+ All Categories
Home > Documents > Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis...

Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis...

Date post: 15-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
20
1 Boskalis International bv 1 Boskalis International bv Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof CEDA Seminar, Tallinn (Estonia) 2 Boskalis International bv Observations from the dredging industry Each project creates an impact to the environment The impact of the project is beyond control of the dredging industry The impact of the execution of the works is to be minimised by the dredging contractor Dredging industry performs a long year, systematic research into this subject
Transcript
Page 1: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

1Boskalis International bv

1Boskalis International bv

Environmental Aspects of Dredging Works in Practice

Stefan AarninkhofCEDA Seminar, Tallinn (Estonia)

2Boskalis International bv

Observations from the dredging industry

• Each project creates an impact to the environment

• The impact of the project is beyond control of the dredging industry

• The impact of the execution of the works is to be minimised by the dredging contractor

• Dredging industry performs a long year, systematic research into this subject

Page 2: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

2Boskalis International bv

3Boskalis International bv

For every new project, questions:

• How standards have been set ?• How standards shall be adhered to ?• How compliance to standards can be

monitored ?• What is cost/benefit ratio for ecology and for

economy ?

Discussed along project experiences

Environmental project regulations

4Boskalis International bv

Øresund Fixed Link Project (1996)

• Peninsula for tunnel approach in Denmark

• Submerged tunnel, 3510 mtr. length

• Artificial Island, 4055 mtr. length• Bridges, total length 7845 mtr.

Page 3: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

3Boskalis International bv

5Boskalis International bv

Øresund Fixed Link ProjectEffects of Dredging

• Impact on sea grass and mussel beds in the direct vicinity of the project area by sediment from the dredging.

• Effect of changing water and salt flow through the Sound and into and out of the Baltic Sea on fish species such as cod and other biological systems.

5% Spill Limit (overall)

“No effects”

Compensationdredging

No previous practical experience so lack of certainty on effects

6Boskalis International bv

Øresund Fixed Link ProjectEnvironmental standards

• Precious environment - high demand for control -high level of care - willing to pay for it

• Standards based on bio-assay - translated into physical parameters by Client

• Contractor responsible for compliance and monitoring

Page 4: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

4Boskalis International bv

7Boskalis International bv

Øresund Fixed Link ProjectMonitoring Strategy

8Boskalis International bv

Øresund Fixed Link ProjectSummary

• Contractor was able to meet standards - against loss of production - with very high effort in monitoring

• Client confirmed criteria were met - follow-up evaluation did not show any impact

• Question: could the same have been achieved with less strict control?

Page 5: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

5Boskalis International bv

9Boskalis International bv

Øresund Fixed Link ProjectConsiderations

• Successful in environmental and economical respect

but• not to be used as standard for the future

as• each project different in all aspects

so• do not copy / paste environmental requirements

10Boskalis International bv

Ruwais Port Extension (UAE, 2000)

• Dredging of 1.5 km approach channel, turning basin and berth pocket

• Environmental concern: coral reef at ??? m

• Strict environmental requirements - very similar to Øresund

• Turbidity around dredger and effluent from disposal area

Page 6: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

6Boskalis International bv

11Boskalis International bv

Ruwais Port ExtensionSummary

• Construction and use of large retention basin

• Extensive monitoring -limits never reached

• Silt curtain supplied -never used

• So: All requirements were met

• Question: was this level of control really necessary ?

12Boskalis International bv

Mejillones (Chile, 2002)

• Dredging for 3 terminals & turning basin

• Bay of Meijllones important for local fishery environmentally sensitive area

• Environmental standards adopted from projects in Middle-East

• Restrictions on size of sediment plumes at dredging and disposal sites

Page 7: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

7Boskalis International bv

13Boskalis International bv

Mejillones (Chile, 2002)

• First set-up:– limits set realistic, protecting

aquaculture– monitoring extensive but no

enforcement– negotiations for lowest price

• Second set-up:– confusion about scope /

responsibilities– monitoring requirements

exceed compliance level

• Monitoring should be integral part of project planning to avoid unforeseen delays / costs

14Boskalis International bv

Mejillones (Chile, 2002)Summary

• Environmental standards adopted from earlier projects

• Monitoring at fixed locations and around dredging / disposal

– up to 100 m depth– up to 11 km distance

• Measurements values only fraction of threshold

• Relevance of measure-ments can be questioned

• No flexibility to review monitoring procedures

Page 8: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

8Boskalis International bv

15Boskalis International bv

Mejillones (Chile, 2002)Contractor responsibility?

“Dredging should not disturb sea lions”

16Boskalis International bv

Safer Fairways to Port of Gothenburg (Sweden, 2003)

• Dredging for channel widening and deepe-ning to ensure safety

• Sensitive habitats (eelgrass, mussels) and recreational demands

• Well engineered realistic monitoring & control requirements

• Absolute values for summer & winter

Page 9: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

9Boskalis International bv

17Boskalis International bv

• Turbidity measured along lines parrallel to channel• Daily reporting of results

Gothenburg (2003)Environmental monitoring

Suspended Substance Concentration

VibrationsNoise

Transparency

Current

18Boskalis International bv

Gothenburg (2003)Summary

• Contractor responsible for reliability of monitoring

• Limited overflow adopted• Good working relationship

between Client and Contractor from start to end

• Outcome of monitoring– confirmed minimal impacts – enabled reduction of

monitoring effort (24/7 12/7)– gave input for public hearings

• Stakeholder involvement & communication crucial for project success

Page 10: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

10Boskalis International bv

19Boskalis International bv

Channel Deepening ProjectMelbourne (Australia, 2005)

• Dredging for channel deepening

• Alliance contract between Port of Melbourne Corporation and Boskalis

• Major concerns on environmental impact

• Trial dredging (2005), project cont. in 2008

• Variety of monitoring, focus here on turbidity

20Boskalis International bv

Turbidity approach

1. Impact pathway – plume to consequence2. Distribution & condition of plants3. Plume extent, concentration & duration4. Light climate–naturally & during dredging5. Biological response of plant to reduced light

6. Estimate impact7. Assess against project acceptability criteria8. Mitigation & management options9. Monitoring

Literature, field investigations, modelling

Risk assessment & management process

Page 11: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

11Boskalis International bv

21Boskalis International bv

1. Impact Pathway

22Boskalis International bv

2. Distribution and condition of marine plants

3. Plume extent, concentration & duration

• Plume

• Plants in plume

• Concentration

• Duration

• Light Reduction

80th Percentile TSS mg/L

Page 12: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

12Boskalis International bv

23Boskalis International bv

Environmental Limits

Light Requirement

15% Irradiance at

3m depth > 50% Time

Light --- TSS

TSS --- NTU

Hydrodynamic Model

Dredging scenarios

Environmental Limits

EWMA

24Boskalis International bv

TURBIDITY

Compliance• 2 Buoys North• 9 Buoys South

Additional• 11 North+South

Turbidity Control

Page 13: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

13Boskalis International bv

25Boskalis International bv

Turbidity Control

• Buoys,– GSM– Ad hoc maintenance– Weekly cleaning– Monthly verification

• EMP– Environmental limit

• Management– Response level 2– Response level 1

• Dashboard Display– EWMA

26Boskalis International bv

Dashboard

Page 14: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

14Boskalis International bv

27Boskalis International bv

Melbourne (2005)Summary

• Alliance contract with PoMCworked out well

• Turbidity limits soundly based on impacts sensitive recievers

• Ecological processes respond to prolonged impacts justifies 6-hour avg + EWMA

• Time-averaging also needed for manageability of operational responses

• Concerns more realistically perceived

28Boskalis International bv

Khalifa Port and Industrial Zone (UAE, 2008)

• Dredging for construction of Khalifa Port

• Port located between world-class coral reef and power plant water intake

• Strong constraints on turbidity levels and other impacts - not well-founded

• Major operational demands (monitoring 24/7, 1-hour response time)

Khalifa

Page 15: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

15Boskalis International bv

29Boskalis International bv

TurbidtyMeasurements

Khalifa PortSensitive recievers

30Boskalis International bv

Fixed monitoring stationsKhalifa data on-line

Page 16: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

16Boskalis International bv

31Boskalis International bv

Example on-line data24-hr turbidity station W4

• Monitoring at fixed stations is only one component (amongst many others)

32Boskalis International bv

Khalifa (2008)Summary

• Challenging project!• Environmental standards

were met so-far• Rigid implementation &

execution of environmental monitoring procedures

• Research monitoring provides data for validation of plume model

• Project benefits from open communication with Client

Page 17: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

17Boskalis International bv

33Boskalis International bv

Monitoring of environmentalparameters

• What is relevant?• How to measure? Where? How often? At which depth?• How to process data? How to interpret results?• What are consequences if criteria are not met?

34Boskalis International bv

Monitoring of environmental parameters

• Anything possible, as long as clear and well to be adhered to

• Clear distinction between compliance and research

• Cost of monitoring in relation to project

sensor

Page 18: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

18Boskalis International bv

35Boskalis International bv

Turbidity in a wider context• Dredging-induced turbidity vs.

other drivers

Jiangsu, Yangtze River (China)

After: Van Houtam and Pauly (2007)

Mississippi River (USA)Lake Michigan (USA)

After: Vanderploeg (2007) After: Walker (1997)

Fishing

Shipping

Nature

36Boskalis International bv

Turbidity Research• Prediction of turbidity around hoppers: TASS

program (funded by SSB)• Ecodynamic Design: Building with Nature

Program (Foundation EcoShape)

ontwikkelenInteractievecases

Generiekonderzoek

ToolBox (instrumentarium)

Kennisproducten

Ontwerp

Uitvoering

Monitoren

Analysebestaande

Cases

Systeem-kennis en

technologie

Uitvoerbare pilots

Modellen

Kennis

ProductsDuurzameontwikkelingsstrategieën

Hypothese-vorming

Besluitvorming

HollandseK

ust

ZuidwestelijkeD

elta

IJsselmeer

Singapore

Hoge-resolutie

monitoring site

Ecodynamicdesign

Interactivecases

Genericresearch

ToolBox (instrumentarium)

Knowledge products

Design

Realisation

Monitoring

Analysis existing Cases

System-Knowledge /technology

Realisable pilots

Models

Knowledge

Sustainabledevelopment

strategies

Hypothesis-

Governance

HollandseK

ust

ZuidwestelijkeD

elta

IJsselmeer

Singapore

High-resolution monitoring

site

Page 19: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

19Boskalis International bv

37Boskalis International bv

Observations from the dredging industry (2)

• Environmental requirements have become common

• Environmental limit values are getting more tight• Tendency to relate limits to biological, chemical

and/or physical processes• Notification of background levels & exposure

times is crucial• Not all clients / consultants aware that imposing

restrictions will increase costs

38Boskalis International bv

Conclusions

• Each project is unique• Lessons from one project to be used for next,

with great care (lessons, not limits)• Formulation of limits needs better justification• Environmental aspects should be integral part of

the project• Communication & stakeholder involvement

prerequisite for successful project

Page 20: Environmental Aspects of Dredging Works in Practice...Boskalis International bv 1 Boskalis International bv 1 Environmental Aspects of Dredging Works in Practice Stefan Aarninkhof

20Boskalis International bv

39Boskalis International bv

Conclusions

• Research is carried out on– The establishment of environmental design

specifications and operational requirements during execution

– The development of equipment to meet these environmental demands

Dredging contractors do care for the environment


Recommended