HOA MAC URBAN DEVELOPMENT AND MANAGEMENT Co.,Ltd
INDUSTRIAL POLLUTION MANAGEMENT PROJECT
ENVIRONMENTAL IMPACT ASSESSMENT
Of Subproject
“CONSTRUCT CENTRALIZED EFFLUENT TREATMENT PLANT
WITH CAPACITY 1,500 M3/DAY AT HOA MAC INDUSTRIAL ZONE –
PHASE 1 (MODULE 1)”
FINAL
HA NAM, 04/2014
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
i
TABLE OF CONTENTS
TABLE OF CONTENTS .................................................................................................. i
LIST OF TABLE ........................................................................................................... x
LIST OF FIGURE ..................................................................................................... xiii
ABBREVIATION ....................................................................................................... xiv
EIA SUMMARY ............................................................................................................. 1
I. HOA MAC IZ PROJECT ............................................................................................. 1
II. PROJECT DESCRIPTION ......................................................................................... 1
III. CURRENT STATUS DESCRIPTION....................................................................... 1
3.1. Hydrological characteristics .................................................................................. 1
3.2. Current environment status ................................................................................... 2
IV. ANALYSIS OF ALTERNATIVES ........................................................................... 2
4.1. WW Treatment Technology .................................................................................. 2
4.2. Discharge Location ............................................................................................... 2
4.3. Sludge Treatment .................................................................................................. 2
V. IMPACT ASSESSMENT AND MITIGATION MEASURES .................................... 2
Construction phase ...................................................................................................... 2
5.1. Air .................................................................................................................... 2
5.2. Water ................................................................................................................ 3
5.3. Soil Environment - Resource ............................................................................. 3
5.4. Solid waste (SW) .............................................................................................. 3
5.5. Socio-economic Impacts ................................................................................... 4
Operation phase ........................................................................................................... 4
5.6. Air .................................................................................................................... 4
5.7. Groundwater ..................................................................................................... 4
5.8. Surface water .................................................................................................... 5
5.9. Soil ................................................................................................................... 5
5.10. Ecology system and landscape ........................................................................ 5
5.11. The community, health and safety ................................................................... 5
VI. ENVIRONMENT MANAGEMENT PLAN .............................................................. 5
6.1. Environmental Monitoring .................................................................................... 5
ii
6.2. Cost Estimate and Implementation Time of The Environment Management Plan
(EMP) .......................................................................................................................... 7
VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...................... 7
7.1. The Objective of Public Consultation .................................................................... 7
7.2. Results of Public Consultation .............................................................................. 7
7.3. Information Disclosure ......................................................................................... 8
INTRODUCTION ........................................................................................................... 9
1.1. ORIGIN OF THE PROJECT ................................................................................ 9
1.2. THE INVESTOR .................................................................................................. 9
1.3. PROJECT’S LOCATION ..................................................................................... 9
1.4. CURRENT SITUATION OF TECHNICAL INFRASTRUCTURE IN HOA MAC
IZ ............................................................................................................................... 11
1.4.1. List of tenants and their WW pre-treatment capacity .................................... 11
1.4.2. Drainage system ........................................................................................... 13
1.4.2.1. Rainwater drainage system ..................................................................... 13
1.4.2.2. Wastewater drainage system ................................................................... 14
1.4.3. Preliminary Treatment Wastewater Treatment System (PTWTS) of the
Tenants (basics and management system) .............................................................. 14
1.4.3.1. PTWTS of FINETEK Vietnam Co.,Ltd ................................................... 15
1.4.3.2. PTWTS of VINAGLAZE Joint Stock Company ..................................... 15
1.4.3.3. PTWTS of NOVAREF Fire Resistant Material Development Joint Stock
Company ............................................................................................................. 16
1.4.3.4. PTWTS of Vietnam Advanced Material Co., Ltd .................................... 16
1.4.4. Management of Domestic and Industrial Wastes .......................................... 16
1.4.5. Traffic system .............................................................................................. 16
1.4.5.1. External traffic ........................................................................................ 16
1.4.5.2. Internal traffic ......................................................................................... 17
1.4.6. Hazardous waste (HW) management ............................................................ 18
1.4.7. Risk management ......................................................................................... 19
1.5. DESCRIPTION OF THE CETP ......................................................................... 21
1.5.1. Treatmnet Technology, Influent and Effluent Characteristics ....................... 21
iii
1.5.1.1. Technology of the CETP ......................................................................... 21
1.5.1.2. Influent and Effluent Standards ............................................................... 21
1.5.2. Charecteristic of the CETP and discharge outlet ........................................... 22
1.5.2.1. WW Characteristics ................................................................................ 22
(1). Types of WW to be treated ....................................................................... 22
(2). Influent Characteristics .............................................................................. 22
(3). Effluent Characteristics .............................................................................. 22
(4). Anticipated WW flow to CETP .................................................................. 23
(5). Evaluation of WW quality ......................................................................... 23
1.5.2.2. Characteristics of CETP .......................................................................... 23
(1). Description of the WW collection system and drainage system .................. 23
(2). Treatment technology ................................................................................ 24
1.5.2.3. Discharge characteristic .......................................................................... 26
(1). Characteristic of discharge systems ............................................................ 26
(2). Discharge method ...................................................................................... 27
(3). Discharge mode ......................................................................................... 27
(4). Discharge flow ........................................................................................... 27
1.5.3. Sludge treatment technology ........................................................................ 27
1.5.4. Total investments and implementation progress ........................................... 27
1.6. ENVIRONMENTAL LEGISLATION AND GUIDELINES .............................. 28
1.6.1. World Bank Policy on Environmental Assessment ....................................... 28
1.6.2. Vietnamese Policy on Environmental Assessment ........................................ 28
1.6.3. The environmental standards and regulaions ................................................ 31
CHAPTER 2 CHARACTERISTICS OF THE PROJECT AREA ................................. 33
2.1. GENERAL CHARACTERISTICS OF THE PROJECT AREA .......................... 33
2.1.1. Natural characteristics .................................................................................. 33
2.1.1.1. Topography, geology, climate ................................................................. 33
(1). Topography ................................................................................................ 33
(2). Geology ..................................................................................................... 33
(3). Climate ...................................................................................................... 37
iv
2.1.2. Socio-economic conditions .......................................................................... 40
2.1.2.1. Socio-economic conditions of Hoa Mac Town in first 6 months of 2013 . 40
(1). Agricultural production .............................................................................. 40
(2). Industrial production - handicraft industry - Civil Construction -
Commercial Services ........................................................................................ 40
(3). Regarding the Traffic – Irrigation system ................................................... 40
(4). Regarding socio-culture issues ................................................................... 40
2.1.2.2. Socio-economic conditions of Chau Giang Commune in first 6 months of
2013 .................................................................................................................... 41
(1). Agricultural production .............................................................................. 41
(2). Services ..................................................................................................... 41
(3). Socio-culture, health care, education .......................................................... 42
2.1.2.3. Socio-economic conditions of Trac Van Commune in 2012 .................... 42
(1). Agricultural production .............................................................................. 42
(2). Industry - Handicraft Industry and Construction......................................... 43
(3). Irrigation .................................................................................................... 43
(4). Culture – Society and education ................................................................. 43
2.1.2.4. Social-economic conditions of Duy Tien District .................................... 43
(1). Agricultural productivity– rural areas ......................................................... 43
(2). Industry – Handicraft- Construction ........................................................... 44
(3). Natural resources and environment ............................................................ 44
(4). Social and cultural fields ........................................................................... 44
(5). Orientations ............................................................................................... 44
(6). Main targets ............................................................................................... 45
(7). Main tasks .................................................................................................. 45
2.2. CHARACTERISTICS OF THE RECEIVING RESOURCE ............................... 47
2.2.1. WW receiving place ..................................................................................... 47
2.2.2. Natural features ............................................................................................ 47
2.2.2.1. Hydrological characteristics of receiving resource................................... 47
2.2.2.2. Aquatic environment ............................................................................... 47
v
2.3. SUMMARY OF THE EXISTING STATE OF THE ENVIRONMENT AT THE
PROJECT AREA ...................................................................................................... 47
2.3.1. Air ................................................................................................................ 47
2.3.2. Soil .............................................................................................................. 49
2.3.3. Groundwater environment ............................................................................ 51
2.3.4. Surface water ............................................................................................... 52
CHAPTER 3 CHAPTER 3. ANALYSIS OF PROJECT ALTERNATIVES................. 55
3.1. CRITERIA FOR SELECTING ALTERNATIVES ............................................. 55
3.2. WASTEWATER TREATMENT TECHNOLOGY ............................................. 55
3.2.1. Aerotank (AAO) Technology is described as follows: .................................. 55
3.2.2. Comparison among treatment technologies .................................................. 57
3.3. DISCHARGE LOCATION ................................................................................. 59
3.4. SLUDGE TREATMENT TECHNOLOGY ........................................................ 62
CHAPTER 4 ENVIRONMENTAL IMPACT ASSESSMENT .................................... 66
4.1. SOURCE, OBJECTS AND AFFECTED SCALE ............................................... 66
4.1.1. Construction phase ....................................................................................... 66
4.1.1.1. Impact sources related wastes .................................................................. 66
4.1.1.2. Impacts sources unrelated to wastes ........................................................ 68
4.1.2. Operation phase ........................................................................................... 69
4.1.2.1. Impact sources related to wastes .............................................................. 69
4.1.2.2. Impact sources unrelated to waste ........................................................... 70
4.2. ENVIRONMENTAL IMPACT ASSESSMENT (EIA) ....................................... 70
4.2.1. Construction phase ....................................................................................... 70
4.2.1.1. Impacts on air environment ..................................................................... 70
(1). Impacts of site clearance ............................................................................ 71
(2). Impacts of dusts created by means of transportation of materials, equipment
......................................................................................................................... 71
(3). Impacts caused by cutting, welding, painting and metal coating operations 71
(4). Impacts created by residence and living operations of the workers on site .. 72
(5). Impacts created by noises in construction activities. ................................... 72
(6). Impact assessment of air pollutants: ........................................................... 74
vi
4.2.1.2. Impacts on the water environment ........................................................... 75
(1). Impacts of domestic WW of workers ......................................................... 75
(2). Impacts of WW from cleaning and maintaining machinery ........................ 76
(3). Impacts on groundwater quality ................................................................. 76
(4). Impacts of rainwater running off ................................................................ 76
(5). Impacts of construction wastewater ............................................................ 77
4.2.1.3. Impacts on soil resource – environment................................................... 77
4.2.1.4. Impacts of solid wastes ........................................................................... 77
4.2.1.5. Impacts on social – economic aspects...................................................... 78
(1). Advantaged impacts ................................................................................... 78
(2). Adverse impacts ......................................................................................... 78
4.2.1.6. Synthetic EIA caused by Construction Phase .......................................... 78
4.2.2. Operation phase ........................................................................................... 79
4.2.2.1. Impacts on air.......................................................................................... 79
4.2.2.2. Impacts on groundwater environment...................................................... 80
4.2.2.3. Impacts surface water environment ......................................................... 80
(1). Domestic WW of operators ........................................................................ 80
(2). WW from the CETP ................................................................................... 80
(3). Rainwater runoff: ....................................................................................... 80
4.2.2.4. Impacts on soil ........................................................................................ 81
(1). Solid waste (SW) generated from the treatment phase ................................ 81
(2). Sludge created by the CETP ....................................................................... 81
(3). Domestic solid waste (DSW) ..................................................................... 82
(4). Hazardous waste (HW) .............................................................................. 82
4.2.2.5. Impacts on the ecology and landscape ..................................................... 82
4.2.2.6. Impacts on the community’s activities, health and safety ........................ 82
4.2.2.7. Environment Incidents in the Operation Phase ........................................ 82
(1). Operation Incidents .................................................................................... 82
(2). Incidents caused by natural disasters .......................................................... 83
4.3. DETAILED LEVEL AND RELIABILITY OF ASSESSMENTS ....................... 83
vii
4.4. EFFECT ON WATER QUALITY ...................................................................... 85
4.4.1. Pollution load ............................................................................................... 85
4.4.2. Impact assessment on receiving source......................................................... 85
4.5. EFFECT ON ENVIRONMENT AND AQUATIC ECOSYSTEM ...................... 86
4.6. EFFECT ON HYDROLOGY ............................................................................. 86
4.7. EFFECT ON AIR ............................................................................................... 86
4.8. EFFECT ON RISK AND ACCIDENTS ............................................................. 87
4.9. SOCIAL – ECONOMIC IMPACTS AND DOWNSTREAM WATER USE ...... 87
4.10. CUMULATIVE IMPACTS .............................................................................. 87
4.10.1. Giat River pollution load analysis ............................................................... 87
4.10.1.1. Maximum pollution load ....................................................................... 87
4.10.1.2. Current pollutant loads .......................................................................... 88
4.10.1.3. Pollutant load from discharge source ..................................................... 88
4.10.1.4. Giat River load receiving capacity ......................................................... 89
4.10.2. Chau Giang River pollution load analysis ................................................... 89
4.10.2.1. Max Pollution load ................................................................................ 90
4.10.2.2. Current pollutant load ............................................................................ 90
4.10.2.3. Pollutant load from discharge source ..................................................... 90
4.10.2.4. Chau Giang River pollution load receiving capacity .............................. 91
CHAPTER 5: POLLUTION MITIGATION MEASURES ............................................ 92
4.11. ENVIRONMENTAL MANAGEMENT PLAN (EMP)..................................... 92
4.11.1. Construction phase ..................................................................................... 92
4.11.1.1. Water pollution mitigation measures ..................................................... 92
4.11.1.2. Mitigation Measures for Impacts of SW and HW .................................. 92
4.11.1.3. Mitigation measures to the air quality .................................................... 93
4.11.1.4. Impact Mitigation Measures for Soil Quality ......................................... 93
4.11.2. Operation phase........................................................................................ 101
4.11.2.1. Impact Mitigation Measures for Water Pollution ................................. 101
(1). Industrial wastewater ............................................................................... 101
(2). Domestic WW ......................................................................................... 101
viii
(3). Rainwater ................................................................................................. 101
(4). Groundwater ............................................................................................ 101
(5). Pollution in outlets ................................................................................... 101
4.11.2.2. Impact Mitigation Measures for Sludge ............................................... 101
4.11.2.3. Impact Mitigation Measures for Air .................................................... 102
4.11.2.4. Impact Mitigation Measures for Soil Quality ....................................... 102
4.11.2.5. Impact Mitigation Measures for SW .................................................... 102
4.12. RISK MANAGEMENT .................................................................................. 106
4.12.1. In the construction phase .......................................................................... 106
(1). Fire & Explosion Prevention and Fighting ............................................... 106
(2). Traffic Accident Mitigation Measures ...................................................... 106
(3). Traffic safety control, health care and incident prevention and fighting
measures ......................................................................................................... 106
4.12.2. In the operation phase .............................................................................. 106
4.12.2.1. Labor safety and hygiene measures ..................................................... 106
4.12.2.2. Preventive measures and Fire & Explosion Response .......................... 107
4.12.2.3. Preventive measures and Fuel Leakage Response................................ 108
4.12.2.4. Lightning system ................................................................................. 109
4.12.2.5. CETP’s Non-operation Response ........................................................ 109
4.13. COMMUNICATION PROGRAM TO THE COMMUNITY AND
COMMUNITY RELATIONS ................................................................................. 112
4.14. TRAINING ..................................................................................................... 112
4.15. ENVIRONMENT MANAGEMENT ORGANIZATIONS AND
RESPONSIBILITIES FOR THE IZ AND CETP ..................................................... 113
4.15.1. Division of Environmental Affairs ........................................................... 113
4.15.1.1. Functions ............................................................................................ 113
4.15.1.2. Obligations .......................................................................................... 113
4.15.2. Departments working in the CETP ........................................................... 114
4.15.2.1. Functions ............................................................................................ 114
4.15.2.2. Obligations .......................................................................................... 114
4.16. ENVIRONMENTAL MONITORING PROGRAM ........................................ 115
ix
4.16.1. Monitoring compliance with mitigation measures and environmental
standards .............................................................................................................. 115
4.16.2. On basis of the Community’s monitoring ................................................. 115
4.16.3. Monitoring the Project’s completion of indexes ....................................... 116
4.16.4. Environment Quality Monitoring (EQM) Indexes .................................... 116
4.16.5. Automatic monitoring .............................................................................. 118
4.17. EXPECTED EXPENSE AND IMPLEMENTATION TIME OF THE EMP ... 119
CHAPTER 5 PUBLIC CONSULTATION ................................................................. 120
5.1. OBJECTIVES OF PUBLIC CONSULTATION ............................................... 120
5.1.1. For appraisal authorities ............................................................................. 120
5.1.2. For the project owner ................................................................................. 120
5.1.3. For the Consulting Agencies ...................................................................... 120
5.1.4. For the People’s Committee and Committee of Vietnam Fatherland’s Front in
commune level ..................................................................................................... 120
5.1.5. For the impacted communities.................................................................... 120
5.2. PUBLIC CONSULTATION IMPLEMENTATION ......................................... 120
5.2.1. Interviewees ............................................................................................... 120
5.2.2. Implementation methods ............................................................................ 120
5.3. CONSULTATION RESULTS .......................................................................... 121
5.3.1. Consultation results in Hoa Mac Town, Chau Giang Commune and Trac Van
Commune ............................................................................................................ 121
5.3.1.1. Adverse impacts of the Project on the natural environment, socio-
economic aspects ............................................................................................... 121
5.3.1.2. The Project’s Environment Impact Mitigation Measures ....................... 121
5.3.1.3. Recommendations to the Investor .......................................................... 121
5.3.2. Interview results ......................................................................................... 121
5.4. INFORMATION DISCLOSURE ...................................................................... 125
5.5. THE INVESTOR’S COMMITMENTS ............................................................ 125
x
LIST OF TABLE Table 1-1. List of Tenants in Hoa Mac IZ ...................................................................... 12
Table 1-2. Concentration of pollutants in influent of CETP ........................................... 21
Table 1-4. WW flow forecast of facilities after complete construction and stable
operation (expected to attract more tenants until the end of 2014) ................................. 23
Table 1-5. Table of total investment ............................................................................... 27
Table 2-1. The depth and thickness of first layer at the drill-hole ................................... 33
Table 2-2. The depth and thickness of second layer at the drill-hole .............................. 33
Table 2-3. Synthetic table of mechanical and physical target of the second layer .......... 33
Table 2-4. The depth and thickness of third layer at the drill-hole ................................. 34
Table 2-5. Synthetic table of mechanical and physical target of the third layer .............. 34
Table 2-6. The depth and thickness of fourth layer at the drill-hole ............................... 35
Table 2-7. Synthetic table of mechanical and physical target of the fourth layer ............ 35
Table 2-8. Synthetic table of mechanical and physical target of the fifth layer ............... 36
Table 2-9. Average temperature in months and years (0C) ............................................. 37
Table 2-10. The hour number of sunshine in months ...................................................... 38
Table 2-12. The average humidity in months and years (%)........................................... 39
Table 2-13. Plants in rich-soil ....................................................................................... 42
Table 2-14. Air quality results in IZ (10th
December 2012) ............................................ 48
Table 2-15. Results of dust, noise and microclimate in some location in IZ (10th
December 2012) ............................................................................................................ 48
Table 2-16. Soil quality (10th
December 2013) ............................................................... 50
Table 2-17. Results of groundwater quality ................................................................... 51
Table 2-18. Results of surface water .............................................................................. 53
Table 3-1. Comparision of applied treatment technologies ............................................ 57
Table 3-2. Analysis of Sludge Treatment Technology Alternative ................................... 62
Table 4-1. Sources of impact related to wastes in the construction phase ...................... 66
Table 4-2. Impacts unrelated to wastes in the construction phase .................................. 68
Table 4-3. Impact sources related to wastes, object and affected scale .......................... 69
Table 4-4. Impact sources unrelated to waste, object, affected scale .............................. 70
Table 4-5. Impacts on Air Environment during Construction Phase .............................. 70
xi
Table 4-6. Pollution coefficient for truck with capacity of 3.6-10 ton ............................. 71
Table 4-7. Ratio of pollutants during welding process (mg/1 welding rod) .................... 72
Table 4-8. Noise intensity of some equipment ................................................................ 73
Table 4-9. Impacts of Air Pollutants .............................................................................. 74
Table 4-10. Forecast the pollution load in waste water of labors (estimated volume of 20
person) .......................................................................................................................... 75
Table 4-11. Flow and Volume of Pollutants Created from Machinery & Equipment
Cleaning and Maintaining Phase on Site ....................................................................... 76
Table 4-12. Pollutant concentration in wastewater of construction phase ...................... 77
Table 4-13. Generalized Table of Impacts in Construction Phase .................................. 78
Table 4-14. Bad Odor Emission Sources in the CETP ................................................... 79
Table 4-15. Calculations of Waste Sludge generated by Hoa Mac IZ’s CETP with
assumed capacity of 1500 m3/day. ................................................................................ 81
Table 4-16. Synthetic Table of Impacts in Operation Phase of the Plant ........................ 83
Table 4-17. Assessment of reliability of the EIA methods applied .................................. 83
Table 4-18. The pollution load in WW of Hoa Mac IZ CETP ......................................... 85
Table 4-19. Pollutant concentrations of Giat River ........................................................ 87
Table 4-20. The max pollution load that nearby surface water source can receive ........ 88
Table 4-21. The current pollution loads ......................................................................... 88
Table 4-22. Pollutant loads from discharge sources ...................................................... 89
Table 4-23. Giat River pollution loads receiving capacity after received the discharge
from the CETP ............................................................................................................... 89
Table 4-24. The limitation values of pollutants in Chau Giang River ............................. 89
Table 4-25. The max pollution load that nearby surface can receive.............................. 90
Table 4-26. The current pollutant load .......................................................................... 90
Table 4-27. The pollution load from Giat river into Chau Giang river ................................ 91
Table 4-28. Chau Giang River pollution load receiving capacity after receiving water
from Giat River and WW from the CETP of Hoa Mac IZ ............................................... 91
Table 5-1. Concerned Agencies in the Environmental Management Programs .............. 92
Table 5-2. Summarized plan for mitigation measures during construction phase ........... 94
Table 5-3. Summarized plan for mitigation measures during operation phase ............. 103
Table 5-4. Summarized plan for mitigation measures for environmental risks ............. 110
xii
Table 5-5. Environmental Monitoring Program ........................................................... 116
Table 5-6. Expected expense of EMP in the construction phase and first year of
operation ..................................................................................................................... 119
Table 6-1. Results of public consultation ..................................................................... 122
xiii
LIST OF FIGURE Figure 1-1. Hoa Mac IZ location ................................................................................... 10
Figure 1-2. The figure shows the CEPT location and CETP service area of Module 1 & 2
- Phase 1 ....................................................................................................................... 10
Figure 1-3. Rainwater (Rw) drainage system of Hoa Mac IZ ......................................... 13
Figure 1-4. WW drainage diagram of Hoa Mac IZ ........................................................ 14
Figure 1-5. Production Wastewater Reuse Diagram ...................................................... 15
Figure 1-6. Domestic WW treated by 3 Compartment Septic Tank Diagram .................. 16
Figure 1-7. Diagram of WW treatment technology of Hoa Mac IZ ................................. 24
Figure 3-2. Location of outlet from bio-pond to open ditch in IZ ................................... 59
Figure 3-3. Location of outlet from open ditch to Giat River ......................................... 60
Figure 3-4. Outlet location ............................................................................................ 61
Figure 3-5. Diagram of sludge transport route .............................................................. 64
Figure 4-1. The impact of noise on people ..................................................................... 74
xiv
ABBREVIATION
AMS: Automatic Monitoring Station
BOD: Biological Oxygen Demand
CETP: Centralized Effluent Treatment Plan
COD: Chemical Oxygen Demand
CW: Construction Waste
DO: Dissolved Oxygen
DONRE: Department of Natural Resource and Environment
DW: Domestic Waste
EIA: Environmental Impact Assessment
EMP: Environmental Management Plan
MONRE: Ministry of Natural Resource and Environment
OST: Oil Separator Tank
ND: Not detected
NH: National Highway
HW: Hazardous Waste
IZ: Industrial Zone
IZMB: Industrial Zone Management Board
PV: Protection of Vietnam
PTWTS: Preliminary Treatment Wastewater Treatment System
RC: Reinforce Concrete
SS: Suspended Solid
SW: Solid Waste
WB: World Bank
WW: Wastewater
1
EIA SUMMARY
I. HOA MAC IZ PROJECT
1. In order to improve the industrial pollution control in Vietnam, The Government of Vietnam
works with The World Bank (WB) to implement an IDA-financed Vietnam Industrial Pollution
Management Project (VIPMP). This project has 3 components of which Component 2 is to
provide financial assistance for qualified selected industrial zones (IZs) to properly construct and
operate Centralized Effluent Treatment Plants (CETPs) and ultimately to comply with national
environmental requirements in Nam Dinh, Ha Nam, Dong Nai, and Ba Ria-Vung Tau (BR-VT)
Province. Hoa Mac IZ is one of the qualified industrial zones in this project.
2. The construction of Hoa Mac IZ was approved by Vietnamese Government in the Decision
No 1107/QĐ-TTg in 21st August 2006. The EIA Report of Hoa Mac IZ Infrastructure
Construction Project was approved in Decision No. 1094/QĐ-UBND in 1st September 2008 of
Ha Nam Province People’s Committee.
3. According to the approved Decision of EIA, the total capacity of Hoa Mac IZ’s CETP is
6,000 m3/day. The investment in the CETP is divided into the following phases:
- Phase 1: 3,000 m3/day, which is divided into two modules: Module 1 – 1,500 m
3/day,
Module 2 – 1,500 m3/ day.
- Phase 2: 3,000 m3/day & night, which is divided into two modules: Module 3 – 1,500
m3/day, Module 4 – 1,500 m
3/ day.
4. In the initial phase, module 1 – Hoa Mac IZ’s CETP will be installed with capacity of 1,500
m3/day. It serves the discharge of the enterprises leasing the land in IZ (hereinafter called as
tenants) at Chau Giang commune with the serve area of 87.4 hectares and entire municipal WW
in Hoa Mac IZ.
II. PROJECT DESCRIPTION
1. The tenants are responsible for treating wastewater (WW) that is in compliance with Column
B of the National Regulation QCVN 40:2011/BTNMT – National Technical Regulation on
Wastewater. This treated WW will be collected and enter the CETP for further treatment before
final discharge in Giat River.
2. The discharge standard and effluent quality of the propsed CETP is the National Regulation
QCVN 40:2011, Column A, responding to Kq = 0.9; Kf = 1.0
3. The standard applied for discharging to Giat river is National Regulation QCVN
08:2011/BTNMT, Column A1.
4. The effluent of the CETP via the slope of the terrain from the Bio-pond to the ditch in the IZ,
then to Giat River and to Chau Giang River.
5. The applied technology to Module 1 of Hoa Mac’s CETP is Sequence Batch Reactor (SBR)
combined with preliminary physicochemical treatment.
III. CURRENT STATUS DESCRIPTION
3.1. Hydrological characteristics
Chau Giang River: It is a river of Red River system, located in Ha Nam Territory. It is connected
to Red River by two gates: Yen Lenh gate at Duy Tien District anh Huu Bi at Ly Nhan district.
At Tien Phong (Duy Tien District), Chau Giang River is divided into two branches. One is
between Ly Nhan and Binh Luc Districts and another is the between Duy Tien and Binh Luc
Districts. Chau Giang River at Ha Nam Province is 58.6 km long. Average flow rate in dry
season and rainseason is in turn 5 – 10 m3/s and 60 m
3/s.
2
Giat River: Giat River receives WW directly from Hoa Mac IZ. It will receive the treated CETP
effluent with the noted characteristics (Column A1). The average flow rate of the river is 22.6
m3/s.
3.2. Current environment status
Surrounding environmental quality monitoring results in the Project site show that the
environmental quality of air, soil, groundwater and surface water are quite good. Most of the
indexes are in the accepted level under Current Regulations QCVN 26:2010, QCVN 05:2009,
QCVN 09:2008, QCVN 08:2009.
Regarding the rivers receiving the WW treated by Hoa Mac IZ’s CETP, according to results of
calculating pollution level, the rivers are able to receive those WW with said indexes.
IV. ANALYSIS OF ALTERNATIVES
4.1. WW Treatment Technology
Two proposed methods of WW treatment technology for Hoa Mac IZ’s CETP were considered
including SBR and Aerotank. After a careful consideration, the Investor selected SBR
technology for Hoa Mac IZ’s CETP because of some following reseasons:
- SBR is operated with playing role of bio-tank also as sedimentation tank.
- It is operated in batches.
- With a healthy microorganism, SBR technology has a lot of advantages in operation such as
high shock resistance, fast recovery capability.
- The performance of nitrogen treatment may reach up 97%.
- The land used for CETP plan is less than other techonology.
4.2. Discharge Location
The treated WW of Hoa Mac IZ’s CETP is expected to be discharged into Giat river via 1
artificial open Ditch in the length of 1500 m and width of 20 m through out one F600 discharge
sewer with reinforcement bottom of +2.5m. The outlet is located at the ending point of this ditch.
There is no alternative considered for dischsrge location.
4.3. Sludge Treatment
The applied sludge treatment technology to Hoa Mac IZ’s CETP is hardened hazardous waste
sludge which is used to make concrete.
The Investor signed the Contract with URENCO 11 to transport and treat sludge under the
current regulations.
The hazardous waste (HW) is required to be treated comprehensively and stably on basis of the
recommended plan on HW treatment and capacity of URENCO 11. URENCO 11 is licensed to
transport and treats hazardous sludge under Vietnamese Regulations and Laws.
V. IMPACT ASSESSMENT AND MITIGATION MEASURES
Construction phase
5.1. Air
Impacts:
Impacts caused by dusts, gas emission of transportation vehicles and noise are the largest
impacts during the construction phase.
Mitigation measures:
3
To use tarpaulins to entirely cover the trucks’ boot during the process of transportation of
building materials such as sand, rocks on roads.
To arrange reasonable routes in order to ensure that the machinery and equipment are always in
the best technical conditions.
To apply the appropriate construction methods, and to mechanize all operations during the
construction phase.
5.2. Water
Impacts:
Main impacts on the water quality during the construction phase of the Project are domestic WW
of workers. Main contents of the pollutants in the domestic WW are waste matter, suspended
solid (SS), organic compounds (BOD/COD), nutrients (N, P) and pathogenic organisms
(Coliform, E. Coli).
Mitigation measures:
The domestic WW of workers must be collected and treated by septic tanks before discharging
to the environment.
To repair, maintain and replace the construction equipment accessories, oil, clout that must be
collected comprehensively to avoid unexpected spilling on site.
To design rainwater drainage ditches surrounding the site to prevent from contamination of
impurities before discharging to the environment.
5.3. Soil Environment - Resource
Impacts:
Because domestic WW of workers, construction wastes, oil and grease are caused by equipment
and machinery on site, in the construction phase, wastes and WW are generated by workers’
activities from temporary camps. The redundance or leaked wastes during the construction
phase, oil and grease from cars, trucks, construction machinery, etc... if are not well collected
and managed may adversely affect the soil environment. However, only a limited number of
workers will be present on the construction site for a short period of time about 6 months, and
few car and truck would be used. Therefore, the impacts on soil in the construction phase is
small, localized, and temporary.
Mitigation measures:
The Investor will implement appropriate mitigation measures such as domestic and hazardous
waste management to address soil pollution.
5.4. Solid waste (SW)
Impacts:
SW in construction phase is divided into 02 types as domestic waste (DW) and construction
waste (CW).
Mitigation measures:
Limit the CW by planning and using building materials reasonably; also remind workers to
save and strictly manage and monitor the workload.
DW is collected and treated correctly under current regulations.
4
HW of this is collected in specialized barrels and cans with covers to meet the hygienic storage,
transported to environmental services agencies for disposal and treatment.
5.5. Socio-economic Impacts
Impacts:
Advantages:
To create employment for local people;
To increase incomes of workers;
Disadvantages:
Gathering the workforce (about 20 workers per day) during the construction period may cause
adverse impacts on the society and public order in the region;
Number of vehicles getting in and out the site during the construction phase may cause heavy
traffic in the region, leading to higher risks of traffic accidents therein.
Mitigation measures:
To limit the speed of vehicles on site;
To avoid transportation in rush hours.
Operation phase
5.6. Air
Impacts:
Factors affecting air quality are mainly odor caused by decomposition of organic matters which
are available in WW and collection of waste via waste filter and pump. Odor are from inlet,
pump pits, oil and grease separator tanks, bio-tanks, agglomerate flocculation tank, primary
sedimentation tank, SBR tank, sludge tank, pump station, bio-ponds, open ditch, and outlet.
Noise is created by the equipment in CETP such as pump or air blowers, causing direct impacts
on operators. Another Impacts on air is from local in the areas surrounding the IZ and the Plant.
Mitigation measures:
To relief the noise, the machinery must be maintained periodical and used correctly as described
in the manual.
To periodically monitor the air surrounding the CETP’s region.
To grow more trees in the buffer zone to create the landscape and to prevent pollution from
spreading odors.
To handle incidents or accidents during operations.
To clear the site surrounding the artificial ditch in the IZ.
5.7. Groundwater
Impacts:
Operations of the CETP may have impacts on groundwater when pipelines or the tank bottom or
WW in sludge tanks is not controlled.
Mitigation measures:
To monitor and control the groundwater quality in the region; to prevent penetration from
anaerobic tank and leakage in the connection points or transitions in WW pipelines.
5
5.8. Surface water
Impacts:
Domestic WW created by operators includes BOD, COD, and TSS. Normally, WW generated
by operators is treated by septic tanks so its pollutant contents reduce significantly and as the
result, the impacts are insignificant.
WW from the CETP includes components containing SS, microorganisms and other
contaminants.
Run-off water, main components are soil, sand, waste, oil and grease, impurities on the ground
and roof, treatment tank, staircase.
Mitigation measures:
For industrial WW, tenants are required to use pre-treatment technology to make sure that
industrial WW reach B type of QCVN 40:2011 before connecting to the CETP.
WW of operators will be collected and treated by septic tanks.
Rainwater will be collected by its drainage system of IZ via culvert holes in sidewalk.
To regularly monitor the water quality in outlet.
5.9. Soil
Impacts:
The soil is mainly impacted by sludge of CETP and domestic wastes of workers.
Mitigation measures:
The Investor signed the Contract with URENCO 11 to collect, transport and dispose waste
sludge in accordance with current regulations.
5.10. Ecology system and landscape
Generally, impacts on construction of the CETP shall not cause any change in landscape and
ecology system because this region’s land is for construction of IZ. The existing CETP may
create the good reputation for the IZ and good relationships with surrounding communities.
5.11. The community, health and safety
The Project causes insignficant impacts on the public works and the community, except for the
possible odor created by the CETPs, making the surrounding industrial tenants uncomfortable.
However, if mitigation measures are implemented correctly, such odor will be reduced.
VI. ENVIRONMENT MANAGEMENT PLAN
6.1. Environmental Monitoring
I CONSTRUCTION PHASE
1 Monitoring of air quality and noise
Parameters and
frequency
Once for 3 months or at the time of accident: PM10, total
particles, noise (24 hours in average) NOx, SO2, CO
Position Proposed location of CETP
Compared to QCVN 06:2008, QCVN 26:2010
2 Monitoring of groundwater quality
Parameters and
frequency
Once for 6 months; pH, color, hardness, SS, Cl-, NH4+,
Xyanua, NO3-, NO2
-, Sulfate, Fe, Mn, As, E.Coli, Total
Coliform;
6
Position 01 location in the Project’s site
Compared to QCVN 09:2008/BTNMT
3 Monitoring of WW quality
Parameters and
frequency
Once for 3 every months; pH, BOD5, COD, SS, Ammonium,
Phosphate, Chloride, surface active agents, oil and grease
Position 1 proposed position at the tents for workers
Compared to QCVN 14:2008/BTNMT
II OPERATION PHASE (This Program shall be implemented simultaneously with the monitoring program of IZ.
Therefore, some repeated parameters and position may be cancelled to avoid repetition)
1. Monitoring of air quality
Parameters and
frequency
Once for 6 months or at the time of acciden: temperature, dust,
noise (24 hours in average), CO, SO2, NO2, NH3, H2S, CH4,
VOC
Position Proposed location of CETP
Compared to QCVN 06:2008, QCVN 26:2010
2. Monitoring of surface water/river quality
Parameters and
frequency
Once for 3 months in the first operation year
Once for 6 months in the following years or at the time of
accident: pH, DO, BOD5, COD, SS, Coliform, turbidity, oil
and grease, N-NH4, N-NO3-, Cl
-, P-PO4
3-, SO4
2-, heavy metals
(As, Pb, Hg, Cd, Ni, Cr (III), Cr (VI), Cu, Mn), and surface
active agents.
If AMS is applied, such indexes as pH, TSS and COD shall be
automatically measured in case of incident or accident.
Position 1. 1 km upstream of discharge point of CETP
2. Discharge point of CETP
3. 1 km downstream of the discharge point of CETP
Compared to QCVN 08:2008
3.
Monitoring of groundwater quality
Parameters and
frequency
Once for 6 months: pH, TDS, turbidity, hardness, N-NO3, N-
NO2, total Fe, Cl-, N-NH3, SO4
2-, E. Coli, Coliform
Position Groundwater near the CETP
Compared to QCVN 09:2008
4. Monitoring of WW quality
Parameters and
frequency
AMS: pH, COD, TSS, and flow rate (continually monitoring)
at effluent discharge point.
Once per month in the first operation year of the CETP
Once for 3 months as the system is operated stably:
temperature, pH, BOD, COD, TSS, TDS, color, N-NH4, total
N, total P, alkali, KLN (As, Hg, Pb, Cd, Ni, Cr (III), Cr (VI),
Cu, Mn, Sn), oil and grease, total CN-, total phenol, chloride,
sulfur, fluoride, residual chloride, total pesticide (organic
chloride and phosphorus or organic matters), total PCB and
coliform.
Position 1. Influent of CETP
2. Effluent of CETP
Compared to QCVN 40:2011
5. Monitoring of sludge quality
7
Parameters and
frequency
Once per month in the first operation year
Once for 3 months: pH, Pb, As, Cd, Hg, Al, total Fe, Ni, Cu,
Zn, Mn, phenol, PAH, total nitrogen, total phosphate, CN-, và
Coliform.
Daily monitoring the quantity of waste sludge
Position 1. In sludge dryer yards
2. In the sludge treatment area
Compared to TCVN 7629:2007, QCVN 03: 2008
6.2. Cost Estimate and Implementation Time of The Environment Management Plan
(EMP)
Unit of Account: Vietnamese dong
No. Description Expense Funding
1 Implementation of mitigation measures Included in the
EPC Contract
IDA funding
2 Environment training for the CETP
operation 30,000,000
Counterpart funding
3 Monitoring the environment quality
during construction period (1 year) 20,000,000
Counterpart funding
4 Monitoring the environment quality in
the first operation year of the CETP 50,000,000
Counterpart funding
5 Environment Protection fee 20,000,000
Counterpart funding
6
Installation and annual operation of the
Automatic Monitoring System (AMS) for
CETP
654,886,364 IDA funding
Total 774,886,364
VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
7.1. The Objective of Public Consultation
The investor have to consult the following objects:
- The People’s Committee and Committee of Vietnam Fatherland’s Front of Hoa Mac Town,
Chau Giang Commune and Trac Van Commune;
- The surrounding local people who are impacted by the Project in construction and operation
process.
7.2. Results of Public Consultation
Project Owner – Hoa Mac IZMB has done in consultation with The People’s Committee and
Committee of Vietnam Fatherland’s Front of Hoa Mac Town, Chau Giang Commune and Trac
Van Commune in 2013, November 20th
and with the people living around the project area in
2013, November 27th
at IZMB’s office. The results are as below:
- The People’s Committee and Committee of Vietnam Fatherland’s Front of Hoa Mac Town,
Chau Giang Commune and Trac Van Commune have basically reached agreements on
adverse impacts of the Project on the natural environment, socio-economic issues and the
8
Project’s Environment Impact Mitigation Measures issued by the Investor. In addition, there
are some recommendations to ensure the environment quality in the project site.
- Comments of the surrounding inhabitants are as follows:Most of them agree (21/24) with
the construction of “CETP Project with capacity of 1,500 m3/day at Hoa Mac IZ, phase 1,
module 1”. The others (3/24) have no comment.
7.3. Information Disclosure
The “EMP” of the “Construction CETP Project with capacity of 1,500 m3/day at Hoa Mac IZ,
Phase I, module 1” will be disclosed in the Headquarter of the People’s Committee of Chau
Giang Commune, Trac Van Commune, Hoa Mac Town for public awareness, check and
inspection before and during the construction works may commence. In addition, the EMP will
be disclosed in English on the website of Vietnam Environment Protection Fund (VEPF),
Infoshop in Washington DC and at Vietnam Development Information Center (VDIC).
9
INTRODUCTION
1.1. ORIGIN OF THE PROJECT
The national industrialization and modernization process is always associated with the protection
of human health and environment. This is a very important issue in which interested by relevant
agencies.
Hoa Mac Industrial Park is built with the aim of contributing to the economy development by
creating employment for local people in the regions surrounding the IZ and Ha Nam province.
The IZ has many factories in varies production fields. Due to the specific characteristics of the
IZ, the waste (air emission, wastewater, solid waste) are complicated and toxic. It shall impact
on environment of not only the IZ but also the surrounding residential regions.
Therefore, the CETP is necessary and urgent to sustainable develop the IZ in particular and Ha
Nam Province in generally. Therefore, the Investor prepared the documents of the project
“Construction CETP with capacity of 1,500 m3/day at Hoa Mac IZ, Phase I, module 1”.
1.2. THE INVESTOR
The Industrial Zone Development: Hoa Mac Industrial Zone Devepment Management
Co.,Ltd
Represented by: Mr. Hoang Quoc Viet Position: President
Headquarter: No. 39 Nguyen Dinh Chieu, Le Dai Hanh Ward, Hai Ba Trung District,
Hanoi City
Telephone number: 04.62881234 Fax: 04.39763890
1.3. PROJECT’S LOCATION
The Project is located at lot KT-01A, Part I, Hoa Mac IZ, Duy Tien District, Ha Nam Province.
Hoa Mac IZ is located in Duy Tien District in 3 communes and town namely Chau Giang
Commune, Hoa Mac Town, and Trac Van Commune. Hoa Mac IZ’s boundaries are as follows:
- The South : is bordered by Highway 38 air traffic (according to planning).
- The North : is bordered by planning road.
- The West : is bordered by planning road
- The East : is bordered by Giat (according to planning).
Hoa Mac IZ is located in the North of the National Highway 38, which is 12 km from Dong Van
Town and 6 km from Hung Yen Town.
The location of Hoa Mac IZ and master plan including CETP is shown under the following
figures:
10
Figure 0-1. Hoa Mac IZ location
Figure 0-2. The figure shows the CEPT location and CETP service area of Module 1 & 2 -
Phase 1
CETP
location CETP service area of
Module 1
CETP service area of Module 2
CETP service area
of Module 1
CETP service area
of Module 2
11
1.4. CURRENT SITUATION OF TECHNICAL INFRASTRUCTURE IN HOA MAC IZ
Hoa Mac IZ is approved by Ha Nam Province People’s Committee under the detailed planning
with scale of 1/500 over the total area of 203 hectares.
Entire IZ area is located in 2 communes and 1 town that are Chau Giang Commune, Trac Van
Commune and Hoa Mac Town. The Investor cleared ground and invested in construction and
business of technical infrastructure, which is divided into 2 phases:
- Phase 1: 131.6 hectares; (consists of Chau Giang Commune, Hoa Mac Town and Trac
Van Commune)
-Phase 2: 71.4 hectares; (Chau Giang Commune)
At present, the Investor is investing in Phase 1 which is divided into 2 modules under the
administration boundaries (See Figure 1-2).
- Module 1 is in Chau Giang commune, Hoa Mac Town, Duy Tien District, Ha Nam
Province over the serve area of 87.4 hectares.
- Module 2 will be in Trac Van commune, Duy Tien District, Ha Nam Province over the
serve area of 44.2 hectares.
- The CETP is placed at the lot KT-01A, Phase I, Hoa mac IZ, Duy Tien District, Ha
Nam Province with the capacity of 1500 m3/ day (Module I) to serve Phase I (See
Figure 1-2). The area of the CETP (Module I) is nearly 1,400m2.Leased land area:
21.4538 hectares; sharing 16.3%
- The rest land area: 110.1462 hectares, sharing 83.7%
- The green area: 15.6407 hectares, sharing 11.88%
1.4.1. List of tenants and their WW pre-treatment capacity
List of tenants investing in Hoa Mac IZ – Phase 1 is presented in Table 1-1 (up to November
2013).
12
Table 0-1. List of Tenants in Hoa Mac IZ
No. Name of Tenants Area
(ha) Industrial Types
Maximal
operation
Freshwater
demand
m3/day &
night)
Discharge
flow (80% of
water supply)
m3/day &
night
Main pollution
parameters
1 Vinaglaze Joint Stock
Company 0.8021
Producing construction
materials and materials for
ceramic production
Operated in
24/24 43.4 34.7
COD, BOD5, TSS,
Total N, Total P
2 NOVAREF Fire- Resistant
Material Co., Ltd 1
Producing fire resistant
concrete
Operated in
24/24 4.3 3.26
COD, BOD5, Total
N, Total P, TSS, Pb,
Mg, Al
3 Vietnam Advanced Material
Company Limited 2.196
Construction of plants for
lease
Operated in
24/24 20.0 16.0
COD, BOD5, TSS,
Total N, Total P
4 Hanoi Battery Joint Stock
Company 2.9379 Producing battery Unexecuted 0 0
COD, BOD5, Total
N, Total P, TSS, Pb
5 KEYRIN Telecom Vietnam
Company 1.5 Electronic parts In-progress 0 0
COD, BOD5, TSS,
Total N, Total P
6 Vietnam Finetek Company
Limited 1.5178 Electronic parts
Operated in
24/24 40.0 32.0
COD, BOD5, TSS,
Total N, Total P
7
PVC-ME1 Machine
Installation and Mechanics
Company
3.0 Mechanics and machine
installation
Operated in
24/24 4.5 3.5
COD, BOD5, TSS,
Total N, Total P,
Total mineral oil
and fat
8 Ha Nam International
Agriculture Company 2.0
Producing husbandary
food/ food industry
preparing for
construction
0 0 COD, BOD5, TSS,
Total N, Total P
9 Ha Nam Vina Breeding Food
Company 4.0
Producing husbandary
food/ food industry Unexecuted 0 0
COD, BOD5, TSS,
Total N, Total P
Total 21.4538
13
The industrial wastewater from tenants in Hoa Mac IZ – Phase 1 must be treated by themself,
complying with the National technical Regulation QCVN 40:2011/BTNMT, column B. This
is stipulated in the WW Treatment Contract signed by Hoa Mac IZ Development
Management Co., Ltd and tenants in IZ. Then, WW from the preliminary treatment system of
tenants shall be connected to the CETP.
Currently, the preliminary treatment systems are installed and operated by tenants, meeting
the requirements of type B of QCVN 40:2011/BTNMT.
WW of the plants shall be treated via the preliminary treatment system during their operation,
then it flows to the drainage sewer to CETP. The effluent flows continuously even if the
plants are not operated fully in 24/24h.
The waste sludge created from the preliminary treatment system and other hazardous wastes
are collected, transported and treated by URENCO 11 Company under the signed contract.
1.4.2. Drainage system
1.4.2.1. Rainwater drainage system
The rainwater drainage system of Hoa Mac IZ is shown in the following figure:
Figure 0-3. Rainwater (Rw) drainage system of Hoa Mac IZ
- Basically, entire IZ is divided into basins on basis of contour line and flows to the drainage
ditch in the North of IZ and the planned drainage route along the expanded NH38. Finally,
rainwater of IZ after separating garbage, oil and grease is discharged to Giat river.
- The rainwater drainage system is the self-flow system which is constituted by drainage
ditches which are 1.5 m – 2 m from bordering thereof (calculated to the ditch centerline)
- Due to low ground leveling of the IZ, it is possible to select the rectangle drainage culvert
with cover slabs close to the sidewalk to limit the burry depth.
- Rainwater on roads flows to the storm water drainage routes via direct collection pits on
road sides
- Rainwater discharged by the plants is directly connected to the external storm water canal.
The connection sections are constructed and installed by the plants.
- Composition of the rainwater drainage system is as follows:
Water from road,
yard cleaning
Rainwater in garage,
warehouses
Rainwater in the
factories
The initial Rainwater
separation reservoir
Oil &
grease
Oil & grease
separation
Rainwater Drainage direction of the IZ
Drainage ditch along NH 38 and Giat River
14
+) The rainwater drainage routes along the sidewalk consist of 02 types: brick ditchs (B = 600
- 800) and reinforced concrete (RC). Calculated load of cover slabs is the load bearing
pedestrians.
+) The rainwater drainage system crossing roads are RC, with sealed cover slabs under
asphalt layer with B = 600 to B = 1,000 with vehicles’ load H30.
1.4.2.2. Wastewater drainage system
Ww created by plants in the IZ is treated preliminarily by tenants that flows naturally to the
closed pipeline system to approach the collection tank. The rainwater drainage system and
WW collection system are separated. Before reaching the collection tank, the raw waste in
WW is separated by the trash racks over the pipeline. Minimal dimensions of retained waste
depends on distance among metal rods of the trash rack. In order to prevent from waste
stagnation and impacting the effluent’s pressure, the tras rods must be regularly cleaned by
taking waste out by manual or motorized manner. Effluent velocity (v) via open slots is about
(0,65 m/s < v < 1 m/s). The width of open slots is varied upon request and dimensions of the
waste.
Figure 0-4. WW drainage diagram of Hoa Mac IZ
1.4.3. Preliminary Treatment Wastewater Treatment System (PTWTS) of the Tenants
(basics and management system)
The tenants investing in Hoa Mac IZ shall sign the WW Treatment Contract with the Investor,
in which their WW quality before connecting to the CETP shall be preliminary treated to
reach type B of QCVN 40:2011/BTNMT. In order to reach the requirements, the tenants must
invest their PTWTS. The PTWTS of 4 in 5 plants is put into operation, which is below
presented in detail. The 5th
plant has not yet been in plan.
Bio-pond → Canal of water drainage in IZ → Giat river → Chau Giang River
PRODUCTION WASTEWATER DOMESTIC WASTEWATER RAINWATER
recirculating water
system or sewer
rain water
drainage
Preliminary processing
in factory
Rainwater first
phase
Rainwater
drainage
Oil, grease separation
CENTRALISED EFLUENCE TREATMENT PLANT OF INDUSTRIAL ZONE
Conventional
wastewater
cleaner
15
1.4.3.1. PTWTS of FINETEK Vietnam Co.,Ltd
The plant does not create the WW from production activities, only domestic WW which is
treated by BAST septic tank. The technology procedure of BAST is summarized as follows:
- WW is put to the first tank with function of sedimentation - anaerobic fermentation. In
the next tank, WW moves from bottom to top to expose the anaerobic microorganisms in the
mud at the bottom of the tank in dynamic conditions. The organic contaminants are absorbed
and metabolized by microorganisms as the source of nutrients for their growth. Also
depending on these tanks, the works become a series of anaerobic reactors in series to permit
separating them into two phases (acidic and alkaline fermentation). Microbial populations in
each tank will be different and favorable for development. In the first tanks, the acidic-
forming bacteria predominate while in the next tanks, the base- forming bacteria prevails and
in the following tank, the methanogens are primarily.
- The WW treated by BAST is directly connected to the WW collection system of Hoa
Mac IZ.
1.4.3.2. PTWTS of VINAGLAZE Joint Stock Company
* For domestic WW
WW in the kitchen area: This type of WW often has relatively high content of oil.
Therefore, before connecting to the CETP of Hoa Mac IZ, WW from this area is pipelined to
oil separator system. Operating principle of the oil separation tank: the tank consists of 02 cup
of oil separation and sediment. The WW to the first cup is stored in certain time to deposit
sediment and surface oil scum is put to the 2nd cup where the rest separated oil scum and
mineral oil in the WW are put to the 2nd chute. The WW flows to the second tank, then to the
3- compartment septic tank of the plan for further treatment.
For WW from the toilets in the factories, operation houses, etc, the most appropriate
measures are to locally handle by the 3- compartment septic tanks. Operating principle of the
tanks is sedimentation and anaerobic decomposition. SS-based treatment effectiveness is
about 65 - 70% and BOD5 is about 60 - 65%. Then, WW is led to the system of WW
collection and CETP. Sedimentations are stored in the tanks in 3 – 6 months under the
impacts of anaerobic microorganisms, organic matters are decomposed into CO2, CH4 and
inorganic substances. Sediment at the bottom is used as compost or transferred to the specific
dumpsite for burry and disposal under regulations. WW, after being handling in the 3
compartment septic tanks, will be taken to the CETP of Hoa Mac IZ.
* For production WW
The main elements of WW from washing machinery and equipment (ball mills, compressors
and frame compression process) are TSS so the pollution degree is not so high. The Owner
shall construct the sedimentation tank system to collect and reuse this water source. Below is
the diagram of WW and material collection from washing machinery and equipment and
frame filtration:
Figure 0-5. Production Wastewater Reuse Diagram
Sedimentation
tank 2
Sedimentation
tank 1 Reused Generating source
Sedimentation
collection
Sedimentation
collection
16
The wastewater contains dissolved solids of which the main component is the materials led to
the trash rank system to prevent from coarse particles which are unable to get in the
Sedimentation Tank 1. Then, the WW is further sediment in the Sedimentation Tank (ST) 1
and 2. The WW in the secondary ST is returned to mix with underground water for reuse.
1.4.3.3. PTWTS of NOVAREF Fire Resistant Material Development Joint Stock Company
The plant does not create the WW from production activities, only domestic WW which is
treated by BAST. The technology procedure of BAST is similarly operated to that of Vietnam
FINETEK Co., Ltd (above mentioned).
1.4.3.4. PTWTS of Vietnam Advanced Material Co., Ltd
The plant does not create the WW from production activities, only domestic WW which is
treated by the 3 compartment septic tanks. Its domestic WW treatment model is shown in the
below diagram:
Figure 0-6. Domestic WW treated by 3 Compartment Septic Tank Diagram
The preliminarily treated WW is led to Hoa Mac IZ’s CETP.
1.4.4. Management of Domestic and Industrial Wastes
Domestic waste is mainly leftovers, shredded paper, plastic bags, etc. At present, total
estimated quantity of domestic waste (DW) of entire Hoa Mac IZ is about 900 kg/ day.
The unhazardous industrial waste includes wooden ballets, carton boxes, plastic waste bins
without hazardous ingredients. However, most of them are reused, or recycled,... and sold in
the markets to recover them as much as possible. Therefore, the ratio for disposal is quite low.
The unhazardous industrial waste (which is not reusable or recyclable) from the plants shall
be collected by the IZ’s Management Board in the temporary storage areas in the IZ under the
signed contracts. Then, Hoa Mac IZ Management Co., Ltd hires functional agencies to
transport and treat them under current regulations and laws.
1.4.5. Traffic system
1.4.5.1. External traffic
+) Roadway:
The existing NH38 (scope: B= 10.5 m) is contiguous to the South of Hoa Mac IZ will be the
main external traffic road of the IZ in short term and it shall be expanded B= 53.0 m in future.
The urban roads passing Hoa Mac IZ plays the roles in collection and connection to the main
external road and others, including:
Compartment 1:
- Circulartion
- Sedimentation
- Biodegradation
Compartment 1:
- Sedimentation
- Biodegradation
Compartment 1:
- Circulartion
- Sedimentation
- Biodegradation
Domestic
WW
Hoa Mac IZ’s CETP
Preliminarily treated
domestic WW
17
+ The urban road passing the IZ from the North to the South has the scope B = 45.0 m,
cross-section 1-1 (7m +11.25 +8.5 m + 11.25 m+7 m) = 45.0 m.
+ The urban road along the North boundary of the IZ has the scope B = 33.95 m, section
4-4 (5m +11.25 m + 3 m +14.75 m = 34m)
+ The urban road along the West boundary of the IZ has the scope B = 24.00 m, section
2-2 (2.75 m +11.25 m +5 m +5 m) = 24.00 m
+ Waterway:
Yen Lenh port is located in the East of Hoa Mac IZ, which is about 2.5 km from the IZ on
Red River so it is very convenient for waterway transportation, goods transportation and
development of the IZ.
1.4.5.2. Internal traffic
Principles of network traffic layout: Internal network traffic in the the IZ is organized in the
form of a chessboard, including a main axis throughout the IZ and branches along the land
boundary and roads perpendicular to the main axis to form a convenient closed traffic system.
- ) Construction scale:
Main technical indexes:
+ Road grade: Internal roads of IZ
+ A1 High-class pavement
+ Modulus of elasticity Eyc >= 153 Mpa
+ Standard design load: 100 kN
+ Design speed: 50 km/h
Construction scale: The cross-section of the main road passing the center of the IZ is 1-1 and
road width is 45m, including:
- Pavement: 11.25m x 2
- Central median: 8.5m
- Sidewalk: 7m x 2
The cross-section of branches is 2-2 and the road width is 21.25 m, including
- Pavement: 11.25m
- Sidewalk: 5m x 2
The cross-section of branches is 3-3 and the road width is 25.25 m, including
- Pavement: 11.25m
- Sidewalk: 7m + 7m = 14m.
+ Structure solutions:
Road base:
The road base is filled with sand from Red River. Its compaction K ≥ 0.95. The upper layer
near the pavement is 50 cm thick, filled with hill soil aggregate with K ≥0.98.
The roads surrounding the IZ are filled with hill soil aggregate with K ≥ 0.95. The upper layer
near the pavement is 50 cm thick, filled with hill soil aggregate with K ≥ 0.98.
18
Slope of the roads surrounding the IZ is 1:1.5, which is adjacent to the plots with vertically
designed roof
Slope of the filled base is stabilized to prevent from erosion by use of riprap in the road
sections passing the canal and growing bamboo leaf grass.
Pavement:
Cross- slope of the pavement i = 2%, the collection pit is installed in the two road edges is in
width of 0.25 m and slope of 20%.
Composition of the pavement structure is as follows:
+ Spreading tack coat with the content of 0.5 kg/m2
+ Overlaying 7 cm Asphalt Concrete Binder Course
+ Spreading prime coat with the content of 1 kg/m2
+ 18 cm- Grade I Aggregate Base Course
+ 36 cm- Grade II Aggregate Base Course
+ Compacted 30 cm fine sand K98
+ Compacted fine sand K95
+ Geotechnical textile R = 12 KN/m
Sidewalk:
Sidewalks for pedestrians and underground infrastructures are designed as follows: the
sidewalk part contiguous to the curbs is 3m wide for pedestrians and the rest is for green trees
(in the equal distance of 8 m/ tree) and grass.
Curbs and cover slabs:
Curbs: the design curbs of roads are concrete class 200. Each curb is 1 m long for straight
road sections and 0.25 m for curving ones. Curbs is 230 mm high. They are placed over the
15 cm- lining concrete class 150.
Cover slabs: Cover slabs are designed for the two road sides and the curbs are contiguous to
triangle ditches of which the bottom is stabilized by concrete cover slabs class 200 in
dimensions of 0.25 x 0, 5 x 0,05 m.
+ Traffic safety control:
Place road signs in the intersections under regulations.
Create road markings.
The road signs and road markings have to comply with the current Road Safety and Sign
Code.
1.4.6. Hazardous waste (HW) management
Currently, HZ in entire IZ is about 4 tons / month, which is mainly waste printing ink boxes,
waste lubricating oil, oil rags, fluorescent bulbs, packs with hazardous ingredients, waste
sludge, etc...
These wastes are classified, stored and labeled in accordance with the provisions of the
Circular No. 12/2011/TT-BTNMT, as follows:
- These waste types are classified separately;
19
- The containers must be sealed;
- They must be stored in the shelters with roofs, clear labels warning hazardous
waste, safe operating and storage procedures.
HWs created by the plants are collected, transported and treated under the contracts signed
with the competent authority which is authorized to transport and handle them under current
regulations and laws.
1.4.7. Risk management
The state of emergency related to the environment include: Fire, explosion, spillway, broken
chemical instruments (including oil), electric failure, defects in drainage system, and technical
problem of the CETP.
a) Fire and explosions
+ Preparations
The companies’ fire extinguishing teams are responsible to monthly check all extinguishing
means and instruments and record them into the Minutes of Fire Prevention & Fighting tools.
The fire extinguishing teams shall cooperate with fire police every six months for training.
The fire extinguishing teams self-practices to response to the emergent case every 3 months.
All practice activities must be recorded into the Minutes of Emergence Response Practice.
The fire extinguishing teams shall daily check and test the fire tankers.
+ Response
Response under the fire prevention and fighting plan accepted by fire police.
b) Spillage of chemicals, oil and grease
+ Preparations
The department/departments using chemicals, oil and grease must be equipped with devices
and rags.
The team leader has to annually popularize the knowledge on preparation and emergence
response to the members.
The Company shall make the emergence response plan every six months. All practice
activities must be recorded into the Minutes of Emergence Response Practice
+ Response
The Board of Directors decides to establish the emergency response team. The Office staff are
responsible for the notices, listing notices to keep officers and staff informed.
Anyone who doubts or suspects any chemical/ oil & grease spillage, it is required to
immediately report to the competent authorities in the list of emergence response (ER) teams.
In case of failure in contact to the responsible people, the detectors must report to the
manager.
The (regional) designated competent officers are responsible for reviewing the situation and
immediately issuing the measures. If any incident is not related to chemicals/ oil & grease,
and not impacting the environment and human beings, the competent authorities is entitled to
clean and make no report. If it is actually caused by spillage/ leakage of chemicals/ oil and
grease or impacting the environment or the health, it is immediately required to issue the
solutions and isolate the incident until it is handled.
20
The officer who is in charge of handling the incidents shall make the best efforts in
minimizing or stopping environment pollution or impacts on human’s health.
In case of failure in settlement, the manager (competent officer) in the venue where the
incident happens, it is required to report the situation to IZ Management Unit
If any solution is made but it does not overcome it comprehensively and it may consequently
cause environment pollution or on the human’s health, the team leader must report the IZ
Management Unit or functional authorities for intervention.
c) Power failure
+ Preparation
The company must make a list of organizations leasing generators (full name, address, contact
phone, email, etc). Those are selected correctly under the procedure on supplier evaluation,
selection and management.
The Office is responsible for passing information to the stations upon receiving notice of a
power outage. The Electric Manager is responsible for arranging and contact to the generator
of tenants.
+ Response
If the power outage happens during operation process, the operators are responsible for
communication to the Electric Manager and generator of tenants but it is no more than 6
hours.
The employees have to operate the generators to the treatment system in case of power outage
under instructions of the generator tenants.
d) Problem of the Drainage system
Problem of the drainage system includes: Broken pipelines, spillage of rainwater and water
supply in the drainage system
+) Preparation
The water treatment plant must prepare instruments to readily cover and seal pipelines.
The Company shall make the emergence response plan every six months. All practice
activities must be recorded into the Minutes of Emergence Response Practice.
+) Response
When receiving feedbacks on the problem (from either internal staff, or hygienic team, or
officers or concerned parties such as customers), the Engineering Department/ the ETP must
immediately approach the site with necessary instruments for handling. In case of failure, it is
obligatory to report the Director for solution.
e) Problem of the Treatment System
+) Preparation
The Team Leader must assign personnel to correctly follow the maintenance schedule;
The operators must prepare instruments for such repair;
The Team Leader shall make the list of organizations to readily maintain or repair the system.
+) Response
Any operator/ or anyone in the treatment plant discovers any problem (of the equipment,
components of the treatment system, etc), it is required to immediately notify the person in
21
charge of repairs. The manager in warranty period is responsible for contact to the warranty
institutes.
If the Company’s technicians are unable to restore the incident, the Chief is entitled to instruct
and contact to the repair and warranty organizations.
It is no more than 6 hours since the system is defected.
Notes:
The Team Leader shall evaluate the results of all practice cases and require actions for
learning experience.
After each troubleshoot, the individual/organizational facilitators must ensure to restore it
comprehensively to cause no impact on the environment.
1.5. DESCRIPTION OF THE CETP
1.5.1. Treatmnet Technology, Influent and Effluent Characteristics
1.5.1.1. Technology of the CETP
Treatment processes of the SBR technology-based CETP consist of the followings:
- Influent contains many large dregs, sand, etc which are removed before reaching the oil
separator tank. This design helps protect the equipment in the CETP.
- Composition of lipid, oils and mineral oil will be removed by oil separator tank to avoid
impacting on the physic-chemical and biological treatment works.
- The group of physic-chemical treatment tanks is designed to remove some heavy
metals, SS in the WW to help stabilize the biological treatment process if influent has varied
pollutant concentration.
- The aerobic biological tank is designed to resolve organic matters. The aerobic bacteria
(activated sludge) will make the process of organic matter decomposing (they are mainly
dissolved organic matters). Oxygen is supplied to the tank through the air blowers to create a
favorable environment for the growth of aerobic bacteria, promoting the decomposition of
organic matters. Circulated sludge flows from the secondary sedimentation tank to anoxic
tank to maintain microorganism content in this tank in appropriate limit.
- Sludge reservoir is designed to reduce the volume and moisture of sludge from 99 % to
96 %. Then, this sludge is pumped through sludge compressor to dewater before being
discharged hygienically.
1.5.1.2. Influent and Effluent Standards
Table 0-2. Concentration of pollutants in influent of CETP
N
o Parameter Unit
Influent stream values
demanded
Safety
coefficient Designed values
1 pH - 5.5-9 1 5.5-9
2 BOD5 (20oC) mg/l 50 6 300
3 COD mg/l 150 3 450
4 TSS mg/l 100 3 300
5 Total N mg/l 60 1 60
6 Total P mg/l 10 1 10
7 Others - QCVN 40:2011/BTNMT
(column B) 1
QCVN 40:2011/BTNMT
(Column B)
22
Quality of influent of CETP must meet the standards in Column B, the Regulation QCVN
40:2011/BTNMT. Details are as follows:
Effluent quality of CETP: WW after treating are meeting the national discharge standard
QCVN 40:2011/BTNMT, column A, Kq = 0.9, Kf = 1.0
1.5.2. Charecteristic of the CETP and discharge outlet
1.5.2.1. WW Characteristics
(1). Types of WW to be treated
Hoa Mac IZ is determined as a multidisciplinary IZ, manufacturing sector is less hazardous
pollution. Orientations of the main industries are as follows:
- The agricultural products and foodstuffs processing industry.
- The garment industry.
- High-class consumer goods producing industry.
- The industry of mechanics, assembly, electronics.
Tenants in Hoa Mac IZ are required to have advanced technology Preliminary Treatment
Wastewater Treatment System under the State’s Regulations, and use of local material supply
and workforce.
With the above mentioned characteristics of the industries in Hoa Mac IZ, compositions of
influent of CETP are mainly from production and business process of the plants in the IZ. In
addition, there is WW from services in the region and domestic WW of officers and staff, etc.
(2). Influent Characteristics
It is recognized that if each tenant has unavailable WW management and treatment measures
before discharge into the general drainage system of the IZ, contents of the pollutants in WW
are large. Concentration of large volume of WW for in-place treatment is ineffective because
the expense of such plant and operation cost are so high and it is very difficult to call
investors. Also it is easy to cause risks of water environment pollution. Therefore, WW from
plants and factories before being discharged into the general drainage system and CETP, must
be preliminarily treated to reach the standards column B, QCVN 40:2011/BTNMT.
(3). Effluent Characteristics
Quality of effluent of the treatment system: The treated WW must meet the standards in
Column A, the Regulation QCVN 40: 2011/BTNMT, responding to Kq=0.9; Kf=1.0.
Table 0-3. The quality of treated WW meeting QCVN 40:2011, column A
No Parameter Unit QCVN40:2011/BTNMT, Column A
1 Temperature 0C 40
2 pH - 6 – 9
3 COD mg/l 75
4 BOD5 mg/l 30
5 SS mg/l 50
6 Total N mg/l 20
7 Total P mg/l 4
8 Color Pt-Co 50
9 Fe mg/l 1
23
No Parameter Unit QCVN40:2011/BTNMT, Column A
10 Pb mg/l 0.1
11 Mn mg/l 0.5
12 As mg/l 0.05
13 Hg mg/l 0.005
14 Coliform MNP/100ml 3000
(4). Anticipated WW flow to CETP
Currently, WW flow in entire Hoa Mac IZ is quite low, about 81.8 m3/day. It is planned to
call for more investors in construction of the CETP. In addition, the existing companies which
have completed the basic construction and be put in stable operations, their WW flow in the
future is anticipated and shown in below table:
Table 0-4. WW flow forecast of facilities after complete construction and stable operation
(expected to attract more tenants until the end of 2014)
No Tenants
Rented
area
(ha)
Demand of
using clean
water (m3/day)
Effluent
(m3/day)
1 Vinaglaze Co.,Ltd 0.8021 86.8 69.4
2 NOVAREF JSC., 1.0 12.9 10.32
3 Advanced material Vietnam Co.,Ltd 2.196 240 192.0
4 Hanoi Battery JSC., 2.9379 150 120.0
5 KEYRIN Telecom Vietnam Company 1.5 170 136.0
6 FineTech Company 1.5178 170 136.0
7 PVC-ME1 Company 3.0 50 40.0
8 Hanam International Agriculture Co.,Ltd 2.0 45 36.0
9 Vina Hanam Animal Feed Company 4.0 65 52.0
10 Expected attracting investment is 12 ha at
the end of 2012 12.0 660
528.0
Total 30.9538 1,649.7 1,319.7
(5). Evaluation of WW quality
The above mentioned criteria of influent and effluent show that: Influent secures to facilitate
the treatment plant to be operated the most effectively to contribute to maintaining the
stability and quality of treated effluent under the applied standards.
1.5.2.2. Characteristics of CETP
(1). Description of the WW collection system and drainage system
Collection culverts: The design culvert pipelines are reinforce concrete (RC) pipeline M300
with the diameter of 300-600 mm. The culvert pipe is centrifugal with the length of 2 m in
each culvert segment. The culvert segments are connected by jute and asphalt, covered with
pure cement mortar.
Apron is the fixed design with RC M200 over the 10 cm compacted sand.
Each 3 m culvert segment uses 03 aprons with the minimal burry depth of 50 cm to the
culvert top.
Manholes: The design manhole is RC M200 over the 10 cm compacted sand. The cover is 10
cm RC M200 slabs.
24
The treated WW will be discharged via RC culvert system to approach the bio-pond, then to
the open ditch in the IZ in the length of 1,500 mm before draining to Giat River.
(2). Treatment technology
The WW treatment technology is described in detail via the following diagram:
Figure 0-7. Diagram of WW treatment technology of Hoa Mac IZ
Wastewater
Pump pit
Oil separation tank
Equalization tank
Coagulation tank
Flocculation tank
Primary sedimentation tank
pH buffer tank
Selector A tank
SBR A tank
Selector B tank
SBR B tank
Disinfection tank
Bio-pond
Sludge tank
Sludge compressor
Fine Screen
Submersible agitator
NaOH
Aluminum
H2SO4
Polymer
NaOH
H2SO4
Floating scum
Sludge
Wastewate
r
Residual
sludge
NaOCl
Discharge Dewater Sludge
Polymer
Slu
dg
e c
ircu
lati
on
25
Technology description:
a) Pump pit
All the effluents from the plants are drained to the pump pits of CETP. Before discharging to
the pump pit, WW is led to the raw trash rack system (10 mm) to remove waste or materials
in the form of large fiber to protect the following works. The pump pits are divided into 02
compartments. As the WW is piped to the pump pit, sand is retained in the first compartment.
The sand volume is periodically suck hygienic by sludge digestion plants (SDP). The WW to
the second compartment is pumped to separate oil and grease.
b) Oil Separator Tank (OST)
Before getting in the OST, WW is led to the fine screen to remove the sediment particles in
sizes of over 2 mm. Most of the WW after sediment separation automatically flows into the
oil scum separator tank (OSST) to remove oil, grease, and SS smaller than the WW density,
then flows to the equalization tank.
c) Equalization tank
Equalization tank functions to circulate the flow and concentration of pollutants in WW. The
sunk stirrer is installed in the tank to minimize sedimentation sludge process. Then, WW is
pumped to coagulation tank.
d) The coagulation tank
At the coagulation tank, WW is mixed with coagulation chemicals which are lit from
chemical reservoir via metering pump. Coagulation substances help stabilize colloidal
particles and stimulate them to combine with the other suspended solids to form larger
particles. At the same time, pH of the WW in coagulation tank is adjusted to the optimum
value for the colloidal process.
e) Flocculation tank
WW from the coagulation tank is led through the flocculation tank. Like coagulation tank, at
flocculation tank, anionic polymer will be lit in order to stimulate the formation of larger
cotton residue. This polymer is able to form the bridge to connect these cotton residues to
constitute larger cotton residues to improve the efficiency of the following sedimentation
tanks. WW from flocculation tank is directed to the primary sedimentation tank to separate
the cotton from sewage sludge.
f ) Primary sedimentation tanks
In the primary sedimentation tank, the sediment solids in WW is settled down by gravity
method. The primary sedimentation tank can help eliminate 60% of SS and a part of BOD in
the organic sediment particles. Sediment sludge at the bottom of the primary sedimentation
tank is transferred to the sludge reservoir with sludge rods and pumped through the sludge
reservoir. The oil scum is floating on the scum tank before being pumped into the sludge
reservoir. After the deposition, the WW flows into the Selector Tank.
g ) SBR Tank
From Selector tank, WW flows to Sequence Batch Reactor Tank (SBR Tank) which is
upgraded from classical activated sludge system of which processes (phases) are treated as
follows: filling, reaction, sediment, and drainage in one tank in certain time in each process.
SBR Tank’s operation process is summarized as follows:
26
Filling T = 2 hours
Discharge T = 1 hours
Sediment discharge
Sediment T = 45 minutes
Reactor T = 2 hours 15
minutes
Disorder
Aerobic
In the filling phase, WW is put into a tank with available certain amount of microorganisms
(sludge). For this phase, the initial decomposition process of organic matter occurs when
microorganisms are exposed to WW. After finishing the filling phase, the process continues
with reaction phase in which WW is mixed with microorganisms by surface air blower. Gas is
provided to the tank to conduct the full decomposition of organic matters. The reaction phase
is followed by sediment to separate microorganisms (sludge) from treated WW.
After finishing the sediment phase, treated WW is removed from the tank by activated
drainage phase and filling phase to carry out the new processing cycle. Discharge process of
residual microorganisms (sludge) in an SBR tank can be carried out as a separate phase or
added in the drainage phase.
h ) Disinfection tank
At the disinfection tank, WW is mixed with disinfectant provided by metering pump system
to destroy bacteria and coliform and other pathogenic microorganisms. The disinfection tank
is designed to create the best mixing between WW and disinfectants. The treated WW is
discharged into the receiving source.
i ) Bio - pond
Bio-pond is known as a pond of oxidation and stabilized WW for treating WW by bio
measures which mainly depends on the self-cleaning process of the pond. In addition to the
effects of stable treatment for WW, it functions to circulate the flow and WW quality before
discharging into the receiving source.
1.5.2.3. Discharge characteristic
(1). Characteristic of discharge systems
WW after treating that meets the National Technical Regulation flows to the bio-pond of IZ,
then to the open ditch via underground culvert before draining to Giat River via F600 culvert
with bottom reinforcement of +2.5 m. The open internal canal is 1500 m long and 7 m wide.
27
(2). Discharge method
Discharge upon the slope of the terrain from the bio-pond to the internal ditch in IZ, then to
Giat river and Chau Giang river.
(3). Discharge mode
As the project of “Construction CETP with capacity of 1,500 m3/day at Hoa Mac IZ, Phase I,
module 1” is completed, WW flow may increase by 1,319.7 m3/day & night. Therefore, it is
operated in 24/24 h as it is exploited officially.
(4). Discharge flow
Maximal discharge: 1,320 m3/day;
Minimal discharge: 250 m3/ day;
Average discharge flow: 860 m3/ day.
1.5.3. Sludge treatment technology
Excess sludge from the primary sedimentation tank and SBR tank will be pumped into the
sludge tank for storage before being pumped to the sludge compressor. Sludge tank is covered
to prevent odor pollution to the surrounding environment.
Sludge dewatering conveyor is used to separate water from the sludge. For this process, the
polymer will be lit as an auxiliary substances in the process of dewatering from the sludge.
After dewatering sludge in cake form will be stored in temporary sludge storage area. Water
separated from the sludge dewatering process will be recycled at the pump pit.
The Investor signed the Contract with URENCO 11 to transport and treat hazardous sludge
under the State’s current regulations (attached the Contract).
1.5.4. Total investments and implementation progress
a) Total investment
Total investment: VND 21,630,394,539
Capital structure:
- Loan from Vietnam Environment Protection Fund (VEPF) (75% total
investment) : VND 16,222,500,000
- Owned fund (25% total investmnet) : VND 5,407,394,539
Table 0-5. Table of total investment
No Items IDA loan
(VND)
Counterpart
fund (VND) Total (VND)
1 Preparing investment 500,000,000 500,000,000
2 Construction 5,500,000,000 1,500,000,000 7,500,000,000
3 Equipment 6,500,000,000 1,500,000,000 8,000,000,000
4 Initial working capital 130,000,000 130,000,000
5 Others 80,000,000 500,394,539 580,394,539
6 Completment,
transfering to use 60,000,000 250,000,000 310,000,000
7 Provision for expenses 3,082,500,000 1,527,500,000 4,610,000,000
Total 16,222,500,000 5,407,894,539 21,630,394,539
28
b) Implementation Progress
- Infrastructure construction: 5 months;
- Installation of equipment, technology pipeline systems: 3 months;
- Pilot run: 2 months;
- Technology transfer, acceptance and handover: 1 month.
1.6. ENVIRONMENTAL LEGISLATION AND GUIDELINES
1.6.1. World Bank Policy on Environmental Assessment
The environmental and social screening according to the criteria described in the Bank’s
policy on environmental assessment has been carried out, and the result shows that the WB
policies on Environmental Assessment (OP 4.01). The screening has also resulted in
categorizing the subproject as a Category B subproject due to it moderate impacts associated
with the construction and operation of the CETP. In addition, the Bank’s requirements on
public consultation and information disclosure will need to be followed.
Environmental Assessment (OP/BP 4.01):
Environmental Assessment (EA) is an umbrella policy for the Bank’s safeguard policies. The
overarching objective is to ensure that Bank-financed projects are environmentally sound and
sustainable, and that decision-making is improved through appropriate analysis of actions and
of their likely environmental impacts. The EA process is intended to identify, avoid and
mitigate potential impacts of Bank operations. EA takes into account the natural environment
(air, water, and land); human health and safety; social aspects (involuntary resettlement,
indigenous peoples, and physical cultural resources); and transboundary and global
environmental aspects. EA considers natural and social aspects in an integrated way.
This subproject triggers OP 4.01 because it involves the construction and operation of the
CETP, resulting in potential adverse environmental and social impacts that require
appropriate mitigation measures. As required by OP 4.01 and the government EA regulation,
the subproject has prepared an EIA with an associated EMP that meet the Government’s and
the World Bank’s safeguards requirements. By the subproject appraisal, the subproject EIA
and has been disclosed locally at the subproject site and at the Bank’s InfoShop, and the
Vietnam Development Information Center.
World Bank Group Environmental, Health, and Safety Guidelines
This subproject should conform to the World Bank Group Environmental, Health, and Safety
Guidelines1 (known as the "EHS Guidelines"). The EHS Guidelines are technical reference
documents with general and industry-specific examples of Good International Industry
Practice.
The EHS Guidelines contain the performance levels and measures that are normally
acceptable to the World Bank Group and are generally considered to be achievable in new
facilities at reasonable costs by existing technology. The environmental assessment process
may recommend alternative (higher or lower) levels or measures, which, if acceptable to the
World Bank, become project- or site-specific requirements.
1.6.2. Vietnamese Policy on Environmental Assessment
(1) National Environmental Legislation
1The EHS Guidelines can be consulted at www.ifc.org/ifcext/enviro.nsf/Content/EnvironmentalGuidelines.
29
- Construction Law issued by the National Assembly of the Socialist Republic of Vietnam on
26 November 2003;
- Fire Prevention and Fire Code issued by the National Assembly of the Socialist Republic of
Vietnam on 29 June 2001;
- Investment Law issued by the National Assembly of the Socialist Republic of Vietnam on
29 November 2005;
- Law on Environmental Protection issued by the National Assembly of Vietnam on 29
November 2005;
- Law on Chemicals issued by the National Assembly of the Socialist Republic of Vietnam on
21 November 2007;
- Law on Biodiversity issued by National Assembly of the Socialist Republic of Vietnam on
13 November 2008;
- Urban Planning Act issued by the National Assembly of the Socialist Republic of Vietnam
on June 17, 2009;
- Law on Water Resources issued by the National Assembly of Socialist Republic of Vietnam
on June 21, 2012.
- Decree No.59/2007/NDTTg dated 09 April 2007 issued by the Prime Minister on the solid
waste management.
- Decree No.29/2008/NDCP dated 14 March 2008 issued by the Government on industrial
zones, export processing zones and economic zones;
- Decree No.29/2011/NDCP dated 18 April 2011 issued by the Government on strategic
environmental assessment, environmental impact assessment, and environmental protection
commitments;
- Decision No.53/2004/QDTTg dated 08 April 2004 issued by the Prime Minister
promulgating the strategic orientation for sustainable development in Vietnam (Agenda 21);
- Decision No.81/2006/QDTTg dated 14 April 2006 issued by the Prime Minister on
approving the "National Strategy of environmental protection until 2010 with a vision to 2020
(NSEP)";
- Document No. 2003/TTg-CP by Prime Minister on the "Agreement of investment policy
Hoa Mac Industrial Park, Hanam province with an area of 203 ha and implementing this IP to
the list of priority industrial park that expected to new set in 2015 by Decision No.1107/QD-
TTG dated 21 August 2006 by the Prime Minister ".
- Decision No. 27/2004/QDBXD on 09 November 2004 issued by the Ministry of
Construction on approval TCXDVN 320 2004 "Hazardous waste landfill - Design Standards";
30
- Decision No.21/2005/QDBXD dated 22 July 2005 issued by Ministry of Construction on
promulgating regulations on the notation system drawings in the construction plans.
- Circular No.19/2008/TTBXD dated 20 November 2008 issued by the Ministry of
Construction on "guiding the formulation, appraisal, approval and management of
construction plan of the industrial zones and economic zones."
- Circular No.08/2009/TTBTNMT dated 15 July 2009 issued by the Ministry of Natural
Resources and Environment on environmental protection regulations of economic zones,
high-tech parks, the industrial zones and industrial clusters ;
- Circular No.01/2011/TTBXD dated 27 January 2011 issued by the Ministry of Construction
guiding the strategic environmental assessment;
- Circular No.26/2011/TTBTNMT dated 18 July 2011 issued by the Ministry of Natural
Resources and Environment on detailing a number of articles of Decree No. 29/2011/NDCP
of the Government on the strategic environmental assessment, environmental impact
assessment, environmental protection commitment.
- Circular No.04/2011/TTBTNMT dated 28 December 2011 issued by the Ministry of Natural
Resources and Environment on amending and supplementing some articles of
(2) Local Environmental Legislations
- Document No. 250/UBND-DN&XTDT dated 8 March 2007 by People’s Committees of
Hanam province on approving the policy "Investor and business building Hoa Mac Industrial
Zone Infrastructure of Hoa Phat construction and Urban Development Jsc ".
- Decision No. 232/QD-UBND dated 30 January 2008 by People’s Committees of Hanam
Province on approving "Detailed planning ratio of 1/500 Hoa Mac Industrial Park (Phase I),
Duy Tien district, Ha Nam province ".
- Decision No.1173/QD-UBND dated 19 September 2008 by People’s Committees of Hanam
Province on approving adjustments "Detailed planning ratio of 1/500 Hoa Mac Industrial
Park (Phase I), Duy Tien district, Hanam province".
- Decision No.878/QD-UBND dated 24 July 2008 by Peolple’s Committees Hanam Province
on "Land Acquisition and temporarily assigned to Hoa Mac Industrial Zone Devepment
Management Co.,Ltd for clearance of the service investment and business building
infrastructure Hoa Mac industrial Park - phase I, in Duy Tien district, Ha Nam province".
- Decision No.1805/QD-UBND dated 29 December 2009 by People’s Committees of Hanam
Province on "Land Acquisition assigned to Hoa Mac Industrial Zone Devepment
Management Co.,Ltd for clearance of the service investment and business building
infrastructure Hoa Mac industrial Park - phase I, in Duy Tien district, Ha Nam province".
31
- Decision No.1094/QD-UBND dated 01 September 2008 by People’s Committees of Hanam
province on "Approving report of environmental impact assessment of investment project and
business building industrial infrastructure Hoa Mac in Duy Tien district, Ha Nam province".
- Decision No.942/QD-UBND dated 11 August 2009 of People’s Committees of Hanam
Province on "Establishment of Hoa Mac Industrial Zone, Hanam Province".
- Delivery record of land in 5 May 2010 at Hoa Mac town and 8 September 2010 at Chau
Giang commune.
(3) Documents related to Component No 2 of the project of industrial pollution management
in the Dong Nai, Nhue Day river basins
- Decision No.1932/QD-BTNMT on 12 November 2012 on approving component No 2 -
Pilot investment loan to build the central wastewater treatment plants in industrial zones of
the project "Industrial Pollution Management in the Dong Nai, Nhue-Day river basins";
- Decision No.1953/QDBTNMT on 14 November 2012 on establishment of the Project
Management Board of Component No 2 - Pilot investment loan to build the central
wastewater treatment plants in the industrial zones of the project "Industrial Pollution
Management of Dong Nai, Nhue-Day river basins";
- Decision No.1196/QDBKHDT on 17 September 2012 of the Minister of Planning and
Investment on approving the feasibility study report on the project “Industrial Pollution
Management of the Dong Nai, Nhue-Day river basins”;
- Decision No.1403/QDBKHDT on 25 October 2012 on amending and supplementing a
number of articles of Decision No. 1196/QDBKHDT;
- Decision No.1205/QDBKHDT on 19 September 2012 on establishment of the Project
Steering Committee for the project “Industrial Pollution Management in the Dong Nai, Nhue-
Day river basins”
- Official Letter No. 13606/BTCQLN on 5 October 2012 on specific lending conditions for
the WB Project “Industrial Pollution Management”.
- Loan Agreement (VIPM Project) between the Socialist Republic of Vietnam and the
International Development Association on 24 September 2012 (No. 5175VN).
- Environment and Social Management Framework, The project “Industrial Pollution
Management in the Dong Nai, Nhue-Day river basins, 2012.
1.6.3. The environmental standards and regulaions
(1).Water Quality
- QCVN 08:2008/BTNMT - National technical regulation on surface water quality;
- QCVN 09:2008/BTNMT- National technical regulations on groundwater quality;
32
- QCVN 14:2008/BTNMT - National technical regulation on domestic wastewater quality;
- QCVN 40:2011/BTNMT- National technical regulations on industrial waste water;
(2). Air Quality
- QCVN 05:2008/BTNMT - Air Quality - National technical regulations on ambient air
quality ;
- QCVN 06:2008/BTNMT - Air quality - Allowable maximum concentration of toxic
substances in the ambient air.
(2).Soil Quality
QCVN 03:2008/BTNMT - National technical regulation on the permissible limits of heavy
metals in the soil;
(3).Solid Waste Management
- TCVN 6696:2009 - Solid waste – Sanitary Landfill- General requirements for the protection
of the environment;
- QCVN 07:2009/BTNMT - The national regulation on classification of hazardous waste;
- QCVN 25:2009/BTNMT - National technical regulation on wastewater leakage from solid
waste landfills;
(4).Noise and vibration
- QCVN 26:2010/BTNMT - National technical regulation on noise;
- QCVN 27:2010/BTNMT - National technical regulation on vibration.
(5).Safety and Occupational Health
Decision No 3733/2002/QD-BYT on 10 October 2002 about applications of 21 standards for
safety and health.
33
CHAPTER 2 CHARACTERISTICS OF THE PROJECT AREA
2.1. GENERAL CHARACTERISTICS OF THE PROJECT AREA
2.1.1. Natural characteristics
2.1.1.1. Topography, geology, climate
(1). Topography
Most of the site in Hoa Mac IZ is cultivated fields of the residents in the area. The terrain is
relatively flat. The area for sunken ponds and irrigation ditches for entire surrounding rice
fields is not large in the average height of +2.3 m. The terrain tends to slope from east to west.
Generally, ground level is relatively low so it is required to elevate the ground during the
construction process on basis of the height of NH38, from +3.8 m to +4.0 m.
(2). Geology
According to result of geological survey of work “CETP with capacity of 1,500 m3/day at
Hoa Mac IZ, Phase I, module 1”, the geology of the project site is as follows:
+ ) Layer 1: Gray-brown Clay
Layer 1 in all 3 drilled holes with the following depth and thickness:
Table 2-1. The depth and thickness of first layer at the drill-hole
Drill-hole number Depth distribution
Layer thickness (m) Layer top Layer bottom
LK1 0.0 0.6 0.6
LK2 0.0 1.2 1.2
LK3 0.0 0.9 0.9
In terms of geology, this layer is not meaningful so it is not required to sample during the
survey process.
+ ) Layer 2: Gray-brown, ash gray clay mud
The layer 2 is under the layer 1 in all 3 drilled holes with the depth and thickness are as
follows:
Table 2-2. The depth and thickness of second layer at the drill-hole
Drill-hole number Depth distribution Layer thickness
(m) Layer top Layer bottom
LK1 0.6 7.5 6.9
LK2 1.2 6.2 5.0
LK3 0.9 9.7 8.8
Average physical and mechanical characteristics are as follows:
Table 2-3. Synthetic table of mechanical and physical target of the second layer
No Target Symbol Unit Standard value
1 Particle
composition
(mm)
0.5 - 0.25
P %
-
0.25 - 0.1 1.0
0.1 - 0.05 30.3
0.05 - 0.01 30.3
0.01 - 0.005 14.3
< 0.005 24.0
34
2 Specific weight ∆ g/cm3 2.68
3 Natural humidity W0 % 54.6
4 Natural volume mass γW g/cm3 1.61
5 Dry volume mass γc g/cm3 1.045
6 Flow limit WL % 48.1
7 Soft limit Wp % 32.0
8 Soft index IS % 16.1
9 Thickness Ip % 1.40
10 Saturation G % 93.2
11 Porosity n % 61.0
12 Porous coefficient εo 1.567
13 Internal friction angle ϕ degree 3028
14 Cohesion C kG/cm2 0.088
15 Coefficient of compression and
subsidence
a1-2 cm2/kG 0.115
16 Total deformation modulus E1-2 kG/cm2 17
17 Convention capacity load RH kG/cm2 0.41
18 Average number of hammer
SPT/30cm
N 4
+ ) Layer 3: Ash gray, dark gray sandy sludge, interleaved clays, sometimes mixed with
organic matters.
The layer 3 is under the layer 2 in all 3 drilled holes with the depth and thickness are as
follows:
Table 2-4. The depth and thickness of third layer at the drill-hole
Drill-hole number Depth distribution
Layer thickness (m) Top Layer Bottom Layer
LK1 7.5 15.0 7.5
LK2 6.2 17.3 11.1
LK3 9.7 18.5 8.8
Average physical and mechanical characteristics are as follows:
Table 2-5. Synthetic table of mechanical and physical target of the third layer
No Target Symbol Unit Standard value
1 Particle
composition
(mm)
0.5 - 0.25
P
%
1.0
0.25 - 0.1 16.7
0.1 - 0.05 35.0
0.05 - 0.01 26.0
0.01 - 0.005 11.0
< 0.005 9.3
2 Specific weight ∆ g/cm3 2.67
3 Natural humidity W0 % 46.0
4 Natural volume mass γW g/cm3 1.67
5 Dry volume mass γc g/cm3 1.147
6 Flow limit WL % 39.7
7 Soft limit Wp % 31.4
8 Soft index IS % 8.3
35
9 Thickness Ip % 1.75
10 Saturation G % 92.4
11 Porosity n % 57.0
12 Porous coefficient εo 1.328
13 Internal friction angle ϕ degree 8040
14 Cohesion C kG/cm2 0.132
15 Coefficient of compression and
subsidence
a1-2 cm2/kG 0.094
16 Total deformation modulus E1-2 kG/cm2 25
17 Convention capacity load RH kG/cm2 0.66
18 Average number of hammer
SPT/30cm
N 5
+ ) Layer 4: Gray-brown clay mud, ash gray, sometimes mixed with organic matters
The layer 4 is under the layer 3 in all 3 drilled holes with the depth and thickness are as
follows:
Table 2-6. The depth and thickness of fourth layer at the drill-hole
Drill-hole number Depth distribution
Layer thickness (m) Top Layer Bottom Layer
LK1 15.0 29.5 14.5
LK2 17.3 29.2 11.9
LK3 18.5 31.8 13.3
Average physical and mechanical characteristics are as follows:
Table 2-7. Synthetic table of mechanical and physical target of the fourth layer
No Target Symbol Unit Standard value
1 Particle
composition
(mm)
0.5 - 0.25
P
%
-
0.25 - 0.1 0.5
0.1 - 0.05 30.0
0.05 - 0.01 37.3
0.01 - 0.005 12.2
< 0.005 20.0
2 Specific weight ∆ g/cm3 2.69
3 Natural humidity W0 % 46.0
4 Natural volume mass γW g/cm3 1.66
5 Dry volume mass γc g/cm3 1.136
6 Flow limit WL % 40.0
7 Soft limit Wp % 24.4
8 Soft index IS % 15.6
9 Thickness Ip % 1.38
10 Saturation G % 90.1
11 Porosity n % 57.7
12 Porous coefficient εo 1.369
13 Internal friction angle ϕ degree 4039
14 Cohesion C kG/cm2 0.125
15 Coefficient of compression and
subsidence
a1-2 cm2/kG
0.093
36
16 Total deformation modulus E1-2 kG/cm2 19
17 Convention capacity load RH kG/cm2 0.54
18 Average number of hammer
SPT/30cm
N 6
+ ) Layer 5: Gray yellow, gray hard plastic clay
The layer 5 is under the layer 4 in all 3 drilled holes. The thickness is not identified because
the surveyed holes end at the depth of this layer.
Physical and mechanical average of the strata as follows :
Table 2-8. Synthetic table of mechanical and physical target of the fifth layer
No Target Symbol Unit Standard value
1 Particle
composition
(mm)
0.5 - 0.25
P
%
-
0.25 - 0.1 7.0
0.1 - 0.05 32.3
0.05 - 0.01 25.7
0.01 - 0.005 15.7
< 0.005 19.3
2 Specific weight ∆ g/cm3 2.70
3 Natural humidity W0 % 21.9
4 Natural volume mass γW g/cm3 1.91
5 Dry volume mass γc g/cm3 1.570
6 Flow limit WL % 30.1
7 Soft limit Wp % 14.9
8 Soft index IS % 15.3
9 Thickness Ip % 0.46
10 Saturation G % 82.0
11 Porosity n % 41.9
12 Porous coefficient εo 0.722
13 Internal friction angle ϕ degree 15052
14 Cohesion C kG/cm2 0.231
15 Coefficient of compression and
subsidence
a1-2 cm2/kG 0.041
16 Total deformation modulus E1-2 kG/cm2 83
17 Convention capacity load RH kG/cm2 1.27
18 Average number of hammer
SPT/30cm
N 16
Survey results showed that the geological conditions of the area is complex. There are 05
layers with different thickness, area and physical properties in the scope of the survey.
- Layer 1: Gray brown landfilling. So it is noted in design and construction.
- Layer 2: Gray-brown, ash gray clay mud appears in all holes RH= 0.41 kG/cm2, E1-2= 17
kG/cm2.
- Layer 3: Ash gray, dark gray sandy sludge, interleaved clays, sometimes mixed with
organic matters. This strata appears in all holes RH= 0.66 kG/cm2, E1-2= 25 kG/cm
2..
37
- Layer 4: Gray-brown clay mud, ash gray, sometimes mixed with organic matters. This
strata appears in all holes RH= 0.54 kG/cm2, E1-2= 19 kG/cm
2..
- Layer 5: Gray yellow, gray hard plastic clay. This strata appears in all holes RH= 1.27
kG/cm2, E1-2= 83 kG/cm
2.
Conclusions:
Hoa Mac IZ’s CETP may be placed on layer 5. However, it is required to stabilize the
foundation by prestressed concrete piles and application of suitable base countermeasures to
ensure quality work and achieve economic efficiency (these technical requirements are shown
in the Contract between the Investor and the Construction Contractor).
(3). Climate
The project site in particular and Ha Nam province in general have the tropical monsoon
climate with two main wind directions: Northeast and Southeast, 4 seasons with 4 types of
weather: Warm spring, hot summer, cool autumn and cold winter.
* Temperature
The average temperature in recent years changes insignificantly, from 23.2 to 24.55 . The
average temperature is shown in the following table :
Table 2-9. Average temperature in months and years (0C)
No Month
Year 2007 2008 2009 2010 2011 2012
1 January 16.5 14.9 15.5 17.7 16.8 17.1
2 February 21.3 13.2 22 21.5 20.8 20.5
3 March 20.9 20.6 20.6 21.6 21.2 20.8
4 April 22.8 24.2 24 13 22.1 23.2
5 May 26.4 26.8 26.4 28.5 27.2 27.8
6 June 29.8 28 30.2 30.6 29.5 28.9
7 July 29.9 29.2 29.4 30.3 29.8 29.5
8 August 28.5 28.5 29.3 27.8 28.9 28.4
9 September 26.6 27.5 28.3 28 27.8 28.1
10 October 24.5 26 26 24.9 24.2 26.1
11 November 20.7 21.3 21.3 21.8 23.5 23.2
12 December 20.1 17.9 19.2 19.3 17.2 18.9
Average 24.0 23.2 24.35 24.55 24.09 24.38
(Source: Statistical Yearbook of Hanam Province in 2012)
* Sunlight and radiation
Total minimal and maximal hours of sunshine at Ha Nam province in 2009 and 2010
were 1.146 hours and 1.426 hours, respectively. The sunshine hours in summer make up 82%
of that in the whole year and the months with the largest sunny hours are May, June, July,
August, September, November.
Solar radiation is an important factor directly affecting the thermal regime in the region,
affecting the dispersion and transformation of pollutants. Average daily radiation layer in Ha
Nam province is 100-120 Kcal/cm2. The months with the highest radiation is in summer (June
, August and September) and the lowest radiation in winter months.
38
Table 2-10. The hour number of sunshine in months
No Month
Year 2007 2008 2009 2010 2011 2012
1 January 63 64 96.4 33 11.1 1.9
2 February 46 27 79.0 90.6 37.3 17.9
3 March 9 58 44.1 59 16.8 20.5
4 April 83 71 77.2 58.6 61.2 105
5 May 146 155 117.6 139.1 159.7 167.2
6 June 232 101 183.9 170.8 151.2 110.8
7 July 234 128 153.7 211.0 170.4 168.2
8 August 126 126 204.2 123.9 177.9 168.5
9 September 126 110 138.6 142.5 109.4 129.4
10 October 89 75 115.4 116.1 65.4 113.1
11 November 91 128 138.7 91.7 98.3 105.6
12 December 32 103 77.8 93.1 73.6 45.7
Total 1277 1146 1426.6 1329.4 1132.3 1153.8
(Source: Statistical Yearbook of Hanam Province in 2012)
* Rainfall
The total average rainfall in 2012 is about 1.768 mm/year. It is divided into two distinct
seasons, wet and dry seasons. The wet season from May to October accounts for about 80 %
of the annual rainfall, which is concentrated in May, June, July, August, September, October
and November and the dry season from November to the following April. The average
rainfall is shown in the following table :
Table 2-11. Average volume of rainfall in months and years (mm)
No Month
Year 2007 2008 2009 2010 2011 2012
1 January 1.6 37 10.3 106.4 13.3 39.9
2 February 59.6 14 9.9 8.7 27.9 29.5
3 March 47.9 23 55.5 17.4 95.8 24.3
4 April 51.7 34 88.0 59.9 52.4 60.9
5 May 329.5 260 347.4 176.9 192.8 200.5
6 June 53.0 372 86.5 213.7 325.2 126.3
7 July 269.3 231 509.5 334.2 223.6 253.7
8 August 228.9 271 115.1 429.5 291.7 251
9 September 231.8 352 285.5 209.7 405.9 382.9
10 October 285.4 323 91.1 136.8 135.4 145.6
11 November 11.6 199 6.7 9.9 70.0 182.9
12 December 11.8 22 32.1 59.0 12.7 71.5
Total 1582.1 2138 1637.6 1762.1 1846.7 1768.8
(Source: Statistical Yearbook of Hanam Province in 2012)
* Humidity
In general, annual average air moisture in Ha Nam province is relatively large, ranging
from 81.3 to 83.5 %, depending on rainfall so there are 2 periods in one year: The period with
high humidity and that with low humidity. The average humidity is shown in the following
table:
39
Table 2-12. The average humidity in months and years (%)
No Month
Year 2007 2008 2009 2010 2011 2012
1 January 72 85 76 84 78 79
2 February 87 77 88 83 85 82
3 March 92 86 87 82 84 81
4 April 85 87 88 90 89 87
5 May 83 83 87 86 84 82
6 June 80 86 76 76 82 85
7 July 80 81 82 80 81 86
8 August 86 86 81 88 83 86
9 September 85 86 83 86 85 83
10 October 83 84 81 76 82 81
11 November 73 78 71 75 71 74
12 December 83 75 78 78 76 78
Average 82.4 82.8 81.5 82 81.7 82
(Source: Statistical Yearbook of Hanam Province in 2012)
* Wind speed and wind direction
In Ha Nam province, there are two main wind directions in one year. There are north wind
and northeast wind in winter from November to next April. There are south wind and
southeast wind in summer from April to August. Ha Nam province is impacted by storms
similarly to the Northern plains.
The average annual wind speed is 2.5 m/s.
* The types of abnormal weather
- The Northeast monsoon
The Northeast monsoon is the high pressure gas which is formed from Asia continent, then to
the North Vietnam via Hoa Nam (China) toward the northeast direction from September to
May. The winds are more and stronger in mid-winter than that in early and late winter. Each
Northeast monsoon period impacts the local weather from 3 to 10 days, which is showned by
sudden lower air temperature and “being tropicalized” to warmer. Some Northeast monsoon
periods in early or late winter face hot moist tropical weather,causing weather disturbance
such as creation of storms, tornados, hails to destruct the localities where they swept through.
- Hoarfrost
It often appears in December and next January after end of the strong northeast monsoon
periods, sunny weather, cloudless nights, calm winds, causing strong ground radiation. Water
vapor in the air closed to the ground condenses in the form of salt crystals to cause cold
weather which is so-called hoarfrost. Hoarfrost can suspend the botanic metabolism, freezing
the tissues to cause the death of tropical mollusca, damaging the respiratory system of humans
and animals .
Conclusions:
The project site is located in the tropical monsoon climate with many varied weather patterns
in different seasons. This type of weather will not affect much to the industrial production
operations of tenants in the IZ.
40
2.1.2. Socio-economic conditions
2.1.2.1. Socio-economic conditions of Hoa Mac Town in first 6 months of 2013
Hoa Mac town is Duy Tien medium district so it is quite favorable in terms of traffic and
socio- economic development.
(1). Agricultural production
Regarding cultivation: The total cultivating area in winter-spring crops is 164 hectares,
making up 100% of the assigned schedule, in which the area for rice growing is 115 hectares
and crop area is 49 hectares. Rice yield reaches 59.1 quintals / hectare. Cereal output is 366
tons.
Regarding husbandry: Husbandary has developed stably. The prevention of disease such as
epidemic disease for livestock and poultry are often interested. According to survey data, in
the entire town:
− Pigs: 854;
− Cows: 8;
− Poultry: about 14,250.
(2). Industrial production - handicraft industry - Civil Construction - Commercial Services
In terms of industry and handicraft: Total production value in the last 6 months is estimated to
be VND 10.2 billion (making up 54 % of the plan). The industries are further maintained and
developed namely production of building materials, furniture, welding, garment and textile,
etc.
In terms of civil construction: Total investment in civil construction in first 6 months of 2013
is estimated to be VND 2 billion. In the first 6 months, it has completed adjacent lines and
yard to the Secondary School and functional office of the Primary School. It has concretized
village roads, alleys under the Province’s policy on cement support.
In terms of commercial services: Up to now, the number of households participating in
commerce services throughout Hoa Mac town are over 742 households, which is 6
households larger than that in 2012. Hoa Mac market’s operations are stable to contribute
significantly to the locality’s budget
(3). Regarding the Traffic – Irrigation system
Hoa Mac People’s Committee established the Steering Committee for Flood and Storm
Control to construct plans, specific schedules to each village, street, to preare sufficient
materials, facilities and personnel to readily respond in emergent cases.
To regularly coordinate with the inter-disciplinary agencies to organize to clear traffic safety
corridor in the region.
(4). Regarding socio-culture issues
* Education and training
Kindergartens: The school is ranked the 11th in the district after the academic year of 2012 –
2013. There are 48 5- year-children in the primary education level in the town.
Primary schools: Number moved students make up 100 %. 31 teachers and 455 students were
rewarded and complimented in the end school year 2012 – 2013. The primary education is
ranked the first in the district
41
Secondary Schools: Number moved students make up 100 %, in which, excelent students
(3.75%), merit (49.44%), satifactory (45.32%) and weak (1.5%). Common secondary
education quality is ranked the 6th in the district
* Health care - population
In the first 6 months of 2013, the local Medical Center organized to provide health care
services to 1,500 turns of patients, to offer oral anthelmintics to 470 infants and vitamin A to
360 infants in the age of 6 – 36 months.
The rate of natural population growth in the first 6 months is 0.27 % . The whole town has
actively implemented a plan on construction and development the Fund for Children
Protection; Action Plan for Children in 2013.
2.1.2.2. Socio-economic conditions of Chau Giang Commune in first 6 months of 2013
(1). Agricultural production
+) Cultivation:
In the winter- spring of 2013, the commune has planted 1,815 hectares, in which:
- The area for rice growing is 1,640 hectares
- The area for maize growing is 150 hectares
- The area for cucumber growing is 8 hectares
- The area for beans and nut growing is 25 hectares
- The area for soy growing is 11 hectares
The average rice yield reaches 66.3 quintals / hectare. Total food productivity is 4630.4 tons
(accounting for 55.78 % of the plan in the year)
Total crop value in the first six months of 2013 is VND 40.5 billion, increasing by 20.9 %
compared to the same period in 2012.
+) Husbandry:
By 30th
June 2013, total pigs are 3,500, reducing by 760 pigs in comparison with that in the
same period, buffaloes are 275, increasing by 15. Poultry is 85,000, increasing by 30,000 in
comparison with that in the same period
Aquaculture has developed in low-lying fields and 455- hectare- ponds in the form of a farm.
Many households’ income is over VND 100 million / hectare / year. Fishery output is 310
tons.
Estimated income from breeding and aquaculture is VND 34.5 billion.
(2). Services
In the first 6 months of 2013, revenues from industrial production, handicraft, and
construction is estimated to be VND 60.6 billion, making up 52.3 % of the plan
Revenue from commercial services is VND 58.2 billion, making up 57.3 % of the plan, in
which:
- Revenue from services: is estimated to be VND 34 billion;
- Income from labor export: VND 9 billion;
- Revenue from social insurance and pension policies for dedicated people and social
welfare beneficiary objects: VND 13.8 billion;
42
- Revenue from salary allowances of officers: VND 1.4 billion.
(3). Socio-culture, health care, education
+) Socio-culture
By June 2013, Chau Giang commune has 15,354 inhabitants, the rate of natural population
growth is 0.4 %, reducing by 0.2 %; 3rd
child rate reduces by 1.5 %.
Communicating and cultural activities are well organized, including to complete 59 wall-
mounted slogans, 65 turns of banners, to hang 2,300 turns of flags, to propagandize in large
events; to prevent social evils and to propagandize to construct the new urban areas; to
intensify management of cultural activitiesto organize cultural exchange, art shows, sport
events, the joining-up songs of 2013, and to organize to receive the honor title of National
Relics for Dinh Dong Ngoai;
+) Health care:
In the first 6 months of 2013, the Medical Station has organized to provide examination and
treatment services to 8,212 turns of patients, in which 2,980 turns of patients are the health
insurance beneficiary objects. For example, to supply VND 80 million for drug.
Number of children having vitamin A is 856 children, the percentage of malnourished
children under 5 years old is 14.9 %, reducing by 0.5 % compared with that in 2012. The
results are medicine are distributed to 74 psychiatric, neurological patients, 5 TB patients, 1
leprosy victim; to check and test 23 food business facilities in 3 inspection times; to actively
propagandize prevention of malnutrition, anemia prevention in association with the provincial
Eye Hospital; to provide examination services to 55 patients, to complete cataract surgeries to
5 patients and Retina surgery to 5 other patients.
+) Education:
In the academic year of 2012 – 2013, A Primary School has 332 students. B Elementary
School has 541 students and Secondary School has 548 students.
The education has made positive changes in the quality of teaching and learning. A number of
attendants are remained in the year, making up 100%; secondary school graduates account for
100%, in which the excellent and merit rate accounts for 43.6 %.
2.1.2.3. Socio-economic conditions of Trac Van Commune in 2012
(1). Agricultural production
+ Cultivation
The area for rice growing was 231 hectares, making up 100% of the plan. Rice
productivity reached 121 kg /hectare, making up 101 % of the plan and 94.3% in the same
period. Rice output reached 2,795 tons.
Table 2-13. Plants in rich-soil
No Crops Area (ha)
Productivity (quintal/ha)
Yield (ton)
1 Corn in Spring Corp 120 50 600
2 Peanut in Spring Corp 20 70 140
3 Bean in Spring Corp 1 27 2.7
4 Corn in Summer Corp 15 60 90
5 Soybean in Summer Corp 65 27 175.5
6 Bean in Summer Corp 50 22 110
7 Corn in Winter Corp 125 50 625
43
Cultivation value was VND 35 billion, four hundred and forty six million, two
thousand dong.
+ Husbandry
Husbandary was relatively stable. Total pigs were 16,098 (in which sows: 723, sucking pigs:
9,639 and porker: 5736), buffaloes, cows and calves were 480. Poultry: 110,091. In addition,
the local people keep honey-bees. The commune has 240 bee herds with the capacity of 3,120
kg. Alquaculture is effective with the capacity of 224 tons.
Livestock production value reached VND fifty two billion, three hundred and eighty nine
million dong.
(2). Industry - Handicraft Industry and Construction
Estimated production value reached VND 71,456,700,000. The main products are silk
weaving, construction, furniture, mechanics, welding, textile and garments, etc.
The commune has 254 builders, 31 silk weavers, 81 garment workers, 91 carpenters, etc.
Total employeed people in the commune is 1,773 out of 5,182 people.
(3). Irrigation
Irrigation and flood control are checked, instructed and directed to maintain and correct key
irrigation works. In addition, the works for agricultural production are improved such as
restoration and dredging 9,000 m3 of ditches; excavation and embankment of 400 m
3.
(4). Culture – Society and education
The commune has 8,409 heads and 2,536 households by December 2012, of which emigrants
are 49; immigrants: 56, birth rate: 168; dealth rate: 73 and marriage: 72 couples.
The local cultural works for activities of the residential communities are operated more
effectively. 8 out of 8 villages remain the title of cultural villages. There are 2,062 standard
cultural families in the commune.
Compulsory primary education level 2 is completed in the commune and it is universalizing
pre-school education to 5-year –old children. There are 03 standard national schools in the
commune. The commune has won 04 prizes in the province level excellent –grade- 5 pupil
contests
It has effectively implemented disease prevention and health care to the local people via
provision of examination and treatment to 8,107 turns of patients, making up 103% of the
plan, in which the patients in the health insurance policies are 4,293 turns of patients.
2.1.2.4. Social-economic conditions of Duy Tien District
First 6 months of 2013
Duy Tien District is located in the North of Ha Nam province. It is the gateway of southern
Hanoi and 20 km from Phu Ly City. The natural area is 13,765.80 hectares, equal to 16.01%
of the province. There are 19 communes, 2 towns, and population of over 130 thousand
people. There are so many key roads, railways, roadways, waterway so passing the district to
bring the favorable conditions in trade and economic development
(1). Agricultural productivity– rural areas
Production in winter crops: The district’s cultivating area is 6637.5 hectares, in which:
- The area for winter-spring rice: 5,778 hectares
44
- The area for spring crops: 859 hectares
Expected Yield: Rice (67.9 kg / hectare), corn (59.9 kg / hectare); peanuts (27,6 kg / hectare).
Cereal output is estimated to be 43,400 tons
Breeding is stable and epidemic diseases do not happen. In detail, the district has:
- Pigs: 45,110;
- Cows and buffaloes: 4,810, including 275 dairy cows;
- Poultry: 1.4 million.
The district has 850 hectares for aquaculture with the estimated output of 1,220 tons.
(2). Industry – Handicraft- Construction
Growth of industry – Handicraft in the district is good, reaching VND 2,710 billion,
increasing by 34.49% in comparison with that in the same period.
The district is taking most of the investments from budgets and actively mobilize resources
for the construction and renovation and upgrading of the engineering infrastructure.
Currently, the district has started construction of some projects namely Lang Giang Temple
Spiritual Tourism Project; Working House of the District, Working House of the Department
of Finance & Accounting; Headquarter of Bach Thuong Commune People’s Committee. In
addition, it focuses on strengthening construction of Projects: Hoa Mac – Chau Giang – Moc
Bac Road, Access Road to the center of communes, towns; Stabilized System of Irrigation,
etc)
(3). Natural resources and environment
To instruct functional departments and communes, towns to complete the construction plans
of dump sites to facilitate transportation to the plant at Duy Minh commune for handling. To
regularly check and remind environmental hygiene and protection in the business units and in
the residential areas.
(4). Social and cultural fields
There are 142 out of 156 villages, cities holding the honor title of cultural villages, streets,
making up 91%. A number of cultural families are 31,955 out of 34,680, accounting for 92%.
Disease prevention and food safety and hygiene control works have been actively
implemented. In the first 6 months of 2013, there is no epidemic disease or food poisoning
cases in the district. Vaccination work is implemented seriously. 100% of the children in the
age of 6 – 36 months take A vitamin under the national policy.
To timely implement social welfare policies. To offer 277 tons of rice to the poor and near-
poor households on the occasions of Tet holidays of Snake year. To exempt electric bill in the
1st quarter to poor families, about VND 276,570,000/ 3,037 families.
B. Development orientations of Duy Tien District in period of 2011 – 2015
(5). Orientations
To enhance leadership skills and capacity of the Party’s organizations.; To firmly and
transparently build the political system from district to grassroots level. To promote
democracy and unity strength of the political system; To intensify the compaign “Study and
follow the moral example of Ho Chi Minh"; To speed up economic development in a
sustainable manner; to combine economic development with socio-cultural promotion,
environmental protection, and improvement of local people’s life; To construct the high
quality workforce to facilitate the economic shifting process and the process of industrial
45
district construction; To mobilize human resources to build economic infrastructure and civil
works; To strictly combine socio-economic development with national defense – security
control; to keep politics, public order and safety sustainable.
(6). Main targets
Gross domestic product per capita in the district increases by 15.15 % / year.
GDP average per capita in 2015 is expected to be VND 42.28 million/ year
Economic restructure by 2015:
+ Industry - construction: 57.75%;
+ Services: 30.75%;
+ Agriculture, forestry and fisheries: 11.5%;
Total food production per capita: 68,686 tonnes / year.
The average production value of agriculture, forestry, fisheries increases by 1.8 % / year.
Value of industry – handicraft output increases by 24.4%/ year in average.
Total retail sales of social consumer goods and services increase by 13.15 % / year in average.
The export value increases by 12.5 % / year in average.
Total payment to the State’s budget increases by 15% / year in average
Number of people with new employment: 3,440 people/ year in average
The natural population growth rate by 2015 is 0.75 %. The birth rate reduces by 0.12%
The poor households are expected to reduce by 6% by 2015.
The rate of malnourished under-5-year infants are expected to reduce by 16% by 2015
The rate of households approaching freshwater by 2015 is expected to make up 91%
Percentage of trained employees by 2015 is expected to make up 40 – 45%
Rate of new urban communes by 2015 is expected to make up 20%
Rate of the Party’s strong and transparent committees is over 85%
(7). Main tasks
+) Industry – Handicraft development
High-speed and sustainable growth is the central task.
It is expected to increase the industry, handicraft output value by 24.4%/ year. To plan
and expand Izs, handicraft industry of the district; to focus on completion of the engineering
infrastructrue of Hoa Mac IZ. To make efforts to fill the area of Dong Van II IZ, Cau Giat
Handicraft Industrial Cluster. To strictly punish the projects which are issued with investment
certificate but they do not implement the business and production operations under the
regulations and laws. To improve the efficiency of Izs in the locality. To attract large
enterprieses, to use modern, energy saving, environmental friendly technologies; to priotize to
invest in high-technology industrial fields, agro-processing, food, etc. To do training and
selection of workers well, to secure to provide welfare policies to workers, etc to priotize to
recruit local workers to work for the tenants.
46
To continue to expand scope of the existing trade villages, to develop new occupations with
high income. To improve the quality, diversify handicraft products; to pay more attentions to
key products with high export value namely rattan, handicraft goods, etc.
+) Development of agricultural commodities; restructuring of the agricultural sector by
increasing the proportion of livestock . Promoting new rural construction
To develop agricultural commodities with high productivity, quality and efficiency. To
actively restructure of agricultural sector by increasing the proportion of livestock. To make
the efforts to develop the agricultural, forestry, fishery values to make up 55% of total
agricultural value. Average agricultural, forestry, fishery value increases by 1.8%/ year in
average.
A positive internal restructuring of the agricultural sector. Striving value livestock industry,
aquaculture, 55 % of the total agricultural value. The value of average increase of 1.8 % /
year.
To promote application of advanced science, technology, especially biotechnology in
farming. To improve rice cultivation, crop restructure, variety restructure to make up over 55
% of hybrid rice, 30% of high quality rice; to enhance winter crop output and land use factor
by 2.65 times. To generalize and expand polyculture model; models of economic households;
patterns of farm economcics with the income of about VND 100 million / hectares or more.
To issue the plans on construction the specialized areas for cultivation, to stimulate to grow
saplings with high economic value or in association with processing, business and export. To
actively execute natural disasters prevention works to minimize possible loss and damage. To
improve the State’s cooperatives attached to the agricultural products. To encourage to
establish specialized cooperatives. To develop strongly centralized husbandary on large scale.
To secure to control epidemic diseases and protect environment. To control veterinary works,
killing and transporting cattle and poultry well. To make the best efforts in producing over
13,550 tons of meat of livestocks / year in average.
To effectively implement the Plan on Pilot Construction of New Urban Model at Doi Son
Commune. To make the efforts in facilitating 5 out of 21 communes and towns to reach the
title of new urban criteria.
Implement effective pilot scheme to build a new rural model in Doi Son commune . Striving
to 2015, with a 5/21 communes and towns reaching new rural criteria.
+) Faster development of trade, services and tourism
To make the best efforts to increase total retail sales of social consumer services by 13.15%/
year in average. To invest, upgrade urban markets, to improve and construct Hoa Mac, Dong
Van markets to become center of commerce in the district. To promote trade in various forms;
to search, expand the markets to consume agricultural and aquacultural products. To pay
more attentions to exploit export markets for advantaged tradditional goods, especially
agricultural products, handicraft goods. To expand and improve the quality of services namely
transport, festival tourism, telecommunications, especially services for productions and urban
living activities. To develop legal consultancy services, insurance, education, health care,
culture, communication and sport. To pay attention to develop high-quality services to better
meet the development demands of the district.
To invest and improve the quality of operations in tourist places namely Doi Son Ploughing
Festival, Doi Son Long Pagado Festival, Lang Giang Temple, etc to make the deep
impressions in the visitors’ mind and to develop the local services at the same time.
47
To enhance investment in attractions : Doi Son charged festival , festivals Long Doi Son
Pagoda , Temple Lang Giang ..., creating deep imprint for tourists to visit in parallel with the
development of local services.
Conclusions:
Generally, the life of local people in the Project site has been much interested by the local
goverment. The policies on social welfare, health care, education and vocational development
are always practical, securing the living quality of local people. The agriculture and handicraft
industries are restructured to ensure that the local people could benefit from them.. Hoa Mac
IZ may, in its favorable location, help increase the the revenue of local area and create
employment for local peoplein the district.
2.2. CHARACTERISTICS OF THE RECEIVING RESOURCE
2.2.1. WW receiving place
WW treated by Hoa Mac IZ’s CETP flows to Giat River to Chau Giang river and finally
further to Red River.
2.2.2. Natural features
2.2.2.1. Hydrological characteristics of receiving resource
Hydrological regime is varied with dense river network. There are 4 surrounding major rivers
namely Red River, Chau Giang River, Nhue River and Duy Tien River. The water resources
are abundant, easily exploited, and sufficient for local production and living demands.
Mac Hoa IZ is directly affected by hydrology of Chau Giang and Giat Rivers. The hydrology
mechanism of the rivers is summarized as follows:
- Chau Giang River: It is originated in Ha Nam Territory. At Tien Phong (Duy Tien),
Chau Giang River is divided into two branches, of which one branch is the separator between
Ly Nhan and Binh Luc Districts and one branch is the separator between Duy Tien and Binh
Luc Districts. Chau Giang River at Ha Nam Province is 58.6 km long. Average flow rate in
dry season and wet season is 5 – 10 m3/s and 60 m
3/s, respectively.
- Giat River: Giat River receives treated WW directly from Hoa Mac IZ. The average
flow rate of the river is 22.6 m3/s.
2.2.2.2. Aquatic environment
Giat river and Chau Giang River are mainly for irrigation purposes in agriculture so the
aquatic environment is less diversified.
Regarding aquatic plants: Basically, there are few aquatic plants, sometime, locally appear in
small amounts of algae in the water
About organisms: they are mainly available fishes namely anabas, sailfish, hemicultur,
shrimp, crabs, snails, etc. In addition, there are limited number of large fishes such as carps,
major carps, etc. Due to heavy rain, fishes escape from surrounding aquaculture ponds.
Generally, natural fishes on Giat river and Chau Giang river are limited in quantity and less
diversified in types.
2.3. SUMMARY OF THE EXISTING STATE OF THE ENVIRONMENT AT THE
PROJECT AREA
2.3.1. Air
The air environment monitoring results in Hoa Mac IZ is displayed in the below table:
48
Table 2-14. Air quality results in IZ (10th
December 2012)
Location of Sample Concentration (mg/m3) Symbol
CO SO2 NO2
Hoa Mac Bridge nearby IZ
0.193 0.154 0.123 K1
Entrance in front of IZMB’s office 0.126 0.11 0.06 K2
Giat bridgehead 0.128 0.05 0.064 K3
At the end of IZ (in Chuyen Thien village, Chau
Giang commune) 0.118 0.072 0.05 K4
Internal road that is far 650 meter from the IZ port
northward 0.131 0.053 0.03 K5
Internal road that is far 90 meter from Dong Doai
cemetery northward 0.114 0.085 0.064 K6
At CETP 0.45 0.124 0.13 K7
QCVN 05-06:2009/BTNMT (1 hour for average) 30 0.35 0.2
Note:
QCVN 05:2009/BTNMT: National technical regulation on ambient air quality.
QCVN 06:2009/BTNMT: National technical regulation on hazardous substances in
ambient air.
Table 2-15. Results of dust, noise and microclimate in some location in IZ (10th
December
2012)
Symbol Location of
Sample
Noise
(dBA)
Dust
(mg/m3)
Tempe
rature
(oC)
Humidit
y
(%)
Wind
Direction
Wind
Velocity
(m/s)
A1
Hoa Mac
bridgehead
nearby IZ
78 0.355 32.9 78.1 South-
east 0.4
A2 Entrance in front
of IZMB’s office 85 1.99 32.4 73.6
South-
east 0.8
A3 Giat bridgehead
77 0.67 33.1 76.9 South-
east 0.51
A4
At the end of IZ
(in Chuyen
Thien village,
Chau Giang
commune)
57 0.145 33.5 66.4 South-
east 0.15
A5
Internal road that
is far 650 meter
from the IZ port
northward
76 0.193 32.8 72.1 South-
east 0.5
A6
Internal road that
is far 120 meter
from Dong Doai
cemetery
northward
83 0.309 31.9 77.8 South-
east 0.75
A7
T-junction
nearby PVC-
ME1 Company
84 0.189 32.1 74.0 South-
east 0.7
49
Symbol Location of
Sample
Noise
(dBA)
Dust
(mg/m3)
Tempe
rature
(oC)
Humidit
y
(%)
Wind
Direction
Wind
Velocity
(m/s)
Limit 70 (*) 0.3(**) -
Note:
(*) QCVN 26:2010/BTNMT: National technical regulation on noise.
(**)QCVN 05:2009/BTNMT: National technical regulation on ambient air quality.
Comment:
The monitoring result shows that the ambient air quality in Hoa Mac IZ is quite good, much
lower than the permited standard.
2.3.2. Soil
The monitoring result shows that the soil quality in the Project area on 10th
December 2013 is
shown in below table:
50
Table 2-16. Soil quality (10th
December 2013)
Parameter
Result
Pb Cd Ni Mn Cu P2O5 N K2O Fe Al3+ Methyl
Parathion
Total
DDT pHkcl
Unit mg/kg % mg/100g ug/kg
Sample
symbol
D1 0.8 0.4 0.07 42.17 14.21 0.06 1.22 1.04 139 0.55 0.002 ND 2.50
D2 0.9 0.18 0.10 33.36 5.53 0.25 0.17 0.43 92.54 2.02 0.001 ND 2.34
D3 0.99 0.28 0.13 51.53 8.26 0.44 0.15 0.92 121.3 0.54 0.002 ND 1.05
D4 0.71 0.11 0.124 40.5 13.7 0.19 0.11 0.64 189.7 1.07 0.001 ND 2.21
QCVN
15:2008/BTNMT - - - - - - - - - - 0.01 0,01
ND
QCVN
03:2008/BTNMT 70 2 - 50 - - - - - - - -
TCVN 373:2004 - - 0.141 - - - - - - - - - -
TCVN 7374:2004 - - - - - 1.05 - - - - - - -
TCVN 7375:2004 - - - - - - - 1.05 - - - - -
TCVN 7377:2004 - - - - - - - - - - - - 4.18
51
Note:
ND: Not detected
D1: Soil position is far 150 meter from IZ’s entrance
D2: Farm land position in IZ is far 25 meter from Giat Bridge
D3: Farm land position in IZ is far 7 meter from internal road
D4: Soil position on IZ is far 400 m Southward from Dong Doai cemetery
QCVN 15:2008/BTNMT: National technical regulation on the pesticide residuals in the soils.
QCVN 03: 2008/BTNMT: National technical regulation on the allowable limits of heavy
metal in the soils
TCVN 7373:2004: Soils quality. Index values of total nitrogen content in the soil of Vietnam.
TCVN 7374:2004: Soils quality Index values of total phosphorus content in the soil of
Vietnam.
TCVN 7375:2004: Soils quality Index values of total Potassium content in the soil of Vietnam
TCVN 7377:2004: Soils quality – pH value index in the soil of Vietnam
Comment:
The soil quality analysis results show that concentration of heavy metals is in the limit
ranges. Generally, soil quality in Hoa Mac IZ has not been polluted. The value and content of
substances are suitable to the prescribed standards.
2.3.3. Groundwater environment
The groundwater quality analysis result in the Project site on 10th December 2013 has been
shown in detail in below table:
Table 2-17. Results of groundwater quality
No Parameter Unit Concentration QCVN
09:2008/BTNMT NN1 NN2
1 pH - 7.4 7.3 5.5 – 8.5
2 SS mg/l 517 518 1500
3 Hardness mg/l 336 345 500
4 COD mg/l 13 14 4
5 Ammonium mg/l 8.8 16.6 0.1
6 Nitrate mg/l 3.4 2.9 15
7 Nitrites mg/l 0.03 0.01 1.0
8 Fe mg/l 0.08 0.12 5.0
9 Pb mg/l ND ND 0.01
10 Mn mg/l 0.15 0.17 0.5
11 As mg/l ND ND 0.05
12 Hg mg/l ND ND 0.001
13 Cl- mg/l 158 153 250
14 Phenol mg/l ND ND 0.001
15 Coliform MPN/100ml 0 0 3
Note:
QCVN 09:2008/BTNMT: National technical regulation on groundwater.
52
ND: Not detected.
NN1: Groundwater at the wells of Nghiem Viet Cuong house, Dong vilage, Chau
Giang commune, Duy Tien district, Hanam province (2013, July 01).
NN2: Groundwater at the wells of Nghiem Viet Cuong house, Dong vilage, Chau
Giang commune, Duy Tien district, Hanam province (2013, July 02).
Comment:
Above table shows that most of the surveyed indexes are in the allowed limit under the
National Regulation QCVN 09:2008/BTNMT. 2 out of 15 indexes exceed the permissible
limit, which are COD and Ammonium, in which COD is 10 times higher and Ammonium is
88-166 times higher.
2.3.4. Surface water
The surface water quality analysis result on 10th December 2013 has been shown in detail in
below table:
53
Table 2-18. Results of surface water
No Parameter Unit
Results QCVN
08:2008
(Column B1) M1 M2 M3 M4 M5 M6 M7 M8 M9
1 Temperature oC 30.5 30.6 30.8 30.4 30.6 30.3 30.6 30.4 29.5 -
2 pH - 7.62 7.35 7.23 7.73 7.42 7.28 7.58 7.88 7.62 5.5 – 9
3 TSS mg/l 11.5 16 12 6.5 21 28 15 28 15.8 50
4 Hardness mg/l 89.6 86.5 112.3 96.8 128.4 152.6 85.8 92.5 87.2 -
5
Total
dissolved
solid
mg/l 101 94 136 100 196 185 118 105 89 -
6 PO43-
mg/l 0.15 0.12 0.06 0.07 0.37 0.14 0.12 0.07 0.12 0.3
7 S2-
mg/l <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
8 SO42-
mg/l 18.5 19.55 40.76 28.3 38.57 48.29 30.62 38.55 21.25 -
9 DO mg/l 5.12 4.63 6.05 5.14 6.21 6.35 5.88 6.41 5.85 ≥4
10 COD mg/l 3.26 8.0 22 17.01 21 24 25 16 2.86 30
11 BOD5 mg/l 1.67 3.8 12.6 6.38 10.2 12.8 10.0 4.2 1.55 15
12 As mg/l 0.002 0.0013 0.0014 0.0015 0.0028 0.0033 0.0021 0.0017 0.002 0.05
13 Cd mg/l 0.0002 0.0004 0.0003 0.0003 0.0003 0.0002 0.0002 0.0004 0.0002 0.01
14 Cu mg/l 0.003 0.004 0.005 <0.001 <0.001 0.002 <0.001 0.005 <0.001 0.5
15 Pb mg/l 0.003 0.003 0.006 0.002 0.002 0.003 0.002 0.004 0.002 0.05
16 Cr mg/l <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 0.5
17 Hg mg/l 0.0007 0.0006 0.0006 0.0007 0.0006 0.0007 0.0006 0.0006 0.0005 0.001
18 Zn mg/l 0.562 0.608 0.624 0.529 0.616 0.513 0.481 0.586 0.465 1.5
19 Mn mg/l 0.029 0.024 0.021 0.026 0.028 0.041 0.027 0.038 0.018 -
20 Si mg/l 0.008 0.009 0.006 0.008 0.005 0.007 0.009 0.006 0.005 -
21 Se mg/l <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 -
22 Fe mg/l 0.256 0.083 0.205 0.165 0.420 0.478 0.324 0.224 0.068 1.5
23 NO3-_N mg/l 0.13 0.26 0.18 0.17 0.17 0.25 0.19 0.32 0.015 10
24 NO2-_N mg/l <0.01 <0.01 0.03 <0.01 <0.01 0.02 0.01 <0.01 <0.01 0.04
25 NH4+_N mg/l 0.017 0.014 0.012 0.012 0.086 2.563 2.393 0.942 0.008 0.5
54
No Parameter Unit
Results QCVN
08:2008
(Column B1) M1 M2 M3 M4 M5 M6 M7 M8 M9
26 CN- mg/l <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 0.02
27 Phenol mg/l <0.001 0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 0.01
28 NaCl mg/l 15.97 19.52 15.97 19.52 298.20 15.97 14.20 15.97 13.86 600
29 F- mg/l 0.19 0.13 0.22 0.10 0.23 0.51 0.31 0.81 0.08 1.5
30 E.Coli MPN/100ml 13 9 43 39 95 43 75 39 8 100
31 Coliform 230 110 430 290 140 430 150 210 120 7500
Note:
QCVN 08:2008/BTNMT: National technical regulation on surface water
M1: Ditch nearby sewer of Hoa Mac
M2: Open ditch in IZ
M3: At the end of IZ (Chuyen Thien village)
M4: Pond’s water nearby IZ
M5: Water of
M6: Water of Giat River at Lat Ha vilage, Trac Van commune
M7: Water of Giat River at position nearby IZ
M8: Water at internal farm-ditch nearby intersection D2N3
M9: Water of Chau Giang river at section of Giat River flowing into
Comment:
The above result shows that the surface water quality surrounding the project area is quite good. The analyzed indexes are lower than required
ones under the National Regulation QCVN 08:2008/BTNMT
55
CHAPTER 3 CHAPTER 3. ANALYSIS OF PROJECT ALTERNATIVES
3.1. CRITERIA FOR SELECTING ALTERNATIVES
The alternatives must secure the efficiency of wastewater treatment under the Regulation
40:2011/BTNMT, Column A.
Selection of alternatives must be in the principle of reasonable investment and low operating
costs.
Locations of the discharging outlet must meet the drainage demands of the CETP and minimize
impacts on the environment and life of local people surrounding the outlet.
Hazardous sludge from the CETP must be treated correctly under the procedure on HW treatment
to prevent from negative impacts.
3.2. WASTEWATER TREATMENT TECHNOLOGY
After consulting the experts in WW treatment, analysis of influent, Hoa Mac IZ Management
Board (IZMB) decides to select feasible Aerotank Technology as the alternative of SBR-based
Effluent Treatment Technology presented in Item 1.5.2.2, this Report.
3.2.1. Aerotank (AAO) Technology is described as follows:
AAO technology-based effluent treatment procedure of the Plant consists of 02 below steps:
Figure 3-1. Diagram of WW treatment technology by biological method
- Step 1: Mechanical treatment
Receiving compartment functions to distribute WW to the plant and partly separate raw residues.
Sand sedimentation tank is to remove most of sand and dirts with relatively large size from the
effluent meanwhile organic SS are not settled here. Water flow and speed are revised suitably as
being distributed to sand sedimentation tank via gate. Sand sedimentation tank is small in size
and located in the highest position compared to the other tanks to use the gravity method for
automatically flowing. Sand at the tank bottom is discharged to the sludge compressor tank via
submersible pump placed in the tank. Water from sand sedimentation tank self flows to
equalization tank.
56
Equalization tank is aimed at stablizing the flow and concentrations of pollutants in WW. The
tank bottom is arranged with system of gas distribution plates to mix and stir WW equally in all
points and to supply a part of oxygen to treat a portion of organic pollutants. Then, WW is
collected to the pump pits before pumping to the primary sedimentation tank
Primary sedimentation tank is designed vertically with beeding layer to increase efficiency and
reduce volume of construction. Tank bottom is sloped 60o to direct the sludge remover toward the
ditch. WW is led from the central pipes in the mid-tank with small speed to separate about 50 %
of SS. Meanwhile, BOD levels will drop 20-30 %. The effluent is collected from the pipelines
surrounding the internal the rim of the tank. The water is collected from the water trough around.
The sludge collected at the bottom of the tank is discharged to the sludge compressor tank by
hydrostatic pressure. The next stage is to combine biological treatment methods to thoroughly
treat the rest organic inorganic and toxic contaminants. Then, ww is led to complex AAO system.
- Step 2: Bio-treatmnet based- AAO technology (Anarobic, Anoxic, Oxic)
System of AAO treatment equipment has special structure. The specialized microorganic buffer
layer inside the equipment to clearly increase efficiency in treatment and to reduce tank volume
compared with conventional methods. The anaerobic, anoxic and oxic processes happen at the
same time here, as follows:
Anaerobic compartment has no oxygen and nitrate composition. It is mainly to remove
phosphorus and hydrocarbon components .
Anoxic compartment has no oxygen composition but plenty of nitrite and nitrate, especially
significant input of nitrate. The biological method is mainly used to remove nitrogen, nitrogen
compounds are released into the environment in the form of nitrogen gas.
Oxic compartment: Air is supplied by aeration machine. In this compartment, possible oxidizing
substances are used to complete entire bio-chemical process meanwhile nitrogen and ammonia
are converted to nitrate by the process of nitrogenizing via microorganisms Nitrifers and BOD
elimination by microorganisms Carbonuos
Anaerobic compartment: A majority of dissolved and suspended organic matters are destructed
by anaerobic microorganisms to form humus decomposition and gas.
Complex aeroten compartment: Treats BOD, nitrogenizing and pre-nitrogenizing at the same
time, organic matters and some inorganic substances will be decomposed to form microbial
biomass, which is known as biological cotton, then water is led to a secondary sedimentation tank
to separate biological cotton and clear water is led out.
Secondary sedimentation tanks: is designed vertically with the system of bottom sediment
discharge. A part of the sediments are pumped to the bio-tank to remain biomass concentration in
the tank. A part of the residues is discharged to the sludge compressor tank to dewater and
landfill.
Sludge treatment: The sludge, sediments in sedimentation compartment and each bio- treatment
compartment are pumped to return a part of activated sludge in biological equipment to ensure
the processing concentration. The residue is pumped to the sludge compressor compartment
where water is separated and returned to the equalization tank for preliminary treatment. Sludge
is compressed in term of volume and pipelined to the designated place and periodically treated.
57
Disinfection: To ensure the quality of treated effluent in line with the standards in terms of
mechanical, physical aspects and microorganism, WW must be disinfected by chlorine to
comprehensively treat pollutants and harmful bacteria effluent is checked in term of quality.
3.2.2. Comparison among treatment technologies
Table 3-1. Comparision of applied treatment technologies
Comparison
criteria SBR Technology Aerotank Technology
Hydraulic
mechanism
SBR – Sequence Batch Reactor is
operated with playing role of bio-tank
also as sedimentation tank. The number
of daily treated batches is adjusted
based on the flow and concentration of
influent.
It is operated continuously with 02
separate bio-tank and sedimentation
tank.
It is always operated in one
mechanism regardless whether
influent is significant or not.
Potential
application to
the IZ’s CETP
Because it is operated in batches so it is
very suitable to IZs’ CETP (because in
IZs, WW led to the CETP is often
varied in terms of flow and
concentration).
It is possible to apply to IZs’ CETP.
However, due to continual
operation, power consumption is
uneconomic and problem often
happens due to changed influent.
Microorganism
Due to the form of batch operation
with each batch mechanism is: water
feeding, reaction (aeration),
sedimentation and drainage. In
maximal sedimentation time, 1 hour,
this is complicated hydraulic condition
with different, continuously changed
states, requiring micro-organisms to
find ways to adapt or be removed. The
mechanism of choice is natural
selection and the struggle for existence
and survival, microorganisms will
compete and combine with each other
to become bigger, stronger and heavier,
when they will be settled faster and
will not be swept by the effluent in
discharging phase. Old, weak or sick
microorganisms shall be eliminated
due to their insufficient time for
sediment. With a healthy
microorganism, SBR technology has a
lot of advantages in operation such as
high shock resistance, fast recovery
capability
With continuous, unchanged
aeration mode, the microorganisms
will not be motivated to compete
and combine with each other. In
addition, current design standards of
biological sedimentation tank, water
storage time is in the range of 3-5
hours (it is noted that it is impossible
to reduce the storage time of the
sedimentation tank because it is for
sludge storage). With such a long
storage time, the weak or sick
microorganisms will be eligible to
be settled down, resulting in
shockage of microorganisms in
Aerotank and the restoration time is
longer than SBR technology
58
Nitrogen
treatment
Ability of nitrogen treatment is one of
the prominent advantages of SBR
technology in addition to its effective
treatment (the performance may reach
up 97%), SBR can adjust nitrogen
treatment efficiency quickly by
adjusting aeration and stirring time in
each batch
Due to the anoxic tank volume is
fixed so adjusting treatment
efficiency under input nitrogen level
is very limited and complicated.
Sludge
treatment
Activated sludge is saved after each
batch so they are treated in maximal
level. The total volume of sludge to the
sludge compressor is insignificant.
Entire sediment activated sludge is
pumped straightly to the sludge
compressor tank, then to the sludge
compressor. Therefore entire sludge
is very large.
Flexible
operation
Due to the batch operation, SBR is
very flexible in adjusting the running
mode. When WW flow or content is
lower than the design ones ((This is
characteristic of CETP), we may
operate it with fewer batch or reduce
the time of a batch to save power and
facilitate maintenance.
Whether WW flow or content is
lower than the design ones, we still
have to operate the system
continously (because the water level
in Aerotank is fixed and WW self
flows to the biological
sedimentation tank so we have to do
continuous aeration in 24/24).
Therefore, it is impossible to save
power if input WW is lower than the
design parameters.
Problem
solving capacity
Due to strong microbial system, SBR is
able to prevent from shockage and
restore higher than Aerotank
technology’s.
It is inflexible because the tank is
operated continuously so when an
incident occurs, we must stop the
system for check and repair.
Power
consumption
expense
Due to the ability to adjust the running
mode on basis of the input WW
parameters, SBR’s power consumption
is varied subject to the input WW
parameters and it is often lower than
Aerotank’s. In specific survey at
Amata IZ’s CETP, in the middle of
Phase 3 (Aerotank) and Phase 4 (SBR),
the power consumption of Phase 4 is
21.7% lower than Phase 3’s in the
same operation condition
The air blowers must be operated
continuously regardless whether the
flow or content of input WW is
lower than the design ones.
Therefore, it is so hard to save
energy and power consumption
expense will be higher than SBR’s.
Land use
demand
SBR plays both the role of reaction
tank and sedimentation tank so the land
use is usually 5-10% lower than
Aerotank’s
Large land use
Due to including reaction tank and
sedimentation tank
59
Conclusions: The above mentioned table shows that SBR technology is more prominent than
Aerotank in all aspects. Therefore, application of SBR technology toWW treatment is entirely
suitable to the conditions of Hoa Mac IZ.
SBR technology is the most prominent technology among Investor's choices
3.3. DISCHARGE LOCATION
After being treated in bio-pond, WW shall be discharged to the artificial open ditch before
draining Giat River via F600 culvert of which the bottom culvert segment is +2.5m. The ditch is
1500 m long and 7 m wide. 1 culvert is placed in the ending point of the ditch to automatic flow
WW to Giat River. With this option, WW is regulated in both effluent flow and quality before
discharging to the receiving source.
Therefore, the Investor only selects the unique location of the discharging plan (Figure 3.4).
Figure 3-2. Location of outlet from bio-pond to open ditch in IZ
60
Figure 3-3. Location of outlet from open ditch to Giat River
61
Figure 3-4. Outlet location
62
3.4. SLUDGE TREATMENT TECHNOLOGY
If sludge generated by IZ’s CETP is considered as HW, there are two treatment alternatives to be
selected: burning and hardened ws –based concrete producing method.
Advantages and disadvantages of the 02 above mentioned ws treatment plans are shown in below
Table 3.2:
Table 3-2. Analysis of Sludge Treatment Technology Alternative
Plan 1 Plan 2
Hardened mixed sludge producing
concrete
Incineration
Advantages - Simple.
- Creation of surplus value when
producing concrete.
- In line with the geographical conditions
for Hoa Mac IZ (because the 2 localities
nearby Ha Nam province are Hung Yen
province and Hanoi where the companies
specialized on HW treatment are
available).
- Safety for the environment.
- Elimination of emissions of air and
water pollutants.
- Simple.
- Suitable to actual conditions in
Vietnam because about 24
incinerators in the country are
used for disposal of HW.
- Easy operation and maintenance.
- Reasonable Investment cost.
Disadvantages - Require some additives such as sand,
stone, cement to produce concrete
- Generating WW, waste gas,
especially dioxins and furans (if
sludge contains organic chlorine
compounds). To remove them,
activated carbons for adsorption
must be used
Although incineration method is quite popular but hardened mixed sludge producing concrete
method has so many advantages so the Investor shall select hardened mixed sludge producing
concrete method to ensure that the treated sludge meets the current standards and reduces
emissions of pollutants at the same time.
Sludge treatment technology of Hoa Mac IZ’s CETP is presented in Section 1.5.3. This
dewatered sludge in the form of a cake will be transported and treated by Urban Environment
Company No. 11 – URENCO 11 with hardened mixed sludge producing concrete technology.
URENCO 11’s HW treatment technology was approved by Vietnam Environment
Administration (VEA) – the Ministry of Natural Resources and Environment (MONRE) with the
HW Management License No. QLCTNH: 1-2-3-4-5.022.VX (the 2nd
issue) (the documents are
attached in appendixes).
63
It is recognized as the suitable method to the existing conditions of the IZ and URENCO 11’s
competence on licensed HW treatment under Vietnamese laws so the Investor has no alternative
for the WS Treatment Company.
URENCO 11’s technology of hardened mixed sludge producing concrete is as follows:
- Sludge is transported from the sludge warehouse of Hoa Mac IZ’s CETP and dumped in
the concrete yard of Solidification Station. It is noted to dump sludge in the intermediate
treatment chamber in separate storage areas. It is prohibited to dump it with other waste types.
- Site preparation: The site is ready for dump of sludge, then solidified waste which are
poured from inside to outside and in suitable slope to facilitate the trucks to dump the mixture
after mixing outside.
- Waste sludge mixture is transported and fed into the mixer in the mixing ratio as
follows:
Waste: coarse sand: 1x2 Stones: Cement: Lime = 1m3: 0.3m
3: 0.5m
3: 250kg: 50kg
- After supply of waste sludge and additives for mixing in the mixer, the driver shall
transport and catch them under the outlet of the mixer.
-Waste sludge after stablly mixing in 5 minutes is discharged to three-wheeled vehicles to
transport to the intermediate treatment area for storage of solidified waste. Solidified sludge
mixture is buried under current regulations and laws in Vietnam.
Transportation route is as follows:
64
Figure 3-5. Diagram of sludge transport route
65
Hoa Mac IZ’s CETP NH 38 Yen Lenh Bridge Chu Manh Trinh Road turn to
Nguyen Van Linh Road (Hung Yen City) NH 39 Kim Dong District Khoai Chau
District Yen My District My Hao District Provincial Road 281 URENCO 11 (Dai
Dong Commune, Van Lam District, Hung Yen Province).
Description of the transportation route:
The transportation route distance from Hoa Mac IZ to URENCO 11 is about 65 km. It is the
shortest route. Details on the route are as follows:
The vehicles shall transport WS from Hoa Mac IZ along NH38 via Yen Lenh Bridge toward
Hung Yen City. The trucks pass Chu Manh Trinh Road to turn to Nguyen Van Linh Road in
Hung Yen City. Then, follow NH39 to pass Kim Dong District, Khoai Chau District, Yen My
District in Hung Yen Province. As passing NH5, it passes My Hao District of Hung Yen
Province to the Provincial Road 281 on Van Lam District, Hung Yen Province. Entire route is
covered with asphalt. The pavement is wide and traffic is favorable. Therefore, it is secured to
minimize potential risks on roads, especially traffic accidents. However, the route passes some
central areas in Hung Yen City (Chu Manh Trinh Road and Nguyen Van Linh Road) and other
residential areas namely the central area of Khoai Chau District and Yen My District. The road
section is quite short, about 12 km. The rest road sections and two road sections are mainly rice
fields of local people.
Finally, the trucks from the Provincial Road 281 turn to URENCO 11’s premise at Dai Dong
Commune, Van Lam District, Hung Yen Province. The road section connecting the Provincial
Road 281 and URENCO 11’s premise is soil path in length of 500 m and width of 5-6 m, which
are surrounded by rice fields of local people.
The above analysis shows that it is the most optimal route to minimize risks of traffic accidents
and negative impacts on the local people.
66
CHAPTER 4 ENVIRONMENTAL IMPACT ASSESSMENT
4.1. SOURCE, OBJECTS AND AFFECTED SCALE
The investment in building CETP with capacity of 1500 m3/day is appropriate to policy of
socio-economic development and environmental protection that is to contribute to solve
environmental issues in IZ. In addition positive impacts, however, it may be caused negative
impacts to environment, economy, and societyduring the construction and operation process if
there were not mitigation measures and appropriate treatment. The impacts of this project are
mainly generated in two stages:
- Construction phase;
- Operation phase.
4.1.1. Construction phase
4.1.1.1. Impact sources related wastes
The impacts of the construction phase of CETP are mostly negligible because this small
building separated from the residential area. The main impacts are listed in the below table:
Table 4-1. Sources of impact related to wastes in the construction phase
No Field Impact source Description Affected
subjects Evaluation
1 Landscape Storage of
construction
materials
Lack of management
of material
exploitation ,
formation of open
landfills
However, impacts
are insignificant
because CETP is
separated from
surrounding area by
shielding barriers.
Local aesthetics Short-term,
small-scale,
insignificant
Construction
activities
Construction
activities cause dusts
that affect on vision.
Similarly, small mass
of construction and
CETP isolated from
residential area, these
impacts are not
significant.
Local aesthetics Short-term,
small-scale,
insignificant
2
Pollution of
air and noise
Noise and
vibration from
mining, leveling
by construction
machinery and
transport
The noise level is in
threshold because of
construction area
isolated from
residential area.
Worker
Short-term,
small-scale,
insignificant
Dusts from Dusts are generated Worker Short-term,
67
No Field Impact source Description Affected
subjects Evaluation
construction,
leveling and
storage of
mining and
construction
materials
from exploitation
materials. However,
this small building,
exploitation
materials are not
significant.
small-scale,
insignificant
Air pollution
from
construction and
material
transport
Mainly pollutants are
dust, SO2, NOx,
CO2. This impact is
also negligible.
Worker , air
environment
Short-term,
small-scale,
insignificant
3 Surface water Wastewater from
living activities
of labors
Domestic wastewater
can be generated by
activities of workers
in the construction
phase. Thus,
wastewater contains
amount of nutrition,
organic substances
and coliform.
Surface water Low, sort-
term and
can be
minimized
Runoff water Mainly component is
SS, oil of hazardous
wastes generated by
improper
management.
Surface water Low, sort-
term and
can be
minimized
4 Underground
water
Exploiting
activities
Underground water
can be polluted if
underground
operations are
necessary for
construction.
Underground
water
Low, sort-
term and
can be
minimized
5 Solid wastes Solid wastes
from labor
activities
Wastes include food,
polymer bag, wood,
metal, glass, etc…
In addition, there is
leachate, odor and
favorable
environment for
insects and disease
vectors.
Local
aesthetics,
worker, local
residents
Low, sort-
term and
can be
minimized
Construction
wastes
Construction wastes
are cement, bricks,
sand, stone, wood,
scrap metal, and
other spilt materials.
Local
aesthetics,
worker, local
residents
Low, sort-
term and
can be
minimized
Hazardous They are containers Soil, surface Low, sort-
68
No Field Impact source Description Affected
subjects Evaluation
wastes of oil, gasoline,
grease and solvents.
However, it is
expected that amount
of these wastes are
very small.
water quality term and
can be
minimized
6 Traffic safety Increasing traffic
jam from
increasing
transportation
trips
Impact is negligible
because they are in
industrial parks.
Transportation Low, sort-
term and
can be
minimized
7 Occupational
safety
Lack of safety
equipments
Incident or accident
occurs in the absence
of safety equipment
and lack of upper
management in the
construction sector.
Worker Low, sort-
term and
can be
minimized
8 Living
activities
labors Construction site is
away from
residential areas.
The number of
workers here is just
not much for small-
scale construction of
CETP.
Local residents Low, sort-
term and
can be
minimized
9 Ecology and
landscape
IP has no evaluation
of ecology and
landscape.
Ecology,
biodiversity
Low, sort-
term and
can be
minimized
4.1.1.2. Impacts sources unrelated to wastes
The impacts unrelated to wastes in the construction phase are generally very small, negligible
because construction area is far from resident. The impacts are listed as below table:
Table 4-2. Impacts unrelated to wastes in the construction phase
No Impact sources Affected subjects Affected scale
1 Noise, vibration in the
construction phase and
equipment installation
Workers, local residents Low, short-term and
can be minimized
2 Pollution of residual heat Workers, local residents Low, short-term and
can be minimized
3 Local flood Surface water,
Underground water,
Landscape.
Low, sort-term and
can be minimized
4 Fire incidents, accidents in the Workers Low, sort-term and
69
No Impact sources Affected subjects Affected scale
construction process can be minimized
5 Social evils caused by workers
from other place who may have
conflicts with local residents
Workers, local residents Low, sort-term and
can be minimized
6 Traffic safety by increasing the
number of vehicles transporting
construction materials,
machinery and equipment in the
project area
Workers, local residents Low, sort-term and
can be minimized
7 The ability to spread infectious
diseases
Workers, local residents Low, sort-term and
can be minimized
4.1.2. Operation phase
CETP is far from residential areas, therefore, impacts in the operation phase don’t affect
the surrounding residential areas. The main impacts are listed in the below table:
4.1.2.1. Impact sources related to wastes
Table 4-3. Impact sources related to wastes, object and affected scale
No Field Impact
sources Description
Affected
objects Affected scale
1
Odor and air
pollution
WW tank Odor from WW Workers, local
residents
Average,
significant, can
be minimized Air pollution from the
anaerobic tank, especially
greenhouse gas
Microorganisms and
bacteria in the air
Smell from oil, gases, and
grease
2 Noise and
vibration
Movement of
vehicles and
machines
It’s caused by starting
activities and movement of
vehicles, far from resident
area
Public areas,
nearby
industries
Low,
significant, can
be minimized
3 Water
pollution
WW It contains high
concentration of SS, COD,
nutrient, waste metal, toxic
chemicals, and pathogens
Surface water Average, can
be minimized
Leakage of
WW
It contains high
concentration of SS, COD,
nutrient, and pathogens
Surface water Low to
average, can
be minimized
Rainwater Its component has SS,
grease, pathogens
Surface water Low to
average, can
be minimized
WW WW of workers
Surface water Low to
average, can
be minimized
4 Solid waste Wastes Solid wastes from multiple Workers Low to
70
No Field Impact
sources Description
Affected
objects Affected scale
stages average, can
be minimized
Sludge Sludge will be treated and
disposed properly
depending on its quality
Community Average, can
be minimized
Domestic
solid wastes
Solid wastes will be
collected for transport to
landfill
Soil, surface
water
Low, can be
minimized
Hazardous
wastes
Grease, scum floating
compounds from water tank
Soil Average, can
be minimized
4.1.2.2. Impact sources unrelated to waste
Table 4-4. Impact sources unrelated to waste, object, affected scale
TT Impact source Affected objects Affected scale
1 Noise, vibration from WW pumps, agitator,
air blower
Operational staffs Low, long-term,
can be minimized
2 Residual heat from machinery activities in
CETP
Operational staffs Low, long-term,
can be minimized
3 Sedimentation of water in Giat river area
Surface water Low, long-term,
can be minimized
4.2. ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
4.2.1. Construction phase
4.2.1.1. Impacts on air environment
The activities in construction and installation phase of the Project cause impacts on the air
environment, which is shown in below table:
Table 4-5. Impacts on Air Environment during Construction Phase
No. Activities Pollutants
1 Site clearance Dusts created by site clearance and construction
of the Project
2 Transportation, loading, storage of
materials
Arising dusts from the process of transportation,
loading of materials
Dust, gas created in the process of storage,
stockpile of fuels and materials.
3 Material transportation means Spilled materials and fuels (sand, rocks, cements,
oil and gas, paint)
Coal dust and gases SO2, NO2, CO, THC
created by exhaust fumes of means of
transportation of sand, stones, bricks, cement,
steel, equipment, fuel, etc, exhaust fumes from
the machinery and equipment for construction
(concrete mixers, crane trucks)
Noise, vibrations created by means of
71
No. Activities Pollutants
transportation
4 Cutting, welding and assembly of
equipment
Thermal radiation from the construction process
with heating works and welding fumes (such as
the cutting, steel welding, cutting, welding for
assembly)
The agents cause impacts on the environment and workers’health. Among them, impacts caused
by dust, gas emissions from means of transportation and noise are main impacts in the
construction phase, which are assessed in details as follows:
(1). Impacts of site clearance
The selected site for construction of the Project is relatively flat. Total area of the ETP, Phase 1 is
1,400 m2. Therefore, the quantity of site clearance is insignificant. Therefore, impacts of the site
clearance on the air environment are little.
(2). Impacts of dusts created by means of transportation of materials, equipment
Table 4-6. Pollution coefficient for truck with capacity of 3.6-10 ton
No Parameter Value (Kg/1000km)
1 Dust 0,9
2 SO2 2,075S
3 NOx 14,4
4 CO 2,9
5 THC 0,8
Source: WHO, Rapit Environment Assessment, 1993
Note: S is sulfur content in Do oil (%)
Impacts of dusts on the human beings and animals depend on their chemical physical
characteristics. They may cause irritation and respiratory diseases, eye problem, skin diseases, etc
in certain levels namely asthma, allergic inflammation, chronic lung diseases. Studies show that
particles with a size of 5-10 µm shall be retained in trachea and bronchi. The particles in size of
0.5 µm may cause impact on the lung. Silic particles in the sand may cause great impacts, even
Sarcoidosis if exposing to this dust for a long time.
Due to objective factors such as traffic density so the road users and inhabitants in the Project site
shall be the objects who are directly impacted by the construction phase. However, it takes 6
months for construction phase so these impacts are short-term.
The means of transportation of materials and devices has created dust and pollutants, such as
COx, NOx, SOx, THC, etc. This kind of polluting source is scattered, difficultly controlled,
directly impacting the local people along the road sides. However, the impact scope is
insignificant because the number of local people along the road sides are small
(3). Impacts caused by cutting, welding, painting and metal coating operations
During the construction phase of the ETP, such operations as cutting, welding, painting and metal
spraying may happen regularly. The equipment namely welding sticks, welding gas and
accessories (steel, iron, etc) are used to cause adverse impacts on the environment.
72
Table 4-7. Ratio of pollutants during welding process (mg/1 welding rod)
No Pollutants Diameter of welding rod, mm
2.5 3.25 4.0 5.0 6.0
1 Welding smoke (containing
many pollutants) 285 508 706 1,100 1,578
2 CO 10 15 25 35 50
3 NOx 12 20 30 45 70
(Source: National Institute of Labour Protection)
Toxic emissions, welding gas created during the cutting and welding phases may cause impacts
on the ambient air quality and the workers’ health. Most of such toxic gases contain heavy metals
such as Zn, Cu, Hg, Cr, highly toxicity and sustainability.
In addition, the used accessories during the process of painting, coating metal particles,
chemicals, paints, solvents, etc to create paint gas, paint dust, sand dust, metal rust, and chemical
substances also cause negative impacts on the surrounding air environment and workers.
Due to impacts from the processes of welding, cutting, painting, metal coating happening mainly
in the construction phase, the Investor shall apply Adverse Impact Mitigation Measures such as
the arrangement of the specific painting, coating areas where less people pass and the workers
must be provided with sufficient protection facilities.
(4). Impacts created by residence and living operations of the workers on site
A number of employees working on site are about 20 people. The daily living activities of
workers impact the air quality due to the following reasons:
- Bad odor (NH3, H2S, mercaptan HS-R) generated from domestic WW;
- The gas generated by the decomposition of organic waste;
- The odor generated by septic tank and organic waste.
Generally, impacts on the air quality due to daily living activities of workers are insignificant and
short-time.
(5). Impacts created by noises in construction activities.
The construction activities in the Project cause noise, including:
For the project, have the potential to cause noise include:
- Project site clearance;
- Means of material transportation;
- Use of machinery during construction and installation of equipment for the CETP;
- Landscape and site clean-up
73
Table 4-8. Noise intensity of some equipment
Equipment The noise
level from
(dBA)
The noise
level from
20m (dBA)
The noise
level from
50m (dBA)
The noise
level from
100m (dBA)
Bulldozer 93 70.5 62.5 56.5
Roller 72.0 - 74.0 49.5 – 51.5 41.5 – 43.5 35.5 – 37.5
Excavator using front spoon
scurf 72.0 - 84 49.5 - 61.5 41.5 - 53.5 35.5 - 47.5
Bucket scooping land 72.0 - 93 49.5 – 70.5 41.5 – 62.5 35.5 – 56.5
Rickshaw 77.0 - 96 54.5 - 73.5 46.5 - 65.5 40.5 - 59.5
Leveling machine 80.0 - 93 57.5 – 70.5 49.5 – 62.5 43.5 – 56.5
Paving the way machine 87.0 – 88.5 64.5 - 66.0 56.5 - 58.0 50.5 - 52
Truck 82.0 - 94 52.5 – 65.5 44.5 – 57.5 38.5 – 51.5
Concrete mixer 75.0 – 88.0 57.5 - 60.5 49.5 - 52.5 43.5 - 46.5
Concrete pile driver 80.0 - 83 57.5 – 60.5 49.5 – 52.5 43.5 – 46.5
Machine of concrete beams 85.0 62.5 54.5 48.5
Generator 72.0 – 82.0 49.5 – 60.0 41.5 – 52.0 35.5 - 46
TCVN 5949:1998 (6h – 18h) 60 dBA
(Source: National Institute of Labour Protection)
The ability to spread the noise of the construction site to the surrounding area is
determined as follows: Li = Lp - ∆∆∆∆Ld - ∆∆∆∆Lc (dBA)
Of which:
- Li: The noise level at the calculation time from the noise source at the distance d (m)
- Lp: The noise level measured at the noise source (from 1.5 m)
- ∆∆∆∆Ld: The noise levels decrease according to the distance d at frequency i
∆Ld = 20 lg[(r2/r1)1+a
] (dBA)
r1: Distance to the noise source with the Lp (m)
r2: Distance calculating the noise level reduction according to the distance correlative with Li (m)
a: Coefficient including the effect of noise absorbing of the surface topography (a = 0)
∆Lc:: The noise level reduction over obstacles. Getting ∆Lc at the project area = 0
From the above formula, we can calculate the noise levels of construction equipment to the
surroundings
Noise and vibration often cause a direct effect in the human auditory system. Their effects
are at different levels: causing fatigue, headache, neurological disorders, ....
According to the calculations in the table above, the noise only affects in a narrow range
of 200m radius, therefore the objects bearing the greatest impact is the construction workers.
However, the level of impact is small, only causing fatigue when working continuously about 12
hours per day
74
Figure 4-1. The impact of noise on people
(6). Impact assessment of air pollutants:
Exhausted pollutants in the construction phase may go inside the human’s body and cause some
symptoms listed in below table:
Table 4-9. Impacts of Air Pollutants
No. Parameters Impacts on human beings
1 Dust - To stimulate respiratory, pulmonary fibrosis, lung cancer;
- To cause Injury to the skin, cornea, diseases of gastrointestinal tract.
2 Acid gas (SOx,
NOx).
- To cause impact on the respiratory system, to be dispersed to the
blood;
- SO2 may cause poinson through skin and reduce alkaline reserve in
blood;
- To make acid rain, to adversely affect the growth of vegetation and
crops;
- To enhance the metal corrosion, concrete material degradation and
buildings;
- To cause adverse impacts on climate, ecosystems and the ozone
layer.
NOISE
EARS
NERVOUS SYSTEM
ORGAN OF
BODY
RESPIRATORY
SYSTEM
CIRCULATORY
SYSTEM KINETIC
SYSTEM
Increasing
respiratory
rate
Reducing ability to
distinguish colors,
reducing the
visibility
Causing
gastritis,
gastric
reduction
Increasing heart
rate, causing
circulatory
system disorders
Making muscles tired,
causing slow reflexes
vestibular disorders
VISUAL
PERCEPTION
DIGESTIVE
SYSTEM
75
No. Parameters Impacts on human beings
3 Oxyt carbon
(CO)
- To reduce oxygen transport of the blood to cells in the impacts of
CO in association with Hemoglobin to constitute CO-hemoglobin
carboxyl
4 Carbonic gas
(CO2)
- To cause pulmonary respiratory disorders
- To cause the greenhouse effect;
- To cause impacts on the ecosystem.
5 Hydrocarbons - To cause acute poisoning: weakness, dizziness, headache, sensory
disturbances, sometimes fatal.
4.2.1.2. Impacts on the water environment
Water environment pollutants in the construction phase consist of:
- WW from construction;
- Domestic WW of workers;
- WW created by cleaning and maintaining machinery;
- Rainwater runoff the construction site rolls dusts, soil, sand, rocks, materials namely
cements, petrol and gas, paint, etc scrattered to cause impacts on water quality;
(1). Impacts of domestic WW of workers
Main impacts on the water quality during the construction phase of the Project are
domestic WW of workers. Main contents of the pollutants in the domestic WW are waste matter,
suspended solid (SS), organic compounds (BOD/COD), nutrients (N, P) and pathogenic
organisms (Coliform, E.Coli). Domestic WW contains biodegradable organic substances,
residues, nutrients and microorganisms to cause contamination of surface water and groundwater
if they are not treated.
Domestic WW of workers is 120 – 150 l/person/day in average. Total domestic ww of workers
on site in the highest point, with 20 employees, is 2400 - 3000 liters, equal to 2.4 to 3.0 m3/ day
and night.
Table 4-10. Forecast the pollution load in waste water of labors (estimated volume of 20 person)
No. Parameter Unit Volume calculated by
WHO Total volume (Kg)
1 BOD g/person/day 45 - 54 0,9 – 1.08
2 COD g/person/day 85 - 102 1,7 – 2,04
3 Suspended Solid g/person/day 70-145
1,4 – 2,9
4 N-T g/person/day 6 - 12 0,12 – 0,24
N- NH4
g/person/day 3,6 – 7,2 0,072 – 0,14
5 P-T g/person/day 0,6 – 4,5 0,012 – 0,09
6 Total bacterias MPN/100ml 109
- 1010
-
7 Coliform MPN/100ml 106
- 109 -
8 Fecal Stemorela MPN/100ml 105- 10
9 -
9 Worm eggs - 103 -
10 Virus
- 102
- 104
-
76
(Source: WHO)
If the number of workers increases, the total amount of pollution (KLON) was calculated
using the formula:
Total KLON (Kg) = KLON (g/person/day) × number of employees (people)
Construction workers are mostly from other localities, so all personal living activities such as
eating, bathing, ... are in place so even though the flow of wastewater is small but if we cannot
collect to treat, this will affect much on the environment landscape.
(2). Impacts of WW from cleaning and maintaining machinery
The process of sanitation, maintenance of machinery and equipment in the construction site will
generate a large amount of organic matters, oil and SS. Flow and volume of pollutants in each
step are shown in below table:
Table 4-11. Flow and Volume of Pollutants Created from Machinery & Equipment Cleaning and
Maintaining Phase on Site
Generation process Flow rate
(m3/day)
Volume of Pollutants (mg/l)
COD Oil and
grease SS
Machinery maintenance 1
20 – 30 – 50 – 80
Machinery cleaning 50 – 80 1.0 – 2.0 150 – 200
QCVN 40:2011/BTNMT, Column A 75 5 50
Source: Generalized ENTEC, 2012.
WW flow rate generated from this phase is insignificant and pollutants such as COD, SS, oil do
not exceed the standard specified in the Regulation QCVN 40:2011/BTNMT, Column A
(3). Impacts on groundwater quality
In general, the construction phase does not cause much impacts on groundwater resource.
However, the construction phase can pollute groundwater. Fuel compositions (gasoline, oil,
organic solvents, etc) can be leaked out from means of transportation and equipment used, stored
on site, which are swept by rainwater to rivers to penetrate into the soil as the groundwater
pollutant in the Project site. In addition, leaked water in the process of concrete mixing, bored
piles, cleaning machinery and equipment may pollute groundwater
(4). Impacts of rainwater running off
According to the World Health Organization (WHO), the concentration of pollutants in rainwater
running off has the typically range from 0.5 to 1.5 mg N/l, from 0.004 to 0.03 mg P/l; 10-12 mg
COD/l and 10-20 mg TSS/l. Rainfall water running off is relatively clean, if flowing through the
construction area, it will entail soil, sand, packages, etc… it will increase the SS contents. If there
is any trash rack to separte trash before flowing to the discharging sources, its influence on water
quality will be not significant.
Calculating the flow of rain water:
- The total project layout area is 1394 m2,
- The largest daily rainfall (mm/day): 9.32 mm/day
77
→ The amount of rainwater running off (max) with the assumption that 100% of rainfall
is involved in the running off process:
1349 (m2) x 9.32 (mm / day) x 10
-3 = 12.99 m
3
With flow as calculated above, the rain water running off can cause the local flooding for the area
surrounding the project. However, the level and scope of impact is low.
(5). Impacts of construction wastewater
Construction of wastewater has pollutant concentrations of BOD, COD and suspended solids are
many times greater than QCVN 40:2011/BTNMT, if the waste water is discharged directly to the
discharging source and this will cause local sediment and pollution. Therefore, this wastewater
must be treated by sedimentation method before discharging to the flow sources, which will
significantly limit the impact.
Table 4-12. Pollutant concentration in wastewater of construction phase
No. Parameter
Unit
Construction
wastewater
QCVN
40:2011/BTNMT
Column B
1 pH - 6.99 5.5 - 9
2 Suspended solid mg/l 663.0 100
3 COD mg/l 640.9 100
4 BOD5 mg/l 429.26 50
5 NH4+ mg/l 9.6 10
6 Total N mg/l 49.27 30
7 Total P mg/l 4.25 6
8 Fe mg/l 0.72 5
9 Zn mg/l 0.004 3
10 Pb mg/l 0.055 0.5
11 As mg/l 0.305 0.1
12 Oil mg/l 0.02 5
13 Coliform MPN/100ml 53x104 5000
(Source: Center of Urban and Industrial Environmental Engineering)
QCVN 40:2011/BTNMT: National Technical Regulation on Industrial Wastewater, column B.
4.2.1.3. Impacts on soil resource – environment
Due to domestic WW of workers, construction wastes, oil and grease caused by equipment and
machinery on site, in the construction phase, wastes and WW are generated by worker activities
from temporary camps. The redundant or leaked wastes during the construction phase, oil and
grease from cars, trucks, construction machinery, etc are not well collected and managed that
may infect the soil environment significantly.
4.2.1.4. Impacts of solid wastes
Solid wastes during construction of this project are divided into two types as domestic wastes and
construction solid wastes.
- Domestic waste: Average volume of domestic waste calculated for a person per day: 0.5
kg/person/day × 20 people = 10 kg/day, mainly organic substances from the left food, plastic
bags, cardboard.
78
- Construction waste: Mainly construction material spilled or damaged packages of
materials, machinery. Due to the construction nature of just using some simple materials such as
cement, steel, bricks, stones, the construction waste volume is small, estimated to average of
about 20-30 kg/day. This waste can be reused.
→ The total amount of waste (domestic and construction): 30-40 (kg/day).
- Hazardous solid waste: Lubricants of construction equipment, oiled mops and gloves,
broken bulbs, adhesive waste, other chemical containers ..., estimated about 3-5 kg /day.
Solid waste and hazardous waste if not being collected will cause unsanitary, impact on
landscape and health of construction workers.
4.2.1.5. Impacts on social – economic aspects
(1). Advantaged impacts
The construction phase of the Project may bring advantaged impacts to the locality’s economic
and social aspects as follows:
- To create employment for local people;
- To increase workers’ income;
- To stimulate development of some types of food services, living and other
entertainment activities to facilitate living demands of workers in the Project site.
(2). Adverse impacts
Gathering the workforce (about 20 workers per day) during the construction period may cause
adverse impacts on the social order and security in the region;
An increasing number of vehicles getting in and out the site may cause heavy traffic, leading to
higher risks of traffic accidents therein.
Therefore, the Investor has to pay more attentions on machinery, vehicles, and engineering
equipment scientifically and control traffic safety to minimize adverse impacts on the
environment and socio economic aspects.
4.2.1.6. Synthetic EIA caused by Construction Phase
Table 4-13. Generalized Table of Impacts in Construction Phase
Environment
elements
Operations of the Project
Site clearance Material
Transportation
Construction of
Work Items Workers
Air environment *** *** ** **
Surface water
environment
0 0 * **
Groundwater
environment 0 0 * *
Biological
diversification
0 0 0 0
Landscape * * * *
Agricultural land 0 0 0 0
Living land 0 0 0 0
79
Environment
elements
Operations of the Project
Site clearance Material
Transportation
Construction of
Work Items Workers
Traffic * *** 0 0
Employment ** * ** **
The community’s
health in the project
site
* * * *
Social evils, contagious
diseases * * * **
Historical relics 0 0 0 0
Note:
High impacts: ***
Mean impacts: **
Low impacts: *
No Impact or insignificant impacts: 0
Conclusion: Above analysis shows that the impacts of construction phase on the surrounding
environment and landscape are insignificant, narrow and short-term. The largest impacts in this
phase are traffic safety control and local people along the two road sides due to material
transportation, dust emissions.
4.2.2. Operation phase
4.2.2.1. Impacts on air
The main factors impacting the air quality are bad odor created by decomposition of organic
matters in WW and waste collection via waste filter and pump. The locations creating the bad
odor are presented in Table 4-14. WW may have bad odor and direct impacts on the workers
here. However, if combining varied treatment engineering measures and keeping it at a safe
distance, these impacts are minimized. In addition, treatment method for aerobic WW only create
a small amount of CH4. The CETP is isolated from the centralized residential area. Therefore,
transmission of pathogenic microorganisms in the air is irregular.
Noise created by the equipment in CETP is mainly pump, air blowers, causing direct impacts on
operators. Impacts on air quality as the CETP’s operations are in the areas surrounding the IZ and
the Plant.
Table 4-14. Bad Odor Emission Sources in the CETP
Locations Pollutants
Inlet WW, exhaust fumes, oil, sludge
Pump pits WW, surface pollutants, sludge, sand
Oil Separator Tank,
Equalization tank
WW, exhaust fumes, oil, surface pollutants, sludge
Flocculation tank –
coagulation tank
Gas emission, oil, bio membrane, chemicals
Primary Sedimentation
Tank
WW, residues, gas emission, surface pollutants, sludge, re-
circulated solvent
80
SBR Tank WW, exhaust fumes, surface pollutants, sand, bio-membrane
Sludge Tank WW, exhaust fumes, oil, surface pollutants, sludge
Pump Station WW, surface pollutants
Bio-pond WW, exhaust fumes, residues, chemicals
Drainage ditch WW, residues, sludge, spilled chemicals and circulating area
Outlet WW, residues, sludge, spilled chemicals
4.2.2.2. Impacts on groundwater environment
The operation of the CETP have impacts on groundwater only when pipelines, the tank
bottom and WW in sludge tanks are not well controlled. However, the risks are possibly
minimized by proper operation and maintenance measures.
4.2.2.3. Impacts surface water environment
(1). Domestic WW of operators
The average content of WW is about 120 liters / person / day in average. However, the common
quorum of operators in the ETP should not exceed 6 people so domestic ww is not large.
Normally, Domestic WW created by operators has pollutants as BOD, COD, TSS. WW
generated by operators is treated through septic tanks so its pollutant contents reduce
significantly and as the result, the impacts are insignificant.
(2). WW from the CETP
WW generated by operations of the ETP consists of many sources:
- WW separated from the process of sludge treatment process, oil and grease scum. The
main elements containing SS, microorganisms and other pollutants.
- The water for cleaning pumping equipment, chemical tanks, filters, floors, etc may be
contaminated by oil and grease with insignificant concentrations;
Entire created WW shall be collected and sent back to the treatment tanks of the CETP.
(3). Rainwater runoff:
The rainwater runoff in the Project area shall sweep soil, sand, waste, oil and grease and
impurities scrattered on ground and on roof, treatment tanks, corridors to water sources. If the
effluent is not well controll, it may cause adverse impacts on the surface water source,
groundwater, and aquatic life in the area. Estimated concentrations of pollutants in average in
rainwater runoff are as follows:
- Suspended solids (SS) : 10-30 mg/l;
- Chemical oxygen demand (COD) : 10-20 mg/l;
- Total Nitrogen (N) : 0.5 – 1.5 mg/l;
- Phosphorus (P) : 0.004 – 0.03 mg/l.
Thus, rainwater runoff is relatively clean in comparison with other emission sources. Therefore,
rainwater drainage system will be completely separated from the WW drainage system via
manholes and trask racks before discharging to the environment via the IZ’s rainwater drainage
system.
81
4.2.2.4. Impacts on soil
Main impacts on soil are sludge from operations of waste in the CETP and domestic waste of the
workers.
(1). Solid waste (SW) generated from the treatment phase
The volume of SW generated from the CETP is affected by:
- Debris from the coarse filter and fine filter;
- Sand from sedimentation tank;
- Sludge from sludge tank including sludge, septic sludge, alum and polymer;
- Biological sludge from the biological treatment work as tanks, dropping filters
and oxygen systems.
(2). Sludge created by the CETP
Sludge is dewatered by sludge compresor and the polymer is considered as an adjuvant for
dewatering process.
Wastewater and sludge mainly consist of organic compounds, decomposited compounds to cause
unpleasant odors. If the sludge composition has toxicity due to industrial WW, it shall be
temporarily stored in the sludge tank, transported and treated if being leaked to cause impacts on
the soil environment .
Table 4-15. Calculations of Waste Sludge generated by Hoa Mac IZ’s CETP with assumed
capacity of 1500 m3/day.
No. Content Quantity Unit
1 Generated sludge content in the physicochemical
sedimentation tank
Daily average flow rate, Q 1,500 m3/day
a. SS gets in the physicochemical treatment clusters, , SSv 300 mg/l
SS gets out the physicochemical treatment clusters, SSr 150 mg/l
Daily physicochemical sludge everyday, M1=Q*(SSv-
SSr)/1000
225 kg/day
b. Created daily flocculated chemical content, MPAC(100%) 60 kg/day
Sludge precipitated from created daily flocculated chemical
content, M2=0.25*MPAC(100%)
15 kg/day
c Total sludge residues in the physicochemical sedimentation
tank,
M'=M1 + M2
240 kg/day
2 Daily created Bio-sludge
Mean flow rate/ day 1.500 m3/day
BOD gets in SBR tank, BODv 210 mg/l
BOD gets out SBR tank, BODr 23 mg/l
Sludge output factor, Y 0,55
82
Bio-sludge daily created in SBR tank, M''=Y*Q*(BODv -
BODr)/1000
154,3 kg/day
3 Total sludge pumped to the sludge compressor, M1=M' +
M''
394,3 kg/day
Compressed sludge in the sludge compressor with the humidity of 82%, equivalent to the
solid content of 18%
Sludge created after the sludge compression,
M2=M1/0.18/1000
2,19 Ton/day
(3). Domestic solid waste (DSW)
Domestic waste generated by workers can be calculated based on the number of employees
working in the CETP (about 6 people). Estimated quantity of generated waste is about 5 – 8 kg /
day under the rate of 0.5 kg/person/day and it is assumed that the workers are permitted to clean
their working place. The quantity is insignificant, collected and treated with DSW in the IZ under
the signed Contract.
(4). Hazardous waste (HW)
Waste grease and oil can be generated from maintenance and operation of vehicles and
machinery. Rest quantity of oil and grease can be identified as HW. If the strict management
measures are not applied to collect and treat the residual oils, this could be a source of pollutant
to the groundwater and soil. However, the estimated impact is insignificant on the environment.
Containers of chemicals are used in the treatment technology should be collected and stored in
accordance with the prescribed standards on safety, collection and periodical treatment.
4.2.2.5. Impacts on the ecology and landscape
Generally, impacts on construction of the CETP will not change any of landscapes and
ecosystems because this area’s current construction purpose changes, it is for building the IZ.
Presence of modern CETP shall build a good reputation to the IZ to the surrounding
communities.
After being treated, water quality shall meet the requirements in the Regulation QCVN
40:2011/BTNMT, Type A before discharging Giat river; therefore the impacts on the ecology of
the river are active in comparison with unavailability of the CETP.
4.2.2.6. Impacts on the community’s activities, health and safety
The Project does not cause much impacts on the public works and community except for bad
odor created by the CETP to make the surrounding industrial tenants unpleasant. However, if
mitigation measures are applied to reduce bad odor, such impacts are insignificant.
4.2.2.7. Environment Incidents in the Operation Phase
(1). Operation Incidents
The CETP may encounter with technical problems due to many reasons such as obstruction, fire
of the pump, automatic defects of the machinery, shortage of maintenance in a long time, etc.
These incidents may cause treated effluent dissatisfactory as discharging to the receiving
environment. The long-lasting incident which is not restored shall cause serious and direct
impacts on the receiving water source quality (receiving environment) and indirect impact on
ecosystems.
83
(2). Incidents caused by natural disasters
In the rain season, natural incidents such as floods, natural disasters may happen to cause the
system of WW collection – drainage damaged. Untreated WW shall be leaked in the surrounding
environment, polluting the water and soil environment in the wide scope toward the direction of
the effluent.
Table 4-16. Synthetic Table of Impacts in Operation Phase of the Plant
No. Impacting Sources Air Water Soil Ecology
and
Landscape
Community
1 Exhaust fumes ** 0 0 * *
2 Wastewater * *** *** ** **
3 SW and HW ** ** *** ** *
4 Polluting noise and
vibration
** 0 0 0 *
5 Environmental
incidents
* ** * * *
Note:
High impacts: ***
Average impacts: **
Low impacts: *
No Impact or insignificant impacts: 0
4.3. DETAILED LEVEL AND RELIABILITY OF ASSESSMENTS
Methods of assessment and reporting are common methods in environmental impact
assessment such as figure listing method, catalogue method and mathematic formula using
method, … Because its nature is an environmental treatment project, but is not the production
factory; its scope is small and volume and nature of emissions are not complicated, methods of
reporting such as network diagram method and map joining method are unused.
Detailed level and reliability of assessing possible environmental impacts, risks,
environmental incidents upon deploying and not deploying the project are objectively presented
in Table 4-17.
Table 4-17. Assessment of reliability of the EIA methods applied
No. Content of assessment Detailed level and reliability
1 In the construction phase
1.1
Assessing impacts caused by
dust and exhaust gas from the
means of transport
High detailed level and high reliability thanks to
sufficient figures about the means of transport
1.2
Assessing impacts caused by
noise from construction
equipments, machines and
means of transport
High detailed level and high reliability thanks to
figures collected from results of actual studies in the
world, specific calculations for the project and
comparison with the Standard on noise in working
place by the Ministry of Public Health
1.3 Assessing impacts caused by High detailed level and high reliability thanks to
84
No. Content of assessment Detailed level and reliability
vibration from construction
equipments, machines and
means of transport
figures collected from results of actual studies in the
world, specific consideration for the project and
comparison with criteria of vibration impact
assessment applied in the world for the
projects/subjects specifically affected in the area
1.4
Assessing impacts caused by
overflowed storm water and
temporary inundation
High detailed level and high reliability thanks to the
overflowed storm water discharge calculated
specifically for the project conditions
1.5
Assessing impacts caused by
domestic solid waste (waste
water and solid waste)
High detailed level and high reliability thanks to
waste mass/ discharge calculated separately for the
project on a basis of figures provided by the
Employer and reference figures of the projects
implemented in the area
1.6 Assessing impacts caused by
construction wastes
Low detailed level and relative reliability thanks to
lack of construction waste studies in Vietnam
1.7 Assessing impacts caused by
waste grease
High detailed level and high reliability thanks to
grease studies conducted in Vietnam and specific
calculations for the project in compliance with
Vietnam’s applicable regulations
1.8
Assessing social impacts
(traffic obstruction,
contradiction between
workers and local people and
industrial accidents)
High detailed level and relative reliability thanks to
identity and assessment of these impacts on a basis of
considering specific conditions of the project and
experience in social impact assessment of the
industrial zone construction projects as well as other
projects conducted by the experts
2 In the operation phase
2.1
Assessing impacts caused by
exhaust gas from activities of
the waste water treatment
plant
High detailed level and high reliability thanks to
reference and inheritance of studies in the world, use
of WHO’s pollution coefficient, inheritance of
industrial zone studies in Vietnam, comparison and
collation with a list of business lines permitted to
invest in the project and separate calculation for the
project
2.2
Assessing impacts caused by
bad odor from the
concentrated waste water
treatment plants
High detailed level and high reliability thanks to
reference of figures and studies about bad odor from
the waste water treatment plants in the world and
separate calculations and assessments for the project
2.3
Assessing impacts caused by
aerosol emitted from the
concentrated waste water
treatment plants
High detailed level and high reliability thanks to
reference of figures and studies about aerosol from
the waste water treatment plants in the world and
separate assessments for the project
2.4 Assessing impacts caused by
waste water
High detailed level and high reliability thanks to
reference of figures and different studies about
industrial and domestic waste water and separate
calculations of pollution discharge and load for the
project
85
No. Content of assessment Detailed level and reliability
2.5 Assessing impacts caused by
solid waste
High detailed level and high reliability thanks to
reference of figures and studies from real surveys and
separate calculations and assessments for the project
2.6 Assessing impacts caused by
hazardous wastes
High detailed level and high reliability thanks to
reference of figures and different studies about
hazardous wastes in conditions of the industrial
zones in Vietnam
2.7
Assessing impacts caused by
sludge from the concentrated
waste water treatment plants
Relative detailed level and high reliability thanks to
forecast of sludge discharged daily for the
concentrated waste water treatment plants
2.8 Assessing impacts caused by
environmental incidents
Relative detailed level and high reliability thanks to
assessments based on specific conditions of the
project
2.9 Assessing impacts on
environmental components
High detailed level and high reliability thanks to
assessments based on other contents of assessment,
use of rapid environmental assessment matrix
(RIAM) with support of computer software
4.4. EFFECT ON WATER QUALITY
4.4.1. Pollution load
At the maximum load of 1500 m3/day, the pollutant load in WW of Hoa Mac CETP can be
estimated as follows:
Table 4-18. The pollution load in WW of Hoa Mac IZ CETP
No. Parameter Concentration
(mg/l)
Pollutant load
(kg/day)
1 TSS 50 75
2 BOD5 30 45
3 COD 75 112.5
4 N-NH3 5 7.5
5 Total Fe 1 1.5
Note: The pollutant load is calculated by theory of WW quality after treatment that meets with
national standard QCVN 40:2011/BTNMT, column A (Kf = 1.0, Kq = 0.9)
4.4.2. Impact assessment on receiving source
The pollutant load will affect directly on receiving source that are Giat River and Hong River at
section passing Ha Nam province. Based on Table 4.18, after CEPT starts operating, a flow of
1500 m3/day will contribute into Giat and Chau Giang River. This average load is 75 kg SS, 45
kg BOD5, 112.5 kg COD, 7.5 kg ammonia and 1.5 kg total iron.
Polluted wastewater can cause the following impacts when it is discharged to the environment:
- Increase turbidity of the river flow due to SS; alter photosynthetic efficiency and reduce DO
in the surface water. Suspended solid could be deposited at the outlet, altering the river flow,
river depth and hydraulic conditions. Organic sludge depositing also causes oxygen deficient,
forming toxic gases like H2S, CH4, etc. If the receiving source is not cleaned properly, the water
will be changed to black and smelly.
86
- Increase organic pollution load (BOD5, COD), increase organic and inorganic compound
oxidization, reducing DO concentration in the water.
- Increase nutrients in the water (total N, total P), causing eutrophication.
- Reduce load bearing and purifying capacity of the river.
- Affect to drinking and production water quality.
4.5. EFFECT ON ENVIRONMENT AND AQUATIC ECOSYSTEM
- Increase turbidity, reduce DO to lead affecting to photosynthesis efficiency, altering number of
aquatic species in the water.
- Impact on food chain of the ecosystem.
- If the river could not purified, water will be polluted by organic substance and nutrients,
affecting seriously to aquatic life, reducing biodiversity (species number and density), etc.
narrowing habitat of small animal species in mangrove forest.
- Pollution of nutrients: Proper nutrient content will promote algae growing adequately in the
food cycle. However, if it increases significantly eutrophication will occur, causing organic
pollution.
- Nitrogen Impacts:
+ Toxic to fish at high concentration
+ Small NH3 concentration and NO3- are nutrients to algae growth.
+ Conversion of NH4+ to NO3
- needs large volume of DO.
- Impacts of Phosphorus:
Phosphorus is an essential nutrient for algae growth. High concentration will promote algae
growth. When algae died it will be organic food for bacteria, altering oxygen content, cause fish
dead.
- Organic Substance Pollution: reduce DO, threatening to fish and other aquatic species.
4.6. EFFECT ON HYDROLOGY
Following the data supplied by the Irrigation Department, Duy Tien district, Ha Nam
province, average flow rate (in August) of Giat river at the section through Ha Nam province is
around 22.36 m3/s, equally to 22,360 l/s.
The wastewater volume of CEPT of Hoa Mac IZ is about 1500 m3/day, equally to 17.36
l/s. This volume is not significant that can’t increase the water flow or the change hydraulic
regime of receiving source.
4.7. EFFECT ON AIR
The maximum capacity of CETP of Hoa Mac IZ phase 1 is 1500 m3/day. They could emit
odor, H2S, Hydrocarbons, Mercaptan among others affecting to areas near the outlet. However
currently there is no detected odor from the Hoa Mac IZ Treatment Plant’s discharges, and was
reflected through the surveying of residents living along project area. Hence it can be concluded
that the discharge wastewater does not affect local air quality.
87
4.8. EFFECT ON RISK AND ACCIDENTS
The large flow may cause a temporary disturbance of the channel and river, which may
cause dangerous, unsafe for small boats moving through the discharge sewer area. However as
small effluent of 1500 m3/
day, equally to 17.36 l/s and at Giat and Chau Giang River no boat is
here because these rivers are for agricultural irrigation and domestic water supply, therefore the
ability to happening risks and accidents is not reality.
4.9. SOCIAL – ECONOMIC IMPACTS AND DOWNSTREAM WATER USE
Wastewater from the treatment facility contains organic substances (BOD5, and COD),
causing turbidity increase in Giat River water, offensively odor at the outlet. The effluent
discharge can affect to socio-economic activities of residents living around effluent area.
However, with the discharge flow if 1500 m3/day and water quality after treating fitting national
standard of QCVN 40:2011/BTNMT column A (kq=1.0; kf =0.9) that influences are not
significant.
4.10. CUMULATIVE IMPACTS
The water quality and flow of Giat and Chau Giang River will be affected after
discharging WW of CETP of Hoa Mac IZ into there. The influence is not significant for rivers
because of small flow and water quality that meets national standard.
To analyze the accumulated impacts of the project toward Giat and Chau Giang River, we
will have to analyze the discharge receiving capacity of Giat and Chau Giang River. The
assessment will be based on Circular 02/2009/TT-BTNMT dated 19/3/2009 of the MONRE.
4.10.1. Giat River pollution load analysis
Pollution loads of Giat River can be analysed by the limits of polluting parameters in Giat
river water. It can be presented in table below:
Table 4-19. Pollutant concentrations of Giat River
Parameter BOD COD SS As Pb Cd Hg
Ctc (mg/l) 15 30 50 0.05 0.05 0.01 0.001
Note: Limitation value Ctc is based on QCVN 08:2008/BTNMT, Column B1
4.10.1.1. Maximum pollution load
The max pollution loads that surface water source can receive are calculated as below
equation:
Ltd = (Qs + Qt) x Ctc x 86.4
When:
- Ltd: Max pollution load of that water sources with a certain pollutants;
- Qs: Flow rate of Giat river Qs= 22.36 m3/s;
- Qt: Wastewater flow, Qt = 1500 m3/day = 0.017 m
3/s;
- 86.4 is the coefficient from (m3/s)x(mg/l) to (kg/day).
88
The max pollution load that nearby surface water sources can receive will be presented in
below table:
Table 4-20. The max pollution load that nearby surface water source can receive
Parameter BOD COD SS As Pb Cd Hg
Qs + Qt (m3/s) 22.377 22.377 22.377 22.377 22.377 22.377 22.377
Ctc (mg/l) 15 30 50 0.05 0.05 0.01 0.001
Ltd (kg/day) 29000.59258001.18 96668.64 96.669 96.669 19.334 1.933
4.10.1.2. Current pollutant loads
The current pollutant loads in the discharge source receiving is calculated as below
equation:
Ln = Qs x Cs x 86.4
When:
- Ln: Current Pollution Loads in receiving water body;
- Qs: Flow rate of Giat river, Qs= 22.36 m3/s;
- Cs: Max concentration of certain pollutants in the river before receives the waste water
discharge;
- 86.4 is the coefficient from (m3/s)x(mg/l) to (kg/day).
The current pollution loads will be presented in below table:
Table 4-21. The current pollution loads
Parameter BOD COD SS As Pb Cd Hg
Qs (m3/s) 22.36 22.36 22.36 22.36 22.36 22.36 22.36
Cs (mg/l) 10 25 118 0.0021 0.002 0.0002 0.0006
Ln (kg/day) 19319.04 48297.6 227964.7 4.057 3.864 0.386 1.159
Note: Cs is the average concentration of result of surface water quality of Giat river on
December, 10th
2013 that was periodic monitoring result of Hoa Mac IZ.
4.10.1.3. Pollutant load from discharge source
Pollutant load from discharge source will be calculated as below equation:
Lt = Qt x Ct x 86.4
When:
Lt: Pollution load in effluent (kg/day);
Qt: Wastewater flow rate, Qt= 0.017 m3/s;
Ct: Max concentration of pollutants in wastewater;
86.4 is the coefficient from (m3/s)x(mg/l) to (kg/day).
Pollution loads from discharge sources will be presented in below table:
89
Table 4-22. Pollutant loads from discharge sources
Parameter BOD COD SS As Pb Cd Hg
Qt (m3/s) 0.017 0.017 0.017 0.017 0.017 0.017 0.017
Ct (mg/l) 30 75 50 0.05 0.1 0.05 0.005
Lt (kg/day) 44.064 110.16 73.44 0.073 0.147 0.073 0.007
Note: Ct was calculated in hypothesis that water quality after treating is meeting with national
standard QCVN 40:2011/BTNMT, column A (Kf=1.0, Kq=0.9)
4.10.1.4. Giat River load receiving capacity
Giat River pollution load receiving capacity will be calculated as below equation:
Ltn = (Ltd – Ln - Lt) x Fs
When:
- Ltn: Giat River pollutant load receiving capacity (kg/day);
- Ltd: max pollution load of that water sources with a certain pollutants;
- Ln: Current Pollution Loads in receiving water body;
- Lt: Pollution load in effluent (kg/day);
- Fs: safety coefficient, Fs = 0.3 – 0.7, the project choice Fs = 0.5.
Giat River pollution loads receiving capacity after received the discharge from the CETP
can be summarized as below:
Table 4-23. Giat River pollution loads receiving capacity after received the discharge from the
CETP
Parameter BOD COD SS As Pb Cd Hg
Ltd (kg/day) 29000.592 58001.18 96668.64 96.669 96.669 19.334 1.933
Ln (kg/day) 19319.04 48297.6 227964.7 4.057 3.864 0.386 1.159
Lt (kg/day) 44.064 110.16 73.44 0.073 0.147 0.073 0.007
Ltn (kg/day 4818.748 4796.72 - 65684.8 46.269 46.329 9.437 0.383
Conclusion: Giat River, having received the treated wastewater from the IZ will still be able to
sustain the loads of parameters BOD, SS, As, Pb, Cd, Hg and remain within national standards.
SS levels are already over the river maximum pollution loads; thus the additional SS load will not
in themselves cause a change in water quality of the canal with respect to existing standards.
4.10.2. Chau Giang River pollution load analysis
Chau Giang river pollution load can be analyzed by the limits of pollutants in Chau Giang
River. It can be presented as below table:
Table 4-24. The limitation values of pollutants in Chau Giang River
Parameter BOD COD SS As Pb Cd Hg
Ctc (mg/l) 4 10 20 0.01 0.02 0.005 0.001
Note: Limitation value Ctc is based on QCVN 08:2008/BTNMT, column A1
90
4.10.2.1. Max Pollution load
Max pollution load that nearby surface water sources can receive, will be calculated using
below equation:
Ltd = (Qs + Qt) x Ctc x 86.4
Of which:
- Ltd: max pollution load of that water sources with a certain pollutants;
- Qs: Flow rate of Chau Giang river in dry season, Qs= 9.6 m3/s;
- Qt: Flow rate of wastewater, Qt = 22.317 m3/s (flow rate of Giat river + flow rate of CEPT of
Hoa Mac IZ);
- 86.4 is the coefficient from (m3/s) x (mg/l) to (kg/day).
The max pollution load that nearby surface water sources can receive will be presented in
below table:
Table 4-25. The max pollution load that nearby surface can receive
Parameter BOD COD SS As Pb Cd Hg
Qs + Qt (m3/s) 22.317 22.317 22.317 22.317 22.317 22.317 22.317
Ctc (mg/l) 4 10 20 0.01 0.02 0.005 0.001
Ltd (kg/day) 11030.52 27576.29 55152.58 27.576 55.153 13.788 2.758
4.10.2.2. Current pollutant load
The current pollutant load can be calculated as below equation:
Ln = Qs x Cs x 86.4
When:
- Ln: The current pollutant load in receiving water body;
- Qs: Flow rate of Chau Giang river in dry season, Qs= 9.6 m3/s;
- Cs: Max concentration of pollutants in the river before receiving the wastewater
discharge;
- 86.4 is the coefficient from (m3/s) x (mg/l) to (kg/day).
Calculation results of the current pollutant loads are presented as below table:
Table 4-26. The current pollutant load
Parameter BOD COD SS As Pb Cd Hg
Qs (m3/s) 9.6 9.6 9.6 9.6 9.6 9.6 9.6
Cs (mg/l) 1.55 2.86 15.8 0.002 0.002 0.0002 0.0005
Ln (kg/day) 1285.632 2372.198 13105.15 1.659 1.659 0.166 0.415
Note: Cs is the average concentration of result of surface water quality of Chau Giang river on
December, 10th
2013 that was periodic monitoring result of Hoa Mac IZ.
4.10.2.3. Pollutant load from discharge source
The pollution load from discharge source will be calculated as below equation:
Lt = Qt x Ct x 86.4
91
When:
- Lt: Pollutant load from discharge source;
- Qt: wastewater flow rate, Qt= 0.017 m3/s;
- Ct: Max concentration of certain pollutants in discharge;
- 86.4 is the coefficient from (m3/s) x (mg/l) to (kg/day).
The pollution load from discharge source will be presented as below table:
Table 4-27. The pollution load from Giat river into Chau Giang river
Parameter BOD COD SS As Pb Cd Hg
Qt (m3/s) 0.017 0.017 0.017 0.017 0.017 0.017 0.017
Ct (mg/l) 5.55 12.86 35.8 0.012 0.022 0.0052 0.0015
Lt (kg/day) 8.152 18.889 52.583 0.018 0.032 0.008 0.002
Note: Ct is average concentration of pollutants in the water quality results of Giat river and
concentration of wastewater after treating with hypothesis that they are meeting with national
quality QCVN 40:2011/BTNMT, column A.
4.10.2.4. Chau Giang River pollution load receiving capacity
Chau Giang river pollution load receiving capacity will be calculated as below equation:
Ltn = (Ltd – Ln - Lt) x Fs
When:
- Ltn: Chau Giang river pollution load receiving capacity (kg/day);
- Ltd: Max pollution load of that water sources with a certain pollutants (kg/day);
- Ln: The current pollutant load in receiving water body (kg/day);
- Lt: Pollution load from discharge source (kg/day);
- Fs: Safety coefficient, Fs = 0.3 – 0.7, the project choice Fs = 0.5.
Chau Giang river pollution load receiving capacity after receiving water from Giat River
(including discharge water from CETP of Hoa Mac IZ) will be presented as below table:
Table 4-28. Chau Giang River pollution load receiving capacity after receiving water from Giat
River and WW from the CETP of Hoa Mac IZ
Parameter BOD COD SS As Pb Cd Hg
Ltd (kg/day) 11030.52 27576.29 55152.58 27.576 55.153 13.788 2.758
Ln (kg/day) 1285.632 2372.198 13105.15 1.659 1.659 0.166 0.415
Lt (kg/day) 8.152 18.889 52.583 0.018 0.032 0.008 0.002
Ltn (kg/day) 4868.366 12592.6 20997.42 12.950 26.731 6.807 1.170
Conclusion: Chau Giang River, after received the treated wastewater from the IP and Giat River
will still be able to sustain the loads of parameters BOD, COD, SS, As, Pb, Cd and Hg.
Cumulative impact assessment was conducted for the CETP of Hoa Mac IZ. It is not enough
information to synthesize and evaluate impacts of Chau Giang River for the other projects in the
same valley.
92
CHAPTER 5: POLLUTION MITIGATION MEASURES
4.11. ENVIRONMENTAL MANAGEMENT PLAN (EMP)
The EMP is developed to help the Investor and contractors minimize the environmental impacts
during construction and operation phases of the Project. The units involved in the environmental
management process include:
Table 0-1. Concerned Agencies in the Environmental Management Programs
Agencies Main obligations
Construction
contractors
To implement Mitigation Measures against the proposed impacts.
To report Environmental Pollution Mitigation and Control Measures
to the Company.
The Company’s
Consultant
To supervise and evaluate implementation of the EMP proposed in
the EIA reports
To report Hoa Mac IZ Development Management Co., Ltd
Consultancy on
environment
monitoring
To supervise and evaluate the environmental quality on basis of
monitoring parameters proposed in the reports.
To implement interviews to the community to record feedbacks and
evaluations of local people on the Project’s EMP
To report Hoa Mac IZ Development Management Co., Ltd
Department of Natural
Resources and
Environment (DONRE)
To supervise and evaluate implementation of Impact Mitigation
Measures proposed in the construction phases via reports of Hoa
Mac IZ Development Management Co., Ltd on actual test results.
Environmental Codes of Practice (ECOPs) are encoded Environmental Impact Mitigation
Measures to help the units involved in environmental management processes easily identify and
manage these impacts, if any, during construction and operation phases of the project and the
environmental risks.
4.11.1. Construction phase
4.11.1.1. Water pollution mitigation measures
Domestic wastewater from the operations of the workers should be collected and treated before
being discharged into the septic tank to the environment. 200 liter mobile toilets are used as a
impact mitigation measure for domestic wastewater of workers.
To repair, maintaint and replace the construction equipment accessories, oil, clout that must be
collected comprehensively to avoid unexpected spilling on site.
To design rainwater drainage ditches surrounding the site to prevent from contamination of
impurities before discharging to the environment.
4.11.1.2. Mitigation Measures for Impacts of SW and HW
SW, during construction phase, damages building materials such as rubble, sand and gravel, dead
cement, the waste external protection devices, etc and domestic waste of workers on site as
protective objects, cement bags, etc. The SW must be treated in a regular, concentrated and
classified manner.
Construction waste: Limit to generate waste in construction by reasonable calculation and use of
raw materials; reminding workers the sense of saving, strictly management and supervision of the
works. The waste is inert, non- toxic agents such as broken bricks, sand residual sand and soil
93
which will be used for site clearance. The Contractors shall collect, classify and store
construction waste regularly in the prescribed locations on site. The storage locations must be
convenient for dumping. They are designed with hard walls, cover, and temporary drainage
ditches, etc to avoid losses and leakage of waste into the environment. The construction waste
will be transported everyday to proper sites. Other wastes such as cement bags, protective
equipment, steel pieces, welding rods, etc are collected and transported to designated places for
reuse or resale to the wanting units. The Project Management Unit or the contractors shall sign
the contracts with the functional units which are specialized in transportation of waste under strict
and regular supervision of the Project Management Board, environmental police, traffic and
public work management authorities, etc to avoid illegal dump of construction waste.
Domestic waste: Is concentrated in 500 liter dust bins near the tents and temporary works to
secure to protect the environment and hygiene and to sign the contracts with the local
Environment Service Suppliers to collect and dispose waste under current current regulations.
The created hazardous solid waste such as oily rags and wasted oil must be collected in the
specialized storage tanks and cans with sealed cover to secure hygienic storage and treated by
hired functional agencies.
4.11.1.3. Mitigation measures to the air quality
To use tarpaulins to cover the trucks’ boot during transporting construction materials such as
sand, stone on roads.
For materials with high dust pollutants (building sand), it is possible to moisten it, where
necessary, in order to minimize impacts on air.
To water to prevent from dusts in sunny, hot, windy days in the areas where dusts are created;
To arrange reasonable transportation routes. To check means of construction to secure the
equipment and machinery in the best engineering conditions;
To minimize reciprocal and accumulated impacts in construction activities of the Project and
operations of the existing CETP;
The vehicles getting out the site must be cleaned to prevent the air from soil spilling over the
roads;
The means of transportation must limit their speeds before getting in the project site;
To apply the appropriate construction methods, and to mechanize all operations during the
construction phase.
4.11.1.4. Impact Mitigation Measures for Soil Quality
The impacts during the construction phase of the Project on the soil are insignificant. Therefore,
the Investor does not implement soil pollution mitigation measures.
94
Table 0-2. Summarized plan for mitigation measures during construction phase
Issues Code Mitigation measures applied Vietnamese
code/regulation
Execution Supervision
Air pollution
WW1
Construction vehicles must undergo a regular
emissions check and get certificated named:
"Certificate of conformity from inspection of quality,
technical safety and environmental protection"
following Decision No. 35/2005 / QD-BGTVT on
21/07/2005;
• TCVN 6438-2005:
Road vehicles.
Maximum permitted
emission limits of
exhaust gas;
• Decision
No.35/2005 QD-
BGTVT on quality
control, technical
safety and
environmental
protection for
vehicles imported
into Vietnam.
• QCVN 05:
2009/BTNMT –
National technical
regulation on
ambient air quality
Contractors IZMB of Hoa
Mac
WW2 Maintant vehicles and equipment daily and every 6
months (or 8,000 km of road)
WW3 Do not burn waste on site
WW4 Monitoring air quality, exhaust emissions, dust, noise
and ambient air quality
Dust
Emissions
D1
Removing waste out of construction site as soon as
possible
• QCVN 05:
2009/BTNMT –
National technical
regulation on
ambient air quality
Contractors IZMB of Hoa
Mac
D2
Cover transport vehicles to prevent dropping of soil,
sand, materials or dust during the transportation.
D3 Contractor’s responsibility is to comply national
regulations on ambient air quality
95
D4
Contractors ensure the amount of dust emission that is
smallest and not being inconvenient for local residents.
Contractor’s responsibility is to carry out dust
controlling plan to maintain safety working
environment and mitigate the disturbance to the
residential / around housing.
D5
Contractor’s responsibility is to carry out measures to
mitigate dust emission as necessary as (such as
spraying car, spraying water on the construction road,
covering area of material storage, etc…
D6
Excavated soil and material storage expanse should be
covered to prevent dispersal by wind and the position
of the raw materials stockpile has to be considered
wind direction and the location of sensitive areas.
The
disturbance
of vegetation
and
ecosystems
TR1
The Contractor shall prepare measures to protect
vegetation outlined in the environmental management
plan approved by the building construction engineer,
according to relevant regulations. Clearance plan must
be approved by the Construction Supervision
Consultant and strict compliance by the contractor
• Law of
environmental
protection No.
52/2005/QH11
Contractors IZMB of Hoa
Mac
Noise and
vibration
N1 To avoid constructing in the night (10 pm to 6 am)
• QCVN
26:2010/BTNMT –
National technical
regulation on noise
N2
The contractor is responsible for compliance with the
relevant Vietnam legislation with respect to noise and
vibration
• QCVN
27:2010/BTNMT:
National technical
regulation on
vibration
96
N3
All vehicles must have appropriate "Certificate of
conformity from inspection of quality, technical safety
and environmental protection" following Decision No.
35/2005/QD-BGTVT to avoid exceeding noise
emissions from poorly maintained machines
Increasing
turbidity in
surface water
TU1 Ensure the technical requirements on wastewater
treatment and run-offs
Contractors IZMB of Hoa
Mac
TU2 Good management of soil erosion and sediment
Domestic
wastewater
of workers
WW1 Build temporary or use portable toilets in the IP (if
necessary) • QCVN
14:2008/BTNMT:
National technical
regulation on
domestic
wastewater
Contractors IZMB of Hoa
Mac
WW2 Build a septic tank (if required) and collect wastewater
and sewage when the construction finishes
WW3 Contractor has responsibility to comply Vietnam law
relating to wastewater discharged source
WW4
Wastewater over permissible values set by Vietnam
standards/regulations must be collected in a septic tank
and transported from the field by a unit licensed
collection
Drainage and
sedimentatio
n control
SW1 Periodic dredging of sewers • TCVN 4447:1987
National standard
on earth works,
codes for
construction,
check and
accetance.
• Circular
22/2010/TT-BXD
about safety in
construction work
• QCVN
08:2008/BTNMT -
Contractors IZMB of Hoa
Mac
SW2
To avoid water runoff containing sediment can affect
water resources, it is necessary to build works
decanting sludge, making slowly flow rate or changing
flow direction and sediment traps to create vegetation.
SW3
To ensure drainage system is always maintained, no
sludge and other obstructions and periodically check
the condition of the drainage system
SW4 To maintain the current conditions and not disturb the
position of the area by the construction activities
SW5
The excavation, digging and creating slope must be
maintained with the appropriate specifications of
construction for the outfall
97
SW6
The Contractor shall comply with the detailed design
of the drainage system including construction plan,
recommence to prevent rain caused local flooding or
erosion of soil in the area protected, resulting in
sediment affect local water (drainage layout of the area
around the building to collect rainwater runoff or
sediment deposition ditch before flowing to water
source)
National technical
regulation on
surface water
quality
Underground
water
pollution
caused by
leackage of
wastewater
GW1 Leackages in the drainage system must be detected and
repaired promptly
QCVN
09:2008/BTNMTNati
onal technical
regulation on
underground water
quality
Contractors IZMB of Hoa
Mac
Solid waste
management
W1
Prior to construction, process of control solid waste
(storage provide bins, schedule collection and disposal,
etc.) must be prepared by the contractor and the
construction management plan and monitored carefully
during construction.
• Decree
59/2007/ND-CP on
solid waste
management
Contractors IZMB of Hoa
Mac
W2 Prior to construction, all discharge permits must be
passed
W3
Solid waste can be temporarily stored at the site in an
area approved by the construction supervision and
local governments and related IZMB to collect and
treat. In case if it is not removed from the construction
site, solid waste or construction waste will be treated at
the site determined and having the acceptability of the
construction supervision consultant inline with solid
waste management plan. In all cases, the contractor
shall not dispose of any materials in sensitive areas,
natural environment or water sources.
W4
Waste storage area must be covered, waterproof,
weather protected and closed to the animal
scavengers.
W5 No burning, disposal or dumping of solid waste
98
Chemical
and
hazardous
waste
HW1
Chemical waste in any form must be disposed of in
appropriate landfills approved and according to the
request of local authorities. The contractor must have a
certificate of hazardous treatment treatment.
• Regulation No.
23/2006/QD-
BTNMT: List of
hazardous waste
• Circular No.
12/2011/TT-
BTNMT: About
Hazardous Waste
Management
Contractors IZMB of Hoa
Mac
HW2
Used oils, lubricants, cleaning materials, etc. from
vehicle maintenance and machinery will be collected
in the tank and removed from the field by companies
in the recycling and disposal of hazardous waste
approved.
HW3
The relevant authorities (IZMB and the Department of
Natural Resources and Environment) promptly notify
the case of oil spills, chemical, or incidents. Prepare
and start remedial measures after any oil spill problem
or accident. In this case, the contractor shall provide a
report assessing, remedial activity done, the
consequences / damage from the spill, and proposed
measures overcome.
HW4 Toxic chemicals stored properly and labeled and
locked containers.
HW5
To propagate, training to raise awareness and response
measures for workers about toxic chemicals in the
workplace
Traffic
management
Prior to construction, making the consultation with
local governments, communities and the traffic police
• Road Traffic Law
No.
23/2008/QH12
• Construction Law
16/2003/QH11
• Circular
No.22/2010/TT-
BXD: egulations
on labor safety in
construction work
Contractors IZMB of Hoa
Mac
99
Safety for
workers and
residents
HS1
Limiting speed at construction site
• Circular No.
22/2010/TT-BXD:
Regulations on
occupational
safety in
construction work
• Directive
02/2008/CT-BXD
reorganize and
strengthen
measures to ensure
occupational
safety, ccupational
health units in the
building industry
• TCVN 5308-91:
Technical
regulations for
safety in
construction
• Decision No.
96/2008/QD-TTg
of demining.
Contractors IZMB of Hoa
Mac
HS2
Avoid transport during peak hours to reduce traffic
congestion
HS3 Installation of lighting at night
HS4
Equip workers with protective equipment
(eg equip with ear plugs and use in case having noise
in the work area by installation of pipe, mixing,.., to
control noise and protect workers)
TCVN 5308-91:
Technical regulations
for safety in
construction
• Decision No.
96/2008/QD-TTg of
demining. HS5
Training workers on safety regulations and ensuring
their compliance
HS6 Ensure safety of construction site , security and order
HS7 Provide protective clothing or protective gloves if they
expose to chemicals and sludge
100
HS8
Prepare and implement action plans to deal with risks
and emergency situations (ie in complex situations,
stopping construction and implementation of necessary
measures) as well as preparing services emergency at
construction site.
HS9 The Contractor shall comply with the regulations of
Vietnam on labor safety.
Communicat
ion with the
local
community
C1 Provide local communities and workers at the site with
the ECOPs (Vietnamese) and the project
Environmental Protection documents related
• Decree No.
73/2010/ND-CP:
The sanctioning of
administrative
violations in the
field of security
and order, social
security
Contractors IZMB of Hoa
Mac
C2 Dissemination of information of the project for
affected groups (such as local governments, businesses
and households affected, etc.) through community
meetings before starting construction, supply mode of
contact from that point the interested parties can get
information about the active site, project status and
results of the project;
Provide all the information, especially technical
solutions, with understandable language for the general
public and information for interested citizens and
officials through the preparation of an information
sheet and informed in the press while conducting the
work of the project.
C3 To supervise community related and require
information as well as the progress of the project;
C4 Feedback telegrams and letters written timely and
accurately
101
4.11.2. Operation phase
4.11.2.1. Impact Mitigation Measures for Water Pollution
(1). Industrial wastewater
For industrial WW, factories in IZ are required to use pre-treatment technology to make sure that
industrial WW reach column B of QCVN 40:2011 before connecting to the CETP.
Treated WW quality must be supervised to reach the Regulation QCVN 40:2011/BTNMT
(Column A) before discharging into the receiving source.
The Investor installed the AMS, it is possible to control such parameters as flow rate, pH, DO,
TSS, COD after treatment.
(2). Domestic WW
Domestic WW from toilets of the CETP operators shall be collected and treated by septic tanks.
(3). Rainwater
Rainwater is collected on basis of the general rainwater drainage system of the IZ via culverts on
sidewalks.
(4). Groundwater
To monitor and control the groundwater quality in the region; to prevent penetration from
anaerobic tank and leakage in the connection points or transitions in WW pipelines
(5). Pollution in outlets
To regularly monitor water quality at the outlets;
To construct warning signs at appropriate locations;
To regularly dredge manholes, drainage system;
To reduce the risks of overflow of WW;
To regularly check preliminarily treated WW quality of tenants.
4.11.2.2. Impact Mitigation Measures for Sludge
The waste sludge generated by Hoa Mac IZ’s CETP is collected, transported and treated by
URENCO 11 under the Contract signed with the Investor and the regulations.
Waste sludge Transportation process from Hoa Mac IZ’s CETP
Sludge from WW treatment process of Hoa Mac IZ’s CETP is dewatered via sludge compressor,
then packed to secure to cause no leakage to the environment and labeled to warn HW before
storing in the slugde warehouses.
URENCO 11 Company shall periodically collect hazardous sludge. Use of specialized vehicles
for transportation of hazardous sludge may reduce leakage along the route from Hoa Mac IZ’s
CETP to the treatment area of URENCO 11 because dust may contain heavy metals and
pathogens that cause diseases, pollutions to foods and others skin and respiratory diseases.
Workers must be equipped with appropriate protective clothes and avoid exposing their open
injuries to the sludge.
102
4.11.2.3. Impact Mitigation Measures for Air
The impacts on air environment in operation phase of the Project are mainly considered in the
following aspects: Noise, toxic gases, bad odors arising from biological treatment tanks.
However, the noise and odors generated in the CETP are expected to be difficultly spread to the
residential areas if application of the buffer area under Vietnamese current Regulation QCXD
01/2008/BXD. Radius of the buffer area must be at least 300 m so that the odor and gas
emissions in the treatment area shall be less absorbed and dispersed
Other mitigation measures include:
- To relief noise caused by operations of machinery by periodical maintenance and correct
use of design capacity;
- To periodically monitor the air environment surrounding the CETP’s region;
- To grow more trees in the buffer zone to create the landscape and to prevent from
spreading odors;
- To handle incidents or accidents during operations;
- To clear the site surrounding the artificial ditch in the IZ.
4.11.2.4. Impact Mitigation Measures for Soil Quality
The operation of the Project does not affect the quality of soil, thus, the Investor does not need to
apply soil pollution mitigation measures.
4.11.2.5. Impact Mitigation Measures for SW
SW generated in the operation phase is mainly Domestic waste of operators; packages, bottles,
chemical containers, biological membrane.
The Domestic waste must be daily collected and transported under the provisions issued by Hoa
Mac IZ Management Board.
Such SW as packages, bottles, chemical containers, biological membrane must be classified and
labeled, then periodically collected and processed in accordance with current regulations.
103
Table 0-3. Summarized plan for mitigation measures during operation phase
No Impacts Code Intensity Mitigation measures Execution Supervisors Source of
funds
Difficulties /
barriers
1 CETP Outlet
discharge/
Effluent
pollution
OD1 Long-term - Regular monitoring the
effluent and river water
quality at the outlet discharge
- Set up warning signs at
suitable locations
- Regular dredging manhole,
sewer
- Reduce the spilling of WW
- Control effluent from
industrial activities in the IZ
before entering the CETP
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
The operating
budget of
Hoa Mac
IZMB
- Worker’s
awareness
- Factories and
tenants in IZ
2 Groundwater
pollution
OD2 Long-term - Monitoring and controlling
groundwater quality in the
area
- Prevent penetration of
anaerobic tank leackage
- Preventing leakage at
connections or transitions in
the WW pipes
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
The operating
budget of
Hoa Mac
IZMB
3 Operational
problems
OP1 Long-term - Training O&M for workers
- Monitoring of water quality
to evaluate the efficiency of
the operation
- Installing the signs to warn
people of the risks relating to
the water bodies
- Noticing the communication
means
- Repairing as soon as
accident happens
- Building bio-pond
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
Lack of
training for
employees
104
4 Odor O1 Long-term` - Ensuring the radius of
buffer zone at least 300m
- Planting trees in the buffer
zone to create landscape and
prevent odor emission
- Regular maintenance of
treatment units
- Solving operational
accidents timely
- Clearance of surrounding of
the ponds
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
Lack of budget
for training
O&M
5 Noise N1 Long-term - Planting trees
- Appropriate O&M regime
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
6 Waste from
operation
WO1 Long-term - A good plan of collecting
and treatment
- Training for workers
- Regular collection of sludge
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
7 Sludge
management
MS1 Long-term - Checking sludge quality in
order to have a suitable plan
- Drying and using as
fertilizer or treating at landfill
based on sludge quality
(analyzed)
- Reducing the leakage along
the haulage distance because
dust could bear heavy metals
and pathogens which results
in food contamination and
diseases related to skin and
respiratory system
- Workers must be equipped
with appropriate safety
clothes and prevent sludge
contact to open wounds:
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
Lack of
transportation
105
gloves, clothes and glasses.
- Dry sludge will be treated in
landfill or buried as sludge
quality doesn’t meet
standards
8 Health and
Safety
HS1 Long-term,
frequently
- Training working safety and
industrial sanitation
- Periodic checking health for
workers
- At least two workers
working in an operating shift
- Keeping a good personal
hygiene
- Prepare specific guidelines
for operation of CETP
CETP
operation
Unit
Hoa Mac
IZMB, Ha
Nam DONRE
106
4.12. RISK MANAGEMENT
The quantity of work of the Project is small and short-term so it is easy to control and
prevent from environmental damages by applying below measures:
4.12.1. In the construction phase
(1). Fire & Explosion Prevention and Fighting
The workers on site must be trainned and instructed in term of Fire & Explosion Prevention and
Fighting Measures;
The flammable solvents and fuels are stored in separate warehouse, and kept away from the
potential sources of ignition and spark-ignition;
Investment in fire & explosion resistant equipment in the fuel storage area on site;
Fully equipping fire & prevention equipment in accordance with current laws and regulations;
In case of any fire incident, the Investor shall coordinate with Ha Nam Province Fire Fighting
Committee to respond to the incident.
(2). Traffic Accident Mitigation Measures
Regulating the means of transport in the project reasonably and correctly transporting;
Communicating and stimulating officers and workers as well as owners of vehicles to well
comply with traffic safety laws and regulations.
(3). Traffic safety control, health care and incident prevention and fighting measures
In compliance with regulations on labor safety when making the construction organization plan,
i.e. construction measures; machinery and equipment outline, labor accident prevention
measures, workers’ use of personal protective equipment such as helmets, masks, gloves,
protective clothes, goggles, shoes, boots as working on site;
Closely monitoring the construction phase under the required procedure, minimizing labor
accidents;
Building fire prevention and fighting programs and sufficient devices equipped to handle any
incident.
4.12.2. In the operation phase
4.12.2.1. Labor safety and hygiene measures
Safety to the equipment:
The CETPs’ equipment consists of many types, depending on the features, structure and function
that IZ Management Board will conduct labor safety control activities under the State’s
Regulations;
The IZ Management Unit shall install the lightning systems at the highest position of the plant to
secure safety to the Plant and labor safety, especially lightning safety in wet seasons;
For devices requiring power supply and sufficient protection system, earth wire, checking their
safety before operation. In addition, the IZ Management Unit shall establish the Power Safety
Regulations to the Plan under the provisions;
For all other machinery systems in the plant, the IZ Management Unit shall establish the
107
Regulations for each equipment on basis of their structure, capacity, and few unique features of
each equipment to secure safe operations.
Labor safety for workers:
Training and guidance for workers to know to operate the Plant safely. On the other hand, the
Investor shall coordinate with the Labor Safety Committee of the Department of Labor, Invalids
and Social Affairs of Ha Nam Province to provide trainings on safety rules and operation of
specific equipment in each stage of production to facilitate the workers to fully understand their
working position and steps to do to secure safety in production;
Sufficiently equipping and provision of personal protection equipment to workers on basis of
layout of workers in each stage of production in line with their jobs.
In addition to the above mentioned pollution control methods, the pollutant mitigation measures
for the workers’ health in the Plant shall be applied comprehensively as follows:
- To well follow the programs on periodical checking and monitoring programs to
the officers and workers in the plants;
- To secure microclimate factors and working conditions to meet the requirements
and standards issued by Ministry of Health to secure workers’ health;
- To control noise to meet requirements and to avoid occupational diseases created
by production process;
- To provide trainings and information on hygiene and safety.
4.12.2.2. Preventive measures and Fire & Explosion Response
Fire & Explosion Safety Control Measures:
Fire safety measures:
There is fire resistant equipment to timely cure the problem occurred;
Workers will be provided with trainings, guidance of fire & explosion prevention and fighting
measures;
The flammable fuels are stored in separated warehouses, kept away from potential ignition
sources, the solvent storage tank will be installed with the safety valve, the temperature
monitoring device, automatic fire alarms;
There are fire alarm systems, communication systems, alarms. The fire-fighting equipment will
be checked regularly and always in a ready state;
The workers are not permitted to smoke or bring lighters, matches, ignition tools via friction,
sparks, etc in flammable areas;
Investment in fire & explosion-proof equipment, layout of fire extinguishing systems around the
region.
Equipment:
The fire extinguishing system is provided, including:
- Water intake system for fire fighting;
- Steam extinguishers, foam extinguishers;
108
- Fire resistant equipment and boxes for all plants;
- Water supply for fire fighting, including lakes and nozzles and pumps;
For the Operating House:
Providing suction equipment, exhaust fan system for ventilation;
The electrical system is designed and installed with safety devices; Regularly checking to
discovery of short-circuit and power failure;
The flammable areas such as warehouses of materials, chemicals, etc will be provided with the
automatic fire alarm systems, water tanks, sand to extinguish the fire. Sufficient provision of fire
extinguishers and fire fighting equipment
Fire & explosion prevention, fighting response procedure:
In the flammable areas, it is required to install fire alarms, communication system, alarms. The
fire-fighting equipment will be checked regularly and always in a ready state;
The machinery, equipment working in high temperature and pressure is required to periodical
check and register;
The fuel types are stored in separated wareshouse which is kept away from potential sources of
ignition and spark. Safe distance among the works is about 12-20 m for fire trucks to easily
approach;
The workers are not permitted to smoke or bring lighters, matches, ignition tools via friction,
sparks, etc in flammable areas;
IZ Management Unit shall coordinate with the Fire Fighting Committing of Ha Nam Province to
construct the fire fighting plan and to arrange the functional team and workers to practice under
the established plan.
4.12.2.3. Preventive measures and Fuel Leakage Response
To prevent and respond to fuel (diesel oil) leaking incidents, the Investor will cooperate with the
functional authorities to strictly control the engineering systems of storage equipment, means of
transportation and to establish the response plans, as follows:
- To regularly check the safety of the fuel tanks to repair, replace and restore fuel leakages
promptly;
- To make the fences around fuel tanks, to place fire and combustible materials warning
signs , prohibition signs in the distance of 5- 10 m from the tanks;
- Means of transportation of petroleum, chemicals (such as tank trucks) will be eligible
and satisfactory to the current safety standards, technical regulations as transporting on
roads;
- To propagandize and remind officers and workers on the Plant to comply with the
Regulations on Fire Prevention and Fighting during the working process.
On the other hand, to prevent and treat fuel and chemical leakage incidents effectively, the
Investor will cooperate with authorities to prepare the prevention measures, responds, supervision
and strict test to the engineering equipment in the warehouses, means of transportation of fuels
and chemicals.
109
4.12.2.4. Lightning system
Installation of anti-lightning systems in the highest position of the plant to attract lightning in
rains and storms;
Installation of the lightning and static electricity collection system and improve the systems on
basis of new technologies to secure high safety to the Project’s operations;
Pulse ground resistor <10 Ω as soil resistor < 50,000 Ω/cm2. Pulse ground resistor > 10 Ω as soil
resistor > 50,000 Ω/cm2;
Installation of the general lightning protection systems to entire project site and each plant,
warehouse;
Use of positive lightning arresters, lightning pillars which are arranged to protect entire project
with the design height of 10 – 14m;
Investment on basis of infrastructure construction progress.
4.12.2.5. CETP’s Non-operation Response
CETP’s non-operations are caused by suspension of machinery and equipment of the station such
as pump, agitators, chemical magnet machine, etc (due to malfunction or power failure). The
other reason is due to workers’ dissatisfactory operation to cause the death of microorganisms so
the CETP has to temporarily suspend its operations to grow them again. This will cause a large
amount of stagnant and untreated WW and environmental pollution.
This problem can be prevented by regular and periodic inspection of the technical conditions of
the operating equipment, timely repairing and replacing damaged machinery. The operators must
be provided with full technical trainings
When the incident occurs, the Investor will receive discharge of the plants with arising effluents
to the CETPs in allowable time.
110
Table 0-4. Summarized plan for mitigation measures for environmental risks
No Issue/Case Action plan/Mitigation measures Execution
1 Complaints from nearby industries and
community on environmental issues of
construction and operation activities
Immediately implement remedial measures if possible
Record in the logbook
Contractors
Discuss with investors, local government to solve
thoroughly the contradictions
Contractors, Hoa Mac
IZMB, Ha Nam DONRE,
PC49
2 Construction or operational accidents First aid and immediately transfer the victim to the nearest
hospital if necessary
Workers and residents
Having warning signs
Making record of the accident
Contractors, CETP, Hoa
Mac IZMB
3 Failure operation of CETP Storage the untreated WW, building bio-pond if possible CETP, Hoa Mac IZMB
Have back-up equipments/facilities
Having the danger signs and report to authorities
Avoid over waste loading from enterprise’s WW
Training the staff on operation, regularly monitoring
Check the design and prepare the new unit of CETP
Prepare for accidental response action plan
4 Improper sludge disposal Contract with relative permitted agencies to disposal
sludge properly if they are found to be hazardous to
environment and human health
CETP
Report and check frequently all emitted amount of sludge
Issue the strict penalties for violation cases
5 Fires Inform authorities (in particular, is that fire police).
Rescue the objects in the danger zone.
Actively isolate the fore with the existing facilities on site.
Contractors,
tenants/industries, CETP,
Hoa Mac IZMB
Support under the guidance of the functional units until
they are present at the scene (especially in situations detect
mines, explosion caused by chemical substances etc).
Contractors, CETP, Hoa
Mac IZMB, industries
Support functional units, local government to set up
security perimeter around hazardous areas.
Contractors,
tenants/industries, CETP,
Hoa Mac IZMB
Check the conditions of fire and explosion safety on site,
ensuring the problem does not continue
Contractors,
tenants/industries, CETP,
111
Suspension of work if they violate conditions of fire safety Hoa Mac IZMB
6 Electric accidents Disconnect power sources in the incident area and
surrounding areas.
Immediate rescue the objects in the danger zone.
Contractors,
tenants/industries, CETP,
Hoa Mac IZMB
Explore the causes of accidents, checking power sources,
wires and contacts etc.
Make records of accidents Contractors,
tenants/industries, CETP,
Hoa Mac IZMB
7 Floods Disconnect power sources in the incident area;
Immediately transfer the machinery out of the floodplain to
avoid damaging by water.
Implement measures in any way to prevent flood water into
WW storage area to prevent it mixing with floodwater that
cause secondary pollution.
Contractors,
tenants/industries, CETP,
Hoa Mac IZMB
112
4.13. COMMUNICATION PROGRAM TO THE COMMUNITY AND COMMUNITY
RELATIONS
The Investor shall make, submit and popularize the EMP in the Headquarter of People’s
Committees of Chau Giang Commune, Trac Van Commune and Hoa Mac Town during the
process of construction and operation of Hoa Mac IZ’s CETP, Phase 1 for public awareness,
supervision and test.
The EMP consists of the following contents:
Organization and operation of the departments in charge of environmental protection
of the project
Planning education, raising public awareness on environmental protection of the
project;
The Investor’s responsibilities for implementation of the solutions, impact mitigation
measures, prevention and response to environmental incidents during the construction
phase and operation of WW treatment systems;
Planning and operation of environmental protection facilities;
Planning and monitoring of emissions; monitoring ambient environment and other
contents during the construction phase and as the CETP is officially operated.
4.14. TRAINING
To strengthen the capacity to respond to environmental incidents which may occur in Hoa Mac
IZ’s CETP, Phase 1, the Investor will implement the following measures:
- The workers who directly work at the CETP shall be trained and guide in terms of
fire & explosion prevention measures.
- Organization of training, assigning tasks to respond to the CETP’s non-operation.
However, this problem can be prevented by periodic inspection of the technical
condition of the operating equipment, timely repairing and replace damaged
machinery, and the workers are trained fully in term of engineering aspects.
- Equipping with sufficient tools and personal protection equipment to workers in
line with their jobs and on basis of labor outline in each operation stage.
- Training and guidance for workers on labor safety in the Plant.
- To know about the safety of the plant. On the other hand , IZ Management Board
will coordinate with the Safety Committee of the Department of Labor , War
Invalids and Social Affairs of Henan Province training safety rules and operation
of specific equipment of each stage of production to workers actually grasp and
understand its working position need to do to CETP operation is safe
- Training and guidance for workers to know to operate the Plant safely. On the
other hand, the Investor shall coordinate with the Labor Safety Committee of the
Department of Labor, Invalids and Social Affairs of Ha Nam Province to provide
trainings on safety rules and operation of specific equipment in each stage of
production to facilitate the workers to actually understand their working position
and steps to do to secure safety in production;
113
In addition to the above solution, the plans are issued and applied to comprehensively mitigate
impacts of pollutants to the worker’s health in the CETP as follows:
- To well implement the periodic health examinations to the officers and workers in
the Plant;
- To make sure the microclimate factors and working conditions issued by the
Ministry of Health to secure the health of workers
- To control noise under the regulations to prevent from occupational diseases
caused by the production process
- To train and supply the information on safety and hygiene.
4.15. ENVIRONMENT MANAGEMENT ORGANIZATIONS AND RESPONSIBILITIES
FOR THE IZ AND CETP
4.15.1. Division of Environmental Affairs
Division of Environmental Affairs is directly under Hoa Mac IZ Management Unit with the
following designated functions and obligations:
4.15.1.1. Functions
To advise the Director on environmental management, WW treatment plant of the Company and
implement environmental consulting services to clients.
To propose plans, solutions and implementation organization for environmental works, the
operation of the WW treatment plant and environmental consulting services to the companies
inside and outside Hoa Mac IZ.
To coordinate with other functional units and customers to closely manage the environment
affairs of the IZ under "the Regulation for industrial parks, processing zones, hi-tech parks"
attached to the Decree No. 36/CP dated 24th
April 2007 of the Government and the current
regulations.
To organize implementation of operations of the CETP and others relating to the environment in
the IZ.
To test, monitor, operate and restore any incidents of the Station and ww quality of the plants and
tenants in Hoa Mac IZ before discharging to the CETP.
To bear responsibilities for treating ww of Hoa Mac IZ to reach Vietnamese Environment
Standards before discharging to the environment.
To manage, operate and exploit functions of the CETPs to secure their effective operations.
4.15.1.2. Obligations
To construct plans, to organize operations of CETP and projects, economic contracts related to
the environment affairs to submit to the Director for approval and to organize implementation.
To monitor by records, to check and supervise land lessees’ compliance with the Environmental
Protection Act; to correctly follow the Business Registration Certificate. To apply the Quality
Management System ISO 14001:2004 in the Company
To exploit available resources, the effect of innovations, advances in science, technology and
environment in business of the CETP to manage, operate and exploit the Station effectively
114
To test, monitor and restore incidents and quality of WW of the CETP and units, plants in the IZ.
To treat WW of Hoa Mac IZ to reach Vietnamese Environment Standards before discharging to
the environment
To coordinate with the Department of Engineering Infrastructure in maintenance of infrastructure
works and technical troubleshooting of WW systems in the Company’s control.
To coordinate with and implement the environmental consulting services; to purchase and sell
scrap; to provide design consultancy, construction supervision services to connect to the WW
system of the Investors in Hoa Mac IZ and clients under the signed economic – engineering –
technology – environment contracts.
To carry out other duties as assigned by the Company's Director.
To implement the Regulations on Organization and Operation of the Company to promote
production and business
To construct operation plans, develop business in line with each phase and assigned duties to
submit the Director for approval and to organize implementation.
To exploit all available resources, to research applications, initiatives and technological, scientific
advances to operate and exploit the machinery and equipment in business
To implement design consulting services, connection, construction, and construction supervision
to connect to the WW system of the Investors in Hoa Mac IZ
To operate and maintain WW infrastructure and the CETP under the Company’s control.
To effectively manage and exploit assets, capitals assigned by the Company in the principle of
continuous improvement of efficiency in production and business.
To correctly comply with the communication – reporting regulations and requirements of the
Company
4.15.2. Departments working in the CETP
4.15.2.1. Functions
To manage and monitor compliance with the environmental regulations under "the Regulation for
industrial parks, processing zones, hi-tech parks" attached to the Decree No. 36/CP dated 24th
April 2007 of the Government. To advise the Director of the Company on matters relating to the
environment work of Hoa Mac IZ; to organize implementation of operations of the CETP and
others relating to the environment in the IZ.
To test, monitor, operate and restore any incidents of the Station and ww quality of the plants and
tenants in Hoa Mac IZ before discharging to the CETP.
To bear responsibilities for treating WW of Hoa Mac IZ to reach Vietnamese Environment
Standards before discharging to the environment.
To manage, operate and exploit functions of the CETP to secure their effective operations
4.15.2.2. Obligations
To implement the Regulations on Organization and Operation of the Company to promote
production and business
To construct operation plans, develop business in line with each phase and assigned duties to
submit the Director for approval and to organize implementation.
115
To exploit all available resources, to research applications, initiatives and technological, scientific
advances to operate and exploit the machinery and equipment in business
To implement design consulting services, connection, construction, and construction supervision
to connect to the WW system of the Investors in Hoa Mac IZ- Phase 1
To operate and maintain WW infrastructure and the CETP under the Company’s control.
To effectively manage and exploit assets, capitals assigned by the Company in the principle of
continuous improvement of efficiency in production and business.
To carry out other obligations assigned by the Board of Directors
4.16. ENVIRONMENTAL MONITORING PROGRAM
Purposes
- To control impacts during the construction phase, which is shown in the EIA report and
to check compliance with the environmental standards.
- To check implementation of environmental protection measures during construction and
operation phases on basis of approved EIA report.
- To propose additional mitigation measures if discovery of new impacts.
- To require the Investors to coordinate with the Government’s environmental
organizations in the local and central levels to solve the existing problems related to
environmental protection in the responsibility of the project.
- To assess effectiveness of impact mitigation measures before construction and
operations of the Project.
- To monitor the environment in the construction and operation phases in 4 levels.
4.16.1. Monitoring compliance with mitigation measures and environmental standards
After EIA is appraised by Vietnam Environment Protection Fund (VEPF) and WB, construction
site-specific environment management plans (CEMPs) shall be developed on basis of EMPs by
the Investor. When the CETP is operated, it is required to prepare and submit the reports on
current status of environmental quality to VEPF and WB, including summary of key environment
management issues, mitigation measures, implemented actions and results as well as compliance
with the Regulations and Standards on Environment.
4.16.2. On basis of the Community’s monitoring
The community shall monitor the projects in their process to secure their CETP to comply with
the regulations on environmental and social affairs to risks issues of environment pollution and
serious health to humans and ecosystems.
Supervisor
01 people
Lab staff
01 people
Operational staffs
03 people
Maintenance staff
01 people
116
Making monitoring methods in the spirit of voluntary reporting solving urgent problems
When environmental degradation occurs, local people and authorities will report to the agencies.
4.16.3. Monitoring the Project’s completion of indexes
IZ Infrastructure Development Company is responsible for reporting the following information to
the Department of Natural Resources every six months:
− Health indexes of workers;
− Water quality in the receiving source;
− Quality of ambient water environment;
− Effective operations of the CETP (WW and sludge treatment)
− New impacts and risks to the environment and health.
− Reports on WW discharge to submit to division of water resource management directly
under the Department of Natural Resources & Environment (DONRE).
− To monitor environment quality to send to DONRE
− To report hw management to send to SW Management Division of DONRE.
4.16.4. Environment Quality Monitoring (EQM) Indexes
Environmental Monitoring Program (EMP) is carried out in 2 phases: Construction phase (it is
proposed to extand in 1 year), operations of the CETP are shown in Table 5.5. For other
indicators, the ETP manager must measure other targets on basis of the required list in the EIA
license. The location monitoring maps and GPS information should be included in the EMP
reports.
Table 0-5. Environmental Monitoring Program
I CONSTRUCTION PHASE
1 Monitoring of air quality and noise
Parameters and
frequency
Once for 3 months or at the time of accident: PM10, total
particles, noise (24 hours in average) NOx, SO2, CO
Position Proposed location of CETP
Compared to QCVN 06:2008, QCVN 26:2010
2 Monitoring of groundwater quality
Parameters and
frequency
Once for 6 months; pH, color, hardness, SS, Cl-, NH4+,
Xyanua, NO3-, NO2
-, Sulfate, Fe, Mn, As, E.Coli, Total
Coliform;
Position 01 location in the Project’s site
Compared to QCVN 09:2008/BTNMT
3 Monitoring of WW quality
Parameters and
frequency
Once for every 3 months; pH, BOD5, COD, SS, Ammonium,
Phosphate, Chloride, surface active agents, oil and grease
Position 1 proposed position at the tents for workers
Compared to QCVN 14:2008/BTNMT
II OPERATION PHASE (This Program shall be implemented simultaneously with the monitoring program of IZ.
117
Therefore, some repeated parameters and position may be cancelled to avoid repetation)
6. Monitoring of air quality
Parameters and
frequency
Once for 6 months or at the time of acciden: temperature,
dust, noise (24 hours in average), CO, SO2, NO2, NH3, H2S,
CH4, VOC
Position Proposed location of CETP
Compared to QCVN 06:2008, QCVN 26:2010
7. Monitoring of surface water/river quality
Parameters and
frequency
Once for 3 months in the first operation year
Once for 6 months in the following years or at the time of
accident: pH, DO, BOD5, COD, SS, Coliform, turbidity, oil
and grease, N-NH4, N-NO3-, Cl
-, P-PO4
3-, SO4
2-, heavy metals
(As, Pb, Hg, Cd, Ni, Cr (III), Cr (VI), Cu, Mn), and surface
active agents.
If AMS is applied, such indexes as pH, TSS and COD shall
be automatically measured in case of incident or accident.
Position 4. 1 km upstream of discharge point of CETP
5. Discharge point of CETP
6. 1 km downstream of the discharge point of CETP
Compared to QCVN 08:2008
8.
Monitoring of groundwater quality
Parameters and
frequency
Once for 6 months: pH, TDS, turbidity, hardness, N-NO3, N-
NO2, total Fe, Cl-, N-NH3, SO4
2-, E. Coli, Coliform
Position Groundwater near the CETP
Compared to QCVN 09:2008
9. Monitoring of WW quality
Parameters and
frequency
AMS: pH, COD, TSS, and flow rate (continually monitoring)
at effluent discharge point.
Once per month in the first operation year of the CETP
Once for 3 months as the system is operated stably:
temperature, pH, BOD, COD, TSS, TDS, color, N-NH4, total
N, total P, alkali, KLN (As, Hg, Pb, Cd, Ni, Cr (III), Cr (VI),
Cu, Mn, Sn), oil and grease, total CN-, total phenol, chloride,
sulfur, fluoride, residual chloride, total pesticide (organic
chloride and phosphorus or organic matters), total PCB and
coliform.
Position 1. Influent of CETP
2. Effluent of CETP
Compared to QCVN 40:2011
10. Monitoring of sludge quality
Parameters and
frequency
Once per month in the first operation year
Once for 3 months: pH, Pb, As, Cd, Hg, Al, total Fe, Ni, Cu,
Zn, Mn, phenol, PAH, total nitrogen, total phosphate, CN-, và
Coliform.
Daily monitoring the quantity of waste sludge
Position 1. In sludge dryer yards
2. In the sludge treatment area
118
Compared to TCVN 7629:2007, QCVN 03: 2008
4.16.5. Automatic monitoring
Automatic monitoring is carried out by the CETP at two levels: (i) to monitor the pretreatment
standards, i.e. the quality of industrial ww in each enterprise before connecting to the CETP (ii)
to monitor operations of the CETP.
The CETP have their own laboratory to monitor the water quality parameters, at least simple
parameters and to monitor suspected pollutants of tenants in the IZ.
a. Monitoring pretreatment standards
CETP staff will examine the pretreatment standards of tenants in the IZ in local treatment
station’s outlet before signing a contract with them for WW treatment. The pretreatment
standards will be determined by the CETP and varied on each case, depending on treatment
capacity, technology and WW treatment unit price. In all of cases, the required tenants must treat
the WW to reach type B, the Regulation QCVN 40: 2011. However, Domestic WW can be
directly connected to the CETP after collecting by septic tanks in their plants.
The CETP staff shall check pretreatment standards regularly to secure no overloading treatment
capacity and to avoid illegal discharging to the WW system. If the tenants fail to comply with
pretreatment standards, punishment measures shall be applied such as administrative sanctions,
temporary suspension of the treatment contracts or water supply applied to the tenants.
As tenants build their WW systems, they must report and be approved by the IZ Management
Unit the discharging points to the general drainage system of the IZ. The construction process
will be supervised by the the CETP and IZ Management Unit staff. Therefore, the CETP staff has
to clearly know the exact location of the connection of each enterprise and easily sample the WW
in any time.
b. Monitoring efficiency of the CETP
The CETP shall have its own laboratory in the region to measure the (minimal) main water
quality parameters such as pH, DO, COD, BOD, TSS, VSS, VFA, SVI, water flow. The CETP’s
laboratory shall use the standard analysis methods and apply QA/QC procedure.
The CETP owns an operating manual supplied and trained by experts on the CETP construction
consultancy. During the operation phase, the staff shall monitor and record all operating
parameters in the Operation Diary and hand over to the next shift. This procedure will help the
CETP staff soon discover any risks and factors impacting the treatment process and timely
implement corrective measures.
Operation records of the CETP include the following times (for each shift). They are compared
with best technical requirements and operational practices:
- Changes of input flow rate (total flow rate, minimal and maximal flow rate);
- The change of the characteristics of flow rates or quality of WW in the treatment tank
(temperature, pH, ORP, BOD, COD, SS (suspended solids), volatile solids VSS, SVI,
DO, color, etc);
- Changes in process operation, which can be generated by: weight changes, the
presence of non- biodegradable components, the decomposed composition ratio
MLSS in Aerotank, change of generated sludge and circulated sludge, change in
sudden temperature and lack of nutrients, etc.
119
- Used chemical dose (i.e. NaOH, H2SO4, NaOCl, polymer, aluminum, nutrients, etc);
- Generated sludge;
- Operational status, the accident of the device, the operating time of the operating
device and spare parts
- Electricity consumption level;
- Schedule of equipment maintenance (such as device codes, working hours, accidents,
causes, solutions, cleaning, oil changes, etc.)
- Results of the AMS, i.e. minimum, maximum, mean value of pH, flow rate, SS, COD;
- Change of effluent concentration (BOD, total nitrogen, total phosphorus, coliforms,
TS and other related parameters);
4.17. EXPECTED EXPENSE AND IMPLEMENTATION TIME OF THE EMP
A summary of the proposed budget for environmental management, mitigation and monitoring
measures which are presented for each activity in the below main EMP:
- Mitigation measures;
- Training environment;
- Environment monitoring expense during the construction and operation of the CETP.
Table 0-6. Expected expense of EMP in the construction phase and first year of operation
Unit of Account: VND
No. Description Expense Capitals
1 Implementation of mitigation measures Included in the
Contract
IDA
2 Environment training for the CETP
operation
30,000,000 Counterpart capital
3 Monitoring the environment quality
during construction period (1 year)
20,000,000 Counterpart capital
4 Monitoring the environment quality in
the first operation year of the CETP
50,000,000 Counterpart capital
5 Environment Protection fee 20,000,000
Counterpart capital
6
Installation and annual operation of the
Automatic Monitoring System (AMS) for
CETP
654,886,364 IDA
Total 774,886,364
Estimated typical cost for annual monitoring is about 70,000, 000 vnd.
120
CHAPTER 5 PUBLIC CONSULTATION
5.1. OBJECTIVES OF PUBLIC CONSULTATION
5.1.1. For appraisal authorities
To assist the appraisal authorities to have more holistic view on the Project on basis of views of
the local goverments and impacted communitites to help evaluate more effectively.
5.1.2. For the project owner
To receive the feedbacks of local authorities and impacted community to have more practical
additional assessment and to propose appropriate and effective mitigation measures. At the same
time, to bear responsibilities for the full implementation of the mitigation measures to minimize
adverse impacts of the Project
5.1.3. For the Consulting Agencies
To receive the feedback of local authorities and impacted community to have more practical
additional assessment and to propose appropriate and effective mitigation measures.
5.1.4. For the People’s Committee and Committee of Vietnam Fatherland’s Front in
commune level
To assist the leaders of the People’s Committee and Committee of Vietnam Fatherland’s Front in
commune level to have better understanding about the project in the following aspects: The
achieved benefits when implementing the project, the Project’s impacts environment and possible
mitigation measures for the project.
Besides, to create opportunities for local governments to raise issues and concerns for the project
5.1.5. For the impacted communities
To help the impacted communities to have better understanding about the project in the following
aspects: The achieved benefits when implementing the project, the Project’s impacts environment
and possible mitigation measures for the project.
Besides, to create opportunities for the impacted communities to raise issues and concerns for
the project.
5.2. PUBLIC CONSULTATION IMPLEMENTATION
5.2.1. Interviewees
The People’s Committee and Committee of Vietnam Fatherland’s Front of Hoa Mac
Town, Chau Giang Commune and Trac Van Commune.
The surrounding local people who are impacted by the Project.
5.2.2. Implementation methods
The Investor shall send the written summary of the Project to the People’s Committee and
Committee of Vietnam Fatherland’s Front of concerned communes for comments.
The Investor shall direct interview and collect the opinions of impacted people by ready-made
forms.
121
5.3. CONSULTATION RESULTS
5.3.1. Consultation results in Hoa Mac Town, Chau Giang Commune and Trac Van
Commune
Details of the consultation results to the People’s Committee and Committee of Vietnam
Fatherland’s Front of Hoa Mac Town, Chau Giang Commune and Trac Van Commune are
included in the Appendix. Below is summary of some of the main content of the consultation
process.
5.3.1.1. Adverse impacts of the Project on the natural environment, socio-economic aspects
After reviewing the attached summary documents for consultations, the People’s Committee and
Committee of Vietnam Fatherland’s Front of Hoa Mac Town, Chau Giang Commune and Trac
Van Commune agree with the Project’s negative impact assessment on the natural environment
and socio-economic aspects. These are true and practical assessment to the actual situation of the
localities.
5.3.1.2. The Project’s Environment Impact Mitigation Measures
After reviewing the characteristics of the effluent and mitigation measures presented by the
Investor, the People’s Committee and Committee of Vietnam Fatherland’s Front of Hoa Mac
Town, Chau Giang Commune and Trac Van Commune agree with these solutions. They are
mitigation measures suitable to the effluents generated by “1.500 m3 / day CETP Project in Hoa
Mac IZ, Phase I”
5.3.1.3. Recommendations to the Investor
The Investor has to comply with the laws and regulations during the construction and operation
phases;
The Investor has to ensure public order and security during construction and operation phases;
The Investor has to warrant collecting and treating WW to meet standards for entire Hoa Mac IZ.
5.3.2. Interview results
The contents of 24 questionnaires distributed to the households on the project of “Construction
CETP with capacity of 1,500 m3/day at Hoa Mac IZ, Phase I, module 1” show the fact that 21 out
of 24 households agree with the Project and 3 out of 24 families have no idea. Please see the
Appendix for details in these questionnaires.
122
Table 5-1. Results of public consultation
No Name Gend
er
Birt
h
year
Address Occupati
on
Water
sources
Is affected by the project
Conclusion Air
Qualit
y
Health Incom
e
Othe
rs
Hoa Mac Town – Duy Tien District – Ha Nam Province
1 Vu Xuan
Truong Male 1971 Hoa Mac town
Protector
Well-
water No No No No Agree
2 Vu Van
Giang Male 1962 Hoa Mac town Protector
Well-
water No No No No Agree
3 Tran Minh
Vuong
Fema
le 1982 Hoa Mac town
Excavato
r
Well-
water
Little
effect No No No Agree
4 Pham Van
Bang Male 1968 Hoa Mac town Farmer
Well-
water No No No No Agree
5
Nguyen
Trung
Thuan
Male 1965 Hoa Mac town Farmer Well-
water No
No
option
No
option No No option
6 Nguyen Huy
Hieu Male 1971 Hoa Mac town Farmer
Well-
water Yes No No No Agree
7 Nguyen Van
Sy Male 1968 Hoa Mac town Farmer
Well-
water No No No No Agree
8 Dang Quang
Tien Male 1976 Hoa Mac town Farmer
Well-
water No No No No Agree
Chau Giang Commune – Duy Tien District – Ha Nam
9 Le Van Sau Male 1976 Van Kenh
village Worker
Well-
water No
Little
effect No No No option
123
No Name Gend
er
Birt
h
year
Address Occupati
on
Water
sources
Is affected by the project
Conclusion Air
Qualit
y
Health Incom
e
Othe
rs
10 Pham Van
Binh Male 1961
Chuyen Thien
village Worker
Well-
water No No No No Agree
11 Pham Van
Thanh Male 1970
Chuyen Thien
village Farmer
Well-
water
Little
effect No No No Agree
12 Nghiem Thi
Huyen
Fema
le 1982
Van Kenh
village Farmer
Well-
water No No No No Agree
13 Pham Quoc
Doan Male 1962
Van Kenh
village Protector
Well-
water No No
Little
effect No No option
14 Nghiem Thi
Van
Fema
le 1971 Dong village Teacher
Well-
water No No No No Agree
15 Luu Van
Thuy Male 1971
Van Kenh
village Famer
Well-
water No No No No Agree
16 Luu Van
Thuy Male 1969
Van Kenh
village Famer
Well-
water No No No No Agree
Trac Van Commune – Duy Tien District – Ha Nam Province
17 Nguyen Van
Luc Male 1964 Lat Ha village Protector
Well-
water No
Small
effect No No Agree
18 Nguyen Van
Khiet Male 1962 Lat Ha village
Village
chiefs
Well-
water No No No No Agree
124
No Name Gend
er
Birt
h
year
Address Occupati
on
Water
sources
Is affected by the project
Conclusion Air
Qualit
y
Health Incom
e
Othe
rs
19 Hoang Thi
Quyen
Fema
le 1972 Lat Ha village Famer
Well-
water No No No No Agree
20 Nguyen Thi
Huong
Fema
le 1992 Lat Ha village Pupil
Well-
water No No No No Agree
21 Dang Van
Chinh Male 1968 Lat Ha village Famer
Well-
water No No No No Agree
22 Nguyen Van
Tinh Male 1968 Lat Ha village Famer
Well-
water No No No No Agree
23 Nguyen Van
Diep Male 1972 Lat Ha village Famer
Well-
water No No No No Agree
24 Hoang Van
Luan Male 1956 Lat Ha village Famer
Well-
water No No No No Agree
125
5.4. INFORMATION DISCLOSURE
EIA reports of the project “Construction CETP with capacity of 1,500 m3/day at Hoa Mac IZ,
Phase I, module 1” shall be sent by the Investor to be listed publicly in the headquarters of the
People's Committee of Chau Giang Commune, Trac Van Commune and Hoa Mac town for
public awareness, supervision. In addition, the EMP is publicized in the headquarter of
Vietnam Environment Protection Fund (VEPF), Infoshop in Washington DC and at Vietnam
Development Information Center (VDIC)
5.5. THE INVESTOR’S COMMITMENTS
The Investor warrants meeting Vietnam Environmental Regulations during construction and
operation phases, including:
+ Ambient air environment: The pollutants discharged to the environment must meet
the Vietnamese Regulations on Ambient Air Quality (QCVN 05:2009/BTNMT, QCVN
06:2009/BTNMT)
+ Noise: generated during the operation phase of the project will meet noise
regulations in the public and residential areas (QCVN 26:2010/BTMNT)
+ The treated effluent: must meet the Vietnamese Regulations on Industrial WW,
Column A, Kq = 0.9 ; Kf = 1.0
+ Solid waste: All SW will be collected, classified by hired functional firms under the
regulations.
+ Waste sludge: is dewatered and transported to the disposal area in accordance with
laws
+ HW: is stored in the areas with safe roof and collected, treated by hired functional
firms
+ Hazardous and non-hazardous wastes are collected and transported to the designated
treatment site in accordance with safety and hygiene requirements. To warrant managing solid
waste in line with the Decree No. 59/2007/NĐ-CP on management of sw; the Circular No.
12/2011/TT-BTNMT dated 14th
April 2011 of MONRE on management of HW;
The Investor warrants applying incident prevention and pollution mitigation measures
as presented in the reports and to intensify trainings to the officers to improve their
environmental management capacity and to ensure to operate the CETP safely, effectively and
environmentally friendly.
The Investor warrants that the WW collection system is connected to all land lessees
as the CETP is officially operated.
The Investor warrants that the CETP only has one regular discharging outlet and one
standby discharging outlet.
The Investor shall bear full responsibilities to the Vietnamese laws if violating the
International Conventions, the Vietnam Standards and for any incidents causing
environmental pollution, if any.