+ All Categories
Home > Documents > Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a...

Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a...

Date post: 19-Apr-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
18
Page 1 of 18 Environmental Improvement Plan Sohar Refinery Feb 2014
Transcript
Page 1: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Page 1 of 18

Environmental Improvement Plan

Sohar Refinery

Feb 2014

Page 2: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

•Background

The treatment of the waste water of the Refinery was

malfunctioning for a long period. Almost no purification

occurred and the water effluent quality was far away

from the standards. The water also emitted vapours

that caused strong odour.

Waste Water Treatment Plant Improvements

Page 2 of 18

Page 3: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

WWTP – 2013 Projects

• Biological improvement (bio augmentation) by addition of special enzymesby KAM Biotechnology.

• Further cleaning and repairs of basins/equipment.• Replacing sand and gravel in Sand Filters.• Building of additional and more robust spent caustic treatment unit from in

order to have a 100% back-up system.• Replacing of gravel and activated carbon in Activated Carbon Filters.• Optimization of the primary units (API and DAF) by different chemicals

from different suppliers to select the best chemicals (on-going).

Page 3 of 18

Page 4: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

WWTP – 2013 Projects

• More tight control of waste water production and draining from the refineryplants. Continuous operation surveillance and monitoring of the WWTP.

• Ensure the implementation of preventive maintenance and repairs of allequipment in the refinery that have direct influence to WWT operation.

• Preparation to implement Zero Discharge Policy: Plan is to send SRtreated effluent water from WWTP into Majis centralized treatment facility.

Page 4 of 18

Page 5: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

WWTP – 2013 Results

• All parameters are within standard except ammonia.• Significant odour emissions reduction.

Parameters/p

pm2011

Nov

2012

Nov

2013

Feb

2014

Standards/p

pm

COD>1,50

0413 110 157 200

Oil & grease 31 12.5 8 6.5 15

TSS 83 31.7 8 36 30

Phenols 56 <0.1 <0.1 <0.1 0.002

Ammonia 128 57.2 96 29 1

Water

quality

from

WWTP

Water

quality into

WWTP

Page 5 of 18

Page 6: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

•Background

For mitigating odours from SR, the primary area for

odour source has been the refinery Waste Water

Treatment Plant. However Hydrocarbon emissions in

other parts of the Refinery could also contribute to

odour. Orpic is taking various actions for controlling

odour emissions, generated from the refinery complex

starting with WWTP. Orpic continues to identify the

possible other sources of odour within the SR.

Odour Nuisance Reduction

Page 6 of 18

Page 7: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Odour Nuisance Reduction

• Installation of temporary spent caustic treatment unit.• Installation of deodorizing additive in basins of WWTP that emit gases in

December 2011.• Use of E-noses for odour detection in September 2012.• A project was launched to cover the WWTP basins, collect the gases and

treat the gases to remove odour components. The project was divided into3 phases. Phase-I is the coverage of the basins and has been completedin October 2012.

• Phase-II Odour control project of installing a ventilation system for someof the covered basins (API and DAF), completed and started up in August2013.

• An odour mapping study to identify all possible sources of odour within theSR was completed in July 2103. Sources other than the WWTP wereidentified, mainly vents of certain tanks and Oily Water sumps. Actions arebeing launched to equip all these sources with a system to collect thevapours.

• Installation of HC and H2S detectors at the impound basin November2013.

Page 7 of 18

Page 8: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Odour Nuisance Reduction

• Phase-III Odour control project of installing scrubber and/or thermaloxidation (RTO) system by end of 2014. The EPC contract tender wasfloated and several offers were received. Currently in process to evaluatethe offers and to select the EPC contractor. This last step will completelyavoid any odour coming from the WWTP.

• As part of the odour reduction program, Orpic assigned a number of itsengineers to work in shift along with the process Operators.

• Other initiative Orpic took to reduce odours is by launching the “Coin YourIdeas” campaign.

Page 8 of 18

Page 9: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Odour Nuisance Reduction

Results• Odour emissions and hydrocarbon releases from the Refinery have

decreased significantly, e-Nose readings show less frequent peaks ofemissions and also the intensity has decreased.

02 1 0 1

4

10

22 23

13

8

0

5

10

15

20

25

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Phone Calls Statistics (Complaints)

Page 9 of 18

Orpic hotline number:80077337

Date Phone call Validation

5/1/2014 One Not Valid

10/1/2014 One Valid

15/1/2014 One Not Valid

29/1/2014 One Not Valid

1/2/2014 One Not Valid

15/2/2014 One Not Valid

Page 10: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Sohar Refinery Flaring

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

2010 2011 2012 2013 YTD

TP

H

Sohar Refinery Flaring Long Term Trend

Average 多項式 (Average)

Projects:• A project was completed to connect the fuel gas system of the Refinery with

Aromatics Plant.• Continue to enhance chillers reliability and using both STG’s to produce

power.• A study has started to recover the remaining low pressure gas that still is

flared and that cannot be recovered by the means mentioned above.Results• Routine flaring rate has been reduced by more than 60% from average of

12.5 tons/hr to 4.5 tons/hr.

Page 10 of 18

Page 11: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Background

• As part of the original Refinery construction,

a Wet Gas Scrubber (WGS) was installed in

Sohar Refinery to reduce Sulfur Dioxide (SO2)

gas emissions from the RFCC unit.

• Due to the changes in RFCC feed quality (higher sulphur

content) from the original design assumptions, Sohar Refinery

experienced higher Sulfur Dioxide emissions than design. Also

poor dispersion of the plume exiting from the WGS stack was an

issue.

SOx Emissions Reduction

Page 11 of 18

Page 12: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

SOx Emissions Reduction

• Original Equipment Manufacturer (OEM) Alstom was contracted fordebottlenecking the existing WGS. An EPC was awarded to Alstom toimplement the modifications and to retrofit. GTB awarded the contract (19M$) in September 2012.

• In October 2012, the packing material level in WGS increased to 100% as afirst short term step. Higher scrubbing efficiency and lower emissions wasobserved.

• On 20 February 2013, mobilization of manpower and lifting equipment startedonsite, to implement planned WGS modifications.

• On 11 March 2013, Fire incident occurred in the WGS Unit, resulting in majordamage to the entire equipment. On 20 March 2013, recovery plan started tore-build the damaged Wet Gas Scrubber, re-instate the sea water system andother utilities on a fast track.

Inlet SO2(mg/Nm3)

Outlet SO2(mg/Nm3)

Efficiency(%)

Outlet SO2(ppmv)

After packingvolume increasedfrom 70% to 100%

7,919 1,500 81 526

Page 12 of 18

Page 13: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

SOx Emissions Reduction

• For a period of 2 months, the agreement was obtained from MECA/SEU tooperate the refinery without the WGS but meeting a SOx limit which wassimilar to the emissions that Orpic had in first half of 2012. Orpic has takenmeasures (use of imported low sulphur feedstock and use of DeSox catalyst)and was able to stay below the agreed limit.

• On 24 May 2013, the main parts of the Wet Gas Scrubber (Absorber Shell &Cone) were delivered to site, manufactured by local vendor.

• On 20 June 2013, Completion of mechanical works with a three seawaterbooster pumps arrangement.

• On 3 July 2013, Wet Gas Scrubber put incold circulation with two seawater boosterpumps. All systems were checked in detail.

• On 27 July 2013, Wet Gas Scrubber put inoperation with hot flue gases.

Page 13 of 18

Page 14: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

SOx Emissions Reduction

• October 2013, the remaining external components (heater system of the fluegases coming from the WGS, fourth standby seawater booster pump) areinstalled.

ResultsInlet SO2(mg/Nm3)

Outlet SO2(mg/Nm3)

Efficiency(%)

Outlet SO2(ppmv)

After WGSRevamp

7,919 780 90 273

Page 14 of 18

857.1

0.0100.0200.0300.0400.0500.0600.0700.0800.0900.0

01

Au

gust2

013

05

Au

gust2

013

09

Au

gust2

013

13

Au

gust2

013

17

Au

gust2

013

21

Au

gust2

013

25

Au

gust2

013

29

Au

gust2

013

02

Se

pte

mbe

r…06

Se

pte

mbe

r…10

Se

pte

mbe

r…14

Se

pte

mbe

r…18

Se

pte

mbe

r…22

Se

pte

mbe

r…26

Se

pte

mbe

r…30

Se

pte

mbe

r…04

Oct

obe

r2

013

08

Oct

obe

r2

013

12

Oct

obe

r2

013

16

Oct

obe

r2

013

20

Oct

obe

r2

013

24

Oct

obe

r2

013

28

Oct

obe

r2

013

01

Novem

ber…

05

Novem

ber…

09

Novem

ber…

13

Novem

ber…

17

Novem

ber…

21

Novem

ber…

25

Novem

ber…

29

Novem

ber…

03

Decem

ber…

07

Decem

ber…

11

Decem

ber…

15

Decem

ber…

19

Decem

ber…

23

Decem

ber…

27

Decem

ber…

31

Decem

ber…

04

Janu

ary

2014

08

Janu

ary

2014

12

Janu

ary

2014

16

Janu

ary

2014

20

Janu

ary

2014

24

Janu

ary

2014

28

Janu

ary

2014

01

Febru

ary

2014

05

Febru

ary

2014

09

Febru

ary

2014

13

Febru

ary

2014

mg/Nm3

SO2 of WGS

SO2 Design SO2

Page 15: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

SOx Emissions Reduction

• A further reduction is expected after the implementation of the Sohar RefineryImprovement Project (SRIP). As a results of the new Refinery units that willbe installed as part of the SRIP, the Sulfur in the RFCC feed will be loweredto 1.8 wt% which resulted in less SOx precursors. Also the amount of fluegases to be scrubbed will decrease. The impact on the WGS performance isthat the 350 mg/Nm3 will be met after start-up of New Units mid-2016.

Inlet SO2(mg/Nm3)

Outlet SO2(mg/Nm3)

Efficiency (%)Outlet SO2

(ppmv)

After SRIP 5,016 350 93 122.8

Page 15 of 18

Page 16: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Leak Detection and Repair (LDAR)

Projects 2013:• An LDAR survey was conducted to all refinery units using best practices

LDAR and Infrared camera scan.

Result

Page 16 of 18

Page 17: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Waste Management

• Export more than 19,000 tons of RFCC spent catalyst from Al Bhatinahfacility and on-site.

• Construct on-site hazardous/non-hazardous waste storage facility.• Continue to find more outlets for different type of waste.

Page 17 of 18

0

5,000

10,000

15,000

20,000

25,000

ton

s

Sep-12

Oct-12

Nov-12

Dec-12

Jan-13

Feb-13

Mar-13

Apr-13

May-13

Jun-13

Jul-13

Aug-13

Sep-13

Oct-13

Nov-13

Dec-13

Jan-14

Feb-14

Accumulative tons 480 970 1,430 2,010 3,190 4,210 5,430 6,750 9,570 10,31 10,61 11,33 13,27 15,43 17,57 18,83 19,14 19,52

Accumulative tons

Page 18: Environmental Improvement Plan Sohar Refinery · operate the refinery without the WGS but meeting a SOx limit which was similar to the emissions that Orpic had in first half of 2012.

Waste Management

RFCC spent catalyst stored on-siteJanuary 2013, total of 8,600 tons.

No RFCC spent catalyst stored on-site Feb 2013.

Page 18 of 18


Recommended