+ All Categories
Home > Documents > ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION...

ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION...

Date post: 04-Sep-2021
Category:
Upload: others
View: 2 times
Download: 1 times
Share this document with a friend
63
VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA PA DISTRICT- LAO CAI PROVINCE Lao Cai - Oct. 2008 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

VOL. 3

NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC.

ENVIRONMENTAL MANAGEMENT PLAN

CAN HO HYDROPOWER PROJECT

SA PA DISTRICT- LAO CAI PROVINCE

Lao Cai - Oct. 2008

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 3: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC.

ENVIRONMENTAL MANAGEMENT PLAN

CAN HO HYDROPOWER PROJECT

SA PA DISTRICT- LAO CAI PROVINCE

Lao Cai - Oct. 2008

Page 4: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 5: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

TABLE OF CONTENT Page

ACRONYMS AND ABBREVIATIONS 3

CHAPTER 1: GENERAL 4

1 . 1 . SUPROJECT BACKGROUND 4

1.2. SUBPROJECT DEVELOPER 4

1.3. OBJECTIVES OF DEVELOPER 4

1.4. RESPONSIBLY FOR SUBPROJECT PREPARATION 4

CHAPTER 2: SUBPROJECT DESCRIPTION AND SETTING 5

2.1. LOCATION OF THE SUBPROJECT 5

2.2. SUBPROJECT SUMMARY 5

2.3. NATURAL CONDITION OF THE SUBPROJECT'S AREA 6

2.4. SOCIAL CONDITION 7

2.5. ENVIRONMENTAL IMPACTS SCREENIIVG 7

CHAPTER 3: KEY ENVIRONMENTAL IMPACTS 18

3. I . CONSTRUCTION PHASE 18

3.2. OPERATION PHASE 20

CHAPTER 4:.KEY MITIGATION AND MANAGEMENT MEASURES 22

4.1. DESIGNING AND PREPARATION PHASE 2 2

4.2. CONSTRUCTION PHASE 25

4.3. OPERATION PHASE 37

CHAPTER 5: SUPERVISION, FOLLOW UP AND MONITORING 39

5. I . MONITORING PLAN 39

5.2. INSTITUTIONAL ROLES AND RESPONSIBILITIES 47

5.3. OPERATION PHASE 5 1

CHAPTER 6: ESTIMATED COST FOR EMP IMPLEMENTATION 52

CHAPTER 7: PUBLIC CONSULTATION AND DISCLOSURE 52

7.1. PUBLIC CONSULTANT 52

7.2. DISCLOSURE 52

ANNEX 1. EMP IMPLEMENTATION REPORT TEMPLATE APPLIED FOR 5 3 DEVELOPER

ANNEX 2. SUMMARY OF PUBLIC CONSULTANT 5 4

ATTACHMENT: SlJBPROJECT MAP

Page 6: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

LlST OF TABLES

Table 1 : Key parameters of project

Table 2. Subproject scoping checklist

Table 3. REDP pre-screening document checklist

Table 4. World bank safeguard checklist

Table 5. Environmental concerns and EMP requirements

Table 6: Land occupancy

Table 7: Affected cultivated land

Table 8: Mitigation Measures on designing and preperation phase

Table 9: ~ i t i ~ a t i o n Measures on construction phase

Table 10: Mitigation Measures on operation phase

Table 1 I : Monitoring plan

Table 12: Subproject Roles and ESF Responsibilities

Table 13. Training cost for EMP implementation

Table 14. Budget for EMP implementation

ABBREVIATION

BOD

COD

DoNRE

EPC

EMP

GOV

MoNRE

MOIT

SIMC

TCVN

TSS

VND

UBND

WB

Biological oxygen demand

Chemical oxygen demand

Department of Natural Resources and Environment

Environmental Protection Commitment

Environmental management plan

Vietnam Government

Ministry of Natural Resources and Environment

Ministry of Industry and Trade

Safety Independent Monitoring Consultant

Vietnam Environmental Guideline

Total suspended solid

Vietnam Dong

People Committee

World bank

Page 7: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Chapter 1: GENERAL

1.1. SUBPROJECT BACKGROUND

Can Ho hydropower subproject which uses the water from three streams of Phin Ho, Can Ho and Van Ho is a part of Ngoi Xan hydropower network including six small hydropower subprojects (in order from up to downstream): Can Ho, Sung Vui, Ngoi Xan I, Ngoi Xan I1 and Van Ho. Nam Tien construction investment and Trading JSC is developer of all six above subprojects, in which Ngoi Xan I and Ngoi Xan I1 projects have been operated since 2007.

1.2. SUBPROJECT DEVELOPER

Can Ho subproject is developed by Nam Tien Construction Investment and Trading JSC, one of the biggest private enterprises of Lao Cai Province, specialized in construction investment ranging from: civil construction, irrigational works, ect.

1.3. OBJECTIVES OF SUBPROJECT

Can Ho hydropower subproject has an installed capacity of MW 4.2, with a total investment capital of USD 6.1 million, in which USD 4.3 million is allocated to the construction and USD1.8 million is for equipment procurement. The objective of the subproject is to increase the supply of electricity to the national grid with an annual output of k w h 16.13 million. The subproject has an important significance in order to maximizing exploitation of hydro power potentials as well as contributing into the socio-economic development of outback area of Sa Pa district - Lao Cai province.

1.4. RESPONSIBLY FOR SUBPROJECT PREPARATION

Nam Tien Construction Investment and Trading JSC is responsible for preparation, design, construction and operation of the subprojects, including environmental assessment and management of subproject impacts and preparation of the environmental management plan (EMP) in compliance with World Bank requirements. A Project Management Board with 13 staffs including experienced experts vary from civil engineering, lawyers, architects, environmentalists ect has been established by developer to manage activities of civil work constructions. Among them, there are 3 staffs who have been assigned for safeguard implementation (one for resettlement, one for environment and other for safety), In some cases, Nam Tien Construction Investment and Trading JSC cooperates with consultant companies to prepare feasible study report; environmental protection commitment procedures followed and official approvals for the documentation from jurisdictional offices.

Page 8: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Chapter 2: SUBPROJECT DESCRIPTION AND SETTING

2.1. LOCATION OF THE SUBPROJECT

The subproject is located in Ban Khoang commune, Sa Pa district, Lao Cai province in the North West of Vietnam, about 18 krn from magnificent tourist area- Sa Pa. The geographic location of the subproject:

North longitude: 22'25 '58"

East latitude: 103'49'04''

Main components of the subproject and effected areas are showed on the attached map (Annex 3).

2.2. SUBPROJECT-SUMMARY

The major components consist of:

- Two dams: Superior one is located on Can Ho Stream and the other on May Ho Stream

- Waterway and Penstock

- Powerhouse is placed on Phin Ho stream

- Transmission line and transformer station

Water in the reservoir is taken via the headrace channel, flowing to the surge tank, then through the penstock to the powerhouse, and finally it is discharged to the Phin Ho stream.

Table 1: Key parameters of subproject

I reservoir i I

No Project components

__i 1 Inferior reservoir 1 Ca~acitv of 38.000m3 1 ~ekgth >7m, top width 3m. ( .33.000m2

Land occupancy , Detailed works

Superior

Size

Capacity of 335,000m3

Hydraulic works

/ Access road i Width 10m i 4km

Powerhouse ---

Inferior dam eight 18m. - Length 23m, top width

Road , Exiting 12 km

Waterway Penstock --

3m, Height 16.5m. Overflow level 1,O 1 Om; B= 20m L= 1,045m L = 687m Nlm= 4,2 MW

52,000m2 1 3,800m2 3,000m2

Page 9: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

I / Total I I I

1 958.000m2 I I

4

2.3. NATURAL CONDITION OF THE SUBPROJECT'S AREA

1. Climate and topography The subproject's area is characterized by tropical monsoon climate region which

has 2 different seasons: + Dry season: from October to the next Match

+ Rain season: from April to November.

Transmission line and transformer station

Air temperature changes clearly due to different terrain. The annual average air

temperature ranges from 17 to 2 0 ' ~ . The absolute maximum of air temperature is

30.2"C and the absolute minimum of air temperature is 1°C. Annual rainfall average:

2,548 mm.

Can Ho hydropower subproject on Phin Ho stream has catchment area of 32.2 km2. Flood season starts on June and ends on November which made up to 65% of annual flow.

transformer station

Transmission line

Almost of the subproject's catchment area is a distinctive mountain zone which has its own unique features. Landslide is common event and becomes one of the biggest environmental trouble in this area as consequence of forest destruction.

2. Natural terrestrial features

35kV* 1 station

35kV; 0.4kV

Forests and forest land account for 81 % of Sapa's total land area. Hoang Lien primeval forest are home to many kinds of value plants and rare animals (black gibbon, weasel, black panther, bear ect and strictly protected. Can Ho hydropower subproject is far from Hoang Lien primeval forest about 15 to 18 krn. However, forest in the subproject's area has been reduced due to forest degradation, land use for cultivation. As results of these, the environment has been negatively changed for terrestrial animals and many forest animals have not been seen for the last decades.

4 k m x lorn

3. Aquatic features

In contrast to terrestrial features, aquatic ecosystem in the subproject's catchment area is very poor although having high stream density but not comfortable for aquatic features living. The main reasons for that are: water temperature is alway low, sloping stream.

Page 10: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

2.4. SOCIAL CONDITION

The subproject's area is dominated by ethnic Dao people, however, very thinly populated on mountain side. According to the annual report of Ban Khoang's people committee, poverty households, which income is below 200,00OVND/person-month, make up to 25-30%. Their life mainly depends on rice, corn and cassava cultivation and forestry. However, almost of cultivated land is one-crop seedling, low productivity and always faces natural calamities (flood, drought, insect...). About 50% children is not compulsory primary education as consequence of low living standard, backward custom, poor traffic system ect.

2.5. ENVIRONMENTAL IMPACTS SCREENING

Table 2. Subproject scoping checklist

ISSUE I RELEVANT? I OUTCOME 1 Is the subproject located in or near a national park or other government designated protected area? NO J

If a dam, is the subproject more than 15 m in height or 3 million cutjic meters in capacity?

Will the subproject affect physical or cultural resources that may be significant?

I I

Will the subproject result in change of land use and 1 Land use resettlement of affected people? I YES

J compensation plan has

Is the subproject situated on or near to an international waterway?

YES J

Do ethnic minorities live or use the area affected by

J

Dam safety review has been done

been prepared Ethnic Minority Plan

all MOlVRE/District people committee Approvals been obtained?

an EIA/EPC been completed?

1 --

YES J

the project?

*-- YES J 1 r

-- consultation of those people potentially

affected by the subproject been undertaken'? Y E S J I 1

YES J 1 has been prepared

Has an environmental management plan been completed? Y E S J 2---- -A

Page 11: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

ISSUE

ecology and those living downstream? 1 Will the subproject affect downstream flows,

RELEVANT?

1 Mitigation measures

OUTCOME

Have construction impacts been hlly mitigated?

Will the subproject result in construction of new I access roads and how will ac-cess be managed? Will the subproject result in construction of a new

Feasibility Study I

YES J

Table 3. REDP prescreening document checklist

1 YES Consideration of the 1 transmission line? 1 EMP

YES J I Mitigation measures

are mentioned in EMP

DOCUMENT

Land compensation Plan

NO J

INCLUDED? I

Approved EPC (if applicable) Environmental Management Plan

/ YES J

Consideration of the EMP

YES dl YES J I

YES J 1

DONRE Approvals (including physical cultural resources) 1 YES

J I

I -- Dam safety review by Dam Safety Panel I YES J 1 Other approvals: if required

YES J I

Page 12: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Table 4. World bank safeguard checklist

SCREENING CRITERIA ENVIRONMENTAL SAFEGUARD

(tick J)

APPLIES, YES OR NO

OPBP 4.04: Natural Habitats Natural habitats are defined as land and water areas where the ecosystems' biological communities are formed largely by native plant and animal species, and human activity has not essentially modified the area's primary ecological functions.

Is the subproject located within any National Biological Conservation Areas, (NBCAs), National/Provincial/District Protected Areas (NPAS, PPAs, DPAs)? (If yes, subproject is

I excluded)

Biological Conservation Areas, (NBCAs), National/Provincial/District Protected Areas (NPAS, PPAs, DPAs)? (if. yes, subproject is eligible but requires permit)

significance? If yes, what is the consequence?

Comment: Will the subproject flood a forested area? (if yes, subproject is eligible but requires permit).

YES 1

YES 1

Based on the above screening, does OP/BP 4.04 Apply? 1 Y E S N O 1

Will the subproject bring about changes to the management, protection, or utilization of natural forests or plantations, whether they are publicly, privately, or communally owned?

YES NO J

Page 13: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

O P B P 4.10: Ethnic Minorities (Indigenous Peoples)

ENVIRONMENTAL SAFEGUARD SCREENING CRITERIA

The World Bank policy on indigenous peoples, underscores the need that subproject developers identlJL indigenous peoples, consult with them, ensure that they participate in, and benefit from Bankyunded operations in a culturally appropriate wuy - and that adverse impacts on them are avoided, or where not feasible, minimized or mitigated. In case of Vietnam and the REDP, this policy has been modiJied to consider ethnic minorities, rather than indigenous peoples.

APPLIES, YES O R NO

Ij-ethnic minorities are to be afSected by an REDP subproject and Ethnic Minority Plan must be prepared

Will the subproject affect ethnic minorities as described by 1 Vietnamese law and in consideration of OP/HP I. lo? YES I J Y

I

Will the subproject result in increased employment opportunities 1 for local communities during construction and lead to an overall YES

Will the subproject create a threat to ethnic minorities traditional use of the land and its resources?

Will the subproject result in impacts to health and social integrity of ethnic minorities?

increase in economic benefits? I 1 Have all claims and grievances associated with development of

the subproject been addressed? I I

YES

YES

I Has an Ethnic Minority Plan (EP) been prepared in compliance with the REDP Ethnic Minority Planning Framework, April 2008.

NO 4 NO

. -

Has the EP been reviewed 'and approved by the respective provincial authorities (Provincial Peoples Committee (PPC))?

Has there been adequate disclosure of the EP in compliance with

disclosure? World Bank and Vietnamese requirements for consultation and

Based on the above screening, does the subproject comply with OP/BP 4.10 and REDP requirements?

YES 1 J ,

D l J

Page 14: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

ENVIRONMENTAL SAFEGUARD

Physical cultural resources include movable or immovable structures, groups o f structures, natural features and archeological, paleontological, historical, other cultural signzficance.

APPLIES, YES SCREENING CRITERIA

OPIBP 4.1 1: Physical Cultural Resources

Will the subproject cause temporary or permanent relocation or any other type of impact on physical cultural resources known-to be of local, regional or national significance based on national or Provincial lists, proposed national or Provincial lists and/or identified during public consultation with local affected groups.

OR NO (tick 4)

I Are chance find procedures in place?

Based on the above screening, does OP/BP 4.1 1 Apply? 1

Are any physical cultural resources considered especially important or sensitive particularly to local groups (e.g. gravesites)

ENVIRONMENTAL SAFEGUARD I APPLIES, YES SCREENING CRITERIA 1 OR NO i

1 (tick 4) OPIBP 4.12 Involuntary Resettlement

YES

The Involuntary Resettlement safeguard will apply in those situations involving involuntary taking of land and involuntary restrictions of access to legally designated porks and protected areas The policy aims to avoid involuntary resettlement to the extent.feusible, or- to minimize and mitigate its adverse .social and economic impucts

NO J

--

Is any land used by people likely to be acquired as a result of t h e r YES subproject?

J -- 1 Will any REDP subproject activity involve restrictions of use on- YES

I adjoining land?

E n d ownership affected by the REDP subproject? YES-

Page 15: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Are non-titled persons present?

Will there be a loss of housing?

Will there be a loss of crops, trees, and other fixed assets?

Will there be a loss of incomes and livelihoods?

Wi l l access to facilities, services or resources be lost?

Will there be lost of business or enterprises?

Will any social or economic activities be affected by land use related changes?

Will there be loss of village common lands, gathering and foraging areas, fishing areas, etc. as a result of the subproject?

Will there be a loss of health facilities, burial grounds, temples, community centers, public transport

Will there be'lost of drinking and other water systems, access and internal roads, electricity or other power sources

Based on the above screening, does OPIBP 4.12 Apply and is a Land compensation Plan required?

-- YES

YES

YES J

YES J

YES

YES

YES J

YES

YES

-- YES

YES J

Page 16: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

(tick J )

ENVIRONEMENTAL SAFEGUARD SCREENING CRITERIA

OPIBP 4.37 Safety on Dams The Safety on Dams Safeguard requires that experienced and competent professionals design and supervise construction, and that the borrower adopts and implements dam safety measures through the project cycle. The policy also applies to existing dams where they influence the performance of a project. In this case, a dam safety assessment should be carried out and necessary additional dam safety measures implemented.

APPLIES, YES OR NO

This policy will apply f a n REDP subproject is to be considered a large dam according to the criteria below and therefore will require that a Dam Safety Assessment be completed.

1 Is the dam height is 15 meters or greater?

I Is dam storage 3 million cubic meter or more?

that are complex and difficult to prepare, or retention of toxic materials?

YES 1 E"O

YES NO

J

Based on the above screening, is the REDP subproject considered to be a large dam and will a Dam Safety Assessment be required?

Is the dam is expected to become a large dam during the operation of the facility?

Y E S F 1 n

YES J

NO

Page 17: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

OPIBP 7.50 Projects on International Waterways

ENVIRONMENTAL SAFEGUARD SCREENING CRITERIA

The objective of OP/BP 7.50 is to ensure that World Bank-financed projects affecting international waterways would not afSect relations between the World Bank and its Borrowers and between states and also not affect the efJicient utilization and protection of international waterways. It applies to projects that involve the use and/or potential pollution of in~ternational waterways. OP/BP 7.50 does not apply to run of the river projects.

APPLIES, YES O R NO (tick J )

, Will the subproject utilize water from or into a river or river tributary that flows to or through or forms a border with a neighboring country?

1 neighboring country?

Is the subproject the first subproject downstream of an international waterway?

Is the proposed subproject the last project on a river that is an international waterway?

YES

Will the subproject discharge water from or into a river or river tributary that flows to or through or forms a border with a

1 Based on the above screening, does OPIBP 7.50 Apply?

YES

NO I ' YES 1 J I

YES I NO

I Overall Safeguard Compliance I

YES

J

NO J

1 Does the subproject comply with the aforementioned YES 4 World Bank Safeguards?

Page 18: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Table 5. Environmental concerns and EMP requirements

Issue or Environmental Concern (Note: Social issues and concerns are dealt elsewhere)

- - - - I Dust?

Air quality impacts on local communities?

I See Table 9

Is Issue or Concern Addressed in EIA or

EPC? Yes or No

- -

b a c t s on Migratory, Rare, ~hreatened;

Is Issue or Concern Addressed in EMP?

Yes or No (tick ~j

Is in a Seismically Active or Geotechnically Unstable Area? Affects Integrity of Protected Areas?

I Endangered Species? 1 1 I

Required Action or Follow-up

YES J

Impacts on Biodiversity? I I J I

See Table 9 NO

(tick 4)

J

J

YES J

NO ,

J

J

Considers Downstream Impacts?

Allowable for small hydropower project

Affect Environmental Flows? See also Annex 5 about environmental flows and why it is important they be maintained.

J See Table 10

i

J See Table I0

Page 19: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

/ Affect Downstream Water Quality?

Issue or Environmental Concern (Note: Social issues and concerns are dealt elsewhere)

1 Affects Fish or Fisheries? I J I J

Is Issue & Concern Addressed in EIA or

EPC? Yes or No

Is Issue or Concern . . ~ddressed in EMP?

Yes or No (tick 4)

Considers Off-site Impacts (e.g. Borrow Pits and Aggregates)?

. ̂*FRequired Action or ,

Follow-up

YES (tick 4)

I See Table 10 I

NO YES

,

See Table 9

NO

Impacts Cultural Property or Resources? 1

Aesthetic and Visual Impacts? t Causes Increased Erosion and Sedimentation During Construction?

J

Involves Construction of New Access

Involves Construction of Worker Camp(s)?

J

See Table 9

J

See section 4.1 -i See section 4.1 I

Has Chance Find Procedures In Place for Physical and Cultural Resources?

--

Has Waste Management Plan (Solid and Liquid Wastes) in Place?

J

- -- -- - -

Is there a Reclamation Plan In Place? -7 J

See section 4.1 1

See section 4.1 --I

Page 20: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

) elsewhere) I EPC? Yes or No

or Environmental Concern (Note: Social issues and concerns are dealt

I I (tick 4)

Is -Issue or Concern Addressed in ELA or

Notification Plan in case of Accident or Event (e.g Release)?

YES NO

Has Included EMP and Environmental Protection Measures as Part of Contract Provisions?

1 Includes Costs and Tirneline for EMP? I J l

J

Has EMP Monitoring and Supervision Procedures in Place?

the subproject that is listed in the EIA or EPC over and above the aforementioned issues that should be addressed?

J

Is Issue or Concern Addressed in EMP?

Yes or No tick 4 +

Recfui~ed Action or ~ollow -up

See section 4.1

See section 4.1

See Table 1 1

See Table 13& 14

See section 3.1

Page 21: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Chapter 3: KEY ENVIROMENTAL IMPACTS

3.1. Construction phase

I . Loss of land: The development of Can Ho hydropower subproject causes losing parts of the

land due to acquisition. 101 ,800m2 of land will be acquired for construction works, in which 23,500m2 is fallow hilly land, 14,800m2 is one-crop rice land, and 63,500m2 is burnt-over land (corn, cassava). Details for each type of acquired land are as described on the following tables:

Table 6: Land occupancy

Table 7: Affected cultivated land

Temporary acquisition (m2)

Place

Ban Khoang commune

TOTAL

Permanent acquisition (m2)

l ~ a n Khoang commune 1 14,800 1 63,500 1 23,500 1

I

Place

There are 22 households of Lu Khau village and Can Ho village will lose cultivated land (78,300m2), most of which is one-crop rice land and burnt-over land growing corn, cassava.

10 1,800

2. Impacts of construction inert waste:

50,000

~ n e - ~ r o ~ rice land (m2)

Includes excess rock and spoil, soil material, concrete. This type of waste may cause erosion, sedimentation, muddy stream water, impoverished soil, land occupancy ect.

15 1 ,800m2

3. Vegetation waste from removal of the reservoir and construction site:

Burnt-over land (m2)

Vegetation debris can lead to bush fire. Additionaly, vegetation debris is disintegrated produces organic contaminants causing surface water pollution.

Fallow hilly land (m2)

4. Erosion and sedimentation:

Erosion and sedimentation are as consequences of level the ground, clear plants

Page 22: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

and grass. Because of local natural condition, erosion can cause landslide, affect to traffic system and agriculral land.

5. Air pollution:

Construction engine equipment exhausts contain several air pollutants such as: CO, NOx, SO2, volatile organic substances, dust. These pollutants will affect to workers and local people.

6. Impacts of noise.

High level noise is generated from operation of construction engine equipment, trucks, concret maker, macadam grinding. Noise level may reach to 80-90dBA at construction sites and impact to workers and local people.

7. Dust

This impact will be serious in dry season. Concentration of dust in the air at construction site, along access road can reach to hundreds mg/m3.

8. Sewage and grey water.

Sewage normaly contains big amount of organic components and has very high concentration of BOD5, COD, N-contained substaces, P-contained substaces. Additionaly, there are dozen of harmful bacterium like: e.coli, colifonn.

9. Solid wastes

Similar to sewage, solid waste is one of the enviromental pollution sources based on organic contaminants and harmful1 bacterium.

10. Hazardous materials (fuels, lubricants, explosives etc).

Risks of hazardous materials may cause serious consequences to human, ecosystems, enviroment and properties, especialy, fuel spill.

11. Affect to the local traffic svstems

Damage road, traffic jam due to increase trasportation means, traffic accident ect.

12. Impact to flora and fauna .

Degration of evergreen and semi- deciduous forests may occur when timber is used for construction camps, uncontrolled collection of firewood and bushfire as resuls of using firewood. Workers may trap and hunt animals, especialy catch fish by electric equipments.

13. Human health

Enviroment polluted by dust, noise, engine exhausts, sewage arid grey water, solid waste can impact to workers and local people health by causing various diseases. Morover, workers may suffer from malaria (one of very popular diseases in outback of Northern Vietnam), diarrhoea, petechial fever, bird flu (H5N1) as well as sexual tranmision diseases include HIVIAids.

Page 23: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

14. Enviromental risks include

Diseases spread, landslide, flood, hazardous materials usages and storage, unexplosives, struck by lightning ect.

15. Chance find of cultural artifacts, and areas/structures of local cultural value.

The project's area used to be primeval forest. People have moved to live around these sites not for long time (about last 30 years) as shifting cultivation of wandering hill tribes custom of Dao ethnic people. So that, it is unnecessary to do archaeological study in the project's site. However, process of excavation may discover graves, especialy tombs of village patriarch.

16. Social issues

Local people may complain because they are. not satisfied with land compensation and environmental pollution, road damages. The conflict between local people and workers may happen because of different culture and religions or racism.

3.2. Operation phase

I . Noise from turbine operation.

Maximum noise level may reach to 80dBA or higher when bo.th turbine operate. It will occur about 4-5 months per year during rain season.

2. Impairment of water quality

The main enviromental impacts of the resevoir are linked to change natural flow. However, its affects are not severe like deep and large lake of big hydropower. These impacts will occur only during the first year of impoundment.

+ The water colour will increase in the first year when organic substances (humus) are released from submerged vegetation and soil.

+ Turbility will increase because of shore erosion and increased plankton production.

+ Production of phytoplankton, zooplankton during the first year together with growth of water weed may lead to contamination.

+ Near bottom, the water will be depleted disolved oxygen and production of C 0 2 will increase lead to pH drop.

+ Plankton organisms will be concentrated to the uppermost stratum

3. Reservoir sedimentation:

During the first year, the shore is not stable enough, moreover, land structure of this area consists of light compositions and soil will be easily eroded inside the reservoir. In comming years. sedimentaion will occur due to sand ancl clay deposit. Life of reservoir would shorten if road construction, mining, agriculture, and other human activities in the upper watersheds are not well controlled to reduce sediment flows into reservoirs.

Page 24: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

4. Downstream changes including modification to naturalflows:

Hydrological regime downstream of the plant will be not changed, so that, interference in agricultural irrigation will not hapepn. However, about 0.8km May Ho Stream (after inferior dam), 1.4km of Can Ho stream (after superior dam), and 1.5km of Phin Ho stream (from confluence of above 2 streams to plant) will be effected, but not entirely dried up because of addition water from other branches and streams. Also, the calculated the flow from reservoirs will still maintain as showed on Hydraulic regime of reservoirs, which are approved by jurisdition offices. These affected downstreams have no function of agricultural irrigation, therefore, its impacts to the life of local people is eliminated.

5. Floating Aquatic Vegetation:

Production of phytoplankton, zooplankton and growth of water weed can occur during the first year. Plankton organisms will be concentrated to the uppermost stratum.

6. Impacts on fish and aquatic biota:

+ Impacts to the reservoir: as described above.

+ Downstream the plant: not much impacts in terms of aquatic life because Hydrological regime is not change.

+ The. first 2.7km after dams is impacted. However, due to of poor natural aquatic life, its impacts are not severe.

Page 25: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Chapter 4 : KEY MITIGATION AND MANAGEMENT MEASURES

The developer will be responsible for carrying out all mitigation measures presented in the below table. The developer's main function is construction of civil works and it has experienced staffs and full equipped machines so that the all the project's main civil works are well within its capacity. Beside, the building materials such as concrete, precast concrete, macadam ... are produced by developer. The contractor is only responsible for equipments supply and installed instruction. These measures are not only apply for this project to mitigate the negative impacts but also help to improve the Nam Tien company staffs'awareness and pratice in term of environmental protection which are applied for other hydropower plants. Furtherrn~re,~ one of them support directly to reduce the negative impacts such as sedimentary and erosive limitation for downstream hydropower plants.

4.1. Designing and preperation phase

Table 8: Mitigation Measures on designing and preperation phase

associated infrastructure

Mitigation or Management Measures Construction of project facility and any associated infrastructure have been sited in compliance with the 'TCVN 285-2002 and other current regulations to avoid forested areas, resettlement and erosion areas, natural mineral resources, agricultural land, water resources and other sensitive environment.

Geological study has been done to ensure main facilities of the project such as powerhouse, main dam, spillway dam, penstock to be well sited

Page 26: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

, Siting of access roads

Siting of transmission line

Wherever possible, access roads shall be minimized and be located in areas of existing roads or disturbance.

An access road register, or list, shall be maintained, documenting which access roads were constructed by the subproject and restored after construction is completed. I Minimal impact construction measures such as minimizing ROW width, installing erosion control measures and avoiding environmental sensitive areas, shall be implemented.

Avoid tree cutting or economically productive lands wherever possible

Wherever possible, transmission lines should be located in areas of existing disturbance.

Access to the transmission line should be minimized after construction and all unnecessary access roads should be removed.

Minimal impact construction measures such as minimizing ROW width, installing erosion control measures and avoiding environmental sensitive areas, shall be implemented.

Avoid tree cutting or economically productive lands wherever possible.

Vegetation management of transmission lines should be done manually or machinery. Use of herbicides for vegetation control is not permitted.

Siting and construction of temporary roads

Constructed limitation of temporary road, try the best to use the available roads for internal road. The temporary road has the sufficient surface to reduce the land occupation. These roads are rehabilitated by planting trees after construction period

I Designation and selection of these roads are considered to limit occupation of forest and cultivated areas that have value medicinal plants

Construction of guarded wall, roof at erosive risk sites

Page 27: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Siting construction camps Developer estimated to arrange 4 camps which each has capacity of 80 workers consist of 2 camps at headwork, 1 camp at powerhouse and the rest at waterway.

All selected sites are at lease 1 km far from inhabitants to advoid the life of resident population, 300 m far from stream, 2-3 krn far from graveyard and do not locate at the sensitive ecological areas.

These camps are tried to locate at even and flat land without big trees but mainly brushwood so that to reduce dig and bulldoze ,

Unex~losive materials I Coordinate with Armv force of Lao Cai urovince to clear landmines and unexulosive materials

Page 28: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

4.2. Construction phase

1- Issues Loss of land

Table 9: Mitigation Measures on construction phase

Mitigation or Management Measures Compensation of cultivated land: the compentation of land is complied with the Decree NO

19712004lND-CP issued by Government and Circular NO 14511 998lTT-BTC dated November 4, 1998 issued by Ministry of Finance and requirements from the World Bank as well as meet the expectation of the land loss households. ,

The developer coordinates with the Peope's committees of SaPa district and Ban Khoang commune to implement the compensation

Compensation has to ensure that all the effected households are compensated their lost assets equal the replacement values and inherited other supports with the aim of improving their living standards or at least getting a living as the same as before project.

Public annoucement on project construction, scope of clearance, effected areas especially the impacted people and households

Ensurance of the effected people's interest is finished at least 1 month before project construction. I The cultivated trees which have not harvested will be compensated by the market price or replecement value

For the temporary effected land and other assets, the compensation is carried out as below: I - Compensation for a harvested crop of treeslfarm by the market price I - Compensation for the lost of income in the next years during land occupation by replacement 1

value

- Rehabilitate to original land afier finishing construction phase

Page 29: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

I Vegetation Removal of the Reservoir and Construction Site

Loss of forest

Topsoil stripping and salvage i Construction inert waste management (excess rock and spoil - soil material)

I--- Erosion and sedimentation

Vegetation debris from clearing operations shall be stacked outside cleared areas. The big tree-trunks, bamboos are reused for construction.

Burning shall be limited and must follow Vietnam Decrees and regulations for prevention of forest fire such as Decree Number 22/CP 9/3/1995 and Decree number 09/2006/ND-CP dated 16/01/2006.

Wherever possible and where safety is assured, villagers will be permitted to remove for their personal use at no charge, vegetation such as bamboo and small trees, that have an economic or practical value

-- -

The forests destroyed have to be replanted or rehabilitated at the end of construction period. Planting of forest along the road to compensate the losses by forming road. .Upon completion of the construction, developer will be responsible to bulldoze and reclaim about 50,000m2 of temporarily used land and return it to the local authority. An estimated reforestation is about 20 ha

Topsoil will be stored in the area of 47,200 m2 along waterway and covered to prevent erosion. Soil will be restored to original location and revegetated.

Rock shall be used as fill to the greatest extent possible, excess material shall be disposed at a disposal site approved by regulatory authorities.

A reinstatement and revegetation plan should be implemented so that the area is fully reclaimed to a productive land use.

Bunds, sedimentation ponds, or other silt trapping devices, such as silt fences, shall be constructed to avoid siltation into surface waters. Construction will occur under dry conditions.

Any transmission towers or other structures will be located to avoid steep slope (230") areas.

In case selection of such slope areas cannot be avoided, structures will be designed to minimize excavation on slopes.

Page 30: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Construction engine equipment exhausts

Fuel storage and handling

Ensure that all construction equipment has valid Vietnamese registration and is in good operating condition.

Ensure that all vehicles must follow TCVN 5937-1 995 on noise, vibration and emission and Decision NO 41 34/2001/QD-BGTVT dated 12/05/2001 issued by the Ministry of Transportation on safety and environmental protection. .

Minimize engine idling by turning off equipment not in use for more than 5 minutes. ,

Fuel storage and transport should follow national or sectoral regulations such as TCVN 5684 - 2003 - Firc prevention for fuel projects- General requirements and TCVN 2622 - 1995 - Fire prevention for housing ; projects - Design requirements.

Best practice for fuel storage areas is to locate them at least 100 meters away from any surface water bodic avoid villages and any population centers.

Place equipment on an impervious surface (preferable a synthetic liner) to prevent leaks from contaminatii soil and groundwater.

Ensure that all fuel storage areas are properly bunded (bermed or contained) to contain 1 10% of the stored volume in the event of a spill.

Ensure that spill equipment is in place and that all operators are properly trained in emergency response measures in the event of a spill.

Page 31: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

materials

Vehicles and construction equipment sites

Follow the regulation TCVN-4587-1997 on preservations, transportation and using of industrial explosives

Beside to comply the regulations on usage of explosive, the developer has to:

- Ensure that all operators have certification of explosive operation issued by the functional authorities. Workers without certification are not allowed to operate the explosive.

- Inform to surrounding community the explosive time to safe for them and their livestock I

- Explosion should take place at fix time to create habit for local community and during afternoon hours (1 1 am to 1 pm) to limit effected people

- Assign staffs the task of warning and instructing direction during explosive operation.

Setting up 4 sites (4 x 400 m2): 2 at headwork, 1 at penstock and the rest at powerhouse.

Best practice for these areas is to locate them at least 100 meters away from any surface water bodies, avoid villages and any population centers.

Place equipment on an impervious surface (preferable a synthetic liner) to prevent leaks from contaminating soil and groundwater

Transportation of construction material, equipments, machines ... though the areas of high population density (distances from central Ban Khoang commune to Sa Pa district and from Quang Kim to Phin Ngang) should limit to take place during nightime hours (from 9.00 PM to 6.00 AM next day)

Construction shall be done only during daytime hours (from 7.00AM to 6.00PM).

If noise level is exceeds 70db in residential areas during the daytime (except during blasting), measures such as installing acoustic barriers or other protection measures will be taken.

I f construction during evening is required, the local affected people will be consulted at least one week in advance. - --

Page 32: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Nuisance and dust control To control nuisance and dust the developer should:

I I Maintain all construction-related traffic at or below 15 mph on road within 200 m of the site; I Maintain all on-site vehicle speeds at or below 10 mph.

Maintain noise levels associated with all machinery and equipment at or below 90 dBA.

Minimize production of dust and particulate materials at all times, to avoid impacts on surrounding families and businesses, and especially to vulnerable people (children, elders).

1 Phase removal of vegetation to prevent large areas frorh becoming exposed to wind I Dust control by spraying water shall be implemented on all unpaved roads and construction surfaces, in dry and windy conditions, minimum 2 times per day (especially distances of high transportation density from Ban Khoang commune to Sa Pa district and from Quang Kim to Phin Ngang).

Wearing comforter during working hours in dry and windy conditions is compulsory to workers

/ Local transportations I Use the vehicles and construction machines that have exhausted gas level under permitted limits.

I Regular check on technical condition of vehicles and machines. I To clarify the weight of transported equipments, machines, materials so that the loadability of roads from Sa Pa to project site should stand.

The developer shall be held responsible for any damage caused to local roads and bridges due to the transportation of excessive loads, and shall be required to repair such damage. 1 The developer shall not use any vehicles, either on or off road with grossly excessive, exhaust or noise emissions. In any built up areas, noise mufflers shall be installed and maintained in good condition on all motorized equipment.

/ Adequate traffic control measures shall be maintained by the Contractor throughout the duration of the 1 Contract and such measures shall be subject to prior approval of the Project owner.

1 The trucks carrying construction materials will be covered to adoid sand, soil to be spilled on road. I

Page 33: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 34: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Solid waste management r

Disposal of Construction and Vehicle Waste

Landfill which follow the Circular N' 0 11200 1lTTLT-BXD-BKHCNMT dated January 18,2001 issued by Ministry of Construction and Ministry of Science, Technology and Environment on regulation of landfill technical standards will be implemented outside camps.

Waste will be daily covered by soil to eliminate bad odor and penetration of insects and animals

Bum of solid waste will be prohibited to avoid bushfire

Discharge of solid waste to streams or sites nearby the surface water resources will be prohibited.

The developer shall establish and enforce daily site clean-up 'procedures, including maintenance of adequate disposal facilities for construction debris.

Debris generated due to the dismantling of the existing structures shall be suitably reused, to the .extent feasible, in the proposed construction (e.g. as fill materials for embankments).The disposal of remaining debris shall be carried out only at sites identified and approved by the Project Engineer.

The developer should ensure that these sites (a) are not located within designated forest areas; (b) do not impact natural drainage courses; and (c) do not impact endangeredrare flora. Under no circumstances shall the contractor dispose of any material in environmentally sensitive areas.

In the event any debris or silt from the sites is deposited on adjacent land, the developer .shall immediately remove such, debris or silt and restore the affected area to its original state.

All arrangements for transportation during construction including provision, maintenance, dismantling and clearing debris, where necessary, will be considered incidental to the work and should be planned and implemented by the developer.

I

Page 35: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Identify and demarcate locations for stockpiles and borrow pits, ensuring that they are 15 meters away from critical areas such as steep slopes, erosion-prone soils, and areas that drain directly into sensitive water bodies.

Stock pile and borrow pits

1 / Limit extraction of material to approved and demarcated borrow pits 1

In any borrow pit and disposal site, the developer shall:

Stockpile topsoil when first opening the borrow pit. After all usable borrow has been removed, the previously stockpiled topsoil should be spread back over the borrow area and graded to a smooth, uniform surface, sloped to drain. On steep slopes, benches or terraces may have to be specified to help control erosion.

Excess overburden should be stabilized and replanted. Where appropriate, organic debris and overburden should be spread over the disturbed site to promote replanting. Natural replanting is preferred to the extent practicable.

I Existing drainage channels in areas affected by the operation should be kept free of overburden.

I I Once the job is completed, all construction -generated debris should be removed from the site. I

Page 36: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Chance find of cultural artifacts, and areas/structures of local cultural value

Community complain

In case any historical, cultural or archeological resources that may be encountered during excavation, chance find procedures shall be implemented as per Annex 8, excavation works shall be stopped and the People's committee of Ban Khoang commune and Sapa district, Department of Culture, Sport and Tourism of Sapa shall be immediately informed.

No persons shall be permitted to remove any historical, cultural or archaeological resources; such action are grounds for dismissal or contract cancellation.

Construction work will only be resumed after inspection and written approval to proceed by regulatory authorities.

In case any transmission line or access road or structure passes through, or is to be sited on, village cemeteries, the alignment or site shall be changed. If it is unavoidable, a special consultation with the affected communities would be held to determine culturally appropriate means of relocating the gravesites in accordance to local customs/beliefs/traditions.

No transmission tower pads are to be placed in cemeteries.

All community complains will be concerned and dealt with directly within developer's capacity

If necessary, public consultation will be conducted to find appropriate deal

Coordinate to People committee's of Ban Khoang commune and village patriarch is a great deal

Awareness of environmental protection for workers will be strengthened

Page 37: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Safety from explosive, bomb

Protection of flora and fauna

Worker health care and HIVIAIDS education

The People's committees of Ban Khoang commune and Sa Pa distric, Army force of Sa Pa distric will be informed directly to get the supports whenever finding out the bomb or explosive

Urgent first aid for the victims and transfer them to the nearest hospitals/clinics

Make the report on the spot .

Preserve the spot and set warning sign

Workers will not be allowed to remove plants, trap or hunt animals, or fish; such actions will be cause for dismissal.

Workers will not be allowed to have firearms in camps.

Developer will arrange a health and safety plan two weeks before starting construction work and be responsible for implementing a program for the detection screening of sexually transmitted diseases, especially with regard to HIVIAIDS, amongst laborers is actually carried out.

Workers will be subjected to health screening and health and safety training sessions will be provided; public health education will be part of the construction program.

Necessary safety tools such as helmets, working shoes, ear protection, dust filter and other personal protective equipment will be provided and be required to. be used by workers.

Assign 0 1 medical staff in construction sites enclosed medicine. The staff is responsible to inform the local health authority on suspected signs of epidemic diseases

Page 38: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Safety during construction The developer's responsibilities include the protection of every person and nearby property from construction accidents. The Contractor shall be responsible for complying with all national and local safety requirements and any other measures necessary to avoid accidents, including the following:

Carefully and clearly mark pedestrian-safe access routes;

If school childrenare in the vicinity, include traffic safety personnel to direct traffic during school hours;

Maintain supply of supplies for traffic signs (including paint, easel, sign material, etc.), road marking, and guard rails to maintain pedestrian safety during construction;

Conduct safety training for construction workers prior to beginning work;

Provide personal protective equipment and clothing (goggles, gloves, respirators, dust masks, hard hats, steel-toed and shanked boots, etc.,) for construction workers and enforce their use;

Post Material Safety Data Sheets for each chemical present on the worksite;

Require that all workers read, or are read, all Material Safety Data Sheets.

Clearly explain the risks to them and their partners, especially when pregnant or planning to start a family. Encourage workers to share the information with their physicians, when relevant;

Ensure that the removal of asbestos-containing materials or other toxic substances be performed and disposed of by specially trained workers;

Suspend all work during heavy rains or emergencies of any kind.

Page 39: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

will develop a worker code of conduct policy and program, stipulating requirements of workers to comply with subproject environmental and social commitments. The following activities are prohibited on or near project site:

Cutting of trees for any reason outside the approved construction area;

Hunting, fishing, wildlife capture, or plant collection;

Buying of wild animals for food;

Disturbance to anything with architectural or historical value;

Building fires outside camp areas;

Use of firearms (except authorized security guards);

Use of alcohol by workers during Project hours;

Washing car, motorbikes or machinery in streams or creeks.

Doing maintenance (change of oils and filters) of cars and equipment outside authorized areas.

Disposing trash in unauthorized places;

Driving in an unsafe manner in local roads.

Having caged wild animals (especially birds) in camps.

Working without relevant safety equipment (including boots and helmets).

I Creating nuisances and disturbances in or near communities.

Disrespecting local customs and traditions

I 1 Community Safety Developer will develop a community safety plan two weeks before starting construction work. I I , 1 The community safety plan should inform local residents of equipment movement and operation.

Page 40: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

4.3. Operation phase Table 10: Mitigation Measures on operation phase

contractors have to ensure to meet international standards (-80 dBA at site of 1 meter far from noise source). Turbine will be placed in sound insulated room

Issues / Noise from powerhouse

I I Workers in turbine room should wear sound protected devjce if noise level in excess of 85 dBA. I

Mitigation and management measures Turbines and/or associated rotating equipment shall be imported from China and developer will require

Downriver hydrological changes including modification to natural flows

The reservoir operation regulation has been approved by authorities and it is one of important document .to implement project.

The operation of reservoir will be compliance with above document in order to maintain neckssary flow from reservoir in dry season.

I ( Impairment of water quality Domestic waste water from powerhouse will be treated by septic tanks which meet standards of TCVN

6772-2000 before discharging into stream.

Selective forest clearing within the impoundment area should be completed before reservoir filling.

Clearance of waste, discarded plants which will be drifted from upstream especially in flood season

Sand sedimentation tank (60 m x 5m x m) will be constructed after water intake door to reduce sedimentation in channel and penstock, protect turbine. This measure will also contribute to mitigate impacts of downstream here are Sung Vui, Ngoi Xan I, Van Ho hydropower plants

Page 41: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Floating Aquatic Vegetation. C

1 Pollution control and pre-impoundment selective forest clearing will make reservoir conditions less I Issues

I 1 conducive to aquatic weed proliferation. Physical removal of floating aquatic weeds is effective, though I

Mitigation and management measures ,

1 Chemical poisoningof weeds or'related insect pests is to be avoided. 1

I

Chapter 5: SUPERVISION, FOLLOW-UP AND MONITO'RING

5.1. Monitoring plan Table 11: Monitoring plan

A-p ( construction?

When is monitoring to be done?

What parameter is to be monitored?

Where is the parameter to is the parameter to be monitored? be monitored type of

monitoring e ui ment?

Prior to construction --

Land and propety Developer

I: conpensation construction. Final

report to PB and Sapa district's

compensation performed property?

Prior to start of

People committee

I Compensation . completed before

Land and property

Affected household claimed of any troubles?

Affected household Visual, interview

Page 42: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

PhaseAssue Who is to monitor

Construction Siting of construction camps and camp services

Vegetation clearing and topsoil stripping

When is monitoring to be done?

Camp location -

disturbed or undisturbed site

Arrangements for water supply, sewage, and solid waste

Campsite properly restored? Vegetation debris, disposal practices

Adequacy of topsoil temporary storage site (covered and erosion protection measures in place).

Landscape plan and reinstatement plan in place Waste rock and spoil disposal

Where , is the parameter to be monitored?

What parameter is to be monitored?

Developer

Developer

How is the parameter to be monitored1 type of monitoring equipment?

Camp site Water supply ,

Sewage and garbage disposal sites Waste register

Campsite

Vegetation disposal andlor storage site

Topsoil temporary storage site when completed, revegetation site

Waste rock disposal sites identified.

Monthly report to PB and DoNRE of Sapa district

-

Monthly report to PB and DoNRE of Sapa district

Developer

Visual

Visual

Visual Monthly report to PB and DoNRE of Sapa district

Page 43: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Construction engine equipment exhausts

Erosion and sedimentation

Noise

Who is to monitor

Developer

Developer

Developer

When is monitoring to be done?

Monthly report to PB and DoNRE of Sapa district

Prior to start of construction

Monthly report to PB and DoNRE of Sapa district

What, parameter is to be monitored?

Include COY SO2, NOx, v o c s according to Decision No 4 1341200 1 IQD- BGTVT of Ministry of Transport dated 051 121200 1 and TCVN-6438- 1998 Construction proceeding in dry season?

Appropriate silt traps, temporary erosion control and runoff discharge systems in place

Construction hours

Sound barriers needed and installed? How much .noise level to meet TCVN- 5948-1 999 and

Where is the parameter to be monitored?

Construction sites and local road

Structure site

Sites prone to erosion

Construction site

How is the parameter to be monitored1 type oJ monitoring equipment? Visual. take samples and have analyzed in a ISOIEEC 17025 certified laboratory

Visual

Site observation

Visual

Spot noise monitoring

Page 44: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Who is to monitor I be monitored?

When is monitoring to be done?

Local population informed of any "off-hour" construction at least

to be monitored/ type of monitoring equipment?

What ,parameter is to be monitored?

I one week in advance 1 I I

Where is the parameter to

Dust Developer Monthly report to PB and DoNRE of Sapa district

Water spraying performed properly?

Water withdrawal sites identified, frequency of withdrawal and impact on stream flows, if surface water.

Construction site and access roads

Water withdrawal sites

Visual

Develop register for water withdrawal

Worker safety Developer At start of individual worker shifts, weekly or monthly checks as necessary

Acceptable health and safety plan prepared?

Safety equipment provided to and being used . by

Active work areas requiring PPE

Visual (with a copy of the health and safety plan for verification)

Before construction Visual review o f / workers? Route selection Access road

Page 45: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

and construction

Transmission line routing and construction

Chance find of mltural artifacts, and ~reas/structurcs of local cultural value

Who is to monitor

Developer

Developer

When is monitoring to be done?

and to end of construction period

Before construction

During construction

What parameter is to be monitored?

offers minimal intrusion with new construction, tree cutting, use of productive land etc.

Develop access road register for existing and new access

Route selection offers minimal intrusion with new construction, tree cutting, use of productive land etc.

Migratory bird paths, Ramsar sites etc. avoided? Accidental find of articles of cultural value

Location of * any cemeteries or structures (natural or

be monitored?

locations

Transmission line route selection

At any excavation site

Along planned alignment routes of any transmission towers, or newly

be monitored/ type of monitoring equipment? plans, site visit, air photos

Update access road register on monthly basis

Visual review of plans, site visit

Determine of authorities notified and proper procedures followed?

Determine if proper

Page 46: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Management of hazardous materials (fuels, lubricants, zxplosives etc.)

Solid waste

'otable water quality

Who is to monitor

Developer

Developer

When is monitoring to be done?

Before start of construction and monthly

Monthly report ~ P B and DoNRE of Sapa

Monthly report t a B

What parameter is to be monitored?

man-made) of local value

Confirm chance find procedures in place Storage facilities locked, fenced, well ventilated, on impervious ground?

Location far from population, centers and more than 100 m from waterbody locations

Landfill location

Camp waste accumulation area identified.

Segrcgation and recycling of waste streams

Potable water

be monitored?

planned access roads

Hazardous materials storage site

Off site landfill locations

Camp central waste accumulation areas

Water withdrawal

be monitored/ @pe of monitoring equipment? completed

Visual inspection all fuel, material and chemical storage areas

Develop waste register to record volumes of waste generated and where they are disposed

Visual, take water

Page 47: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

in camp supplies

Who is to monitor

water Developer

When is monitoring to be done?

monitored as to standard water

What parameter$ is to be monitored?

and DoNRE of Sapa .

quality parameters of Ministry of Health (TC 132912002 BYTIQD

sources should be

I to ensure a safe

Monthly report to PB and DoNRE of Sapa

water supply provided to workers. is 1 Confirm if municipal connection in place, if not confirm sewage disposal system in place at camp

Monitor standard parameters as required by TCVN- 6772-2000 - BOD, pH, oil and grease,

1 COD, TSS, I

be monitored?

location or treatment plant

Outfall of sewage disposal

Develop waste register to record waste water performance

How is the parameter to be monitored1 type of monitoring equipment? samples and have analyzed in an ISOIEEC 17025 certified laboratory

Visual, take water samples and have analyzed in an ISOIEEC 17025 certified laboratory

Lp-- 1- I coliforms etc. . I- Operation Noise (from power 1 Developer 1 Quarterly report to 1 Noise levels I At or near power 1 Portable noise

Page 48: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

house)

Solid waste

Sewage

Who is to monito~

Developer

Developer

When is monitoring to be done?

PB and DoNRE of Sapa

Quarterly report to PB and DoNRE of Sapa

Quarterly report to PB and DoNRE of S apa

What parameter is to be monitored?

Sound absorbing measures installed (housing, tree planting, sound barriers etc.) Landfill location

Camp waste accumulation area identified.

Segregation and recycling of waste streams

Confirm if municipal connection in place, if not confirm sewage disposal system in place at c-P

Monitor standard parameters - as required by TCVN- 6772-2000 - BOD,

be monitored?

house

Nearest population benters (particularly if there are complaints) Off site landfill locations

Camp central waste accumulation areas

Outfall of sewage disposal

Develop waste register to record waste water performance

How is the parameter to be monitored type of monitoring equipment? monitoring equipment - db meter

Visual

Develop waste register to record volumes of waste generated and where they are disposed

Visual, take water samples and have analyzed in an ISOIEEC 17025 certified laboratory

Page 49: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Who is to monitor When is monitoring to be done?

What parameter is to be monitored?

pH, oil and grease, COD, TSS, coliforms etc.

be monitored? 1 be monitored1 type of

Where is the pardmeter to

I monitoring

How is the parameter to

Page 50: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

5.2. Institutional Roles and Responsibilities

The main actors are as follows:

Developers - responsible for design, construction and operation of renewable energy subprojects, including environmental assessment and management of subproject impacts. Responsible for preparation of the environmental management plan (EMP) in compliance with World Bank requirements.

Participating Banks (PB) - responsible for providing subproject financing and to undertake a due diligence role to ensure subproject compliance to environmental and social commitments as part of loan agreement provisions.

Administrative Unit (AU) - a unit of the PMB of the Ministry of Indpstry and Trade (MOIT) responsible for administration of the refinancing facility of the investment component of REDP and an oversight role in regard to subproject environmental and social commitments.

Project Management Board (PMB) - unit of the MOIT responsible for overall coordination and management of REDP.

Ministry of Finance (MOF) - facilitates subproject financing to the participating banks upon assurances of the PMB that the subproject complies with project environmental and social commitments.

World Bank - maintains and oversight role in REDP and may provide technical assistance and institutional strengthening in regard to implementation of subproject environmental and social commitments.

Page 51: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Table 12: Subproject Roles and ESF Responsibilities

1 Institution 1 Role in REDP I Responsibility in ESP I Developers

Participating Banks (PBs)

Developers have the main responsibility to d e s i e , build and operate their subprojects. They will ensure all technical and environmental regulatory requirements for approval by Vietnamese authorities have been obtained prior to application to REDP for subproject financing.

Developer is responsible for screening to establish the level of subproject environmental risk, preparation of an EMP, conducting and documenting a public consultation on the EMP, and public disclosure of the EMP. It is also responsible for EMP implementation, monitoring and follow-up procedures to ensure com'pliance with the EMP and Bank safeguards throughout the construction and operation period.

During subproject implementation, developers will submit monthly progress reports on ESF compliance to the PBs.

PBs provide loans to Developers and refinance 80% of the loans from the REDP credit facility.

PB will make sure that the subproject meets all environmental eligibility criteria for REDP refinancing and is in compliance with WB environmental and social safeguards. It will review technical documentation submitted by the developers and undertake due diligence to ensure compliance with all Vietnamese environmental regulatory requirements and approvals. It will also review the EMP and ensure that EMP commitments form part of the loan agreement.

During subproject implementation, PB will supervise subproject implementation to ensure that the responsibilities and protocols specified in the EMP are being properly followed and document their findings as part of their overall reporting of subproject supervision.

PB will submit quarterly progress reports on ESF compliance of REDP developers to the AU.

Page 52: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Institution

Administrative Unit (ALJ)

Project Management Board (PMB)

Role in REDP

The AU is the administrative unit of the PMB and assists in the administration and execution of the refinancing facility of the REDP.

The PMB is responsible for the overall implementation of the REDP on behalf of MOIT.

Responsibility in ESF

The AU is responsible for assisting the PMB to verify that the environmental and social due diligence of the PB was done properly from a procedural basis and issue a letter to the PMB recommending the subproject for financing under the REDP.

During impleryentation, the AU will assist the PMB to verify performance of the PBs in monitoring and reporting of EMP implementation by the developers. This may include a site visit if necessary.

During implementation, the AU will submit quarterly progress reports on ESF compliance of REDP developers to the PMB. The AU will hire consultants to carry out independent monitoring of EMP implementation for all subprojects under the REDP.

The PMB will approve the loan package recommended by the AU, including verification of compliance with REDP environmental and social requirements and WB Safeguard Policies. The PMB will also obtain a no objection from the World Bank regarding the EMP.

During implenientation, the PMB will submit quarterly progress reports to the World Bank including a performance evaluation of the various institutions in regards to ESF compliance.

The PMB, as required, will provide TA to developers, PBs, or the AU to assist them in improving their implementation performance.

The PMB will establish and maintain a pool of qualified environmental consultants from which a developer may select

Page 53: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Ministry of Finance 1 (MOF)

Institution

World Bank (WB)

to assist in meeting the requirements of the ESF. I Role in REDP Responsibility in ESF

The WB will maintain an oversight role in the REDP and ensure compliance to environmental and social safeguards.

Provides financing to Participating Banks

The World Bafik will initially review the EMP of all subprojects to ensure compliance with ESF requirements. When satisfied that the document review and oversight process by the PBs and the AU is satisfactory, the World Bank will limit its reviews to a more modest level. However, if the World Bank feels implementation is not acceptable and does not see any improvements it will recommend institutional capacity building measures to the PMB in order to correct any inadequacies.

Provides financing upon assurance of the PMB that subproject complies with environmental and social commitments.

Page 54: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

5.3. Plan for increasing capacity of environmental management

Developer has appointed environmental experts, whom act as counsellor and help developer to deal with environmental issues during the project implementation. Environmental experts will take part:

1 . Workshops on safety policy of WB as a part of Renewable Energy Development Project

2. Annual training about implementation of environment management for renewable projects development and other power distribution and transmission line projects. Such training courses shall be organized annually by MoIT.

3. Regular training on using and safety of electric organized by Lao Cai Electricity to local resident and company staff.

4. Regularly distributing document and papers on electric. safety to local resident.

Table 13. Training cost for EMP implementation

No

1

2

3

Construction ~ h a s e

Activities

Operation phase

Cost estimates

Participate training courses in Hanoi hosted by WB and MoIT 2 people x 3,000,000 VNDlpersonItime x 2 times Participate local training courses 3 people x 1,000,000 VNDIpeopleltime x 2 times Materials cost

4 1 Annual training (5.000.000 VNDiyear x 30 years) Total

12,000,000

6,000,000

5,000,000 Sub-total

150,000,000 173,000,000

23,000,000

Page 55: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Chapter 6: ESTIMATED COST FOR EMP IMPLEMENTATION

The estimated cost for EMP plementation is presented in the table as below:

Table 14. Budget for EMP implementation (VND)

r ~ o n t e n t s I Construction phase 1 Operation phase (30 years) I 1 Mitigation measures I It's calculated in detailed estimates 1 It's calculated in detailed ~ - 1 of the project 1 estimates of the roject

I I P Cost for samples taking and analysis

-4 timeslyear x 2 years x 10,000,000 VND/time= 80,000,000VND

Chapter 7: PUBLIC CONSULTATION AND DISCLOSURE

Parameters: Noise, wastewater, supply water, air pollutants and dust:

4 ' timeslyear x 30 years x 5,000,000 VND/time= 600.000.000VND

Cost for environmental management improvement

7.1. Public consultant

Parameters: Noise, wastewater, supply water

15,000,000 VND

The public consultation has been conducted in early 2008. the results of the consultation is summarised in Annex 2 as well as attached in this EMP

According to O P B P 4.01 Environmental Assessment policy and Degree No 80/2006/ND-CP of the Vietnam Government dated on Aug. 9.2006, Nam Tien construction investment and trading JS Co submitted EPC to the Ban Khoang people committee as well as Head of Villages related to the project and posted up summary of EPC at the Ban Khoang people committee's office. Developer will do the same with EMP report as soon as it is completed.

EMP report (both in English and Vietnamese) will be posted to Vietnam Information Development Centre, situated at 63 Ly Thai To Str. Hanoi in order to provide information to NGO's and community. EWIP report will be placed in InfoShop of WR.

Page 56: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

I 1 1~301 JO s a ~ n l ~ n ~ ~ s / s e a ~ e pue c s ~ 3 e ~ ~ ~ e le~n11n3 JO pug a3uey3 1 9 1

-

as!oN I I a 8 e ~ l e s pue 8u!dd!~ls ~ ! o s d o ~ 0

~uarua8auem a 8 ~ q ~ e 8 pue a 8 e ~ a s 6

uo!lez!m!u!m uo!~nllod J!V 8

I uo!~~n~lsuo:, pue 8 u y s au!l u o ~ s s ~ m s u e ~ ~ I p I I

uo!l3rulsuo:, pue 8u!l!s peal ssamv I f sdme3 JO uo!~woq

o;

-

uo!lesuadmo:, /Olado~d pue pug7

losodo~dpuo sruauiuto~ samsoaut u o ~ r v $ r ~ ~ san ssl

Page 57: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Venue 7 Time

Annex 2. Summary of public consultant

Meeting hall of the Ban Khoang People committee

7.30 to 11.30

Jan. 0 1.2008

Number of participants

34

Participants

1. Tan Van Chan, Secretary of Party Board of Ban Khoang

2. Chao Phu Chan, Chairman of the Ban Khoang people committee

3. Tan Van Chan, Secretary of Youth Union

4. Ly Quay Dao, Chairman of Ban Khoang farmer Union

5. Tan Coi May, Chairman of Ban Khoang women union

6. Chao Duan Chan, Head of Lu Khau Village

7. Chao Dao On, Head of Can Ho A Village 8. Chao Duan Ta, Head of Can Ho B Village

9. Giang A Phang, Head of Can Ho Mong Village

10. Chao Duan Ngan A, Head of Suoi Thau Village

1 I . Ly Quan Phau, Head of Phin Ho Village

12. Chao Duan Ngan B, Head of Gia Khau Village

13. Representatives of 22 affected households

Summary of participants opinions

- Advocate and create suitable opportunities to carry out the project because of its great advantages in improving local economy and infrastructures, especially traffic system and electricity transmission lines.

- ~ e v k l o ~ e r must carry out feasible measures to minimize negative environmental impacts and ensure sustainable development. '

- Agree with land and property compensations proposal of developer.

Page 58: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 59: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 60: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 61: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 62: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA
Page 63: ENVIRONMENTAL MANAGEMENT PLAN - World Bank · 2016. 7. 15. · VOL. 3 NAM TIEN CONSTRUCTION INVESTMENT AND TRADING JSC. ENVIRONMENTAL MANAGEMENT PLAN CAN HO HYDROPOWER PROJECT SA

Recommended