+ All Categories
Home > Documents > Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report...

Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report...

Date post: 08-Aug-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
53
Environmental Monitoring Report Semestral Report July 2013 PRC: Kunming Qingshuihai Water Supply Project Prepared by Kunming Municipal Government for the People’s Republic of China and the Asian Development Bank.
Transcript
Page 1: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

Environmental Monitoring Report Semestral Report July 2013

PRC: Kunming Qingshuihai Water Supply Project Prepared by Kunming Municipal Government for the People’s Republic of China and the Asian Development Bank.

Page 2: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

1

Kunming Qingshuihai Water Supply Project

Technical Report of Environment Monitoring

(AUGUEST 2012 –JUNE 2013)

Yunnan University

AND

Xishan District Environmental Monitoring Institution, Kunming

July, 2013

Page 3: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

2

Content

1. INTRODUCTION ...................................................................................... 1

1.1 Project Background ............................................................................ 3

1.2 Project Summary ................................................................................ 4

1.3 Project Components ............................................................................ 5

1.4 Project organization structure ............................................................. 7

1.5 Implementation of Environment Monitoring Program ...................... 9

1.6 Implementation of Environmental Responsibility Scheme .............. 10

2. PROGRESS ................................................................................................ 1

2.1 General Progress ................................................................................. 1

2.2 Project Progress .................................................................................. 1

3. IMPLEMENTATION OF ENVIRONMENTAL PROTECTION PROGRAM

......................................................................................................................... 1

3.1 Targets of Environment Management Program ................................. 1

3.2 Implementation of Mitigation Measures ............................................ 1

3.3 Information Disclosure ....................................................................... 6

3.4 Implementation of Staff Training ....................................................... 6

4. ENVIRONMENTAL MONITORING ..................................................... 21

4.1 Monitoring of water quality .............................................................. 21

4.2 Clean-ups of the camps upon completion of the construction ......... 28

5. CONCLUSION AND ADVICE ............................................................... 31

5.1Conclusion ......................................................................................... 31

5.2 Advice ............................................................................................... 32

Appendix:Photos of Construction Sites

Attachment: Monitoring Report (K.X.H.J.Z[2013] No. 398)

Page 4: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

3

1. Introduction

1.1 Project Background

The purpose of the Kunming Qingshuihai Water Supply Project

(hereinafter referred to as “The Project”) is to ease the recent tension of water

supply in Kunming. It plans to divert 104 million cubic meter water from the

Xiao Jiang River basin in Dongchuanying of Xundian County in northern

Kunming to the Jinzhongshan reservoir in Songming County, serving as water

supply for the New Airport Development Zone and the East Development Zone.

On December 3, 2004, KMG gave its consent to the implementation fo the

Project through K.Z.F.[2004] No.61 Written Reply on Planning Report of

Kunming Water Supply Project, thereafter, China Water Conversation and

Hydropower Science academy and Yunan Provincial Water Conservation and

Hydropower Investigation and Design Institute conducted the Environment

Impact Assess for the Project.

The projected construction duration of the Project is five and half years

(from early 2008 to June 2013). The Environmental Impact Assessment Report

on the Project (hereinafter referred to as “EIA”) requires environmental

monitoring during the entire construction and operational period, mitigation of

the impact on the project affected area, examination of the effectiveness of

applied mitigation measures, and prompt adjustments of responding measures

based on analytical results of monitoring reports.

In June of 2010, the Kunming Water Supply Group Qingshuihai Water

Sources Development and Construction Branch Company(hereinafter calls as

"the Employer”) contracted Yunnan University to prepare the Environment

Monitoring Report for the Project during the construction period. As of

February of 2012, Yunnan University has Subcontracted with Kunming Xishan

Page 5: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

4

District Environmental Monitoring Institute (XEMI) to conduct five times of

environment monitoring on construction activities from the year of 2010 to

2012 (twice per year for the year 2010 and 2011, once in the first half of 2012)

and it has submitted the Environmental Monitoring Report to the Employer.

Based on monitoring results, the Employer informed contractors to make

rectifications within a certain time limit regarding environmental issues during

construction period. Therefore, the environmental impacts during the

construction period have been effectively minimized.

Because the Project was basically completed in July of 2012, all

management responsibilities of reservoirs, water conveyance facilities as well

as related equipments was transferred to the new established project operation

unit—Kunming QingYuan Water Supply Co., Ltd. Therefore, this report is

mainly about the monitoring of the environmental recovery after completion of

the Project. Based on the site surveys and by combining Technical Report of

Monitoring for Kunming Qingshuihai Water Supply Project (from 2010 to

2012), and the monitoring report of May of the year 2013, make a assessment

on the environmental restoration after completing the project. According to the

analysis of previous monitoring reports, we provide corresponding improving

suggestions. This report will provide a theoretical context for further

minimizing environmental impact of project construction.

1.2 Project Summary

The basic information about the Project Loan is provided in Table 1-1.

Table 1-1: Basic Information

ADB Loan No. : 2388-PRC Project Title : Kunming Qingshuihai Water Supply

Project Borrower : Ministry of Finance, People’s

Page 6: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

5

Republic of China Executing Agency : Kunming Municipal Government Implementing Agency : Kunming Water Supply Group

Company Limited Total Estimated Cost : $255.94 million ADB Loan Amount : $80 million Date of ADB Board Approval : 12 December 2007 Date of Signing of Loan Agreement : 26 March 2008 Date of Loan Effectiveness : 20 June 2008 Original Loan Closing Date : 31 December 2013 Revised Loan Closing Date : N/A Date of Signing of Implementation Consulting Contract

: 17 February 2009

Date of Start of Implementation Consulting Services

: 1 March 2009

Type of This Monitoring Report : The sixth Progress Report Period Covered by This Progress Report

: 1 August 2012 – 30 June 2013

1.3 Project Components

The Project comprises the diversion of water from 4 locations on the upper

reaches of tributary streams to the Xiaojiang River. The Project consists of the

water sources component and the conveyance works component:

A:Water sources component

The water sources component includes six dams of Shiqiaohe river,

Banqiaohe river, Xintianhe river, Tabizi Spring and Jinzhongshan. Water will

be transferred through a network of tunnels and channels to the Qingshuihai

reservoir. From Qingshuihai reservoir, the water will be transferred through a

combination of pipes and tunnels to two existing reservoirs. The main receiving

reservoirs will be the existing Jinzhongshan Reservoir (to be enlarged by a new

dam, about 600 m upstream from the old dam in Songming County) and

Songhuaba Reservoir (an existing reservoir) to the north / northeast of the

Page 7: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

6

present Kunming City. Specifications for these planned works are shown in

Table 1-2.

Table 1-2 Summary of Reservoir Works

Item Unit Dam

Qingshuihai Banqiao River

Shiqiao River

Xintian River

Jinzhongshan Reservoir

Location Xundian County

Baizai River

Xundian County

Banqiao River

Xundian County

Shiqiao river

Xundian County

Xintian River

Guandu District

Duilong RiverCatchment Area km2 34.5 102.0 26.6 56.6 23.4 Average Annual

Run-off m3 24,700,000 81,740,000 18,530,000 41,980,000 9,770,000

Total Storage m3 154,170,000 2,515,000 1,835,000 9,600,000

Preferred Dam type Earth Earth Concrete Gravity

Concrete Gravity Earth

Foundation Sandy, Clay Lacustrine formation

Basalt Basalt Mudstone/ Shale Basalt

Seismic Classification

(Intensity) Class VIII VIII VIII VIII VIII

Dam Height m 13 61.5 29 28.9 39.7

Crest Length m 206.2 133.7 81 67.5 111

B:Water conveyance works

The water conveyance system will be operated by gravity, through tunnels

and pipes to the Tongxin Gate. At Tongxin Gate the regulated flow from

Qingshuihai can be split for discharge into Songhuaba Reservoir and

Jinzhongshan Reservoir.

The tunnel and pipeline works are shown in Table 1-3.

Table 1-3: Water Conveyance Works

Section Tunnels Length (km)

Aqueducts/Channels Length (km)

Total km

Shiqiao Dam to Qingshuihai 13.92 0 13.92 Banqiao Dam to

Qingshuihai 2.4 0 2.4

Qingshuihai to Tongxin diversion gate 36.97 6.15 43.12

Page 8: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

7

Tongxin diversion gate to Jinzhongshan Reservoir 5.04 2.56 7.6

Tabizi diversion gate to Qingshuihai Reservoir _ 5.7 5.7

The Project submerged six roads near reservoirs; two of them had been

rehabilitated, while the rest four roads will be the subject of compensation to

local government, as shown in Table 1-4.

Table 1-4: Road Works Qingshuihai Qingshuihai Qingshuihai Qingshuihai

Qingshuihai Haiwei to Management 3.8 4 Holiday village road 2.3 Compensate Qinghai to Haiwei 3.3 4.4

Sub-total 9.4 8.4 Jinzhongshan Reservoir

Laobao to Deshi 4 Compensate

Xintian Reservoir

Rural road 3.5 Compensate

Banqiao Reservoir

Rural road 4.2 Compensate

1.4 Project organization structure

Figure 1-1: Schematic Organization Structure for the Project

Page 9: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

8

Note:

a) PLG membership: Kunming Development and Reform Commission, Kunming Finance Bureau, Kunming Water Bureau, Kunming Municipal Government Administration, Kunming Construction Bureau, Environment Protection Bureau, Planning Bureau, Water Supply Group, Land and Resources Bureau, Resettlement Bureau, Public Utility Bureau, New Airport Management Commission, Forest Administration Bureau, Reservoir Dianchi Administration Bureau, Songming County, Xundian County, and Guandu District.

b) PMO: fourteen full-time staff on administration (6), engineering / technical (5), and accounting / finance (3). c) IA: KWSG Qingshuihai Water Source Development and Construction Branch will be the project implementing unit responsible for project management and operations, implementation of resettlement, and environmental monitoring.

The Kunming Municipal Government (KMG) is the Executing Agency for

the Project. The Project Leading Group (PLG) has been set up, with the

responsibility of policy guidance and high-level coordination during

implementation. Headed by the Vice Mayor, the PLG comprises representatives

Page 10: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

9

from the Kunming Financial Bureau, Kunming Development Reform

Commission, related agencies, and county governments. The PLG meets as

required and will be maintained until project completion.

The PMO has been established within Kunming Development and Reform

Commission. It serves as the secretariat for the PLG and is responsible for

coordinating the implementation of project activities. The specific duties of the

PMO include: (i) ensure adequate interdepartmental cooperation and

interagency coordination, (ii) monitor the progress of project implementation,

and (iii) coordinate communication and interaction among ADB, KWSG and

agencies concerned.

The IA is Kunming Water Supply Group Co. Ltd. (KWSG), which is a

limited liability company incorporated under the 2004 PRC Company Law. The

KWSG is responsible for operating and managing project facilities, direct daily

project management, construction supervision, preparation of progress reports

to the PMO for submission to ADB, and strategic planning for water supply and

management services and operations. KWSG is well organized, with experience

of implementing World Bank and JBIC loan projects. A project implementation

unit (PIU) has been established in the KWSG and is responsible for undertaking

detailed implementation activities. KWSG will retain the services of design

institutes, procurement agencies, and construction supervision companies to

assist with implementation activities.

1.5 Implementation of Environment Monitoring Program

Internal environmental monitoring consists of two types. The first type

requires field sampling and lab analysis that is undertaken by a licensed

environmental institute, for such environmental parameters as water quality, air

quality and noise levels. The second type refers to visual inspections of such

Page 11: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

10

things as soil erosion, restoration of vegetation, solid waste disposal and so on.

The field sampling and lab analysis has been conducted, according to the

environmental monitoring program as stipulated in the SEIA, by the Xishan

District Environmental Monitoring Institution (XEMI) under contract to the IA.

Field inspections have been undertaken by the on-site environmental engineer

of the contractor, Environmental Management Office(EMO)officers and

PMO officers on a regular basis.

External monitoring is undertaken by Kunming Xishan District

Environmental Monitoring Institution. Yunnan University is responsible for

reports preparation, and responsible for advising the PMO, IA and construction

contractors on the environmental protection in construction activity.

The implementation status of the environmental monitoring program, as

proposed in the SEIA, is presented in the right column of the Table 1-5. The

detailed results of field sampling and lab analysis are presented in the ensuing

chapter. In summary, the environmental monitoring program has to date been

implemented properly.

1.6 Implementation of Environmental Responsibility Scheme

An environmental management system, consisting of inspection,

monitoring, reporting, and initiating corrective actions or measures, was set up

prior to project implementation. In the design stage, PMO and IA passed the

EMP to the design institutes for incorporating mitigation measures into the

detailed designs of each subproject. The EMP was reviewed and confirmed at

the end of the detailed design, and was finally passed to selected contractors. To

ensure that contractors will comply with the EMP’s provisions, PMO and IA

prepared and provided the following specification clauses for incorporation into

the bidding documents: (i) a list of environmental items to be budgeted by the

Page 12: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

11

bidders in their proposals; and (ii) environmental clauses for contract conditions

and specifications.

An EMO was established by the IA prior to the start of the project

implementation. It is charged with the responsibility of coordinating and

supervising the EMP implementation. The EMO is headed a deputy general

manager of the IA. The IA has also recruited an environmental officer who also

serves as the focal point for grievance redress. Meanwhile, the PMO has drawn

the expertise from the Kunming environmental protection bureau in supervising

the environmental management system.

Yunnan University has contracted the Environmental Protection

Monitoring Station of Xishan District of Kunming (hereinafter referred to as

Xishan Institution)to conduct one environmental monitoring in The first half

of 2013. The results of the monitoring were shown in chapter five. The

implementation of the environmental responsibility scheme is shown in Table

1-6.

Page 13: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

12

Table 1-5 Implementation Status of Environmental Monitoring Program

Item Parameters Location Time and Frequency Implementing Agency

Supervising Agency Implementation Status

A. Construction 1. Work camp domestic wastewater quality

pH, SS, DO, NH3-N, TP, BOD5, COD, total coliform, oil

Internal monitoring will be conducted at all construction sites and domestic wastewater discharge area. External monitoring will be conducted at 24 camp sites

Random spot check of the domestic wastewater effluent sites One sampling each day each time, twice per year including once in dry season and once in rainy season

Internal monitoring: contractors, IA /environmental supervisor External monitoring: licensed EMC

IA KEPB

Monitoring has been conducted subject to the plan during construction period and the project has been completed without domestic sewage drainage from camps.

2. Construction wastewater and wastewater pollution mitigation measures

pH, SS, oil Internal monitoring will be conducted at all construction sites. External monitoring will be conducted at 24 sites

Random spot check of the wastewater effluent sites One sampling each day each time, twice per year

Internal monitoring: contractors, IA/environmental Supervisor External monitoring: licensed EMC

IA KEPB

Monitoring has been conducted subject to the plan during construction period and the project has been completed without sewage from construction sites.

3. Water quality of receiving water body Water source protection measures

pH, SS, DO, TP, NH3-N, BOD5, COD, total coliform, oil

Internal monitoring will be conducted at all construction sites. 200 m downstream of the dam of BQR, SQR, XTR, TDP, and the confluence of BQ river and XT river

Random spot Checks One sampling each day each time, twice per year

Internal monitoring: contractors, IA/environmental Supervisor External Monitoring licensed EMC

IA KEPB

Receiving water body was conducted by Xishan District Environmental Monitoring Institution and the monitoring results are shown in Chapter 5.

Page 14: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

13

Table 1-5 (continued) Item Parameters Location Time and

Frequency Implementing

Agency Supervising

Agency Implementation Status

4. Construction workers’drinking water source

Hardness, Mn, Fe, CC14, fecal coliform, sulfate,nitrate, residual chlorine

Drinking water source areas or water supply

Random spot Checks One sampling each time, once a year

Internal monitoring: contractors, IA/environmental Supervisor External Monitoring licensed EMC

IA KEPB

Monitoring has been conducted subject to the plan during construction period and the project has been completed. Personnel who were preparing documents in the camps used running water.

5. Air All the air pollution prevention measures

Use of dust shrouds, water spraying Maintenance and condition of vehicles and equipment. TSP, SOx, NOx

Internal monitoring will be conducted at all construction sites and nearby villages. External monitoring will be conducted at 14 sites: Haiwei, Xiniutang, Ma'anshan, Hujing, Laohaitou, Xiatuoqi, Enjia, Luoduo, Niuluzhuang, Zhujiaying, Taohua’an, Qumiao, Xiaobeidang, Gegentang

Spot check of construction sites Once per year at Peak construction period, two samplings 1 day at each location each time

Internal monitoring: contractors, IA /environmental Supervisor External Monitoring licensed EMC

IA KEPB/XEPB

As the project has been completed, monitoring of ambient air quality was not conducted this time.

Table 1-5 (continued)

Page 15: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

14

Item Parameters Location Time and Frequency Implementing Agency

Supervising Agency Implementation Status

6. Noise Noise pollution control measures

Leq (dB[A))

Same locations as air quality monitoring

Random, but at least once monthly, 1day each time and two samples each day: once during daytime, once during nighttime Random, but at least once a year, 1 day each time and two samples each day: once during daytime, once during nighttime

Internal monitoring: contractors, IA /environmental Supervisor External Monitoring licensed EMC

IA KEPB/XEPB/ SEPB

As the project has been completed, monitoring of ambient sound quality was not conducted this time.

7. Xundian fish

Behavior and location of spawn sites of Xundian fish

Qingshuihai reservoir First 5 years, from April to June.

External monitoring: Fishery Research Institute

KEPB KEPB

The 2010 fish ecology survey didn’t find the Xundian white fish (Anabarilius xundianensis) in the water of Qingshuihai, and as the project has been completed no further inspection is conducted.

Note: the above progress as the deadline to June 30, 2013。

BOD5 = 5-day biochemical oxygen demand, CCl4 = carbon tetrachloride, CODcr =chemical oxygen demand , DO = dissolved oxygen , Fe = iron, Leq = equivalent continuous noise level, Mn =manganese, NH3-N = ammonia nitrogen, NOx = nitrogen oxides, Q&S = quarries and spoil sites, Rd =roads, SOx = sulfur oxides, SS = suspended solids, T&P = tunnels and pipelines, TP = total phosphorus, TN =total nitrogen,TSP = total suspended particles,

Page 16: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

1

Table 1-6 Fulfillment of Environmental Responsibilities Phase Agencies Environmental Responsibilities Status of Fulfillment

Preparation

Environmental Institutes KMG, YPG

Preparation of EIA for Project and other project documentation such as SEPP and Strategic Environmental Assessment Review and approval of project documentation, and water permit, SEPP

Fulfilled.

PMO, SEPA

Review and approval of the EIA and EMP Fulfilled.

ADB, PMO

Review and approval of the SEIA including the EMP Fulfilled.

Design DI

Updating the EMP in cooperation with environmental institutes, and incorporating mitigation measures in engineering detail designs and contracts

EMPs were reviewed and no update was necessary. The mitigation measures were incorporated into the detailed engineering designs.

PMO,KWSG Review and approval of environmental measures Fulfilled.

Tendering

PMO, contractors, KWSG Incorporating EMP clauses in the bidding documents The mitigation measures were incorporated into the tendering documents and construction contracts.

Construction

PMO, KWSG, KEBP, county EPBs

Advising on implementation of mitigation measures Fulfilled.

Contractors

Implementation of mitigation measures Fulfilled.

KWSG Internal inspection and monitoring Fulfilled.

KEPB, county EPBs

External monitoring and inspection of implementation of mitigation measures.

Fulfilled.

Operation KWSG

Implementation of mitigation measures Internal environmental monitoring and inspection

Not yet due.

KEPB, county EPBs

Periodical and random environmental monitoring and inspection of environmental compliance

Not yet due.

Page 17: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

1

2. Progress

2.1 General Progress

As of June 30th, 2013, except Civil Works Contract Package No.16, all

other parts of the Project have been completed and accepted. Reservoirs, water

conveyance facilities as well as related equipments had all been transferred to

the project operation unit—Kunming QingYuan Water Co., Ltd.

The Civil Works Contract Package No.16 is not accepted because its

concrete lining works of 1# Adit of Tongxin Tunnel has not been completed,

which is expected to be completed in the middle of July.

2.2 Project Progress

It has been mentioned in the Technical Report (2012) of Monitoring for the

Project that in April 2012, the Project has achieved the goal of trial water supply

required by KMG in due time. During the period of trial operation, which is

form 1 April, 2012 to 13 April, 2013 Qingshuihai has accumulatively supplied

26 million square water to Kunming’s main city, Chenggong district and the

Airport Economic Zone, with the average water supply of 69000m3/day.

Table 2-1 Water Environment Monitoring Spots of the Project Category Construction

Camp No. Location Progress Category

Water sources

construction

1# Banqiao River Construction, Under Banqiao River Dam 200m.

The project

has been completed

and put into in

process of trial

operation

The camp has been withdrawn. 2# Shiqiao River Construction camp,

Under Shiqiao River Dam 200m.

3# Xintian River Construction camp, Under Xintian Dam 200m. The camp has been

withdrawn. 4# Tabizilong Pool Construction Camp, Under Quanliu construction camp 200m.

5# Water body of Qingshuihai Reservoir beside Haiwei Village

The construction camp has not been

withdrawn

Page 18: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

2

Category Construction Camp No. Location Progress Category

6# Water body of Qingshuihai Reservoir beside Maichong Tunnel Entrance

The camp has not been withdrawn.

Water Diversion

Construction

7# Construction Camp of Xiatuoqi Tunnel Entrance and aqueduct The construction

camp has been withdrawn. 8#

Construction camp of Enjia Tunnel Entrance and aqueduct and open channel

Water Diversion

Construction

9# construction camp of Enjia Tunnel Exit and Haidang Tunnel Entrance

The project

has been completed

and put into in

process of trial

operation

The construction camp has been

withdrawn.

10# Banqiao River Tunnel Exit construction Camp

11# Construction Camp of Maichong Tunnel Exit and Maichong open channel

12# Dapingdi Tunnel Exit, Bailiqing Tunnel Entrance

13# Xixian Trench Construction Camp

14#

Construction camp of Xiaobeidang open channel, 12th maintenance gang inverted siphon, Dashuidong Tunnel entrance

15#

Construction camp of Dashuidong Tunnel exit, aqueduct, Qinjiazhuang Tunnel, aqueduct, Longjia Village Tunnel entrance

16# Construction camp of Pujia Mountain Tunnel exit, Laofangziqing aqueduct, Dahu Mountain Tunnel exit

17# Construction camp of Dong Village Tunnel exit and Xi village inverted siphon

18# Construction camp of Dashanqing Tunnel exit and Moshiqing Tunnel entrance

19# Construction camp of Baishi mountain Tunnel exit, aqueduct, Jinji Mountain Tunnel entrance

20# Construction camp of Jinji Mountain Tunnel exit, aqueduct, Xin Village aqueduct and Tunnel entrance

21# Construction camp of Xin Village Tunnel exit, gegentang aqueduct and Tunnel Exit

22# Construction camp of Gegentang Tunnel exit, Qiutianchong open channel

23# construction camp of Tongxin Reservoir diversion gate

The camp has not been withdrawn.

Page 19: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

3

Category Construction Camp No. Location Progress Category

Water source

construction 24# Jinzhong Mountain Reservoir

construction camp

Note:progress report updated to June 30, 2013

In Table 2-1, equipments that have not been withdrawn in the project

points of 1# and 2# needs to be guarded, and personnel of the site office are

collecting materials of the project points of 6#, 23# and 24#. Therefore, site

offices of these five project points have not been withdrawn yet. Workers in

other works have all been withdrawn, and the temporary construction built in

the duration of construction have been demolished in most parts of work points,

except work points of 1#, 2# and 5#.

During the construction of the Project, the ground above Daping Tunnel

sank, the exit sections of Haidang Tunnel and Yujiazhuang Tunnel had the

phenomenon of subsurface filtration, and Dashuidong Tunnel collapsed and had

the phenomenon of subsurface filtration, the main reason for such problems are

the geological conditions of these areas were poor. But these problems have

been properly solved.

Page 20: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

1

3. Implementation of Environmental Protection Program

3.1 Targets of Environment Management Program

The objective of establishing an EMP is not only to propose appropriate

mitigation measures, but also to recommend establishment of institutions or

mechanisms to monitor and ensure compliance with environmental regulations

and implementation of the proposed mitigation measures. Such institutions and

mechanisms will seek to ensure continuously improving environmental

protection activities during preconstruction, construction, and operation in order

to prevent, reduce, or mitigate adverse impacts. The EMP drew on the

individual EIA reports and on the PPTA discussions and agreements with the

relevant government agencies.

3.2 Implementation of Mitigation Measures

The important aspects of the implementation of mitigation measures are

highlighted as follow:

1) Environmental Clauses in Civil Works Contracts

All civil works contracts contain provisions on workers and community,

environmental protection and protection of physical and cultural relics. The

environmental clauses are summarized as below.

Workers’ and Community Safety

The contractor will take precautionary measures to ensure workers’ safety.

Protective devices will be worn at all times for any person entering the

construction site. Safety training shall be undertaken for workers and staff. In

case of bodily harm to any worker, the contractor will have full responsibility

for medical care and compensation according to PRC labor law. The contractor

Page 21: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

2

will also be responsible for any bodily harm and property damage caused by

construction activities on site or in the vicinities, including land occupation.

The contractor is required to strengthen safety management, especially in

regard to the use of flammables, explosives, toxic and corrosive substances.

Before the start of construction, the contractor shall submit to the independent

construction supervision agency an emergency preparedness and response plan.

Environmental Protection

The contractor shall comply with all relevant laws and regulations on

environmental protection, and will take precautionary measures to minimize any

potential impact on the environment. It will be responsible for restoring and

rehabilitating the environment to its original state at its own costs. An

environmental management plan (EMP) with mitigation measures will be

prepared and submitted to the construction supervision agency for approval

before the commencement of construction.

The contractor will treat and dispose its construction wastewater, sewage

from workers’ camps and solid wastes properly so as not to cause any damage

to the environment, drinking water sources and public health. The disposal of

spoils and solid wastes shall not obstruct flood ways and risk public safety. All

slopes shall be protected with retention walls, proper drainage systems and

vegetation to avoid geological hazards. Noise, dust, air emissions, wastewater

and waste oils will be controlled to minimize annoyance to local communities.

Natural and Cultural Relics

All physical and cultural relics discovered at the construction sites are

owned by the state. The contractor will report any such discoveries immediately

to the local relics protection authority and in the meantime immediately inform

the construction supervision agency. The contractor shall take effective

measures to protect the unearthed physical and cultural relics. The contractor

Page 22: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

3

will be held responsible for any loss of damage to the discovered relics, and

prosecuted for any delayed and fraudulent reporting.

2) Pollution control measures proposed by Technical Report (2007) of

Monitoring for the Project

Spoil Disposal: Sixty five spoil disposal sites have been located

throughout the Project construction area for the disposal of a net total (after uses

for fill) of 2.2115 million m3 of excavated spoil. The SEPP provides a detailed

analysis of all erosion sources as mitigation measures to prevent or control

them. It includes setting principles and erosion control prescriptions for spoil

dumps. These have been incorporated into the EMP.

Erosion Damage: Erosion potential from all construction sites, including

preparation of resettlement areas and road making, was estimated at about

75,000 m3. A comprehensive Soil Erosion Prevention Report (SEPR) had been

prepared. It provides a detailed analysis of all erosion sources with mitigation

measures to prevent or control them. It includes erosion control prescriptions for

borrow pits and quarries, dam and infrastructure construction, and construction

work areas and camps. These have also been incorporated into the EMP. To

date, contractors have taken measures to control soil erosion. Soil erosion

measures during construction include minimizing land surface disturbance and

exposure and use of settlement ponds. Upon completion of construction, all the

construction sites will be re-vegetated with trees and grasses.

Construction Wastewater: Wastewater produced during the construction

period come from washing aggregates, pouring and curing concrete, as well as

oil-containing wastewater from machinery repairs. The major pollutant in

construction wastewater is suspended solids. Settlement ponds are used to retain

the sediments in the construction wastewater before they are discharged into

Page 23: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

4

rivers. The settlement ponds are cleaned when they are filled up with sediments.

Tires of construction vehicles are cleaned with spray water before they leave the

construction site. And the oil-water separators used for treating oil wastewaters.

Recycled water has been used to spray for dust control. All sludge was removed

from site.

Domestic Wastewater: Daily living wastewater produced by the

construction staff is about 440 m3. Deep latrines and seepage pits have been

installed in the each camp. After Project completion, the sites will be closed

only after waste has been effectively treated or removed, in order to minimize

pollution in the rivers.

Gaseous Air Pollution: Construction will consume about 8,925 tons of

diesels, releasing significant amounts of gaseous SOx, CO and NOx. The major

sources of air emissions are construction equipment and construction vehicles.

The vehicles delivering granular or fine materials to the sites were covered with

tarpaulin sheets. Vehicle speeds are controlled on construction sites. Equipment

was maintained to a high standard to ensure efficient running and fuel-burning.

High-horsepower equipment was installed with tail gas purifier. Atmospheric

monitoring was carried out during the construction period. A regular inspection

and certification system has been initiated to make sure that exhaust gases

complied with emission standards.

Dust: Construction sites will produce fugitive dust from material storage

areas, waste dump sites, concrete mixing and excavation sites. Material

stockpiles and concrete mixing equipment was equipped with dust shrouds. The

operators regularly maintained the shrouds to ensure their effective operation.

For both construction sites and construction roads, water spraying for the

suppression of dust was standard site management practice.

Page 24: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

5

Noise: Noise was generated by construction machinery (excavators,

bulldozers, conveyers, concrete mixers) and transport vehicles. Works were

scheduled according to the noise rating of the machinery used and the distance

to sensitive receptors to achieve Emission Standard of Environment Noise for

Boundary of Construction (GB12523-2011). Noise impacts for transport

vehicles were reduced by attention to road surfaces near village areas and the

erection of temporary noise barriers.

Household refuse: In the five and half years of construction, a total of 6000

tons of waste were be generated. The accumulation of waste will have serious

impact on worker’s health. Thus, each construction camp was equipped with

dustbins, which will be regularly sprayed with pesticides, to reduce flies. In the

course of transporting domestic garbage and construction materials, loads were

sealed or covered, to avoid spillage en route.

Construction Wastes: Construction and demolition wastes could have

adverse impacts on surrounding environments. The solid wastes that could not

be collected at the waste dump, and could not discarded in a way which will

damage farmland or the surrounding environment. Solid waste were stored and

regularly transported off-site for disposal.

Spills of Hazardous Materials: A construction materials handling

protocol (e.g., storage away from watercourses and provision of retention areas

to contain accidental spills of toxic, hazardous, and harmful construction

materials, oil and petroleum products, and asphalt materials) were prepared and

applied to prevent soil and surface/ground water pollution.

The implementation status of the mitigation measures, as proposed in the

SEIA, is presented in the right column of the Table 3-1 (this table and the tables

for this chapter thereafter are placed at the end of this chapter). In summary, the

Page 25: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

6

mitigation measures have to date been implemented effectively.

3.3 Information Disclosure

Bulletin boards have been erected at each construction site, which contains

a description of the project, layout map, construction safety, labor standards,

environmental and health standards, name of the contractor(s) and names and

contact information of the on-site managers and company executives.

3.4 Implementation of Staff Training

The proposed institutional strengthening and capacity building program in

the EMP and the status of implementation of the proposed capacity building

activities are presented in Table 3-2. In summary, the institutional strengthening

and capacity building programs has to date been implemented well.

Page 26: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

7

Table 3-1 Implementation Status of Mitigation Measures Impact Factor/

Stage

Environmental Impacts and

Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation Status

A. Preconstruction 1. FS stage Site/alignment

selections The recommended sites/pipeline routes for the individual project components were selected from various alternatives so as to minimize adverse impacts on the environment.

IA, DI, and EIA team

EA, KMG, YEPB, KEPB

Implemented during project preparation

EIA report As required by law, ensure that the EIA has been prepared for the Project.

EIA team on behalf of IA

EA, SEPA, YEPB, KEPB

Implemented during project preparation

Soil Erosion Prevention Plan

As required by law, ensure that the SEPP has been prepared for the project.

DI on behalf of the IA

EA, YEPB

Implemented during project preparation

Public consultations

Hold two rounds of public consultations on environmental issues, poverty, and resettlement during the project design and EIA preparation.

EIA team, IA, TA team

EA, YEPB, KEPB

Implemented during project preparation

Resettlement plan

As required by law, prepare the RP for the project to required ADB and PRC standards.

DI

EA, YWRB, MWR

Implemented during project preparation

2. Design stage Updating EMP

Update mitigation measures defined in this EMP and incorporate them into the detailed design to minimize adverse environmental impacts.

DI, IA

EA, KEPB, YEPB

The mitigation measures were appropriate and ad

equate, and that no revision was necessary.

Land take confirmation

Update the RP and incorporate it into the detailed design.

DI, IA

EA, YWRB, MWR

Implemented during project preparation

Endangered fish research Undertake additional studies on the reproductive

habits of xundian white fish to help protect this special species in Qingshuihai.

DI EA, YWRB,

MWR

The principal has commissioned Yunnan University to conduct

this research Qingshuihai

reservoir water quality modeling

During the detailed design phase, use a multi-dimensional model to predict the degree of reservoir stratification that might occur and assist in the appropriate design of a multi-level offtake structure.

DI, IA

EA, YWRB, MWR

Implemented during project preparation

Page 27: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

8

Table 3-1(continued) ImpactFactor/Stage

Environmental Impacts and Issues

Mitigation Measures Implementing Agency

Supervising Agency

Implementation Status

Annual flow of downstream

xiaojiang River reduced by 11.6%

KWSG will commission further survey during the detailed design period to collect data on water use and in-stream ecology in the downstream reaches of the 1iaojiang River (to confirm initial finding of minimal impact).

DI, IA

EA, YWRB, MWR

Related data have been collected and the impacts of the project have been

minimized

Water transfer issues within the

basin: reduction of downstream flows

of Banqiao and Shiqiao dams

The will be prepared by the IA following the completion of detailed design and before commissioning of reservoirs.

DI, IA

EA, YWRB, MWR

Executive agency has finished

detailed design before trail operation

Sediment buildup in source reservoirs

To protect Qingshuihai from sediment transfer from source areas, each dam will be designed with a low-level sluice to maintain a slope on the silt deposited near the dam wall to ensure that silt is kept clear of the level of the offtake by periodic flushing. A Sediment Flushing Plan will be prepared by the IA and incorporated into operational maintenance programs .

DI, IA

EA, YWRB, MWR

A Sediment Flushing Plan

prepared by the IA and incorporated into operational

maintenance programs.

Dam safety and function

i. Confirm reservoir rim stability and identify any adverse slopes in the design phase.

ii. Investigate potential rock joint instability and slope/foundation failures including drilling of boreholes and e4-1cavation of tunnel adits at the larger dams.

iii. Long-term seismic movement of the xiaojiang Fault has been estimated at about 200 mm over 100 years, while sudden movement due to a Magnitude I4-1 event is estimated to be about 1.9 m. Include in the designs substantial filter widths and sufficient freeboard to accommodate any potential settlement.

DI, IA

EA, YWRB, MWR

The work about the Dam safety and

function was completely

finished by DI and IA

Page 28: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

9

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and Issues

Mitigation Measures ImplementingAgency

SupervisingAgency

Implementation Status

3. Bidding and

constructionpreparation

Bidding documents and contractors’ qualifications

i. To ensure initial environmental capability among contractors, prepare environmental prequalification clauses and specifications to be included in the prequalification package to contractors.

ii. Prepare an environment section in the terms of reference for bidders.

iii. Select spoil disposal sites based on specific criteria in the SEPP, and as revised by the EIA. Define spoil disposal sites, borrow pits, and quarry locations in the construction tender documents.

iv. Prepare environmental contract clauses for contractors, namely the special conditions (e.g., reference EMP and monitoring table).

v. Prepare covenants for loan agreement as defined in the EMP.

IA EA, KEPB, YEPB,

Environmental provisions and clauses were included

for bidders and construction and supply

contracts.

Complaint and Information Office or appointed person

i. Establish a complaint and information office or appoint a responsible person before starting the construction.

ii. Ensure that staff at the office is well trained to handle crisis situations or conflicts with residents.

Contractors IA, EA

A deputy manager was appointed as the

responsible person. An environmental officer was recruited in Qingshuihai

(IA) prior to construction.

Environmental Operation and Supervision

Manual

As per the contract for approval by IA, require contractors to prepare a Site Environmental Management and Supervision Manual.

Contractors IA, KEPB The contractors prepared and submitted an

environmental operation and supervision manual and approved by the IA.

Environmental protection training

Invite environmental specialists and/or officials from YEPB/KEPB and/or WRB to provide contractors with training on implementing and supervising environmental mitigation measures.

IA YEPB, KEPB

IA and EMO in Qingshuihai organized EMP training for construction managers and engineers.

Page 29: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

10

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation Status

Resumption of land and property process and management.

i. Establish a resettlement office comprising localgovernment officials to manage the resettlementprocess.

ii. Conduct community consultation programs andensure that information about entitlement based onthe Land Administration Law is disseminated.

iii. Ensure that all relocation and resettlementactivities are reasonably completed beforeconstruction starts on any subproject.

IA

EA, KMG

RO was established. The resettlement information brochure (RIB) was distributed to all APs and posted in local communities. APs were resettled before construction started.

B. Construction The construction period is 5 year and a half span 1. Water Wastewater

from construction camps

Install deep latrines and seepage pits in the camps. After project completion, vacate the sites only after waste has been effectively treated or removed.

C ontractors IA, KEPB, County EPBS

Each construction camp has disposed of wastes effectively before removal.

Tunnelling wastewater

Wastewater from tunnelling will be collected in sediment tanks, retention ponds, and filter tanks to remove silts and oil, and then be reused for the tunnelling operations. Process should follow the flow paths and specifications specified in the SEPP.

Contractors

IA, KEPB, County KWRB

Most construction camps have taken corresponding measures and complied with the standard of wastewater discharge during construction period

Washing aggregates, pouring and curing concrete, machinery repairs

i. Establish settling ponds, oil-water separators. ii. Use recycled water to spray for dust control. iii. Remove sludge from site.

Contractors

IA, KEPB, County KWRB

Complied with.

Page 30: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

11

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and

Issues

Mitigation Measures ImplementingAgency

Supervising Agency

Implementation Status

Handling of hazardous and

harmful materials

i. Prepare a protocol for handling and disposing of construction materials which includes spill responses, and apply it to prevent soil and surface water/ground- water pollution.

ii. Construct storage facilities, bunds, and cleanup installations. iii. Ensure that the fuel supplier is properly licensed, follows the proper

protocol for transferring fuel, and complies with PRC regulation on Transportation, Loading and Unloading of Dangerous or Harmful Goods.

iv. Ensure that vehicles and equipment are properly staged in designated areas to prevent contamination of soil and surface water.

v. Carry out vehicle, machinery, and equipment maintenance and refueling in such a way that spilled materials do not seep into the soil.

vi. Ensure proper storage of fuels, oil etc., within secured areas on an impermeable surface.

vii. Keep fuel storage and refilling areas at least 300 m from drainage structures and important water bodies.

viii. If fuel storage and refueling areas are located in agricultural land or areas supporting vegetation, ensure that topsoil is stripped, stockpiled, and returned after completion of refueling activities.

xi. Provide oil traps for service areas and parking areas.

Contractors

IA, KEPB, County KWRB

Implemented during project

preparation subject to the requirements

2. Air Generation of dust

i. Cover vehicles carrying soil, sand, or other fine materials to and from the sites.

ii. Locate materials storage sites 300 m away from residential areas and cover them with canvas or spray with water.

iii. Spray water on construction sites and access roads twice a day. v. Equip all conveyors and hoppers with hoods or other dust control devices.

Contractors

IA, KEPB, County KWRB

Implemented during project preparation subject to requirements

Air emission from vehicles and equipment

i. Ensure that vehicle emissions are in compliance with PRC regulations. ii. Maintain equipment and machinery to a high standard to ensure efficient

running and fuel burning. Install tail gas purifier on high horsepower equipment to ensure emissions are in compliance with PRC regulations.

iii. Initiate a regular inspection and certification system.

Contractors

IA, KEPB, County KWRB

Implemented during project preparation subject to requirements

Page 31: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

12

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and

Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation

Status

3. Noise and vibration

Noise from vehicles and construction machinery

i..Ensure that noise levels from equipment and machinery strictly conform to PRC-GB 12523-90.

ii. Provide adequate route for large trucks to keep them away from residential areas.

iii. Improve the road surface near village areas. iv. Install portable noise shields near sensitive receptors such as schools,

hospitals, and residential areas. v. At construction sites within 500 m of the nearest habitation, stop

noise-generating construction work between 2200 and 0600 hours.

Contractors

IA, KEPB, County KWRB

Implemented during project preparation subject to requirements

Vibrations and blasting

i. Limit use of heavy vehicles and e4-1cessive vibrations near sensitive structures, walls, residences.

ii. Use blasting mats and design blasts to limit ground-borne vibrations and air overpressure.

Contractors

IA, KEPB, County KWRB

Implemented during project preparation subject to requirements

Domestic waste from workers’ camps

i. Provide multi-compartment collection bins for each construction camp to facilitate the reuse, recycling, and composting of solid waste. Spray the dustbins regularly with pesticides to reduce flies.

ii. Store wastes away from water bodies and regularly haul them to a suitable landfill or designated dumping site.

iii. Require the contractors to provide appropriate waste storage containers.

iv. Where appropriate, sign agreements with locals for waste disposal through local facilities and to approved disposal sites.

v. In the course of transporting domestic garbage, seal or cover loads to avoid spillage en route

Contractors

IA, KEPB, County KWRB

Implemented during project preparation subject to requirements

Page 32: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

13

Table 3-1 (Continued) Impact Factor/ Stage

Environmental Impacts and Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation

Status

4. Solid wastes Construction and

demolition wastes could have adverse impacts on surrounding environments.

i. Collect at the waste dump the solid wastes that cannot be used. Do not discard them in such a way that they will damage farmland or the surrounding areas.

ii. Store solid waste and regularly transport it off-site for disposal.

Contractors

IA, KEPB, County KWRB

The contractor has collected all the waste and transported them off-site for disposal.

5. Soil erosion and stability

Erosion from spoil disposal sites

i. Strip and stockpile topsoil. ii. Build retaining walls to safely contain spoil. iii. Provide temporary detention ponds or containment

to control silt runoff. iv. Construct intercepting ditches and drains to prevent

outside runoff from entering disposal sites, and transfer runoff from sites to e4-1isting drainage system or ponds.

v. Use clay bags for temporary protection during the dumping period.

vi. Preserve e4-1isting vegetation where no construction activity is planned, or temporarily preserve vegetation where activity is planned for a later date.

vii. Where topsoil is poor or in short supply, augment by mulched vegetation removed from inundation areas and set aside for the purpose.

viii. Rehabilitate the sites first with grass. Additional plantings only when grass has established.

Contractors

IA, KEPB, County,

KWRB,YWR

A lot of retaining walls and temporary detention ponds have been built during construction period and the contractors have adopt many measures according to prevention methods of water and soil erosion

Page 33: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

14

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and

Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation

Status

Erosion from quarries, and borrow pits

i. Strip and stockpile topsoil. ii. Provide temporary detention ponds or containment to control

silt runoff. iii. Construct intercepting ditches and drains to prevent outside

runoff from entering disposal sites, and transfer runoff from sites to e4-1isting drainage system or ponds.

iv. Preserve x-1isting vegetation where no construction activity is planned, or temporarily preserve vegetation where activity is planned for a later date.

v. Rehabilitate borrows sites into grassland, woodland, or farmland after closing.

Contractors

IA, KEPB, County EPBS, KWRB, YWR

As the above item.

Erosion from construction sites

i. Strip and stockpile topsoil. ii. Provide temporary detention ponds or containment to control

silt runoff. iii. Construct intercepting ditches and chutes to prevent outside

runoff from entering construction sites, and transfer runoff from sites to e4-1isting drainage system or ponds.

iv. Rehabilitate construction sites into grassland, woodland, or farmland at completion.

Contractors

IA, KEPB, County EPBS

Complied with.

Replanting of disturbed areas including spoil disposal sites

i. In compliance with PRC’s forestry law, the IA will undertake compensatory planting of an equivalent or larger area of affected forest trees.

ii. Replanting will use a selection of species that are suitable for this area and have the most appropriate attributes to survive and serve their designated functions.

iii. All quarries and borrow pits will be restored, where possible, to productive agricultural land or grass and woodland.

iv. Spoil disposal sites will be restored initially with grass. Additional plantings only when grass has established.

v. New plantings will be maintained during the operation period.

Contractors, IA

IA, KEPB, County EPBS KWRB, YWRB, KFB

Complied with.

Page 34: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

15

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation

Status

6. Ecological study

Disturbance to xundian white fish

While ecological studies of the fish are being completed, semiartificial breeding spots in the form of floating fish nests will be installed and maintained.

Contractors, IA

IA, KEPB, County EPBS KWRB, YWRB

The semiartificial breeding center of xundian white fish is planning by contractor and IA.

7. Social Resettlement All affected persons will be compensated and resettled in a timely and adequate manner, in accordance with the resettlement plan. Communities 948,000 (Included in RP) Resettlement environmental protection measures are garbage disposal; monitoring drinking water, air, and noise; health monitoring.

IA, Contractors,

EA, KMG, communities

Almost most of affected persons have been compensated and they are resettling.

Traffic management

i. Site and manage interim roads to avoid traffic problems. ii. Select transport routes to reduce disturbance to regular

traffic. iii. Divert traffic at peak traffic hours. iv. Block and reinstate interim roads to original condition on

completion of construction.

Contractors, IA

EA, xundian And Songming Traffic authorities

Complied with

Work camp health and hygiene

i. Require contractors to safeguard environmental hygiene in the construction camps, including the quality of food and water supplies. Establish medical facilities among the camps and screen workers for health problems.

ii. Implement the HIV/AIDS action plan described in the poverty and social assessment, including awareness training for both workers and villagers.

iii. Require all construction sites to provide necessary personal protective equipment and other resources to create a safe working environment.

iv. Ensure that construction site operations comply with the PRC’s State Administration of Worker Safety Laws and Regulations.

Contractors, IA

IA, local or/and provincial health bureau

Complied with

Page 35: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

16

Table 3-1(continued) Impact Factor/ Stage

Environmental Impacts and Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation

Status

Cultural heritage protection

i. Preserve cultural heritage values where identified. In accordance with PRC regulations, no person shall destroy, damage, deface, conceal, or otherwise interfere with a relic.

ii. In case an important site is unearthed, stop work immediately and promptly refer the matter to the county, municipal, provincial, or state agencies for evaluation and decision on appropriate actions.

Contractors

IA, local or/and provincial cultural heritage bureau

So far, no cultural relics were discovered at the construction sites.

8. Water quality

Any organic materials left in the inundation area, such as trees, shrubs, and grasses will decay during initial inundation resulting in depleted DO.

i. Clear and remove all vegetation from inundation zone before flooding.

ii. Mulch vegetation and use in rehabilitation of disturbed areas.

iii. Avoid delay in construction or inundation, providing time for natural vegetation to grow back.

IA, XFB, SFB EA, KEPB, County EPBS

Complied with

Greenhouse gases with reservoirs emitting CO2 and methane

Clear and remove all vegetation from inundation zone to avoid emission of CO2 and methane (see above).

IA, XFB, SFB EA, KEPB, county EPBS

All vegetation from inundation zone were cleared and disposed with scientific methods

C. Operation 1. Water

Fish raising

Currently fish raising is allowed in the Qingshuihai Reservoir. It will be discontinued during project operation.

IA, MWR,

YWRB, KEPB, County EPBS

Not yet due.

Reservoirside commercial development

The operation of tourist villages on the foreshore of Qingshuihai Reservoir will be discontinued in the medium term.

IA, MWR,

YWRB, KEPB, County EPBS

Not yet due.

Sediment flushing from source reservoirs

Flushing operations will be undertaken in combination with wet season spillway flows and in accordance with the Sediment Flushing Plan.

DI, IA EA, YWRB, MWR

Not yet due.

Page 36: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

17

Table 3-1 (Continued) Impact Factor/

Stage

Environmental Impacts and

Issues Mitigation Measures Implementing

Agency Supervising

Agency Implementation

Status

Wastewater from the management office

i. Wastewater from the management office will be collected and hauled to the waste treatment facilities directly.

ii. A septic tank or one set of on-site wastewater treatment device will be installed for treating wastewater from management offices before being discharged into the receiving water bodies.

IA KEPB, county EPBS

Only reservoirs next to the village are are arranged with administrators, who are all the residents nearby and not accommodated in the management places.

Water quality of return waters from Kunming city reentering the river basin

i. In the developing areas of Kunming city, which will be the main beneficiaries of project water, four new WWTPs will be built with a combined capacity of 200,000 m3/day.

ii. New industrial developments will be screened to lower the amounts of water consumption and discharge, as well as reduce the discharge of pollutants.

iii. KMG will target a goal of 20% water recycling rate, using a range of measures including implementation of the “one household, one meter” policy.

IA, Kunming Drainage Company, Management Office of NADZ and EDZ

KEPB, county EPBS

Not yet due.

2. Solid wastes

Solid waste from management office

i. Provide multi-compartment collection bins to facilitate the reuse, recycling, and composting of solid waste.

ii. Sign agreements with locals for waste disposal, where appropriate, through local facilities.

iii. In transporting domestic garbage, seal or cover loads to avoid spillage en route.

IA

XEPB, SEPB, KEPB

The household refuse produced by administrators should be cleared up by local sanitation department.

Page 37: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

18

Table 3-1 (Continued) Impact Factor/ Stage

Environmental Impacts and Issues

Mitigation Measures Implementing Agency

Supervising Agency

Implementation Status

3. Ecological issues

Water transfer issues within the basin:reduction of downstream flows of Banqiao and Shiqiao dams

Implement an adaptive management approach for the control of downstream releases at Shiqiao and Banqiao river dams in accordance with detailed rules defining triggers and impact thresholds for change in the riparian release prepared by the IA before commissioning of reservoirs. Use the results of downstream environmental monitoring as feedback to influence the storage operation. This involves a monitoring and review function. Hire one person from each downstream village to monitor the water flow to downstream areas and report on livelihood changes.

IA

Downstream Village committee XEPB

Not yet due.

Invasion of unwanted aquatic plants in reservoirs

EIA concluded that the potential for invasion of unwanted aquatic plants is very low. During the first 5 year period, monitor aquatic plants at the inlet of the Qingshuihai reservoir. Implement interception measures where any unwanted aquatic plants are found.

IA

KEPB Not yet due.

4. Health risks

Public health threats and increase of health risks

Investigation results show no waterborne diseases in the project area. No mitigation measures are required beyond the recommended environment monitoring program.

See monitoring plan

Not yet due.

5. Induced seismic instability

The small capacities of the Banqiao and Shiqiao reservoirs and the marginally increased capacities of Qingshuihai and Jinzhongshan reservoirs are unlikely to induce seismic events.

No mitigation measures are required.

Implemented during project preparation

Page 38: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

19

Table 3-1(continued) Impact Factor/

Stage Environmental

Impacts and Issues Mitigation Measures ImplementingAgency

Supervising Agency Implementation Status

6. Environmental risks

Dam safety and function

i. Provide adequate supervision and management. ii. Enhance operation monitoring. iii. Regularly maintain environment facilities. iv. Prepare emergency response plans. v. To minimize sedimentation in the reservoirs,

include in the designs low-level sluices for flushing of sediment through the reservoirs to keep the transfers clear.

contracting institutes and reservoir authority

Local government, KEPB,county EPBS

Not yet due.

Flood and seismic events

i. Put in place warning plans for floods to warn people downstream. Include spillway flows and occasional sediment flushing.

ii. Set up an earthquake monitoring station at Haiwei.

iii. KMG will be responsible for the Emergency Action Plan.

IA EA,YWRB, MWR

Implemented during project preparation

Fall gradients and velocity of water flow

The height difference between Qingshuihai reservoir and Kunming is 220 m and the transfer distance is 75 km. The gradient is very small. Include energy dissipation installations in the steep sections.

DI, IA EA, YWRB, MWR

Implemented during project preparation

Bank erosion and flooding risks

No mitigation measures are required. Not yet due.

Insufficient environmental management capacity

Conduct training for environmental management, and develop facility and staff setup.

IA

KEPB, county EPBS

Not yet due

Note: the above progress as the deadline to June 30, 2013.

Page 39: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

20

Table 3-2 Implementation Status of Institutional Strengthening and Capacity Building

Training Topics Attendees Contents Number of Trainees Implementation Status

Environmental laws, regulations, and policies

PMO, IA/operators, contractors representatives

(i) Environmental laws and regulations (ii) Environmental policies and plans (iii) Basic environmental management

15

Fulfilled.

EMP implementation

IA, contractors

(i) Responsibility and duties for project construction, management, and environmental protection (ii) Task of environmental protection during project construction (iii) Key environmental protection contents, etc., in project construction (iv) Various forms of environmental reporting (v) EMP improvement and corrective actions

40

Fulfilled.

Crisis handling KWSG/operators, contractors

Crisis handling methods 10 Fulfilled.

Environmental aspects of facility operation and maintenance

KWSG/operators, contractors

(i) Adaptive management of riparian release (ii) Environmental “housekeeping” (iii) Safety operation regulations (iv) Emergency response procedures

15

Fulfilled.

Environmental monitoring, inspection, and reporting

KWSG/operators, KEPB/county EPBs

Monitoring and inspection methods; collecting, processing, and interpreting data; reporting system. 15

Fulfilled.

Note: the above progress as the deadline to June 30, 2013。

Page 40: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University

(AUGUEST 2012 –JUNE 2013)

21

4. Environmental Monitoring

The engineering construction of the project has been completed and

construction camps have been removed. In order to analyze the changes

of ambient quality status before and after construction, Xishan Institute

monitored water sources of the major surface around the construction

sites and the monitoring locations are shown in Table 4-1.

Table 4-1 Environmental monitoring locations of surface water No. Name of surface

watersources Monitoring locations

1 Qingshuihai Reservoir

the middle spot of Qingshuihai 2 Haiwei 3 Maichong 4

Xintianhe Reservoir Estuary

5 Intake 6 Jinzhongshan

Reservoir Front dam

7 Back reservoir 8 Shiqiaohe Reservoir Dam site 9

Banqiaohe Reservoir Upper reaches of the dam site

10 Dam site 11 Lower reaches of the dam site 12 Tabizi Spring Center

4.1 Monitoring of water quality

In May 2013, Xishan Institution monitored the major locations of

surface watersources flowing through the construction sites and the

monitoring frequency is once a day. Take a composite water sample and

the monitoring items are pH, dissolved oxygen, permanganate index,

chemical oxygen demand, 5-day biochemical oxygen demand, ammonia

nitrogen, total nitrogen, total phosphorus and fecal coliform.

(1) Monitoring results

Page 41: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University

(AUGUEST 2012 –JUNE 2013)

22

Results of the water monitoring items in each monitoring locations

are shown in table 5-2 and the water quality standard is subject to Type II

under GB3838-2002 Environmental Quality Standard of Surface Water.

Page 42: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

23

Table 4-2 Statistical table of quality monitoring results Items Sampling site Time

pH Dissolved

oxygen (mg/L)

Permanganate index

(mg/L)

Chemical oxygen demand (mg/L)

5-day biochemical

oxygen demand (mg/L)

Ammonia nitrogen (mg/L)

Total nitrogen(mg/L)

Total phosphorus(mg/L)

Fecal coliform(No/L)

Up-to-standard

evaluation

The middle spot of

Qingshuihai 05.28 8.43 7.12 1.7 10L 0.8 0.087 0.63 0.018 20 Exceed the

standard

Haiwei of Qingshuihai 05.28 8.64 6.32 1.9 10L 1.0 0.103 0.58 0.020 20 Exceed the

standard Maichong of Qingshuihai 05.28 8.56 6.25 2.0 10L 0.9 0.111 0.52 0.021 20 Exceed the

standard Estuary of Xintianhe 05.28 / / / / / / / / / /

Intake of Xintianhe Reservoir

05.28 / / / / / / / / / /

Front dame of Jinzhongshan

Reservoir 05.28 8.32 7.02 3.2 10L 3.0 0.181 0.49 0.018 20 Reach the

standard

Back Jinzhongshan

Reservoir 05.28 8.12 7.32 2.8 10L 2.9 0.166 0.47 0.017 20 Reach the

standard

Dam site of Shiqiaohe 05.28 7.98 8.23 1.6 10L 2.5 0.222 0.43 0.019 500 Reach the

standard Upper

reachesof the dam site of Banqiaohe

05.28 8.12 8.31 1.0 10L 1.1 0.157 0.35 0.019 200 Reach the standard

Dam site of Banqiaohe 05.28 8.40 8.37 1.1 10L 1.3 0.185 0.37 0.023 280 Reach the

standard

Page 43: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

24

Table 4-2 (continued) Items Sampling site Time

pH Dissolved

oxygen (mg/L)

Permanganate index

(mg/L)

Chemical oxygen demand (mg/L)

5-day biochemical

oxygen demand (mg/L)

Ammonia nitrogen (mg/L)

Total nitrogen(mg/L)

Total phosphorus(mg/L)

Fecal coliform(No/L)

Up-to-standard

evaluation

Lower reaches of the dam

site of Banqiaohe

05.28 8.32 7.35 1.3 10L 1.6 0.177 0.36 0.024 320 Reach the standard

Tabizi Spring 05.28 8.23 7.19 3.4 10L 3.2 0.312 0.73 0.037 480 Exceed the standard

Standard value 6-9 ≥6 ≤4 ≤15 ≤3 ≤0.5 ≤0.5 ≤0.025 ≤2000 /

Note: Xintianhe Reservoir has dried up owing to drought which leads to failure of collecting water sample. So the monitoring data is lacking.

Page 44: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

25

(2) Analysis of monitoring results

It can be known from table 4-1; the water quality of all the other

locations is up to Class II under GB3838-2002 Environmental Quality

Standard of Surface Water, except Qingshuihai (the middle spot of

Qingshuihai, Haiwei and Maichong) and Tabizi Spring.

In accordance with the water quality monitoring data of each

location during the environmental assessment phase subject to the

Written Report of the Project, and water quality monitoring data of 2012

provided by Xundian Environment Protection Bureau towards each

location in October 2012, and data of this phase, work out the water

quality conditions of each location before construction period, during

construction, and after the construction, all of which are shown in Table

4-3:

Page 45: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

26

Table 4-3 Quality conditions of surface waterduring the engineering

construction of the project

Name of the locations Water quality before construction

Water quality during construction (Oct. 2012)

Water quality after construction after

construction ( May 2013)

The middle spot of Qingshuihai (Ⅱ May 2005) Ⅱ Ⅲ

Haiwei of Qingshuihai (Ⅱ May 2005) —— Ⅲ Maichong of Qingshuihai —— —— Ⅲ

Estuary of Xintianhe (Ⅱ May 2005) —— —— Intake of Xintianhe

Reservoir (Ⅲ July 2006) Ⅲ ——

Front dame of Jinzhongshan

Reservoir (Ⅲ May 2005) —— Ⅱ

Tail of Jinzhongshan Reservoir (Ⅳ May 2005) —— Ⅱ

Dam site of Shiqiaohe (Ⅲ May 2005) —— Ⅱ Upstream of the dam

site of Banqiaohe (Ⅳ May 2005) —— Ⅱ

Dam site of Banqiaohe (Ⅳ May 2005) Ⅳ Ⅱ

Downstream of the dam site of Banqiaohe (Ⅴ May 2005) —— Ⅱ

Tabizi Spring (Ⅴ July 2006) Ⅲ Ⅲ Note: 1、“—”means the items that have not been monitored this time or there are no data. 2、 Xintianhe Reservoir has dried up owing to the long-term drought, which led to the failure of collecting water sample in the current monitoring, so there are no monitoring data about Xintianhe Reservior in 2013

By comparing the water quality conditions before construction (the

year of 2006, 2007) and during construction (2012), it can be concluded

that the water quality of Qingshuihai Reservoir maintains at Class II both

before and after construction; the water quality of Xintianhe Reservoir

maintains at Class III, the water quality of Banqiaohe Reservoir remains

at Class IV, and the water quality of Tabizi Spring changes from Class V

into Class III. It can be easily seen that the construction of the project

exerts no influences on the water quality of each location; in adverse, due

to the implementation of the construction, the impact of non-point source

pollution on the water quality of Tabizi Spring has decreased, so as to

make the water quality of Tabizi Spring turns into Class III in 2012.

Page 46: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

27

Up to June 2013, the Project enters into completion phase. It can be

known by a comparison of the water quality before construction and after

construction that except for the change from Class II into Class III in

Qingshuihai Reservoir, and no water sample collected owning to

consecutive drought in Xinhetian Reservoir, water quality at the rest four

locations have improved , namely, water quality Class of Jinzhongshan

Reservoir, Shiqiaohe Reservoir , Tabizi Spring, and Banqiaohe Reservoir

all have turned into Class II from Class IV, Class III, Class III and Class

IV respectively.

Main reasons of the above are: catchment area of these reservoirs is

relatively small; the water quality is easily to be effected by the rainfall in

dry and rainy seasons, and rainy season didn’t come when the monitoring

was conducted in 2005, drought and little rainfall in 2012, while the

rainfall during the monitoring period in 2013 is sufficient. Since the water

source of Tabizi Spring is groundwater, and the water quality has little to

do with the rainfall, the water quality of 2013 varied little from that of

2012. It can be seen from the comparisons over the years that the

implementation of the project exerts little impacts on the water quality of

the surrounding surface water.

During construction period of the Project, wastewater treatment

measures have been taken at each site and camp to avoid impacts on the

surrounding surface water, so the water quality of the surrounding surface

water maintains stable.

Meanwhile, it can be inferred from Table 5-2 that the current water

quality of Qingshuihai reservoir after construction is worse than that

before construction, which now is Class III. The major reasons are: Since

December, 2012, Qingshuihai Reservoir started to receive water from

banqiaohe Reservoir, Xintianhe Reservoir, Shibanqiaohe Reservoir and

Tabizi Spring, entered into primary impoundment period, for which the

Page 47: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

28

water body is in a process of blending, the water quality needs a

stabilization-oriented process. At the same time, due to the reservoir

capacity of Qingshuihai Reservoir, less vibration of water quality resulted

from rainfall. As a result, the influences of dry and rainy seasons on the

water quality of Qingshuihai Reservoir are relatively small than other

water sources.

In conclusion, the implementation of this project has exerted little

influences on the surface water; the decrease of water quality has been

caused by the water quality of the upstream after the water diversion

project started to work.

4.2 Clean-ups of the camps upon completion of the construction

By June 30, 2013, the construction of the project has been completed,

all contractors removed. There leaves administrative staff who are

responsible for collecting data in construction sites, namely 1#

construction camp of Banqiaohe, 2# construction camp of Shiqiaohe,

Qingshuihai section next to 6# Maichong tunnel entrance, distribution

gate of 23# Tongxin Reservior, 24# Jinzhongshan Reservior) while other

construction sites have all be removed.

Page 48: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

29

Table 4-4 Clearing-Up of the Camps After Completion

Type No. of the

ConstructionCamp

Location Clearing-Up of the Camps

Water Source project

1# Banqiao River Construction camp The equipment has not been removed totally and there left personnel of site office to take care of the equipment.

2# Shiqiao River Construction camp

3# Xintian River Construction camp The camp has been cleared up. 4# Tabizilong Pool Construction camp

5# Water body of Qingshuihai Reservoir beside Haiwei Village

The workers have removed and the camps have not been dismantled.

6# Water body of Qingshuihai Reservoir beside Maichong Tunnel Entrance

The camp has been dismantled and there were personnel who were preparing documents in the site office.

Water convey

ance Project

7# Construction Camp of Xiatuoqi Tunnel Entrance and aqueduct The camp has been cleared up.

8# Construction camp of Enjia Tunnel Entrance and aqueduct and open channel The camp has been removed and

the household refuse was not deal with. 9# construction camp of Enjia Tunnel

Exit and Haidang Tunnel Entrance

10# Banqiao River Tunnel Exit construction Camp

Water convey

ance Project

11# Construction Camp of Maichong Tunnel Exit and Maichong open channel The camp has been cleared up.

12# Dapingdi Tunnel Exit, Bailiqing Tunnel Entrance

13# Xixian Trench Construction Camp The camp has been removed and the household refuse was not deal with.

14#

Construction camp of Xiaobeidang open channel, 12th maintenance gang inverted siphon, Dashuidong Tunnel entrance

The camp has been cleared up.

15#

Construction camp of Dashuidong Tunnel exit, aqueduct, Qinjiazhuang Tunnel, aqueduct, Longjia Village Tunnel entrance

The camp has been removed and the household refuse was not deal with.

16#

Construction camp of Pujia Mountain Tunnel exit, Laofangziqing aqueduct, Dahu Mountain Tunnel exit The camp has been cleared up.

17# Construction camp of Dong Village Tunnel exit and Xi village inverted siphon

18# Construction camp of Dashanqing Tunnel exit and Moshiqing Tunnel entrance

The camp has been removed and the refuse dumps and cesspools were not deal with.

Page 49: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

30

Type No. of the Construction Camp

Location Clearing-Up of the Camps

Water convey

ance Project

19# Construction camp of Baishi mountain Tunnel exit, aqueduct, Jinji Mountain Tunnel entrance

The camp has been cleared up.

20#

Construction camp of Jinji Mountain Tunnel exit, aqueduct, Xin Village aqueduct and Tunnel entrance

The camp has been removed and the household refuse was not deal with.

21# Construction camp of Xin Village Tunnel exit, gegentang aqueduct and Tunnel Exit

The camp has been cleared up.

22# Construction camp of Gegentang Tunnel exit, Yangtianchong open channel

The camp has been cleared up and some parts are returned for

farming.

23# construction camp of Tongxin Reservoir diversion gate The camp has been removed and

there left personnel of site office to prepare documents. Tail-end

Reservior 24# Jinzhong Mountain Reservoir construction camp

Based on the conditions of site survey, most of the removed camps

have cleared up and smoothed the temporary lands that were occupied but

have not greened and restore them for farming; only the lands of 22#

construction camps of Gegentang Tunnel exit and Yangtianchong open

channel have been returned for farming. The four camps, 13#, 15#, 18#,

20# did not cleared up the sites when removed, which exerted certain

influences on the environment.

The personnel of Qingshuihai Reservoir beside Haiwei Village did

not remove the camp buildings after removal. As the reservoir water of

Qingshuihai is not intensive owing to many years of drought, it will

submerge the remaining buildings and have certain impact on the water

quality of Qingshuihai when the water storage is increased.

After the removal, the seven construction camps (namely, 8#, 9#,

10#, 13#, 15#, 18#,20# ) did not clear up the solid wastes generated

during the construction period, which polluted the environment.

Page 50: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

31

5. Conclusion and recommendation

5.1Conclusion

(1)Monitoring of water quality

As of June 30, 2013, the environment monitoring during

construction period of Qingshuihai water supply project has been

implemented for half and five years. Project engineering construction in

the current monitoring has been completed and this monitoring is

conducted focusing on the environment of surface water.

Most contractors well kept their promise of protecting environment

during construction period, and mitigation measures of environmental

protection and environment monitoring measures have been carried out

effectively. The surface water beside most construction sites was not

influenced by the construction and water quality is up to the Class II

under GB3838-2002 Environmental Quality Standard of Surface Water.

The reasons why the water quality of Qingshuihai reservoir

decreased from II before the construction to III are mainly as follows:

factors such as large amounts of overland runoff in rainy seasons and

unstable water quality in the primary water storage period.

(2)Recovery of temporary occupied lands of construction camps

upon completion of the construction

The project has been completed and contractors have all removed

from the construction sites. Most temporary lands of camps have been

cleared up when contractors removed. However, some camps (namely, 8#,

9#, 10#, 13#, 15#, 18#, 20#) have not been dealt with when the

contractors removed and there left solid wastes and household refuse

Page 51: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

32

generated during the construction period, which exerts some impacts on

the around environment.

5.2 Recommendation

Subject to the site survey of each construction camp by the research

group and taking the environment monitoring results into consideration,

the following mitigation measures about the Project (from August, 2012

to June, 2013 ) are put forward:

(1)When all site offices are removed, it is required that temporary

occupied lands should be cleared up and restored for farming;

(2)The camps that have been removed and cleared up the sites

shall recover or return ecological vegetation of the temporary

construction lands for farming;

(3)The camps that have been removed but not cleared up the sites,

shall clear up and remove the solid wastes among which building wastes

shall be assigned to a qualified unit for removal; at the same time,

leveling the lands and ecological recovery shall be conducted.

( 4)Construct side slope for all the built roads to reinforce

protection, and plant vegetation in planting slope when necessary to

prevent natural disaster such as mud and rock flow and landslide, etc.

(5)Pay close attention to the landform evolution around the

subsidence area of Dapingdi Tunnel Exit to prevent the expansion of

subsidence area as the result of continual construction which shall

aggravate the impacts. When the condition is allowed, it is desirable to

backfill the subsidence area as soon as possible and recovery the

vegetation of this area.

Page 52: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

Appendix: Photo of construction sites

Access road of Shiqiaohe Reservior Remaining Shiqiaohe Construction Camp

Xintianhe Construction Camp has been cleared up Tabizi Spring

Water body of Qingshuihai Reservoir Fence of Qingshuihai

beside Haiwei Village Reservoir beside Haiwei Village

The remaining Banqiaohe Construction Camp Diversion project of Banqiaohe Dam of trail operation

Page 53: Environmental Monitoring Report€¦ · Kunming Qingshuihai Water Supply Project Technical Report of Environment Monitoring (AUGUEST 2012 –JUNE 2013) Yunnan University AND Xishan

KUNMING QINGSHUIHAI WATER SUPPLY PROJECT Yunnan University (AUGUEST 2012 –JUNE 2013)

The remaining camp of Qingshuihai Water body from Reservoir beside Haiwei Village Haidang Tunnel Exit to Qingshuihai

Qingshuihai Dam Land condition of removed desilter of Maichong Tunnel Exit

Remaining construction camp Distribution gate of Jinzhongshan

of Maichong Tunnel Exit

Jinzhongshan Reservior The dam of Jinzhongshan


Recommended