Episode 22 : PROJECT EXECUTION

Date post: 23-Jan-2017
Category:
Upload: sajjad-khudhur-abbas
View: 78 times
Download: 4 times
Share this document with a friend
20
SAJJAD KHUDHUR ABBAS Chemical Engineering , Al-Muthanna University, Iraq Oil & Gas Safety and Health Professional – OSHACADEMY Trainer of Trainers (TOT) - Canadian Center of Human Episode 22 : PROJECT EXECUTION
Transcript
Page 1: Episode 22 : PROJECT EXECUTION

SAJJAD KHUDHUR ABBASChemical Engineering , Al-Muthanna University, IraqOil & Gas Safety and Health Professional – OSHACADEMYTrainer of Trainers (TOT) - Canadian Center of Human Development

Episode 22 : PROJECT EXECUTION

Page 2: Episode 22 : PROJECT EXECUTION

Component Assembly

•Transportation of component

•Installation of components at plant sitePolice approval

•Large components – used suitable cranes, usually are leased/rent– electronically controllable by remote control

•Medium/Smaller components– hoists or fork‐lifts are used– are ordered to the building site at an early stage and intermediately

stored there.

‐If possible, at the same time, during the assembly of main components, the assembly of medium/smaller components will begin.‐Subcontractor is required to provide suitable packaging or tarpaulin cover(cover for vessel opening such as nozzle, by means of plastic caps)

Transport analysis

‐Headroom of bridge & tunnel

‐turning circle of vehicle (U‐turn)

Page 3: Episode 22 : PROJECT EXECUTION

Crane

Fork‐liftHoist

3

Page 4: Episode 22 : PROJECT EXECUTION

PIPE ASSEMBLY

•Begin after the installation of the essential components has been completed.• Depend on several factors. Example:

Case of metal pipe, welding work is required.• The non‐destructive testing also need

to consider.

Prefabricated piping

Two possibilities in the fabrication of the piping.

Site‐run piping

PREFABRICATED PIPING

Requires a good and detail piping planning.• Pipe routes are prefabricated on the pipe supplier’s premises.

• Delivered to the building site in the form of a conglomerate of pipe formations.

Advantages‐ Has a time advantages.‐ During prefabricated phase,

construction and component assembly can be excluded.

‐ Building site activities are less.

Disadvantages‐ The collisions and alterations are

considerable (cause extra cost needed).‐ Rubber lined pipe systems must

prefabricated (time effort involved).

Page 5: Episode 22 : PROJECT EXECUTION

SITE‐RUN PIPING

•With the aid of the piping and instrumentation flow charts the piping routes are planned and dimensioned.

•Planning effort – lower and CAD systems ‐ no need

• Probability of collisions –lower

• Planning the piping routes no‐•The piping documentation has to be integrated or prepared on ‐ site during the

construction phase

• Disadvantage ‐ not suitable at high temperature.

• Advantage ‐ small nominal widths do not require stress calculation.

• fixed flanges• rotatable flanges• screwed connections• glued joints• welding joints

• other fittings

FITTING AND CONNECTIONS

5

Page 6: Episode 22 : PROJECT EXECUTION

ASSEMBLY E/MC TECHNOLOGYUsually assembly of electrotechnical equipment is independently from the plant

erection because of the control cabinets are accommodated in separated rooms.

More difficult is the installation of measuring instruments and cabling. Since a large part of measuring instruments is integrated in the pipes, the assembly occurs within the framework of the piping and fitting assembly.

Cabling will begins with so‐called “cable

reels”. Cable Reels:

Where cable laid from control station to the individual consumer or measuring points in the cable trays.

The cable reel requires an external temperature of more than 5°C. If the external temperatures are lower, there will be the risk that either the cables break or the cable trays will be deformed due to the embrittlement of the cable insulation.

The cable reel can be passed through before the assembly of the actual consumer.

Page 7: Episode 22 : PROJECT EXECUTION

The cable connecting plans generated both from the piping plans and from the piping and instrumentation diagrams that shows the position of the consumer or connecting points in the plant.

In the majority of cases, cables are laid in protective conduits as soon as they leave the cable trays.

Finally the cables are connected to the terminal boxes of the motor.

Usually the cable connection work requires separate scaffolds. Moreover, the concurrent assembly of components and cable reels bears the risk of damaging the newly laid cables. This applies especially to the insulation work to be done.

It is advisable to carry out the cable reel work only after the completion of theassembly.

The usual time pressure, however, does not allow for such a procedure.

7

Page 8: Episode 22 : PROJECT EXECUTION

•Insulation work start after assembly of the piping.•The insulation consist of mineral wool layer.•For longer vertical pieces, dual grip rings used which hold the insulation wool to protected against slipping.•Finally,

insulation caps or moulted partsmounted after pressure and leakage tests.

Page 9: Episode 22 : PROJECT EXECUTION

• Plant Marking and Safety Marking• Commissioning• Cleaning• Pressure Test, Functional Test, System

Test• Cold and Warm Commissioning• Warranty Run/ Acceptance

9

Presentation Scope

Page 10: Episode 22 : PROJECT EXECUTION

Plant Marking

10

1) Marking of the operating resources2) Pipeline marking3) Cable marking4) Safety marking5) Other markings (at sole discretion of customer)

Marking of the operating resources may be designed as engraved labels or profile rails with individual letters being inserted.

Fixing of the labels occurs by means of clamps, rivet joints, cable ties etc

For the pipes, marked are done with banderols either directly glued on to the pipes or on to the insulation

Colour of the banderol represent media carried by the pipeline

Page 11: Episode 22 : PROJECT EXECUTION

Comprises the marking of hazardous material according to the Ordinance on Hazardous Substances.– hazardous substances symbols in yellow/black (skull for

toxic media, etched hand for acids etc.).– instruction signs in blue/white (eye protection,

breathingprotection, ear protection)

11

Safety Marking

Page 12: Episode 22 : PROJECT EXECUTION

Commissioning

12

The commissioning coincides with the residual work ofthe assembly

The person mainly responsible ~ commissioning manager C.M should be able to use their considerable experience

gained in other projects. It also is subjected to a time schedule that should be adhered

to. Depends on the philosophy of the plant manufacturer. The considerations regarding commissioning of a

plant should already be integrated in the beginnings of the plant engineering.

Furthermore, the optimum implementation of the commissioning activities requires competent commissioning management .

After all, insights gained in the commissioning process should be absolutely documented to draw advantages for future projects.

Page 13: Episode 22 : PROJECT EXECUTION

Cleaning

13

• After completion of the assembly work the preliminary cleaning of the building site and the plant has to be carried out. The inside cleaning of the plant is considerably more difficult.

• The containers and apparatus have to be cleaned from inside and then the piping will be purged.

• In order to protect sensitive plant components, in particular pumps, measuring instruments and control valves, during the flushing process it is advisable to shut them off by means of blanks.

a) Sensitive measuring instruments can be removed. The orifices are to be closed by blind flanges or caps.

b) For control valves, flushing inserts can be ordered and installed.

c) Pumps can be protected by installing blanks on the suction and pressure side.

Page 14: Episode 22 : PROJECT EXECUTION

After completion of the assembly work the preliminary cleaning of the building site and the plant has to be carried out. The inside cleaning of the plant is considerably more difficult.

There is the alternative to protect sensitive plant parts through the installation of so – called start - up strainers or flushing sieves.

Usually, it is flushed from the pumps in the direction of the vessels or apparatuses.

In order to enable the removal of coarse impurities, interval flushing is advantageous. The flushing conduit will be opened and kept open for a determined interval and will finally be closed again. This procedure can be repeated several times.

14

Cleaning

Page 15: Episode 22 : PROJECT EXECUTION

- Generally limited to the assembled pipes.1) The system is filled and then evacuated at the highest point.2) Pressure test appliedand time-related pressure drop will be recorded.3) Visual test of all connecting points also carried out.4) Eliminate leakages and finally discharge water from the pipes.

Functional Test- The individual aggregates and measuring points are tested for their correct function- Examples of functional test applied

1) Pump2) Fixtures and fittings3) Apparatus – agitators, centrifuges and etc.4) Black boxes – self contained and operative small plants5) Measuring instruments

15

Pressure Test

Page 16: Episode 22 : PROJECT EXECUTION

System Test- Carry out after functional test on each individual aggregates

and measuring points- The controls of the main system will be tested whether the

entire system function work properly or not.

Cold and Warm CommissioningCold Commissioning After inspection of all system controls Liquid processing plant first filled with water up

to control levels Individual system controls are activated Flow-through and level controls can be tested and

optimized Timing elements have to be optimized

16

Page 17: Episode 22 : PROJECT EXECUTION

Cold and Warm Commissioning• Warm Commissioning Testing and optimizing of plant components ( heat

supply/heat removal ) Application of the real media Warming up of the steam pipes Shut off discharge valve ( no more condensate ) Connect condenser Heating of the respective heat exchanger

Warm Dry Run Cooling water system ( with water in the

plant )

Plant dischargedOptimization tasks measurements

real starting material for 1st time inter alia, calibration of all quality

17

Page 18: Episode 22 : PROJECT EXECUTION

Warranty Run/AcceptanceMain Objective- To verify the proper function of constructed plant

Warranty Run1. Before2. During3. After/Acceptance

1) Operating condition during test run must be agreed with operator

2) Different loading conditions of the plant are shown and guaranteed qualities are measured

BEFORE

18

Page 19: Episode 22 : PROJECT EXECUTION

o Several minor failure or one major failure1)Restart the test run2) List of defect, retrofitting measures and deadlines have to be

determined3) If retrofit not success, plant manufacturer face claim for relevant

penaltyo Major defect that cannot be remedied by retrofit

1)Entitle operator to reject the whole plant

DURING

AFTER

19

o During warranty period1) Plant manufacturer to remedy them but not covered damages

caused by operator due to improper handling2) Plant manufacturer refer deficiencies to relevant subcontractor

o After warranty period1)Plant deficiencies is the responsibility of customer and insurances

policyo Operation

1)The operation of plant is taken over by operator staff

Page 20: Episode 22 : PROJECT EXECUTION

Thanks for Watching Please follow me / SAJJAD KHUDHUR ABBAS