific name Important Features
Shirish Albizia lebbeck Shady tree, yellowish green fragrant flowers
Neem Azadiracta indica Large tree, good for roadside plantation
Peepal Ficus religiosa Large tree, good for roadside plantation
Maharukh Ailanthus excelsa Large tree, good for roadside plantation
Nandruk Ficus retusa Shady tree, good for roadside plantation
Karanj Pongamia pinnata Shady tree.
Ashoka tree Saraca asoka Tall, Shady tree with red-yellow flowers.
Katesavar Bombax ceiba Large tree, red flowers.
Kadamb Anthocephallus cadamba Shady, large tree, ball shaped flowers.
B)List of Native Trees suitable for beautification in middle of project site:
Tree
Common name
Scientific name Important Features
Bahava, Cassia fistula Medium sized deciduous tree.
Beautiful yellow flowers, Butterfly host plant
Bakul Mimusops elengi Shady tree, small white fragrant flowers
Parijatak Nyctanthes arbor-tristis Small deciduous fast growing tree, beautiful
flowrers.
Tamhan Lagerstroemia flos-
regineae
State flower tree of Maharashtra
Medium sized tree, beautiful purple flowers
Kunti Murraya paniculata Small tree, Fragrant white flowers,
Butterfly host plant
Shivan Gmelina arborea Fast growing tree with beautiful yellow flowers
Lemon Citrus sp Butterfly host plant
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 38
K. DISASTER/ RISK ASSESSMENT AND MANAGEMENT PLAN
The Proposed Building blocks have a maximum height of 49.7meters which comes under the purview of Fire
safety clearance. Fire NOC is under Process. We are providing adequate Fire safety precautions to mitigate
the fire accidents as per NBC code and Bye-Laws of Telangana State Govt.
All the Commercial blocks including podium area are proposed to provide with Sufficient & Effectively
Smoke Exhaust System, Good Ventilation System on each floor throughout the entire Building, which can be
evacuate the Fire Smoke out from the entire building at the time of Fire incidence.
L. SOCIO-ECONOMICS/ DEMOGRAPHY IMPACTS OF THE PROJECTS
Raidurg Nawkhalsa used be one of the commercial zone of Hyderabad which is being urbanized fast. This
area is located near the hubs of Information Technology (IT) such as Hi-tec City and Gachibowli. Many of the
IT majors such as Infosys, Wipro and Microsoft have set up base here, making Raidurg area the choice
destination for IT professionals. One of the advantages of being close to prestigious institutions and IT hubs is
that the return on investment would appreciate. There would be a greater demand for rentals in this locality as
more people from other states would want to rent places closer to their place of work rather than commute.
Investment in this region has multifold effects on the overall economy of the region. Development of the well-
planned Construction project makes a powerful contribution to the formation and strengthening of linkages
with other sectors of the economy and, in the process, stimulates the creation and expansion of micro
enterprises at the local level, and helps to generate adequate socio-economic benefits to the local people and
also supplementary cash income opportunities for the women & other disadvantaged groups.
Any measure of such economic impact can be an indicator of improvement in the overall economic well-
being of the study area, which is one of the major goals of developmental efforts and deployment of resources
in the construction project.
The project will lead to multi-facet benefits for the society and some of the benefits are as given below:-
Economic gain (Increase in taxes to government)
Employment generation;
Infrastructural developmental works, such as improved access to potable water, communications, roads
(access to markets), and improved health and education services;
Increased personal income and wealth creation
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 39
(i) Economic gain
The proposed project brings not only the local people, but also the people from the other regions thereby
generate direct & indirect economic gains to the people. The proposed Commercial offices will be paying
taxes and service charges for the services extended by local municipal authorities.
(ii) Employment generation
The development of the project is also going to generate pro-poor employment (direct as well as indirect)
because; it is a highly labor-intensive industry housemaids, drivers, helpers. Indirectly children will join
nearby schools; residents will shopping in nearby shops, some of them may hire other services like laundry,
cleaning, etc.
(iii) Infrastructure creation
In addition to employment and business opportunities, construction projects often brings with it improved
infrastructure, security, communications, community development.
Health and education services for the poor can also be improved since government revenues generated from
such project activities may subsequently be invested in these services.
(iv) Increased personal income and wealth creation
Due to development of this high class quality Commercial Building project activities, the property values in
the region would also be a reflection of economic impact of the project. As discussed earlier, the project
would create new employment and business opportunities. Also the spin-off effects of the projects in the
neighborhood area would also increase the business volumes of existing businesses. These new opportunities
would result in increased personal income and better standards of living. With the increase in personal income
and new opportunities, the property values in the nearby areas would increase, thus resulting in wealth
creation for the nearby community. It is also important to note that when property values go up, the buying
class is generally the richer class of the society or business entities. This phenomenon, though difficult to
quantify at this stage, would redistribute wealth within the society and create opportunities for the people
owning property in the nearby region.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 40
M.ENVIRONMENT MANAGEMENT PLAN
9.0 PROJECT MONITORING
Pollution monitoring program includes periodic analysis of air, ground water, soil and wastewater samples.
Ground water and soil samples at representative locations within and nearby the project site will be
periodically analyzed to detect contamination if any.
In the event of any contamination, concerned authorities will be intimated immediately and appropriate
corrective action in consultation with an approved technical agency will be initiated.
9.1 MONITORING STRATEGY
The monitoring of various environmental parameters is necessary and is a part and parcel of the environmental
protection measures. Monitoring is as important as that of control of pollution since the efficiency of control
measures can only be determined by monitoring.
A well-defined environmental monitoring program would be employed to monitor the environmental attributes
to check whether they maintained within the permissible limits.
The following Environmental attributes would be monitored:
Air pollution and meteorological aspects
Water and waste water quality
Noise levels
Soil characteristics
Ecological preservation and up gradation
Maintenance of water conservation methods
Maintenance & operation of STP
Locations and frequency of monitoring would be as per the guidelines of TSPCB/CPCB and MOEF.
9.2 Ambient Air Monitoring
As per MOEF&CC there is a need to identify 2 ambient air stations at 120o angle keeping the main source in
the center. The ground level concentrations of suspended particulate, sulphur dioxide and nitrogen oxides in
the ambient air outside the project boundaries and in the adjoining areas will be monitored at regular intervals.
Any deviation from predicted/expected values will be investigated and necessary action will be taken.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 41
9.3 Noise Monitoring
Noise levels in the complex will be monitored periodically. If any deviation is observed necessary corrective
measures will be taken.
Monitoring noise levels is essential to assess the efficacy of maintenance of schedules undertaken to reduce
noise levels and noise protection measures. A good quality sound pressure level meter is essential for this
purpose. Noise surveillance is for the benefit of the well being of residents and to keep track of sources.
9.4 Water Quality Monitoring
Ground water near the project site will be routinely tested for its quality. No contamination of ground water
and surface water is expected. However the water will be periodically tested for any change of water quality.
The sewage coming out of the Commercial building should be monitored regularly. Ground water is
recommended to be monitored in at least two points in the direction of ground water flow to keep surveillance
on the ground water quality.
9.5 Sewage Treatment Plant
The operations of STP are monitored to ensure the quality of treated water and discharge of waste water into
municipal sewage system. The de-silting of sludge on regular basis needs to be ensured.
9.6 BUDGET FOR EMP:
The details of activities and expenses to be incurred on EMP are presented below.
Table no.16. EMP Budget
S.No. Component Amount
Rs Lakhs
1 STP & Rainwater Harvesting 60
2 Green Belt Development and landscaping 20
3 Organic waste converter 30
4 Solar and LED lightening 20
5 2no.s of DG sets for power backup 10
6 Environment Monitoring, Maintenance 10
Total 150 lakhs or 1.5 crores as
Capital Expenditure
Recurring Expenditure 30 lakhs
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 42
The recurring expenditure includes maintenance of green area & landscape, monitoring of environmental
attributes and maintenance & operation of STP and rain harvesting system.
The budget for the components of EMP will be a part of project cost while the recurring expenditure will be
met from the maintenance charges collected from individual Offices in commercial floors on monthly basis.
Implementation
The Environmental Management will be implemented by the project promoters through a responsible in
charge person, appointed exclusively for the purpose, with the help of assistants.
9.7 Manpower requirement
The maximum peak man power required for the development of proposed project during construction and
occupation stages are given in below table. Skilled occupations include carpenters, electricians, plumbers,
ironworkers, masons, and many other manual crafts, as well as those involved in project management.
Table 17
Manpower Requirement
S.No Phase Number Remarks
1 Construction Phase 100 Skilled, unskilled, supervisors, etc
2 Operation Phase 50 Security guards, Shopping staff in the Podium
block, Maintenance staff in Commercial Offices,
STP operators, gardeners, housemaids,
electrician, plumbers, Cab drivers etc
9.8 ENVIRONMENT MANAGEMENT PLAN
Environmental Management Plan (EMP) is the key to ensure a safe and clean environment. The desired results
from the environmental mitigation measures proposed in the project may not be obtained without a
management plan to assure its proper implementation & function. The EMP envisages the plans for the proper
implementation of mitigation measures to reduce the adverse impacts arising out of the project activities. EMP
has been prepared addressing the issues like:
• Pollution control/mitigation measures for abatement of the undesirable impacts caused during the
construction and operation stage
• Institutional set up identified/recommended for implementation of the EMP
• Post project environmental monitoring programme to be undertaken
• Expenditures for environmental protection measures and budget for EMP
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 43
Proposed Environmental Mitigation Measures
These measures together constitute part of Environmental Management Plan (EMP). The environmental
mitigation measures for construction and operation phases has been given in Table – 18.
Table – 18 : Proposed Environmental Mitigation Measures
Area Mitigation Measures
Construction Stage:
Water quality • Toilet and drinking water facilities for construction workers will be provided by the
contractor at the construction site to avoid unhygienic condition at site.
Air quality • Dust suppression measures will be undertaken such as regular sprinkling of water
around vulnerable areas of the construction site by suitable methods to control
fugitive dust during earthwork and construction material handling/ over hauling.
• Properly tuned construction machinery & vehicles in good working condition with
low noise & emission will be used and engines will be turned off when not in use.
Noise level • Protective gears of such as ear mufflers etc. will be provided to construction
personnel exposed to high noise levels.
Solid wastes • Waste construction materials will be recycled and excess construction debris will
be disposed at designated places in tune with the local norms.
Landscape • Appropriate landscape including plantation of evergreen and ornamental flowering
trees, palms, shrubs and ground covers at open spaces within the complex will be
done, which would serve the dual purpose of controlling fugitive dust and
improving the aesthetics of the area.
Safety • Adequate safety measures complying with the occupational safety manuals will be
adopted to prevent accidents/hazards to the construction workers.
Operation Stage:
Water quality • Sewage will be treated up to the tertiary level in the proposed STP.
• Entire treated sewage will be reused for toilet flushing and horticulture.
• Regular monitoring of STP effluent quality will be carried out as per norms.
Air quality • Back up DG sets will comply the applicable emission norms.
• Adequate stack height for DG sets will be provided as per norms.
• Back up DG sets will be used only during power failure.
• Regular monitoring of emissions from DG sets and ambient air quality will be
carried out as per norms.
Noise level • DG sets will be installed in the basement to minimize the vibration and impact on
ambient noise.
• DG room will be treated acoustically as per norms to control the noise from DG
sets.
• Pumps, STP, Compressors, DG sets etc. will be properly maintained for fuel
efficiency and noise control.
• Personal protective equipment will be provided to the maintenance staff working in
high noise areas.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 44
Solid wastes • Solid wastes will be segregated into organic and inorganic components.
• The recyclable inorganic wastes will be sold to prospective buyers.
• The bio-degradable wastes will be collected in the secondary processing area and
fed to an Organic Convertor the compost will be used as manure.
• Dewatered / dried sludge from STP will be used as manure in horticulture.
Hazardous waste • Used / spent oil from DG sets will be sold to registered recyclers.
Rainwater
harvesting
• Adequate rainwater harvesting will be provided by means of recharge into the
groundwater.
Fire protection • Adequate fire protection facilities will be installed including fire detectors, fire
alarm and fire fighting system as per National Building Code of India.
Landscape • Proper maintenance of landscape round the year including replacement of the
decayed plants.
Safety • Adequate safety measures complying to the occupational safety manuals to prevent
accidents/hazards to the maintenance workers.
Others • The building will be provided with disabled-friendly design, timber-free
construction, energy efficient lighting & ventilation, and control of indoor
environment.
• Undertaking all necessary pollution control measures to maintain the emissions and
discharges within the prescribed/stipulated limits.
It is imperative that the Project Authority set up regular monitoring stations to assess the quality of the
surrounding environment during construction and after the commissioning of the project. An environmental
monitoring programme is important as it provides useful information and helps to:
• Verify the predictions on environmental impacts presented in this study,
• Assist in detecting the development of any unwanted environmental situation, and thus, provides
opportunities for adopting appropriate control measures, and
• Evaluate the performance and effectiveness of mitigation measures proposed in the EMP and suggest
improvements in management plan, if required,
• Satisfy the legal and statutory obligations.
The post project monitoring plan including areas, number and location of monitoring stations, frequency of
sampling and parameters to be covered is summarized in Table -19. The monitoring will be the responsibility
of EMC.
The post operational monitoring Programme will be under the supervision of the Site Engineer at the project
site. Monitoring will be get carried out by recognized laboratories.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 45
Table -19: Environmental Monitoring Plan – Operation Phase
ource Monitoring Location Parameters to be
Monitored Frequency
Ambient Air
Quality
At 2 locations (one inside
the project site and one at
boundary of the project site
along predominant wind
direction)
PM10, PM2.5, SO2,
NOx and CO
Twice a year or as per
conditions of EC or as per
requirement of
CPCB/SPCB
Sewage Treatment
Plant
Inlet and Outlet of STP pH, BOD, Suspended
Solid, Oil & Grease
Twice a year or as per
conditions of EC or as per
requirement of
CPCB/SPCB
Ambient Noise At 2 locations (one inside
the project site and one at
boundary of the project site
nearest to building area)
Day and night
equivalent noise level
Twice a year or as per
conditions of EC or as per
requirement of
CPCB/SPCB
9.9 Environment Management Cell
The composition of the Environment Management Cell and responsibilities of its various members are given
in Table – 20.
Table -20 : Environment Management Cell
S. No Person Proposed Responsibility
1. Project Level
(Construction
phase):
Site In-charge
• Environmental management & pollution control during
construction stage
• Installation of pollution control facilities and implementation of
the conditions of Environmental Clearance and Consent to
Establish
• Environmental monitoring during construction stage
• Secondary responsibility for ensuring legal compliance during
construction stage
2. Project Level
(Operation):
Maintenance
Manager
• Environmental management and operation & maintenance of
pollution control facilities during operation stage
• Environmental monitoring during operation stage
• Secondary responsibility for environment management and
decision making for all environmental issues
• Secondary responsibility for ensuring legal compliance and
interaction with regulatory agencies during operation stage
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 46
N.PROJECT BENEFITS
a.Introduction
Raidurg village of Serilingampally is a major IT suburb of Hyderabad which is near to Gachibowli and
Hi-tech city. Many of the IT majors such as Infosys, Wipro and Microsoft have set up base here,
making Tellapur the choice destination for IT professionals.
Hyderabad’s brand image of being ranked fifth dynamic city in the world too has propelled the sector
resultantly offering more options both in terms of residential and commercial structures. The
proposed Commercial Building project consists of Shopping areas in the podium and Commercial
office spaces in 12 floors, due to this project some of the benefits expected area as follows.
Improvements of Physical Infrastructure
Improvements in Social Infrastructure
Direct and indirect employment to locals
b. Improvements of Physical infrastructure
Due to the proposed project the revenue of the local municipal will increase because of permissions
and municipal taxes, sales taxes, etc. Small scale units of nearby areas will get boost and sales will
improve because of increased demand for their products.
c. Improvements in Socio Infrastructure
Due to the proposed project the social infrastructure of the project area and its surroundings will
improve. The following changes in socio-economic status are expected to take place with this project.
a. Development of infrastructure with all the amenities
b. Developing green belt
c. Providing STP and dual plumbing for effective water recycling.
d. Employment Potential
The main advantage of the construction sector is direct employment generation
1. Absorbs rural labour and unskilled workers (in addition to semi-skilled and some skilled)
during construction phase.
2. Permits large-scale participation of women workers both during construction and operation
phase. The maximum benefit will be for local labor as they are easily accessible.
Additionally it is estimated that good number of jobs will be created as an indirect employment
opportunities at local/ regional level due to contractual, marketing and associated jobs directly with the
project. The other related employment due to transportation requirement, supply of essential items and
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 47
services to the project site and other community services will be plenty. The project provides direct
employment to Security guards, blue color workers in the Podium block, Maintenance staff in
Commercial Offices, STP operators, gardeners, housemaids, electrician, plumbers, Cab drivers etc
The construction sector has major linkages with the building material industry since construction
material accounts for sizeable share of the construction costs of the project. These include cement,
steel, bricks/ tiles, sand, aggregates, fixtures, fittings, paints, construction equipment, petro-products,
timer, mineral products, aluminium, glass and plastics.
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 48
ANNEXURES
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 49
Annexure-1
Highrise Clerance from Airport Authority of India, Begumpet
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 50
Project: Proposed Commercial Building Activity of M/s. Green House Plantations Pvt. Ltd
Project Location: Sy. No. 45, 46, 47 & 53, Raidurg Nawkhalsa (V), Serilingampally(M), Ranga Reddy (Dst), Telangana.
ENVIRONMENT MANAGEMENT PLAN Page 51
ANNEXURE-2
LAND DOCUMENTS
. .,
,. 1
�.
I'
'I��·�-�-c.---
_:::,-:::.. '• ..
. . •, ?·".<.'-: '.-· ....;·
.. ·
. . . ;,�-.�� n--.c-h-,o--5) '�"G
I . ��1 °}<. _ f"') --5\�� . � ti
( .. • "b.'lr°h0'\6�Zl. J, �G:)
. . "'f''P� � 1'..,.·'
.:.,IS'Oi-<:,� �"Q�,c,�,rtf '?;o,-�-4£.
·��� 'Qo.� ·O/s ·4�'4�� ,t,..•G
.. -��� C-"'.. ·.
,•'j c/. -. • ·o,�l)'!�C,. . � . .. ... .
'• t ••
,., �