Environmental Monitoring Report Semestral Report July 2013
PRC: Kunming Qingshuihai Water Supply Project Prepared by Kunming Municipal Government for the People’s Republic of China and the Asian Development Bank.
1
Kunming Qingshuihai Water Supply Project
Technical Report of Environment Monitoring
(AUGUEST 2012 –JUNE 2013)
Yunnan University
AND
Xishan District Environmental Monitoring Institution, Kunming
July, 2013
2
Content
1. INTRODUCTION ...................................................................................... 1
1.1 Project Background ............................................................................ 3
1.2 Project Summary ................................................................................ 4
1.3 Project Components ............................................................................ 5
1.4 Project organization structure ............................................................. 7
1.5 Implementation of Environment Monitoring Program ...................... 9
1.6 Implementation of Environmental Responsibility Scheme .............. 10
2. PROGRESS ................................................................................................ 1
2.1 General Progress ................................................................................. 1
2.2 Project Progress .................................................................................. 1
3. IMPLEMENTATION OF ENVIRONMENTAL PROTECTION PROGRAM
......................................................................................................................... 1
3.1 Targets of Environment Management Program ................................. 1
3.2 Implementation of Mitigation Measures ............................................ 1
3.3 Information Disclosure ....................................................................... 6
3.4 Implementation of Staff Training ....................................................... 6
4. ENVIRONMENTAL MONITORING ..................................................... 21
4.1 Monitoring of water quality .............................................................. 21
4.2 Clean-ups of the camps upon completion of the construction ......... 28
5. CONCLUSION AND ADVICE ............................................................... 31
5.1Conclusion ......................................................................................... 31
5.2 Advice ............................................................................................... 32
Appendix:Photos of Construction Sites
Attachment: Monitoring Report (K.X.H.J.Z[2013] No. 398)
3
1. Introduction
1.1 Project Background
The purpose of the Kunming Qingshuihai Water Supply Project
(hereinafter referred to as “The Project”) is to ease the recent tension of water
supply in Kunming. It plans to divert 104 million cubic meter water from the
Xiao Jiang River basin in Dongchuanying of Xundian County in northern
Kunming to the Jinzhongshan reservoir in Songming County, serving as water
supply for the New Airport Development Zone and the East Development Zone.
On December 3, 2004, KMG gave its consent to the implementation fo the
Project through K.Z.F.[2004] No.61 Written Reply on Planning Report of
Kunming Water Supply Project, thereafter, China Water Conversation and
Hydropower Science academy and Yunan Provincial Water Conservation and
Hydropower Investigation and Design Institute conducted the Environment
Impact Assess for the Project.
The projected construction duration of the Project is five and half years
(from early 2008 to June 2013). The Environmental Impact Assessment Report
on the Project (hereinafter referred to as “EIA”) requires environmental
monitoring during the entire construction and operational period, mitigation of
the impact on the project affected area, examination of the effectiveness of
applied mitigation measures, and prompt adjustments of responding measures
based on analytical results of monitoring reports.
In June of 2010, the Kunming Water Supply Group Qingshuihai Water
Sources Development and Construction Branch Company(hereinafter calls as
"the Employer”) contracted Yunnan University to prepare the Environment
Monitoring Report for the Project during the construction period. As of
February of 2012, Yunnan University has Subcontracted with Kunming Xishan
4
District Environmental Monitoring Institute (XEMI) to conduct five times of
environment monitoring on construction activities from the year of 2010 to
2012 (twice per year for the year 2010 and 2011, once in the first half of 2012)
and it has submitted the Environmental Monitoring Report to the Employer.
Based on monitoring results, the Employer informed contractors to make
rectifications within a certain time limit regarding environmental issues during
construction period. Therefore, the environmental impacts during the
construction period have been effectively minimized.
Because the Project was basically completed in July of 2012, all
management responsibilities of reservoirs, water conveyance facilities as well
as related equipments was transferred to the new established project operation
unit—Kunming QingYuan Water Supply Co., Ltd. Therefore, this report is
mainly about the monitoring of the environmental recovery after completion of
the Project. Based on the site surveys and by combining Technical Report of
Monitoring for Kunming Qingshuihai Water Supply Project (from 2010 to
2012), and the monitoring report of May of the year 2013, make a assessment
on the environmental restoration after completing the project. According to the
analysis of previous monitoring reports, we provide corresponding improving
suggestions. This report will provide a theoretical context for further
minimizing environmental impact of project construction.
1.2 Project Summary
The basic information about the Project Loan is provided in Table 1-1.
Table 1-1: Basic Information
ADB Loan No. : 2388-PRC Project Title : Kunming Qingshuihai Water Supply
Project Borrower : Ministry of Finance, People’s
5
Republic of China Executing Agency : Kunming Municipal Government Implementing Agency : Kunming Water Supply Group
Company Limited Total Estimated Cost : $255.94 million ADB Loan Amount : $80 million Date of ADB Board Approval : 12 December 2007 Date of Signing of Loan Agreement : 26 March 2008 Date of Loan Effectiveness : 20 June 2008 Original Loan Closing Date : 31 December 2013 Revised Loan Closing Date : N/A Date of Signing of Implementation Consulting Contract
: 17 February 2009
Date of Start of Implementation Consulting Services
: 1 March 2009
Type of This Monitoring Report : The sixth Progress Report Period Covered by This Progress Report
: 1 August 2012 – 30 June 2013
1.3 Project Components
The Project comprises the diversion of water from 4 locations on the upper
reaches of tributary streams to the Xiaojiang River. The Project consists of the
water sources component and the conveyance works component:
A:Water sources component
The water sources component includes six dams of Shiqiaohe river,
Banqiaohe river, Xintianhe river, Tabizi Spring and Jinzhongshan. Water will
be transferred through a network of tunnels and channels to the Qingshuihai
reservoir. From Qingshuihai reservoir, the water will be transferred through a
combination of pipes and tunnels to two existing reservoirs. The main receiving
reservoirs will be the existing Jinzhongshan Reservoir (to be enlarged by a new
dam, about 600 m upstream from the old dam in Songming County) and
Songhuaba Reservoir (an existing reservoir) to the north / northeast of the
6
present Kunming City. Specifications for these planned works are shown in
Table 1-2.
Table 1-2 Summary of Reservoir Works
Item Unit Dam
Qingshuihai Banqiao River
Shiqiao River
Xintian River
Jinzhongshan Reservoir
Location Xundian County
Baizai River
Xundian County
Banqiao River
Xundian County
Shiqiao river
Xundian County
Xintian River
Guandu District
Duilong RiverCatchment Area km2 34.5 102.0 26.6 56.6 23.4 Average Annual
Run-off m3 24,700,000 81,740,000 18,530,000 41,980,000 9,770,000
Total Storage m3 154,170,000 2,515,000 1,835,000 9,600,000
Preferred Dam type Earth Earth Concrete Gravity
Concrete Gravity Earth
Foundation Sandy, Clay Lacustrine formation
Basalt Basalt Mudstone/ Shale Basalt
Seismic Classification
(Intensity) Class VIII VIII VIII VIII VIII
Dam Height m 13 61.5 29 28.9 39.7
Crest Length m 206.2 133.7 81 67.5 111
B:Water conveyance works
The water conveyance system will be operated by gravity, through tunnels
and pipes to the Tongxin Gate. At Tongxin Gate the regulated flow from
Qingshuihai can be split for discharge into Songhuaba Reservoir and
Jinzhongshan Reservoir.
The tunnel and pipeline works are shown in Table 1-3.
Table 1-3: Water Conveyance Works
Section Tunnels Length (km)
Aqueducts/Channels Length (km)
Total km
Shiqiao Dam to Qingshuihai 13.92 0 13.92 Banqiao Dam to
Qingshuihai 2.4 0 2.4
Qingshuihai to Tongxin diversion gate 36.97 6.15 43.12
7
Tongxin diversion gate to Jinzhongshan Reservoir 5.04 2.56 7.6
Tabizi diversion gate to Qingshuihai Reservoir _ 5.7 5.7
The Project submerged six roads near reservoirs; two of them had been
rehabilitated, while the rest four roads will be the subject of compensation to
local government, as shown in Table 1-4.
Table 1-4: Road Works Qingshuihai Qingshuihai Qingshuihai Qingshuihai
Qingshuihai Haiwei to Management 3.8 4 Holiday village road 2.3 Compensate Qinghai to Haiwei 3.3 4.4
Sub-total 9.4 8.4 Jinzhongshan Reservoir
Laobao to Deshi 4 Compensate
Xintian Reservoir
Rural road 3.5 Compensate
Banqiao Reservoir
Rural road 4.2 Compensate
1.4 Project organization structure
Figure 1-1: Schematic Organization Structure for the Project
8
Note:
a) PLG membership: Kunming Development and Reform Commission, Kunming Finance Bureau, Kunming Water Bureau, Kunming Municipal Government Administration, Kunming Construction Bureau, Environment Protection Bureau, Planning Bureau, Water Supply Group, Land and Resources Bureau, Resettlement Bureau, Public Utility Bureau, New Airport Management Commission, Forest Administration Bureau, Reservoir Dianchi Administration Bureau, Songming County, Xundian County, and Guandu District.
b) PMO: fourteen full-time staff on administration (6), engineering / technical (5), and accounting / finance (3). c) IA: KWSG Qingshuihai Water Source Development and Construction Branch will be the project implementing unit responsible for project management and operations, implementation of resettlement, and environmental monitoring.
The Kunming Municipal Government (KMG) is the Executing Agency for
the Project. The Project Leading Group (PLG) has been set up, with the
responsibility of policy guidance and high-level coordination during
implementation. Headed by the Vice Mayor, the PLG comprises representatives
9
from the Kunming Financial Bureau, Kunming Development Reform
Commission, related agencies, and county governments. The PLG meets as
required and will be maintained until project completion.
The PMO has been established within Kunming Development and Reform
Commission. It serves as the secretariat for the PLG and is responsible for
coordinating the implementation of project activities. The specific duties of the
PMO include: (i) ensure adequate interdepartmental cooperation and
interagency coordination, (ii) monitor the progress of project implementation,
and (iii) coordinate communication and interaction among ADB, KWSG and
agencies concerned.
The IA is Kunming Water Supply Group Co. Ltd. (KWSG), which is a
limited liability company incorporated under the 2004 PRC Company Law. The
KWSG is responsible for operating and managing project facilities, direct daily
project management, construction supervision, preparation of progress reports
to the PMO for submission to ADB, and strategic planning for water supply and
management services and operations. KWSG is well organized, with experience
of implementing World Bank and JBIC loan projects. A project implementation
unit (PIU) has been established in the KWSG and is responsible for undertaking
detailed implementation activities. KWSG will retain the services of design
institutes, procurement agencies, and construction supervision companies to
assist with implementation activities.
1.5 Implementation of Environment Monitoring Program
Internal environmental monitoring consists of two types. The first type
requires field sampling and lab analysis that is undertaken by a licensed
environmental institute, for such environmental parameters as water quality, air
quality and noise levels. The second type refers to visual inspections of such
10
things as soil erosion, restoration of vegetation, solid waste disposal and so on.
The field sampling and lab analysis has been conducted, according to the
environmental monitoring program as stipulated in the SEIA, by the Xishan
District Environmental Monitoring Institution (XEMI) under contract to the IA.
Field inspections have been undertaken by the on-site environmental engineer
of the contractor, Environmental Management Office(EMO)officers and
PMO officers on a regular basis.
External monitoring is undertaken by Kunming Xishan District
Environmental Monitoring Institution. Yunnan University is responsible for
reports preparation, and responsible for advising the PMO, IA and construction
contractors on the environmental protection in construction activity.
The implementation status of the environmental monitoring program, as
proposed in the SEIA, is presented in the right column of the Table 1-5. The
detailed results of field sampling and lab analysis are presented in the ensuing
chapter. In summary, the environmental monitoring program has to date been
implemented properly.
1.6 Implementation of Environmental Responsibility Scheme
An environmental management system, consisting of inspection,
monitoring, reporting, and initiating corrective actions or measures, was set up
prior to project implementation. In the design stage, PMO and IA passed the
EMP to the design institutes for incorporating mitigation measures into the
detailed designs of each subproject. The EMP was reviewed and confirmed at
the end of the detailed design, and was finally passed to selected contractors. To
ensure that contractors will comply with the EMP’s provisions, PMO and IA
prepared and provided the following specification clauses for incorporation into
the bidding documents: (i) a list of environmental items to be budgeted by the
11
bidders in their proposals; and (ii) environmental clauses for contract conditions
and specifications.
An EMO was established by the IA prior to the start of the project
implementation. It is charged with the responsibility of coordinating and
supervising the EMP implementation. The EMO is headed a deputy general
manager of the IA. The IA has also recruited an environmental officer who also
serves as the focal point for grievance redress. Meanwhile, the PMO has drawn
the expertise from the Kunming environmental protection bureau in supervising
the environmental management system.
Yunnan University has contracted the Environmental Protection
Monitoring Station of Xishan District of Kunming (hereinafter referred to as
Xishan Institution)to conduct one environmental monitoring in The first half
of 2013. The results of the monitoring were shown in chapter five. The
implementation of the environmental responsibility scheme is shown in Table
1-6.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
12
Table 1-5 Implementation Status of Environmental Monitoring Program
Item Parameters Location Time and Frequency Implementing Agency
Supervising Agency Implementation Status
A. Construction 1. Work camp domestic wastewater quality
pH, SS, DO, NH3-N, TP, BOD5, COD, total coliform, oil
Internal monitoring will be conducted at all construction sites and domestic wastewater discharge area. External monitoring will be conducted at 24 camp sites
Random spot check of the domestic wastewater effluent sites One sampling each day each time, twice per year including once in dry season and once in rainy season
Internal monitoring: contractors, IA /environmental supervisor External monitoring: licensed EMC
IA KEPB
Monitoring has been conducted subject to the plan during construction period and the project has been completed without domestic sewage drainage from camps.
2. Construction wastewater and wastewater pollution mitigation measures
pH, SS, oil Internal monitoring will be conducted at all construction sites. External monitoring will be conducted at 24 sites
Random spot check of the wastewater effluent sites One sampling each day each time, twice per year
Internal monitoring: contractors, IA/environmental Supervisor External monitoring: licensed EMC
IA KEPB
Monitoring has been conducted subject to the plan during construction period and the project has been completed without sewage from construction sites.
3. Water quality of receiving water body Water source protection measures
pH, SS, DO, TP, NH3-N, BOD5, COD, total coliform, oil
Internal monitoring will be conducted at all construction sites. 200 m downstream of the dam of BQR, SQR, XTR, TDP, and the confluence of BQ river and XT river
Random spot Checks One sampling each day each time, twice per year
Internal monitoring: contractors, IA/environmental Supervisor External Monitoring licensed EMC
IA KEPB
Receiving water body was conducted by Xishan District Environmental Monitoring Institution and the monitoring results are shown in Chapter 5.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
13
Table 1-5 (continued) Item Parameters Location Time and
Frequency Implementing
Agency Supervising
Agency Implementation Status
4. Construction workers’drinking water source
Hardness, Mn, Fe, CC14, fecal coliform, sulfate,nitrate, residual chlorine
Drinking water source areas or water supply
Random spot Checks One sampling each time, once a year
Internal monitoring: contractors, IA/environmental Supervisor External Monitoring licensed EMC
IA KEPB
Monitoring has been conducted subject to the plan during construction period and the project has been completed. Personnel who were preparing documents in the camps used running water.
5. Air All the air pollution prevention measures
Use of dust shrouds, water spraying Maintenance and condition of vehicles and equipment. TSP, SOx, NOx
Internal monitoring will be conducted at all construction sites and nearby villages. External monitoring will be conducted at 14 sites: Haiwei, Xiniutang, Ma'anshan, Hujing, Laohaitou, Xiatuoqi, Enjia, Luoduo, Niuluzhuang, Zhujiaying, Taohua’an, Qumiao, Xiaobeidang, Gegentang
Spot check of construction sites Once per year at Peak construction period, two samplings 1 day at each location each time
Internal monitoring: contractors, IA /environmental Supervisor External Monitoring licensed EMC
IA KEPB/XEPB
As the project has been completed, monitoring of ambient air quality was not conducted this time.
Table 1-5 (continued)
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
14
Item Parameters Location Time and Frequency Implementing Agency
Supervising Agency Implementation Status
6. Noise Noise pollution control measures
Leq (dB[A))
Same locations as air quality monitoring
Random, but at least once monthly, 1day each time and two samples each day: once during daytime, once during nighttime Random, but at least once a year, 1 day each time and two samples each day: once during daytime, once during nighttime
Internal monitoring: contractors, IA /environmental Supervisor External Monitoring licensed EMC
IA KEPB/XEPB/ SEPB
As the project has been completed, monitoring of ambient sound quality was not conducted this time.
7. Xundian fish
Behavior and location of spawn sites of Xundian fish
Qingshuihai reservoir First 5 years, from April to June.
External monitoring: Fishery Research Institute
KEPB KEPB
The 2010 fish ecology survey didn’t find the Xundian white fish (Anabarilius xundianensis) in the water of Qingshuihai, and as the project has been completed no further inspection is conducted.
Note: the above progress as the deadline to June 30, 2013。
BOD5 = 5-day biochemical oxygen demand, CCl4 = carbon tetrachloride, CODcr =chemical oxygen demand , DO = dissolved oxygen , Fe = iron, Leq = equivalent continuous noise level, Mn =manganese, NH3-N = ammonia nitrogen, NOx = nitrogen oxides, Q&S = quarries and spoil sites, Rd =roads, SOx = sulfur oxides, SS = suspended solids, T&P = tunnels and pipelines, TP = total phosphorus, TN =total nitrogen,TSP = total suspended particles,
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
1
Table 1-6 Fulfillment of Environmental Responsibilities Phase Agencies Environmental Responsibilities Status of Fulfillment
Preparation
Environmental Institutes KMG, YPG
Preparation of EIA for Project and other project documentation such as SEPP and Strategic Environmental Assessment Review and approval of project documentation, and water permit, SEPP
Fulfilled.
PMO, SEPA
Review and approval of the EIA and EMP Fulfilled.
ADB, PMO
Review and approval of the SEIA including the EMP Fulfilled.
Design DI
Updating the EMP in cooperation with environmental institutes, and incorporating mitigation measures in engineering detail designs and contracts
EMPs were reviewed and no update was necessary. The mitigation measures were incorporated into the detailed engineering designs.
PMO,KWSG Review and approval of environmental measures Fulfilled.
Tendering
PMO, contractors, KWSG Incorporating EMP clauses in the bidding documents The mitigation measures were incorporated into the tendering documents and construction contracts.
Construction
PMO, KWSG, KEBP, county EPBs
Advising on implementation of mitigation measures Fulfilled.
Contractors
Implementation of mitigation measures Fulfilled.
KWSG Internal inspection and monitoring Fulfilled.
KEPB, county EPBs
External monitoring and inspection of implementation of mitigation measures.
Fulfilled.
Operation KWSG
Implementation of mitigation measures Internal environmental monitoring and inspection
Not yet due.
KEPB, county EPBs
Periodical and random environmental monitoring and inspection of environmental compliance
Not yet due.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
1
2. Progress
2.1 General Progress
As of June 30th, 2013, except Civil Works Contract Package No.16, all
other parts of the Project have been completed and accepted. Reservoirs, water
conveyance facilities as well as related equipments had all been transferred to
the project operation unit—Kunming QingYuan Water Co., Ltd.
The Civil Works Contract Package No.16 is not accepted because its
concrete lining works of 1# Adit of Tongxin Tunnel has not been completed,
which is expected to be completed in the middle of July.
2.2 Project Progress
It has been mentioned in the Technical Report (2012) of Monitoring for the
Project that in April 2012, the Project has achieved the goal of trial water supply
required by KMG in due time. During the period of trial operation, which is
form 1 April, 2012 to 13 April, 2013 Qingshuihai has accumulatively supplied
26 million square water to Kunming’s main city, Chenggong district and the
Airport Economic Zone, with the average water supply of 69000m3/day.
Table 2-1 Water Environment Monitoring Spots of the Project Category Construction
Camp No. Location Progress Category
Water sources
construction
1# Banqiao River Construction, Under Banqiao River Dam 200m.
The project
has been completed
and put into in
process of trial
operation
The camp has been withdrawn. 2# Shiqiao River Construction camp,
Under Shiqiao River Dam 200m.
3# Xintian River Construction camp, Under Xintian Dam 200m. The camp has been
withdrawn. 4# Tabizilong Pool Construction Camp, Under Quanliu construction camp 200m.
5# Water body of Qingshuihai Reservoir beside Haiwei Village
The construction camp has not been
withdrawn
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
2
Category Construction Camp No. Location Progress Category
6# Water body of Qingshuihai Reservoir beside Maichong Tunnel Entrance
The camp has not been withdrawn.
Water Diversion
Construction
7# Construction Camp of Xiatuoqi Tunnel Entrance and aqueduct The construction
camp has been withdrawn. 8#
Construction camp of Enjia Tunnel Entrance and aqueduct and open channel
Water Diversion
Construction
9# construction camp of Enjia Tunnel Exit and Haidang Tunnel Entrance
The project
has been completed
and put into in
process of trial
operation
The construction camp has been
withdrawn.
10# Banqiao River Tunnel Exit construction Camp
11# Construction Camp of Maichong Tunnel Exit and Maichong open channel
12# Dapingdi Tunnel Exit, Bailiqing Tunnel Entrance
13# Xixian Trench Construction Camp
14#
Construction camp of Xiaobeidang open channel, 12th maintenance gang inverted siphon, Dashuidong Tunnel entrance
15#
Construction camp of Dashuidong Tunnel exit, aqueduct, Qinjiazhuang Tunnel, aqueduct, Longjia Village Tunnel entrance
16# Construction camp of Pujia Mountain Tunnel exit, Laofangziqing aqueduct, Dahu Mountain Tunnel exit
17# Construction camp of Dong Village Tunnel exit and Xi village inverted siphon
18# Construction camp of Dashanqing Tunnel exit and Moshiqing Tunnel entrance
19# Construction camp of Baishi mountain Tunnel exit, aqueduct, Jinji Mountain Tunnel entrance
20# Construction camp of Jinji Mountain Tunnel exit, aqueduct, Xin Village aqueduct and Tunnel entrance
21# Construction camp of Xin Village Tunnel exit, gegentang aqueduct and Tunnel Exit
22# Construction camp of Gegentang Tunnel exit, Qiutianchong open channel
23# construction camp of Tongxin Reservoir diversion gate
The camp has not been withdrawn.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
3
Category Construction Camp No. Location Progress Category
Water source
construction 24# Jinzhong Mountain Reservoir
construction camp
Note:progress report updated to June 30, 2013
In Table 2-1, equipments that have not been withdrawn in the project
points of 1# and 2# needs to be guarded, and personnel of the site office are
collecting materials of the project points of 6#, 23# and 24#. Therefore, site
offices of these five project points have not been withdrawn yet. Workers in
other works have all been withdrawn, and the temporary construction built in
the duration of construction have been demolished in most parts of work points,
except work points of 1#, 2# and 5#.
During the construction of the Project, the ground above Daping Tunnel
sank, the exit sections of Haidang Tunnel and Yujiazhuang Tunnel had the
phenomenon of subsurface filtration, and Dashuidong Tunnel collapsed and had
the phenomenon of subsurface filtration, the main reason for such problems are
the geological conditions of these areas were poor. But these problems have
been properly solved.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
1
3. Implementation of Environmental Protection Program
3.1 Targets of Environment Management Program
The objective of establishing an EMP is not only to propose appropriate
mitigation measures, but also to recommend establishment of institutions or
mechanisms to monitor and ensure compliance with environmental regulations
and implementation of the proposed mitigation measures. Such institutions and
mechanisms will seek to ensure continuously improving environmental
protection activities during preconstruction, construction, and operation in order
to prevent, reduce, or mitigate adverse impacts. The EMP drew on the
individual EIA reports and on the PPTA discussions and agreements with the
relevant government agencies.
3.2 Implementation of Mitigation Measures
The important aspects of the implementation of mitigation measures are
highlighted as follow:
1) Environmental Clauses in Civil Works Contracts
All civil works contracts contain provisions on workers and community,
environmental protection and protection of physical and cultural relics. The
environmental clauses are summarized as below.
Workers’ and Community Safety
The contractor will take precautionary measures to ensure workers’ safety.
Protective devices will be worn at all times for any person entering the
construction site. Safety training shall be undertaken for workers and staff. In
case of bodily harm to any worker, the contractor will have full responsibility
for medical care and compensation according to PRC labor law. The contractor
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
2
will also be responsible for any bodily harm and property damage caused by
construction activities on site or in the vicinities, including land occupation.
The contractor is required to strengthen safety management, especially in
regard to the use of flammables, explosives, toxic and corrosive substances.
Before the start of construction, the contractor shall submit to the independent
construction supervision agency an emergency preparedness and response plan.
Environmental Protection
The contractor shall comply with all relevant laws and regulations on
environmental protection, and will take precautionary measures to minimize any
potential impact on the environment. It will be responsible for restoring and
rehabilitating the environment to its original state at its own costs. An
environmental management plan (EMP) with mitigation measures will be
prepared and submitted to the construction supervision agency for approval
before the commencement of construction.
The contractor will treat and dispose its construction wastewater, sewage
from workers’ camps and solid wastes properly so as not to cause any damage
to the environment, drinking water sources and public health. The disposal of
spoils and solid wastes shall not obstruct flood ways and risk public safety. All
slopes shall be protected with retention walls, proper drainage systems and
vegetation to avoid geological hazards. Noise, dust, air emissions, wastewater
and waste oils will be controlled to minimize annoyance to local communities.
Natural and Cultural Relics
All physical and cultural relics discovered at the construction sites are
owned by the state. The contractor will report any such discoveries immediately
to the local relics protection authority and in the meantime immediately inform
the construction supervision agency. The contractor shall take effective
measures to protect the unearthed physical and cultural relics. The contractor
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
3
will be held responsible for any loss of damage to the discovered relics, and
prosecuted for any delayed and fraudulent reporting.
2) Pollution control measures proposed by Technical Report (2007) of
Monitoring for the Project
Spoil Disposal: Sixty five spoil disposal sites have been located
throughout the Project construction area for the disposal of a net total (after uses
for fill) of 2.2115 million m3 of excavated spoil. The SEPP provides a detailed
analysis of all erosion sources as mitigation measures to prevent or control
them. It includes setting principles and erosion control prescriptions for spoil
dumps. These have been incorporated into the EMP.
Erosion Damage: Erosion potential from all construction sites, including
preparation of resettlement areas and road making, was estimated at about
75,000 m3. A comprehensive Soil Erosion Prevention Report (SEPR) had been
prepared. It provides a detailed analysis of all erosion sources with mitigation
measures to prevent or control them. It includes erosion control prescriptions for
borrow pits and quarries, dam and infrastructure construction, and construction
work areas and camps. These have also been incorporated into the EMP. To
date, contractors have taken measures to control soil erosion. Soil erosion
measures during construction include minimizing land surface disturbance and
exposure and use of settlement ponds. Upon completion of construction, all the
construction sites will be re-vegetated with trees and grasses.
Construction Wastewater: Wastewater produced during the construction
period come from washing aggregates, pouring and curing concrete, as well as
oil-containing wastewater from machinery repairs. The major pollutant in
construction wastewater is suspended solids. Settlement ponds are used to retain
the sediments in the construction wastewater before they are discharged into
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
4
rivers. The settlement ponds are cleaned when they are filled up with sediments.
Tires of construction vehicles are cleaned with spray water before they leave the
construction site. And the oil-water separators used for treating oil wastewaters.
Recycled water has been used to spray for dust control. All sludge was removed
from site.
Domestic Wastewater: Daily living wastewater produced by the
construction staff is about 440 m3. Deep latrines and seepage pits have been
installed in the each camp. After Project completion, the sites will be closed
only after waste has been effectively treated or removed, in order to minimize
pollution in the rivers.
Gaseous Air Pollution: Construction will consume about 8,925 tons of
diesels, releasing significant amounts of gaseous SOx, CO and NOx. The major
sources of air emissions are construction equipment and construction vehicles.
The vehicles delivering granular or fine materials to the sites were covered with
tarpaulin sheets. Vehicle speeds are controlled on construction sites. Equipment
was maintained to a high standard to ensure efficient running and fuel-burning.
High-horsepower equipment was installed with tail gas purifier. Atmospheric
monitoring was carried out during the construction period. A regular inspection
and certification system has been initiated to make sure that exhaust gases
complied with emission standards.
Dust: Construction sites will produce fugitive dust from material storage
areas, waste dump sites, concrete mixing and excavation sites. Material
stockpiles and concrete mixing equipment was equipped with dust shrouds. The
operators regularly maintained the shrouds to ensure their effective operation.
For both construction sites and construction roads, water spraying for the
suppression of dust was standard site management practice.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
5
Noise: Noise was generated by construction machinery (excavators,
bulldozers, conveyers, concrete mixers) and transport vehicles. Works were
scheduled according to the noise rating of the machinery used and the distance
to sensitive receptors to achieve Emission Standard of Environment Noise for
Boundary of Construction (GB12523-2011). Noise impacts for transport
vehicles were reduced by attention to road surfaces near village areas and the
erection of temporary noise barriers.
Household refuse: In the five and half years of construction, a total of 6000
tons of waste were be generated. The accumulation of waste will have serious
impact on worker’s health. Thus, each construction camp was equipped with
dustbins, which will be regularly sprayed with pesticides, to reduce flies. In the
course of transporting domestic garbage and construction materials, loads were
sealed or covered, to avoid spillage en route.
Construction Wastes: Construction and demolition wastes could have
adverse impacts on surrounding environments. The solid wastes that could not
be collected at the waste dump, and could not discarded in a way which will
damage farmland or the surrounding environment. Solid waste were stored and
regularly transported off-site for disposal.
Spills of Hazardous Materials: A construction materials handling
protocol (e.g., storage away from watercourses and provision of retention areas
to contain accidental spills of toxic, hazardous, and harmful construction
materials, oil and petroleum products, and asphalt materials) were prepared and
applied to prevent soil and surface/ground water pollution.
The implementation status of the mitigation measures, as proposed in the
SEIA, is presented in the right column of the Table 3-1 (this table and the tables
for this chapter thereafter are placed at the end of this chapter). In summary, the
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
6
mitigation measures have to date been implemented effectively.
3.3 Information Disclosure
Bulletin boards have been erected at each construction site, which contains
a description of the project, layout map, construction safety, labor standards,
environmental and health standards, name of the contractor(s) and names and
contact information of the on-site managers and company executives.
3.4 Implementation of Staff Training
The proposed institutional strengthening and capacity building program in
the EMP and the status of implementation of the proposed capacity building
activities are presented in Table 3-2. In summary, the institutional strengthening
and capacity building programs has to date been implemented well.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
7
Table 3-1 Implementation Status of Mitigation Measures Impact Factor/
Stage
Environmental Impacts and
Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation Status
A. Preconstruction 1. FS stage Site/alignment
selections The recommended sites/pipeline routes for the individual project components were selected from various alternatives so as to minimize adverse impacts on the environment.
IA, DI, and EIA team
EA, KMG, YEPB, KEPB
Implemented during project preparation
EIA report As required by law, ensure that the EIA has been prepared for the Project.
EIA team on behalf of IA
EA, SEPA, YEPB, KEPB
Implemented during project preparation
Soil Erosion Prevention Plan
As required by law, ensure that the SEPP has been prepared for the project.
DI on behalf of the IA
EA, YEPB
Implemented during project preparation
Public consultations
Hold two rounds of public consultations on environmental issues, poverty, and resettlement during the project design and EIA preparation.
EIA team, IA, TA team
EA, YEPB, KEPB
Implemented during project preparation
Resettlement plan
As required by law, prepare the RP for the project to required ADB and PRC standards.
DI
EA, YWRB, MWR
Implemented during project preparation
2. Design stage Updating EMP
Update mitigation measures defined in this EMP and incorporate them into the detailed design to minimize adverse environmental impacts.
DI, IA
EA, KEPB, YEPB
The mitigation measures were appropriate and ad
equate, and that no revision was necessary.
Land take confirmation
Update the RP and incorporate it into the detailed design.
DI, IA
EA, YWRB, MWR
Implemented during project preparation
Endangered fish research Undertake additional studies on the reproductive
habits of xundian white fish to help protect this special species in Qingshuihai.
DI EA, YWRB,
MWR
The principal has commissioned Yunnan University to conduct
this research Qingshuihai
reservoir water quality modeling
During the detailed design phase, use a multi-dimensional model to predict the degree of reservoir stratification that might occur and assist in the appropriate design of a multi-level offtake structure.
DI, IA
EA, YWRB, MWR
Implemented during project preparation
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
8
Table 3-1(continued) ImpactFactor/Stage
Environmental Impacts and Issues
Mitigation Measures Implementing Agency
Supervising Agency
Implementation Status
Annual flow of downstream
xiaojiang River reduced by 11.6%
KWSG will commission further survey during the detailed design period to collect data on water use and in-stream ecology in the downstream reaches of the 1iaojiang River (to confirm initial finding of minimal impact).
DI, IA
EA, YWRB, MWR
Related data have been collected and the impacts of the project have been
minimized
Water transfer issues within the
basin: reduction of downstream flows
of Banqiao and Shiqiao dams
The will be prepared by the IA following the completion of detailed design and before commissioning of reservoirs.
DI, IA
EA, YWRB, MWR
Executive agency has finished
detailed design before trail operation
Sediment buildup in source reservoirs
To protect Qingshuihai from sediment transfer from source areas, each dam will be designed with a low-level sluice to maintain a slope on the silt deposited near the dam wall to ensure that silt is kept clear of the level of the offtake by periodic flushing. A Sediment Flushing Plan will be prepared by the IA and incorporated into operational maintenance programs .
DI, IA
EA, YWRB, MWR
A Sediment Flushing Plan
prepared by the IA and incorporated into operational
maintenance programs.
Dam safety and function
i. Confirm reservoir rim stability and identify any adverse slopes in the design phase.
ii. Investigate potential rock joint instability and slope/foundation failures including drilling of boreholes and e4-1cavation of tunnel adits at the larger dams.
iii. Long-term seismic movement of the xiaojiang Fault has been estimated at about 200 mm over 100 years, while sudden movement due to a Magnitude I4-1 event is estimated to be about 1.9 m. Include in the designs substantial filter widths and sufficient freeboard to accommodate any potential settlement.
DI, IA
EA, YWRB, MWR
The work about the Dam safety and
function was completely
finished by DI and IA
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
9
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and Issues
Mitigation Measures ImplementingAgency
SupervisingAgency
Implementation Status
3. Bidding and
constructionpreparation
Bidding documents and contractors’ qualifications
i. To ensure initial environmental capability among contractors, prepare environmental prequalification clauses and specifications to be included in the prequalification package to contractors.
ii. Prepare an environment section in the terms of reference for bidders.
iii. Select spoil disposal sites based on specific criteria in the SEPP, and as revised by the EIA. Define spoil disposal sites, borrow pits, and quarry locations in the construction tender documents.
iv. Prepare environmental contract clauses for contractors, namely the special conditions (e.g., reference EMP and monitoring table).
v. Prepare covenants for loan agreement as defined in the EMP.
IA EA, KEPB, YEPB,
Environmental provisions and clauses were included
for bidders and construction and supply
contracts.
Complaint and Information Office or appointed person
i. Establish a complaint and information office or appoint a responsible person before starting the construction.
ii. Ensure that staff at the office is well trained to handle crisis situations or conflicts with residents.
Contractors IA, EA
A deputy manager was appointed as the
responsible person. An environmental officer was recruited in Qingshuihai
(IA) prior to construction.
Environmental Operation and Supervision
Manual
As per the contract for approval by IA, require contractors to prepare a Site Environmental Management and Supervision Manual.
Contractors IA, KEPB The contractors prepared and submitted an
environmental operation and supervision manual and approved by the IA.
Environmental protection training
Invite environmental specialists and/or officials from YEPB/KEPB and/or WRB to provide contractors with training on implementing and supervising environmental mitigation measures.
IA YEPB, KEPB
IA and EMO in Qingshuihai organized EMP training for construction managers and engineers.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
10
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation Status
Resumption of land and property process and management.
i. Establish a resettlement office comprising localgovernment officials to manage the resettlementprocess.
ii. Conduct community consultation programs andensure that information about entitlement based onthe Land Administration Law is disseminated.
iii. Ensure that all relocation and resettlementactivities are reasonably completed beforeconstruction starts on any subproject.
IA
EA, KMG
RO was established. The resettlement information brochure (RIB) was distributed to all APs and posted in local communities. APs were resettled before construction started.
B. Construction The construction period is 5 year and a half span 1. Water Wastewater
from construction camps
Install deep latrines and seepage pits in the camps. After project completion, vacate the sites only after waste has been effectively treated or removed.
C ontractors IA, KEPB, County EPBS
Each construction camp has disposed of wastes effectively before removal.
Tunnelling wastewater
Wastewater from tunnelling will be collected in sediment tanks, retention ponds, and filter tanks to remove silts and oil, and then be reused for the tunnelling operations. Process should follow the flow paths and specifications specified in the SEPP.
Contractors
IA, KEPB, County KWRB
Most construction camps have taken corresponding measures and complied with the standard of wastewater discharge during construction period
Washing aggregates, pouring and curing concrete, machinery repairs
i. Establish settling ponds, oil-water separators. ii. Use recycled water to spray for dust control. iii. Remove sludge from site.
Contractors
IA, KEPB, County KWRB
Complied with.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
11
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and
Issues
Mitigation Measures ImplementingAgency
Supervising Agency
Implementation Status
Handling of hazardous and
harmful materials
i. Prepare a protocol for handling and disposing of construction materials which includes spill responses, and apply it to prevent soil and surface water/ground- water pollution.
ii. Construct storage facilities, bunds, and cleanup installations. iii. Ensure that the fuel supplier is properly licensed, follows the proper
protocol for transferring fuel, and complies with PRC regulation on Transportation, Loading and Unloading of Dangerous or Harmful Goods.
iv. Ensure that vehicles and equipment are properly staged in designated areas to prevent contamination of soil and surface water.
v. Carry out vehicle, machinery, and equipment maintenance and refueling in such a way that spilled materials do not seep into the soil.
vi. Ensure proper storage of fuels, oil etc., within secured areas on an impermeable surface.
vii. Keep fuel storage and refilling areas at least 300 m from drainage structures and important water bodies.
viii. If fuel storage and refueling areas are located in agricultural land or areas supporting vegetation, ensure that topsoil is stripped, stockpiled, and returned after completion of refueling activities.
xi. Provide oil traps for service areas and parking areas.
Contractors
IA, KEPB, County KWRB
Implemented during project
preparation subject to the requirements
2. Air Generation of dust
i. Cover vehicles carrying soil, sand, or other fine materials to and from the sites.
ii. Locate materials storage sites 300 m away from residential areas and cover them with canvas or spray with water.
iii. Spray water on construction sites and access roads twice a day. v. Equip all conveyors and hoppers with hoods or other dust control devices.
Contractors
IA, KEPB, County KWRB
Implemented during project preparation subject to requirements
Air emission from vehicles and equipment
i. Ensure that vehicle emissions are in compliance with PRC regulations. ii. Maintain equipment and machinery to a high standard to ensure efficient
running and fuel burning. Install tail gas purifier on high horsepower equipment to ensure emissions are in compliance with PRC regulations.
iii. Initiate a regular inspection and certification system.
Contractors
IA, KEPB, County KWRB
Implemented during project preparation subject to requirements
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
12
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and
Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation
Status
3. Noise and vibration
Noise from vehicles and construction machinery
i..Ensure that noise levels from equipment and machinery strictly conform to PRC-GB 12523-90.
ii. Provide adequate route for large trucks to keep them away from residential areas.
iii. Improve the road surface near village areas. iv. Install portable noise shields near sensitive receptors such as schools,
hospitals, and residential areas. v. At construction sites within 500 m of the nearest habitation, stop
noise-generating construction work between 2200 and 0600 hours.
Contractors
IA, KEPB, County KWRB
Implemented during project preparation subject to requirements
Vibrations and blasting
i. Limit use of heavy vehicles and e4-1cessive vibrations near sensitive structures, walls, residences.
ii. Use blasting mats and design blasts to limit ground-borne vibrations and air overpressure.
Contractors
IA, KEPB, County KWRB
Implemented during project preparation subject to requirements
Domestic waste from workers’ camps
i. Provide multi-compartment collection bins for each construction camp to facilitate the reuse, recycling, and composting of solid waste. Spray the dustbins regularly with pesticides to reduce flies.
ii. Store wastes away from water bodies and regularly haul them to a suitable landfill or designated dumping site.
iii. Require the contractors to provide appropriate waste storage containers.
iv. Where appropriate, sign agreements with locals for waste disposal through local facilities and to approved disposal sites.
v. In the course of transporting domestic garbage, seal or cover loads to avoid spillage en route
Contractors
IA, KEPB, County KWRB
Implemented during project preparation subject to requirements
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
13
Table 3-1 (Continued) Impact Factor/ Stage
Environmental Impacts and Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation
Status
4. Solid wastes Construction and
demolition wastes could have adverse impacts on surrounding environments.
i. Collect at the waste dump the solid wastes that cannot be used. Do not discard them in such a way that they will damage farmland or the surrounding areas.
ii. Store solid waste and regularly transport it off-site for disposal.
Contractors
IA, KEPB, County KWRB
The contractor has collected all the waste and transported them off-site for disposal.
5. Soil erosion and stability
Erosion from spoil disposal sites
i. Strip and stockpile topsoil. ii. Build retaining walls to safely contain spoil. iii. Provide temporary detention ponds or containment
to control silt runoff. iv. Construct intercepting ditches and drains to prevent
outside runoff from entering disposal sites, and transfer runoff from sites to e4-1isting drainage system or ponds.
v. Use clay bags for temporary protection during the dumping period.
vi. Preserve e4-1isting vegetation where no construction activity is planned, or temporarily preserve vegetation where activity is planned for a later date.
vii. Where topsoil is poor or in short supply, augment by mulched vegetation removed from inundation areas and set aside for the purpose.
viii. Rehabilitate the sites first with grass. Additional plantings only when grass has established.
Contractors
IA, KEPB, County,
KWRB,YWR
A lot of retaining walls and temporary detention ponds have been built during construction period and the contractors have adopt many measures according to prevention methods of water and soil erosion
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
14
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and
Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation
Status
Erosion from quarries, and borrow pits
i. Strip and stockpile topsoil. ii. Provide temporary detention ponds or containment to control
silt runoff. iii. Construct intercepting ditches and drains to prevent outside
runoff from entering disposal sites, and transfer runoff from sites to e4-1isting drainage system or ponds.
iv. Preserve x-1isting vegetation where no construction activity is planned, or temporarily preserve vegetation where activity is planned for a later date.
v. Rehabilitate borrows sites into grassland, woodland, or farmland after closing.
Contractors
IA, KEPB, County EPBS, KWRB, YWR
As the above item.
Erosion from construction sites
i. Strip and stockpile topsoil. ii. Provide temporary detention ponds or containment to control
silt runoff. iii. Construct intercepting ditches and chutes to prevent outside
runoff from entering construction sites, and transfer runoff from sites to e4-1isting drainage system or ponds.
iv. Rehabilitate construction sites into grassland, woodland, or farmland at completion.
Contractors
IA, KEPB, County EPBS
Complied with.
Replanting of disturbed areas including spoil disposal sites
i. In compliance with PRC’s forestry law, the IA will undertake compensatory planting of an equivalent or larger area of affected forest trees.
ii. Replanting will use a selection of species that are suitable for this area and have the most appropriate attributes to survive and serve their designated functions.
iii. All quarries and borrow pits will be restored, where possible, to productive agricultural land or grass and woodland.
iv. Spoil disposal sites will be restored initially with grass. Additional plantings only when grass has established.
v. New plantings will be maintained during the operation period.
Contractors, IA
IA, KEPB, County EPBS KWRB, YWRB, KFB
Complied with.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
15
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation
Status
6. Ecological study
Disturbance to xundian white fish
While ecological studies of the fish are being completed, semiartificial breeding spots in the form of floating fish nests will be installed and maintained.
Contractors, IA
IA, KEPB, County EPBS KWRB, YWRB
The semiartificial breeding center of xundian white fish is planning by contractor and IA.
7. Social Resettlement All affected persons will be compensated and resettled in a timely and adequate manner, in accordance with the resettlement plan. Communities 948,000 (Included in RP) Resettlement environmental protection measures are garbage disposal; monitoring drinking water, air, and noise; health monitoring.
IA, Contractors,
EA, KMG, communities
Almost most of affected persons have been compensated and they are resettling.
Traffic management
i. Site and manage interim roads to avoid traffic problems. ii. Select transport routes to reduce disturbance to regular
traffic. iii. Divert traffic at peak traffic hours. iv. Block and reinstate interim roads to original condition on
completion of construction.
Contractors, IA
EA, xundian And Songming Traffic authorities
Complied with
Work camp health and hygiene
i. Require contractors to safeguard environmental hygiene in the construction camps, including the quality of food and water supplies. Establish medical facilities among the camps and screen workers for health problems.
ii. Implement the HIV/AIDS action plan described in the poverty and social assessment, including awareness training for both workers and villagers.
iii. Require all construction sites to provide necessary personal protective equipment and other resources to create a safe working environment.
iv. Ensure that construction site operations comply with the PRC’s State Administration of Worker Safety Laws and Regulations.
Contractors, IA
IA, local or/and provincial health bureau
Complied with
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
16
Table 3-1(continued) Impact Factor/ Stage
Environmental Impacts and Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation
Status
Cultural heritage protection
i. Preserve cultural heritage values where identified. In accordance with PRC regulations, no person shall destroy, damage, deface, conceal, or otherwise interfere with a relic.
ii. In case an important site is unearthed, stop work immediately and promptly refer the matter to the county, municipal, provincial, or state agencies for evaluation and decision on appropriate actions.
Contractors
IA, local or/and provincial cultural heritage bureau
So far, no cultural relics were discovered at the construction sites.
8. Water quality
Any organic materials left in the inundation area, such as trees, shrubs, and grasses will decay during initial inundation resulting in depleted DO.
i. Clear and remove all vegetation from inundation zone before flooding.
ii. Mulch vegetation and use in rehabilitation of disturbed areas.
iii. Avoid delay in construction or inundation, providing time for natural vegetation to grow back.
IA, XFB, SFB EA, KEPB, County EPBS
Complied with
Greenhouse gases with reservoirs emitting CO2 and methane
Clear and remove all vegetation from inundation zone to avoid emission of CO2 and methane (see above).
IA, XFB, SFB EA, KEPB, county EPBS
All vegetation from inundation zone were cleared and disposed with scientific methods
C. Operation 1. Water
Fish raising
Currently fish raising is allowed in the Qingshuihai Reservoir. It will be discontinued during project operation.
IA, MWR,
YWRB, KEPB, County EPBS
Not yet due.
Reservoirside commercial development
The operation of tourist villages on the foreshore of Qingshuihai Reservoir will be discontinued in the medium term.
IA, MWR,
YWRB, KEPB, County EPBS
Not yet due.
Sediment flushing from source reservoirs
Flushing operations will be undertaken in combination with wet season spillway flows and in accordance with the Sediment Flushing Plan.
DI, IA EA, YWRB, MWR
Not yet due.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
17
Table 3-1 (Continued) Impact Factor/
Stage
Environmental Impacts and
Issues Mitigation Measures Implementing
Agency Supervising
Agency Implementation
Status
Wastewater from the management office
i. Wastewater from the management office will be collected and hauled to the waste treatment facilities directly.
ii. A septic tank or one set of on-site wastewater treatment device will be installed for treating wastewater from management offices before being discharged into the receiving water bodies.
IA KEPB, county EPBS
Only reservoirs next to the village are are arranged with administrators, who are all the residents nearby and not accommodated in the management places.
Water quality of return waters from Kunming city reentering the river basin
i. In the developing areas of Kunming city, which will be the main beneficiaries of project water, four new WWTPs will be built with a combined capacity of 200,000 m3/day.
ii. New industrial developments will be screened to lower the amounts of water consumption and discharge, as well as reduce the discharge of pollutants.
iii. KMG will target a goal of 20% water recycling rate, using a range of measures including implementation of the “one household, one meter” policy.
IA, Kunming Drainage Company, Management Office of NADZ and EDZ
KEPB, county EPBS
Not yet due.
2. Solid wastes
Solid waste from management office
i. Provide multi-compartment collection bins to facilitate the reuse, recycling, and composting of solid waste.
ii. Sign agreements with locals for waste disposal, where appropriate, through local facilities.
iii. In transporting domestic garbage, seal or cover loads to avoid spillage en route.
IA
XEPB, SEPB, KEPB
The household refuse produced by administrators should be cleared up by local sanitation department.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
18
Table 3-1 (Continued) Impact Factor/ Stage
Environmental Impacts and Issues
Mitigation Measures Implementing Agency
Supervising Agency
Implementation Status
3. Ecological issues
Water transfer issues within the basin:reduction of downstream flows of Banqiao and Shiqiao dams
Implement an adaptive management approach for the control of downstream releases at Shiqiao and Banqiao river dams in accordance with detailed rules defining triggers and impact thresholds for change in the riparian release prepared by the IA before commissioning of reservoirs. Use the results of downstream environmental monitoring as feedback to influence the storage operation. This involves a monitoring and review function. Hire one person from each downstream village to monitor the water flow to downstream areas and report on livelihood changes.
IA
Downstream Village committee XEPB
Not yet due.
Invasion of unwanted aquatic plants in reservoirs
EIA concluded that the potential for invasion of unwanted aquatic plants is very low. During the first 5 year period, monitor aquatic plants at the inlet of the Qingshuihai reservoir. Implement interception measures where any unwanted aquatic plants are found.
IA
KEPB Not yet due.
4. Health risks
Public health threats and increase of health risks
Investigation results show no waterborne diseases in the project area. No mitigation measures are required beyond the recommended environment monitoring program.
See monitoring plan
Not yet due.
5. Induced seismic instability
The small capacities of the Banqiao and Shiqiao reservoirs and the marginally increased capacities of Qingshuihai and Jinzhongshan reservoirs are unlikely to induce seismic events.
No mitigation measures are required.
Implemented during project preparation
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
19
Table 3-1(continued) Impact Factor/
Stage Environmental
Impacts and Issues Mitigation Measures ImplementingAgency
Supervising Agency Implementation Status
6. Environmental risks
Dam safety and function
i. Provide adequate supervision and management. ii. Enhance operation monitoring. iii. Regularly maintain environment facilities. iv. Prepare emergency response plans. v. To minimize sedimentation in the reservoirs,
include in the designs low-level sluices for flushing of sediment through the reservoirs to keep the transfers clear.
contracting institutes and reservoir authority
Local government, KEPB,county EPBS
Not yet due.
Flood and seismic events
i. Put in place warning plans for floods to warn people downstream. Include spillway flows and occasional sediment flushing.
ii. Set up an earthquake monitoring station at Haiwei.
iii. KMG will be responsible for the Emergency Action Plan.
IA EA,YWRB, MWR
Implemented during project preparation
Fall gradients and velocity of water flow
The height difference between Qingshuihai reservoir and Kunming is 220 m and the transfer distance is 75 km. The gradient is very small. Include energy dissipation installations in the steep sections.
DI, IA EA, YWRB, MWR
Implemented during project preparation
Bank erosion and flooding risks
No mitigation measures are required. Not yet due.
Insufficient environmental management capacity
Conduct training for environmental management, and develop facility and staff setup.
IA
KEPB, county EPBS
Not yet due
Note: the above progress as the deadline to June 30, 2013.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
20
Table 3-2 Implementation Status of Institutional Strengthening and Capacity Building
Training Topics Attendees Contents Number of Trainees Implementation Status
Environmental laws, regulations, and policies
PMO, IA/operators, contractors representatives
(i) Environmental laws and regulations (ii) Environmental policies and plans (iii) Basic environmental management
15
Fulfilled.
EMP implementation
IA, contractors
(i) Responsibility and duties for project construction, management, and environmental protection (ii) Task of environmental protection during project construction (iii) Key environmental protection contents, etc., in project construction (iv) Various forms of environmental reporting (v) EMP improvement and corrective actions
40
Fulfilled.
Crisis handling KWSG/operators, contractors
Crisis handling methods 10 Fulfilled.
Environmental aspects of facility operation and maintenance
KWSG/operators, contractors
(i) Adaptive management of riparian release (ii) Environmental “housekeeping” (iii) Safety operation regulations (iv) Emergency response procedures
15
Fulfilled.
Environmental monitoring, inspection, and reporting
KWSG/operators, KEPB/county EPBs
Monitoring and inspection methods; collecting, processing, and interpreting data; reporting system. 15
Fulfilled.
Note: the above progress as the deadline to June 30, 2013。
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University
(AUGUEST 2012 –JUNE 2013)
21
4. Environmental Monitoring
The engineering construction of the project has been completed and
construction camps have been removed. In order to analyze the changes
of ambient quality status before and after construction, Xishan Institute
monitored water sources of the major surface around the construction
sites and the monitoring locations are shown in Table 4-1.
Table 4-1 Environmental monitoring locations of surface water No. Name of surface
watersources Monitoring locations
1 Qingshuihai Reservoir
the middle spot of Qingshuihai 2 Haiwei 3 Maichong 4
Xintianhe Reservoir Estuary
5 Intake 6 Jinzhongshan
Reservoir Front dam
7 Back reservoir 8 Shiqiaohe Reservoir Dam site 9
Banqiaohe Reservoir Upper reaches of the dam site
10 Dam site 11 Lower reaches of the dam site 12 Tabizi Spring Center
4.1 Monitoring of water quality
In May 2013, Xishan Institution monitored the major locations of
surface watersources flowing through the construction sites and the
monitoring frequency is once a day. Take a composite water sample and
the monitoring items are pH, dissolved oxygen, permanganate index,
chemical oxygen demand, 5-day biochemical oxygen demand, ammonia
nitrogen, total nitrogen, total phosphorus and fecal coliform.
(1) Monitoring results
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University
(AUGUEST 2012 –JUNE 2013)
22
Results of the water monitoring items in each monitoring locations
are shown in table 5-2 and the water quality standard is subject to Type II
under GB3838-2002 Environmental Quality Standard of Surface Water.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
23
Table 4-2 Statistical table of quality monitoring results Items Sampling site Time
pH Dissolved
oxygen (mg/L)
Permanganate index
(mg/L)
Chemical oxygen demand (mg/L)
5-day biochemical
oxygen demand (mg/L)
Ammonia nitrogen (mg/L)
Total nitrogen(mg/L)
Total phosphorus(mg/L)
Fecal coliform(No/L)
Up-to-standard
evaluation
The middle spot of
Qingshuihai 05.28 8.43 7.12 1.7 10L 0.8 0.087 0.63 0.018 20 Exceed the
standard
Haiwei of Qingshuihai 05.28 8.64 6.32 1.9 10L 1.0 0.103 0.58 0.020 20 Exceed the
standard Maichong of Qingshuihai 05.28 8.56 6.25 2.0 10L 0.9 0.111 0.52 0.021 20 Exceed the
standard Estuary of Xintianhe 05.28 / / / / / / / / / /
Intake of Xintianhe Reservoir
05.28 / / / / / / / / / /
Front dame of Jinzhongshan
Reservoir 05.28 8.32 7.02 3.2 10L 3.0 0.181 0.49 0.018 20 Reach the
standard
Back Jinzhongshan
Reservoir 05.28 8.12 7.32 2.8 10L 2.9 0.166 0.47 0.017 20 Reach the
standard
Dam site of Shiqiaohe 05.28 7.98 8.23 1.6 10L 2.5 0.222 0.43 0.019 500 Reach the
standard Upper
reachesof the dam site of Banqiaohe
05.28 8.12 8.31 1.0 10L 1.1 0.157 0.35 0.019 200 Reach the standard
Dam site of Banqiaohe 05.28 8.40 8.37 1.1 10L 1.3 0.185 0.37 0.023 280 Reach the
standard
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
24
Table 4-2 (continued) Items Sampling site Time
pH Dissolved
oxygen (mg/L)
Permanganate index
(mg/L)
Chemical oxygen demand (mg/L)
5-day biochemical
oxygen demand (mg/L)
Ammonia nitrogen (mg/L)
Total nitrogen(mg/L)
Total phosphorus(mg/L)
Fecal coliform(No/L)
Up-to-standard
evaluation
Lower reaches of the dam
site of Banqiaohe
05.28 8.32 7.35 1.3 10L 1.6 0.177 0.36 0.024 320 Reach the standard
Tabizi Spring 05.28 8.23 7.19 3.4 10L 3.2 0.312 0.73 0.037 480 Exceed the standard
Standard value 6-9 ≥6 ≤4 ≤15 ≤3 ≤0.5 ≤0.5 ≤0.025 ≤2000 /
Note: Xintianhe Reservoir has dried up owing to drought which leads to failure of collecting water sample. So the monitoring data is lacking.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
25
(2) Analysis of monitoring results
It can be known from table 4-1; the water quality of all the other
locations is up to Class II under GB3838-2002 Environmental Quality
Standard of Surface Water, except Qingshuihai (the middle spot of
Qingshuihai, Haiwei and Maichong) and Tabizi Spring.
In accordance with the water quality monitoring data of each
location during the environmental assessment phase subject to the
Written Report of the Project, and water quality monitoring data of 2012
provided by Xundian Environment Protection Bureau towards each
location in October 2012, and data of this phase, work out the water
quality conditions of each location before construction period, during
construction, and after the construction, all of which are shown in Table
4-3:
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
26
Table 4-3 Quality conditions of surface waterduring the engineering
construction of the project
Name of the locations Water quality before construction
Water quality during construction (Oct. 2012)
Water quality after construction after
construction ( May 2013)
The middle spot of Qingshuihai (Ⅱ May 2005) Ⅱ Ⅲ
Haiwei of Qingshuihai (Ⅱ May 2005) —— Ⅲ Maichong of Qingshuihai —— —— Ⅲ
Estuary of Xintianhe (Ⅱ May 2005) —— —— Intake of Xintianhe
Reservoir (Ⅲ July 2006) Ⅲ ——
Front dame of Jinzhongshan
Reservoir (Ⅲ May 2005) —— Ⅱ
Tail of Jinzhongshan Reservoir (Ⅳ May 2005) —— Ⅱ
Dam site of Shiqiaohe (Ⅲ May 2005) —— Ⅱ Upstream of the dam
site of Banqiaohe (Ⅳ May 2005) —— Ⅱ
Dam site of Banqiaohe (Ⅳ May 2005) Ⅳ Ⅱ
Downstream of the dam site of Banqiaohe (Ⅴ May 2005) —— Ⅱ
Tabizi Spring (Ⅴ July 2006) Ⅲ Ⅲ Note: 1、“—”means the items that have not been monitored this time or there are no data. 2、 Xintianhe Reservoir has dried up owing to the long-term drought, which led to the failure of collecting water sample in the current monitoring, so there are no monitoring data about Xintianhe Reservior in 2013
By comparing the water quality conditions before construction (the
year of 2006, 2007) and during construction (2012), it can be concluded
that the water quality of Qingshuihai Reservoir maintains at Class II both
before and after construction; the water quality of Xintianhe Reservoir
maintains at Class III, the water quality of Banqiaohe Reservoir remains
at Class IV, and the water quality of Tabizi Spring changes from Class V
into Class III. It can be easily seen that the construction of the project
exerts no influences on the water quality of each location; in adverse, due
to the implementation of the construction, the impact of non-point source
pollution on the water quality of Tabizi Spring has decreased, so as to
make the water quality of Tabizi Spring turns into Class III in 2012.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
27
Up to June 2013, the Project enters into completion phase. It can be
known by a comparison of the water quality before construction and after
construction that except for the change from Class II into Class III in
Qingshuihai Reservoir, and no water sample collected owning to
consecutive drought in Xinhetian Reservoir, water quality at the rest four
locations have improved , namely, water quality Class of Jinzhongshan
Reservoir, Shiqiaohe Reservoir , Tabizi Spring, and Banqiaohe Reservoir
all have turned into Class II from Class IV, Class III, Class III and Class
IV respectively.
Main reasons of the above are: catchment area of these reservoirs is
relatively small; the water quality is easily to be effected by the rainfall in
dry and rainy seasons, and rainy season didn’t come when the monitoring
was conducted in 2005, drought and little rainfall in 2012, while the
rainfall during the monitoring period in 2013 is sufficient. Since the water
source of Tabizi Spring is groundwater, and the water quality has little to
do with the rainfall, the water quality of 2013 varied little from that of
2012. It can be seen from the comparisons over the years that the
implementation of the project exerts little impacts on the water quality of
the surrounding surface water.
During construction period of the Project, wastewater treatment
measures have been taken at each site and camp to avoid impacts on the
surrounding surface water, so the water quality of the surrounding surface
water maintains stable.
Meanwhile, it can be inferred from Table 5-2 that the current water
quality of Qingshuihai reservoir after construction is worse than that
before construction, which now is Class III. The major reasons are: Since
December, 2012, Qingshuihai Reservoir started to receive water from
banqiaohe Reservoir, Xintianhe Reservoir, Shibanqiaohe Reservoir and
Tabizi Spring, entered into primary impoundment period, for which the
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
28
water body is in a process of blending, the water quality needs a
stabilization-oriented process. At the same time, due to the reservoir
capacity of Qingshuihai Reservoir, less vibration of water quality resulted
from rainfall. As a result, the influences of dry and rainy seasons on the
water quality of Qingshuihai Reservoir are relatively small than other
water sources.
In conclusion, the implementation of this project has exerted little
influences on the surface water; the decrease of water quality has been
caused by the water quality of the upstream after the water diversion
project started to work.
4.2 Clean-ups of the camps upon completion of the construction
By June 30, 2013, the construction of the project has been completed,
all contractors removed. There leaves administrative staff who are
responsible for collecting data in construction sites, namely 1#
construction camp of Banqiaohe, 2# construction camp of Shiqiaohe,
Qingshuihai section next to 6# Maichong tunnel entrance, distribution
gate of 23# Tongxin Reservior, 24# Jinzhongshan Reservior) while other
construction sites have all be removed.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
29
Table 4-4 Clearing-Up of the Camps After Completion
Type No. of the
ConstructionCamp
Location Clearing-Up of the Camps
Water Source project
1# Banqiao River Construction camp The equipment has not been removed totally and there left personnel of site office to take care of the equipment.
2# Shiqiao River Construction camp
3# Xintian River Construction camp The camp has been cleared up. 4# Tabizilong Pool Construction camp
5# Water body of Qingshuihai Reservoir beside Haiwei Village
The workers have removed and the camps have not been dismantled.
6# Water body of Qingshuihai Reservoir beside Maichong Tunnel Entrance
The camp has been dismantled and there were personnel who were preparing documents in the site office.
Water convey
ance Project
7# Construction Camp of Xiatuoqi Tunnel Entrance and aqueduct The camp has been cleared up.
8# Construction camp of Enjia Tunnel Entrance and aqueduct and open channel The camp has been removed and
the household refuse was not deal with. 9# construction camp of Enjia Tunnel
Exit and Haidang Tunnel Entrance
10# Banqiao River Tunnel Exit construction Camp
Water convey
ance Project
11# Construction Camp of Maichong Tunnel Exit and Maichong open channel The camp has been cleared up.
12# Dapingdi Tunnel Exit, Bailiqing Tunnel Entrance
13# Xixian Trench Construction Camp The camp has been removed and the household refuse was not deal with.
14#
Construction camp of Xiaobeidang open channel, 12th maintenance gang inverted siphon, Dashuidong Tunnel entrance
The camp has been cleared up.
15#
Construction camp of Dashuidong Tunnel exit, aqueduct, Qinjiazhuang Tunnel, aqueduct, Longjia Village Tunnel entrance
The camp has been removed and the household refuse was not deal with.
16#
Construction camp of Pujia Mountain Tunnel exit, Laofangziqing aqueduct, Dahu Mountain Tunnel exit The camp has been cleared up.
17# Construction camp of Dong Village Tunnel exit and Xi village inverted siphon
18# Construction camp of Dashanqing Tunnel exit and Moshiqing Tunnel entrance
The camp has been removed and the refuse dumps and cesspools were not deal with.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
30
Type No. of the Construction Camp
Location Clearing-Up of the Camps
Water convey
ance Project
19# Construction camp of Baishi mountain Tunnel exit, aqueduct, Jinji Mountain Tunnel entrance
The camp has been cleared up.
20#
Construction camp of Jinji Mountain Tunnel exit, aqueduct, Xin Village aqueduct and Tunnel entrance
The camp has been removed and the household refuse was not deal with.
21# Construction camp of Xin Village Tunnel exit, gegentang aqueduct and Tunnel Exit
The camp has been cleared up.
22# Construction camp of Gegentang Tunnel exit, Yangtianchong open channel
The camp has been cleared up and some parts are returned for
farming.
23# construction camp of Tongxin Reservoir diversion gate The camp has been removed and
there left personnel of site office to prepare documents. Tail-end
Reservior 24# Jinzhong Mountain Reservoir construction camp
Based on the conditions of site survey, most of the removed camps
have cleared up and smoothed the temporary lands that were occupied but
have not greened and restore them for farming; only the lands of 22#
construction camps of Gegentang Tunnel exit and Yangtianchong open
channel have been returned for farming. The four camps, 13#, 15#, 18#,
20# did not cleared up the sites when removed, which exerted certain
influences on the environment.
The personnel of Qingshuihai Reservoir beside Haiwei Village did
not remove the camp buildings after removal. As the reservoir water of
Qingshuihai is not intensive owing to many years of drought, it will
submerge the remaining buildings and have certain impact on the water
quality of Qingshuihai when the water storage is increased.
After the removal, the seven construction camps (namely, 8#, 9#,
10#, 13#, 15#, 18#,20# ) did not clear up the solid wastes generated
during the construction period, which polluted the environment.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
31
5. Conclusion and recommendation
5.1Conclusion
(1)Monitoring of water quality
As of June 30, 2013, the environment monitoring during
construction period of Qingshuihai water supply project has been
implemented for half and five years. Project engineering construction in
the current monitoring has been completed and this monitoring is
conducted focusing on the environment of surface water.
Most contractors well kept their promise of protecting environment
during construction period, and mitigation measures of environmental
protection and environment monitoring measures have been carried out
effectively. The surface water beside most construction sites was not
influenced by the construction and water quality is up to the Class II
under GB3838-2002 Environmental Quality Standard of Surface Water.
The reasons why the water quality of Qingshuihai reservoir
decreased from II before the construction to III are mainly as follows:
factors such as large amounts of overland runoff in rainy seasons and
unstable water quality in the primary water storage period.
(2)Recovery of temporary occupied lands of construction camps
upon completion of the construction
The project has been completed and contractors have all removed
from the construction sites. Most temporary lands of camps have been
cleared up when contractors removed. However, some camps (namely, 8#,
9#, 10#, 13#, 15#, 18#, 20#) have not been dealt with when the
contractors removed and there left solid wastes and household refuse
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
32
generated during the construction period, which exerts some impacts on
the around environment.
5.2 Recommendation
Subject to the site survey of each construction camp by the research
group and taking the environment monitoring results into consideration,
the following mitigation measures about the Project (from August, 2012
to June, 2013 ) are put forward:
(1)When all site offices are removed, it is required that temporary
occupied lands should be cleared up and restored for farming;
(2)The camps that have been removed and cleared up the sites
shall recover or return ecological vegetation of the temporary
construction lands for farming;
(3)The camps that have been removed but not cleared up the sites,
shall clear up and remove the solid wastes among which building wastes
shall be assigned to a qualified unit for removal; at the same time,
leveling the lands and ecological recovery shall be conducted.
( 4)Construct side slope for all the built roads to reinforce
protection, and plant vegetation in planting slope when necessary to
prevent natural disaster such as mud and rock flow and landslide, etc.
(5)Pay close attention to the landform evolution around the
subsidence area of Dapingdi Tunnel Exit to prevent the expansion of
subsidence area as the result of continual construction which shall
aggravate the impacts. When the condition is allowed, it is desirable to
backfill the subsidence area as soon as possible and recovery the
vegetation of this area.
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
Appendix: Photo of construction sites
Access road of Shiqiaohe Reservior Remaining Shiqiaohe Construction Camp
Xintianhe Construction Camp has been cleared up Tabizi Spring
Water body of Qingshuihai Reservoir Fence of Qingshuihai
beside Haiwei Village Reservoir beside Haiwei Village
The remaining Banqiaohe Construction Camp Diversion project of Banqiaohe Dam of trail operation
KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)
The remaining camp of Qingshuihai Water body from Reservoir beside Haiwei Village Haidang Tunnel Exit to Qingshuihai
Qingshuihai Dam Land condition of removed desilter of Maichong Tunnel Exit
Remaining construction camp Distribution gate of Jinzhongshan
of Maichong Tunnel Exit
Jinzhongshan Reservior The dam of Jinzhongshan