+ All Categories
Home > Documents > Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff...

Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff...

Date post: 23-Apr-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
171
Environmental Monitoring Report Project Number: 40080-013 Semi - Annual Environmental Monitoring Report (January June 2019) March 2020 VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Prepared by Ha Noi Metropolitan Railway Management Board for Ha Noi People’s Committee and the Asian Development Bank.
Transcript
Page 1: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Environmental Monitoring Report

Project Number: 40080-013

Semi - Annual Environmental Monitoring Report (January – June 2019)

March 2020

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon

– Ha Noi Station Section)

Prepared by Ha Noi Metropolitan Railway Management Board for Ha Noi People’s Committee and the Asian Development Bank.

Page 2: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

NOTE

In this report, “$” refers to US dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT Project Number: 40080-013 Code: PMS2-MRB-SEMR-21.3 Rev 4 Reporting Period: January to June 2019 September 2019

VIE: Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section)

Prepared by: Project Management Support Phase 2 - TPF Getinsa Euroestudios S.L.

Page 4: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

AMENDMENTS RECORD

Revision number

Date Amendment Description

0 25.09.2019 Initial Edition

1 22.11.2019 Updated based on ADB’s comments

2 02.03.2020 Updated based on ADB’s comments

3 12.03.2020 Updated based on ADB’s comments

4 20.03.2020 Updated based on ADB’s comments

Prepared by:

Date: 22/11/2019 Checked by:

Sergio Mata Gallego International Environmental Specialist

Francisco Javier de Bonifaz Barrio Team Leader

Page 5: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04

i

INDEX

I. INTRODUCTION .................................................................................................... 1

A. BACKGROUND ..................................................................................................... 1

B. SCOPE OF THE REPORT ..................................................................................... 1

II. PROJECT GENERAL DESCRIPTION .................................................................... 2

A. OBJECTIVES OF THE PROJECT ......................................................................... 2

B. PROJECT’S MAIN FEATURES.............................................................................. 2

C. STRUCTURE IN PACKAGES ................................................................................ 3

D. CHANGES IN PROJECT SCOPE .......................................................................... 4

III. PROJECT IMPLEMENTATION PROGRESS ......................................................... 7

A. GENERAL PROGRESS as of JUNE 2019 ............................................................. 7

B. CONSTRUCTION WORKS 1ST SEMESTER 2019 ................................................. 9

IV. AGENTS’ ENVIRONMENTAL MANAGEMENT .................................................... 13

A. INCORPORATION OF ENVIRONMENTAL REQUIREMENTS INTO PROJECT CONTRACTUAL ARRANGEMENTS. CEMPs ...................................................... 13

B. CONTRACTOR’S ENVIRONMENTAL AND SAFETY SPECIALISTS MOBILIZATION .................................................................................................... 13

C. OTHER AGENCIES’ SPECIALISTS MOBILIZATION ........................................... 15

V. INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION AND SUPERVISION ............................................................ 16

A. INSTITUTIONAL RESPONSIBILITIES FOR ENVIRONMENTAL MANAGEMENT ASSESSMENT ..................................................................................................... 16

B. ENVIRONMENTAL AND SAFETY MONITORING STRUCTURE ......................... 22

C. ENVIRONMENTAL SUPERVISION PERFORMANCE OF PIC.ASSESSMENT ... 23

D. PROJECT ENVIRONMENTAL REPORTING SYSTEM. ASSESSMENT ............. 24

VI. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS ....... 28

VII. TASKS CARRIED OUT BY THE PMS2 DURING THE PERIOD .......................... 33

VIII. COMPLIANCE WITH EMP. ENVIRONMENTAL MAIN FINDINGS ....................... 37

A. COMPLIANCE WITH EMP ................................................................................... 37

B. TREE RELOCATION/REMOVALACTIVITIES PERFORMED .............................. 58

C. SOIL DISPOSAL AREAS ..................................................................................... 59

D. BUILDING CONDITION SURVEY (BCS) ............................................................. 61

E. INCIDENT RECORD ............................................................................................ 61

F. ISSUES FROM PREVIOUS REPORT(S) ............................................................. 61

G. ISSUES IDENTIFIED BY ADB’S REVIEW MISSION IN APRIL 2019 ................... 64

IX. ENVIRONMENTAL MONITORING PLAN ............................................................ 66

A. Monitoring Plan and Responsibilities .................................................................... 66

B. Result of Environmental Effect Monitoring ............................................................ 68

C. Land Subsidence and Settlement Monitoring at the Underground Section ........... 69

X. PUBLIC CONSULTATION, GRIEVANCE REDRESS MECHANISM .................... 69

A. COMMUNICATION SYSTEM ............................................................................... 69

B. CONSULTATION ACTIVITY DURING THE MONITORING PERIOD ................... 70

C. GRIEVANCE REDRESS MECHANISM (GRM) .................................................... 70

D. STATUS OF RESOLUTION OF COMPLAINTS ................................................... 70

XI. INSTITUTIONAL STRENGTHENING AND TRAINING ......................................... 72

Page 6: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04

ii

XII. CONCLUSION ..................................................................................................... 75

XIII. APPENDICES ...................................................................................................... 82

Appendix 1: PHOTOGRAPHIC REPORT ..................................................................... 82

Appendix 2: TREE RELOCATION AND REMOVAL STATUS. DETAIL ........................ 98

Appendix 3: ENVIRONMENTAL MONITORING RESULTS ........................................ 114

Appendix 4: ENVIRONMENTAL INFORMATION PROVIDED BY PIC IN ITS MONTHLY REPORTS. 1ST SEMESTER 2019 ...................................................................... 125

Appendix 5: INSTRUCTIONS TO PIC REGARDING ITS SUPERVISION AND REPORTING ACTIVITIES. SPECIFIC REPORT ................................................ 148

Appendix 6: INCIDENT RECORD ............................................................................... 153

Appendix 7: PROPOSAL OF ENVIRONMENTAL TRAINING COURSE ..................... 157

Appendix 8: HPC. DRAFT GUIDELINE FOR ENTITIES PERFORMING REDRESS GRIEVANCES OF ORGANIZATIONS, INDIVIDUALS RELATING TO THE IMPLEMENTATION OF HANOI PILOT LIGHT METRO LINE PROJECT, SECTION NHON – HANOI RAILWAY STATION ............................................... 159

List of tables

Table 1. Main Scope of Packages..................................................................................... 3

Table 2. Progress of the Project. June 2019 ..................................................................... 7

Table 3. Carried out works during 1st semester 2019, as of June 2019 ............................ 9

Table 4. Process and status of the CEMPs ..................................................................... 13

Table 5. Status of contractor’s HSE Specialists mobilization ........................................... 14

Table 6. Institutional responsibilities for environmental management .............................. 16

Table 7. Assessment of Project environmental reporting system .................................... 24

Table 8. Status of compliance with ADB’s Loan Covenants ............................................ 29

Table 9. Environmental activities carried out by PMS2 during the period ........................ 34

Table 10.Letters issued during the First Quarter 2019 .................................................... 35

Table 11.Letters issued during the Second Quarter 2019 ............................................... 36

Table 12. Compliance with EMP ..................................................................................... 38

Table 13.Tree Relocation Status ..................................................................................... 58

Table 14.Status of soil disposal areas ......................................................................... 60

Table 15. Status of the Issues raised in the previous SEMR ..................................... 62

Table 16. Issues Identified by ADB’s Review Mission April 2019 .................................... 64

Table 17. Issues Identified by ADB’s Review Mission Site Visit in April 2019 .................. 65

Table 18.Training activities of contractors (First quarter 2019) ........................................ 73

Table 19.Training activities of contractors (Second quarter 2019) ................................... 74

Table 20. PIC's training activities. 1st semester 2019 ..................................................... 74

Table 21.Summary of main identified issues and actions required .................................. 77

List of Figures

Figure 1. General Project’s alignment map ....................................................................... 5

Figure 2.Denomination of the metro stations ..................................................................... 6

Figure 3. General overview of the Project implementation progress as of June 2019........ 8

Figure 4.Environmental and Safety Monitoring Structure ................................................ 23

Figure 5.Current reporting process ................................................................................. 28

Page 7: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04

iii

ABBREVIATIONS

ADB Asian Development Bank AFC Automatic Fare Collection system AFD Agence Française de Development BCS Building Condition Survey CEMP Contractor Environmental Management Plan CP Construction Package DD Detail Design DGTresor Direction General du Tresor DAELIM DAELIM industrial Co., LTD DONRE Department of Natural Resources and Environment EEM Environmental Effect Monitoring EIA Environmental Impact Assessment EIB European Investment Bank EMoP Environmental Monitoring Plan EMP Environmental Management Plan EMR Environmental Monthly Report EMS Environmental Management System EMU Environmental Management Unit EQR Environmental Quarterly Report E&M Electrical and Mechanical GCM Grievance Coordination Mechanism GoV Government of Viet Nam GRM Grievance Redress Mechanism GRSSU Grievance, receiving, Screening and Settling Unit HANCORP Hanoi Construction Corporation HDOT Hanoi Department of Transport HDOJ Hanoi Department of Justice HPC Ha Noi Peoples’ Committee HSE Health, Safety and Environment IES International Environmental Specialist IEVR Independent Environmental Verification Report MONRE Ministry of Natural Resources and Environment MOU Memorandum of Understanding (ADB) MRB Ha Noi Metropolitan Railway Management Board NES National Environmental Specialist PCR Physical Cultural Resources PIC Project Implementation Consultant PID1 Project Implementation Department 1 PMS2 Project Management Support, Phase 2 PPE Personal Protective Equipment RFP Request for Proposal SEMR Semi-annual Environmental Monitoring Report SONO Statement of No Objection TBM Tunnel Boring Machine TOR Terms of Reference TTMP Temporary Traffic Management Plan

Page 8: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 1 of 158

I. INTRODUCTION A. BACKGROUND

1. The Hanoi People’s Committee (HPC) through the Hanoi Metropolitan Railway Management Board (MRB), is carrying out the project HANOI METRO RAIL SYSTEM (LINE 3: SECTION NHON – HANOI RAILWAY STATION), with loans from a number of Financiers to the Government of Vietnam (GoV) including: Asian Development Bank (ADB); European Investments Bank(EIB); and two French Government Agencies - Direction Generale du Tresor de France (DGTresor) and Agence Francaise de Development (AFD).Part of the proceeds of the ADB Loan Agreement has been applied to implement Consulting Services for Project Management Support, Phase 2 (PMS2).

2. TPF GETINSA EUROESTUDIOS, S.L in association with GETINSA VIETNAM JOINT STOCK COMPANY (JSC)as Sub-Consultant, was invited to submit a Proposal to provide the Consulting Services according to the RFP No.: CS1, issued on 19 April 2017. THE AGREEMENT was signed on 27 April 2017, between MRB and TPF GETINSA EUROESTUDIOS, S.L., hereinafter, PMS2.

3. The Consultant PMS2 mobilization started on 15 May 2018.The National Environmental Specialist (NES)was mobilized since 14 June 2018 and the International Environmental Specialist (IES)was mobilized on 25 June 2018 1 . Since then, NES is mobilized permanently, full time and IES was mobilized again in January 2019 and currently in August 2019.

B. SCOPE OF THE REPORT

4. This report, named Semi-Annual Environmental Monitoring Report (SEMR), presents the results of the environmental management performance of monitoring activities developed by involved agents during the period January to June 20192. It’s the third SEMR prepared by PMS2 to inform MRB and ADB about this subject.

5. This SEMR is in line with the Terms of Reference (TOR)of the Consultant’s PMS2 contract. The report documents the implementation of the Environmental Impact Assessment (EIA) 3 specifications and Contractors Environmental Management Plans (CEMP) of civil work packages currently under activity, which reflects the specifications contained in the previous Environmental Management Plan (EMP) prepared for the Detail Design (DD) document.

6. The report was mainly prepared through reviewing the Monthly Progress Reports prepared from January to June 2019 by the Project Implementation Consultant, PIC (no specific environmental monitoring report was prepared by PIC, and specific Environmental Monthly Reports (EMR) and Environmental Quarterly Reports (EQR) for the first semester 2019 prepared by PMS2. As well, site visits were carried out monthly by a National Specialist and on 14 August 2019, jointly by both National and International Specialists of the PMS2. The observations are also considered in the content of the report.

7. Finally, some meetings for coordination activities were held between PMS2 environmental specialists, MRB technical staff and ADB environmental expert.

1Implementation commenced in 2010 with initial works on the depot, while PMS Phase 1 (IDOM) was mobilized from April 2014 to September 2015. During the absence of PMS (after September 2015), a national environmental consultant mobilized by ADB supported MRB in environmental monitoring and its reporting.

2The last environmental monitoring report which covers the period from July to December 2018 has been disclosed on ADB website since May 2019.

3The (updated) EIA has been disclosed on ADB website since August 2013.

Page 9: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 2 of 158

8. The EMR covers the following items or aspects:

• Status of compliance with ADB environmental loan covenants and with the environmental requirements of the Government of Viet Nam during the report period;

• Status of implementation of the environmental mitigation measures during the report period based on the EIA and CEMPs, including information of complaints, if any.

• Results of the environmental monitoring activities for air quality, noise, vibration and surface water quality conducted by the contractors. These results were provided directly by contractors as in the PIC Monthly Progress Report there is no content about contractor’s environmental monitoring activities.

II. PROJECT GENERAL DESCRIPTION

A. OBJECTIVES OF THE PROJECT

9. Building an Urban Railway Line complying with the Plan for transport development of Hanoi Capital up to 2030, vision to 2050 approved by the Prime Minister in the Decision ref No. 519/2015/QD-TTg dated 31 March 2016.

10. Developing synchronously urban infrastructural system in line with modernization in order to improve the public transportation capacity, respond to requirements for social-economic development of the Capital, disentangle the congestion occurrences, improve the traffic safety, reduce pollution caused by traffic in the center area of Hanoi.

11. Socially the project will be a benefit to the population in the project area. The population, located in the western area of Ha Noi will, by using the metro, avoid traffic congestion and reduce traffic safety hazards (especially traffic accidents); reduce health-related problems (especially respiratory problems) due to air pollution and dust; and save time and benefit from a good transportation alternative to go to Ha Noi Centre and the central railway station (Ga Ha Noi).

B. PROJECT’S MAIN FEATURES

12. The Project runs crossing Hanoi City from Ha Noi University in the West to Ha Noi Railway Station, in the East, always in the South of West Lake (Figure 1). The approved scope of the project includes civil works, equipment, consulting services and resettlement for the implementation of a metro line of about 12.5 kilometers with 12 stations, eight elevated and four underground (see Figure 2). The Project is included in the Plan for Transport Development of Hanoi Capital up to 2030, vision to 2050.

13. Here are summarized the main features of this project:

✓ Total length of the line is 12.5 km, ✓ Maintenance Depot with stabling area at Nhon, start point, ✓ 8.5 km elevated viaduct section, ✓ 12 stations comprising: 8 elevated stations, 4 underground stations (Average

distance between stations of 1,000m), ✓ 4 km twin tube underground tunnel, ✓ Double line track on separate guide way: 1,435 mm gauge, ✓ CBTC (Communications-Based Train Control) signaling system, ✓ 10 trains comprising 4 cars, with commercial speed 39 km/h and maximum

speed 80 km/h ✓ Traction power of 750v Direct Current (DC) through 3rd rail,

Page 10: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 3 of 158

✓ Communication system: radio, telephone, data, CCTV (Closed Circuit Television) public address,

✓ OCC (Operations Control System) - SCADA (Supervisory Control and Data Acquisition) SYSTEM,

✓ Central Control Room, ✓ Surveillance and alert system, ✓ Firefighting systems, ✓ Electrical and Mechanical (E&M) system, ✓ Automatic Fare Collection system (AFC).

14. The systems will be designed and built according to international and local standards and regulations. The route of the line and the station locations are shown in Figure 1.

C. STRUCTURE IN PACKAGES

15. The project includes 9 main civil works and system packages, as shown inTable 1.Some of them, CP01 to CP05 are construction units with clear environmental implications.

Table 1. Main Scope of Packages

Package Title Main Scope

CP01 Construction of Elevated section - Line

Viaduct, Bridges, Access ramp to depot, Above ground part of ramp to underground station

CP02 Construction of Elevated section - Stations

Structures, Architectural finishes Low voltage and plumbing

CP03 Construction of Underground section Tunnels and Stations

Structures, Architectural finishes Low voltage and plumbing

CP04 Construction of Depot Infrastructure

Depot infrastructure

CP05 Construction of Depot Architectural works

Construction of buildings and workshops

CP06

Rail systems 1: Rolling stock, Depot equipment, OCC/SCADA, signaling, communication, power supply

Design, supply and install: Rolling stock, Depot equipment, OCC/SCADA (includes BMS in stations), signaling, communication, power supply (medium voltage 22kV and traction power)

CP07 Rail systems 2: Electrical and Mechanical (E&M)

Design, supply and install: E&M systems, Ventilation systems, Firefighting systems, Lifts and escalators, Dewatering

CP08 Rail systems 3: Track Works

Design, supply and install: Rails for all the line and inside the Depot (includes 3rd rail)

CP09 Rail systems 4: Automatic Fare Collection (AFC)

Design, supply and install AFC system

16. As well, there is a consulting firm for the project design, supervision of the civil works and implementation support, named Project Implementation Consultant (PIC).

Page 11: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 4 of 158

D. CHANGES IN PROJECT SCOPE

17. There has been no change in the project scope that might mean any new environmental determination or a change in the intensity of the already foreseen impacts.

Page 12: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 5 of 158

Figure 1. General Project’s alignment map

Page 13: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 6 of 158

Figure 2.Denomination of the metro stations

Page 14: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 7 of 158

III. PROJECT IMPLEMENTATION PROGRESS

A. GENERAL PROGRESS as of JUNE 2019

18. Table 2 shows the progress of the civil works until June 2019, as it’s reflected in the Consultant’s Monthly Report Project Quality and Progress for that month, as last available updated information for this first semester 2019.In terms of percentage of the total construction cost, the progress may be summarized as follows (Table 2):

Table 2. Progress of the Project. June 2019

Pack. Started Completed Progress Dec 2018

(%)

Progress Jun 2019

(%) Remarks

CP01 4 Jul 2014

August 2018, 50 months (expected, according to the last approved

amendment of the contract)

99.12 99.39

Currently, a new amendment is being negotiated to expend

the contract duration. According to that amendment, in case it’s finally approved,

works will finish by December 2019.

CP02 27 May 2014

Initial duration: 57 months

59.27 61.32

Initial approved period has expired. Currently, an

amendment for its extension is being prepared.

CP03 6 Feb 2017

Initial duration: 49 months

2.59 5.01

According to the progress, it’s expected that completion will not be as scheduled. Tunnel works have not started yet.

CP04 22 Sep 2010

Initial duration: 18 months

Completion date: December 2017

100 100 Completed, construction works

are finished.

CP05 10 Jan 2013

71 months (according to the amendment 6 of

the contract)

52.43 54.64

According to the total extended period, works should have been finished in December

2018.

CP06 16 Oct 2017

Initial duration: 47 months

18.79 34.44

CP07 26 Apr 2016

Initial duration: 40 months

28.12 34.67

CP08 05 Sep 2017

Initial duration: 36 months

41.56 50,69

CP09 0 0 This Package is still in tender

phase.

Page 15: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 8 of 158

Figure 3. General overview of the Project implementation progress as of June 2019

Page 16: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 9 of 158

B. CONSTRUCTION WORKS 1ST SEMESTER 2019

19. Updated information provided by the PIC through the Monthly Progress report for June 2019, details the status of works during the first semester 2019 for each package. Along this semester, seven packages (CP01, CP02, CP03, CP05, CP06, CP07 and CP08) were active on site, although the progress of the works was not significant except for packages CP06, that almost doubled the progress compared with the previous semester, CP07, that progressed about 6% and CP08, that progressed about 9%. Regarding CP06, CP07 and CP08, Table 2 shows a significant progress during this semester, although Table 3shows that no appreciable construction activity on site. This is due to the concept of progress, which is referred to percentage of total cost. These mentioned packages mostly provided and stored material for future works.

Table 3. Carried out works during 1st semester 2019, as of June 2019

Package / Contractor

Construction activities

CP01

Completed works: - Pile, Pile cap, Pier, Pier cap, Bridge Superstructure (CIP Girder), Bridge

Superstructure (Cantilever Segments), Bridge Concrete Parapet (CIP Girder), Bridge Metal Parapet (FCM Bridge), Bridge Aluminum Cladding (FCM Bridge), Typical U Girder Production, Typical U Girder Erection, Ramp Structures (Top Slab), Ramp Structures (Walls/Parapets), Steel Handrail.

- All special bridges - Casting concrete 1st stage foundation for RIS at P341-P342. - Installation of aluminum cladding at 2RR Bridge.

Pending works are as follows: - construction of Road underneath Access bridge, to complete the drainage

connection to city manhole, and relocation of noted obstructions. - site handover of viaduct to CP08 - completion of MSE wall landscaping works. - completion of RIS foundation

Road re-instatement, drainage works, and removal of temporary fence were progressing at various locations.

CP02

Design activities: General progress design is 84.32%. Several items are already approved, mainly regarding steel structure design, architecture, plumbing and access entrance.

Construction activities: - Concourse level to Platform level structure 3909: Station 1 to 8 completed. - Road reinstatement has completed at station 1, 2, 3, 4, 5, 6 & 7. - Technical room at ground level (masonry): Completed at Station 1, 2, 3, 4, 5, 6

&7, and progressing at Station 8. - Architecture work (masonry and screed at concourse level and platform level) is

in progress at Station 1, 2, 3, 4, 5, 6 7 & 8. - Fabrication of Steel structure has started from 9th of October. PSC has to speed

up the production and delivery of Main roof steel structures for Stations 1, 4 & 5. - Installation of main roof at Station: • Station 2, 3 & 6 - Erection of main roof structural component was completed, on-

going for final welding works. PSC has to finalize construction documents for roof cover materials and to start installation of roof cover promptly.

• Station 1, 4 & 5 - To accelerate fabrication, delivery and erection of main roof structural components.

- Roof finishing works: Preparation works started in Station 6. - Access entrance construction: PSC has to accelerate submittal for technical design

change for S05, S06, S07 & S08, construction documents for test pile, jet grouting pile foundation, concrete & architectural drawing for upper structure, and to complete trial pit for checking the underground obstruction for S02-S08.

Page 17: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 10 of 158

Package / Contractor

Construction activities

The Contractor has to follow-up/obtain for DOT’s approval. - Finalize HOTSA for site access to CP07 to start ECS & FFS works at Station 1 &

2, and initiate HOTSA process for Station 3 & 4. - Water pipeline and sanitary drainage pipe installation by CP02 are progressing at

Station 6. - Cable tray installation by CP02 is progressing at Stations 6 & 1. - Duct and FFS installation by CP07 are progressing at Stations 6. - Embedded items for walls by CP06 are progressing at Stations 6.

CP03

Design activities: Progress of the design is 55.41%. As planned, Design should be already finished.

Construction activities: Progress of the construction works is 5%. - At Station 10, trial fencing work started from 12 April 2018. The formal handing

over to contractor of Phase 1 (North Part) was completed. The site hand over at Small Kim Ma Street was finalized.

- At Station 9 and Ramp E, trial fencing work started from 27 October 2018. The permanent fencing already finished.

- On 22 May 2019, HGU received the Emergency shaft from the Employer. - At Station 12, trial fencing work started from 22 June 2019. - The temporary site office almost completed but still not inspected. - Fencing at Ramp Zone E and St.9 are completed in December 2018. - Tree cutting and replanting activity: Trees at Ramp zone E&C, St.9 and St.11 are

done. At shaft and station 12 this work has a major delay. - The Thu Le Detour road is partially performed up to subbase and one section was

handed over to CP1 on 15 June 2018. The area handed over back by CP01 by 10/8/2018 with 10 days delay.

- Ramp zone A+B: The pilot bored pile, bored pile at Ramp and its pile tests were completed and accepted. D-wall started on 24 October 2018 and is currently done

- Ramp zone E: D-wall started on 22 December 2018 and is currently under progress.

- Station 9: D-wall started on 23 December 2018 and finished on 21 May 2019. Excavation of top slab started from 20 May 2019 and already done without PIC’s supervision for 7 segments.

- Station 10: D-wall of north side is completed. HGU start excavation from 19 April 2019.

CP05

- Building No. 1-2-14-31A: • Brickwork: From the 1st floor to 5th floors 1st floor completed 95%. Areas not

completed are affected by the hoist. • Internal plastering work: The 2nd /3rd/4th/5th floors completed 100%. • External plastering work: Building No.1 completed 100%; Building No.2, 31

completed 95%; • Building No.14 completed 100%. The area affected by the hoist has not finished

yet. • MEP work: Installation of electric conduits and water supply pipes: Completed

100% at the 2nd/3rd/4th/5th floors & 60% on the 1st floor. • Tiling work: Completed 100% for the 2nd, 3rd, 4th and 5th floor. The toilet area

has been completed 100% for the 2nd, 3rd, 4th, 5th floors and 50% for the 1st floor. External wall tiling is completed 25% for the building No.1, 90% for the building No.2-31, 0% for the building No.14.

• Waterproofing work: the toilet areas were completed and completed 100% for the 1st, 2nd, 3rd, 4th, 5th floors. Other areas, in progress.

- Building No. 21A: • Concrete for pile caps, cable trench, lean concrete for ground slab are completed

100%. • Setting rebar, formwork for column is ongoing.

Page 18: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 11 of 158

Package / Contractor

Construction activities

- Building No. 21B, 22, 24: • Lean concrete for piles caps is completed 36%. • Cutting & treatment pile head is ongoing.

- Building No. 23, 27: • Concrete for pump pit is completed 100%. • Lean concrete for pile caps & ground beam is completed 90%. • Concrete for cable trench is completed 50%. • Fabrication for rebar of ground beam, pile caps are ongoing and sand mix

cement back filling is ongoing. - Building No. 07: • Welding work of steel frame, lining concrete for pump pit (axis G-K/4-6),

Concrete for pump pit (axis 4-5/H-I) completed at 100%. • Filling sand and pile head chipping for foundation axis G-K/1-4 is on progress

- Building 8,9,10,11: • Pile caps, ✓ lean concrete of MBF axis 1-2, excavation work for slab, pump pit

Axis D-G, plastering work for septic tank and welding work of main steel column in Quang Minh factory have been completed at 100%.

• Concreting work for ditch and cable trough (axis 5-21/D-G) is completed 80% • Concreting work for pump pit (axis 5-21/D-G) and for cable trench axis (20-21/D-

G) is completed 90% • Filling sand for foundation and ground slab (axis 5-14/D-G), rebar installation for

ground slab axis 14-21/D-G and 1-5/D-G, MEPF work for ground slab is on progress.

- Building No. 04: • Installation of traveling-crane steel beam, staircase, brickworks, internal and

external plastering works and the toilet areas for the 2nd floor have been completed.

- Building No. 06: • Steel structure installation, fabrication and installation of shutter frames and roof

metal sheet installation have been completed at 100%; • Steel platform support (column and beam) has been installed about 70%.

- Building No. 12: • Pile cap has been completed at 100%; • Steel material delivery to manufactory is completed 60%.

- Building No. 13: • Plastering of external & internal wall and waterproofing for roof has been

completed 100%. • MEP work: PVC pipe installation for roof drainage system has been completed.

- Building No. 20: • Plastering of external & internal wall, PVC pipe installation for roof drainage

system and waterproofing for roof have been completed 100%. - Building No. 15: • MEP work: the installation of electric conduits and water supply pipes; brick &

plastering wall works and waterproofing for roof have been completed 100%. • Tiling work: It has been completed 50%. • Roof metal sheet installation has been completed at 95%.

- Building No. 17-19: • Brick and plastering works: external walls have been done at 99% and internal

wall have been completed at 100%, 1st floor and90%, 2nd floor. • MEP work: the installation of electric conduits and water supply pipes (2nd floor)

and tiling work for slab and toilet are in progress. • Concreting work in progress for bracing (1-21/A-D) 100% & stair 1, 2 has been

completed at 100% • Metal sheet installation work has been done at 98%.

Page 19: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 12 of 158

Package / Contractor

Construction activities

• Canopy installation is completed 90% - Building No. 28-29: • Brick work & Installation of electric conduit and water supply pipes have been

completed at 100% • Internal plastering work: Completed at 80%.

- Building No. 31B: • Brick works, external and internal plastering works, installation of electric

conduits and water supply pipes, roofing metal sheet work and tiling work for slab and toilet have been completed at 100%.

CP06

Design activities progressed to 54.79%. Procurement activities progressed to 36.87%.

Manufacturing and FAT’s for majority of sub-systems are under progress, with several shipments that have already been delivered to UJV warehouse(s) in Hanoi. Serval shipments are still pending customs TAX clearance.

Installation activities. Progress is not reflected in the PIC report - Thales have started the installation works in Station 6 for containment in

Concourse areas and embedded conduits for Access Control in “back of house” technical rooms.

- There are several on-going pre-HOTSA’s being carried out for the remaining Thales technical rooms, LPS room and UPS Battery room in Station 6. The final HOTSA has been rejected by CP06.

- Preparation work for the two EVN cable routes, Cau Dien to Station 2 and My Dinh to Station 5, have been reviewed by PIC and MRB and have also now been agreed with Local Authorities.

CP07

Design activities progressed to 65.92%. Procurement activities progressed to 40.66%. Interface and HOTSA status. Preparing escalator area at Station 6. The HOTSA for station 01 gridline (5-15) is signed. No HOTSA is signed for station 02. Installation and Construction activities. Contractor had continued the installation of ECS duct system, firefighting pipes, clean agent pipes, fire alarm system, and preparation for the Escalator installation in station 6.

CP08

Design activities progressed to 57.26%. Procurement activities progressed to 62.04%. Installation and Construction activities. The logistics for installation activities have started.

Page 20: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 13 of 158

IV. AGENTS’ ENVIRONMENTAL MANAGEMENT

A. INCORPORATION OF ENVIRONMENTAL REQUIREMENTS INTO PROJECT CONTRACTUAL ARRANGEMENTS. CEMPs

20. The EMP which is part of the EIA was included in the biding documents of five civil contractors (CP-01, CP-02, CP-03, CP-04 and CP-05). They were required to prepare Contractor’s EMP (CEMP) for detailing their mitigation action plans based on the EMP, to address construction impacts specific to site conditions. The CEMPs of CP-01, CP-02, CP-03, CP-04 and CP-05 were approved prior to construction start, as follows:

Table 4. Process and status of the CEMPs

Status CP01 CP02 CP03 CP04 CP05

Send PIC for review 06/092014 13/01/2014 20/02/2017 15/12/2013 21/02/2013 Issue No objection by PIC

10/09/2014 05/02/2014 08/05/2017 28/12/2013 07/03/2013

MRB Review and agree to submit CEMP to ADB for clearance and approval

4/6/2016 02/04/2014 28/07/2017 22/01/2014 08/04/2013

ADB’s receipt 1st review 2nd review 3rd review 4th review

20/10/2014 18/12/2014 23/01/2014 01/06/2016 15/12/2016

03/04/2014 30/06/2014 15/10/2014 21/10/2014 15/12/2014

28/07/2017 5/10/2017

19/01/2013 01/02/2013

08/04/2013

ADB’s approval Approved Approved Approved Approved Approved

21. Contractors for Packages CP-06 to CP-09, although they were not requested to prepare their specific CEMP, they need to implement main basic environmental protection measures, according to the approved EIA, Vietnamese regulations and ADB Policy.

B. CONTRACTOR’S ENVIRONMENTAL AND SAFETY SPECIALISTS MOBILIZATION

22. The key personnel mobilization in each contractor’s staff, regarding to Health, Safety and Environment(HSE) matters, is described as follows and summarized inTable 5. This information was updated in the end of June 2019.

23. The contractors established HSE management units in charge of environment and safety to ensure implementation of the CEMP, in the first semester of 2018. Site inspections for safety issues are conducted daily by safety engineers of contractors; the contractors have always at least one safety engineer on site during construction time. All environmental and safety staff of contractors have been trained on HSE course and have certificates on labor safety supervision issued by authorized agencies such as Safety Training – Inspection – Environmental Survey JSC and Solution Safety and Health Co., Ltd.

Page 21: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 14 of 158

Table 5. Status of contractor’s HSE Specialists mobilization

PACK. POSITION CURRENT STATUS

REMARK PROPOSED APPROVED MOBILIZED NAME

CP01 Environmental Manager - - - -

Safety Manager Yes Yes Yes Vu Van Thuy was replaced by Nguyen Khanh Toan in Q3 2018

HSE Manager

CP02 Environmental Manager Yes Yes Yes Nghiem Xuan Anh Safety Manager Yes Yes Yes Nguyen Quoc Tuan HSE Manager

CP03 Environmental Manager - - Yes Tran Bien Gioi Mobilized in Q2 2019

Safety Manager Yes Yes Yes Paul Evans. HSE Manager. Mobilized in Q1 2019

CP05 Environmental Manager - - - - Safety Manager Yes Yes Yes Nguyen Thanh Son HSE Manager

CP06 Environmental Manager - - - - No construction works.

Activities are developed in France Safety Manager - - - -

CP07 Environmental Manager - - - - Safety Manager Yes Yes Yes Duong Quoc Hung HSE Manager

CP08 Environmental Manager - Safety Manager Yes Yes Yes Vu Van Thuy HSE Manager

Page 22: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 15 of 158

24. In the table it may be observed that Packages CP02 and CP03 have one staff for environmental matters aside from one Safety Manager. Packages CP01, CP05, CP07 and CP08 keep mobilizing since June 2019 one manager for three subjects (Health, Safety and Environment). PMS2 considers that this is enough, as CP01 is near completion, and other packages are developed also in well limited and restricted areas. As well, no significant environmental impacts have happened in these packages. Therefore, PMS2 considers that, according to the current progress of the works and the scale of the pending works, one HSE Manager for each of these packages can develop the supervision of the three matters. CP04 has already finished works and CP06 is mainly developing design works and activities, carried out in France, so currently no staff on site. Regarding CP03, it’s noted that the contractor mobilized a specialist for environmental matters in Q2 2019.

C. OTHER AGENCIES’ SPECIALISTS MOBILIZATION

25. Project Implementation Consultant (PIC) has assigned one international HSE specialist, already mobilized when PMS2 started works in May 2018, in charge of these three matters (HSE) and for all packages under PIC supervision. However, in view of large and long construction site (about 12 km) and very strict requirements on safety, the specialist focused mainly on safety issues, with less attention to EMP compliance monitoring and reporting. In previous SEMRs, PMS2 recommended that PIC should mobilize a specific environmental specialist.

26. Regrettably, not only the recommendation was not assumed but also the HSE Manager was demobilized in February 2019.It means that during almost the whole semester (after February to June 2019), PIC had no specialized staff for any of these three subjects. PMS2 considers this fact not acceptable as Health-Safety and Environment are essential part of the implementation of a project during the construction phase.

27. Regarding this important non-compliance with PIC’s responsibility, it has to be also pointed out that during the preparation of this report, August 2019, it was not informed the mobilization of a new HSE.

28. Ha Noi Metro Railway Board (MRB)assigned an experienced environmental specialist as the specific officer for environmental management since April to December 2017. This officer has conducted regular site inspections, reviewed environmental reports prepared by contractors, PIC and other all tasks related to environmental and safety issues. However, since December 2017, MRB has no specialist for environment, health and safety issues, although there is one engineer in charge of the coordination with PMS2 for these subjects. PMS2 acts in fact as Client’s direct support, as requested by MRB, being in charge of environmental matters.

29. Project Management Support consultant, Phase 2 (PMS2), which contract was signed in May 2018, has mobilized full time a NES by middle June 2018. Until June 2019, this specialist continues developing his duties. As well, the IES was mobilized to arrange and coordinate the works for a first period by end of June 2018 to prepare the SEMR No.1, for a second period by January 2019 to prepare the corresponding SEMR No.2 and currently for a third period in August 2019.

30. The External Specialist was also mobilized on 27 June 2018 and prepared an Independent Environmental Verification Report (IEVR No.1) that was submitted and approved by MRB. After the resignation of this specialist, due to private matters, a new one was proposed to MRB and he was evaluated for approval. While drafting this report, ADB expressed no objection to the proposal and MRB issued its approval. It’s scheduled that the independent specialist may be mobilized in September 2019 to prepare the IEVR No.2 (covering the period from July 2018 to September 2019) (See item “External Expert” of Table 6).

Page 23: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 16 of 158

V. INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION AND SUPERVISION

A. INSTITUTIONAL RESPONSIBILITIES FOR ENVIRONMENTAL MANAGEMENT ASSESSMENT

31. The roles and responsibilities of the different project stakeholders in EMP implementation and monitoring are described in Table 6, as well as a brief assessment of the compliance with each of them.

Table 6. Institutional responsibilities for environmental management

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

HPC/MRB

Project owner with overall responsibility for project construction and operation. Ensure that sufficient funds are available to properly implement the EMP. Ensure that EMP provisions are implemented for the entire Project regardless of financing source. Ensure that Project implementation complies with the GOV and ADB's environmental policy principles and requirements.

Complied with PMS2 environmental experts were mobilized in June 2018 and they are developing their tasks according to the Terms of Reference of PMS2 Contract, supporting MRB in all activities related with the assessment of the compliance with GOV and ADB’s environmental policy and requirements.

- Project implementing agency with designated overall responsibility for project construction and operation including environmental performance.

- Submit semi-annual monitoring reports on EMP implementation to ADB and MONRE.

- Engage external expert(s) to undertake annual independent verification of monitoring information submitted to ADB and to determine if various EMP provisions are being implemented in thorough and timely manner and in accordance with budget identified within the EMP.

- Submit annual external environmental monitoring reports to ADB.

- Ensure that tender and contract documents include the EMP.

- Liaison with Department of Defense and Vietnamese Army on UXO issues.

- Ensure that EMP provisions are strictly implemented during pre-

Partially complied with - This semi-annual monitoring report,

3rd since PMS2 started its works, covers the period Jan-Jun 2019.

- The external environmental monitoring report for the period March 2017 to June 2018 has been submitted to ADB and approved.

- MRB keeps coordination with related agencies in matters of mutual concern.

- UXO: The project is hiring a company that has suitable functions and capabilities (Lung Lo Co., Ltd) under Ministry of National Defense to clear mines and explosives before the construction of all sites of the project; ensuring safe distance and warnings for people during the implementation in accordance with QCVN 01: 2012/BQP - National technical regulations on clearance of explosive ordnance and QCVN 02: 2008/BCT-National technical standards on safety in transportation, preservation, use and destruction of industrial explosive materials. No finding UXO so far.

Page 24: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 17 of 158

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

construction, construction and operation phases of the project.

- MRB, through its Project Management Support Consultant (PMS2), inspects weekly or bi-weekly all main construction sites to verify if the EMPs are in fact being implemented accordingly with the specifications.

- The results of those inspections and from the review of the documentation generated by PIC are submitted to MRB through monthly reports.

Establish a grievance redress mechanism (GRM) as described in the EIA. Establish an Environmental Management Unit (EMU) staffed by qualified and experienced environmental officer and occupational health and safety officer.

Partially complied with, as the GRM has not been approved yet. A Grievance, Receiving, Screening and Settling Unit (GRSSU) was established at the MRB per Decision No.63/QD-DSDT-VP dated 22 May 2017. A draft final GRM has been developed in consultation with ADB and submitted to HPC for clearance and approval on 3 July 2017. After that, the GRM document was submitted to Department of Justice for review and consideration. While preparing this report MRB confirmed that Department of Justice agreed with the GRM and that it was again sent to HPC for final approval. In August 2018, HPC submitted a letter to MRB including some comments regarding this GRM proposed, requesting clarification. In October 2018, MRB convened a meeting with HPC in order to explain and discuss those comments. After that, HPC drafts a Guideline “For entities performing redress grievances of organizations, individuals relating to the implementation of Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi railway station” with some corrections to the previous draft of GRM and resubmits to MRB. MRB submits the draft to ADB for review, by mail, on 3 June 2019. On 10 July 2019, ADB sent back the document with some comments for its update. Currently, MRB is updating the draft guideline considering the comments received from ADB and other related agencies and will resubmit it to HPC for final approval.

Page 25: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 18 of 158

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

As of August 2019, the GRM is not yet approved by HPC. An EMU has not been established, but MRB has signed a contract with an experienced environmental specialist in April 2017, in charge of environment and safety issues at MRB. This specialist stopped working by end of 2017.MRB has not been assigning an qualified and experienced environmental officer since December 2017. Since the mobilization of support consultant’s environmental specialists by middle June 2018, PMS2 has been requested by MRB to take in charge this responsibility and assume MRB’s environmental duties. Currently, PMS2 is developing this task through a continuous cooperation with MRB staff in charge of environmental coordination. Therefore, it may be considered that the tasks of the EMU are being developed.

Undertake monitoring of the implementation of the EMP (mitigation and monitoring measures) with assistance from PIC.

complied with During this first semester 2019, weekly or bi-weekly environmental inspections of the construction sites are being conducted by PMS2 NES, according to our duties with the TOR and agreements with MRB.

Project Implementation

Consultant (PIC)

SYSTRA

Undertake environmental effects monitoring during pre-construction and construction phases for depot, viaduct and tunnel components

Not satisfactory complied with After the last change in the contract of PIC on 21 March 2014, the Supervision Consultant does not take responsibility to implement the effect monitoring program. PMS2 does not consider or value this change in PIC’s contract but considers that it’s a non-compliance with its duties as a construction supervision consultant. Since January 2019 and especially in August 2019, PMS2, in coordination with MRB, is trying to change this situation. In this line of action, in August 2019 and following MRB instructions after PMS2 proposed it, a specific report was prepared with detailed instructions for PIC to carry out and report environmental supervision on site. This report is included in this SEMR as Appendix 5.

Page 26: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 19 of 158

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

Undertake environmental training for EMU, HRB/PMU staff as required in the EMP

Not complied with PIC did not undertake environmental training for EMU, MRB staff as required in the EMP. Developed activities with other parties were as follows: - training in class for site inspectors. - monitored CP02, CP03, CP05 and CP08 HIV and Gender mainstreaming training. - monitored CP08 HSE Induction.

Monitor the environmental performance of contractors in terms of implementation of mitigation measures for pre-construction and construction phase as specified in the EMP. Monitor over-all implementation of various EMP provisions. Review and approve the specific environmental management plans (e.g., Spoils Disposal Plan, Dust Control Plan, Noise Control Plan, etc.) to be prepared by contractors as specified in the EMP.

Being Complied with PIC carries out daily site inspections in term of contractor’s mitigation measures implementation, even at night when it’s needed, reviews and revises contractor’s monthly internal monitoring reports incorporated with a checklist on EMP implementation. CEMP of all contractors were already approved before ending 2017. However, as no information about the daily activities are included in the monthly progress reports, works on site may not be verified.

Prepare monthly environmental monitoring reports on EMP implementation.

Not complied with. There has been no HSE specialist under PIC since February 2019. This semester, PIC did not prepare any environmental monitoring report on EMP implementation as requested since PMS2 began its works. The environmental information provided by PIC in the Monthly Progress Report does not reflect environmental monitoring works. PIC includes a short section regarding environmental management in their monthly progress reports, for each construction package. The section shows only some comments about environmental subjects but not the level of compliance with each CEMP. Therefore, the content of this section is considered not enough at all as complete information from the Supervision Consultant. Even, it was observed that the content of this section is absolutely similar in all the 6 reports of the semester. This reported information is included in this SEMR as Appendix 4.

Page 27: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 20 of 158

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

Project Management

Support consultant,

Phase 2 (PMS2)

Ensure that the PIC is implementing its responsibilities specified in the EMP such as conduct of environmental effects monitoring; monitoring of environmental performance of contractors; implementation of environmental training for EMU, HRB/PMU staff; over-all monitoring of EMP implementation; and preparation of monthly environmental monitoring reports for submission to HRB Assist HRB/PMU/EMU in preparing semi-annual environmental monitoring reports for submission to ADB. The semi-annual reports shall be based on the monthly reports prepared by the PIC as well as PMSC’s own observations/inspections to assess progress of EMP implementation during pre-construction and construction phases.

Being Complied with Current PMS Consultant for Phase 2 was mobilized in May 2018. The mobilization of the NES was approved to start by 14 June 2018 and the mobilization of the IES has started on 25 June 2018.Therefore, this condition is being complied since middle June 2018, after the approval by MRB for the mobilization of the specialists. PMS2 began to prepare Monthly and Quarterly Environmental reports, gathering information about compliance with the CEMP and giving support to MRB regarding improvements that should be implemented. PMS2 assesses the PIC’s performance of their duties. In this sense, we already informed in our reports that the PIC is not carrying out monitoring works and is not preparing specific environmental monthly reports

Review and approval of specific environmental management plans prepared by contractors prior to commencement of site works.

Complied with The PIC has taken responsibility for these tasks. CEMPs of contractors were all already approved before the commencement of PMS2 works (see Table 4).

Contractors

Appoint and environment, health and safety officer to oversee timely and proper implementation of mitigation and monitoring measures specified in the EMP. Implement and provide sufficient funding and human resources for proper and timely implementation of required mitigation measures in the EMP for pre-construction and construction phases Prior to start of site works, prepare environmental management action plans in the form of specific management plans (Dust and Noise Control Plan, Spoils Disposal Plan, Traffic Management Plan, etc.) specified in the EMP. Such plans shall be submitted to the PSC for approval.

Partially Complied with4 All contractors have mobilized a responsible for environment, health and safety matters, according to the specification in the EIA. But approved CEMPs include a specific Environmental Manager or Officer or Specialist. So that, only CP02 and CP03 have officially (CP03, in fact) mobilized a specific Environmental Manager as well. During the first semester 2019, contractors developed monitoring activities. PMS2 did not receive official information about them. Reports achieved by PMS2 are the following: - CP01. No report. - CP02. No report. - CP03. Monitoring activities in March

and June 2019 (quarterly monitoring)

4 See Table 5. Status of contractor’s HSE Specialists mobilization

Page 28: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 21 of 158

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

- CP05. Monitoring activities in May 2019 (semi-annual monitoring).

According to the specifications of the EIA, all parameters should be monitored each 3 months except groundwater quality monitoring during tunnel construction (not yet begun) that should be carried out monthly. It means that only CP03 complies with the specification in the EIA. New Regulation in Vietnam states that environmental quality parameters must be monitored bimonthly. PMS2 informed contractors about this fact. The results of analytics obtained are included in this report as Appendix 3.

Undertake land subsidence and settlement monitoring program specified in the EMP during the pre-construction and construction phase (TBM contractor only) and submit monthly reports to PIC and HRB/PMU/EMU

Complied with The contractor continues this first semester 2019 carrying out monitoring twice a week and the reports have been submitted to MRB and PIC as monthly reports

External Expert

Undertake independent annual reviews to verify the monitoring information submitted by HPC/HRB to ADB on the implementation of the environmental management plan (EMP). The external expert shall also assess if various EMP provisions are being implemented as required. Review and verify the accuracy, breadth, depth, and relevance of information provided by HRB to ADB with regard to EMP implementation. Determine if EMP provisions (mitigation, monitoring, reporting, etc.) are being conducted in thorough and timely manner and in accordance with budget identified within the EMP. Submit environmental monitoring report to ADB and HPC.

Partially Complied with - The mobilization of external expert for

the preparation of IEVR (for the period after July 2018) under PMS2 was not mobilized until September 2019. This unexpected event was due to the resignation of the previous expert and the difficulties to find a National expert with the requested experience and for a contract of only one month per year. These difficulties were explained to MRB and ADB since July 2019.

- The commencement of the preparation of IEVR (for the period after July 2018) did not start until September 2019, and submission has been delayed significantly. The main reason for this delay is that the process to approve a new expert has not been agile: difficult to find an experienced specialist who give compliance to the specifications in the TOR and slow decision making after PMS2’s proposal as it was needed two steps for approval, MRB and ADB.

The new external expert of PMS2 started his mobilization on 2 July 2018 and has prepared the Independent Environmental Verification Report (IEVR) for the period March 2017 to

Page 29: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 22 of 158

Organization EMP Responsibility

committed in updated EIA (2013)

Current Implementation status

June 2018, which was already approved by MRB and ADB. Next mobilization of the External Environmental Specialist is expected to in September 2019, in order to prepare the IEVR for the period July 2018 to June 2019. The delay in the mobilization is due to the resignation of the External Specialist and the difficulties to recruit a national specialist for one month per year and with 15 years of experience. In July 2019 PMS2 proposed MRB a new specialist. He has enough experience in ODA projects, but he does not reach 15 years of experience. Therefore, the case was carefully analyzed and also presented to ADB. After receiving communication from ADB with the no objection to this proposal and the subsequent final approval from MRB, the consultant was mobilized in September 2019.

MONRE

Approval of GOV EIA in accordance with Law on Environment Protection 2005

Complied with The GOV EIA was approved by MONRE in 2009 (2nd version).

Environmental monitoring and supervision during construction and operation

Not yet complied with No environmental inspection was conducted by MONRE from the construction commencement to June 2019.

Ha Noi DONRE

Monitoring environmental performance of project throughout construction and operation Participate in resolution of community complaints on environmental impacts of the project during construction and operation

Not yet complied with No environmental inspection was conducted by Ha Noi DONRE from the construction commencement to June 2019.

B. ENVIRONMENTAL AND SAFETY MONITORING STRUCTURE

32. The environmental and safety monitoring structure is described in PID1 = Project Implementation Department No.1 of MRB.

33. MRB had assigned an experienced environmental officer to conduct environmental and safety issues monitoring and review the environmental report submitted by the contractors and PIC since April 2017 to the end of 2017. However, since December 2017 until June 2019, MRB has no specialist for any of both subjects. MRB commissioned PMS2 to be in charge of this matter, acting in its name.

Page 30: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 23 of 158

Continuous Monitoring Activities Temporary Monitoring Activities Ended Monitoring Activities PID1 = Project Implementation Department No.1 of MRB

Figure 4.Environmental and Safety Monitoring Structure

C. ENVIRONMENTAL SUPERVISION PERFORMANCE OF PIC.ASSESSMENT

34. The information in the HSE section of the PCI’s monthly progress reports is too brief or even there is a lack of environmental information. It must be more explained to present the issues in detail, following and assessing the implementation of the EMP, as well as the correction actions to be taken. Furthermore, most of the content of these reports are copied from one month to the following months. In addition, it must include the instructions of PIC to guide the Contractors in case of requirement, if any.

35. By the obligations of the PIC as per stated in its time-base contract, a specific HSE report must be prepared and submitted to the MRB for review and approval, in which the supervised information must be specified and detailed to explain all the supervision activities and its results with specific reference and recommendation of PIC to assess the compliance of the contractors basing the EMP of the project and approved CEMPs

36. Copy of the HSE content of PIC’s monthly progress reports is included in this SEMR No.3 as Appendix 4.

HPC ADB

DONRE MRB

PIC SYSTRA

PMS2

PID1

Contractors CP01, CP02, CP 03 and CP05

Weekly

Daily

Quarterly

Page 31: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 24 of 158

37. A detailed plan to improve the PIC’s performance and its reporting activities is included in this SEMR No.3 as Appendix 5.

38. It’s noted that PIC does not have HSE Manager to manage and supervise the HSE issues during the construction of the project since February 2019. New personnel have been submitted to the MRB by PIC to review and approval for mobilization, but this is pending so far.

D. PROJECT ENVIRONMENTAL REPORTING SYSTEM. ASSESSMENT

39. In accordance with the approved EMP, monthly, semi-annual and annual monitoring reports on EMP compliance as well as quarterly environmental quality monitoring reports must be prepared by relevant stakeholders. PMS2 assessment of the project environmental reporting system is included below, inTable 7. The structure of the reporting process is shown in Figure 5.

Table 7. Assessment of Project environmental reporting system

Agency Required reports in approved EIA

Addressee Assessment

PIC (SYSTRA)

Monthly environmental monitoring reports on environmental performance of contractors.

MRB Not complied with During the first semester 2019, PIC continued preparing monthly reports on Project quality and progress in which only a short section on health, safety and environment was included and it did not include any substantive environmental information. Furthermore, the content of this section is more or less the same each monthly report, so that, it doesn’t provide enough detailed information about the daily HSE management on site (see Appendix 4 in this SEMR No.3). It has to be mentioned that PIC does not prepare any specific monthly report about environmental issues: impacts, assessment of compliances with CEMP, implemented corrective measures, etc., as it may be inferred from the terms of its contract and as it is a common practice in other similar projects while construction phase. PMS2 proposed MRB to increase the transfer of information from Supervision Consultant (PIC) to MRB, with monthly frequency, through a specific environmental monitoring report, detailing the results of all related activities, including the results of specific site inspections. During the second semester 2018 this suggestion was not implemented, although PMS2 and MRB began to

Page 32: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 25 of 158

Agency Required reports in approved EIA

Addressee Assessment

analyze the PIC’s responsibilities in its contract to find the best solution as soon as possible. While preparing this SEMR, PMS2 prepared a specific report for MRB detailing a proposal to improve PIC’s performance, including an outline of the content of the environmental reports that PIC should prepare with monthly frequency.

Quarterly reports on results of environmental quality monitoring

MRB Not complied with CENMA (who carried out environmental effect monitoring) prepared quarterly environmental quality monitoring reports from Sep 2012 to Feb 2015. Since November 2015, contractors have been preparing semi-annual environmental quality monitoring reports. The environmental quality monitoring reports prepared before PMS2 starts works were undertaken in December 2017 by four contractors (CP01, CP02, CP03 and CP05). PIC reviewed these reports and issued No Objection to the reports. It means that the PIC didn’t prepare a report, just indicated “No Objection”. During the first semester of 2018 there was no available information about any monitoring activity on site and it was not received by PMS2 any report with new data of the analysis of environmental parameters. During the second semester 2018 and the first semester 2019, PMS2 collected directly from contractors the reports with the results of the monitoring activities.

PMS2 (TPF GETINSA EUROESTUDIOS)

Assist MRB to prepare Semi-annual Environmental Monitoring Reports (SEMR)

MRB Being complied with Consultancy services of PMSC (Phase 1) ended in September 2015. Since then, SEMRs were temporarily prepared by ADB consultants. In May 2018, a new PMS2 was contracted and the IES was mobilized by end of June, in order to assist MRB to prepare the semi-annual environmental monitoring reports. SEMR No. 1 and 2 are already

Page 33: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 26 of 158

Agency Required reports in approved EIA

Addressee Assessment

approved by MRB, reviewed and approved by ADB and also posted in ADB’s website. This third SEMR of PMS2 is currently being drafted for review and approval and it will be submitted to MRB and ADB by end of September 2019.

MRB Semi-annual Environmental Monitoring Report (SEMR)

ADB Being complied with Since PMS2 started its works, 2 environmental reports were semi-annually prepared and approved. A SEMR No.3 is currently being drafted and will be submitted to ADB for review and approval (see previous paragraph) after being approved by MRB.

Independent Environmental Verification Report (IEVR)

ADB Being complied with After the new PMS2 started works, a NES was mobilized to prepare the IEVR for the period March 2017-June 2018, which has been submitted and approved by ADB. Next mobilization of the External Environmental Specialist it’s scheduled to happen by middle September 2019, in order to prepare the IEVR for the period July 2018 to June 2019, it means annually, as stated in the contract of PMS2. The delay in the mobilization is due to the resignation of the External Specialist and the difficulties to recruit a national specialist for one month per year and with 15 years of experience.

Contractors Not defined MRB Partially complied with Compliance preparing monthly internal environmental and safety monitoring reports, reviewed by PIC and then submitted to MRB. The exception for this compliance is related with the frequency of the environmental effect monitoring reports, different to the specification in the EIA for CP05, as it was commented above in Table 7. Regarding the frequency of the environmental quality monitoring activities, while the EIA 2009 requires daily (archaeological relics), weekly (traffic), monthly (groundwater quality

Page 34: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 27 of 158

Agency Required reports in approved EIA

Addressee Assessment

for tunnel construction) or quarterly monitoring for the rest of parameters and packages, the new Regulation in Vietnam - Circular 24/TT/BTNMT issued on 01 September 2017 by MONRE, specifies that they must be carried out each 2 months. MRB was informed about this change in the National Law, on 29 August 2018, while PMS2 was taking contact with the project, reviewing the existing information, procedures and documents, after the specialists were mobilized to start works. According to this fact, PMS2 proposed MRB to increase the frequency of the analytics to give compliance to the new Regulation. Until now, August 2019, no action was taken by contractors and the frequency remains as in the previous semester.

40. Figure 5 shows as a flow chart the current reporting process or chain for transferring the environmental information from site to final receptors, Donors.

Page 35: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 28 of 158

Figure 5.Current reporting process

Note: under Project Implementation Department No.1 (PID1), groups have been established to manage all packages of the project such as a group in charge of CP01, another in charge of CP02, etc. and these groups have responsibility of storing documents, resolving problems related the contractors or consultants under their management.

VI. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS

41. Table 8 shows the status of compliance with ADB’s loan covenants relating to environment, health and safety during this report period.

Contractor’s reports after revision and review by PIC

Report to Document storage and exchange

MRB ADB

Semiannual EMR Annual External EMR

Monthly reports on Project quality and progress including a section of Health, Safety Environment.

PIC Systra

Contractors CP01, 02, 03 and 05

Internal monthly environmental monitoring reports

Semi-annual environmental quality monitoring reports

PID1

G 1

G 2

G 3

G X

Page 36: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 29 of 158

Table 8. Status of compliance with ADB’s Loan Covenants

Schedule Para No.

Description Remarks/Issues

(Status of Compliance) Schedule

5 7 Grievance Redress Mechanism. HPC shall ensure that within

60 days from the effective date, a complaint and problem management task force, acceptable to ADB, is established and functioning effectively to: (a) review and document eligible complaints of project stakeholder; (b) proactively address grievances; (c) provide the complainants with notice of the chosen mechanism/action; and (d) prepare periodic reports to summarize the number of complaints received and resolved, and final outcomes of the grievances and chosen actions and make these reports available to ADB upon request. Eligible complaints include those related to the project, any of the service providers, any person responsible for carrying out the project, complaints on misuse of funds and other irregularities, and grievances due to any safeguard issues, including resettlement, environment, ethnic minorities, and gender.

Partially complied with The GRM has not been approved yet A draft final GRM has been developed in consultation with ADB and submitted to HPC for clearance and approval on 3 July 2017. After that, the GRM document was submitted to Department of Justice for review and consideration. While preparing this report MRB confirmed that Department of Justice agreed with the GRM and that it was again sent to HPC for final approval. In August 2018 HPC submitted a letter to MRB including some comments regarding this GRM proposed, requesting clarification. In October 2018 it was convened by MRB a meeting with HPC in order to explain and discuss those comments. After that, HPC drafts a Guideline “For entities performing redress grievances of organizations, individuals relating to the implementation of Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi railway station” with some corrections to the previous draft of GRM and resubmits to MRB. MRB submits the draft to ADB for review, by mail, on 3rd June 2019. On July 10, 2019, ADB sent back the document with some comments for its update. Currently, MRB is updating the draft guideline considering the comments received from ADB and other related agencies and will resubmit it to HPC for final approval. Until now, August 2019, the GRM is not yet approved by HPC.

Schedule 5

8 Environment. HPC shall, and shall cause HRB to, ensure that: (a) the project is designed, constructed, and operated in

accordance with the environmental laws and regulations of the Borrower, SPS, EIA, and EMP; if there is any discrepancy between the Borrower's laws and regulations, and SPS, then SPS shall apply;

(b) the institutional arrangements for effective implementation of environmental safeguards including the grievance redress

Partially complied with (a) Complied with, through all established mechanisms for supervision. (b) Not satisfactory complied with until now. Since December 2017, MRB

has no specialist for environment, health and safety issues, although there is one engineer in charge of the coordination with PMS2 for these subjects. The GRM has not been approved yet. (see above item).

(c) Complied with. The GOV EIA was approved by MONRE in 2009.Subsequent environmental approvals such as CEMPs, Tree

Page 37: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 30 of 158

Schedule Para No. Description

Remarks/Issues (Status of Compliance)

mechanism (as described in EIA) are in place before commencement of works construction;

(c) environmental approvals are submitted to ADB; (d) works contracts are supervised and monitored in

accordance with EMP; (e) the mitigation measures as specified in EIA and EMP, are

fully implemented in a timely manner and are incorporated into the bidding documents and works contracts, and compliance of contractors to the provisions of the EMP is ensured;

(f) if any unanticipated environmental impacts become apparent during project implementation, a corrective action plan is prepared and approved by ADB;

(g) the EMP is implemented in full to address the environmental aspects during the construction of the project, including actions to be taken for auditing, measuring and monitoring the environment and safety conditions of the work, and responding to breaches in environmental or safety requirement;

(h) if there are any additional components or changes in the project resulting in adverse environmental impacts and are not within the scope of EIA, new or supplementary environment assessment report, consistent with the SPS, is prepared and approved by the relevant agencies of the Borrower and ADB;

(i) semiannual reports on implementation of the EMP are submitted to ADB on a timely basis;

(j) project components to be funded by the Borrower and other financiers adopt the provisions of EIA and EMP and comply with SPS; and

(k) HPC engages and retain qualified and experienced external experts, acceptable to ADB, to review and verify the environmental monitoring information provided by HPC or HRB to ADB with regard to EMP implementation. The

relocation permits, BSC, PCR reports are being provided through the addition to the corresponding deliverables.

(d) Not satisfactory complied with. PIC has currently no environmental specialist following up the works. Each contractor has their own internal environmental and safety supervision staff or HSE Manager. PMS2 has mobilized a NES, full time, who follows up the construction works at least weekly or bi-weekly. As well, an international Specialist is being mobilized according to the TOR.

(e) Partially Complied with; Some pending issues need to be solved, such as disposals capacity, etc.

(f) Complied with. All significant impacts were already anticipated in the previous documents, as the EIA. The magnitude of them is being similar to what was expected. During the construction stage, no unanticipated impacts arose. It may be commented the concern about the possible affection in the future to the Temple of the Literature and private houses, when the underground excavation begins.

(g) Partially complied with. The CEMPs do not reflect exactly the EMPs. The timing of the monitoring works is not the same for all contractors. As the National Regulation for these activities has recently changed, PMS2 has given this information to MRB and has prepared and submitted a new plan for monitoring implementation that still needs to be implemented.

(h) Complied with. Currently, there are no additional components or changes in the project that could mean any changes in the impact forecast.

(i) Being complied with.08 semi-annual environmental monitoring reports and 3 annual reports were submitted to ADB up to December 2018. This SEMR 09covers the monitoring period of January-June 2019.

(j) Complied with. Arisen impacts or lack of efficiency are continually followed up by PMS2, requesting actions or new measures on site.

(k) Complied with. An external expert has been recruited within the framework of the PMS2 contract, to prepare the annual external EMR, named IEVR. A first IEVR for the period March 2017 to June 2018 was

Page 38: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 31 of 158

Schedule Para No. Description

Remarks/Issues (Status of Compliance)

external experts shall not be involved in day-to-day supervision of the project. Monitoring shall be undertaken annually, and corresponding report shall be submitted to ADB on a timely basis.

already submitted and approved by MRB and ADB.

Schedule 5

10 Applicability of ADB's Safeguard Policy to Entire Project. The Borrower shall ensure that the portions of the project to be financed by EIB, DGT, and AFD abide by all the requirements under SPS.

Being complied with (As it was explained above and along the whole report)

Schedule 5

12 Health risks. In coordination with the local health bureaus, HPC shall, and shall cause HRB to, ensure that (a) the HIV/AIDS prevention plan is implemented in

accordance with its terms; (b) the works contractors disseminate information and conduct

awareness training on the risks and prevention measures of HIV/AIDS and other communicable diseases to their employees, temporary laborers and family members, and subcontractors during project implementation;

(c) measures to prevent other communicable diseases are implemented within the construction sites, as specified in the EMP, and

(d) these requirements are included in the works contracts, monitored and reported semiannually to ADB through HPC.

Being complied with. Improvable a) Partially complied with. There is a HIV/AIDS prevention plan

implemented but according to the information collected by PMS2, during the first quarter 2019 there was no HIV/AIDS prevention training in any package. During the second quarter, CP03 conducted two sessions about this matter.

b) (see paragraph above). c) HSE training activities were carried out during the period (see

chapter XII). PIC and PMS2 reports about any significant incident happened on site.

d) The requirements are included in the works contracts. MRB, through PMS2 reporting system, informs to ADB semiannually and also prepares specific reports when ADB requests. It’s unknown the reporting system of HPC.

Schedule 5

13 Labor Standards. HPC shall, and shall cause HRB to, ensure that the construction contractors (a) provide timely payment of wages and safe working

conditions to all workers; (b) pay equal wages to the women and make employees for

equivalent labor; (c) do not employ child labor as required by the relevant laws

and regulations of the Borrower; (d) the contractors involved in the project implementation

maximize the employment of local people, particularly women and ethnic minorities, who meet the job and

Partially complied with. Safety conditions are in general being assured on site. When a violation of these conditions happens, HSE managers act to solve the situations a) The contractors provide timely payment of wages and safe working

conditions to all workers, although sometimes some workers do not abide the instructions.

b) Complied with during this period (Please kindly refer the Quarterly Reports on Gender Action Plan, Quarters 1stand 2nd 2019).

c) No child is working on site. d) Most of workers and suppliers are local people. There is no

information about the employment of ethnic minorities. Please refer

Page 39: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 32 of 158

Schedule Para No. Description

Remarks/Issues (Status of Compliance)

efficiency requirements for project construction, operation and maintenance; and

(e) such workers are provided with adequate on-the-job training and safety training.

to social and gender reports and specialists for more clarification in this matter.

e) According to the information provided by the PIC through its reports, Contractor for package CP02 conducted HSE training in January 2019 and after, stopped this activity. Contractors for CP03 and CP05 conducted training sessions during the first quarter 2019 but only CP03 during the second quarter.

Page 40: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 33 of 158

VII. TASKS CARRIED OUT BY THE PMS2 DURING THE PERIOD

42. Since the beginning of the mobilization of the PMS2 environmental specialists (NES by 14 June 2018 and IES by 27 June 2018), several different tasks were carried out in the framework of the duties of the contract. In addition to the daily work collecting documentation and analyzing it, first works were focused to achieve a general comprehension of the project and the different involved agents.

43. Since the beginning of PMS2 works, visits to site were carried out, usually with weekly or bi-weekly frequency. As well, the IES inspected sites in January 2019, while preparing the SEMR No.2.The second site visit, useful for the SEMR No.3. was not conducted by the IES until August 2019, which is out of the coverage period but it’s the way to verify the situation on site after the whole assessed period. As well, it has to be mentioned that the SEMR covers the period from 1st January to 30th June, so the report cannot be prepared until PIC submits PMS2 their monthly report for June and this report is submitted, obviously, in July.

44. The tasks carried out and works developed by the PMS2 environmental specialists during the period of this report (1stsemester 2019) are shown below in Table 9.

45. Regarding the submitted letters, Table 10 shows the subjects of each of them.

10

Page 41: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 01 Page 34 of 158

Table 9. Environmental activities carried out by PMS2 during the period

Site inspections Letter submission1 Report submission2 Meeting3 Reports/Documents

received

Jan Feb Mar Jan Feb Mar Jan Feb Mar Jan Feb Mar Jan Feb Mar

08, 15, 22

19, 27 5, 12,

21 11, 21 25, 27 21, 22 11, 21 27 21 16, 30 20 20 17 20, 27 15, 26

Site inspections Letter submission1 Report submission2 Meeting3 Reports/Documents

received

April May June April May June April May June April May June April May June

1, 11, 17, 22, 25, 26

9, 10, 17, 22

04, 05, 11, 18

12, 17 20 18 17 20 18 23 10 05, 20 16 10, 21 17

(1), (2) refer to Table 10 for detailed information (3) attend the meeting with MRB’s staffs on 16, 30 January, 20 February and 20 March 2019;

attend the meetings between MRB, ADB, PIC, PMS2 and Contractor CP03 at VRM office on 23 April; MRB’s staffs on 10 May; MRB, PIC, CP03 and Hanoi Environmental Police at HGU office on 05 June; MRB, CP01 and Tay Tuu CPC at Tay Tuu CPC on 20 June 2019.

(4) the internal meetings were held in the PMS2’s office; attend the meeting at VRM with ADB, MRB, PIC and Contractors on 02 October 2018; attend the meeting with MRB for proposal on modification of environmental monitoring frequency which is covered by PMS2;

Page 42: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 35 of 158

Table 10.Letters issued during the First Quarter 2019

No. Reference No. Date Receiver Subject Brief Explanation

1 PMS2-MRB-WP-24 11-Jan-2019 MRB Disposal Plan. CP03

An assessment on receive capacity of current disposal areas of CP03 and a proposal on finding new disposal area with the measures to control the disposal activity has been submitted to the MRB

2 PMS2-MRB-128 21-Jan-2019 MRB Submission of Quarterly Environmental Monitoring Report – 4th Quarter 2018

The 2nd QEMR has been prepared and submitted to the MRB

3 PMS2-MRB-WP-26 25-Feb-2019 MRB

Comment on Environmental Monitoring Report, Communication Session in HIV and AIDS Prevention Report, Environmental Management Plan and Environmental Compliance Inspection Reports of CP03

Support the MRB to review the reports of contractor CP03 and comment on these reports

4 PMS2-MRB-142 27-Feb-2019 MRB Submission of Monthly Report on Environmental Monitoring for January 2019

The MEMR January 2019 has been prepared and submitted to the MRB

5 PMS2_MRB_EMR_19.06_rev 01

27-Feb-2019 MRB Monthly Environmental Monitoring report, period January 2019

The MEMR January 2019 has been prepared and submitted to the MRB

6 PMS2-MRB-153 21-Mar-2019 MRB Submission of Monthly Report on Environmental Monitoring for February 2019

The MEMR February 2019 has been prepared and submitted to the MRB

7 PMS2-MRB-WP-27 22-Mar-2019 MRB Comment on Environmental Compliance Inspection Report of January 2019 of CP03

Support MRB to review and comment on ECR January 2019 of Contractor CP03

Page 43: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 36 of 158

Table 11.Letters issued during the Second Quarter 2019

No. Reference No. Date Receiver Subject Brief Explanation

1 PMS2-MRB-171 17-Apr-2019 MRB Submission of Quarterly Environmental Monitoring Report - 1st Quarter 2019

QEMR – 1st Quarter 2019 has been prepared and submitted to the MRB for review and approval

2 PMS2-MRB-QEMR-

20.03-rev01 17-Apr-2019 MRB

Quarterly Environmental Monitoring Report – 1st Quarter 2019

QEMR – 1st Quarter 2019 has been prepared and submitted to the MRB for review and approval

3 PMS2-MRB-WP-31 12-Apr-2019 MRB Station 8. Construction site arrangement and control

Description of the actual poor condition of construction site of station 8 and suggestion of countermeasures to improve the situation

4 PMS2-MRB-187 20-May-2019 MRB Submission of Monthly Report on Environmental Monitoring for April 2019

MEMR April 2019 has been prepared and submitted to the MRB

5 PMS2-MRB-EMR-19.08-rev01

20-May-2019 MRB Monthly Environmental Monitoring Report – April 2019

MEMR April 2019 has been prepared and submitted to the MRB

6 PMS2-MRB-202 19-Jun-2019 MRB Submission of Monthly Report on Environmental Monitoring for May 2019

MEMR May 2019 has been prepared and submitted to the MRB

7 PMS2-MRB-EMR-

19.09-rev01 19-Jun-2019 MRB

Monthly Environmental Monitoring Report – May 2019

MEMR May 2019 has been prepared and submitted to the MRB

Page 44: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 37 of 158

VIII. COMPLIANCE WITH EMP. ENVIRONMENTAL MAIN FINDINGS

A. COMPLIANCE WITH EMP

46. In August 2019, the Environmental Specialists of PMS2 analyzed the environmental situation on site during the first semester 2019 as a last check for this report. As well, PMS2 reviewed the documents and reports submitted by the PIC, that are the main source of information for MRB and, therefore, for PMS2. Table 12presents the results of this work and the compliances/non-compliances of Contractors with the approved EMP included in the EIA.

47. As PMS2 is a management support consultant for the client, MRB, we depend on the information provided by the PIC to MRB. As it’s explained along this SEMR No.3 and in previous reports, PIC do not provide any information regarding the compliance or no compliance with the EMP or even the CEMPs.

48. Therefore, and until the new reporting system is implemented by PIC following PMS2 proposal and MRB instructions, the assessment of the compliance with the EMP has to be considered just with information directly collected by PMS2 from contractors and after periodical site visits.

Page 45: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 38 of 158

Table 12. Compliance with EMP

Environmental Aspects/Concern

Proposed Mitigation Measures Compliance

Construction. Depot

1. Air quality impacts due to gaseous and dust emissions

a) Strictly implement approved Dust Control Plan b) Consider paving Road 70 c) Wherever possible, use electrically-powered equipment rather than gas or diesel-

powered equipment d) Position any stationary emission sources (e.g., portable diesel generators,

compressors, etc.) as far as is practical from sensitive receptors; e) Use only vehicles and equipment that are registered and have necessary permits. f) Burning of wastes generated at the construction sites, work camps and other project-

related activities shall be strictly prohibited. g) Construction equipment and vehicles shall be well-maintained and shall meet national

QCVN emission standards. h) Specify the use of clean fuels such as ultra-low Sulphur diesel in dump trucks and other

heavy-duty diesel vehicles and/or equipment, in conjunction with the use of particulate trap control devices, as well as catalytic converters, to avoid excessive diesel emissions.

i) Keep stockpiles moist and cover vehicles with tarpaulin sheets or other suitable materials to minimize dust emission and prevent spillage of materials (e.g., soil, cement, stone, sand, aggregates, etc.).

j) Provide temporary covers (e.g., tarpaulins, grass, etc.) on long term materials stockpiles. k) Concrete mixing areas at the Depot site shall be located at least 100 m from the nearest

residential area. l) Clean road surfaces of debris/spills from construction equipment and vehicles. m) Install temporary fencing or barriers around particularly dusty activities in vicinity of

sensitive receivers n) Ensure availability of water trucks on site and if the works surface and access roads

near sensitive receptors (i.e., residential areas, roadside tea and food stalls, schools, hospitals and other sensitive receptors) are dry and dusty, spray water on the exposed surfaces to reduce dust emission.

o) All construction equipment and machinery shall be fitted with emission control equipment in full compliance with the national (QCVN) and local regulations.

Partially complied with n) There is not any available water truck on site, a dusty status was noted, for example, during ADB mission on 26 April 2019. The contractor has installed a water supply system with taps along potential dusty areas such as access roads to ensure watering activity during hot dry days in order to minimize the spread of dust. Watering frequency is, at least, 4 times in hot dry days.

Page 46: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 39 of 158

Environmental Aspects/Concern

Proposed Mitigation Measures Compliance

p) Fuel-efficient and well-maintained haulage trucks will be used to minimize exhaust emissions. Smoke belching vehicles and equipment shall not be allowed and shall be removed from the project.

q) Impose speed limits on construction vehicles to minimize road dust in areas where sensitive receptors are located.

r) Locations for stockpiling material at the depot area will be at least 100 m from the nearest residential sensitive receivers.

s) Undertake immediate repairs of any malfunctioning construction vehicles and equipment.

t) Discourage idling of engines u) Provide prior notification to the community on schedule of construction activities v) Implement 24-hour community complaints hotline

2. Noise impacts due to operation of construction equipment/ vehicles and various construction activities

a) Strictly implement of Noise Control Plan b) All construction equipment and vehicles shall be well maintained, regularly inspected for

noise emissions, and shall be fitted with appropriate noise suppression equipment consistent with applicable national and local regulations.

c) Use only vehicles and equipment that are registered and have necessary permits. d) No noisy construction-related activities (e.g., transport of materials along residential

areas and other sensitive receptors, piling, etc.) will be carried out during the night. Such activities shall be restricted to daylight hours.

e) Truck drivers and equipment operators shall minimize the use of horns. f) Impose speed limits on construction vehicles to minimize noise emission along areas

where sensitive receptors are located (houses, schools, hospitals, etc.). g) Provide temporary noise barriers (3-5-meter-high barrier can reduce 5-10 dB(A), as

necessary, if depot works will generate high noise levels that could disturb nearby households and other sensitive receptors.

h) As much as possible, use quiet equipment and working method. i) Whenever possible, completely enclose noisy equipment which can reduce noise level

by 15-25 dB(A), restrict use of noisy equipment (e.g.15 min for every consecutive 30 min period) and undertake sequential operation of equipment with objective to reduce noise generated;

j) No noisy construction activities near schools during examination period. k) Avoid noisy construction activities in vicinity of sensitive receivers during night time or

other sensitive periods (e.g. during school hours in vicinity of schools)

Reasonably complied with

Page 47: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 40 of 158

Environmental Aspects/Concern

Proposed Mitigation Measures Compliance

l) Provide prior notification to the community on schedule of construction activities

3. Wastewater from concrete batch plants (CBP)

a) Prior to operation of CBP, construct settling/retention ponds with sufficient specifications/capacity for treatment of wastewater (e.g., from washing of equipment such as mixer drums, trucks and chute, contact storm water, etc.)

b) Properly operate and maintain settling/retention ponds to ensure effluent quality meets applicable QCVN 24:2009/BTNMT (National Technical Regulation for Industrial Wastewater)

There is no CBP installed on site. The contractor is buying commercial concrete from suppliers who have certificate for construction works

4. Potential contamination of groundwater due to spills of fuel and other hazardous substances.

a) Strict implementation of Spill Management Plan b) Store fuel and hazardous substances in paved areas with embankment. If spills or leaks

do occur, undertake immediate clean up. c) Ensure availability of spill clean-up materials (e.g., absorbent pads, etc.) specifically

designed for petroleum products and other hazardous substances where such materials are being stored.

d) Train relevant construction personnel in handling of fuels and spill control procedures. e) Ensure all storage containers are in good condition with proper labeling. f) Regularly check containers for leakage and undertake necessary repair or replacement. g) Store hazardous materials above flood level. h) Equipment maintenance areas shall be provided with drainage leading to an oil-water

separator that will be regularly skimmed of oil and maintained to ensure efficiency. Discharge of oil contaminated water shall be prohibited.

i) Store waste oil, used lubricant and other hazardous wastes in tightly sealed containers to avoid contamination of soil and water resources. Transport and off-site disposal of such wastes shall be consistent with national and local regulations.

j) Should HRB decide to install a back-up well for reliable water supply, this shall be designed and constructed such that surface pollution is prevented from percolating downward along the annular space between the borehole and the well casing.

Reasonably complied with

5. Drainage obstruction/flooding

a) Avoid placement of construction materials, waste storage areas or equipment in or near drainage channels surrounding the Depot.

b) Prohibit disposal of waste materials to drainage channels. c) In case existing drainage ditch is filled-up as required for the construction works,

provide alternative drainage for rainwater. d) Regularly inspect and maintain all drainage channels to keep these free of obstructions.

Complied with

6. Generation of solid wastes

a) Provide garbage bins and facilities within the project site for temporary storage of construction waste and domestic solid waste.

Not complied with Waste management must be improved.

Page 48: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 41 of 158

Environmental Aspects/Concern

Proposed Mitigation Measures Compliance

b) Separate solid waste into hazardous, non-hazardous and reusable waste streams and store temporarily on site in secure facilities with weatherproof flooring and roofing, security fencing and access control and drainage/ wastewater collection systems

c) Ensure that wastes are not haphazardly dumped within the project site and adjacent areas

d) Undertake regular collection and disposal of wastes to sites approved by local authorities.

It was observed that waste was disposed on site directly on the ground. No separation of selected waste materials. Not enough containers for waste management.

7. Damage to community facilities

a) Immediately repair any damage caused by the Project to community facilities such as water supply, power supply, communication facilities and the like.

b) Access roads damaged during transport of construction materials and other project-related activities shall be reinstated upon completion of construction works.

Complied with

8. Traffic build-up along access road to the depot

a) Strictly implement approved Traffic Management Plan b) Post traffic advisory signs (to minimize traffic build-up) in coordination with local

authorities c) As much as possible, schedule delivery of construction materials and equipment during

non-peak hours. d) Regularly monitor traffic conditions along access roads to ensure that project vehicles

are not causing congestion.

Complied with

9. Hazards to health and safety of workers and the public due to construction works

a) Strictly implement approved Occupational and Community Health and Safety Plan, and approved Emergency Response Plan

b) Appoint an environment, health and safety manager to look after implementation of required environmental mitigation measures, and to ensure that health and safety precautions are strictly implemented for the protection of workers and the general public in the vicinity of construction areas

c) Conduct orientation for construction workers regarding health and safety measures, emergency response in case of accidents, fire, etc., and prevention of HIV/AIDS and other related diseases

d) Provide first aid facilities that are readily accessible by workers. e) Provide firefighting equipment at the work areas, as appropriate, and at construction

camps. f) Provide adequate drainage in workers camps to prevent water logging/accumulation of

stagnant water and formation of breeding sites for mosquitoes. g) Provide adequate housing for all workers at the construction camps. h) Provide reliable supply of potable water

Partially complied with c) HSE training was stopped in the second quarter and should be conducted continually j) The sanitation facilities/toilets with sufficient water supply have been provided but they are not separated for male and female workers e) Fire extinguisher was found under the sun. This equipment must be stored covered

Page 49: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 42 of 158

Environmental Aspects/Concern

Proposed Mitigation Measures Compliance

i) Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers

j) Establish clean canteen/rest area. k) Ensure proper collection and disposal of solid wastes within the construction camps

consistent with local regulations. l) Provide fencing on all areas of excavation greater than 2 m deep. m) Provide appropriate personnel safety equipment such as safety boots, helmets, gloves,

protective clothes, breathing mask, goggles, and ear protection n) Ensure reversing signals are installed on all construction vehicles. o) Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast

sections, etc.) do not fall onto or hit construction workers. p) Implement fall prevention and protection measures whenever a worker is exposed to

the hazard of falling more than two meters, falling into operating machinery or through an opening in a work surface. Based on a case-specific basis, fall prevention/protection measures may include installation of guardrails with mid-rails and toe boards at the edge of any fall hazard area, proper use of ladders and scaffolds by trained employees, use of fall prevention devices, including safety belt and lanyard travel limiting devices to prevent access to fall hazard, fall protection devices such as full body harnesses, etc.

10. Social conflicts due to presence of workers

a) Consider the location of construction camps away from communities in order to avoid social conflict in using resources and basic amenities such as water supply.

b) Maximize number of local people employed in construction works. c) Maximize goods and services sourced from local commercial enterprises.

Complied with No worker camps are installed on site

11. Additional environmental mitigation measures

The Contractor shall implement corrective and/or additional measures to avoid, mitigate or compensate for adverse environmental impacts due to construction

Complied with The contractor has installed water supply along the dusty areas with taps to ensure the watering activity during hot dry days in order to minimize the spread of dust

Page 50: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 43 of 158

Construction. Viaduct and Stations

1. Air quality impacts due to gaseous and dust emissions

a) Strictly implement approved Dust Control Plan b) Wherever possible, use electrically-powered equipment rather than gas or diesel-powered

equipment c) Position any stationary emission sources (e.g., portable diesel generators, compressors,

etc.) as far as is practical from sensitive receptors;

d) Use only vehicles and equipment that are registered and have necessary permits. e) Burning of wastes generated at the construction sites, work camps and other project-

related activities shall be strictly prohibited. f) Construction equipment and vehicles shall be well-maintained and shall meet national

QCVN emission standards. g) Specify the use of clean fuels such as ultra-low Sulphur diesel in dump trucks and other

heavy-duty diesel vehicles and/or equipment, in conjunction with the use of particulate trap control devices, as well as catalytic converters, to avoid excessive diesel emissions.

h) Keep stockpiles moist and cover vehicles with tarpaulin sheets or other suitable materials to minimize dust emission and prevent spillage of materials (e.g., soil, cement, stone, sand, aggregates, etc.).

i) Provide temporary covers (e.g., tarpaulins, grass, etc.) on long term materials stockpiles. j) As much as possible, the casting yard for the Project will make use of already established

and licensed site(s) for concrete forming activities where all the pre-cast sections of the viaduct, pier columns and cross members will be fabricated.

k) Ensure that necessary environmental approvals are obtained for the establishment and operation of a new casting yard,

l) Store excavated materials outside road reserve, but where there is no area, spoils shall be loaded and transported immediately.

m) Clean road surfaces of debris/spills from construction equipment and vehicles. n) Undertake daily cleaning of paved routes around the pier construction sites. o) Install temporary fencing or barriers around particularly dusty activities in vicinity of

sensitive receivers p) Ensure availability of water trucks on site and if the works surface and access roads near

sensitive receptors (i.e., residential areas, roadside tea and food stalls, schools, hospitals and other sensitive receptors) are dry and dusty, spray water on the exposed surfaces to reduce dust emission.

Complied with

Page 51: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 44 of 158

q) All construction equipment and machinery shall be fitted with emission control equipment in full compliance with the national (QCVN) and local regulations.

r) Fuel-efficient and well-maintained haulage trucks will be used to minimize exhaust emissions. Smoke belching vehicles and equipment shall not be allowed and shall be removed from the project.

s) Impose speed limits on construction vehicles to minimize road dust in areas where sensitive receptors are located.

t) Undertake immediate repairs of any malfunctioning construction vehicles and equipment. u) Discourage idling of engines v) Provide prior notification to the community on schedule of construction activities w) Implement 24-hour community complaints hotline

2. Noise and vibration impacts due to operation of construction equipment/vehicles and various construction activities

a) Strictly implement approved Noise Control Plan b) Erection of temporary walls around the elevated station sites and other construction sites,

as necessary. Especially near sensitive areas such as schools, hospitals, houses, etc. Temporary noise barriers (3-5-meter-high) can reduce noise level by 5-10 dB(A).

c) Use of churned drill pile method will has significantly lower noise and vibration emission levels that diesel hammer piles

d) Truck drivers and equipment operators shall minimize the use of horns. e) Position any stationary equipment that produce high noise levels (e.g., portable diesel

generators, compressors, etc.) as far as is practical from sensitive receptors; f) All construction equipment and vehicles shall be well maintained, regularly inspected for

noise emissions, and shall be fitted with appropriate noise suppression equipment consistent with applicable national and local regulations.

g) Use only vehicles and equipment that are registered and have necessary permits. h) No noisy construction-related activities will be carried out during the night. Such activities

shall be restricted to daylight hours. i) Impose speed limits on construction vehicles to minimize noise emission along areas where

sensitive receptors are located (houses, schools, hospitals, etc.)

j) As much as possible, use quiet equipment and working method. k) Whenever possible, completely enclose noisy equipment which can reduce noise level by

15-25 dB(A), restrict use of noisy equipment (e.g.15 min for every consecutive 30 min period) and undertake sequential operation of equipment with objective to reduce noise generated;

l) No noisy construction activities near schools during examination period.

Complied with Main noise is due to traffic

Page 52: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 45 of 158

m) Avoid noisy construction activities in vicinity of sensitive receivers during night time or other sensitive periods (e.g. during school hours in vicinity of schools).

n) Sheet piling at Thu Le Lake shall only to be carried out during daylight hours. o) Provide prior notification to the community on schedule of construction activities p) Implement 24-hour community complaints hotline

3. Spoils generation from pier excavation works

a) Strictly implement approved Spoils Disposal Plan b) Spoil disposal will only be to DONRE and DOC approved areas c) Trucks transporting spoils shall be tightly covered with tarpaulin or other suitable materials

to minimize dust emission and spills. d) Wheel washing shall be undertaken to remove mud so as to ensure that access roads are

kept clean. e) Road surfaces shall be regularly cleaned of spilled spoils f) Spoil disposal shall not cause sedimentation and obstruction of flow of watercourses,

damage to agricultural land and densely vegetated areas. g) The spoils disposal site shall be located at least 50 m from surface water courses and shall

be protected from erosion by avoiding formation of steep slopes and grassing.

Complied with

4. Wastewater from concrete batch plants (CBP)

a) Prior to operation of CBP, construct settling/retention ponds with sufficient specifications/capacity for treatment of wastewater (e.g., from washing of equipment such as mixer drums, trucks and chute, contact storm water, etc.)

b) Properly operate and maintain settling/retention ponds to ensure effluent quality meets applicable QCVN 24:2009/BTNMT (National Technical Regulation for Industrial Wastewater)

Not Applicable There is no CBP installed on site. The contractor is buying commercial concrete from suppliers who have certificate for construction works

5. Pollution due to spills of fuel and other hazardous substances.

a) Strictly implement approved Spills Management Plan b) Store fuel and hazardous substances in paved areas with embankment. If spills or leaks do

occur, undertake immediate clean up. c) Ensure availability of spill clean-up materials (e.g., absorbent pads, etc.) specifically

designed for petroleum products and other hazardous substances where such materials are being stored.

d) Train relevant construction personnel in handling of fuels and spill control procedures. e) Ensure all storage containers are in good condition with proper labeling. f) Regularly check containers for leakage and undertake necessary repair or replacement. g) Store hazardous materials above flood level. h) Equipment maintenance areas shall be provided with drainage leading to an oil-water

separator that will be regularly skimmed of oil and maintained to ensure efficiency. Discharge of oil contaminated water shall be prohibited.

Complied with

Page 53: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 46 of 158

i) Store waste oil, used lubricant and other hazardous wastes in tightly sealed containers to avoid contamination of soil and water resources. Transport and off-site disposal of such wastes shall be consistent with national and local regulations.

6. Sedimentation of Thu Le Lake and generation of sediment-laden wastewater from piers excavations

a) Installation of a sheet piled wall along Thu Le lake prior to filling. b) Sedimentation from filling materials behind the sheet piled wall shall be prevented from

entering into Thu Le Lake by silt curtains anchored to the ends of the piled structure. c) Immediately restore damaged riprap along Thu Le Lake to minimize erosion d) Undertake regular inspection and maintenance of erosion and sediment controls e) Prior to discharge, alkaline water from the casting yard shall be settled and neutralized, f) Ensure that excavation spoils are not stockpiled or dumped near or into water courses g) To prevent clogging of canals, sediment-laden water from excavation for pier placement

shall be settled prior to discharge to the nearest storm drain.

Complied with

7. Drainage obstruction/flooding

a) Placement of construction materials, excavated spoils, equipment shall not block flow of rainwater into canals/drainage structures.

b) Prohibit disposal of waste materials to drainage channels. c) Regularly inspect and maintain all drainage channels to keep these free of obstructions.

Complied with

8. Generation of solid wastes

a) Provide garbage bins and facilities within the project site for temporary storage of construction waste and domestic solid waste.

b) Separate solid waste into hazardous, non-hazardous and reusable waste streams and store temporarily on site in secure facilities with weatherproof flooring and roofing, security fencing and access control and drainage/ wastewater collection systems.

c) Ensure that wastes are not haphazardly dumped within the project site and adjacent areas d) Undertake regular collection and disposal of wastes to sites approved by local authorities.

Not complied with The mitigation measures proposed in the EMP have not been implemented at station 8 (under CP02) (observed on 19 Feb 2019) and in Pier 365 (under CP01) (observed on 09 May 2019) The issue at Pier 365 has been corrected. At station 8, the solid waste has been collected and removed by authorized company (URENCO), but it still needs more housekeeping activity. At 3 locations: Stations 6, 8 and initial ramp from Depot, it was observed a lot of useless construction materials and debris spread on the ground. Waste management must be improved removing all of them from site and

Page 54: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 47 of 158

transport to approved disposal sites.

9. Damage to community facilities

a) Immediately repair any damage caused by the Project to community facilities such as water supply, power supply, communication facilities and the like.

b) Access roads damaged during transport of construction materials and other project-related activities shall be reinstated upon completion of construction works.

Complied with

10. Traffic congestion and access problems

a) Strictly implement approved Traffic Management Plan b) Provide signs advising road users that construction is in progress and that the road narrows

to one lane using cones. c) Employ flag persons to control traffic at the station sites for safety reasons when

construction equipment is entering or leaving the work area. d) Lanes through the work site, created by rope or flagging, shall be developed to minimize

risks and injuries from falling objects. e) As much as possible, lifting and placing of the pre-cast pier and viaduct sections will be

done at night to minimize traffic congestion. f) Post traffic advisory signs (to minimize traffic build-up) in coordination with local authorities g) Provide road signs indicating the lane is closed 500 m before the worksite. h) Use traffic cones to direct traffic to move to the open lane. i) Provide sufficient lighting at night within and in the vicinity of construction sites. j) Regularly monitor traffic conditions along access roads to ensure that project vehicles are

not causing congestion. k) Define and observe schedules for different types of construction traffic trips (e.g., transport

of pre-cast sections, haulage of spoils, delivery of construction materials, etc.). l) As much as possible, schedule delivery of construction materials and equipment as well as

transport of spoils during non-peak hours. m) Avoid movements of noisy vehicles during night time in vicinity of sensitive receivers. n) Implement suitable safety measures to minimize risk of adverse interactions between

construction works and traffic flows through provision of temporary signals or flag controls, adequate lighting, fencing, signage and road diversions.

o) Ensure relocation of any affected public transport infrastructure (but stops, shelters etc.) prior to commencement of works

p) Provide advance notification to the community regarding changes to public transport facilities or routes.

Complied with

Page 55: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 48 of 158

q) Schedule construction works to minimize extent of activity along linear construction site at any one time

r) Comply with traffic regulations and avoid, where possible, roads with the highest traffic volumes, high density of sensitive receivers or capacity constraints are not used as access to and from the construction areas and spoils disposal sites.

s) Install temporary accesses to properties affected by disruption to their permanent accesses. t) Reinstate good quality permanent accesses following completion of construction.

11. Hazards to health and safety of workers and the public due to construction works

a) Strictly implement approved Occupational and Community Health and Safety Plan, and approved Emergency Response Plan

b) Appoint an environment, health and safety manager to look after implementation of required environmental mitigation measures, and to ensure that health and safety precautions are strictly implemented for the protection of workers and the general public in the vicinity of construction areas

c) Conduct orientation for construction workers regarding health and safety measures, emergency response in case of accidents, fire, etc., and prevention of HIV/AIDS and other related diseases

d) Provide first aid facilities that are readily accessible by workers. e) Provide firefighting equipment at the work areas, as appropriate, and at construction

camps. f) Provide adequate drainage in workers camps to prevent water logging/accumulation of

stagnant water and formation of breeding sites for mosquitoes. g) Provide adequate housing for all workers at the construction camps. h) Provide reliable supply of potable water. i) Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water

supply for male and female workers j) Establish clean canteen/rest area. k) Ensure proper collection and disposal of solid wastes within the construction camps

consistent with local regulations. l) Provide fencing on all areas of excavation greater than 2 m deep. m) Provide appropriate personnel safety equipment such as safety boots, helmets, gloves,

protective clothes, breathing mask, goggles, and ear protection n) Ensure reversing signals are installed on all construction vehicles. o) Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast

sections, etc.) do not fall onto or hit construction workers. p) Implement fall prevention and protection measures whenever a worker is exposed to the

hazard of falling more than two meters, falling into operating machinery or through an

Partially complied with j) Except station 6, all the toilets for workers have been removed from construction site of elevated station (under CP02). Until the end of June 2019, there is no improvement. m) At Station 2 a worker was observed cutting metal bars without wearing gloves. Contractor shall ensure that all workers are provided and use their PPE.

Page 56: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 49 of 158

opening in a work surface. Based on a case-specific basis, fall prevention/protection measures may include installation of guardrails with mid-rails and toe boards at the edge of any fall hazard area, proper use of ladders and scaffolds by trained employees, use of fall prevention devices, including safety belt and lanyard travel limiting devices to prevent access to fall hazard, fall protection devices such as full body harnesses, etc.

q) Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast sections, etc.) do not fall onto or hit people, vehicle, and properties in adjoining areas.

r) Fencing of construction sites and excavation sites and guarding such areas to restrict public access.

s) Prior to excavation work, provide fencing on all sides of areas to be excavated. t) Provide warning signs at the periphery of the construction site. u) Strictly impose speed limits on construction vehicles along residential areas and where

other sensitive receptors such as schools, hospitals, and other populated areas are located. v) Educate drivers on safe driving practices to minimize accidents and to prevent spill of

hazardous substances and other construction materials during transport.

12. Social conflicts due to presence of workers

a) Consider the location of construction camps away from communities in order to avoid social conflict in using resources and basic amenities such as water supply.

b) Maximize number of local people employed in construction works. c) Maximize goods and services sourced from local commercial enterprises.

Complied with

13. Additional environmental mitigation measures

The Contractor shall implement corrective and/or additional measures to avoid, mitigate or compensate for adverse environmental impacts due to construction works and other project-related activities performed by the Contractor and its subcontractors.

N/A No need additional measures during the first semester 2019

Construction. Tunnel

1. Air quality impacts due to gaseous and dust emissions

a) Strictly implement approved Dust Control Plan b) Wherever possible, use grid rather than generator set electrical power for construction

equipment such as the tunnel boring machine and equipment to be used during cut-and-cover tunnel excavations.

c) Position any stationary emission sources (e.g., portable diesel generators, compressors, etc.) as far as is practical from sensitive receptors;

d) Use only vehicles and equipment that are registered and have necessary permits. e) Burning of wastes generated at the construction sites, work camps and other project-

related activities shall be strictly prohibited. f) Construction equipment and vehicles shall be well-maintained and shall meet national

QCVN emission standards.

Partially complied with At station 10 excavated soil which is temporary disposed on site for back filling is not covered, so that it may generate dust emissions.

Page 57: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 50 of 158

g) Specify the use of clean fuels such as ultra-low Sulphur diesel in dump trucks and other heavy-duty diesel vehicles and/or equipment, in conjunction with the use of particulate trap control devices, as well as catalytic converters, to avoid excessive diesel emissions.

h) Keep stockpiles moist and cover vehicles with tarpaulin sheets or other suitable materials to minimize dust emission and prevent spillage of materials (e.g., soil, cement, stone, sand, aggregates, etc.).

i) Provide temporary covers (e.g., tarpaulins, grass, etc.) on long term materials stockpiles. j) Store excavated materials outside road reserve, but where there is no area, spoils shall be

loaded and transported immediately. k) Provide truck-washing facilities to prevent truck-out of mud and dust onto city streets. l) As much as possible, the casting yard for the Project will make use of already established

and licensed site(s) for concrete forming activities where all the pre-cast sections will be fabricated.

m) Ensure that necessary environmental approvals are obtained for the establishment and operation of a new casting yard,

n) Daily cleaning of road surfaces of debris/spills from construction equipment, haulage trucks and vehicles,

o) Install temporary fencing or barriers around particularly dusty activities in vicinity of sensitive receivers

p) Ensure availability of water trucks or other dust suppressants and appropriate equipment for applying the suppressant (e.g., a tank tuck with spray bars) on site and if the works surface and access roads near sensitive receptors (i.e., residential areas, roadside tea and food stalls, schools, hospitals and other sensitive receptors) are dry and dusty, spray water on the exposed surfaces to reduce dust emission.

q) All construction equipment and machinery shall be fitted with emission control equipment in full compliance with the national (QCVN) and local regulations.

r) Fuel-efficient and well-maintained haulage trucks will be used to minimize exhaust emissions. Smoke belching vehicles and equipment shall not be allowed and shall be removed from the project.

s) Impose speed limits on construction vehicles to minimize road dust in areas where sensitive receptors are located.

t) Undertake immediate repairs of any malfunctioning construction vehicles and equipment. u) Daily visual inspections to identify and address potential areas of dust and odor emissions. v) Discourage idling of engines w) Provide prior notification to the community on schedule of construction activities x) Implement 24-hour community complaints hotline

Page 58: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 51 of 158

2. Noise and vibration impacts due to operation of construction equipment/ vehicles and various construction activities

a) Strictly implement approved Noise Control Plan b) Erection of temporary walls around the underground station excavation sites and tunnel

portal. Temporary noise barriers (3-5meter high) can reduce noise level by 5-10 dB(A). c) Diesel hammer piling shall be limited in favor of drill piling. d) Truck drivers and equipment operators shall minimize the use of horns. e) Position any stationary equipment that produce high noise levels (e.g., portable diesel

generators, compressors, etc.) as far as is practical from sensitive receptors; f) All construction equipment and vehicles shall be well maintained, regularly inspected for

noise emissions, and shall be fitted with appropriate noise suppression equipment consistent with applicable national and local regulations.

g) Use only vehicles and equipment that are registered and have necessary permits. h) No noisy construction-related activities will be carried out during the night. Such activities

shall be restricted to daylight hours. i) Impose speed limits on construction vehicles to minimize noise emission along areas where

sensitive receptors are located (houses, schools, hospitals, etc.). j) As much as possible, use quiet equipment and working method. k) Whenever possible, completely enclose noisy equipment which can reduce noise level by

15-25 dB(A), restrict use of noisy equipment (e.g.15 min for every consecutive 30 min period) and undertake sequential operation of equipment with objective to reduce noise generated;

l) No noisy construction activities near schools during examination period. m) Avoid noisy construction activities in vicinity of sensitive receivers during night time or other

sensitive periods (e.g. during school hours in vicinity of schools). n) Provide prior notification to the community on schedule of construction activities o) Implement 24-hour community complaints hotline

Complied with

3. Spoils generation from tunneling and excavation works at underground station sites

a) Strictly implement approved Spoils Disposal Plan b) Spoil disposal will only be to DONRE and DOC approved areas c) The capacity of disposal sites shall be adequate to accept the quantity of spoils without

alienating areas outside the site boundaries. d) Undertake random sampling of spoils from underground station excavations and tunneling

to determine presence of contaminants. e) Disposal of contaminated spoils shall only be to disposal sites equipped and licensed to

handle such wastes. f) Determine water content of spoils to ascertain if spoils dewatering is necessary. g) Undertake necessary spoils dewatering and provide adequate treatment facilities to ensure

that resulting wastewater meets QCVN standards.

Partially complied with Some soils are deposited on site and they will be used for back filling on the underground stations Sites are provided with wheel cleaner system to avoid soils on the streets

Page 59: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 52 of 158

h) Stockpiling of spoils shall not be undertaken due to the limited footprint of the construction site. Spoils shall be trucked away immediately to disposal sites.

i) Should any small stockpiles be developed, these shall be covered by plastic sheeting j) Trucks transporting spoils shall be tightly covered with tarpaulin or other suitable materials

to minimize dust emission and spills. k) Load-out areas shall be cleaned and watered to ensure no accumulated dust originates that

could be dispersed to surrounding areas. l) Wheel washing shall be undertaken to remove mud so as to ensure that access roads are

kept clean. m) Road surfaces shall be regularly cleaned of spilled spoils. n) The spoils disposal site shall be located at least 50 m from surface water courses and shall

be protected from erosion by avoiding formation of steep slopes and grassing. o) Spoil disposal shall not cause sedimentation and obstruction of flow of watercourses,

damage to agricultural land and densely vegetated areas.

4. Wastewater from concrete batch plants (CBP)

a) Prior to operation of CBP, construct settling/retention ponds with sufficient specifications/capacity for treatment of wastewater (e.g., from washing of equipment such as mixer drums, trucks and chute, contact storm water, etc.)

b) Properly operate and maintain settling/retention ponds to ensure effluent quality meets applicable QCVN 24:2009/BTNMT (National Technical Regulation for Industrial Wastewater)

Not Applicable There is no CBP installed on site. The contractor is buying commercial concrete from suppliers who have certificate for construction works

5. Pollution due to spills of fuel and other hazardous substances.

a) Strictly implement approved Spills Management Plan b) Store fuel and hazardous substances in paved areas with embankment. If spills or leaks do

occur, undertake immediate clean up. c) Ensure availability of spill clean-up materials (e.g., absorbent pads, etc.) specifically

designed for petroleum products and other hazardous substances where such materials are being stored.

d) Train relevant construction personnel in handling of fuels and spill control procedures. e) Ensure all storage containers are in good condition with proper labeling. f) Regularly check containers for leakage and undertake necessary repair or replacement. g) Store hazardous materials above flood level. h) Equipment maintenance areas shall be provided with drainage leading to an oil-water

separator that will be regularly skimmed of oil and maintained to ensure efficiency. Discharge of oil contaminated water shall be prohibited.

i) Store waste oil, used lubricant and other hazardous wastes in tightly sealed containers to avoid contamination of soil and water resources. Transport and off-site disposal of such wastes shall be consistent with national and local regulations.

Complied with

Page 60: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 53 of 158

6. Drainage obstruction/flooding

a) Placement of construction materials, excavated spoils, equipment shall not block flow of rainwater into canals/drainage structures.

b) Prohibit disposal of waste materials to drainage channels. c) Regularly inspect and maintain all drainage channels to keep these free of obstructions.

Partially complied with Exception: At Station 10, unhealthy stagnant water was observed. It must be pumped from site.

7. Potential contamination of groundwater due to tunneling

a) Non-toxic slurry and additives shall be used to minimize the impact of potential pollution to the water wells.

b) Minimize the amount of slurry and additives applied to reduce the potential for pollution. c) Ensure that pressure applied to tunneling and ground treatment is controlled to prevent

excessive pressure that will drive the slurry out of the desired range increasing the risk of damaging nearby wells and their water quality.

d) Cooperate with the water agency to shut down the nearby municipal wells while tunneling or ground treatment is taking place.

e) Undertake regular monitoring of water wells located within the range of potential impact with reference to QCVN drinking water standards and pollution indicators (of slurry). Baseline sampling shall also be undertaken prior to start of tunneling.

Complied with

8. Generation of solid wastes

a) Provide garbage bins and facilities within the project site for temporary storage of construction waste and domestic solid waste.

b) Separate solid waste into hazardous, non-hazardous and reusable waste streams and store temporarily on site in secure facilities with weatherproof flooring and roofing, security fencing and access control and drainage/ wastewater collection systems.

c) Ensure that wastes are not haphazardly dumped within the project site and adjacent areas d) Undertake regular collection and disposal of wastes to sites approved by local authorities.

Partially complied with At Station 11, demolition materials generated during the demolition of houses are disposed on the ground. Local people use these amounts as a waste disposal. All materials and debris should be removed from site.

9. Damage to community facilities

a) Immediately repair any damage caused by the Project to community facilities such as water supply, power supply, communication facilities and the like.

b) Access roads damaged during transport of construction materials and other project-related activities shall be reinstated upon completion of construction works.

Partially complied with Demolition materials deposited on the street at Station 11 made it difficult for local people to access their houses. All materials and debris should be removed from site.

10. Land Subsidence Depending on the results of the land subsidence monitoring conducted by the TBM contractor,

suitable mitigation measures shall be developed and implemented by to avoid or minimize damage to properties.

Complied with

11. Traffic congestion and access problems

a) Strictly implement approved Traffic Management Plan b) Locate construction support facilities such that generation of construction traffic trip

numbers and lengths are minimized.

Complied with

Page 61: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 54 of 158

c) To allow one side of the road to be open to two-way traffic, excavation for the underground stations (except for Van Mieu) shall be carried out first on one half of the station width. After excavation is completed and covered, excavation shall then commence at the opposite side.

d) Provide signs advising road users that construction is in progress and that the road narrows to one lane using cones.

e) Employ flag persons to control traffic at the station sites for safety reasons when construction equipment is entering or leaving the work area.

f) Lanes through the work site, created by rope or flagging, shall be developed to minimize risks and injuries from falling objects.

g) Post traffic advisory signs (to minimize traffic build-up) in coordination with local authorities h) Provide road signs indicating the lane is closed 500 m before the worksite. i) Use traffic cones to direct traffic to move to the open lane. j) Provide sufficient lighting at night within and in the vicinity of construction sites. k) Regularly monitor traffic conditions along access roads to ensure that project vehicles are

not causing congestion. l) Define and observe schedules for different types of construction traffic trips (e.g., transport

of pre-cast sections, haulage of spoils, delivery of construction materials, etc.). m) As much as possible, schedule delivery of construction materials and equipment as well as

transport of spoils during non-peak hours. n) Avoid movements of noisy vehicles during night time in vicinity of sensitive receivers. o) Implement suitable safety measures to minimize risk of adverse interactions between

construction works and traffic flows through provision of temporary signals or flag controls, adequate lighting, fencing, signage and road diversions.

p) Ensure relocation of any affected public transport infrastructure (but stops, shelters etc.) prior to commencement of works

q) Provide advance notification to the community regarding changes to public transport facilities or routes.

r) Schedule construction works to minimize extent of activity along linear construction site at any one time

s) Comply with traffic regulations and avoid, where possible, roads with the highest traffic volumes, high density of sensitive receivers or capacity constraints are not used as access to and from the construction areas and spoils disposal sites.

t) Install temporary accesses to properties affected by disruption to their permanent accesses. u) Reinstate good quality permanent accesses following completion of construction.

12. Hazards to health and safety of workers

a) Strictly implement approved Occupational and Community Health and Safety Plan, and approved Emergency Response Plan

Partially complied with

Page 62: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 55 of 158

and the public due to construction works

b) Appoint an environment, health and safety manager to look after implementation of required environmental mitigation measures, and to ensure that health and safety precautions are strictly implemented for the protection of workers and the general public in the vicinity of construction areas.

c) Conduct orientation for all workers on safety and environmental hygiene. d) Provide first aid facilities that are readily accessible by workers. e) Provide firefighting equipment at the work areas, where appropriate, and at construction

camps. f) Provide adequate drainage in workers camps to prevent water logging and formation of

breeding sites for mosquitoes. g) Provide potable water, hygienic sanitation facilities/toilets with sufficient water supply h) Establish clean canteen/rest area. i) Provide fencing on all areas of excavation greater than 2 m deep. j) Provide appropriate personnel safety equipment such as safety boots, helmets, gloves,

protective clothes, breathing mask, goggles, and ear protection k) Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast

sections, etc.) do not fall onto or hit construction workers. l) Implement fall prevention and protection measures whenever a worker is exposed to the

hazard of falling more than two meters, falling into operating machinery or through an opening in a work surface. Based on a case-specific basis, fall prevention/protection measures may include installation of guardrails with mid-rails and toe boards at the edge of any fall hazard area, proper use of ladders and scaffolds by trained employees, use of fall prevention devices, including safety belt and lanyard travel limiting devices to prevent access to fall hazard, fall protection devices such as full body harnesses, etc.

m) Provide sufficient lighting such as the tunnel areas, underground station excavation sites as well as in other construction areas, as appropriate, to enable safe equipment operation. Provide emergency lighting system of adequate intensity that is automatically activated upon failure of the principal artificial light source to ensure safe equipment operation, safe shut-down, evacuation, etc.

n) Ensure that sufficient fresh air is supplied at confined workspaces such as the tunnel and underground station excavation sites. Recirculation of contaminated air is not acceptable. Air inlet filters shall be kept clean and free of dust and microorganisms.

o) Confined spaces (e.g., tunnel) shall be provided with safety measures for venting, monitoring, and rescue operations, to the extent possible.

p) Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast sections, etc.) do not fall onto or hit people, vehicle, and properties in adjoining areas.

At Station 12 some workers were observed working without wearing appropriate clothes, mainly boots and helmets. They said that they have this equipment, but they don’t use because of hot. Contractor must ensure that all workers use the provided PPE.

Page 63: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 56 of 158

q) Fencing of construction sites and excavation sites and guarding such areas to restrict public access.

r) Prior to excavation work, provide fencing on all sides of areas to be excavated. s) Provide warning signs at the periphery of the construction site. t) Strictly impose speed limits on construction vehicles along residential areas and where

other sensitive receptors such as schools, hospitals, and other populated areas are located. u) Educate drivers on safe driving practices to minimize accidents and to prevent spill of

hazardous substances and other construction materials during transport.

13. Potential damage to undiscovered archaeological relics

The following ‘chance-find’ principles will be implemented by the contractor throughout the construction works to account for any undiscovered items identified during construction works:

a) Workers will be trained in the location of heritage zones within the construction area and in the identification of potential items of heritage significance

b) Should any potential items be located, the site supervisor will be immediately contacted and work will be temporarily stopped in that area

c) If the site supervisor determines that the item is of potential significance, an officer from the Department of Culture and Information (DCI) will be invited to inspect the site and work will be stopped until DCI has responded to this invitation

d) Work will not re-commence in this location until agreement has been reached between DCI and HRB as to any required mitigation measures, which may include excavation and recovery of the item

e) A precautionary approach will be adopted in the application of these procedures

Complied with

14. Potential damage to the Temple of Literature

a) Consult with managers of Temple of Literature and DCI prior to commencement of construction to inform them of construction schedule and activities and identify requirements for specific mitigation measures to minimize air, noise, or traffic impacts in addition to those already required in the EMP.

b) Establish a photographic record of the fence and gates, especially at ground level. c) To monitor settlement, install inclinometers along the fence, the gate and other structures

closest to the flower garden. These inclinometers shall be left in place for 2 years after construction and regularly monitored.

d) Install a vibration recording device and undertake continuous monitoring for the period when the TBM is traversing the Temple of Literature.

e) Adjust tunneling speeds and periodicity should the vibration monitoring indicate excessive vibrations.

f) Should the monitoring indicate that settlement has taken place based on photographic record, inclinometer reading and depending on the severity, the following remedial measures

Partially complied with No construction activity in the surroundings ADB missions required CP03 and MRB to prepare PCR Risk Assessment and Management Plan to implement EIA requirements. On 28 May 2019, ADB discussed with MRB’s staff and HGU’s engineers to clarify the requirements of PCR report. On 10 June 2019, ADB issued a letter with a detailed instructions and requirements for PCR report.

Page 64: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 57 of 158

shall be applied, as appropriate: i. Fill the garden area with soil and re-level the ground; ii. Re-install the fence and supports; iii. Jack-up the building(s) and rebuild the base with cement forms or engineered earth; iv. Repair cracks and re-plaster walls.

On 5 July 2019, MRB discussed with HGU’s engineer on the PCR report outline; The report outline has been submitted to ADB for consultation, while the PCR Risk Assessment and Management Plan was under preparation by CP03. The contractor submitted to MRB an uncompleted draft for review by middle October 2019 and PMS2 had to give support to write the most important items of the plan. Currently, while reviewing this report, PMS2 has just transfer these items to the contractor (21 October 2019) Plan for consultation is expected to be in November 2019, then the contractor must update the plan if it is necessary, submit it to MRB and MRB to ADB. Contractor´s BCS also includes PCRs which are considered to be impacted by construction activities of underground section.

15. Social conflicts due to presence of workers

a) Consider the location of construction camps away from communities in order to avoid social conflict in using resources and basic amenities such as water supply.

b) Maximize number of local people employed in construction works. c) Maximize goods and services sourced from local commercial enterprises.

Complied with

16. Additional environmental mitigation measures

The Contractor shall implement corrective and/or additional measures to avoid, mitigate or compensate for adverse environmental impacts due to construction works and other project-related activities performed by the Contractor and its subcontractors.

N/A

Page 65: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 58 of 158

B. TREE RELOCATION/REMOVALACTIVITIES PERFORMED

49. During the first quarter 2019, there is not any tree relocation action taken on site. Data are reviewed in comparison with data offered in the previous SEMR.

50. During the second quarter, tree relocation/removal was implemented at different locations as it’s explained in Appendix 2 and according to Permit no. 63/GP-SXD and Permit no. 40/GP-SXD.

51. The method to manage the trees was according to the method statement and properly carried out by specialists.

52. Table 13 presents the tree relocation status by end of March and June 2019, it means, end of the period of reference of this report. Detailed information is presented in Appendix 2. This issue is being updated continuously in the reports prepared by PMS2

53. No endangered species were removed from their natural original location during the period covered by this report.

Table 13.Tree Relocation Status5

No. Concept Unit Quantity

CP02 CP03 Total

MARCH 2019

1

Total of relocated tree tree 61 156 217

Total number of trees growing normally

tree 52 143 195

Total number of trees no longer able to grow (dried body, leaf wilting)

tree 9 13 22

2 Total of removed tree tree 8 67 75

JUNE 2019

1

Total of relocated tree tree 61 161 222

Total number of trees growing normally

tree 51 148 199

Total number of trees no longer able to grow (dried body, leaf wilting)

tree 10 13 23

2 Total of removed tree tree 8 67 75

June 2019. Permit no. 63/GP-SXD dated 18 August 2016

1 Total of relocated tree tree 106

2 Total of removed tree tree 2

June 2019. Permit no. 40/GP-SXD dated 15 June 2017

1 Total of relocated tree tree 67

2 Total of removed tree tree 50

5 Some figures in this table are not consistent with the ones in the previous SEMR. Previous information contained small mistake, supposedly due to the large list of individuals.

Page 66: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 59 of 158

No. Concept Unit Quantity

CP02 CP03 Total

TOTAL JUNE 2019 tree

1 Total of relocated tree tree 395

2 Total of removed tree tree 127

C. SOIL DISPOSAL AREAS

54. The information and status of foreseen and approved disposal places of the project is presented inTable 14.

55. It has to be mentioned that a problem arose regarding the available disposal places for CP03 and, therefore, a letter explaining the situation was addressed by PMS2 to MRB on January 11, 2019.

56. According to the reference: i) “Item 1.2 Total Bill of Package, section 6.3 Bill of Quantities and Price Centers, Contract Package – HPLML/CP03”, total surplus material from structure excavation is 624,321.21 m3.

57. But total surplus material which is estimated by Contractor CP03 is about 896,190.10 m3 in which Underground stations, Ramp and Emergency Shaft is 727,061.47 m3 and Tunnel is 160,928.63 m3 and Thu Le Lake road is 8,200.00 m3.

58. The Contractor CP03 has proposed 2 disposal areas with total receiving capacity is 1,749,585.00 m3 in which Van Noi disposal area is 349,766.00 m3 and Nguyen Khe disposal area is 1,399,819.00 m3.

59. However, actually Van Noi disposal area is no longer available to receive more surplus soils and Nguyen Khe disposal area is used for many projects in Hanoi and its capacity is also near to be finished. Currently, the information from Nguyen Khe disposal area owner indicate that the remaining capacity of this disposal area is 865,710.00 m3 but it is expected to be quickly filled with many projects that are using this disposal area to dispose their own surplus while the remaining surplus soil volume of package CP03 is very big.

60. It’s essential to look for other disposal areas to ensure that all the surplus material of the project is properly disposed in authorized locations but until now, no mere actions were taken regarding this issue.

61. It’s noted that the permit to dispose unsuitable material in the disposal place which is registered by contractor CP05 – HANCORP has expired on December 31, 2016. For unsuitable material disposal plan in the future, the contractor HANCORP must find and submit documentation of new disposal area to PIC for review and approval. Up to now, excavated material is deposited directly on site, beside the excavation and it will be reused to fill the foundations. After those works, remaining soil must be disposed in a location already approved at that moment.

62. It is also suggested that the excavation work only could continue if the PIC grants Statement of No Objection (SONO) to the action plan of contractor in order to manage this material.

Page 67: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 60 of 158

Table 14.Status of soil disposal areas SOIL DISPOSAL AREAS

Package/ SD No.

Location Approved Area (m2)

Approved Capacity

(m3)

Ownership6 Approval Operation

Name Contact Info Local

Authority7 PIC

CP01/SD1 Vien Noi, Van Noi commune, Dong Anh district, Ha Noi city

Vietnam Industry trade and services JSC

Vien Noi, Van Noi commune, Dong Anh district, Ha Noi city

12-Oct-2007 Yes Under

operation

CP02/SD1 Thap Boi, Phung town, Dan Phuong district, Ha Noi city

10,300 50,000 Thanh Cong Co-operative

145 Me Tri str, Thanh Xuan district, Hanoi

24-Apr-2013 Yes Closed

CP02/SD2 Vinh Quynh disposal area, Thanh Tri district, Ha Noi city

304,500 (tons)

Environmental Technology and Ecology JSC

24 Nhan Hoa str, Thanh Xuan district, Hanoi

30-Aug-2012 Yes Closed

CP02/SD3 Van Noi commune, Dong Anh district, Ha Noi city

349,766

Hanoi construction and demolition waste treatment and environmental development JSC (CDWT&EDI., JSC)

Floor 1st, N03 building, South East Business University Urban Area, Mai Dich Wards, Cau Giay district, Hanoi

27-Sep-2011 Yes

Under operation (CP02 has

finished disposal at the end of

2016)

CP03/SD1 Van Noi commune, Dong Anh district, Ha Noi city

349,766 CDWT&EDI., JSC SAA 27-Sep-2011 Yes Under

operation

CP03/SD2 Nguyen Khe commune, Dong Anh district, Ha Noi city

1,399,819 CDWT&EDI., JSC SAA 27-Sep-2011 Yes Under

operation

CP05/SD1 Vinh Quynh disposal area, Thanh Tri district, Ha Noi city

304,500 (tons)

Environmental Technology and Ecology JSC

24 Nhan Hoa str, Thanh Xuan district, Hanoi

30-Aug-2012 Yes Closed

6 - For a public land, indicate whether it is the property of the commune, district or city, etc 7 - HPC issued the approval, including any written agreement between the Contractor and the landowner

Page 68: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon –

Hanoi Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 61 of 158

D. BUILDING CONDITION SURVEY (BCS)

63. Contractor for CP03 (HGU) finished the building condition survey (BCS), along the sections between stations 9 and 12, in August 2018. The report with the results and the method statement for monitoring the possible affections to houses was submitted to MRB for review. On 23 May 2019, MRB submitted the completed report to ADB.On 28 May 2019, a meeting was arranged between parties to discuss about the report. ADB agreed with the report and the issue may be considered closed.

64. The BCS report identifies the current condition of buildings which are considered will be impacted by construction works of underground section. It consists in photographic records. Its purpose is to be useful to compare in case of relevant grievances during construction period.

E. INCIDENT RECORD

65. No incident was reported by PIC in January, February, May and June 2019.

66. On 21 March 2019, in package CP03, during the lowering of a re-bar cage into the excavated D Wall panel at 22:15 hrs, a pulley assembly which is part of the lifting equipment configuration for the rebar cage fell approximately 6m to the ground; this incident was due to Human error and not mechanical failure. The activity was routine and part of the normal procedure to remove shackles as the cage is lowered, however during this lift one of the signal men holding one side of the wire rope attached to the pulley slipped and released the wire rope causing the weight of the pulley to pull to the opposite side falling towards the ground. This is usually prevented by using the correct method of connecting the two ends of wire by means of a shackle.

67. No Injuries were sustained as a result of the incident. The lift was performed after sunset and delayed from the previous schedule therefore the lifting team had worked on to complete the lift which resulted in a 15-hour shift. HGU Deputy PM went to S9 at approximately 23.00 to carry out initial investigation.

68. HGU did not follow procedure and therefore PIC was not informed officially until the following day at 09.00.

69. On 21 March 2019, HGU sub-contractor FECON was using a crane to move equipment at station 10 without working permission. Unloaded crane started to swing around without retracting the boom and then the hook assembly struck the hotel exterior causing damage to the concrete next to a window on the fifth floor of Pullman Hotel.

70. It’s agreed that the Pullman Hotel shall repair the damage by itself and all the reparation cost shall be charged to the contractor.

71. Copy of the specific report is included in this SEMR asAppendix 6.

72. On 12 April 2019, aluminum bar dropped to pick up truck’s roof at Nhue Bridge (under CP01). The truck roof got a 5cm long scratch but no human injury. The contractor has smoothly settled this incident with the truck driver under the witness of Public Security of North Tu Lien District, Hanoi city.

F. ISSUES FROM PREVIOUS REPORT(S)

73. The evolution of some issues happened since PMS2 started the works and that were reflected in previous SEMRs is now reflected in this chapter, either because new observations are related with previous situations or because previous issues were being solved, totally or partially, during the semester of reference of this SEMR.

74. It has to be remarked one issue that in the previous SEMRs was highlighted: the mobilization by the PIC of HSE Manager, in charge of all safety, health and environment

Page 69: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 62 of 158

matters. Since the beginning of PMS2 works in June 2018, PMS2 considered that in fact this HSE Manager was specialized in health and safety, not in environment. The lack of environmental information and assessments provided by the PIC in its reports confirmed that appreciation.

75. As well, and related with that issue, it has to be remarked the lack of detailed information in the PIC’s monthly reports. In fact, PIC did not prepare any specific HSE monthly report so far (until June 2019). PIC is the supervision consultant on site and MRB (and subsequently PMS2) depends on this supervision to receive appropriate and detailed information about what is happening daily in the construction areas.

76. MRB-PMS2 considers essential that PIC strengthen its supervision works by weekly inspections on site and reporting to MRB-PMS2, by collecting all environmental information from contractors, by assessing the status of environmental conditions on site, and detailing the measures to be taken in case of impacts. All these reinforced activities, also, need to be included in reports. MRB-PMS2 requests that PIC prepares specific environmental, health and safety reports, although some main comments could be included in the general monthly progress reports. So that, MRB (and consequently its support consultant) will be periodically informed about environmental situation on site, status of complaints, affections detected by PIC, measures implemented, results of analytics, etc.).

77. PIC’s HSE Manager was demobilized in February 2019. It means that during almost the whole first semester 2019, PIC had no specialized staff for any of these three subjects. PMS2 considers this fact not acceptable as Health-Safety and Environment are essential part of the implementation of a project during the construction phase.

78. PMS2 insists, for a full compliance of the duties of a supervision consultant company and for a project with the features and difficulties that this presents, in the recommendation that the PIC mobilizes as soon as possible specific environmental and health-safety specialists or a HSE Manager and environmental and health-safety officers to support HSE Manager in these subjects.

79. There is no new information about any proposal of additional disposal sites for unsuitable materials. Contractor for CP03 is requested to give attention to this issue as soon as possible.

80. The status of all the issues raised in the previous SEMR is summarized in Table 15.

Table 15. Status of the Issues raised in the previous SEMR

Issues Targets/Solutions Remark

CP03 did not mobilize officially any Environmental Manager (EM)

After review the contract and discuss with the stakeholders, EM of CP03 is not key personnel, therefore, this position must not be officially submitted and approved by PIC or MRB

The contractor has mobilized a qualified EM in HSE team to control the environmental issue during implementing the construction work

MRB did not mobilize any Environmental Specialist

MRB shall make a proposal to HPC for approval to mobilize this personnel

Expected in early of 2020

The GRM has not yet been formally approved by HPC

MRB needs to try to speed up the process to get the final approval from HPC

As soon as possible

No training to EMU of MRB was carried out since 2013. A proposal for a training plan and its content was already submitted to MRB for

PMS2 will develop training activities with MRB staff who is involved in environmental matters.

Environmental training workshop has been provided to MRB on 27 August 2019

Page 70: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 63 of 158

Issues Targets/Solutions Remark consideration but it’s not yet approved

It’s needed that MRB approves the proposed training plan and/or suggest any change in its content

PIC does not prepare Environmental Monthly Reports. Environmental information contained in its Monthly Progress Reports does not include enough and detailed information about the events happened on site and are not enough assessed

PIC should be requested to give compliance to its duties through specific environmental monthly reports, that must include detailed information and assessment about the daily events happened on site and recorded after each inspection, as well as collect and assess the environmental activities and management developed by each contractor

Immediately

Environmental Effect Monitoring results are not included in PIC’s reports

PIC must include the EEM results of the contractors in their report with the assessment

Immediately. EEM data should be included in the Environmental Monthly Reports to be prepared by the PIC, as requested

At Ramp zone, it’s noted that there are some signs of erosion happened and sediment was swept into the lake because of the Contractor CP03 didn’t apply the storm water, erosion and sedimentation control measures as statement in its approved CEMP, especially, in rainy season.

The Contractor has surrounded the impacted area with sand bags to prevent tracking of soil or other material offsite. The mitigation measure is acceptable in this dry season, from October until April next year.

No impact observed

It’s noted that the permit for the unsuitable material disposal place which is registered by contractor CP05 – HANCORP has expired. Up to now, excavated material is deposited directly on site, beside the excavation and it will be reused to fill the foundations. After those works, remaining soil must be disposed in a location already approved at that moment.

The soil for back fill and unsuitable soil must be separated and managed with correspondent measures as stated in Item 6.3 Waste management procedure of its approved CEMP.

For unsuitable material disposal plan in the future, the contractor HANCORP must find and submit documentation of new disposal area to PIC for review.

It is also suggested that the excavation work only could continue if the PIC grants SONO to the action plan of contractor in order to manage this material.

Before the Contractor has to remove useless soil from site. It’s recommended to speed up the search of a new disposal site as the process to get the approval needs a quite long time.

At Stations 1 and 2 it’s noted that there is no standard mobile toilet provided for workers.

Separated and sanitary toilets must been provided for female and male workers

No improvement in this semester/Immediately

PCR risk assessment has not been initiated, regarding the possible affection to Temple of Literature due to the construction of Station 11.

PCR Risk Assessment and Management Plan must be drafted by contractor CP03 and the consultation with relevant stakeholders (Hanoi DCST, Management Units of impacted heritages) must be implemented

As soon as possible, any case, before starting the construction works

Page 71: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 64 of 158

Issues Targets/Solutions Remark before implementing construction work in Station 11

G. ISSUES IDENTIFIED BY ADB’S REVIEW MISSION IN APRIL 2019

81. Table 16 shows the status of resolution of the main issues identified by ADB’s Review Mission carried out in April 2019 and, subsequently, included in the corresponding MOU.

82. Regarding the environmental findings during ADB’s site visit, some considerations are previously reflected:

(i) Some situations founded or observed cannot be followed up as they were punctual or during specific works. When PMS2 detected similar issues, they were communicated to contractors and reported to MRB through PMS2’s monthly, quarterly and semi-annual reports.

(ii) Error! Reference source not found.Actions taken against the issues identified during the site visit by ADB Review Mission in April 2019 are summarized in Table 16.

(iii) Social issues (land acquisition, resettlement, gender, etc.) are not a subject of this report and they are included in social subject reports for reference.

Table 16. Issues Identified by ADB’s Review Mission April 2019

ISSUE AGENT DEADLINE STATUS. ACTIONS Environmental Safeguards Review CP03’s updated EMS and HSE corrective action report, clear the reports and submit to ADB

MRB 10 May 2019

MRB had reviewed the updated EMS and CEMP of CP03, however it is required to supplement the information in this updated version. CP03 is revising the CEMP, based on the requirement of the MRB

Submit BCS report MRB 10 May 2019

The report has been submitted to ADB on 23 May 2018

PCR assessment i Prepare a draft PCR

risk assessment and management plan (including PCR mitigation measures and PCR monitoring plan) and submit to ADB

ii Hold consultation with Hanoi DCST, UNESCO Vietnam and the custodians of the Temple of Literature on the draft plan

iii Disseminate the information of the draft plan to the public

CP03, MRB

(i) 10 May 2019 (ii) (iii) 31 May 2019 (iv) 14 June 2019

- On 28 May 2019, ADB discussed with MRB’s staff and HGU’s engineers to clarify the requirement on PCR report

- On 10 June 2019, ADB issued a letter with a detail instruction and requirement for PRC report

- On 05 July 2019, MRB discussed with HGU’s engineer on the PRC report outline

- The report outline has been submitted to ADB for consultation, and the

Page 72: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 65 of 158

ISSUE AGENT DEADLINE STATUS. ACTIONS iv Finalize the plan by the

reflecting the comments and opinions of the stakeholders and submit to ADB

PCR Risk Assessment and Management Plan is under preparation by CP03

Environmental Reporting i Submit revised SEMR

(cover period form Jul to Dec 2018)

ii Submit revised IEVR (covering the period from Mar 2017 to Jun 2018)

iii Prepare monthly environmental monitoring reports on EMP implementation for submission to MRB

iv Prepare a monthly environmental monitoring report template

(i) MRB (assisted by PMS2) (ii) External monitoring consultant (PMS2) (iii) PIC (iv) MRB with PMS2, PIC and relevant contractors

(i) 10 May 2019 (ii) 10 May 2019 (iii) From May 2019 (iv) 31 May 2019

(i) revised SEMR has been submitted to ADB and it has been approved and uploaded to the website (ii) revised IEVR has been submitted to ADB and finally approved and uploaded to ADB’s website (iii) not yet (PIC has not mobilized its HSE manager) (iv) the monthly environmental monitoring report template has been prepared by PMS2, discussed with ADB and accepted by MRB

MRB’s Institutional Arrangement i Discuss the assignment

of qualified and experienced environmental officer and occupational health and safety officer internally and with HPC

ii Approve the environmental training plan

MRB (i) (ii) 31 May 2019

(i) MRB will make a proposal to HPC by 31 December 2019 to obtain HPC’s approval for the recruitment of additional staff within 2020. (ii) environmental training plan has been approved by MRB, for a first seminar, in August 2019. The seminar was conducted by the IES on 27 August 2019, while preparing this SEMR No.3.

Table 17. Issues Identified by ADB’s Review Mission Site Visit in April 2019

Identified Issue Actions Taken Remarks

@Station6: Separate toilets were not provided for male and female workers.

Provide separate toilets for female and male workers

The contractor has provided three mobile toilets for workers in this station and they are also separated for male and female workers

@Depot: material (sand) stockpiles were left haphazardly dry and uncovered. Some of them were left for a long time enough for grasses to grow on them;

Keep the moisture of the temporary material stockpile; maintain the grass cover on long-term stockpile

Material (excavated soil) has been used for backfilling work

@Depot: the construction site, access road, and the vicinity of the construction site were

Watering the surface of potential dusty areas with frequency that is appropriate to

The contractor has installed the water supply tube along the potential dusty areas and

Page 73: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 66 of 158

dusty with scattered sand and wind. CP05 contractor explained they spray water only twice a day even on dry sunny days;

minimize the spread of dust (at least 4 times in dry windy days)

watered the surface of these area to ensure that the dust emission is minimized

@Depot: the maintenance area was not equipped with drainage leading to an oil-water separator. CP05 contractor explained that they didn’t construct settling/retention pond for treatment of wastewater, because there are no concrete batch plants at the construction site. It’s not clear if the effluent from the site meets the national technical standard for industrial wastewater, because the result of water quality monitoring is not reported in the SEMRs;

The wastewater treatment system for the maintenance area has been constructed and completed by contractor CP04 before handing over to the contractor CP05. The result of surface water monitoring indicated that all the monitored parameters are under the threshold in Vietnam technical regulation of surface water quality

@Depot: there are opening ditch holes with contaminated stagnant water inside which can be breeding sites for mosquitoes. There was no fencing around the holes, and this can create a falling hazard to the workers as well. CP05 contractor explained that the holes were left open by CP04 contractor and CP05 contractor is not responsible for covering the holes.

All the opening ditch holes have been covered and fenced surrounding to ensure the safety for workers

IX. ENVIRONMENTAL MONITORING PLAN

A. Monitoring Plan and Responsibilities

83. PMS2 prepared the Environmental Monitoring Plan (EMoP) to be implemented by PMS2 and submitted to the MRB in the middle July 2018 for approval.

84. By the plan, the first Environmental Monitoring work should be implemented in the 3rd quarter 2018, but it was not implemented as it has to be previously approved by MRB and ADB. This EMoP will be implemented by PMS2 during the next 4 years. The plan was prepared mainly considering the specifications contained in the Terms of Reference of the support consultant’s contract and also according to the current situation on site and the expected progress of the works.

85. After some discussions regarding the content of this plan and the certifications that the sub-consultant should have, by letter dated 31 October 2018, MRB communicated the approval of the EMoP. PMS2, on 6 November 2018, submitted MRB a letter with the proposal for the sub-consultant in charge of the implementation of the monitoring works. By letter dated on 16 November 2018, MRB accepted the sub-consultant in charge of EMoP implementation. On 20 December 2018 MRB submitted the documentation related with the EMoP to ADB for review and approval. ADB addressed a letter dated 17 January 2019

Page 74: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 67 of 158

indicating ADB’s No Objection to adjustment of the EMoP under PMS2 Contract. Therefore, the plan could not be implemented during the second semester of 2018, as expected.

86. The Plan was not implemented during the first semester 2019 due to financial complications for the transfer of payments to PMS2.

87. As well, this plan may be modified when the conditions on site recommend it. In such case, PMS2 will propose MRB the changes to improve the efficiency of the environmental quality control.

88. During the third quarter 2018, Contractors were implementing the environmental monitoring as per stated in approved CEMPs, except CP03. The Contractor’s Environmental Monitoring Reports have been submitted to the MRB and PIC. Having reviewed the requirements for environmental monitoring during construction phase in the EIA approved by MONRE in 2009 (Vietnamese EIA 2009), chapter IX, subchapter B and current related regulation of DONRE, it’s noted that the environmental monitoring work of the Contractors do not satisfy these requirements. For CP03, PIC stated that there is no continuous Environmental Monitoring performed during Contiguous Bored Pile in its monthly reports; PIC also requested the CP03 to comply with its approved CEMP.

89. A proposal has been submitted to the MRB on 29 August 2018 to suggest that the environmental monitoring work of the Contractors should be complied with the Vietnamese EIA 2009 as well as the current regulation of MONRE, in particularly Circular no. 24/2017/TT-BTNMT dated 01 September 2017 on Environmental Monitoring Techniques of MONRE. Environmental Monitoring Program in Monthly Environmental Monitoring Report of PMS2 which was submitted to the MRB on 17 September 2018.

90. During the fourth quarter 2018, regarding the environmental monitoring works that is covered by PMS2, due to the application of new regulation on environmental monitoring techniques, Circular 24/2017/TT-BTNMT, a proposal to modify environmental monitoring frequency and remove some unnecessary parameters has been prepared and submitted to MRB for review and approval.

91. First semester 2019. Currently, June 2019, this proposal has received No Objection from ADB and, subsequently, was approved by MRB.

92. For the environmental monitoring works that are under contractors responsibility, they have been implemented by CP03 and CP05, in frequency as per stated in approved CEMPs, however, it’s noted that the environmental monitoring frequencies are not uniformed between the Contractors and these frequencies do not comply with the Vietnamese EIA 2009 and with the new regulation on environmental monitoring techniques of MONRE, Circular 24/2017/TT-BTNMT.

93. CP02 has stopped its monitoring activities as main works along the elevated section are already finished.

94. According to the approved CEMPs, the environmental monitoring frequency of CP03 is once per quarter for all the monitored parameters; and for CP05, it states to monitor only noise at two locations once each month. However, actually, contractor CP05 is carrying the environmental monitoring work for noise, vibration, surface water quality and ambient air quality with frequency of once every 6 months.

B. Result of Environmental Effect Monitoring8

8 ADB’s Safeguard policy requires that when the host country regulations differ from internationally recognized standards such as the WB Group’s EHS Guidelines, the borrower/client will achieve whichever is more stringent. Therefore, from the next SEMR, the assessment of environmental monitored results shall be made against the WB EHS Guideline to comply with ADB’s Safeguard Policy

Page 75: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 68 of 158

95. Environmental monitoring work under contractors’ implementation. It has been implemented in frequency as per stated in approved CEMPs; however, it’s noted that the environmental monitoring frequencies are not uniform between the Contractors and the frequencies do not give compliance to the Vietnamese EIA 2009 and new regulation on environmental monitoring techniques of MONRE, Circular 24/2017/TT-BTNMT. It means that the CEMPs do not reflect what it was stated in the Vietnamese EIA 2009 about this matter.

96. According to the approved CEMPs, the environmental monitoring frequency of CP03 is once per quarter for all the monitored parameters; and for CP05, it states to monitor only noise at two locations once each month. However, actually, contractor CP05 is carrying the environmental monitoring work for noise, vibration, surface water quality and ambient air quality with frequency of once every 6 months. CP01 and CP02 did not carry out any monitoring activity during the semester.

97. CP05:

1. Noise monitoring: noise measurement was carried out during the period from 8h to 22h. All the noise monitoring results shall be compared with National standard of Vietnam QCVN 26:2010/BTNMT for common areas, that points out a period of measurement rather different, from 6h to 21h. All the data measured (Laeq) at all positions are lower than the level stipulated on regulation (please see Appendix 3 for detailed information about noise levels in each location).

2. Vibration monitoring: All vibration acceleration at the observation location are below level stipulated on National standard of Vietnam QCVN 27:2010/BTNMT.

3. The air environment: monitoring results in majority of monitoring locations are lower than the limit values specified in National standard of Vietnam QCVN05: 2013/BTNMT.

4. Surface water: The results of surface water quality monitoring shows that all parameters analyzed are Lower than the limit value permitted under QCVN 08-MT: 2015 /BTNMT column B1.

98. CP03:

- 1st quarter: 1. Noise monitoring: Noise measurement time ranging was from 6h to 22h. All the

noise monitoring results shall be compared with Vietnam Technical regulation on Noise QCVN 26:2010/BTNMT for common areas, that points out a period of measurement rather different, from 6h to 21h. Some specific data that were measured for one hour are higher than threshold stipulated on regulation and the highest level is 75.9 dBA measured in location K1 from 10h00 – 11h00 in the first quarter; however, other measurements taken at all locations are lower than the level stipulated on regulation and the average results indicated that they are lower than threshold stipulated at all positions. At several timelines, noise values are over standard value caused by the high numbers of public vehicles involved in the traffic.

2. Vibration monitoring: All vibration measurements at the observation locations are below level stipulated on National standard of Vietnam QCVN27: 2010/BTNMT.

3. The air environment: Monitoring results in all of monitoring locations are lower than the limit values specified in National standard of Vietnam QCVN05: 2013/BTNMT

4. Surface water: The concentration of the analyzed parameters in the surface water samples are within the limit set in QCVN 08-MT:20l5/BTNMT, column B2.

5. Soil quality: All analyzed parameter are meet in line with National Technical Regulation on Soil quality QCVN 03-MT:20l5/BTNMT.

Page 76: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 69 of 158

- 2nd quarter: 1. Noise monitoring: Noise measurement time ranging from 6h to 22h. All the noise

monitoring results shall be compared with Vietnam Technical regulation on Noise QCVN 26:2010/BTNMT for the common area from 6h to 21h. Most of the data were measured at all positions that are lower than the level stipulated on regulation, there is only one sample measured from 12h to 13h higher than threshold stipulated (70.7 dBA) in position K2. Noise value is over standard value caused by the high numbers of public vehicles involved in traffic.

2. Vibration monitoring: All vibration measurements at the observation locations are below level stipulated on National standard of Vietnam QCVN 27:20 1 O/BTNMT.

3. The air environment: Monitoring results in all of monitoring locations are lower than the limit values specified in National standard of Vietnam QCVN05: 2013/BTNMT.

4. Surface water: The concentration of the analyzed parameters in the surface water samples are within the limit set in QCVN 08-MT:2015/BTNMT, column B2.

5. Soil quality: All analyzed parameter are met in line with National Technical Regulation on Soil quality QCVN 03-MT:2015/BTNMT.

The environmental monitoring results from all monitoring samples which have been implemented by the contractors are detailed presented in Appendix 3.

C. Land Subsidence and Settlement Monitoring at the Underground

Section

99. According to the information, verbally provided by the contractor, HYUNDAI E&C – GHELLA JV continued during the first semester 2019 carrying out land subsidence monitoring with frequency twice a week. The reports have been submitted to MRB and PIC. These reports were not provided to PMS2. The results should have been included in the PIC’s Monthly Reports, which are the reports in fact provided to PMS2 for review and assessment. In general, the subsidence is insignificant but there are horizontal movements of steel sheet pile at sections of Ramp and Station 10.

X. PUBLIC CONSULTATION, GRIEVANCE REDRESS MECHANISM

A. COMMUNICATION SYSTEM

100. A communication team has been established at MRB per Decision 13/QD-DSDT-VP issued by MRB (dated 7 February 2017) that have several missions, as follows:

1. External Media 2. Press Releases 3. Internal Media.

101. A communication team was created in MRB and it has coordinated with another communication team from ADB to establish a communication strategy for 2017 – 2018 that shall be a comprehensive guidance for communication activities of MRB during the period of the project implementation.

B. CONSULTATION ACTIVITY DURING THE MONITORING PERIOD

102. During the first semester 2019 there was no consultation activity related with environmental matters. Please refer to social issues reports for information about consultations, interviews and meetings with social agents.

C. GRIEVANCE REDRESS MECHANISM (GRM)

Page 77: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 70 of 158

103. A Grievance Receiving, Screening and Settling Unit (GRSSU) has been established at the Metropolitan Railway Management Board (MRB) per Decision No.63/QD-DSDT-VP issued by MRB (dated 22 May 2017) and also a GRM at project level has been proposed by the coordination of ADB and MRB, but since the GRM has not yet been formally approved by HPC, the GRM was not yet disseminated.

104. The current status for its approval and implementation is as follows:

✓ GRM at project level was submitted to HPC for approval on 30 June 2017. ✓ GRM was submitted by MRB to HPC and HPC required Inspection Department

of Hanoi reviewing and reporting the solution. ✓ Inspection Department of Hanoi reviewed and reported to HPC. MRB has

revised and submitted to HPC in March 2018. ✓ Proposed GRM was submitted to Department of Justice for consideration and

in June 2018 (according to the received information), re-submitted to HPC for approval with the agreement of the quoted department.

✓ Project’s Grievance Coordination Mechanism (GCM) has been finalized by incorporating inputs from Hanoi Department of Justice (HDOJ). It was received in August 2018 and submitted to HPC in September 2018 for approval.

✓ In August 2018 HPC submitted a letter to MRB including some comments regarding this proposed GRM and requesting clarification.

✓ In October 2018 it was convened by MRB a meeting with HPC in order to explain and discuss those comments.

✓ After that, HPC drafts a Guideline “For entities performing redress grievances of organizations, individuals relating to the implementation of Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi railway station” with some corrections to the previous draft of GRM and resubmits to MRB.

✓ MRB submits the draft to ADB for review, by mail, on 3rd June 2019. This draft guideline, prepared by HPC, it’s included in this SEMR No.3 as Appendix 8.

✓ On July 10, 2019, ADB sent back the document with some comments for its update.

✓ Currently, MRB is updating the draft guideline considering the comments received from ADB and other related agencies and will resubmit it to HPC for final approval.

✓ At the end of the period of this report, June 2019, the GRM was not yet approved by HPC. While preparing this SEMR in August 2019, the GRM is not yet finally approved.

105. Description of the GRSSU objectives, procedures and components is already included in the SEMR No.1, for its consultancy.

D. STATUS OF RESOLUTION OF COMPLAINTS

106. PIC, according to the duties of a construction supervision consultant, is in charge of the follow up of the complaints received from affected local people, households affected by the construction activities and any matter related with the project implementation. Therefore, PMS2 requested PIC to provide updated information about the status of the processes to solve the pending complaints. Currently, PIC did not provide in its monthly reports any new information about pending complaints.

107. Regarding PMS2 information, during the first quarter 2019 we didn’t receive any information about new complaints.

108. The information collected during the second quarter includes also some complaints happened in the first quarter.

Page 78: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 71 of 158

109. In March 2019, MRB has visited the construction site of road underneath Access Bridge to Depot of CP01 and received grievances on house cracking due vibration during carrying out construction work in this area, road no. 70, Tay Tuu ward, Bac Tu Liem district. The affected houses are vicinity of the construction site which include the houses of Nguyen Dang Chien, Dang Thi Doan Huong, Đinh Van Su, Dinh Van Vien, Pham Thi Duyen, Pham Quang Trung, Ta Xuan Luan, Bui Van Truong, Nguyen Khac Phuong.

110. In order to ensure the safety of affected people, quality and progress of the construction package, MRB issued letter No 440/ĐSĐT-DA1 on March 8, 2019 to request Daelim Contractor and Systra Consultant to implement the following tasks: (i) recheck the construction method and offer the solutions for safety assurance during construction to completely avoid collapse of the affected houses and (ii) check and evaluate the damages caused by the construction work (if any) and to compensate the damaged properties as per the contract regulations and law regulations.

111. Right after receiving MRB’s letter No 440/ĐSĐT-DA1, Daelim Contractor has immediately adjusted the method of compaction to prevent any potential damages to residents’ properties. At the same time, Daelim has been carrying out the crack investigation in residents’ houses at the construction site of Road underneath the Access Bridge to Depot and working closely with the local authorities (Tay Tuu CPC) on the present issue.

112. On 10 May 2019, MRB issued letter 945/ĐSĐT-VP-DA1 to propose Bac Tu Liem DPC and Tay Tuu CPC to redefine the origin of land use and the origin of houses built on land of AHs in order that MRB could use it as a legal basis to reply to AHs and redress the people’s house cracking grievance following the legal regulations. A meeting between Tay Tuu CPC, MRB and the contractor CP01 has been arranged on 20 June 2019 to plan in order to solve this matter. It’s expected to hold a meeting with the affected households in early of July 2019.

113. Up to date, the total number of households eligible to resettlement allocation is 127 (21 in Depot & Access Line and 106 in CP03). Out of 127 households eligible for land plots or resettlement apartment allocations of the whole project, 115 households have received land plots or resettlement apartments, the remaining 12 households have not yet received them. All of these 12 households belong to Package CP03.

114. Relating to 21 households affected by Phase 2 - Depot and Access Line, issue that was commented in the SEMR No.2, Bac Tu Liem District has already allocated all of them for resettlement plots in Xuan Phuong RS. Infrastructure, electric and potable water system in Xuan Phuong RS are adequate, near schools and not far from their acquired land. So, their lives are not much affected by the project.

115. Up to date, there are still 62 grievances of affected households relating in compensation policies, positions of land for compensation, unit price for compensation and policy of relocation in which 42 grievances in Depot & Access Line, 9 at Tay Tuu Road No 70 about cracks on houses, 10 from AHs and 1 from affected organization in Package CP03 (Underground Tunnel & Stations).

116. PMS2 specialists for social and resettlement matters are continually working in the pending complaints. Please see social and resettlement monthly reports for detailed information about all complaints and pending social issues.

XI. INSTITUTIONAL STRENGTHENING AND TRAINING During the period of this report, first semester 2019, the training activities developed by the contractors are detailed in Tables 18 and 19.

Page 79: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 72 of 158

Table 18.Training activities of contractors (First quarter 2019)

PACKAGE TRAINING DATE LOCATION PARTICIPANTS CP01 - - - -

CP02 HSE induction training for workers of Remec

company 15-Jan-2019 Office 11

CP03

HSE Induction 18-Jan-2019 HGU Office 15 HSE Induction 26-Jan-2019 HGU Office 2 HSE Induction 16-Feb-2019 HGU Office 45 HSE Induction 20-Feb-2019 HGU Office 7 HSE Induction 23-Feb-2019 HGU Office 2 HSE Induction 28-Feb-2019 HGU Office 31 HSE Induction 05-Mar-2019 HGU office 15 HSE Induction 14-Mar-2019 HGU office 6 HSE Induction 22-Mar-2019 HGU office 15 HSE Induction 25-Mar-2019 HGU office 12 HSE Induction 28-Mar-2019 HGU office 16 HSE Induction 29-Mar-2019 HGU office 17

CP05

HSE Induction 03-Jan-2019 Meeting room

2

HSE Induction 05-Mar-2019 Meeting room

16

HSE Induction 22-Mar-2019 Meeting room

62

HSE Induction 29-Mar-2019 Meeting

room 22

CP06 - - - - CP07 - - - - CP08 - - - -

Page 80: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 73 of 158

Table 19.Training activities of contractors (Second quarter 2019)

CONTRACTOR TRAINING DATE LOCATION PARTICIPANTS CP01 - - - - CP02 - - - -

CP03

HIV/AIDS Prevention

training 09-Apr-2019 HGU Office 11

HSE Induction 19-Apr-2019 HGU Office 10 HSE Induction 23-Apr-2019 HGU Office 9 HSE Induction 23-Apr -2019 HGU Office 2 HSE Induction 23-Apr -2019 HGU Office 7

HIV/AIDS Prevention

training 28-May-2019 HGU Office 16

HSE Induction 03-May-2019 HGU Office 10 HSE Induction 10-May-2019 HGU Office 10 HSE Induction 14-May-2019 HGU Office 21 HSE Induction 21-May-2019 HGU Office 10 HSE Induction 31-May-2019 HGU Office 3

CP05 - - - - CP06 - - - - CP07 - - - - CP08 - - - -

117. Regarding HSE training of contractors during the first quarter 2019, it has to be mentioned that:

Contractor for CP01, CP06, CP07 and CP08 have not developed any activity, although it must be stated that CP01 has finished main works and CP06 is developing design works at office in France.

Contractor for package CP02 stopped these activities in January. Contractor for package CP03 developed training sessions at office all months. Contractor for package CP05 carried out training sessions at office in January

and in March.

118. Regarding HSE training of contractors during the second quarter 2019, the activities were as follows:

Contractor for CP01, CP02, CP05, CP06, CP07 and CP08 have not developed any activity, although it must be stated that CP01 has finished main works and CP06 is developing design works at office in France.

Contractor for CP03 conducted several training sessions at office in April and May, stopping this activity on 31st May.

119. PIC’s training activities during the semester, according to the content of the Monthly Progress Reports, were as follows (same every month and same previous semester):

Table 20. PIC's training activities. 1st semester 2019

MONTH ACTVITIES January - SYSTRA training in class of site inspectors

- PIC monitored CP02, CP03 and CP05 HIV and gender mainstreaming training - PIC monitored CP08 HSE Induction

Page 81: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 74 of 158

MONTH ACTVITIES February - SYSTRA training in class of site inspectors

- PIC monitored CP02, CP03, CP05 and CP08 HIV and gender mainstreaming training - PIC monitored CP08 HSE Induction

March - SYSTRA training in class of site inspectors - PIC monitored CP02, CP03, CP05 and CP08 HIV and gender mainstreaming training - PIC monitored CP08 HSE Induction

April - SYSTRA training in class of site inspectors - PIC monitored CP02, CP03, CP05 and CP08 HIV and gender mainstreaming training - PIC monitored CP08 HSE Induction

May - SYSTRA training in class of site inspectors - PIC monitored CP02, CP03, CP05 and CP08 HIV and gender mainstreaming training - PIC monitored CP08 HSE Induction

June - SYSTRA training in class of site inspectors - PIC monitored CP02, CP03, CP05 and CP08 HIV and gender mainstreaming training - PIC monitored CP08 HSE Induction

Note: It’s not well understood the meaning of “monitored” as a PIC’s own training activity.

120. According to the duties of the PMS2, expressed in the contract, classroom and on the job training of MRB staff is an integral part of its consultancy. So that, the IES will provide a training course for staff of MRB and other agencies through invitation of MRB if the EA considers so.

121. The courses will give staff a basic understanding and technical knowledge about environmental impact and protection, to be able to understand the implications of environmental matters arising during construction and implementation of the project.

122. PMS2 suggests that, although no specific environmental staff is currently mobilized in MRB, basic courses should be given to civil engineers, inspectors on site, etc., about environment related subjects such as impact of construction works, environmental protection measures, climate change, etc.

123. Regarding the training activities which will be developed by the PMS2, a Training Plan was prepared by the PMS2, to be implemented by the IES. This plan was submitted to MRB for approval by middle December 2018. This plan included both training in class and on site, over 2-3 mornings.

124. It was expected that the seminar was given during the mobilization of the IES in August 2019 but previously, in June, MRB instructed PMS2 to change the content of this first training activity and prepare a short one focused in the environmental situation in this project and in the policies and regulations that must be complied. In July it was submitted to MRB a first proposal and a final one in August, with some little changes in the content. As Appendix 7it’s included in this SEMR No.3 copy of the official letter with the content of the new proposed seminar.

125. While this report was being prepared, the seminar was conducted. It’s expected that for the next mobilization of the IES, the first proposed seminar could be conducted.

XII. CONCLUSION

Page 82: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 75 of 158

126. As this report is a summary report of the activities performed by all agents involved in the project during the period of reference of the SEMR, conclusions are distributed in each chapter for each item.

127. As it has been mentioned along the report, it has to be remarked as an essential conditioning for the content of this SEMR, the lack of detailed information in the PIC’s monthly reports. PIC is the supervision consultant on site and MRB-PMS2 depends on this supervision to receive appropriate and detailed information about what is happening daily in the construction areas. The solution of this issue is pending since PMS2 started its works in June 2018.

128. Main findings and operation problems identified during the first semester 2019, recommended actions and proposed deadline for final solution are now summarized in Table 21. MRB, organization for which PMS2 was contracted for support management, has been continually informed, by letter and through our environmental monthly reports, about those findings and recommendations.

129. To correct the environmental issues that arise during carrying out construction work, in the weekly meetings with the contractors MRB has requested and reminded the contractors to implement the appropriate mitigation measures which have been stated in EMP and approved CEMPs. PIC also was requested to instruct and supervise the corrective action of the contractors.

Page 83: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon –

Hanoi Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 76 of 158

Table 21.Summary of main identified issues and actions required

Issues Targets/Solutions Proposed Issue Closed date

1. MRB hasn't established EMU

MRB is proposing to HPC to agree to mobilize an environmental staff and establish EMU inside MRB arrangement

MRB expected that HPC shall agree with MRB’s proposal hence MRB can establish EMU in early next year

2. PIC did not mobilize any Environmental or HSE Manager since February 2019

Mobilize him when received the approval from MRB.

If a HSE Manager is mobilized, also an environmental specialist should be mobilized as support.

Immediate

3. Contractor’s mobilization of an Environmental Manager or Specialist

All contractors have mobilized a responsible for HSE, but approved CEMPs include the duty to mobilize a specific Environmental Manager or Officer or Specialist as well. Only CP02 and CP03 have officially (CP03, in fact) mobilized a specific Environmental Manager.

- Proposal to cover this position: 15 Oct 2019

- Approval: 10 days after

- Mobilization: 15 days after approval

4. The GRM has not yet been formally approved by HPC. However, all the grievances including environmental grievances are managed and followed by GRSSU.

MRB needs to speed up the update of the GRM according to HPC review, to get the final approval from HPC.

the GRM logbook is available in MRB and the contractors’ office.

All the environmental grievances are handled with the procedure of (i) grievance receive, (ii) contact the stakeholders, (iii) grievance investigation, (iv) making an agreement between the stakeholders on the grievance redress, (v) grievance redress implementation, and (vi) closing the grievance.

5. No training to EMU of MRB was carried out since 2013.

Proposals for two different training seminars to be conducted by PMS2 and their content were already submitted to MRB for consideration.

PMS2 will develop training activities with MRB staff who is involved in environmental matters and other technical staff working in the project.

By July-August 2019 a first plan was approved

Expected to be done in August 2019, when the IES of PMS2 will be mobilized

6. PIC did not develop any training activity with MRB or HRB staff, as required in the EMP

PIC is required to carry out its duties in this matter, preparing a training plan and submitting it to MRB for approval and later implementation

Before December 31, 2019. No change since June 2018

Page 84: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 77 of 158

Issues Targets/Solutions Proposed Issue Closed date

7. PIC does not prepare Environmental Monthly Reports to assess the contractors’ performance on CEMP implementation. Environmental information contained in its Monthly Progress Reports does not include enough and detailed information about the events happened on site and, therefore, the compliance of the works on site with the approved EMP is not assessed

PIC is requested to give compliance to its duties through specific environmental monthly reports, that must include detailed information and assessment about the daily events happened on site and recorded after each inspection, as well as collect and assess the environmental activities and management developed by each contractor

PMS2 has given direction to prepare these reports.

Immediately. No change since June 2018

The first specific environmental report should be prepared for October 2019

8. No environmental inspection was conducted by DONRE or MONRE since the commencement of the construction works

MRB should contact these agencies to offer the possibility of site visits, at least when any incident happens, or a serious problem arises

As soon as possible

9. The contractors are implementing environmental effect monitoring as the requirement in their contracts. Contractor CP05 is carrying out EEM with the frequency of every 6 months while EIA 2013 requests a frequency of every 3 months. Contractor CP03 is complying with the EEM requirement in EIA. However, there is a change of monitoring regulation (Circular 24/2017/TT-BTNMT on Environmental Monitoring Techniques) with the new monitoring frequency. The current monitoring frequency of the contractors as stated in the construction contracts did not comply with the new Regulation of Vietnam regarding the frequency of the monitoring of environmental quality parameters

New Regulation in Vietnam states that environmental quality parameters for out-door air environment and surface water environment must be monitored bimonthly. PMS2 informed contractors about this fact. Requested frequency must be implemented.

Immediate for all contractors that carry out monitoring activities according to the EIA

10. Environmental Effect Monitoring results are not

PIC has to request contractors to provide the results of their

Immediately. No change since June 2018

Page 85: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 78 of 158

Issues Targets/Solutions Proposed Issue Closed date

included in PIC’s reports and not provided to PMS2 for assessment and/or verification

EEM activities, assess these results, give instructions in case of any deficiency or impact, and include the information and assessment in specific environmental monthly reports.

EEM data should be included in the Environmental Monthly Reports to be prepared by the PIC, as requested

11. Base on the contract, PMS2 shall implement the EEM but they have not initiated environmental effect monitoring since its mobilization in May 2018 due to the contract issue.

PMS2 shall coordinate with MRB to fix the contract issue to implement environmental effect monitoring work

It’s expected to initiate in January 2020

12. It’s noted that the permit for the unsuitable material disposal place which is registered by contractor CP05 – HANCORP has expired. Up to now, excavated material is deposited directly on site, beside the excavation and it will be reused to fill the foundations. After those works, remaining soil must be disposed in a location already approved at that moment.

The soil for back fill and unsuitable soil must be separated and managed with correspondent measures as stated in Item 6.3 Waste management procedure of its approved CEMP.

For unsuitable material disposal plan in the future, the contractor HANCORP must find and submit documentation of new disposal area to PIC for review.

It is also suggested that the excavation work only could continue if the PIC grants SONO to the action plan of contractor in order to manage this material.

Before the Contractor has to remove useless soil from site. It’s recommended to speed up the search of a new disposal site as the process to get the approval needs quite a long time.

13. Hazards to health and safety of workers on site. Except station 6, all the toilets for workers have been removed from construction site of elevated station (under CP02).

Until the end of June 2019, there is no improvement.

Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers

Immediately

14. ADB requests the contractor CP03 and MRB to additionally assess all the impacted PCR along the underground section and consult with the stakeholders before carrying out the main construction work in station 11.

On 26 October 2018, a meeting has been held with participation of ADB, MRB, HGU and the Literature Temple management board.

The study and assessment were expected to start in early 2019.

On 10 June 2019 ADB sent a letter including the

Prepared, submitted to ADB, reviewed (when necessary) and finally approved always and any case, before starting the construction works at Station 11.

According to the last information, the process will finish around 15 – 30 December 2019

The fact that excavation work started in April 2019 at Station

Page 86: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 79 of 158

Issues Targets/Solutions Proposed Issue Closed date

However, the PCR risk assessment has not been initiated.

requirements for PCR report's content to MRB.

Later on, MRB held a meeting with HGU engineers to transfer this requirement. In that meeting PMS2 instructed the contractor how to prepare the report, with report outline. This report outline also was sent to ADB for consultation and ADB agreed with this outline. It was officially sent to the contractor HGU to prepare the draft report on 31 July.

In the last meeting with ADB in VRM office, the contractor informed that they shall complete the draft at the end of September, then submit it to MRB for competence agencies and public consultation.

Public consultation shall be implemented in October 2019 and the report shall be finalized in November and submitted to ADB before carrying out the construction work at Station 11.

10 before conducting PCR risk assessment jeopardizes the compliance with SPS 2009 as alerted by ADB. MRB is taking action to respond to ADB request for full compliance with SPS 2009, 2013 EIA and Mission MOU. Outcomes will be reported in the SEMR Jun-Dec 2019

15. CEMP implementation issues

CP01: There is not any available water truck on site, a dusty status was noted, for example, during ADB mission on 26 April 2019.

CP02: Except station 6, all the toilets for workers have been removed from construction site of elevated station (under CP02). Until the end of June 2019, there is no improvement.

At Station 2 a worker was observed cutting metal bars without wearing gloves. Contractor shall ensure that all workers are provided and use their PPE.

CP03: At Station 12 some workers were observed working without wearing appropriate clothes, mainly boots and helmets. They said that they have this equipment, but they don’t use because of

The contractors must strictly comply with the environmental mitigation/minimize measures as stated in their approved CEMPs and the project’s EMP

It is noted that CEMP implementation and contractors’ performance has not been regularly reported by PIC Systra in its monthly reports. MRB will look into this issue and fix the reporting arrangements through contracts with contractors, PIC and PMS2, in line with the 2013 EIA

Page 87: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 80 of 158

Issues Targets/Solutions Proposed Issue Closed date

hot. Contractor must ensure that all workers use the provided PPE.

At Station 11, demolition materials generated during the demolition of houses are disposed on the ground. Local people use these amounts as a waste disposal. All materials and debris should be removed from site.

At station 10 excavated soil which is temporary disposed on site for back filling is not covered, so that it may generate dust emissions.

CP08: Waste management must be improved.

It was observed that waste was disposed on site directly on the ground. No separation of selected waste materials. Not enough containers for waste management.

Page 88: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon –

Hanoi Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 81 of 158

XIII. APPENDICES

Appendix 1: PHOTOGRAPHIC REPORT

Subject 22-May-2019. Watering works to avoid dust

14 August 2019. Portable toilet on site Location CP05. Depot area Date

Subject Electrical installation well closed and isolated. Fire extinguisher directly

under the sun. Location CP05. Depot area Date 14-Aug-2019

Page 89: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 82 of 158

Subject Workers wear safety equipment, including women Location CP05. Depot area Date 14-Aug-2019

Page 90: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 83 of 158

Subject Preparing foundations for maintenance buildings Location CP05. Depot area Date 14-Aug-2019

Subject Most of construction site is clean and tidy Location CP05. Depot area Date 14-Aug-2019

Page 91: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 84 of 158

Subject Poor performance of waste management Location CP05. Depot area Date 14-Aug-2019

21-Mar-2019 17-May-2019

Subject Workers wear full appropriate equipment. Site is clean and tidy Location CP03. Station 9 Date

Subject Settling pond. Safety fence Location CP03. Station 9 Date 14-Aug-2019

Page 92: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 85 of 158

Subject First-aid cabine. Double toilet for men and women. Tire washing point Location CP03. Station 9 Date 14-Aug-2019

Subject Building a canal to evacuate waters. Soft soil disposed on site for back

filling Location CP03. Station 10 Date 14-Aug-2019

Subject Hazardous substances well stored. Unhealthy stagnant waters Location CP03. Station 10 Date 14-Aug-2019

Page 93: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 86 of 158

Subject General overview of construction area. Safety scaffold Location CP03. Station 10 Date 14-Aug-2019

Subject Tire washing point. Double toilet for men and women Location CP03. Station 10 Date 14-Aug-2019

Page 94: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 87 of 158

22-Mar-201928-May-2019

Subject 22-Mar-2019. HSE Induction, HANCORP Office – CP05 28-May-2019. HIV Prevention training, HGU Office – CP03

Location Date

15-Jan-2019 14-Aug-2019

Subject Evolution of the demolition of houses Location CP03. Station 11 Date

Page 95: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 88 of 158

Subject Demolition materials and debris are spread along the site and the public

street. Local people add waste to these accumulations of garbage Location CP03. Station 11 Date 14-Aug-2019

Subject Difficulties for local people to access to their houses Location CP03. Station 11 Date 14-Aug-2019

Subject General overview of construction site. Tire washing point. Demolition

materials on site. Location CP03. Station 12 Date 14-Aug-2019

Page 96: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 89 of 158

Subject Replacement works of the electric line and other services. Workers do not

wear PPE, especially appropriate boots. Location CP03. Station 12 Date 14-Aug-2019

Page 97: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 90 of 158

21-Mar-2019 14-Aug-2019

Subject On street level,left side, construction materials and debris are spread on the ground

Location CP02. Station 8 Date

19-Feb-2019, 14-Aug-2019

Subject On street level, right side, construction materials and debris are still spread on the ground, although some removal was done

Location CP02. Station 8 Date

Subject First floor. Construction materiales are stored but also debris are disposed. Location CP02. Station 8 Date 14-Aug-2019

Page 98: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 91 of 158

Subject Surfaces are clean and no waste is spread on them. Installing safety nets Location CP02. Station 2 Date 14-Aug-2019

Subject Double toilet, for men and women. Cutting metal bars without gloves Location CP02. Station 2 Date 14-Aug-2019

Subject Safety signals. Fence. Scaffols Location CP02. Station 2 Date 14-Aug-2019

Page 99: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 92 of 158

15-01-2019,19-Feb-2019

Subject Construction area has been paved and handed over to authority

Location CP02. Station 3 Date

Subject Traffic is mostly restarted. Wrong waste management. Dirtiness Location CP02. Station 6 Date 14-Aug-2019

Subject Construction site is full of stored materials. Life-line for works on height Location CP02. Station 6 Date 14-Aug-2019

Page 100: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 93 of 158

Subject Scaffold that needs to be reinforced. Safety signals and equipment Location CP02. Station 6 Date 14-Aug-2019

11-June-2019 14-Aug-2019

Subject Broken fence was repaired. Much waste is still on site Location CP01. Initial ramp from depot Date

Subject New canal for street drainage. Waste was partially removed Location CP01. Initial ramp from depot Date 14-Aug-2019

Page 101: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 94 of 158

Subject General overview under and on the deck Location CP01. Between ST1 and ST3 Date 14-Aug-2019

Subject General overview of the elevated section Location CP01. Between ST8 and RR2 Date 14-Aug-2019

Page 102: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 95 of 158

15-Jan-2019 14-Aug-2019

Subject Sodding works under the deck Location CP01 Date

Subject Grass and bushes under the deck Location CP01. Around ST8 Date 14-Aug-2019

Page 103: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 96 of 158

Subject Surfaces are kept clean without debris Location CP08. Depot and ramp from Depot Date 14-Aug-2019

Subject Site is clean and tidy Location CP08. Ramp from Depot Date 14-Aug-2019

Page 104: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 97 of 158

Appendix 2: TREE RELOCATION AND REMOVAL STATUS. DETAIL TREE RELOCATION STATUS

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

A. CP03 161

I Ramp Zone 29

Permit no. 53/GP-SXD dated 24/7/2017 and

Permit no 90/GP-SXD dated 14 Nov 2018

1 1 Khaya Wood 1 13.4 3.5 Normal growth

2 6 Senna 1 11.5 6.0 Normal growth

3 7 Senna 1 35.7 8.5 Died

4 9 Engelhardtia spicata 1 17.8 6.0 Died

5 10 Engelhardtia spicata 1 21.0 9.0 Normal growth

6 12 Flamboyant 1 11.5 4.0 Normal growth

7 13 Senna 1 39.8 10.0 Normal growth

8 15 Senna 1 23.2 11.0 Normal growth

9 18 Senna 1 44.6 13.0 Normal growth

10 19 Lagerstroemia 1 15.6 8.0 Normal growth

11 20 Senna 1 42.0 13.0 Normal growth

12 25 Flamboyant 1 35.0 8.5 Normal growth

13 31 Milkwood pine 1 30.6 7.0 Normal growth

14 35 Lagerstroemia 1 16.9 5.5 Normal growth

15 44 Flamboyant 1 38.8 13.0 Normal growth

16 45 Flamboyant 1 49.0 15.0 Normal growth

17 46 Milkwood pine 1 43.0 12.0 Normal growth

18 47 Flamboyant 1 30.6 9.0 Normal growth

19 80 Engelhardtia spicata 1 35.0 8.0 Normal growth

20 81 Engelhardtia spicata 1 20.4 7.5 Normal growth

21 69 Cassia fistula L 1 17.5 8.0 Normal growth

22 70 Khaya senegalensis 1 64.0 12.0 Normal growth

23 71 Khaya senegalensis 1 41.0 11.0 Normal growth

24 74 Engelhardtia spicata 1 16.0 6.0 Normal growth

25 75 Khaya senegalensis 1 60.6 12.0 Normal growth

26 76 Lagerstroemia speciose

1 14.0 6.5 Normal growth

27 77 Engelhardtia spicata 1 22.0 7.0 Normal growth

28 78 Engelhardtia spicata 1 26.6 7.5 Normal growth

29 79 Chukrasia tabularis 1 20.0 5.5 Normal growth

II Station 9 88

Permits no. 53/GP-SXD dated 24/7/2017 and 94/GP-SXD dated

07/11/2017

Page 105: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 98 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

1 1 Lagerstroemia 1 33.4 9.5 Normal growth

2 2 Lagerstroemia 1 15.0 4.0 Normal growth

3 3 Lagerstroemia 1 14.5 8.5 Normal growth

4 4 Lagerstroemia 1 26.1 8.5 Normal growth

5 5 Chukrasia tabularis 1 15.3 7.0 Normal growth

6 6 Lagerstroemia 1 14.6 6.5 Normal growth

7 7 Lagerstroemia 1 17.2 6.0 Normal growth

8 8 Lagerstroemia 1 25.5 9.5 Normal growth

9 9 Lagerstroemia 1 22.3 8.5 Normal growth

10 10 Lagerstroemia 1 30.4 10.0 Normal growth

11 11 Lagerstroemia 1 21.0 8.5 Normal growth

12 12 Lagerstroemia 1 19.1 8.0 Normal growth

13 13 Lagerstroemia 1 23.4 9.0 Normal growth

14 14 Lagerstroemia 1 25.0 8.5 Normal growth

15 15 Lagerstroemia 1 19.3 7.0 Normal growth

16 16 Lagerstroemia 1 29.3 8.5 Normal growth

17 17 Lagerstroemia 1 17.7 6.0 Died

18 18 Lagerstroemia 1 19.1 6.5 Died

19 19 Lagerstroemia 1 22.6 11.0 Normal growth

20 20 Lagerstroemia 1 21.3 8.5 Normal growth

21 21 Lagerstroemia 1 25.0 11.0 Normal growth

22 22 Lagerstroemia 1 33.7 11.0 Normal growth

23 23 Lagerstroemia 1 13.4 4.0 Normal growth

24 24 Chukrasia tabularis 1 14.3 7.0 Normal growth

25 25 Lagerstroemia 1 18.6 7.5 Normal growth

26 26 Lagerstroemia 1 20.4 8.0 Normal growth

27 27 Lagerstroemia 1 30.2 8.5 Normal growth

28 28 Lagerstroemia 1 30.6 8.5 Normal growth

29 29 Lagerstroemia 1 21.6 7.5 Normal growth

30 30 Lagerstroemia 1 29.4 8.0 Normal growth

31 31 Lagerstroemia 1 20.4 5.5 Normal growth

32 32 Lagerstroemia 1 21.8 6.0 Normal growth

33 33 Lagerstroemia 1 30.4 6.5 Died

34 34 Lagerstroemia 1 26.3 6.5 Normal growth

35 35 Lagerstroemia 1 20.7 5.5 Normal growth

36 36 Lagerstroemia 1 17.2 5.0 Normal growth

37 39 Lagerstroemia 1 25.5 5.0 Normal growth

38 40 Lagerstroemia 1 20.5 5.0 Normal growth

39 42 Bauhinia 1 18.0 5.0 Normal growth

Page 106: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 99 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

40 43 Pterocarpus macrocarpus

1 15.0 6.0 Normal growth

41 44 Lagerstroemia 1 27.1 5.5 Normal growth

42 45 Lagerstroemia 1 16.6 5.5 Normal growth

43 46 Streblus asper 1 31.8 6.0 Died

44 47 Milkwood pine 1 41.4 7.5 Normal growth

45 48 Milkwood pine 1 26.7 7.0 Normal growth

46 49 Millettia ichthyochtona 1 14.8 5.0 Normal growth

47 50 Lagerstroemia 1 22.3 5.5 Normal growth

48 51 Chukrasia tabularis 1 15.0 5.0 Normal growth

49 52 Millettia ichthyochtona

1 17.5 5.0 Normal growth

50 53 Chukrasia tabularis 1 20.1 5.0 Normal growth

51 56 Lagerstroemia 1 18.8 5.0 Normal growth

52 57 Lagerstroemia 1 14.0 3.5 Normal growth

53 87 Ficus benjamina L 1 89.1 15.0 Normal growth

54 90 Milkwood pine 1 70.0 14.0 Normal growth

55 2-S Milkwood pine 1 31.8 10.0 Normal growth

56 3-S Milkwood pine 1 48.7 11.5 Normal growth

57 4-S Milkwood pine 1 54.4 14.0 Normal growth

58 5-S Milkwood pine 1 56.3 13.0 Normal growth

59 6-S Milkwood pine 1 30.2 11.0 Normal growth

60 7-S Milkwood pine 1 50.3 15.0 Normal growth

61 8-S Milkwood pine 1 64.6 16.0 Normal growth

62 101-S Flamboyant 1 44.2 15.0 Normal growth

63 37 Chukrasia tabularis 1 15.3 4.5 Normal growth

64 38 Millettia ichthyochtona 1 20.2 5.0 Normal growth

65 54 Lagerstroemia 1 21.3 6.5 Normal growth 66 55 Milkwood pine 1 30.9 6.5 Died 67 108 Engelhardtia spicata 1 9.5 7.0 Normal growth

68 109 Engelhardtia spicata 1 19.0 8.0 Normal growth

69 110 Engelhardtia spicata 1 25.0 8.0 Normal growth

70 111 Engelhardtia spicata 1 19.5 4.0 Died

71 113 Engelhardtia spicata 1 24.0 4.0 Normal growth

72 114 Engelhardtia spicata 1 10.5 4.5 Normal growth

73 125 Lagerstroemia 1 30.5 9.0 Normal growth

74 126 Lagerstroemia 1 23.0 8.0 Normal growth

75 127 Lagerstroemia 1 20.0 8.0 Normal growth

76 128 Lagerstroemia 1 26.0 10.5 Normal growth

Page 107: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 100 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

77 129 Lagerstroemia 1 27.5 10.0 Normal growth

78 130 Milkwood pine 1 47.8 10.5 Normal growth

79 131 Milkwood pine 1 41.7 12.0 Normal growth

80 134 Lagerstroemia 1 19.0 9.5 Normal growth

81 135 Lagerstroemia 1 23.0 9.5 Normal growth

82 136 Lagerstroemia 1 38.5 10.0 Normal growth

83 137 Lagerstroemia 1 39.0 10.5 Normal growth

84 39 Alstonia Scholaris 1 36.3 12.5

Permit no. 70/GP-SXD dated 26/072018

85 41 Ficus Benjamina 1 110.1 10.5

86 43

Lagerstreomia speciose 1 15.9 4.5

87 44 Ficus Benjamina 1 88.8 9.5

88 139 Ficus Benjamina 1 20 13.5

III Vertical shaft 8 Permit no. 53/GP-SXD dated 24/7/2017

1 1 Engelhardtia spicata 1 43.4 10.0 Normal growth

2 2 Lagerstroemia 1 23.1 6.0 Normal growth

3 3 Lagerstroemia 1 20.4 6.0 Normal growth

4 4 Lagerstroemia 1 22.3 6.0 Normal growth

5 5 Lagerstroemia 1 21.3 3.0 Normal growth

6 6 Lagerstroemia 1 24.2 8.0 Normal growth

7 7 Lagerstroemia 1 15.3 5.0 Normal growth

8 8 Lagerstroemia 1 17.5 6.0 Normal growth

9 9 Khaya Wood 70.0 12.0 Not yet

10 10 Khaya Wood 89.1 12.0 Not yet

11 11 Khaya Wood 79.6 12.0 Not yet

12 12 Khaya Wood 85.9 12.0 Not yet

IV Small Kim Ma str Renovation 7 Permit no. 41/GP-SXD dated 07/5/2018

1 17 Milkwood pine 1 47.1 8.5 Normal growth

2 18 Milkwood pine 1 52.5 10 Normal growth

3 20 Lagerstroemia 1 28.3 7 Normal growth

4 21 Lagerstroemia 1 20.1 6.5 Normal growth

5 22 Lagerstroemia 1 30.9 8 Normal growth

6 23 Chukrasia tabularis 1 15.3 6 Normal growth

7 24 Ficus microcarpa 1 35 7 Normal growth

8 25 Bucida molinetii 13 6.5 Handed over to Hanoi Green Tree Park at Yen So Arboretum

9 26 Bucida molinetii 13 6.5

10 27 Bucida molinetii 12 6.5

Page 108: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 101 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

11 28 Bucida molinetii 12 6.5

12 29 Bucida molinetii 12 6.5

13 30 Bucida molinetii 11 6.5

14 31 Bucida molinetii 11 6.5

15 32 Bucida molinetii 11 6.5

V Station

10 29 Permit no. 14/GP-SXD

dated 23/01/2018

1 1 Senna 1 19.4 8 Normal growth

2 2 Senna 1 22.9 7 Normal growth

3 3 Cananga Odorata 1 10.2 4 Normal growth

4 4 Engelhardtia spicata 1 43 9 Normal growth

5 5 Engelhardtia spicata 1 32.1 7 Normal growth

6 6 Flamboyant 1 23.2 8 Normal growth

7 7 Senna 1 19.1 7 Normal growth

8 8 Ficus bengalensis 1 70 6 Normal growth

9 9 Lagerstroemia 1 20.2 4 Normal growth

10 10 Milkwood pine 1 25 5 Normal growth

11 12 Lagerstroemia 1 15.9 3 Normal growth

12 13 Flamboyant 1 29.1 7 Normal growth

13 14 Cananga Odorata 1 11.5 5 Normal growth

14 17 Milkwood pine 1 30.6 8 Normal growth

15 18 Cananga Odorata 1 12.1 6 Normal growth

16 19 Cananga Odorata 1 9.5 5 Normal growth

17 20 Flamboyant 1 24.8 5 Normal growth

18 21 Cananga Odorata 1 12.4 6 Normal growth

19 22 Senna 1 15.6 5 Normal growth

20 24 Magnolia × alba 25 5 Normal growth

21 26 Milkwood pine 1 25.5 8 Normal growth

22 27 Cassia fistula 1 10.8 3 Normal growth

23 28 Glyptostrobus pensilis

15.9 5 Normal growth

24 30 Cassia fistula 1 11.1 3 Normal growth

25 31 Plumeria 17.5 3 Relocated by Pullman

Hotel 26 32 Cassia fistula 1 11.1 3 Died

27 34 Cassia fistula 1 9.5 3 Died

28 35 Cassia fistula 1 8 3 Died

29 37 Senna 1 40 7 Normal growth

30 40 Cassia fistula 1 6.4 3 Died

31 42 Cassia fistula 1 6.4 3 Died

Page 109: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 102 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

32 52 Plumeria 19.1 4 Relocated by Pullman

Hotel

33 53 Plumeria 19.1 4 Relocated by Pullman

Hotel

34 54 Plumeria 23.9 4 Relocated by Pullman

Hotel

35 55 Plumeria 26.1 4 Relocated by Pullman

Hotel

36 59 Ficus microcarpa 47.7 3 Relocated by Pullman

Hotel 37 63 Engelhardtia spicata 1 29.6 9 Normal growth

38 64 Barringtonia acutangula

25 6 Relocated by Pullman

Hotel

B CP02 61 Permit no. 35/GP-SXD dated 10/4/2018

I Station 1 1

1 T1 Milkwood pine 1 25.0 8.0 Normal growth

II Station 2 6

1 T1 Milkwood pine 1 17.0 6.0 Normal growth

2 T2 Milkwood pine 1 25.0 7.0 Normal growth

3 T3 Milkwood pine 1 22.0 5.0 Normal growth

4 T4 Milkwood pine 1 30.0 8.0 Normal growth

5 T5 Milkwood pine 1 30.0 8.0 Normal growth

6 T6 Milkwood pine 1 20.0 8.0 Normal growth

III Station 3 13

1 T1 Dracontomelon duperreanum 1 17.0 8.0 Normal growth

2 T2 Dracontomelon duperreanum

1 17.0 8.0 Normal growth

3 T3 Dracontomelon duperreanum

1 17.0 8.0 Died

4 T4 Dracontomelon duperreanum

1 17.0 8.0 Died

5 T8 Milkwood pine 1 38.0 10.0 Normal growth

6 T9 Milkwood pine 1 20.0 6.0 Died

7 T10 Milkwood pine 1 30.0 8.0 Normal growth

8 T11 Milkwood pine 1 25.0 8.0 Normal growth

9 T12 Milkwood pine 1 30.0 10.0 Normal growth

10 T13 Milkwood pine 1 30.0 10.0 Normal growth

11 T14 Dracontomelon duperreanum

1 7.0 5.0 Died

12 T15 Milkwood pine 1 25.0 9.0 Normal growth

13 T16 Milkwood pine 1 25.0 9.0 Normal growth

IV Station 4 18

Page 110: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 103 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

1 T1 Milkwood pine 1 21.0 10.0 Normal growth

2 T2 Milkwood pine 1 22.0 10.0 Normal growth

3 T3 Milkwood pine 1 20.0 10.0 Normal growth

4 T4 Milkwood pine 1 25.0 10.0 Normal growth

5 T5 Milkwood pine 1 30.0 10.0 Died

6 T6 Milkwood pine 1 20.0 9.0 Normal growth

7 T7 Lagerstroemia 1 12.0 5.0 Died

8 T8 Milkwood pine 1 30.0 11.0 Died

9 T9 Milkwood pine 1 20.0 9.0 Died

10 T10 Milkwood pine 1 14.0 7.0 Normal growth

11 T11 Milkwood pine 1 18.0 7.0 Normal growth

12 T12 Milkwood pine 1 25.0 10.0 Normal growth

13 T13 Milkwood pine 1 13.0 6.0 Normal growth

14 T14 Milkwood pine 1 18.0 7.0 Normal growth

15 T15 Milkwood pine 1 23.0 8.0 Died

16 T16 Milkwood pine 1 17.0 6.0 Normal growth

17 T17 Milkwood pine 1 23.0 9.0 Normal growth

18 T18 Milkwood pine 1 25.0 9.0 Normal growth

V Station 5 12

1 T1 Milkwood pine 1 12.0 5.0 Normal growth

2 T2 Milkwood pine 1 24.0 8.0 Normal growth

3 T3 Milkwood pine 1 20.0 8.0 Normal growth

4 T4 Milkwood pine 1 22.0 8.0 Normal growth

5 T5 Milkwood pine 1 18.0 10.0 Normal growth

6 T6 Milkwood pine 1 25.0 10.0 Normal growth

7 T7 Senna 1 10.0 6.0 Normal growth

8 T8 Senna 1 25.0 10.0 Normal growth

9 T9 Senna 1 20.0 10.0 Normal growth

10 T10 Senna 1 28.0 9.0 Normal growth

11 T11 Senna 1 20.0 10.0 Normal growth

12 T12 Senna 1 35.0 10.0 Normal growth

VI Station 6 8

1 T4 Senna 1 25.0 9.0 Normal growth

2 T6 Senna 1 31.0 10.0 Normal growth

3 T8 Senna 1 39.0 8.0 Normal growth

4 T9 Senna 1 35.0 8.0 Normal growth

5 T11 Senna 1 40.0 8.0 Normal growth

6 T12 Senna 1 30.0 8.0 Normal growth

7 T13 Senna 1 30.0 8.0 Normal growth

Page 111: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 104 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

8 T14 Senna 1 36.0 8.0 Normal growth

VII Station 7 1

1 T1 Senna 1 36.0 8.0 Normal growth

VIII Station 8 2

1 T3 Engelhardtia spicata 1 35.0 12.0 Normal growth

2 T6 Lagerstroemia 1 20.0 7.0 Died

C. Permit no. 63/GP-SXD dated 18 August 2016

I. Plants under management of Hanoi Zoo

1 2 Lagerstroemia 1 35 8 Normal growth 2 4 Delonix regia 1 51 12 Normal growth 3 6 Delonix regia 1 32 8 Normal growth 4 8 Lagerstroemia 1 20 5 Normal growth 5 10 Lagerstroemia 1 10 3 Normal growth 6 12 Lagerstroemia 1 25 6 Normal growth 7 14 Delonix regia 1 28 13 Normal growth 8 16 Delonix regia 1 30 12 Normal growth 9 18 Delonix regia 1 25 8 Normal growth 10 20 Delonix regia 1 38 13 Normal growth 11 22 Delonix regia 1 43 13 Normal growth 12 24 Delonix regia 1 53 13 Normal growth 13 26 Delonix regia 1 29 4 Normal growth 14 28 Delonix regia 1 51 14 Normal growth 15 30 Alstonia scholaris 1 12 4 Normal growth 16 32 Delonix regia 1 52 11 Normal growth 17 34 Alstonia scholaris 1 22 7 Normal growth 18 36 Alstonia scholaris 1 32 9 Normal growth 19 38 Alstonia scholaris 1 23 8 Normal growth 20 40 Ficus benjamina 1 20 5 Normal growth 21 42 Alstonia scholaris 1 25 7 Normal growth 22 44 Delonix regia 1 39 9 Normal growth 23 46 Delonix regia 1 42 10 Normal growth 24 48 Delonix regia 1 50 10 Normal growth 25 50 Delonix regia 1 40 11 Normal growth 26 52 Delonix regia 1 35 11 Normal growth 27 54 Delonix regia 1 41 11 Normal growth 28 56 Delonix regia 1 31 10 Normal growth 29 58 Delonix regia 1 40 10 Normal growth 30 60 Delonix regia 1 48 10 Normal growth 31 62 Delonix regia 1 40 10 Normal growth 32 64 Delonix regia 1 51 8 Normal growth 33 66 Lagerstroemia 1 22 8 Normal growth

Page 112: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 105 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

34 68 Mangifera 1 73 12 Normal growth 35 70 Lagerstroemia 1 35 9 Normal growth 36 72 Lagerstroemia 1 17 3 Normal growth 37 74 Lagerstroemia 1 28 8 Normal growth 38 76 Lagerstroemia 1 41 12 Normal growth 39 78 Lagerstroemia 1 16 6 Normal growth 40 82 Lagerstroemia 1 29 11 Normal growth 41 84 Lagerstroemia 1 23 8 Normal growth 42 86 Lagerstroemia 1 33 8 Normal growth 43 88 Alstonia scholaris 1 24 7 Normal growth 44 90 Lagerstroemia 1 29 5 Normal growth 45 92 Alstonia scholaris 1 42 11 Normal growth 46 94 Baccaurea sapida 1 17 4 Normal growth 47 95 Ficus benjamina 1 68 12 Normal growth 48 96 Lagerstroemia 1 27 4 Normal growth 49 97 Lagerstroemia 1 31 8 Normal growth 50 98 Lagerstroemia 1 53 7 Normal growth

51 99 Engelhardtia roxburghiana 1 20 5 Normal growth

52 100 Delonix regia 1 57 12 Normal growth 53 101 Lagerstroemia 1 28 8 Normal growth 54 102 Delonix regia 1 20 5 Normal growth

55 103 Engelhardtia roxburghiana 1 25 6 Normal growth

56 104 Khaya Wood 1 104 16 Normal growth 57 106 Delonix regia 1 33 8 Normal growth 58 107 Delonix regia 1 50 11 Normal growth 59 108 Delonix regia 1 51 11 Normal growth 60 109 Lagerstroemia 1 39 10 Normal growth

II. Plants under management of Greenery Park

61 1 Khaya Wood 1 69 18 Normal growth 62 3 Khaya Wood 1 70 13 Normal growth 63 5 Khaya Wood 1 60 13 Normal growth 64 7 Khaya Wood 1 67 13 Normal growth 65 9 Khaya Wood 1 67 13 Normal growth 66 11 Khaya Wood 1 97 14 Normal growth 67 13 Khaya Wood 1 60 14 Normal growth 68 15 Khaya Wood 1 64 13 Normal growth 69 17 Khaya Wood 1 46 8 Normal growth 70 19 Khaya Wood 1 92 14 Normal growth 71 21 Khaya Wood 1 59 12 Normal growth 72 23 Khaya Wood 1 72 14 Normal growth 73 25 Khaya Wood 1 70 13 Normal growth

Page 113: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 106 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

74 27 Khaya Wood 1 91 14 Normal growth 75 29 Khaya Wood 1 67 12 Normal growth 76 31 Khaya Wood 1 68 13 Normal growth 77 33 Khaya Wood 1 53 11 Normal growth 78 35 Khaya Wood 1 70 12 Normal growth 79 37 Khaya Wood 1 76 13 Normal growth 80 39 Khaya Wood 1 62 10 Normal growth 81 41 Khaya Wood 1 70 12 Normal growth 82 43 Khaya Wood 1 45 11 Normal growth 83 45 Khaya Wood 1 78 11 Normal growth 84 47 Khaya Wood 1 96 12 Normal growth 85 49 Khaya Wood 1 27 4 Normal growth 86 51 Khaya Wood 1 73 12 Normal growth 87 53 Khaya Wood 1 40 8 Normal growth 88 55 Khaya Wood 1 54 12 Normal growth 89 57 Khaya Wood 1 61 12 Normal growth 90 59 Khaya Wood 1 59 14 Normal growth 91 61 Khaya Wood 1 73 12 Normal growth 92 63 Senna alata 1 17 6 Normal growth 93 65 Senna alata 1 43 8 Normal growth 94 67 Senna alata 1 23 8 Normal growth 95 69 Lagerstroemia 1 23 5 Normal growth 96 71 Lagerstroemia 1 10 3.5 Normal growth 97 73 Lagerstroemia 1 25 7 Normal growth 98 75 Lagerstroemia 1 25 5 Normal growth 99 77 Senna alata 1 22 6 Normal growth

100 79 Senna alata 1 25 6 Normal growth 101 81 Senna alata 1 51 10 Normal growth 102 83 Lagerstroemia 1 17 4 Normal growth 103 85 Lagerstroemia 1 18 5 Normal growth 104 87 Delonix regia 1 22 5 Normal growth 105 89 Senna alata 1 33 10 Normal growth 106 105 Khaya Wood 1 83 13 Normal growth D. Permit no. 40/GP-SXD dated 15 June 2017

1 9 Alstonia scholaris 1 25,1 9 Normal growth 2 10 Alstonia scholaris 1 30,6 11 Normal growth 3 11 Alstonia scholaris 1 38,8 11 Normal growth 4 12 Alstonia scholaris 1 37,2 10,5 Normal growth 5 13 Alstonia scholaris 1 38,2 11 Normal growth 6 14 Ficus benjamina 1 93,3 12 Normal growth 7 15 Alstonia scholaris 1 43,6 13,5 Normal growth 8 17 Ficus benjamina 1 84,7 11,5 Normal growth

Page 114: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 107 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

9 18 Ficus benjamina 1 114 13 Normal growth 10 20 Lagerstroemia 1 11,1 4,5 Normal growth 11 22 Ficus benjamina 1 66,5 9 Normal growth 12 23 Ficus benjamina 1 60,8 9 Normal growth 13 25 Ficus benjamina 1 126,7 9,5 Normal growth 14 27 Alstonia scholaris 1 46,5 12 Normal growth 15 28 Ficus benjamina 1 85,6 12,5 Normal growth 16 32 Ficus benjamina 1 111,4 10,5 Normal growth 17 36 Bauhinia purpurea 1 19,1 5 Normal growth 18 39 Alstonia scholaris 1 36,3 12,5 Normal growth 19 40 Alstonia scholaris 1 57 13,5 Normal growth 20 41 Ficus benjamina 1 110,1 10 Normal growth 21 43 Lagerstroemia 1 15,9 4,5 Normal growth 22 44 Ficus benjamina 1 88,8 9,5 Normal growth 23 49 Lagerstroemia 1 15,9 5,5 Normal growth 24 50 Ficus benjamina 1 93,6 11,5 Normal growth 25 51 Ficus benjamina 1 78,3 11 Normal growth 26 52 Ficus benjamina 1 103,8 12,5 Normal growth 27 53 Ficus benjamina 1 60,2 10,5 Normal growth 28 84 Ficus benjamina 1 79,3 10,5 Normal growth 29 85 Alstonia scholaris 1 23,6 7 Normal growth 30 86 Delonix regia 1 27,1 7 Normal growth 31 87 Alstonia scholaris 1 14,6 4 Normal growth 32 93 Bauhinia purpurea 1 15 4 Normal growth 33 94 Alstonia scholaris 1 29,3 10 Normal growth 34 95 Alstonia scholaris 1 25,5 9 Normal growth 35 96 Ficus benjamina 1 43,9 11 Normal growth 36 108 Lagerstroemia 1 24,8 7 Normal growth 37 109 Alstonia scholaris 1 39,5 13,5 Normal growth 38 111 Lagerstroemia 1 35,7 9,5 Normal growth 39 115 Lagerstroemia 1 23,6 6,5 Normal growth 40 116 Elaeis Guineensis 1 20,7 4,5 Normal growth 41 118 Elaeis Guineensis 1 20,7 4 Normal growth 42 119 Lagerstroemia 1 22,3 5 Normal growth 43 120 Elaeis Guineensis 1 22,6 3 Normal growth 44 122 Lagerstroemia 1 26,7 6,5 Normal growth 45 124 Lagerstroemia 1 21,3 5,5 Normal growth 46 125 Elaeis Guineensis 1 25,5 4 Normal growth 47 126 Lagerstroemia 1 26,4 4,5 Normal growth 48 127 Lagerstroemia 1 25,8 5 Normal growth 49 128 Lagerstroemia 1 24,2 5 Normal growth

Page 115: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 108 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Tree status on 30

June 2019

50 129 Ficus benjamina 1 98,7 15 Normal growth 51 131 Lagerstroemia 1 27,4 9 Normal growth 52 133 Lagerstroemia 1 19,7 5 Normal growth 53 134 Lagerstroemia 1 27,1 6,5 Normal growth 54 135 Elaeis Guineensis 1 22,3 3 Normal growth 55 136 Ficus benjamina 1 98,4 11 Normal growth 56 137 Ficus benjamina 1 63,3 10,5 Normal growth 57 139 Ficus benjamina 1 120 13,5 Normal growth 58 140 Lagerstroemia 1 13,7 3,5 Normal growth 59 141 Ficus benjamina 1 126,4 15 Normal growth 60 143 Alstonia scholaris 1 26,7 8 Normal growth 61 144 Alstonia scholaris 1 18,1 7 Normal growth 62 147 Ficus benjamina 1 78,3 14,5 Normal growth 63 148 Ficus benjamina 1 34,7 12 Normal growth 64 149 Ficus benjamina 1 101,9 16 Normal growth 65 152 Ficus benjamina 1 37,2 5,5 Normal growth 66 128-A Elaeis Guineensis 1 21,5 1,5 Normal growth 67 37-A Alstonia scholaris 1 47 12,5 Normal growth

Total A+B+C+D 395

Page 116: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 109 of 158

TREE REMOVAL STATUS

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Note

A. CP03 67

I Ramp zone 25 Permit no. 53/GP-SXD

dated 24/7/2017

1 5 Senna 1 27.7 7.5

2 8 Senna 1 31.2 9.0

3 11 Senna 1 50.0 9.0

4 14 Senna 1 38.2 11.0

5 16 Senna 1 27.7 12.0

6 17 Senna 1 15.9 6.0

7 21 Senna 1 59.5 13.0

8 22 Senna 1 39.8 12.0

9 23 Senna 1 39.8 10.0

10 32 Baccaurea sapida 1 17.8 3.5

11 34 Roystonea regia 1 41.4 14.0

12 36 Roystonea regia 1 46.5 13.0

13 37 Ficus racemosa 1 31.8 11.0

14 38 Palm 1 24.2 13.0

15 38-A Palm 1 24.0 13.0

16 39 Roystonea regia 1 38.8 14.0

17 40 Palm 1 22.6 12.0

18 40-A Palm 1 23.0 12.0

19 40-B Palm 1 21.0 12.0

20 41 Roystonea regia 1 48.7 14.0

21 42 Roystonea regia 1 40.1 15.0

22 43 Flamboyant 1 44.6 14.0

23 57 Senna 1 11.3 3.5

24 72 Cassia fistula L 1 50.6 12.0 Permit no 90/GP-SXD dated 14 Nov 2018 25 73 Khaya senegalensis 1 34.6 8.0

II Station 9 17 Permits no. 53/GP-SXD dated

24/7/2017 and 94/GP-SXD dated 07/11/2017

1 88 Bauhinia purpurea 1 20.7 5.0

2 89 Bauhinia purpurea 1 25.5 7.5

3 1-S Bauhinia purpurea 1 30.2 4.5

4 1-A-S

Broussonetia papyrifera 1 28.1 5.5

5 100-S Bauhinia purpurea 1 20.5 4.5

6 100-A-S Bauhinia purpurea 1 6.7 2.5

7 102-S Bauhinia purpurea 1 15.3 4.0

8 103-S Bauhinia purpurea 1 11.1 4.0

Page 117: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 110 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Note

9 104-S Bauhinia purpurea 1 19.1 5.0

10 105-S Bauhinia purpurea 1 21.5 5.5

11 105-A-S Bauhinia purpurea 1 14.3 4.5

12 106-S Bauhinia purpurea 1 30.2 6.0

13 41 Lagerstroemia 1 16.6 4.0

14 107 Engelhardtia spicata 1 25.5 8.0

15 112 Engelhardtia spicata 1 9.0 3.0

16 132 Broussonetia papyrifera 1

29.3 9.5

17 133 Terminalia catappa 1 40.5 11.0

III Vertical Shaft 0 Permit no. 53/GP-SXD

dated 24/7/2017

IV Small Kim Ma str Renovation 6 Permit no. 41/GP-SXD

dated 07/5/2018

1 9A

Broussonetia papyrifera 1 15.9 8.0

2 9B Ficus microcarpa 1 25.5 6.0

3 11A

Broussonetia papyrifera 1 12.7 7.0

4 11B Ficus microcarpa 1 15.0 4.0

5 12

Broussonetia papyrifera 1 28.7 8.0

6 19 Bauhinia purpurea 1 24.8 4.5

V Station 10 19 Permit no. 14/GP-SXD

dated 23/01/2018

1 11 Senna 1 17.2 7

2 15 Cananga Odorata 1 13.1 5

3 16 Senna 1 19.1 6

4 23 Broussonetia papyrifera 1

11.1 3

5 33 Roystonea regia 1 46.2 11

6 38 Roystonea regia 1 46.2 11

7 41 Roystonea regia 1 47.7 12

8 43 Roystonea regia 1 47.7 12

9 45 Roystonea regia 1 47.7 12

10 47 Roystonea regia 1 47.7 12

11 49 Roystonea regia 1 50.9 12

12 50 Roystonea regia 1 50.9 12

13 51 Roystonea regia 1 50.9 12

14 56 Roystonea regia 1 57.3 12

15 57 Roystonea regia 1 57.3 12

16 58 Roystonea regia 1 57.3 12

Page 118: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 111 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Note

17 60 Terminalia catappa 1 46.2 8

18 61 Roystonea regia 1 47.1 12

19 62 Terminalia catappa 1 42.7 8

B CP02 8 Permit no. 35/GP-SXD dated

10/4/2018

I Station 1 0

II Station 2 0

III Station 3 3

1 T5 Coconut 1 32.0 15.0

2 T6 Coconut 1 32.0 15.0

3 T7 Coconut 1 32.0 15.0

IV Station 4 0

V Station 5 0

VI Station 6 3

1 T5 Senna 1 35.0 6.0

2 T7 Senna 1 37.0 8.0

3 T10 Senna 1 38.0 8.0

VII Station 7 0

VIII Station 8 2

1 T1 Baccaurea sapida 1 7.0 6.0

2 T2 Baccaurea sapida 1 7.0 6.0

C 2 Permit no. 63/GP-SXD dated 18

August 2016

1 80 Lagerstroemia 1 16 3

2 93 Khaya Wood 1 70 10

D Permit no. 40/GP-SXD dated 15 June 2017

50

1 16 Lagerstroemia 1 9,5 3,5

2 19 Fig tree 1 14,6 4 3 21 Fig tree 1 21 4 4 24 Bauhinia purpurea 1 27,1 6 5 26 Bauhinia purpurea 1 34,4 3,5 6 30 Lagerstroemia 1 13,7 4,5 7 31 Bauhinia purpurea 1 23,9 6,5 8 33 Bauhinia purpurea 1 21 4,5 9 34 Bauhinia purpurea 1 36,9 4,5 10 35 Bauhinia purpurea 1 22,6 5,5 11 37 Bauhinia purpurea 1 19 1,5 12 38 Delonix regia 1 51 8,5 13 42 Bauhinia purpurea 1 14 3,5 14 45 Bauhinia purpurea 1 22 4,5 15 46 Bauhinia purpurea 1 26,4 4

Page 119: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 112 of 158

No. Code Tree Q'ty D1,3 (cm)

HVN

(m) Note

16 47 Cây Ficus benjamina 1 30 7 17 48 Bauhinia purpurea 1 35 3,5 18 55 Bauhinia purpurea 1 17,5 5,5 19 56 Bauhinia purpurea 1 29,6 4,5 20 57 Bauhinia purpurea 1 19,7 4 21 58 Bauhinia purpurea 1 25 4 22 59 Bauhinia purpurea 1 26 3 23 60 Bauhinia purpurea 1 31 5 24 62 Morus Alba 1 9,5 3,5 25 63 Bauhinia purpurea 1 25,5 5 26 64 Bauhinia purpurea 1 39,5 5,5 27 65 Bauhinia purpurea 1 29,6 5,5 28 66 Bauhinia purpurea 1 25,5 4,5 29 67 Bauhinia purpurea 1 27 4 30 68 Bauhinia purpurea 1 29 5 31 69 Bauhinia purpurea 1 34,7 4,5 32 88 Bauhinia purpurea 1 19 4,5

33 89 Broussonetia papyrifera 1 26,7 6

34 91 Delonix regia 1 26,4 6,5 35 92 Delonix regia 1 26 6,5 36 97 Delonix regia 1 65,5 14,5

37 107 Broussonetia papyrifera 1 33,7 11

38 110 Delonix regia 1 26 8 39 112 Elaeis Guineensis 1 23 7 40 113 Senna alata 1 35 5 41 114 Elaeis Guineensis 1 21 7 42 117 Senna alata 1 36,3 9,5 43 121 Delonix regia 1 40,4 10 44 123 Elaeis Guineensis 1 20,4 7,5 45 130 Bauhinia purpurea 1 24 5 46 132 Bauhinia purpurea 1 19,4 4

47 138 Broussonetia papyrifera 1 32 9,5

48 142 Bauhinia purpurea 1 23,6 5 49 145 Fig tree 1 24,4 12 50 146 Cassia Fistula 1 59,5 14,5 Total A+B+C+D 127

Page 120: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 113 of 158

Appendix 3: ENVIRONMENTAL MONITORING RESULTS CP03

➢ 1ST QUARTER Monitoring results of noise (dBA)

Vibration monitoring results

Page 121: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 114 of 158

Air quality monitoring results

Surface water quality monitoring results

Soil quality monitoring results

Page 122: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 115 of 158

➢ 2ndQUARTER Monitoring results of noise (dBA)

Vibration monitoring results

Page 123: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 116 of 158

Air quality monitoring results

Surface water quality monitoring results

Soil quality monitoring results

Page 124: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 117 of 158

CP05

Page 125: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 118 of 158

Page 126: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 119 of 158

Page 127: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 120 of 158

Page 128: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 121 of 158

Page 129: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 122 of 158

Page 130: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 123 of 158

Page 131: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 124 of 158

Appendix 4: ENVIRONMENTAL INFORMATION PROVIDED BY PIC IN ITS MONTHLY REPORTS. 1ST SEMESTER 2019

Page 132: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 125 of 158

Page 133: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 126 of 158

Page 134: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 127 of 158

Page 135: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 128 of 158

Page 136: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 129 of 158

Page 137: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 130 of 158

Page 138: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 131 of 158

Page 139: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 132 of 158

Page 140: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 133 of 158

Page 141: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 134 of 158

Page 142: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 135 of 158

Page 143: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 136 of 158

Page 144: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 137 of 158

Page 145: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 138 of 158

Page 146: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 139 of 158

Page 147: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 140 of 158

Page 148: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 141 of 158

Page 149: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 142 of 158

Page 150: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 143 of 158

Page 151: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 144 of 158

Page 152: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 145 of 158

Page 153: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 146 of 158

Page 154: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 147 of 158

Appendix 5: INSTRUCTIONS TO PIC REGARDING ITS SUPERVISION AND REPORTING ACTIVITIES. SPECIFIC REPORT

➢ BACKGROUND

MRB, jointly with PMS2, has detected serious deficiencies in the PIC’s environmental reporting activities. These deficiencies have as a consequence that the information transfer chain from site to MRB and ADB is interrupted at PIC step. After having analyzed the problem and the regulations, the contract’s specifications and the already approved bidding documents, after received complaints from ADB environmental expert and after several working meetings to find the solution to improve this issue, MRB instructs the PIC to strengthen the development of its duties regarding environmental follow up of the works and, as well, improving the content of the periodical reports. The decisions taken have been agreed also with ADB, donor organization that requests the implementation of its Environmental Policy and procedures in this project. ➢ REFERENCES

(i) PIC Time-Based Contract and Appendix B: Reporting Requirements (ii) ADB’s Safeguard Policy Statement (SPS), 2009 (iii) EMP specifications included in the approved EIA – last version 2013

(iv) The current reporting activities carried out by PIC ➢ PIC DUTIES AND RESPONSIBILITIES

According to the reference (i), the PIC’s contract specifies general and particular duties and responsibilities as follows:

1. Chapter No.3. Obligations of the Consultant:

- 3.1.1: “The Consultant shall perform the Services and carry out their obligations hereunder with all due diligence, efficiency and economy, in accordance with generally accepted professional techniques and practices and knowledge by International professional organizations in pursuant with practical conditions of the Project…”

- 3.1.2: “The Consultant shall perform and handle the Services in accordance with the applicable law…”

- 3.1.3: “Assignments of the Consultant shall include, but not limit, the assignments as specified in the Appendix A…”

2. Appendix A, chapter 4:

“In principle, the supervision shall be done following Vietnamese regulations. PIC, with the role of Supervision consultant will be responsible for:

- Quality management…” 3. Appendix B: Reporting Requirements

“The following documentations will be submitted to HRB during supervision of the project.

1. Monthly Progress Report

2. Quality Control Report 3. Safety and Environmental Report… “

According to the reference (ii), and among other defined related specifications, SPS 2009 indicates that “ADB’s project completion reports and project performance evaluation reports include review of the implementation of safeguards.”

According to the reference (iii), it’s clearly stated in the EMP that:

Page 155: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 148 of 158

1. Table 9.8: EMP implementation responsibilities by key donors, project implementers, and agencies. Project Supervision Consultant (PSC) (=PIC): Undertake environmental effects monitoring during pre-construction and

construction phases for depot, viaduct and tunnel components. Undertake environmental training for EMU, HRB/PMU staff as required in the

EMP. Monitor the environmental performance of contractors in terms of

implementation of mitigation measures for pre-construction and construction phase as specified in the EMP.

Monitor over-all implementation of various EMP provisions.

Review and approve the specific environmental management plans (e.g., Spoils Disposal Plan, Dust Control Plan, Noise Control Plan, etc.) to be prepared by contractors as specified in the EMP.

Prepare monthly environmental monitoring reports on EMP implementation. 2. Paragraph 554 – EMP Reporting:

(i) Monthly environmental monitoring reports on environmental performance of contractors: from PSC to HRB/PMU/EMU.

(ii) Quarterly reports on results of environmental effects monitoring and compilation of results of Land Subsidence and Settlement Monitoring Program: from PSC to HRB/PMU/EMU.

According to the reference (iv), the assessment of MRB-PMS2 is clearly unsatisfactory. No specific environmental report was prepared until now and the related chapter included in the monthly progress reports has almost no information regarding the compliance with EMP nor details about the impacts, complaints, implemented measures and pending issues.

Furthermore, the content of the chapter is almost the same for every month since 2018, with same comments.

As Appendix A it’s included an example (PIC’s Monthly Progress Report for June 2019).

➢ ANALYSIS OF PIC PERFORMANCE

1. As PIC has to give compliance with the previous contractual approved documents, such as EIA, It has to be considered that all documentations mentioned in the Time-Based Contract are independent reports, as it’s clearly stated in the EMP.

2. According to ADB’s SPS 2009, paragraph number 16, project performance evaluation reports have to be prepared and have to include an assess about the compliance of the project with the safeguards.

3. Until now, PIC just included a chapter for safety and for environment in their Monthly Reports. No specific monthly and quarterly reports were prepared.

4. The content of these chapters is clearly not enough developed to consider that safety and, especially environmental matters, are well reported to MRB or any other agency or organization that may be interested in following up the construction works under this point of view.

5. There is no environmental specialist mobilized by PIC. Although it may be not specifically included in the specifications of the contract, MRB-PMS2 considers that it’s needed. All projects, national and international, during the construction phase, need the presence of, at least, an HSE Manager and an Environmental Officer to assure the compliance with the law and applicable regulations.

Page 156: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 149 of 158

6. The duties of the PMS2 are focused in checking the results of PIC safety and environmental protection activities and assessments regarding the implementation of the CEMPs by the contractors and, as well, verify the consistency with the real situation on site. So that, all these activities: results, findings, requests to contractors, implemented measures and pending issues, need to be clearly informed by PIC through periodic reports. Until now, there is no evidence about the continuous follow up by PIC specialist of the status of implementation of the CEMPs.

7. It has to be considered, as well, the usual extended procedure in this kind of projects, mainly those under ADB funding, that includes specific environmental and safety monthly and quarterly reports for the Implementing Agency.

➢ MRB INSTRUCTIONS

1º PIC is requested to mobilize enough qualified personnel to give the best service and assure the compliance of its duties and responsibilities.

2º PIC will prepare specific reports as stated in the approved EMP (attached as Appendix C) and its time-based contract, with monthly and quarterly frequency, informing in detail about all the environmental and safety events happened or even expected to happen on site.

These reports will include basic information about the project features, the progress during the month, the staff assigned to environmental and safety supervision (PIC and contractors), the results of PIC supervision on site, assessment of contractors’ reports, assessment of the monitoring data provided by the contractors, requested protection measures to be implemented, status of claims and functioning of the GRM, pending issues, target dates to solve or minimize the arisen impacts, assessment of the compliance with ADB’s SPS 2009, as well as any other matter which could be significant. PMS2, as Project Management Support Consultant, in accordance to its duties informing MRB and giving recommendations for the best possible performance of the project implementation regarding environmental and safety subjects, has prepared an outline template for these reports (attached as Appendix B) which is provided to PIC as guidance. With this template, the correct transfer of the necessary information also when preparing semi-annual and annual reports for MRB and ADB, may be assured. In the general Monthly Progress Report from PIC it will be included a chapter only with the main safety and environmental events happened and activities developed during the period. This report should be prepared at least since August 2019 or, if possible (enough information collected by PIC in July), also a report for this month, as a review of the previous already submitted report for that month. Similar template will be submitted to all contractors in order to prepare homogeneous information since the first step, contractors, and to facilitate PIC the transfer of information to prepare the specific environmental monthly reports,

APPENDIX A: PIC’s MONTHLY PROGRESS REPORT. JUNE 2019. CHAPTER 3

(already included as Appendix 4 in the SEMR No. 4)

APPENDIX B: TEMPLATE FOR MONTHLY ENVIRONMENTAL MONITORING REPORT. OUTLINE

1. Introduction 1.1 Report Purpose 1.2 Project Activities and Implementation Progress The information will be provided through a table, using this template:

Page 157: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 150 of 158

Package Construction activities Start date /

Completion Plan Progress during the

period / Total progress

CPXX - XX - XX

2. Change in Project Scope Such as change in alignment or footprint in case of horizontal infrastructure, implementation of additional Project components and corresponding safeguard measures undertaken, if applicable 3. Summary of PIC’s HSE activity during the period (e.g., site inspection, meeting, training, letter and document issued and received, etc.) 4. Summary of Environmental Mitigation Measures Implemented Based on CEMP and EMP; may include measures related to air quality, water quality, noise quality, pollution prevention, biodiversity and natural resources, health and safety, physical cultural resources, capacity building, and others (e.g., disposal, traffic management plan, etc.). 5. Summary of Environmental Monitoring Environmental Effect Monitoring Results (implemented by the Contractors in the period of the report) should be assessed and summarized. Table of activity carried out by each contractor. 6. Contractor’s and PIC’s HSE Mobilization The information will be provided through a table, using this template:

PACKAGE POSITION CURRENT STATUS

REMARKS PROPOSED APPROVED MOBILIZED NAME

CPXX

Safety Manager

Yes / No Yes / No Yes / No

Environmental Specialist

Yes / No Yes / No Yes / No

HSE staff Yes / No Yes / No (number) HSE Staff Yes / No Yes / No (number)

PIC Safety Manager

Yes / No Yes / No Yes / No

Environmental Specialist

Yes / No Yes / No Yes / No

HSE staff Yes / No Yes / No (number) HSE Staff Yes / No Yes / No (number)

7. Incident records Summary of environmental incidents which happen during carrying out the construction work of the project in the period of the report. Incident report should be enclosed in an appendix. 8. Grievances Intakes Present the environmental grievance received from the affected people and organizations during the period of the report. The previous grievances which has not been closed also should be presented in this item. The closed ones during the period must be also mentioned and explained. The information will be provided through a table, using this template:

No. Date receipt

Subject (noise, cracks…)

Description of thecomplaint

No. affected people/objects

Identity of HH (1)

Actions taken by Contractor

Status of resolution

Remarks Photos (before and after)

1 (1) HH: House Holder

Page 158: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 151 of 158

9. Tree Relocation Plan and Implementation Present the tree relocation status until the period of the report. Status of relocated tree (survival or not, if not please explain the dead time record). The information will be provided through a table, using this template:

No. TREE Quantity D1.3 (cm)

HVN

(m) STATUS OF MAINTENANCE

LOCATION PERMIT REFERENCE

1 Scientific name / local name

10. Assessment of Compliance with the EMP (e.g., non-compliance to loan covenants, EMP and/or government environmental requirements; insufficient mitigation measures to address Project impacts; complaints; incidents; accidents; etc.) 10.1 Key Environmental Issues Identified 10.2 Correction Action Taken 10.3 Additional Action Required This information will be provided through a complete table in which the level of compliance of contractors with the approved EMP is monthly assessed by PIC. The template to be used for that table, to be fulfilled, will be as follows:

No. ENVIR.

ASPECTS

ENVIRONMENTAL COMPLIANCE

AND ISSUES (1) LOCATION

FIRST DATE OBSERVED

CORRECTIVE / MITIGATION

ACTIONS

CURRENT STATUS

1

1. Air quality impacts due to gaseous and dust emissions

- - -

- - -

- - -

- - -

- - -

etc.

(1) List of all specifications contained in the EMP for each aspect 11. Conclusion and Recommendations 12. Appendices 12.1 Photographic report 12.2 Specific Reports (if any) 12.3 Approval/No approval (e.g., new disposals) 12.X (any other significant information) APPENDIX C: ENVIRONMENTAL MANAGEMENT PLAN

(not considered necessary to include in this SEMR No.3)

Page 159: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 152 of 158

Appendix 6: INCIDENT RECORD

Page 160: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 153 of 158

Page 161: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 154 of 158

Page 162: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 155 of 158

Page 163: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 156 of 158

Appendix 7: PROPOSAL OF ENVIRONMENTAL TRAINING COURSE 14 August 2019

Ref: PMS2-MRB-234 To: Mr. Nguyen Cao Minh - General Director Hanoi Metropolitan Railway Management Board (MRB) From: Mr. Jose Carlos Pazos Riaño - PMS2 Tealll Leader TPF Getinsa Euroestudios, S.L - PMS2 Consultant Subject: Proposal of Environmental training course provided by International

Environmental Specialist Project Management Support Consultancy (PMS- Phase 2) under Hanoi Pilot

Light Metro Line, Section Nhon – Hanoi Station Ref: (i) Letter PMS2-MRB-106 dated December 17th, 2018 Proposal for training

course provided by International Environmental Specialist (ii) Letter PMS2-MRB-197 dated 11 June 2019, Proposal of 3rd Mobilization of International Environmental Expert INT-14 (iii) Letter PMS2-MRB-214, dated July 12th, 2019 Proposal of environmental training course provided by International Environmental Specialist

_____________________________________________________________________ Dear Sir, First of all, we would like to express our sincere thanks for your support provided to us so far. Pursuant to Contract No. 02/2018/HD-TV, Appendix A, Terms of Reference, sub-clause 5.5 Training in areas of particular concern to financiers. MoU Donor's review mission April 2019 paragraph. 78 Following our proposal of training under references (i) and (iii) and mobilization of International Environmental Specialist under reference (ii), the Consultant PMS2 would like to propose a training course in areas of particular concerns to financiers (task 2.2) as follows: - Name of training: EIA: process. ADB Policies and Procedures. Differences

compared with Vietnamese Procedures - Training mode: Classroom Training - Time: Three hours, proposed 27/08/2019 - Location: MRB office - Attendee: MRB staffs in charge of environmental issues. All staff concerned

about environmental protection. Project managers and engineers with any responsibility in the implementation of transport projects.

The proposed content of the workshop will be as follows:

i) General concepts about environmental assessment ii) EIA general technical process iii) EIA procedure according to ADB Policy iv) Main Vietnamese environmental Regulations v) EIA procedure in Vietnam vi) EIA procedure in Spain vii) Main differences between ADB, Spain and Vietnamese procedures for EIA

development

Page 164: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 157 of 158

The main expected objective to be achieved is double:

1- on one hand, that the participants increase they concerns about the environmental protection during the whole process of a project implementation and, on the other hand

2- Provide a general framework about the environmental policies that must be applied in ADB funded projects and a basic knowledge about the official procedures to get an environmental permit or approval, as well as basic ideas about the technical process to prepare the main environmental document: EIA. Finally, it will be commented how policies and procedures are included in Metro Line 3 Project, and how the compliance is monitored by ADB and the Implementing Agency, MRB.

If the proposal is accepted, PMS2 will prepare the materials to be distributed in advance to the attendees. Yours sincerely _____________________________________________________________________ TEAM LEADER JOSE CARLOS PAZOS RIAÑO (MR.) TPF GETINSA EUROESTUDIOS, S, L. - SPAIN

Page 165: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 158 of 158

Appendix 8: HPC. DRAFT GUIDELINE FOR ENTITIES PERFORMING REDRESS GRIEVANCES OF ORGANIZATIONS, INDIVIDUALS RELATING TO THE IMPLEMENTATION OF HANOI PILOT LIGHT METRO LINE PROJECT, SECTION NHON – HANOI RAILWAY STATION

HANOI PEOPLE’S COMMITTEE

THE SOCIALIST REPUBLIC OF VIETNAM

Independence - Freedom - Happiness

GUIDELINE

For entities performing redress grievances of organizations, individuals relating to

the implementation of Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi railway

station

(Promulgated with the Decision No. /QD-UBND dated of Hanoi People’s Committee)

CHAPTER I

GENERAL PROVISION

Article 1. Scope of governing

This Guideline provides principle, responsibility, procedure and content to be

coordinated among agencies in dealing with grievances of organizations, individuals relating

to the implementation of Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi

railway station.

Article 2. Regulated entities

This Guideline applies to: City Citizen Reception Board, City Inspectorate, Hanoi

Metropolitan Railway Management Board (MRB), People’s Committee of Districts: Bac Tu Liem, Nam Tu Liem, Cau Giay, Ba Dinh, Dong Da, Hoan Kiem, and relevant entities.

Article 3. Principle of coordination

On basis of State management functions, being promulgated by the Laws and

decentralization of Hanoi People’s Committee (HPC), the relevant entities shall have responsibility to redress the grievances of organizations, individuals as per its authority.

Relevant entities shall have responsibility to proactively coordinate in redress such

grievances on basis of its tasks, powers and the consistent instruction of Hanoi People’s Committee (HPC).

CHAPTER II

COORDINATION CONTENT

Article 4. Mode of coordination.

The entities have responsibility to regularly coordinate with MRB, assign 01 Leader

in charge and 01 staff to follow up with grievances relating to Hanoi Pilot Light Metro Line

Project, section Nhon – Hanoi railway station.

Prior to 25th monthly, relevant entities shall send the summarization on results of

receiving and resolving complaints to MRB for summarizing, reporting the result to HPC,

public on MRB’s website and inform to the Donors. The coordination shall under the authority of each entity, and ensure to be in the right

process, in the time limit for redress as stipulated by the Laws.

Article 5. Content to be coordinated

1. Coordinate to receive, process, discuss, and provide information

Page 166: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 159 of 158

2. Coordinate in propaganda, dissemination “Guideline for entities performing redress grievances of organizations, individuals relating to the implementation of

Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi railway station” to citizen, organizations.

3. Coordinate in sharing result of grievance redress

4. MRB shall regularly organize periodic meeting quarterly.

5. Other contents shall be in compliance with the Laws.

Article 6. Method for coordination.

1. Discussions, forwarding grievances, providing information can be performed in

writing, by email, direct phone call, facsimile and texting.

2. Periodic meeting will be organized quarterly

3. Conferences for sum-up partially and review the implementation of the Guideline.

4. Update, sharing information on the database.

5. Monthly reporting to MRB by relevant agencies, and to Ha Noi People's

Committee and project financiers by MRB.

Article 7. Responsibility of entities in coordination.

1. Hanoi Metropolitan Railway Management Board (MRB)

a) Receive complaints, petitions sent by organizations, individuals, District People’s Committees, City Citizen Reception Board.

b) Deal with those complaints, petitions relating to construction works, environment

and safety issues.

c) Forward to competent authorities the grievances of organizations, individuals

which its contents beyond the power and authority of MRB and monitor the

resolution process.

d) Coordinate with relevant entities to establish the database on Project grievance

management.

e) Be the focal point to summarize, report to HPC monthly, to the Donors on

receiving and dealing with grievances relating to Hanoi Pilot Light Metro Line

Project, section Nhon – Hanoi railway station.

f) Organize quarterly meetings with the District People's Committees and City

Citizen Reception Board on the progress and issues of complaints settlement.

2. District People’s Committee

a) Receive complaints, petitions sent by organizations, individuals, City Citizen

Reception Board, MRB.

b) Deal with those complaints, petitions relating to land acquisition, compensation

and resettlement issues.

c) Forward to competent authorities the grievances of organizations, individuals

which its contents beyond the power and authority of District People’s Committee, follow up with the redress process, summarize the result.

d) Manage the Project grievance data

e) Summarize the result of receiving, dealing with grievances and send to MRB for

summarizing prior to 25th monthly.

3. City Citizen Reception Board

a) Receive complaints, petitions sent by organizations, individuals, MRB and District

People’s Committee. b) Deal with those complaints, petitions relating to the result of 1st redress done by

MRB and District People’s Committee.

Page 167: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 160 of 158

c) Forward the grievances of organizations, individuals to MRB if its contents

relating to construction, environmental and safety issues and to District People’s Committee if its contents relating to land acquisition, compensation and

resettlement issues for dealing under such entity’s power and authority. d) Manage the Project grievance data

e) Summarize the result of receiving, dealing with grievances and send to MRB for

summarizing prior to 25th monthly.

CHAPTER II

COORDINATION CONTENT

Article 8: Implementation arrangement.

City Citizen Reception Board, City Inspectorate, Hanoi Metropolitan Railway

Management Board (MRB), People’s Committee of Districts: Bac Tu Liem, Nam Tu Liem, Cau Giay, Ba Dinh, Dong Da, Hoan Kiem, and relevant entities have responsibility to

implement this Guideline.

Article 9. Funding for implementation

Agency in charge of the task will use its own budget to perform the work as per the

Laws.

Article 10. Amendment, supplementation

During the implementation of this Guideline, in case of any difficulties or obstacles

arise, the agencies shall inform to MRB for summarize and report to HPC for review and

amendment accordingly.

c.c.

- FOR CHAIRMAN

VICE CHAIRMAN

(signed and sealed)

Nguyen The Hung

Page 168: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 161 of 158

APPENDIX 1

Monthly summarization on implementation of coordination mechanism in grievance redresses

relating to the implementation of Hanoi Pilot Light Metro Line Project, section Nhon – Hanoi

railway station

(Promulgated with the Decision No. /QD-UBND dated of Hanoi People’s Committee)

1. Receiving grievance

Total grievances received:

- Numbers of grievances under the authority to deal with:

……………………………………………………………………………………………………

- Numbers of grievances forwarded to other agencies:

+ To Hanoi Metropolitan Railway Management Board

……………………………………………………………………………………………………

+ To District People’s Committee

……………………………………………………………………………………………………

+ To City Citizen Reception Board

……………………………………………………………………………………………………

2. Result of redress

2.1. Numbers of grievances redressed in the month

No Full name of

complainant Address

Content of

complain

Redress

result Note

1

2

2.2. Numbers of grievances under redress process

No Full name of

complainant Address

Content of

complain

Redress

result Note

1

2

3. Numbers of overdue grievances

No Full name of

complainant Address

Content of

complain

Redress

result Note

1

2

4. Reasons of overdue and solutions

………………………………………………………………………………………

5. RECOMMENDATIONS, PROPOSAL (if any)

Page 169: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 162 of 158

APPENDIX II

SUMMARY OF PROCESS FOR RECEIVING, DEALING WITH GRIEVANCES

RELATING TO THE IMPLEMENTATION OF HANOI PILOT LIGHT METRO

LINE PROJECT, SECTION NHON – HANOI RAILWAY STATION

(Promulgated with the Decision No. /QD-UBND dated of Hanoi People’s Committee)

I. PROVISIONS ON GRIEVANCES

1. Grievance shall be written in Vietnamese, clearly state the date of writing; full name,

address, signature or press fingerprint of such grievance writing person. The grievance shall

clearly state name, address of agency, organization, entity, individual to be complained, the

content and reason for complaining and request of the complainant.

2. If the grievance relating to land acquisition, compensation, resettlement issue, the

complainant shall be named in the Decision on land acquisition, compensation, resettlement. If

the complainant is a representative of a group of people to perform their right to complain, such

complainant shall have a power of attorney of such group of people to perform the complaint

(enclose to the origin signature) as per the Laws.

II. PROCESS FOR 1st GRIEVANCE REDRESS

Step 1. Receiving a grievance

Complainant sends a grievance and relevant documents (if any) to the receiving entity (address

of the receiving entity is available in Appendix III)

If the grievance is not under the jurisdiction of the receiving entity, the receiving entity shall

transfer the grievance to the competent authority for settlement and notify in writing the

complainant of such transfer of the grievance.

The entity being transferred the grievance shall notify in writing the forwarding entity and

complainant that the grievance was received and expected date for response such grievance.

Step 2. Accepting and settling a grievance

Within 10 days since a grievance under its own authority is received, MRB, District People’s Committee, or City Citizen Reception Board shall accept and notify the complainant in writing

on the acceptance for settlement; in case a grievance is not accepted, the complainant shall be

notified and the reason for not accepting such grievance shall be clearly stated.

Step 3. Verifying the content of a grievance.

If it is necessary to verify the content of a grievance, the verification shall follow the Article 29,

Law on Complaint, Section 2, Chapter II of Circular No. 07/2013/TT-TTCP dated 31/10/2013

of Government Inspectorate promulgating procedure for settling complaint. The verification

duration shall not be exceeded 30 days.

Step 4. Organize dialogs with the complainant

If necessary MRB, District People’s Committee will organize dialogs with the complainant, the complained people and entities to clarify the content of grievance.

Step 5. Issuance of a decision on grievance settlement

MRB, District People’s Committee shall issue a decision on grievance settlement within 03 working days since the acceptance of a grievance and send the decision on grievance settlement

to complainant, and complained people, entities.

In case the complainant disagrees with decision on grievance settlement of MRB, District

People’s Committee, the complainant is entitled to send 2nd grievance to Hanoi People’s Committee (via City Citizen Reception Board) or institute an administrative lawsuit at court in

accordance with the Laws.

Page 170: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi

Station Section)

Ref: PMS2_MRB_SEMR_21.03_ver 04 Page 163 of 158

II. PROCESS FOR 2nd GRIEVANCE REDRESS

Step 1. Receiving a grievance

2nd time complaint under the competent of chairperson of city-level People’s Committee following Article 20, 21 of Law on Complaint, Complainant sends a grievance enclosed with a

copy of Decision on 1st grievance settlement (via City Citizen Reception Board)

Step 2. Accepting and settling a grievance

Within 10 days since a grievance is received, City Citizen Reception Board shall accept and

notify the complainant in writing on the acceptance for settlement; in case a grievance is not

accepted, the complainant shall be notified and the reason for not accepting such grievance shall

not be clearly stated.

Step 3. Verifying the content of a grievance.

During redress process for the 2nd grievance, competent agency shall on the basis of the content,

nature of grievance to undertake verification, conclude the content of grievance. The verification

shall follow the Clause 2, 3, 4 Article 29, Law on Complaint, Section 2, Chapter II of Circular

No. 07/2013/TT-TTCP dated 31/10/2013 of Government Inspectorate promulgating procedure

for settling administrative complaint. The verification duration shall not be exceeded 30 days.

Step 4. Organize dialogs with the complainant

During redress process for the 2nd grievance, competent agency will organize dialogs with the

complainant, the complained people and entities to clarify the content of grievance.

Step 5. Issuance of a decision on grievance settlement

Chairperson of City People’s Committee shall issue a decision on grievance settlement within 07 working days since the acceptance of a grievance and send the decision on grievance

settlement to complainant, and complained people, entities (including the first-time complaint

settler and the agency that has forwarded the complaint).

In case the complainant disagrees with decision on grievance settlement of City People’s Committee, the complainant is entitled to institute an administrative lawsuit at court in

accordance with the Laws.

Page 171: Environmental Monitoring Report · 2020-03-25 · environmental specialists, MRB technical staff and ADB environmental expert. 1Implementation commenced in 2010 with initial works

Package CS1: Consulting Services for Project Management Support

(Phase 2) under Hanoi Metro Rail System Project (Line 3: Nhon –

Hanoi Station Section)

Ref: PMS2_MRB_SEMR_21.02_ver 01 Page 164 of 158

APPENDIX III

LIST OF LEADERS AND OFFICERS RESPONSIBLE FOR RECEIVING AND SETTLING COMPLAINTS RELATED TO THE

IMPLEMENTATION OF THE PILOT URBAN RAILWAY LINE PROJECT - NHON-HA NOI STATION SECTION

No. Name of agency

Full name of person in

charge

Position Phone

number Email Note

1

Hanoi Metropolitan

Railway

Management Board

2 Ba Dinh District

People’s Committee

3 Hoan Kiem District

People’s Committee

4 Dong Da District

People’s Committee

5 Bac Tu Liem District

People’s Committee

6 Residents Receiving

Unit of Hanoi City


Recommended