+ All Categories
Home > Documents > EPRI Procurement Forum Agenda August 23-25, 2011...

EPRI Procurement Forum Agenda August 23-25, 2011...

Date post: 07-Sep-2018
Category:
Upload: vandat
View: 215 times
Download: 0 times
Share this document with a friend
333
EPRI Procurement Forum Agenda August 23-25, 2011 ~ Minneapolis, MN Page 1 of 3 Tuesday, August 23, 2011 TIME TOPIC 7:00 a.m. Breakfast– Universe 8:00 a.m. Opening Remarks / Introductions – Planets 8:30 a.m. Information Notice 2011-01 - EPRI & NRC - Open Discussion 9:20 a.m. Break 9:35 a.m. Current Events and Concerns in your Organization - Open Discussion - Note to all attendees : Please bring examples of improvements or changes with positive impact, things your organization does well, and areas that challenge you. 10:50 a.m. Break 11:00 a.m. Back to Basics – Selecting Critical Characteristics - Marc Tannenbaum, EPRI - Case Study (Open Discussion) 12:00 p.m. Lunch – Universe 1:00 p.m. Cyber Security - Matt Bowman, ATC Nuclear Acceptance of Commercial Grade Software Guidance Update - Marc Tannenbaum, EPRI Current Regulatory Issues - JUTG Steering Committee 2:25 p.m. Break 2:40 p.m. Managing Procurement Engineering Work - Murray Kraemer, Bruce Power - Paul Saksvig 3:35 p.m. Break 3:50 p.m. Outsourcing Equivalency Evaluations at USA - Howard LeCompte, Detroit Edison Co. 4:15 p.m. Topics for Next Meeting 4:30 p.m. Procurement Engineering On-Line - Greg Keller, Nuclear Logistics, Incorporated 5:00 p.m. Adjourn 5:30 –7:30 p.m. EPRI Networking Reception & Supplier Information Exchange – Stars
Transcript

EPRI Procurement Forum Agenda August 23-25, 2011 ~ Minneapolis, MN

Page 1 of 3

Tuesday, August 23, 2011

TIME TOPIC

7:00 a.m. Breakfast– Universe

8:00 a.m. Opening Remarks / Introductions – Planets

8:30 a.m. Information Notice 2011-01 - EPRI & NRC - Open Discussion

9:20 a.m. Break

9:35 a.m. Current Events and Concerns in your Organization - Open Discussion - Note to all attendees: Please bring examples of improvements or changes with positive

impact, things your organization does well, and areas that challenge you.

10:50 a.m. Break

11:00 a.m. Back to Basics – Selecting Critical Characteristics - Marc Tannenbaum, EPRI - Case Study (Open Discussion)

12:00 p.m. Lunch – Universe

1:00 p.m. Cyber Security - Matt Bowman, ATC Nuclear

Acceptance of Commercial Grade Software Guidance Update - Marc Tannenbaum, EPRI

Current Regulatory Issues - JUTG Steering Committee

2:25 p.m. Break

2:40 p.m. Managing Procurement Engineering Work - Murray Kraemer, Bruce Power - Paul Saksvig

3:35 p.m. Break

3:50 p.m. Outsourcing Equivalency Evaluations at USA - Howard LeCompte, Detroit Edison Co.

4:15 p.m. Topics for Next Meeting

4:30 p.m. Procurement Engineering On-Line - Greg Keller, Nuclear Logistics, Incorporated

5:00 p.m. Adjourn

5:30 –7:30 p.m. EPRI Networking Reception & Supplier Information Exchange – Stars

EPRI Procurement Forum Agenda August 23-25, 2011 ~ Minneapolis, MN

Page 2 of 3

Wednesday, August 24, 2011

TIME TOPIC

7:00 a.m. Breakfast– Universe

8:00 a.m. Topics for Next Meeting

8:10 a.m. EPRI Procurement Update - Marc Tannenbaum, EPRI

Part 21 Update - Victor Hall

9:20 a.m. Break

9:35 a.m. Off-Site Repair of Large Critical Assets - Bhavesh Patel, Progress Energy - William Ware, Southern Nuclear Operating Co.

10:35 a.m. Break

10:50 a.m. Breakout Sessions - NRC Ideas for Improving / Clarifying 10CFR21 - Application of Dedication Methodology to Software - Dedication Challenges

12:00 p.m. Lunch – Universe

1:00 p.m. Reverse Engineering - Sam Yousif, Dynamic Solutions - Daryl Prisby, Exelon

2:00 p.m. Cameron Update

2:25 p.m. Break

2:40 p.m. Ask the Vendor

3:25 p.m. Nuclear Procurement Issues Committee (NUPIC) Update - Fawaz Jabali, Arizona Public Service

Regulatory Concerns - Open Discussion

4:35 p.m. Topic, Presenters & Locations for Future Meetings

5:00 p.m. Adjourn

EPRI Procurement Forum Agenda August 23-25, 2011 ~ Minneapolis, MN

Page 3 of 3

Thursday, August 25, 2011

TIME TOPIC

7:00 a.m. Breakfast– Universe

8:00 a.m. Identify Topics, Presenters & Locations for Future Meeting

8:25 a.m. New Supplier Entrance - Fawaz Jabali, Arizona Public Service - Cesar Mejia, ValvTechnologies - Rick Easterling, Kinectrics, Inc.

9:40 a.m. Break (Luggage/Checkout)

10:05 a.m. Ask the Regulator - Paul Prescott and Richard McIntyre, NRC - Open Discussion – Regulatory Concerns

10:50 a.m. Break (Luggage/Checkout)

11:00 a.m. Identify Topics, Presenters & Locations for Future Meeting

11:25 a.m. Adjourn

JUTG Procurement Forum Attendees ~ August 23‐25, 2011 ~ Minneapolis, MN

Full Name Company Email Address Work PhoneDave Bishop South Carolina Electric & Gas Co. [email protected] 803‐345‐4658Scott Borland Versatile Measuring Instruments [email protected] 800‐742‐1413Matthew Bowman ATC Nuclear [email protected] 865‐218‐8242Jose Camacho Cameron Measurement Systems jose.camacho@c‐a‐m.com 708‐717‐1572Milton Concepcion U.S. Nuclear Regulatory Commission [email protected] 301‐251‐7457Mark Coren Duke Energy Corp. mark.coren@duke‐energy.com 980‐875‐5887Christopher Crawford Babcock & Wilcox Co. [email protected] 865‐241‐9213Roy Croft Southern Nuclear Operating Co. [email protected] 205‐992‐7417Dan Dancer Xcel Energy Services, Inc. [email protected] 651‐388‐1121 x4492Scott Davis Constellation Energy [email protected] 410‐495‐2629Sam Davis Entergy Services, Inc. [email protected] 914‐272‐3307Spencer Daw Bechtel Corp. [email protected] 509‐371‐5849Rick Easterling Kinectrics, Inc. [email protected] 804‐550‐3109Shannon Echols Edgen Murray Corp. [email protected] 803‐554‐6108Chris Faraglia PKMJ Technical Services, Inc. [email protected] 412‐865‐3040Greg Galletti U.S. Nuclear Regulatory Commission [email protected] 301‐415‐1831P. Gallo AP Services, Inc. [email protected] 815‐529‐1001James Geer Cameron International jim.geer@c‐a‐m.com 562‐321‐9162George Gharabeigie Southern California Edison Co. [email protected] 949‐368‐3717Gary Gilmartin Gilmartin Engineering Works [email protected] 865‐360‐8689Jim Grant Duke Energy Corp. jim.grant@duke‐energy.com 803‐701‐3683Victor Hall U.S. Nuclear Regulatory Commission [email protected] 301‐415‐2915Brad Hemphill AP Services, Inc. [email protected] 724‐295‐6200Brian Hendel Energy Northwest bjhendel@energy‐northwest.com 509‐377‐4573Greg Hott ATC Nuclear [email protected] 865‐406‐1219Craig Irish Nuclear Logistics, Inc. [email protected] 978‐250‐1684Fawaz Jabali Arizona Public Service Co. [email protected] 623‐393‐6712Donald Jones FirstEnergy Nuclear Operating Co. [email protected] 419‐321‐8538Greg Keller Nuclear Logistics, Inc. [email protected] 702‐869‐6300Laura Knight ATC Nuclear [email protected] 423‐315‐1331Ralph Krause Nebraska Public Power District [email protected] 402‐825‐5662

Page 1 of 3 Note: Contact information omitted by request.

JUTG Procurement Forum Attendees ~ August 23‐25, 2011 ~ Minneapolis, MN

Full Name Company Email Address Work PhoneAlbert Lafleur Florida Power & Light Co. [email protected] 561‐845‐3343Robert Lane ATC Nuclear [email protected] 865‐964‐9864Howard LeCompte III Detroit Edison Co. [email protected] 734‐586‐5159Seth McClintock Omaha Public Power District [email protected] 402‐533‐6531Richard McIntyre U.S. Nuclear Regulatory Commission [email protected] 301‐415‐3215Beth McRimmon Electric Power Research Institute (EPRI) [email protected] 704‐595‐2536Cesar Mejia ValvTechnologies [email protected] 860‐961‐0823Matt Miles Edgen Murray Corp. [email protected] 704‐222‐3993Ujjal Mondal CANDU Owners Group [email protected] 416‐595‐1888 x116Michael Murdock Duke Energy Corp. MichaelW.Murdock@duke‐energy.com 980‐875‐4237Lisa Nolin Duke Energy Carolinas lisa.nolin@duke‐energy.com 980‐875‐5579Tyler Owen Lincoln Structural Solutions [email protected] 402‐290‐1481Bhavesh Patel Progress Energy, Inc. [email protected] 919‐362‐2566Cong Pham STP Nuclear Operating Company [email protected] 361‐972‐7996Daniel Philipps FirstEnergy Nuclear Operating Co. [email protected] 440‐604‐9796Dave Pirro Westinghouse Electric Co. [email protected] 724‐875‐0289Jeff Polacek NextEra Energy Point Beach, LLC [email protected] 920‐755‐6315Paul Prescott U.S. Nuclear Regulatory Commission [email protected] 301‐415‐3026Daryl Prisby Exelon Corporation [email protected] 815‐406‐3502Jerald Rogers Rolls‐Royce Corporation rogersj@ds‐s.com 256‐705‐2152Chuck Rogers Cameron International chuck.rogers@c‐a‐m.com 281‐582‐9507Paul Saksvig Dominion Generation [email protected] 804‐273‐2689Bob Salsky Cameron International bob.salsky@c‐a‐m.com 281‐582‐9500Russell Schaefer Dominion Energy Kewaunee, Inc. DEKI [email protected] 920‐388‐8725Arun Sharma Atomic Energy of Canada, Ltd. [email protected] 613‐584‐8811 x46359Jennifer Snead Duke Energy Carolinas jennifer.snead@duke‐energy.com 864‐885‐4113Garry Snyder Lincoln Structural Solutions [email protected] 678‐588‐8895Stan Stack Nutherm International, Inc. [email protected] 618‐244‐6000 x3011Keith Stall Cameron International keith.stall@c‐a‐m.com 361‐815‐9044Darlene Stimart Xcel Energy Services, Inc. [email protected] 612‐330‐6522Marc Tannenbaum Electric Power Research Institute (EPRI) [email protected] 704‐595‐2609

Page 2 of 3 Note: Contact information omitted by request.

JUTG Procurement Forum Attendees ~ August 23‐25, 2011 ~ Minneapolis, MN

Full Name Company Email Address Work PhonePaul Tobin PKMJ Technical Services, Inc. [email protected] 412‐865‐3040 x102Ararat Torosyan Enertech [email protected] 714‐528‐2301 x102Bill Van Wormer Westinghouse Electric Co. [email protected] 412‐716‐9753William Ware Southern Nuclear Operating Co. [email protected] 334‐814‐4566Stephen Werlick Scientech, Curtiss‐Wright Flow Control [email protected] 519‐938‐8084Robert Wieser Arizona Public Service Co. [email protected] 623‐393‐5715Gary Wiley Progress Energy, Inc. [email protected] 919‐362‐2955Edward Wynne Fluor Enterprises, Inc. [email protected] 864‐644‐8054Sam Yousif Dynamic Solutions USA, Inc. [email protected] 914‐456‐0227

Page 3 of 3 Note: Contact information omitted by request.

EPRI Joint Utility Task Groupon Procurement Engineering

Summer MeetingMinneapolis, Minnesota

August 23-25, 2011g ,

Administrative Details

• Safety MomentExits– Exits

– Hazards

• Facilities– Internet Access (Guest Rooms)

B k L h R ti– Breaks, Lunches, Reception

• Meeting FeedbackMeeting Feedback– Its your forum– Meeting Feedback

3© 2011 Electric Power Research Institute, Inc. All rights reserved.

– We want your ideas and suggestions

Safety Moment

MeetingMeals

Reception

4© 2011 Electric Power Research Institute, Inc. All rights reserved.

Conference Expectations

• Reduce DistractionsPlease silence cell phones beepers etc– Please silence cell phones, beepers, etc.

– Minimize email and other business

• Respect Participants and Presenters• Respect Participants and Presenters– Please return from breaks on time– Please refrain from side conversations during

presentations

• ConfidentialityAll i t ll i t t– All sessions are open to all registrants

– Utility and vendor representatives participate

Pl id did f db k

5© 2011 Electric Power Research Institute, Inc. All rights reserved.

• Please provide candid feedback

Joint Utility Task Group Background

• Formed in 1990– Address NRC Concerns with procurementAddress NRC Concerns with procurement

(Comprehensive Procurement Initiative)

– Provide utilities a forum to share common resources and expertise

– Develop technical evaluations and commercial grade item dedication plans for commonly procured replacement items.

• Subsequent development of guidelines to assist utilities’ in addressing technical and regulatory issues related to procurement– Ongoing efforts

– These guidelines continue to form the technical basis for member procurement engineering programs

– Currently working on obsolescence, counterfeits, dedication

6© 2011 Electric Power Research Institute, Inc. All rights reserved.

• Through its evolution, the JUTG has emerged as the recognized “community of practice” for nuclear procurement engineering

JUTG Today

Other JUTG Activities

• ASME NQA-1

– Engineering & Procurement Subcommittee

• Nuclear Supply Chain Strategic Leadership (NSCSL)(NSCSL)

– Resolution of key supplier issues

• JUTG Procurement Forums• JUTG Procurement Forums

• JUTG Surveys & Special Projects

• Benchmarking & Assist visits

8© 2011 Electric Power Research Institute, Inc. All rights reserved.

2011 Joint Utility Task Group Steering Committee

William Ware, Chair,

Jim Grant, Vice Chair

Craig Irish NLICraig Irish, NLI

Bhavesh Patel

Daryl Prisby

Paul Saksvig

Marc Tannenbaum, PM

Beth McRimmon Support

9© 2011 Electric Power Research Institute, Inc. All rights reserved.

Beth McRimmon, Support

In the next few days . . .

Registrants Include– US and Canadian Utilities– Department of Energy– Nuclear Regulatory Commission– Nuclear Suppliers and Consultants

Discussion & Topics:– Regulatory activity and concerns

S l ti iti l h t i ti– New Supplier entrance in the

nuclear marketplace– Selecting critical characteristics– Software Acceptance– Managing PE work

Outsourcing equivalency eval’s

nuclear marketplace– “Ask the Regulator”– “Ask the Vendors”

– Outsourcing equivalency eval’s– Off-site repair of critical assets– Reverse Engineering

10CFR21 Rulemaking

10© 2011 Electric Power Research Institute, Inc. All rights reserved.

– 10CFR21 Rulemaking

Upcoming JUTG Meeting

February 21-23 2012February 21-23, 2012•San Antonio, Texas

Agenda items will be establishedduring this meeting

•• Bring up ideas and concerns during theBring up ideas and concerns during the•• Bring up ideas and concerns during the Bring up ideas and concerns during the meetingmeeting

•• Use the Open Discussion templateUse the Open Discussion template•• “Its your meeting”“Its your meeting”•• The Steering Committee welcomes The Steering Committee welcomes

feedback and suggestionsfeedback and suggestions

11© 2011 Electric Power Research Institute, Inc. All rights reserved.

feedback and suggestionsfeedback and suggestions

Meeting Materials

• Meeting materials are available for download at event registration pageregistration page

12© 2011 Electric Power Research Institute, Inc. All rights reserved.

13© 2011 Electric Power Research Institute, Inc. All rights reserved.

Q ti ?Questions?

14© 2011 Electric Power Research Institute, Inc. All rights reserved.

U.S. NRC Information Notice2011-01(Commercial-Grade Dedication IssuesIdentified during NRC Inspections)

Marc H. TannenbaumP j t M EPRIProject Manager, EPRI

Joint Utility Task Group MeetingAugust 23, 2011

US NRC Information Notice 2011-01

• Commercial Grade Dedication Issues Identified during NRC InspectionsNRC Inspections

– Based upon 2 years worth of NRC supplier inspections

• Lack of Engineering Justification During the CGD Process

• Documentation

• Difference between Vendor Audits and CG Surveys

S li Pl• Sampling Plans

2© 2011 Electric Power Research Institute, Inc. All rights reserved.

Lack of Engineering Justification During the CGD Process

3© 2011 Electric Power Research Institute, Inc. All rights reserved.

Lack of Engineering Justification During the CGD Process

Take Away

1 CG1. CGD evaluations must be revised by engineering prior to changing dedication acceptance activities

2 Use equivalency evaluation and modification processes to2. Use equivalency evaluation and modification processes to address design changes, dedication is an acceptanceprocess

Concern/Clarification

Design changes need to be handled outside of the dedication process Dedication is an acceptance process that requiresprocess. . Dedication is an acceptance process that requires engineering involvement.

Interpret as: “Vendor made changes to the technical evaluation

4© 2011 Electric Power Research Institute, Inc. All rights reserved.

or acceptance processes . . .”

Documentation

5© 2011 Electric Power Research Institute, Inc. All rights reserved.

Documentation

6© 2011 Electric Power Research Institute, Inc. All rights reserved.

Documentation

7© 2011 Electric Power Research Institute, Inc. All rights reserved.

Documentation

Take Away

(1. The entire commercial grade dedication process (technical evaluation and acceptance) must be clearly documented in work instructions.

2. Decisions made during acceptance activities must be documented along with results

Concern/Clarification

Expectation that the purchaser must review every dedication plan prior to dedication occurringplan prior to dedication occurring

Ensure the purchaser reviews dedication plans in instances where: (1) The dedicating entity is not familiar with end use

8© 2011 Electric Power Research Institute, Inc. All rights reserved.

( ) g y

(2) Known problems exist with the dedication program

Vendor Audit versus Commercial Grade Survey

9© 2011 Electric Power Research Institute, Inc. All rights reserved.

Vendor Audit versus Commercial Grade Survey

Take Away

1 A i l d t f li t l1. A commercial grade survey must focus on supplier controls related to the critical characteristics identified in the dedication technical evaluation

2. Surveys are necessary even if the supplier has an ISO 9000 Quality Assurance program

3. Limited scope audits are only appropriate when the supplier has a QA program that complies with 10CFR50, Appendix B

4 Pay attention to terminology4. Pay attention to terminology

• “Audit” refers to a look at all 18 Criteria of 10CFR50, Appendix B

10© 2011 Electric Power Research Institute, Inc. All rights reserved.

pp

• “Survey” refers to a look at commercial QA controls

Sampling Plans

11© 2011 Electric Power Research Institute, Inc. All rights reserved.

Sampling Plans

Take Away

S1. Sampling must provide reasonable assurance that items successfully tested or inspected conform to requirements.

2 It is important to document the basis for selection of2. It is important to document the basis for selection of sampling plans, particularly when heat traceability or lot/batch control can not be established.

12© 2011 Electric Power Research Institute, Inc. All rights reserved.

Discussion

(From GL 89-02)

13© 2011 Electric Power Research Institute, Inc. All rights reserved.

Discussion

Concern/Clarification

GL 89-02 places restrictions on the use of both Methods 2 and 4 but onlyGL 89 02 places restrictions on the use of both Methods 2 and 4 but only restricts Method 4 from being used as the sole method of acceptance

Method 2 is restricted to situations in which:

(1) Th li h d t d ff ti t l d if li bl(1) The supplier has documented effective controls, and if applicable,

(2) When distributors are involved; the distributor must also be surveyed

Take AwayTake Away

A single survey cannot be used as a basis for accepting all subsequent purchases from the supplier surveyed unless:p pp y

a)Controls verified during the survey are related to critical characteristics

b)Controls verified during the survey are documented and imposed on the purchase order

14© 2011 Electric Power Research Institute, Inc. All rights reserved.

c) Some type of incoming inspection or verification of certification is

performed for each shipment of items

Flow Chart

Concern/Clarification1 In addition to safety function/significance1. In addition to safety function/significance,

credible failure modes and design characteristics (included in EPRI NP-5652), the Document Results box suggests that design margin be documented in thedesign margin be documented in the technical evaluation.

Considerations involving design margin should be addressed as part of the design process. The design process must be complete prior to using CGD to accept an item. Although design margin may be considered during the modification or design change process, it is not evaluated during the commercial grade item dedication process.

2 Reference to GL 89-02 (repeat)

15© 2011 Electric Power Research Institute, Inc. All rights reserved.

2. Reference to GL 89 02 (repeat)

Summary

Take Away – Recommendations

1 Ensure provisions are included in procedures for reviewing the supplier’s1. Ensure provisions are included in procedures for reviewing the supplier s dedication plan when:

a) The supplier is not familiar with end-use application, safety function(s) etcfunction(s), etc.

b) Known issues exist with the supplier’s dedication program

2. Reinforce the importance of documenting decisions made relative to using M h d 2 l d f if i d i h h fMethod 2 alone and of verifying documentation that supports the use of Method 2 at receipt inspection for every purchase

3. Reinforce the importance of documenting the use of sampling plans (e.g. h t i l l t d d h t f t id d ( hwhy a certain plan was selected and what factors were considered (such

as lot homogeneity, complexity of items, safety significance of characteristics, etc.)

16© 2011 Electric Power Research Institute, Inc. All rights reserved.

Q ti ?Questions?

17© 2011 Electric Power Research Institute, Inc. All rights reserved.

EPRI F ll 2011 JUTG M tiEPRI Fall 2011 JUTG Meeting

Current Events / Concerns in your PE O i tiOrganization

What concerns you most about or within PE – are there any hot

Current Events and Concerns in your Organizations y y

issues that you are dealing with?

Have you had recent assessments (Self assessments or Quality/Oversight assessments) that looked at your PE activities – what did they find – any areas of strength or any areas for improvement?

Are you aware of Industry issues affecting PE such as Software Dedication and NUPIC Findings relating to vendor dedication practices?practices?

How is your interface with your NUPIC representatives and are you notified of significant findings related to PE activities?y g g

How often do you provide the proper safety function of the item being procured on a PO?

Joint Utility Task Group Back to Basics

Selecting Critical CharacteristicsCharacteristics

Marc TannenbaumEPRI P MEPRI Program Manager

Joint Utility Task Group MeetingMinneapolis, MN

1© 2011 Electric Power Research Institute, Inc. All rights reserved.

August 23, 2011

Module 2-2 Objectives

•Understand the process for identifying and l ti iti l h t i ti f tselecting critical characteristics for acceptance

•Understand the NRC definition of critical characteristicscharacteristics

• Identify different types of critical characteristics

U d t d th f id tif i iti l•Understand the process for identifying critical characteristics for seismically sensitive items

•Understand the relationship between critical•Understand the relationship between critical characteristics for acceptance and the item’s safety function(s)

2© 2011 Electric Power Research Institute, Inc. All rights reserved.

y ( )

What is the recommended process for determining safety classification and establishing critical characteristicscharacteristics

• Failure Modes and Effect AnalysisAnalysis Process Conclusion/Resulty

What are the safetyfunctions of the

host component or system?

What are the plant-specific designfunctions including known safety

functions of the item?

What are the postulated, crediblefailure mechanisms of

the item?

What properties or attributes provide reasonable assurance the item conforms

to procurement documents (meets specified requirements)? Criterion VII

Wh t ti tt ib t id

Critical Characteristics for Acceptance

3© 2011 Electric Power Research Institute, Inc. All rights reserved.

What properties or attributes provide reasonable assurance the item received will perform its intended safety function?

10CFR21 Definition

Acceptance

Background/basis

• Per NP-5652, critical characteristics (for acceptance) are:“identifiable and measurable attributes/variables of a commercial grade item“identifiable and measurable attributes/variables of a commercial grade item, which once selected to be verified, provide reasonable assurance that the item received is the item specified.”

1988

• Per NP-6406, critical characteristics for design are:“those properties or attributes which are essential for the item’s form, fit and functional performance. Critical characteristics for design are the identifiable

1989functional performance. Critical characteristics for design are the identifiable and/or measurable attributes of a replacement item which provide assurance that the replacement item will perform its design function.”

1989

• Per 10CFR21, Rev. 2, critical characteristics are:“those important design, material, and performance characteristics of a commercial grade item that, once verified, will provide reasonable assurance th t th it ill f it i t d d f t f ti ”

1995

4© 2011 Electric Power Research Institute, Inc. All rights reserved.

that the item will perform its intended safety function.”

Definitions are consistent and compatible because:

• Intent is to select critical characteristics that provide reasonable assurance the item will perform its safetyreasonable assurance the item will perform its safety functions

• Item’s design function(s) are important in determining critical characteristics for design (CCD)

• Item’s safety function(s) are important in determining critical characteristics for acceptance (CCA)characteristics for acceptance (CCA)

• Selection of CCAs is “based upon the complexity, intended safety-related function, and performance of the CGI using engineering judgment”

NRC does not distinguish

5© 2011 Electric Power Research Institute, Inc. All rights reserved.

NRC does not distinguish between CCAs and CCDs

Original categories of critical characteristics

• Physical CharacteristicsMaterial chemical composition Dimensions– Material chemical composition - Dimensions

– Material strength - Electrical properties– Dimensions - Durometer hardness

• Performance Characteristics• Performance Characteristics– Pick-up/drop-out voltage– Open/close time

Input/output voltage

The physical and performance characteristics are the things we measure– Input/output voltage

– Ability to withstand temperature, pressure, humidity, etc.• Product Identification

– Color coding

g

The 1995 10CFR21 definition suggests that identification attributes are not

– Color coding– Part number/unique identifier– Nameplate data

6© 2011 Electric Power Research Institute, Inc. All rights reserved.

that identification attributes are not considered to be critical characteristics

Original concept of critical characteristics(prior to 1995 revision of 10CFR21)

Critical characteristics for design (2)

(p )

Critical characteristics for acceptance (3)

(1) Other characteristics are

inherent to the item’s design but are not required/used in the

purchaser’s application.

(2) These characteristics are application specific and include

physical and performance characteristics.

(3) All must be verified once selected. Justification for why an

identified critical characteristic selected for acceptance is not

ifi d h ld b d t d

7© 2011 Electric Power Research Institute, Inc. All rights reserved.

Item characteristics (1)

verified should be documented.

Verifying all Critical Characteristics for Design – Not the intent of EPRI or NRC Guidance

Critical characteristics for design (2)

Critical characteristics for acceptance (3)

Yikes, talk about

8© 2011 Electric Power Research Institute, Inc. All rights reserved.

overkillItem characteristics (1)

Inadequate Selection of Critical Characteristics for Acceptance

Critical characteristics for design (2)

Critical characteristics for

p

acceptance (3)

This is way too

9© 2011 Electric Power Research Institute, Inc. All rights reserved.

Item characteristics (1)

weak

Original concept of critical characteristics(prior to 1995 revision of 10CFR21)

Critical characteristics for design (2) Critical characteristics for

acceptance (3)

(p )

A good rule ofA good rule of thumb is to select at least one CCA to address each safety functionsafety function

Cross-hatched area represents:1) Those CCDs that are related to the

item’s safety function2) The CCAs that are measurable

Now this looks reasonable but

2) The CCAs that are measurable(physical or performance type)

10© 2011 Electric Power Research Institute, Inc. All rights reserved.

Item characteristics (1)

Now this looks reasonable, but what about part number?

Identification Attributes

• Strictly speaking, identification characteristics such as part number are not critical characteristics as defined in 10CFR21– They are not design, material, and performance characteristics that

once verified provide reasonable assurance that the item will perform its intended safety function

• Identification characteristics are still important and are typically verified• Identification characteristics are still important, and are typically verified during initial receipt inspection– In accordance with ANSI N45.2.2, Section 5.2 (currently NQA-1,

Subpart 2.2, Section 502.2)• Verification of identification characteristics is important

– Reviewed during technical evaluation to help determine if procurement is like-for-like or alternate item

– Identifies the item and links it to procurement documents that useIdentifies the item and links it to procurement documents that use identification characteristics (such as part number) to communicate with suppliers

– Provides some assurance that a change has not occurred– Confirms identify of the item prior to proceeding with dedication

11© 2011 Electric Power Research Institute, Inc. All rights reserved.

Confirms identify of the item prior to proceeding with dedication acceptance methods to verify design, material, and performance characteristics

USNRC comments regarding the use of industry guidance (NRC IP 43004)

“The identified critical characteristics that are important for the item to perform its safety function as determined in

y g ( )

the item to perform its safety function, as determined in the technical evaluation, are to be verified.”

“Not all design requirements need to be considered criticalNot all design requirements need to be considered critical characteristics; however, licensees or applicants must assure the suitability of all parts, materials, and services for their intended safety related applications ”for their intended safety-related applications.”

“Reliance on part number verification and certification d t ti l i t i i ffi i t tdocumentation alone on receipt is insufficient to ensure the quality and suitability of commercially procured products.”

12© 2011 Electric Power Research Institute, Inc. All rights reserved.

NRC Inspection Procedure 43004, Inspection of Commercial-Grade Dedication Programs (04/25/11)

USNRC comments regarding the use of industry guidance (NRC IP 43004)

“Seismic and environmental qualification should be treated as critical characteristics to be verified ”

y g ( )

as critical characteristics to be verified.

In other words, what about the item enables it to perform p

safety functions during and after design basis accidents?

• Typically for a seismic application, the item’s dimensions and physical material properties are critical.

• Typically for an application inside containment in a post-LOCA environment, the item’s physical and chemical material properties are critical.

13© 2011 Electric Power Research Institute, Inc. All rights reserved.

p pNRC Inspection Procedure 43004, Inspection of Commercial-Grade Dedication Programs (04/25/11)

WOW!Lessons learned

• Although component specifications may not include part level design information it should not be

WOW!

part-level design information, it should not be interpreted that the item has no critical characteristics

• Once selected, each CCA should be properly verifiedy

• Not every technical requirement specified in a procurement document may need to be verified

C l iti l h t i ti f• Conversely, more critical characteristics for acceptance may be selected than those specified in the procurement document

• Verification that “the item received is the item specified” is NOT meant to infer only verification of the part number

14© 2011 Electric Power Research Institute, Inc. All rights reserved.

part numberCCA – Critical Characteristic for Acceptance

Proper identification of critical characteristics

These things are NOT critical characteristics as they are

• Form, fit and function

• Certificate of conformance

H d t ti t t

ynot design, material, and

performance characteristics that provide reasonable assurance the item will

• Hydrostatic test

• Receipt inspection

• Lot homogeneity

perform its intended safety function!

• Lot homogeneity

• Commercial grade survey

• Maintenance instruction

• Environmental test report

• Vendor manual

15© 2011 Electric Power Research Institute, Inc. All rights reserved.

• Part number

Seismic considerations

Unless the item is “seismically

16© 2011 Electric Power Research Institute, Inc. All rights reserved.

yinsensitive”, you should determine

seismic critical characteristics

Determining seismic critical characteristics

17© 2011 Electric Power Research Institute, Inc. All rights reserved.

Determine the theory of operation of the item

• Important in order to identify the appropriate criticalImportant in order to identify the appropriate critical characteristics

• Should describe how the item functions and how the item is designed

• This may include detailed information that may not be t i d f th f t ’ bli h dascertained from the manufacturer’s published

product information or from drawings of the item

• It may be necessary to closely examine the item’sIt may be necessary to closely examine the item s moving parts, and internal mechanical/electro-mechanical sub-assemblies

18© 2011 Electric Power Research Institute, Inc. All rights reserved.

Seismic safety functions

• Should be identified based upon the safety function of the parent equipment and the functional mode (i ethe parent equipment and the functional mode (i.e., active or passive) of the component in that application

• Seismic safety functions are those design functions of th it th t f th t tthe item that are necessary for the component to perform its safety functions during and after a seismic event

• Typical seismic safety functions include:

– Maintain structural integrity– Maintain contact state– Maintain electrical integrity

Maintain calibration

19© 2011 Electric Power Research Institute, Inc. All rights reserved.

– Maintain calibration– Operate without spurious action

Seismic failure mechanisms

• Failures of each item should be postulated based upon its application and the accident conditions toupon its application and the accident conditions to which it might be exposed

• Defined as “the manner by which an item may fail, d di th it ’ bilit t f th t/degrading the item’s ability to perform the component/ system function under evaluation”

• Typical seismic failure mechanisms may include:yp y

– Structural failure– Chatter of contacts (inadvertent change of state

due to seismic vibration)– Failure to operate

Loss of calibration or setpoint

20© 2011 Electric Power Research Institute, Inc. All rights reserved.

– Loss of calibration or setpoint– Inadvertent actuation

Critical seismic attributes

• Critical seismic attributes are defined as “those properties or attributes that are essential for the item's seismic performance”

• They should be selected to address both the seismicThey should be selected to address both the seismic safety function(s) and any postulated seismic failure mechanisms

E l f iti l i i tt ib t i l d• Examples of critical seismic attributes include:

– Coil magnetic strength

Armature over travel– Armature over-travel

– Mass of moving contacts

– Torsion/return spring force

21© 2011 Electric Power Research Institute, Inc. All rights reserved.

Torsion/return spring force

Seismic critical characteristics

• Seismic critical characteristics are “those important design, material, and performance characteristics of a g , , pCGI that once verified, will provide reasonable assurance that the item will perform its intended seismic safety function(s)”seismic safety function(s)

• Seismic critical characteristics that may affect the ability to perform during or after a seismic event i l dinclude:

– Mass and strength of the materials– Configuration and dimensions/tolerances of theConfiguration and dimensions/tolerances of the

item and certain sub-components– Spring constant

C t t b ti

22© 2011 Electric Power Research Institute, Inc. All rights reserved.

– Contact bounce time– Operate time

Seismic critical characteristics

• Each critical seismic attribute should have a related critical characteristic for acceptance

• Factors that can be considered in selecting related seismic critical characteristics for acceptance include:seismic critical characteristics for acceptance include:

– Complexity of the item

– End use applicationEnd use application

– Margin between seismic capacity and demand

23© 2011 Electric Power Research Institute, Inc. All rights reserved.

Seismic critical characteristics

• In some instances the related critical characteristic will• In some instances the related critical characteristic will be a direct measure of the critical seismic attribute (e.g., operating torque is a direct measure of torsion

d t i f )and return spring forces).

• In many cases it will be an indirect measure (may• In many cases it will be an indirect measure (may require verification in combination with other related critical characteristics to establish a clear link to the qualification basis)qualification basis)

24© 2011 Electric Power Research Institute, Inc. All rights reserved.

Options for obtaining or recovering acceptance criteria

• Measurements taken from hardwareOption 1 Measure the tested item in conjunction with seismic testing– Option 1 - Measure the tested item in conjunction with seismic testing

– Option 2 - Measure a qualified item procured concurrently with seismic test specimen

– Option 3 - Measure an identical item procured subsequent to seismicOption 3 Measure an identical item procured subsequent to seismic testing but traceable through the seismic test report

Option 1:

Measure characteristics on the

Option 2:

Measure characteristics on a

Option 3:

Measure characteristics on

Qualified items

(same lot as the item that was tested)

tested item qualified item an identical item

Tested item

that was tested)Identical item

(procured subsequent to the seismic test)

25© 2011 Electric Power Research Institute, Inc. All rights reserved.

Seismic test report

Assigning tolerances to measured characteristics

• Any of the options for taking measurements still only provide a nominal valueprovide a nominal value

• Tolerances should be assigned taking into consideration factors such as:

– Margin between seismic capacity and demand• Seismic capacity - The highest seismic level for which

required adequacy has been verified (for an item)q q y ( )

• Seismic demand - A quantification of the service requirements due to earthquake loads on the item being evaluated

– Seismic safety functions – End-use application– Typical allowable tolerances employed during

26© 2011 Electric Power Research Institute, Inc. All rights reserved.

Typical allowable tolerances employed during manufacture of the item

Options for obtaining or recovering acceptance criteria

• Information provided by the supplier

– Manufacturer’s published technical literature

Technical

Man al VendorManual Vendor

catalog Seismic

test

Drawings

– Direct communication with the manufacturerreport

Can you provide me with the spring t i l d i t t?

27© 2011 Electric Power Research Institute, Inc. All rights reserved.

material and spring constant?

Acceptance methods

• ANSI N45.2.13 allows the licensee various means by which selected critical characteristics may be verified:which selected critical characteristics may be verified:

– Special testing/inspection of the hardware received

– Performance-based evaluation of the manufacturer’s quality controls

– Source verification at the manufacturing facility

R li hi t i l f f th it d– Reliance on historical performance of the item and its supplier

• Special tests/inspections are the most common usedSpecial tests/inspections are the most common used method for dedicating CGIs

• The evaluations focus on those special functional t t d/ i ti th t ld d t l if

28© 2011 Electric Power Research Institute, Inc. All rights reserved.

tests and/or inspections that would adequately verify the critical characteristics identified

Adequate acceptance plans

• If the seismic CGI acceptance plan is adequate, thenIf the seismic CGI acceptance plan is adequate, then it should supplement the overall CGI acceptance/dedication plan for the seismically sensitive itemsensitive item

• There may be other critical characteristics requiring y q gverification (in addition to those seismic critical characteristics) to reasonably assure that the item will perform other safety-related functions under normalperform other safety related functions under normal and accident conditions

29© 2011 Electric Power Research Institute, Inc. All rights reserved.

Inadequate acceptance plans

• If the seismic CGI acceptance plan is not adequate, then the following actions should be considered:following actions should be considered:

– Procure an alternate item

– Procure the item as a basic component from a nuclear psupplier with a 10CFR50, Appendix B QA program.• The supplier performs qualification activities under their nuclear QA

program. In this case the supplier may be the original equipment p g pp y g q pmanufacturer (OEM) or a third-party supplier. The user should consider including the seismic critical characteristics in the performance-based supplier audit (PBSA) plan.)

– Consider alternate acceptance methods • Commercial grade survey• Source verification

30© 2011 Electric Power Research Institute, Inc. All rights reserved.

– Consider seismic testing

Maintaining equipment qualification

V ifi ti f CCA ( t ) fi th t th• Verification of CCAs (acceptance) confirms that the item received conforms to design requirements

• Acceptance may also add assurance that the designAcceptance may also add assurance that the design of the item has not changed over time (i.e., acceptance assures that items received now are identical to those previously qualified)identical to those previously qualified)

Therefore, acceptance activities provide assurance that an item procured today remains “qualified”

31© 2011 Electric Power Research Institute, Inc. All rights reserved.

p y q

Acceptance based on generic applications

• Critical characteristics should be selected id i th t li ticonsidering the most severe application

• National codes and standards may bound critical characteristics for designg

• Benefits of generic acceptance

– End use does not need to be determined

– Can procure, accept, and store on a generic basis

Cost savings through parts consolidation– Cost savings through parts consolidation

32© 2011 Electric Power Research Institute, Inc. All rights reserved.

Q ti ?Questions?

33© 2011 Electric Power Research Institute, Inc. All rights reserved.

Guideline for the Utilization of Commercial Grade Computer Programs in Nuclear Safety-Related ApplicationsApplications

Marc H. TannenbaumP j t M EPRIProject Manager, EPRI

Joint Utility Task Group MeetingAugust 23, 2011

Historical Perspectives on Acceptance of Commercial Grade Computer Programsp g

• Computer programs (not embedded in plant equipment) could be perceived as not meeting the definition of acould be perceived as not meeting the definition of a “commercial grade item” in 10CFR21

C t t i t• Computer programs use was not as prominent

– Regulatory documents mention software but do not address it in detail

• Acceptance performed by subject matter experts

• Licensees implement software quality assurance (SQA) programs under the umbrella of their 10CFR50, Appendix

2© 2011 Electric Power Research Institute, Inc. All rights reserved.

B QA programs.

Historical Perspectives on Acceptance of Commercial Grade Software

• Methods such as verification and validation were used

– Verify Software performs as expected

– Validate Software leads to the correct answer

– Testing for base code and updates

• We are doing the right things!

– Acceptance not always packaged as “dedication”

– Safety function and related critical characteristics not always identified in that context

3© 2011 Electric Power Research Institute, Inc. All rights reserved.

Discussion on the topic recently emerged

• Audit of new plant engineering, construction and procurement firms (2009/10)procurement firms (2009/10)

• NRC audit of new plant activities (2010)NRC audit of new plant activities (2010)

• Clear verbal communication from NRC (2010)

– Verification and Validation is not enough

– Nothing has changed

• Nuclear Energy Institute is engaged

4© 2011 Electric Power Research Institute, Inc. All rights reserved.

gy g g

Where is the NRC?

• Rulemaking is underway

P d i i / it t 10CFR P t 21– Proposed revision/rewrite to 10CFR, Part 21

• SECY to commission in September, 2011

• Expect effort to be fast-tracked and underway in 2012

– Considerations involving relocation of regulatory guidance on dedicationguidance on dedication

– “Software” will be clearly identified as a basic componentcomponent

– Software is listed as one of 25 topics the NRC plans to address in 10CFR21 rulemaking

5© 2011 Electric Power Research Institute, Inc. All rights reserved.

Where is NUPIC?

• Memo issued in late February 2011 to all auditors and supplierssuppliers

– Expectation that commercial design analysis software be dedicated “in accordance with NP-5652”

• Revised direction was provided in a NUPIC newsletter in May 2011May 2011

– References more pertinent EPRI guidance TR-106439

• Findings are being issued against suppliers, even when they have robust software QA, verification ,and validation

6© 2011 Electric Power Research Institute, Inc. All rights reserved.

– . . . but don’t package acceptance as “dedication”

Where are we now?

• Project to develop guidance is underway

– First meeting in March

– Second meeting in June

– Third meeting in August

– Third draft is out for review with NEI New Plant QA Task Force

• EPRI is working with NEI to seek NRC endorsement as early as possible

7© 2011 Electric Power Research Institute, Inc. All rights reserved.

Represented on the team

8© 2011 Electric Power Research Institute, Inc. All rights reserved.

EPRI Project - Acceptance of Commercial Grade Software for use as a Basic Componentp

• Project initiated in October of 2010

– Currently on third draft

– Primary focus is design analysis software used as a b i t i f t l t d li tibasic component in safety related applications

– EPRI is working with Nuclear Energy Institute to support NRC endorsement of EPRI guidancesupport NRC endorsement of EPRI guidance

• Scope includes commercial software/computer code that is NOT installed in plant systems and equipmentis NOT installed in plant systems and equipment

– Software inherent in plant equipment is addressed in EPRI TR-106439 and other EPRi documents.

9© 2011 Electric Power Research Institute, Inc. All rights reserved.

Report Contents

Computer Program

Categories &

Baseline Terminology –Definitions &Categories &

Uses

Section 4

Section 3

Definitions & Acronyms

Generic Technical Evaluation & Acceptance Processes

Section 5

Section 2

Introduction

Functional Safety Classification of

Computer ProgramsSection

6Section

9References & Bibliography

Section 8

Section 7

10© 2011 Electric Power Research Institute, Inc. All rights reserved.

Procurement Examples of Computer

Programs

Acceptance Of Commercial Grade

Computer Programs

Safety Classification Methodologies

Classification Considering Impact

Classification Considering Failure Risk-Informed

Functional Safety Classification

Considering Impact Categorization

Considering Failure Modes and Effects

Risk-Informed Safety Classification

Section 6.3.1 Section 6.3.2 Section 6.4

• Deterministic methodologies

• Result in two classifications (Safety-Related or Non-Safety Related)

• Typically performed by technical/engineering

• Risk-informed methodology

• Results in four safety classifications

• Probabilistic Risk Assessment• Typically performed by technical/engineeringpersonnel

• Probabilistic Risk Assessment(PRA) is needed

11© 2011 Electric Power Research Institute, Inc. All rights reserved.

Does the computer program perform safety-

related function?

Procure computer program

non-safety

No7.1

Yes Procure computer

Yes

alua

tion

Is the computer program

b i d

No

program as a basic

component

echn

ical

Eva

7.2

Sections 5 & 6

being procured as a basic component?

Identify critical characteristics

Document results

Tep

tanc

e7.3

Select acceptance method(s)

Acc

e

7.4

7.5

Method 4*Method 3Method 2Method 1 Combination of two or more of the

four methods

Item accepted

* Generic Letter 89-02 provides conditions for using Method 4 alone.

Relationship of Design and Acceptance for Software

DesignQualification

of design

Technicalevaluation &

acceptanceacti ities

Figure 1 - Typical process flow for hardware items

activities

Co

Requ

RetD

Insta

Mai

Technical evaluation and acceptance activitiesoncept

uirements

tirement

Design

Test

all/Check

nt,/Op’s

Design,qualification of design,maintenance & updates

acceptance activities

14© 2011 Electric Power Research Institute, Inc. All rights reserved.

Figure 2 - Typical process flow (lifecycle) for softwareFigure 3 – Overlaying dedication techniques to accept software

Relationship of Design and Acceptance for Software

R In M

Concept

Requirem

ent

Retirem

ent

Design

Test

nstall/Chec

Maint,/O

p’s

Figure 2 - Typical process flow (lifecycle) for software

ts tk s

Co

Requ

RetD

Insta

Mai

Technical evaluation and acceptance activitiesoncept

uirements

tirement

Design

Test

all/Check

nt,/Op’s

Design,qualification of design,maintenance & updates

acceptance activities

15© 2011 Electric Power Research Institute, Inc. All rights reserved.

Figure 3 – Overlaying dedication techniques to accept software

Application of Acceptance Methods

Inspection Attribute/Critical Characteristics

Acceptance Criteria Possible Method(s) of Acceptance

Software Revision Number Conforms to the procurement document Standard Receipt Inspection

Update (configuration) Control Current configuration remains suitable for the application

Method 2 (CG Survey)

Platform compatibility (operating system, etc.)

Computer program is compatible with the current operating system

Method 1 (Testing)

Hardware compatibility Computer program is compatible with the current hardware

Method 1 (Testing)

Built-in-Quality Appropriate in-process tests and inspections are performed

Method 2 (CG Survey)

Q lit f D i d I l t ti D i t l f d i M th d 2 (CG S )Quality of Design and Implementation Design controls are performed in accordance with SQA

Method 2 (CG Survey)

Functions/Applications Outputs are consistent and accurate for various applications

Method 1 (Testing), Method 2 (CG Survey)

Range (input variables, limits of Outputs are consistent and accurate Method 1 (Testing), application, etc.) over a range of inputs and applications Method 2 (CG Survey)

Accuracy Outputs are mathematically accurate Method 1 (Testing), Method 2 (CG Survey)

Consistency Repeatability Outputs are consistent and accurate Method 1 (Testing)

16© 2011 Electric Power Research Institute, Inc. All rights reserved.

Consistency Repeatability Outputs are consistent and accurate over numerous times the computer program is used

Method 1 (Testing), Method 2 (CG Survey)

What should we be doing internally?

I iti t di l b t P t• Initiate dialog between Procurement Engineering, Information Technology, and your Vendor Audit organizationsVendor Audit organizations

–Review internal software acceptance methods

•Classification processClassification process

•Ensure safety function and failure modes are consideredare considered

–Establish a point of contact for requesting SME support for supplier assessments

17© 2011 Electric Power Research Institute, Inc. All rights reserved.

pp pp

Q ti ?Questions?

18© 2011 Electric Power Research Institute, Inc. All rights reserved.

Current Regulatory Issues

Marc H. TannenbaumP j t M EPRIProject Manager, EPRI

Joint Utility Task Group MeetingAugust 23, 2011

Current Regulatory Activities

• Acceptance of Software for use in non-plant SSC Nuclear Safety Related ApplicationsRelated Applications

– Development of industry guidance

Miti ti f C t f it d F d l t It• Mitigation of Counterfeit and Fraudulent Items

– NRC Public Meeting on June 30, 2011

• Proposed changes to 10CFR, Part 21

– NRC Public Meeting on August 1, 2011

– Clarify reporting requirementsClarify reporting requirements

– Relocate commercial grade dedication requirements

– Possible revision to EPRI NP-5652 to support NRC endorsement of industry guidance

2© 2011 Electric Power Research Institute, Inc. All rights reserved.

of industry guidance

Managing PE Work

Managing PE Work -Managing PE Work EPRI JUTG Presentation

Problem StatementProblem Statement

Currently, Procurement Engineering has processes in place to manage work thatprocesses in-place to manage work that are labour intensive, contain multiple data sources and does not provide a clear linesources and does not provide a clear line of sight on overall priorities within our core businessbusiness.

PassPort RoutingPassPort Routing

• Time Consuming• Time Consuming

• Difficult to Manage Resource Loading

• Inability to

Track HistoryTrack History

Cognos ReportingCognos Reporting

• Cognos is a reporting tool that queries data from PassPort• Cognos is a reporting tool that queries data from PassPort

• Bruce Power I.T owns and updates Cognos reports

LimitationsC i l t• Cognos is slow to run

• Requires months to update or to generate new reports

• Report data is limited in the number of rows that can be pulled

Ti i k i d h d l k• Time consuming to track metrics and schedule work

• Daily manual effort needed to run reports

• Only available for viewing in select formats

Procurement EngineeringProcurement EngineeringWork Management System

Mission StatementMission Statement

Our mission is to protect ProcurementOur mission is to protect Procurement Engineering’s core business of setting up CID’s for purchase in support of safe andCID s for purchase in support of safe and reliable plant operations at Bruce A and Bruce BBruce B.

PE Work Programs and PrioritiesPE Work Programs and Priorities

Goals:- Provide Clear Work Visibility And Improve Work Management - Reduce/Eliminate Wasted Resources And Identify Risks Early

Automated Scheduling & MetricsAutomated Scheduling & Metrics

• Required Date, TCD and Scope Changes allow prioritization and optimizationprioritization and optimization.

• Automation reduces required resources for• Automation reduces required resources for delegation, tracking and reporting.

• Consolidating several work sources into one to simplify and organize demand reports.simplify and organize demand reports.

Automated SchedulingAutomated Scheduling

Managing PE Work

Reporting Made EasyReporting Made Easy

• Dynamic reports allow Managers and Engineers to present specific/detailedEngineers to present specific/detailed information as required.

R t b i d i lti l t• Reports can be viewed in multiple ways to meet the needs.

A– Access

– Excel

Word document– Word document

Automated ReportingAutomated Reporting

Resource LoadingResource Loading

Risk AnalysisRisk Analysis

• System identifies changes not currently recorded by PassPort such as scheduledrecorded by PassPort such as scheduled dates and tracks the issues for Procurement to analyze.y

• Upcoming workload identification toUpcoming workload identification to provide early indicators of work load increases and decreases.

Optimize ResourcesOptimize Resources

• The system updates itself at a set time each day from data in PassPorteach day from data in PassPort.

• Work done in PassPort will be updated i t th tinto the system.

• No external changes to the company or any outside procedure required.

• Less effort, less noise, higher accuracy., , g y

CloseClose

Questions or Comments

Managing Procurement Engineering WorkEngineering Work

Paul Saksvig

Supervisor, Procurement Engineering

i iDominion

1

PurposePurpose

• How Dominion Procurement Engineers fit• How Dominion Procurement Engineers fit into the T-schedule.

PE i i i i f O li d• PE prioritizing of Outage, on-line and non-scheduled items

2

PE Work Drivers (Mostly)PE Work Drivers (Mostly)

• T Week Scheduled Work• T-Week Scheduled Work

• Outage Work

• Material Issues/Discrepancies/Obsolescence

• Corrective Actions

• Project Support/General SCM Support

• Safety Stock Processing/Non Scheduled• Safety Stock Processing/Non-Scheduled

3

Corrective ActionsCorrective Actions

Material Discrepancies and Corrective Actions to SCM typically wind up withActions to SCM typically wind up with PE

•On average 100-150 CA/yr for VA alone

•Issues during quote process and upon•Issues during quote process and upon receipt – (mostly obsolescence or vendor supplying different part) take time to

4

supplying different part) take time to resolve

Dominion PE ResourcesDominion PE Resources

• Dominion Procurement Engineering• Dominion Procurement Engineering– 8 PEs and Supervisor at Millstone

5 PE d S i K– 5 PEs and Supervisor at Kewaunee

– 9 PEs and Supervisor at Surry/North Anna

• All PEs use common platform and procedures for job functions

5

Dominion PE ResourcesDominion PE Resources

• Each Site Manages day to day PE issues• Each Site Manages day to day PE issues

• Inter-site support for emergent needs

• Working to expand fleet sharing of resources

6

VA PE Support

Procurement Engineers in VA gsupport two sites so it becomes a challenge to track and meet thechallenge to track and meet the scheduling requirements of two

kwork groups.

7

Software PlatformsSoftware Platforms

• SAP for stock system and P O processing• SAP for stock system and P.O. processing– PE products are produced and stored in SAP

and linked to the material stock numberand linked to the material stock number

– Material discrepancies – notifications are generated in SAPgenerated in SAP

– Buyer’s communication to PE on parts issues are generated and stored in SAPare generated and stored in SAP

8

Software PlatformsSoftware Platforms

• Maximo for work control• Maximo for work control– Restraints created in Maximo for items that

require PE action Equivalencies QArequire PE action – Equivalencies, QA mismatch, other

– Restraints may be auto/manual created– Restraints may be auto/manual created

– PE can create/complete restraints

9

P i i i i W kPrioritizing Work• Until last year prioritizing work in PEs buckets was difficult

•Typically - the group that requested the loudest that got higher priority

• No consolidated list which made tracking work by the PE supervisors

10

very time consuming

Backlog Database Developed

•Improved tracking database has helped considerably with managing p y g gwork load

All k f i i i•All PE tasks from requisition processing to receipt notifications associated with an item or on theassociated with an item or on the list

11

Backlog Database Developed

•Groups common issues allowing PEs to know what tasks need to be completed before the issue is resolved.

•Puts in graphical form upcoming workwork

12

Priority Ranking

1 -Work Starting in next 16 weeks

2 W k S i 16 k2- Work Starting > 16 weeks

3- Critical Stock Reorders – 0 on hand

4- Critical Stock Reorders – some on handhand

5- Non-Critical/Non-Scheduled stock d

13

orders

T-Week Scheduling

Request for paperwork (IEE) completion is being pushed further outis being pushed further out

T 6 IEE must be approved or stationT-6 – IEE must be approved or station willing to carry at risk (not quite thereyet)yet)

14

Use of the ListUse of the List

• Database updated weekly Monday morning for use by PEs LIST

• Proving an effective tool for PEs to manage their work

• Visual tool to look ahead to upcoming IEEs CHARTCHART

15

ChallengesChallenges

The database has helped a lot but:

•PEs tend to focus on Priority 1 or 2 items and ignore low hanging fruit in other groups

•Daily issues tend to keep focus off of•Daily issues tend to keep focus off of scheduled work

16

•Other product due dates direct resources

ChallengesChallenges

Site SCM Coordinators/PE Sup Interface

•Have gotten better at screening non-priority issues and pushing back on items that are not really emergent

•PE Supervision needs to be actively•PE Supervision needs to be actively engaged in screening requests

17

Other Actions to Manage WorkOther Actions to Manage Work

•Procedure enhancement to minimize errors and standardize processesand standardize processes

•Leveraging vendors to provide the evaluation with the material

•Process improvements to better define “non•Process improvements to better define non-plant” work and non-critical changes

18

•IEE Short Form

ConclusionConclusion

• Procurement Eng support of the T-Schedule has improved significantly p g y

• Database and Chart tools are improving managing the work loadmanaging the work load

• Too many other issues still pull on PE resources and are not easily trackedand are not easily tracked

19

QUESTIONS?QUESTIONS?

20

Backlog Report by Priority

North Anna and Surry Power Stations

Procurement Engineering

Virginia Backlog Report

1a) Work Starting in the Next 16 WeeksStock# Description OnHandQA Ttl ResRestricted BlockedQI Man.Entry?

0000041248

ASSIGNED

8/8/2011

06506841 Relay, control, 12 vdc coil voltage 0 0 0 0 Rec.# 13734

Earliest Sch. Date Best Delivery Date (Lead Time):

Requestor: TERESA J LAMBERT

0

08/01/11Doc Creation:CHANGEMMSR#

Responsible: Paul SaksvigPlant: SURR

Age of Doc. (days): 7

38103088978 0POD01-CP-PNL-1Planner, Loc, WO, Event, Qty Res, Start Date:

0000035197

ASSIGNED

8/8/2011

41047103 Valve, ball, 1/2 , body material ss ast 0 0 0 0 Rec.# 10758

Earliest Sch. Date Best Delivery Date (Lead Time):

Requestor: TERESA J LAMBERT

0

03/31/11Doc Creation:CHANGEMMSR#

Responsible: Richard D. LeePlant: SURR

Age of Doc. (days): 130

0Planner, Loc, WO, Event, Qty Res, Start Date:

0000007433

ASSIGNED

8/8/2011

42138648 Assembly, rotating, includes impellar, 0 0 0 0 Rec.# 2614

Earliest Sch. Date Best Delivery Date (Lead Time):

Requestor: BRENDA S WELCH

0

09/08/09Doc Creation:CHANGEMMSR#

Responsible: T. Bryan JacobsPlant: SURR

Age of Doc. (days): 699

n/a 0tion01-FW-P-1A/BPlanner, Loc, WO, Event, Qty Res, Start Date:

2000052293 10/26/09

06486978 Tube, "u" bundle, heat exchanger, ss 0 0 0 0 Rec.# 6152

Earliest Sch. Date Best Delivery Date (Lead Time):

0

Doc Creation:REQ#

Responsible: PE - VAPlant: SURR

Age of Doc. (days):

38102330172 10/26/20090tion02-CH-E-4-HTEXCHPlanner, Loc, WO, Event, Qty Res, Start Date: Eddie Turner

98842

OPEN

8/7/201108/12/10

98842 Unapproved Parts 0 0 0 0

Earliest Sch. Date Best Delivery Date (Lead Time):

0

08/20/10Doc Creation:OPENRESTRAINT#

Responsible: Unapproved-UnassignedPlant: SURR

Age of Doc. (days): 352

38102743738 8/12/20100On-LineSU-09-00074Planner, Loc, WO, Event, Qty Res, Start Date: NORMAN PARHAM

98843

OPEN

8/7/201108/12/10

98843 Unapproved Parts 0 0 0 0

Earliest Sch. Date Best Delivery Date (Lead Time):

0

08/20/10Doc Creation:OPENRESTRAINT#

Responsible: Unapproved-UnassignedPlant: SURR

Age of Doc. (days): 352

38102743738 8/12/20100On-LineSU-09-00074Planner, Loc, WO, Event, Qty Res, Start Date: NORMAN PARHAM

98844

OPEN

8/7/201108/12/10

98844 Unapproved Parts 0 0 0 0

Earliest Sch. Date Best Delivery Date (Lead Time):

0

08/20/10Doc Creation:OPENRESTRAINT#

Responsible: Unapproved-UnassignedPlant: SURR

Age of Doc. (days): 352

38102743738 8/12/20100On-LineSU-09-00074Planner, Loc, WO, Event, Qty Res, Start Date: NORMAN PARHAM

98845

OPEN

8/7/201108/12/10

98845 Unapproved Parts 0 0 0 0

Earliest Sch. Date Best Delivery Date (Lead Time):

0

08/20/10Doc Creation:OPENRESTRAINT#

Responsible: Unapproved-UnassignedPlant: SURR

Age of Doc. (days): 352

Thursday, August 11, 2011 Page 1 of 180

Generation SCM Key IndicatorsGeneration SCM Key IndicatorsWeekly IndicatorsWeekly IndicatorsWeekly IndicatorsWeekly Indicators

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Combined Kewaunee Millstone North Anna Surry

Upcoming Receipt Activity CAUTION! CAUTION! CAUTION! CAUTION! CAUTION!

Upcoming Issue Activity GOOD GOOD CAUTION! GOOD CAUTION!

(Caution: There is at least 1 week above the average receipts)*

* Upcoming Issue Activity GOOD GOOD CAUTION! GOOD CAUTION!

PE Aggregate Backlog GOOD GOOD CAUTION! GOOD GOOD

(Caution: There is at least 1 week above the average issues)

(Caution: There was an increase in the last four weeks compared to the previous four weeks)

*

*

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Combined MRP PE Sourcing Other

Requisition Backlog GOOD GOOD GOOD CAUTION! CAUTION!

(Caution: There was an increase in the last four weeks compared to the previous four weeks)

* Monthly Indicators

1

Requisition Backlog GOOD GOOD GOOD CAUTION! CAUTION!

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐(Caution: There was an increase in the last four weeks compared to the previous four weeks)

Open IEEsOpen IEEspp

800

900

45

50

IEEs Required - Nuclear

Combined Kewaunee Millstone North Anna Surry

600

700

800

30

35

40

45 yCAUTION! CAUTION! CAUTION! CAUTION! GOOD

300

400

500

15

20

25

30

100

200

5

10

15

00

Outages IEEs Required Avergae Age of Group

2

Level: NuclearLevel: NuclearGroup: PEGroup: PEFrequency: MonthlyFrequency: Monthly

KewauneeStations: Millstone North Anna Surry

NextMore Detail

Open IEEsOpen IEEspp

800

18

20

IEEs Required - North Anna

500

600

700

12

14

16

18

300

400

6

8

10

12

0

100

200

0

2

4

6

00

Outages IEEs Required Avergae Age of Group

3

Level: NuclearLevel: NuclearGroup: PEGroup: PEFrequency: MonthlyFrequency: Monthly Back

More Detail

Open IEEsOpen IEEspp

171

155 156

700

160

180

Fleet Open IEEs

Combined Kewaunee Millstone North Anna Surry144 144

362 400

500

600

120

140

160

IEEs

Average A

ge (Days Good

Combined Kewaunee Millstone North Anna SurryCAUTION! CAUTION! CAUTION! CAUTION! GOOD

(Caution: Increase in numbers or average age)

319 326 324 313

362

200

300

400

60

80

100#

s)

0

100

0

20

40

Jan 11 Feb 11 Mar 11 Apr 11 May 11 Jun 11 Jul 11 Aug 11 Sep 11 Oct 11 Nov 11 Dec 11Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11

Open IEEs Average Age (Restraint)

4

Level: NuclearLevel: NuclearGroup: PEGroup: PEFrequency: MonthlyFrequency: Monthly

KewauneeStations:Millstone

North AnnaSurry

Back

Open IEEsOpen IEEspp

69

70080

North Anna Open IEEs

64

69

400

500

600

50

60

70

IEEs

Average A

ge (Days Good

271252

200

300

400

20

30

40

#

s)

0

100

0

10

20

Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11

Open IEEs Average Age (Restraint)

5

Level: Nuclear Level: Nuclear ‐‐ StationStationGroup: PEGroup: PEFrequency: MonthlyFrequency: Monthly Back

More Detail

Open IEE DetailOpen IEE DetailNorth AnnaNorth Anna99359053024801 01 CM MUX 10A INTCPM NEED IEE TO USE CABLE # 42070504 7/26/2011North AnnaNorth Anna

AgeList of IEEs by Age (blank due dates are unscheduled work orders)

WO # Equipment ID Description Due DateAgeList of IEEs by Age (blank due dates are unscheduled work orders)

WO # Equipment ID Description Due Date

993

14

14

103

01-BY-BC-1-I-BATTRY NEED IEE 10000016639 FOR SN 42169182 8/2/2011

5910209764301-EE-BKR-1H1-2N-C1-

CKTBRKNEED IEE FOR REPLACEMENT CONTACTOR 8/2/2011

59102229654

59053024801 01-CM-MUX-10A-INTCPM NEED IEE TO USE CABLE # 42070504 7/26/2011

59102229686 01-BY-BC-1C-I-BATTRY NEED IEE 10000016639 FOR SN 42169182 8/1/2011 132

132

132

132NEED IEE FOR TOL

9/28/2011

9/28/2011

9/28/2011

9/29/2011

NEED IEE

NEED IEE FOR TOL

NEED IEE FOR TOL

02-EP-BKR-2C2-2-C4-CKTBRK

02-EP-BKR-2C1-3-E1-CKTBRK02-EP-BKR-2C1-3-B1-

02-EP-BKR-2C2-2-B2-CKTBRK

59101614494

59101612470

59101614415

59101614439

103

14

2588/10/2011NEED IEE WRITTEN TO USE Z00-1.6 OVERLOAD

INSTEAD02-EE-BKR-2J1-1-A4-

CKTBRK59101654460

01-EE-BKR-1H1-4-B4-CKTBRK

NEED IEE FOR REPLACEMENT CONTACTOR 8/3/2011

59102229662 01-BY-BC-1-II-BATTRY NEED IEE 10000016639 FOR SN 42169182 8/4/2011

59102099767

CKTBRK33

132

132

896

9/29/2011

NEED IEE TO USE SN 42159895.INSTALLED TOL IS A Z4

NEED IEE FOR TOL

9/29/2011

9/29/2011

10/4/2011

02-EP-BKR-2C1-3-C1-CKTBRK02-EP-BKR-2C1-3-E3-CKTBRK

NEED IEE FOR TOL

PROC ENG LOOKING FOR REPLACEMENT RTD

CKTBRK

02-EP-BKR-2C1-3-C3-CKTBRK

59101614421

59101614433

59101614427

59101814741 02-CH-TE-2116-DETECT

188

103

103

8/10/2011

8/11/2011

8/29/2011

INSTEAD

NEED IEER FOR MATERIAL STOCK #42159963. OVERLOAD

NEED IEE FOR REPLACEMENT CONTACTOR

NEED IEE FOR REPLACEMENT CONTACTOR

CKTBRK

02-EE-BKR-2J1-1-A4-CKTBRK

02-EE-BKR-2J1-3-A1-CKTBRK

01-EE-BKR-1H1-3-B1-CKTBRK

59102199455

59102099893

59102099758

896

357

103

10310/27/2011NEED IEE FOR REPLACEMENT CONTACTOR

10/4/2011PROC ENG LOOKING FOR REPLACEMENT RTD

02-EE-BKR-2H1-1-C4-CKTBRK

02-EE-BKR-2H1-1-B2-CKTBRK

59102099965

59102099821 NEED IEE FOR REPLACEMENT CONTACTOR 10/26/2011

59101814741

01-EE-BKR-1H1-1-F3-CKTBRK

NEED IEE 10/24/201159102095933

02 CH TE 2116 DETECT

02 EE BKR 2H1 1 B104

5

125

159/26/2011

9/14/2011

9/25/2011

9/25/2011

Evaluate IEE for use of item 07553160

02-EP-BKR-2C1-1-C4-CKTBRK

02-TM-62-2TMAN01-RELAY

NEED IEE 10000002754 APPROVED

need location added to iee10000000714 sn42109670

NEED IEE FOR REPLACEMENT OVERLOAD02-EE-BKR-2J1-2S-J1-

01-HV-F-31-MOTOR

59102105499

59102287028

59102252500

59101614528

103

216

238

659

59102097418

59101667425

59101913907

59101897698

02-EE-BKR-2H1-1-B5-CKTBRK01-EP-BKR-1B2-4-B2-CKTBRK

01-FW-E-4B-HTEXCH

01-BLD-BLD-SB-BLDG

NEED IEE FOR REPLACEMENT CONTACTOR

NEED IEE TO USE REPLACEMENT O/L STK#42156501

Needs further evalauation

Fixture (obsolete) MMSR # 0000005286 (Paul S k i

10/27/2011

10/31/2011

11/1/2011

11/8/201115

124

124

124

132

NEED IEE FOR EGS CONNECTOR 42078417

9/27/2011

9/27/2011

9/27/2011

9/27/2011

NEED IEE FOR EGS CONNECTOR 42078417

NEED IEE FOR TOL

NEED IEE FOR EGS CONNECTOR 42078417

02-EP-BKR-2C1-2-C1-CKTBRK

CKTBRK02-FW-LT-2476-IXMITR

02-FW-LT-2475-IXMITR

02-FW-LT-2474-IXMITR

59101697165

59101697167

59101697177

59101614522

556

14

14

59101945720 01-FP--1179-VALVE

59102229742

59102229718

59102229726

02-BY-BC-2C-II-BATTRY

02-BY-BC-2-III-BATTRY

02 BY BC 2 IV BATTRY

NUT # 42141941 IS NO LONGER MADE BY VALVE CO.

NEED IEE 10000016639 FOR SN 42169182

NEED IEE 10000016639 FOR SN 42169182

NEED IEE 10000016639 FOR SN 42169182

11/21/2011

1/16/2012

1/17/2012

1/18/2012

6

123

123

9/28/2011

9/28/2011

NEED IEE 10000013531 ISSUED

NEED IEE 10000013531 ISSUED

02-RC-E/P-2455A-IXMITR

02-RC-E/P-2455B-IXMITR

59101633284

59101633292

14

108359076736202 02-FP-MS-2-IBISSW NEED THIS MARK NUMBER ADDED TO IEER NEL00910 000

1/24/2012

59102229726 02-BY-BC-2-IV-BATTRY NEED IEE 10000016639 FOR SN 42169182 1/18/2012

Level: Nuclear Level: Nuclear –– Station Station ‐‐ Detail Detail Group: PEGroup: PEFrequency: MonthlyFrequency: Monthly Back

USA/STARS Alliance Obsolescence Project (EOS)USA/STARS Alliance Obsolescence Project (EOS)/ j ( )Outsourcing Replacement Evaluations/ j ( )Outsourcing Replacement Evaluations

2011 JUTG Summer Meeting

Howard T. LeCompteHoward T. LeCompteDTE Energy

Chairman, USA/STARS Obsolescence  Project Team

Engineered Obsolescence Solutions

What is EOS?g

• Engineered Obsolescence Solutions (EOS) 

– Created to address common challenges associated to proactive 

obsolescence solution development across the USA/STARS 

(“the Alliance”)

– Leverages the strengths of engineering services (PKMJ) and 

hardware supplier (CWFCN) 

Engineered Obsolescence Solutions

What is EOS?g

• Purpose is to develop and implement solutions created by Obsolescence

– Engineering Solutions are performed under PKMJ’s 

Appendix B program 

– Hardware solutions by CWFC are provided under their 

Appendix B program

Engineered Obsolescence Solutions

2010 Pilot Project Participantsg

• Ameren• Ameren • PG&E• PG&E• Arizona Public Service Co. • Detroit Edison Co. • Energy Northwest

• Arizona Public Service Co. • Detroit Edison Co. • Energy Northwest

• PPL Susquehanna• PSEG• Southern California Edison

• PPL Susquehanna• PSEG• Southern California EdisonEnergy Northwest

• Luminant• Nebraska Public Power District • Omaha Public Power District

Energy Northwest• Luminant• Nebraska Public Power District • Omaha Public Power District

• Southern California Edison • STP Nuclear Operating Co.• Wolf Creek Nuclear Operating 

Co

• Southern California Edison • STP Nuclear Operating Co.• Wolf Creek Nuclear Operating 

Co• Omaha Public Power District • Omaha Public Power District  Co.Co.

Engineered Obsolescence Solutions

2010 Pilot Scopeg

• 8 Items were selected for solution development

– “Equity” for solution development was established across the 

participating stations

– These 8 items yielded 59 site specific equivalency evaluations

– Of the 8 items, 1 was a reverse engineering solution, and will g g

move into the 2011 project for completion

Engineered Obsolescence Solutions

Challenges Resolved g

• Establishing a list of obsolete items that provided “equity” to all 

t ti i l dstations involved

• Establishing access to site data systems using remote access (VPN)

• Assuring all QA requirements were aligned

• Issuing of Purchase Orders to PKMJ

– Challenge for sites to obtain funding needed for participation

• Acquiring site specific application informationq g p pp

Engineered Obsolescence Solutions

Lessons Learnedg

• Selecting list of evaluations to be pursued

• Specifying due dates for site requests

• Monthly Indicators streamlined to show better project summaries 

and less details

• Engineering portion of project started late

– Evaluations started in June due to equity selections 

– Late Purchase Orders resulted in shortened engineering windowg g

Engineered Obsolescence Solutions

Cost Savingsg

• Cost Savings on a per evaluation level (cont):

– 70% Cost savings, in man‐hours, is attained in the base 

evaluation cost after the first evaluation is completed

– Cost savings achieved by leveraging “Economies of Scale” and 

“Engineer Once, Implement Many” concepts

– In the pilot scope of this project, we resolved 2,355 obsolete 

installed locations.

Engineered Obsolescence Solutions

Cost Savingsg

• Additional cost savings achieved of 6 man‐hours per evaluation by 

utilizing CMIS Lite (software tool)

• Savings achieved by:

– Reducing the number of administrative errors found in 

completing an equivalency evaluation

– Strict procedural compliance

– Replicationp

– Provides a communication portal between each participating 

site and off‐site engineering resources to facilitate the reviewsite and off site engineering resources to facilitate the review 

and approval cycle

Engineered Obsolescence Solutions

Cost Savingsg

• Cost Savings Indicator (as of 1/20/2011):

*1,223 of the remaining components are associated to a reverse engineer project to be completed in early 2011.

Engineered Obsolescence Solutions

2011 Current Statusg

• Alliance has Developed a 5 Year Plan Moving Forward with this Project

– 20112011

• Scope of items have been selected, and are being worked

• Process improvements identified in pilot year have been incorporated, p p y p ,

and are yielding positive results

• Process for leveraging OIRD solutions has been developed and 

implemented

Engineered Obsolescence Solutions

2011 Project Participantsg

• Ameren• Ameren • PG&E• PG&E• Arizona Public Service Co. • Detroit Edison Co. • Energy Northwest

• Arizona Public Service Co. • Detroit Edison Co. • Energy Northwest

• PPL Susquehanna• PSEG• Southern California Edison

• PPL Susquehanna• PSEG• Southern California EdisonEnergy Northwest

• Luminant• Nebraska Public Power District* • Omaha Public Power District*

Energy Northwest• Luminant• Nebraska Public Power District* • Omaha Public Power District*

• Southern California Edison • STP Nuclear Operating Co.• Wolf Creek Nuclear Operating 

Co

• Southern California Edison • STP Nuclear Operating Co.• Wolf Creek Nuclear Operating 

Co• Omaha Public Power District* • Omaha Public Power District*  Co.Co.

*Pending Purchase Orders*Pending Purchase Orders

Engineered Obsolescence Solutions

2011 Current Statusg

• 2011 Selection list 

M f t M d l N b D i ti Sit I t dManufacturer Model Number Description Sites Impacted

Weston Aerospace 4303 Indicator, Instrument 4

United Brass Works 126S Valve 7

Leeds Northrup 708211 PH Analyzer 5

Leeds Northrup 7773 Sensor Element 6

Moore LTD 58S Pressure Relay 6y

Siemens Fire Safety DIS5B Smoke Detector 4

Fisher 4160KR PR Controller 0

R t N l 4915401 P S l 4Rosemount Nuclear 4915401 Power Supply 4

Masoneilan 3720721 AOV 2

Masoneilan 3820771 AOV 3

Masoneilan 3820721 AOV 3

Engineered Obsolescence Solutions

2011 and Beyondg

• Alliance has Developed a 5 Year Plan Moving Forward with this Project

– 20112011

• Refine process of item selection – reduce number of series challenges or 

reduce total number of project items if focused on series challenges

• Continue to solve remaining challenges from pilot year (2010)

• Work with a pilot set of sites to develop a process to leverage Alliance 

project into daily process and to develop backlog reduction plans

• Apply lessons learned from pilot year to a more streamlined process

• Continue to obtain VPN connections at each site

• Select a pilot set of sites to train PKMJ engineers to site process

This will reduce time and effort required for site’s involvement in the– This will reduce time and effort required for site’s involvement in the 

long run

Engineered Obsolescence Solutions

Lesson Learnedg

• Start the Replacement Evaluation selection process 2nd Quarter of the 

proceeding year to assure the final list is approved prior to the start of the p g y pp p

project.

• Develop Project Schedule and Milestones to assure the Project stays on track

• Bi‐weekly conference call between the site and EOS teams to assure each 

organization is aligned and up to date on the progress.

• Site managements involvement to help eliminate obstacles associated with 

Project completion.

• VPN access established at site to reduce impact on the engineering staff• VPN access established at site to reduce impact on the engineering staff.

• EOS Team qualified to the sites ESP program for Replacement Evaluations.

Engineered Obsolescence Solutions

Questionsg

Procurement Engineering and Supply Chain Updatepp y p

Marc H. TannenbaumP j t M EPRIProject Manager, EPRI

Joint Utility Task Group MeetingAugust 23, 2011

Topical

• Suspected counterfeit and fraudulent items

• Substandard item reporting

• Acceptance of commercial grade software for use as aAcceptance of commercial grade software for use as a basic component in safety-related applications

• Engineered item procurement and refurbishmentEngineered item procurement and refurbishment templates

• Shelf life guidanceShelf life guidance

• Project Ideas for 2012

2© 2011 Electric Power Research Institute, Inc. All rights reserved.

3© 2011 Electric Power Research Institute, Inc. All rights reserved.

Counterfeit and Fraudulent Items

• Source of Data

– Suspect Counterfeit and Fraudulent Items Database

• scfi.epri.com (Beta)

• Existing Guidance

– 1020955, Counterfeit, Fraudulent, and Substandard Items Computer Based Training Version 1 0 (2010)Computer Based Training Version 1.0 (2010)

– 1021493, Counterfeit and Fraudulent Items: A Self-Assessment Checklist (2010)

– 1019163, Counterfeit, Fraudulent and Substandard Items: Mitigating the Increasing Risk (2009)

4© 2011 Electric Power Research Institute, Inc. All rights reserved.

– Standard contract requirements clause

Are we where we need to be?

• CFSIs are still an evolving concern and we will continue to check and adjust

5© 2011 Electric Power Research Institute, Inc. All rights reserved.

• Public meeting with NRC on June 30, 2011

Gaps identified by 4 NRC working groups

• (1) Current reporting requirements only require the reporting of defects and failures to comply that could leadreporting of defects and failures to comply that could lead to a substantial safety hazard and significant events driven by equipment failures

– Basic components that are determined to be CFSls but do not constitute a substantial safety hazard or cause reportable event would not be required to be reportedepo tab e e e t ou d ot be equ ed to be epo ted

• (2) Lack of clarity whether CFSI constitutes a deviation, failure to comply, or condition adverse to quality as defined in existing rules and guidance

6© 2011 Electric Power Research Institute, Inc. All rights reserved.

Some gaps identified by NRC

• (3) Current interpretation of Part 21 only applies to basic components (items that have passed receipt inspection orcomponents (items that have passed receipt inspection or completed the dedication processes)

– CFSI identified during receipt inspection and dedication gmay not be evaluated for reportability under Part 21

(4) 10 CFR 50 A di B C it i XV XVI d t• (4) 10 CFR 50, Appendix B, Criteria XV, XVI, and current guidance do not explicitly require licenses and vendors to enter CFSI occurrences identified during receipt inspection and dedication processes in their nonconformance or corrective action programs.

7© 2011 Electric Power Research Institute, Inc. All rights reserved.

Some gaps identified by NRC

• (7) There is no requirement for a licensee facility or vendor to quarantine suspected CFSI materials for furthervendor to quarantine suspected CFSI materials for further analysis, regulatory/law enforcement purposes. Guidance on how suppliers of Critical Digital Assets implement the

li t l t i d i R l t G id 5 71supplier controls contained in Regulatory Guide 5.71 (Cyber Security)

• (9) The NRC does not currently perform procurement, Commercial-Grade Dedication, or Part 21 inspections at operating power plants to ensure licensees areoperating power plants to ensure licensees are adequately screening for CFSI during receipt inspection and commercial grade dedication activities.

8© 2011 Electric Power Research Institute, Inc. All rights reserved.

Some gaps identified by NRC

• (10) CFSI is not specifically included in NRC inspection guidance [Response Working Group] i) NRC inspectorsguidance. [Response Working Group] i) NRC inspectors are not directed to look for the possibility of CFSI, or to look at a vendor/licensee's program for detecting and

ti CFSIpreventing CFSI

• (11) Guidance on how suppliers of Critical Digital Assets• (11) Guidance on how suppliers of Critical Digital Assets implement the supplier controls contained in Regulatory Guide 5.71

• (12) NRC inspection authority for non-safety related critical digital assets (Regulatory Guide 5.71)

9© 2011 Electric Power Research Institute, Inc. All rights reserved.

Some gaps identified by NRC

• (14) There currently is no regulatory guidance or requirements for the authentication and testing ofrequirements for the authentication and testing of components necessary to identify a counterfeit or fraudulently identified item

• (15) There is no NRC guidance that specifically addresses the need for licensees or suppliers to implement programsthe need for licensees or suppliers to implement programs to identify fraudulent documentation

• (16) Current NRC requirements do not require licensees to pass down contractual requirements for supplier CFSI programs to identify and eliminate fraudulent goods

10© 2011 Electric Power Research Institute, Inc. All rights reserved.

programs to identify and eliminate fraudulent goods obtained from subsuppliers.

Some gaps identified by NRC

• (19) 10 CFR 50 Appendix S, Criterion XVI does not require cause determination for conditions adverse torequire cause determination for conditions adverse to quality.

• (20) No regulatory guidance for implementing measures ( ) g y g gto prevent CFSI associated with RTNSS (Regulatory Treatment of Non-Safety Systems).

• (21) There is a lack of regulatory requirements associated• (21) There is a lack of regulatory requirements associated with the procurement of non-safety related critical infrastructure equipment.

11© 2011 Electric Power Research Institute, Inc. All rights reserved.

Substandard Item Reporting

• Detected through robust receiving practices

• Initiated from counterfeiting and fraud concerns

– Alternative to mandatory reporting of all substandard y p gitem incidents as operating experience

– Voluntary, but strongly recommendedy g y

– 58% Units / 31% Licensees currently represented

O t it t id tif t d d d• Opportunity to identify trends and respond

– Supplier communication

12© 2011 Electric Power Research Institute, Inc. All rights reserved.

– Enhanced specification, testing, etc.

Industry Participation

Substandard Item Reporting Participation

60.00%

70.00%

40.00%

50.00%

rcen

t

% Units

% Utilities

20.00%

30.00%Pe

% Utilities

0.00%

10.00%

3Q10 4Q10 1Q2011

13© 2011 Electric Power Research Institute, Inc. All rights reserved.

Reporting Period

Data Contributors

Quantity of Incidents

DominionDukeE lExelonFirstEnergyFPL/NextEraFPL/NextEraProgress EnergySCANASouthern NuclearTVAWCNOC

14© 2011 Electric Power Research Institute, Inc. All rights reserved.

WCNOC

Data

• Submittal via provided spreadsheet vastly improved quality of data and reduced meeting timequality of data and reduced meeting time

• Use of the EPRI format/spreadsheet will be continued

• New focus on increasing participation

– Entergy attended part of the meeting and committed to provide data moving forward

15© 2011 Electric Power Research Institute, Inc. All rights reserved.

Substandard Items by Type

Item Type ReportableIncidents

Relay 55

Valve 43

Switch 33

Breaker 31

Elbow 28

Regulator 18g

Transmitter 11

Flange 9

Controller 8Controller 8

Contact 8

Pipe 6

Screw 6

16© 2011 Electric Power Research Institute, Inc. All rights reserved.

Screw 6

Substandard Items by Type with Qualifier

Item Qualifier ReportableIncidents

Breaker Circuit 25

Elbow Pipe 25

Regulator Pressure 17

Switch Pressure 15

Valve Relief 12

Valve Solenoid 11

Relay Aux 9

Relay Time Delay 9

Transmitter Pressure 9

Relay Overload 8

Flange Pipe 7

Valve Check 7

17© 2011 Electric Power Research Institute, Inc. All rights reserved.

Valve Check 7

Contact Aux 6

Engineered Item Procurement/Refurbishment Templatesp

• Identify key phases of procurement and refurbishment projectsprojects

– (e.g. design and specification, supplier qualification, supplier planning and specification review, supplier goversight, manufacturing, receiving, etc.)

Ch kli t f h h• Checklists for each phase

– Potential problems & operating experience

– Good practices– Good practices

– Precautions

– Oversight activities

18© 2011 Electric Power Research Institute, Inc. All rights reserved.

g

Critical Pump Refurbishment and Procurement: Key Project Phases and Considerations Checklist 1022960j

1. Preliminary identification of capable suppliers

f2. Review of initiating event

3. Develop Specification

4 Supplier Selection4. Supplier Selection

5. Initial disassembly/inspection by supplier

6. Review of supplier inspection report and repair plan6. Review of supplier inspection report and repair plan

7. Manufacturing, repair and refurbishment activities

8. Shop testing

9. Receiving on site

10. Installation

19© 2011 Electric Power Research Institute, Inc. All rights reserved.

11.Post installation functional testing

20© 2011 Electric Power Research Institute, Inc. All rights reserved.© 2011 Electric Power Research Institute, Inc. All rights reserved.

Shelf Life Guidance Revision

• Revisit the guidance in EPRI NP-6408 (1992) and update as necessary(1992) and update as necessary

– Original intent was to add new materials and applications

– If appropriate, update activation energy values

– More discussion on shelf life extension

– More discussion on how to addressMore discussion on how to address “installed” limited life items

– More discussion on when to start the l k

21© 2011 Electric Power Research Institute, Inc. All rights reserved.

clock

Upcoming JUTG Meeting

February 21-23, 2012•OMNI Riverwalk - San Antonio, Texas

22© 2011 Electric Power Research Institute, Inc. All rights reserved.

Q ti ?Questions?

23© 2011 Electric Power Research Institute, Inc. All rights reserved.

EPRI JUTGEPRI JUTG

August 24, 2011

Part 21 Rulemaking Overview and Update

Victor HallOffice of New Reactors

Right Time for Change

• NRC believes changes to Part 21 and associated

Right Time for Change

• NRC believes changes to Part 21 and associated regulations are desirable– Many issues despite generic communications and outreach efforts

– Recent audits by Office of the Inspector General reiterated issues

• New plant construction is the appropriate time to• New plant construction is the appropriate time to consolidate guidance and clarify the NRC’s expectations

• Opportunity to clarify expectations for non-reactor facilities

“Even as the final rule was published on June 6 1977 the CommissionEven as the final rule was published on June 6, 1977, the Commission recognized that future experience and further information might warrant clarifying or other changes to the rule.” (NUREG-0302) 2

Right Time for Change (cont’d)

202020

10

15

1111

1515

1010

1414 1313

99

5

1010

33

8899

330

2007 2008 2009 2010 2011

Vendor Inspections With Part 21 Related Findings

(to date)

3

p g

Right Time for Change (cont’d)

95 - "Other" Quality Assurance

49 Part 21 Violations49 - Part 21 Violations

14 - Identification of Deviations

36 - Commercial-Grade Dedication

99 Total Part 21-related findings

Vendor Inspection Findings (2007 to 2011)

4

e do spect o d gs ( 00 to 0 )

Build on ExperienceBuild on Experience

EVALUATING AND REPORTINGRequires

RegulationChange

New Requirement

AdditionalGuidance

EndorseIndustry

Guidance1. Lack of Regulatory Guidance ✔

2. Quality Requirements in Procurement Documents ✔ ✔ ✔

3. Procurement language in definition of Basic Component for non-reactor facilities ✔ ✔

4. Clarify point of discovery ✔ ✔

5. Evaluating and Reporting Responsibility ✔ ✔5. Evaluating and Reporting Responsibility ✔ ✔

6. Deferral of Evaluation - 21.21(a) ✔ ✔ ✔

7. Use of Licensee Event Reporting (i.e. 50.72/73) ✔ ✔

8. Acceptable forms of written notification per 21.21(2) for non-reactor facilities ✔ ✔

9. 50.55e Redundancy ✔

10. Evaluation of Counterfeit Fraudulent and Suspect Item (CFSI) under Part 21 ✔

11. Clarify Deviation and delivery ✔ ✔

12. Contemporary posting requirements ✔

13. Training ✔

COMMERCIAL-GRADE DEDICATION

RequiresRegulation

ChangeNew

RequirementAdditionalGuidance

EndorseIndustry

GuidanceA. Lack of Regulatory Guidance ✔ ✔

B. Proper Place for Dedication ✔

C. Definition of Dedication ✔

D D fi iti f C i l G d ItD. Definition of Commercial-Grade Item ✔

E. Clarify that Dedication is a Safety-Related activity ✔

F. Dedication plans and the importance or safety function ✔ ✔ ✔ ✔

G. Sampling Requirements ✔ ✔

H. Use of Commercial Calibration (and Testing) Labs ✔ ✔

I. Software Dedication ✔ ✔

ADMINISTRATIVE CHANGESRequires

Regulation New AdditionalEndorseIndustry

5

ADMINISTRATIVE CHANGES Change Requirement Guidance Guidancei. Add “Part 52” to definition of Dedication ✔

ii. Definitions for Part 76 facilities (i.e. Basic Component, Substantial Safety Hazard) ✔

iii. Definition of Critical Characteristics for non-reactor facilities ✔

Build on Experience (cont’d)Build on Experience (cont d)

• Clarify the Regulations• Clarify the Regulations– Simplify when possible

– Revisit definitions in Part 21

– Must comply with Section 206 “Noncompliance”

of the Energy Reorganization Act of 1974

• Provide Updated Regulatory Guidance– Benefit from over 33 years of experience

– Opportunity to consolidate existing guidance

• Use stakeholder input to improve the Part 21 processUse stakeholder input to improve the Part 21 process

6

MilestonesMilestones

Offi f N R t b li i

212121• Office of New Reactors began preliminary

rulemaking activities in December 20091

• NRC agency-wide Part 21 working group formed in January 2011

1

y– Discussions on holistic approach to clarify Part 21

P li i di i t bli ti• Preliminary discussions at public meetings– 2011 RIC

– NUPIC Vendor Conference

– EPRI JUTG7

Milestones (cont’d)Milestones (cont d)212121

• August 1, 2011: Public Meeting for early stakeholder feedback

1• September 2011: Commission (SECY)

1

paper – Communicate the staff’s plan to develop the

regulatory basis for rulemakingregulatory basis for rulemaking

• Rulemaking kickoff meeting in Fiscal Year 2012• Rulemaking kickoff meeting in Fiscal Year 20128

Milestones (cont’d)Milestones (cont d)YOU YOU ARE ARE

HEREHERE

YOU YOU ARE ARE

HEREHERE

Final RuleProposed Rule

Regulatory (Technical)Basis

Identify need for rulemaking

HEREHEREHEREHERE

Basisrulemaking

NRC staff issueduser need memo i 2009

• Foundation of effective rulemaking

• Draft text & guidance

•Final text & guidance

I l iin 2009 rulemaking

• Public meetings • 75 day public comment period

•Implementation period (if needed)

•Public meetings on i l t ti• Draft rule text

comment period (typically)

implementation

9Opportunities for public participation

How to Get InvolvedHow to Get Involved

Victor HallVictor HallOffice of New Reactors

Victor Hall@nrc [email protected]

(301)415-2915

10

Vendor Quality Program for Critical y gEquipment & Major Purchases

Business Need

This program is in response to the need for improved vendor quality with the repair and fabrication of critical equipment quality with the repair and fabrication of critical equipment and major purchases of plant equipment. The focus on equipment reliability and the economic risk of downtime equipment reliability and the economic risk of downtime associated with vendor work on critical equipment and major purchases have increased significantly due to:• Shortened outages and longer operating cycles (days vs. months)

• A greater business need for maximizing plant productiong g p p(goal of decile vs. quartile)

• Implementation of Major Projects and New Plant Development

2

Business NeedThis program is intended to address high risk critical equipment and major purchases. This program addresses:

• Off-site vendor critical equipment repair• Off-site vendor critical equipment fabrication and • Off-site vendor critical equipment fabrication, and • Major purchases (i.e. considered to be a cost greater than

$100K (cost per item) for new repair or rework of $100K (cost per item) for new, repair, or rework of spare/replacement equipment, Major Project equipment and key parts).y p )

• Repair/Fabrication of critical equipment and major purchases can have a significant impact to the site outage/operating schedule if nonconforming or unacceptable conditions are identified during the fabrication, receiving, pre-installation review or installation process.installation process.

3

Business Need

• Appendix B: QA Programs robust & abundant

T h i l ti dil il bl• Fewer vendors with App. B QA

Programs

That was then: 25/30 yrs. ago This is now:

• Technical expertise readily available• Growing market in Nuclear• Utility and AE presence at vendor

Programs• Eroding knowledge transfer (Retirements)

• Nuclear is a small niche marketUtility presence at vendor is limitedcommonplace

• Lead time flexibility• Detailed engineering reviews

• Utility presence at vendor is limited• Shorter outages, longer operating cycles• Less staff (on both sides) I’m sure you all

h h d “d ith l ” • Specifications reflected current technology• High volume of purchases• Equipment/Operating reliability standards

have heard “do more with less”. • Specifications out of date• Lower volume of purchases

Equipment/Operating reliability standards lower • Higher equipment reliability standards

4

Program Intent

The basic intent of this Program is to proactively schedule and determine quality assurance measures to be and determine quality assurance measures to be implemented prior to sending high risk critical equipment out for repair or acquiring new high risk critical equipment. This for repair or acquiring new high risk critical equipment. This helps ensure critical equipment and major purchases are repaired/purchased and received in a timely manner to support improved Equipment Reliability.

5

Program IntentEngagement and ownership of vendor quality by the plant Engineering and Maintenance organizations, Major Projects and New Plant Development organizations as well as Supply Chain is the most Development organizations, as well as Supply Chain is the most important factor for this program to be successful. The different elements of the program have “natural” lead organizations, but it is expected that all impacted organizations collaborate to lend the most effective support to plant operations.• Engineering is responsible to designate what equipment is critical, preparation of g g p g q p , p pCommon/Update Specifications, participate in completion of Major Purchases & Vendor Quality Checklists, and vendor shop surveillances as needed.• Maintenance is responsible to participate in completion of Quality Checklists, perform vendor shop surveillances as needed, and perform pre-/post-implementation inspection and testing of items. • Supply Chain is responsible to coordinate selection of preferred providers, assist in identification of high risk critical equipment or major purchases for application to this program identification of high risk critical equipment or major purchases for application to this program, and facilitate completion of Major Purchases & Vendor Quality Checklists.

6

Guiding Principles1. Clearly and proactively communicate what is expected of

internal organizations and the vendor (i e providing clear internal organizations and the vendor (i.e. providing clear and accurate specifications or requirements).

2 Ensure the vendor has internalized the expectations (i e 2. Ensure the vendor has internalized the expectations (i.e. the people actually performing the work understand the expectations as opposed to the sales rep.) i.e. their Engineering, QA and Shop personnel

3. Provide feedback and hold the vendor accountable if performance does not meet expectations i H d performance does not meet expectations. i.e. How can a vendor improve his quality, if no one tells him it is not up to your standards?

7

Program Participants• Component Engineers (these folks make good subject

matter expects)p )

• System Engineers• Responsible Engineers (Site Design Engineering, p g ( g g g,

Major Projects, or New Plant Development)

• Procurement Engineers• Supply Chain personnel • Project Managers• Maintenance Supervisors (including Maintenance

Subject Matter Expects, really these folks work with this equipment everyday, therefore input should be very much valued)

8

Measures Applied to a Repair/Purchase1. Proactive scheduling of equipment repairs and purchases2. Clearly identify and communicate technical and quality

requirements• Repair/purchase specs or other requirements• Pre-repair/purchase submittals (these can be repair plans,

repair/fabrication related procedures, drawings, FME procedures )

• Vendor surveillance (get intrusive your paying the bill)• Vendor surveillance (get intrusive, your paying the bill)

• Vendor documentation (ask for it in writing and make sure you get all of it, you may not get a second chance, ensure the vendor understands that any deviation f th PO i t d t b id tifi d)from the PO requirements need to be identified)

• Acceptance testing (will it be during fabrication, per/post installation?)

• Receiving inspection (this inspection should be timely not 2 or 3 months after • Receiving inspection (this inspection should be timely, not 2 or 3 months after you received the material at your site – so that any non-compliances can be dealt with in a timely manner)

9

Measures Applied to a Repair/Purchase (cont.)

3. Update CAT ID and prepare requisition4. Perform vendor surveillance (try to use a subject matter expert, identify any

NDE/testing witness points, perform cleanliness and FME inspections (before the point of no-return where onsite inspections cannot see the FME), are there final performance tests to be witnessed at the vendors’ facility?)

5 R i i t d f i t i ti 5. Receive equipment and perform receipt inspection (consider using enhanced receiving inspection requirements by specifying critical acceptance criteria that can be examined at receipt )

6 P f P /P t i t ll ti i ti /t ti 6. Perform Pre-/Post installation inspection/testing (Maintenance inspection/testing of equipment (beyond what is required during the receipt inspection) should be performed promptly after receipt – where needed. This provides for early identification of potential quality concerns that may not be identified during the receiving identification of potential quality concerns that may not be identified during the receiving process)

10

Checklists• NGGM-PM-0020 is the governing program manual which

contains the following elements:• Major Purchases and Vendor Quality Checklist (this is the heart of

this program. Supply Chain Procurement Specialists will facilitate the completion of the Checklist with Engineering providing technical and quality guidance along with Maintenance providing their perspective. This is best accomplished in a face-to-face working meeting to complete the Checklist. The Checklist helps ensure all perspectives have been considered in determining what supplemental vendor quality measures are warranted in a given case This is really a very useful tool for both a seasoned warranted in a given case. This is really a very useful tool for both a seasoned professional, or a young person in their nuclear career, since it provides excellent questions to help facilitate a quality product.

• Risk Assessment Guide (this provides examples of equipment and scenarios Risk Assessment Guide (this provides examples of equipment and scenarios that should be considered for evaluation under this program)

11

• Is the program working? - - Good Question -p g g

Some success stories:• Some success stories: Due to intrusive vendor surveillance for a Dry Fuel Storage Project, one of our auditors

identified fraudulent material being used during the fabrication of the dry storage canisters. As a result the supplier wrote a Part 21 to the industry and further testing / evaluation was As a result the supplier wrote a Part 21 to the industry and further testing / evaluation was performed on other material that was supplied.

As part of a vendor / PGN Improvement plan an FME procedure was implemented by a As part of a vendor / PGN Improvement plan, an FME procedure was implemented by a vendor in all their business units.

We have seen a decreasing trend in Vendor Quality NCRs and Vendor Quality Receiving We have seen a decreasing trend in Vendor Quality NCRs and Vendor Quality Receiving Deficiency Rates. These trends have been monitored since 2005.

12

QUESTIONS ?QUESTIONS ?

13

EPRI JUTG Procurement ForumOff Si R i f L C i i l AOff-Site Repair of Large Critical Assets

August 24, 2011g ,

William Ware

1

Program Scope and Objectives• Off-Site Repair of Critical Components

Subset of Vendor Oversight Program activities– Subset of Vendor Oversight Program activities

• Vendor Oversight Program Objectives:• Vendor Oversight Program Objectives:To improve the quality of engineeredcomponents through p g

– a more rigorous approach to the performance of internal procurement activities, and

– a more structured and involved approach in the oversight of the vendor’s activities

–2

Definitions• Engineered Component

An item that has been specifically designed and– An item that has been specifically designed and manufactured to meet SNC technical requirements.

• Large MotorLarge Motor– Horsepower rating of 250 horsepower and greater

• Large PumpLarge Pump– Power plant pumps that are driven by large motors.

• Performance Part– Directly affects component performance

– Testing is required to determine part acceptability.

–3

Process Outline• Determine applicability of enhanced process

• Pre-plan and identify requirements

• Develop procurement requirements

• Prepare specifications, surveillance plans, etc.

• Issue PO and ship componentIssue PO and ship component

• Receive and approve repair plan from supplier

E d i h i i i• Execute vendor oversight activities

• Receive repaired component

–4

Process Details• New requests for purchase or repair are

screened for Engineered Component orscreened for Engineered Component or Performance Part applicability

• If applicable user prepares Procurement• If applicable, user prepares Procurement Planning Questionnaire

Procurement Milestones & Requirements– Procurement Milestones & Requirements

– Procurement Planning Team Member Names

25 Q ti P l D t & O i ht– 25 Questions – People, Documents, & Oversight

– Completed, approved, and attached to requisition

–5

Process Details (con’t)• Procurement Risk Assessment

• Technical Contract Management

• Develop Component Repair Specification

• Conduct Vendor Surveillance

• Maintain Vendor Oversight NotebookMaintain Vendor Oversight Notebook

• Receive Repaired Component

–6

Repair Specifications

• Engineering procedure for development, review, and approval of equipment repair specificationsand approval of equipment repair specifications

• Equipment Repair Specifications should include:Identification of applicable equipment– Identification of applicable equipment

– Incoming inspection requirements

– Disassembly and evaluation requirementsDisassembly and evaluation requirements

– Visual and dimensional inspection requirements

– As-Found and as-left documentation requirements

– Repair requirements with tolerances and limitations

– Witness and hold points

–7

Repair Specifications (con’t)

• Equipment Repair Specifications (con’t):S ifi d i t– Specific code requirements

– Special handling requirements

– Reconditioning requirements– Reconditioning requirements

– Reassembly requirements

– Parts requirementsq

– Painting and coating requirements

– Service performed nameplate

– Deliverables, documentation, tests, etc.

– Pre and post maintenance testing requirements

–8

Questions and Comments

–9

JUTG Breakout Sessions

August 24, 2011

Topics

• Ideas for improving/clarifying 10CFR21 guidance and revising EPRI NP-5652

• Application of dedication methodology to softwareApplication of dedication methodology to software

• Commercial grade item dedication challenges

2© 2011 Electric Power Research Institute, Inc. All rights reserved.

Breakout Agenda

1. Brief introductions (Name and company)

2. Elect a spokesperson

3 Identify and record problem statements3. Identify and record problem statements

4. Share experiences, discuss possible solutions

5. Identify the best way to communicate solutions to other JUTG members

Presentation

EPRI Project

3© 2011 Electric Power Research Institute, Inc. All rights reserved.

Other

Technical Advisory Group Volunteers

4© 2011 Electric Power Research Institute, Inc. All rights reserved.

–– A VIRTUAL TOURA VIRTUAL TOUR ––In OBSOLESCENCE & REVERSE ENGINEERING In OBSOLESCENCE & REVERSE ENGINEERING

TechniquesTechniquesEPRI JUTG EPRI JUTG –– Minneapolis, MN Minneapolis, MN

DATE: August 24th 2011

BY: SAM A. YOUSIFBY: SAM A. YOUSIF(24/7) Call 914.456.0227

e-mail: [email protected]: www.dsusainc.com

www.dsusainc.com (24/7) Phone 914.456.0227 1

ULR: www.dsusainc.com

L t U St t ithLet Us Start with:No calling on earth is insignificant if itNo calling on earth is insignificant if it

is accomplished with pride and artistry. Do whatever your heart leads you to do but do it so well that those whodo, but do it so well that those who come to see you do it … will bring others to watch you do it again and

again & again. g gwww.dsusainc.com (24/7) Phone 914.456.0227 2

ANYONE KNOWS WHO ANYONE KNOWS WHO THESE PEOPLE ARE?THESE PEOPLE ARE?

www.dsusainc.com (24/7) Phone 914.456.0227 3

Th i i l f t lThey Are: A Purchasing Agent, a

The original manufacturer no longer exists,

Obsolete manufacturing processes or technology,

Procurement Engineer And / Or Maintenance

The original manufacturer of a product no longer produces a product,

Manufacturers unwilling to produce Planner, …

LOOKING FOR AN

g plimited or small quantities,

Unusual component / material requirements, including tight delivery schedules,

OBSOLETECOMPONENT!

,

There is inadequate documentation of the original design,

The original design documentation has been lost or never existed,been lost or never existed,

www.dsusainc.com (24/7) Phone 914.456.0227 4

WHY One Should Consider WHY One Should Consider Reverse Engineering as Reverse Engineering as S l i f Ob l N lS l i f Ob l N la Solution for Obsolete Nuclear a Solution for Obsolete Nuclear

SafetySafety--Related ItemsRelated Items

R i i Th t AGING PLANTS HAVE ONE1) Recognizing That our AGING PLANTS HAVE ONE COMMON ASPECT … THAT IS … OBSOLESCENCE

2) Plant’s Supply ChainSupply Chain Philosophy Changed FROM:2) Plant s Supply ChainSupply Chain Philosophy Changed FROM:Just-in-Case … to … Just-in-Time

3) Approach is supported by EPRI NP-107372 & INPO NX 1037

RECOMMENDATION TO SUPPLIERSRECOMMENDATION TO SUPPLIERSIn Order to Ensure Successes PLEASE GET YOUR NQAIn Order to Ensure Successes … PLEASE GET YOUR NQA, ENGINEERING, PURCHASING, & SUPPLIERS, INVOLVED

EARLY IF NOT DURING QUOTATION STAGE!IF NOT DURING QUOTATION STAGE!

www.dsusainc.com (24/7) Phone 914.456.0227 5

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

FROM THIS?Figure 1: 32 YEARS OLD OBS Expansion

Differential Detector – WHAT WE STARTED with

AND THIS: Figure 2: Back View Steel Base Geometry

www.dsusainc.com (24/7) Phone 914.456.0227 6

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

ANDTHIS:Figure 3: Top View - Steel Base Geometry

AND THIS: Figure 4: U Core Configuration

www.dsusainc.com (24/7) Phone 914.456.0227 7

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

FROMTHIS: FROMTHIS:Figure 5: U Core Coil ANALYSIS

AND THIS: Figure 6: U Core Coil ANALYSIS

www.dsusainc.com (24/7) Phone 914.456.0227 8

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

www.dsusainc.com (24/7) Phone 914.456.0227 9

–– VIRTUAL TOURVIRTUAL TOUR ––VIRTUAL TOURVIRTUAL TOURREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

Figure 7: MOLD - Bobbin For U-Core Figure 8: U Core Coil Configuration

www.dsusainc.com (24/7) Phone 914.456.0227 10

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

Figure 9: U Core Configuration & Layout Figure 10: U Core / Coil BobbinFigure 9: U Core Configuration & Layout Figure 10: U Core / Coil Bobbin Configuration

www.dsusainc.com (24/7) Phone 914.456.0227 11

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

Figure 11: RE Unit Wiring to Coils & External Cable Lay Figure 12: RE Unit POTTING PROCESSFigure 11: RE Unit Wiring to Coils & External Cable Lay Out

Figure 12: RE Unit POTTING PROCESS

www.dsusainc.com (24/7) Phone 914.456.0227 12

–– VIRTUAL TOURVIRTUAL TOUR ––VIRTUAL TOURVIRTUAL TOURREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYFigure 13: WHAT WE STARTED WITH FAILED UNIT Figure 14: REVERSE ENGINEERED TESTED UNITSFigure 13: WHAT WE STARTED WITH – FAILED UNIT Figure 14: REVERSE ENGINEERED TESTED UNITS -

FINAL PRODUCTS

www.dsusainc.com (24/7) Phone 914.456.0227 13

Dollar$ and $en$e REVERSE ENGINEERING SUCCESS STORY REVERSE ENGINEERING SUCCESS STORY

TANGIBLE RESULTSTANGIBLE RESULTS

OEM Special Run No Assurance of No

Changes From originally

Reverse Engineered By DS USA, Inc

Like-for- LikeChanges From originally Supplied

12 Month 12 Month Lead Time Minimum Order 12 Units

Like-for- Like Assurance Provided

4 Month 4 Month Lead Time One Prototype & No Minimum Order 12 Units

Unit Cost For Min. Order = $ 25,000.00T t l C t f Mi O d

One Prototype & No Minimum Order

Unit Cost = $ 11,000.00 Total $aving$ = 56 % Total Cost for Min. Order

= $ 300,000.00 Total $aving$ = 56 %

www.dsusainc.com (24/7) Phone 914.456.0227 14

EFFECTIVNESS OF DS USA, Inc Approach To EFFECTIVNESS OF DS USA, Inc Approach To , pp, ppREVERSE ENGINEERING Of Obsolete Components In REVERSE ENGINEERING Of Obsolete Components In

Nuclear Power PlantsNuclear Power Plants OUR PROGRAMOUR PROGRAM MATURED OVER THE LAST 9 YEARS TO OUR PROGRAMOUR PROGRAM MATURED OVER THE LAST 9 YEARS TO

FULL INTEGRATION Over 54 DevicesOver 54 Devices, all Installed & Functional Without any

Problems, OFFERED To PLANTS OFFERED To PLANTS THAT MOVED FROM:

“Just-in-Case Policy” To “Just-in-Time Policy” OUR Customers Reported Back SHORTER Lead Time & OUR Customers Reported Back SHORTER Lead Time & pp

40-60% Savings Over the Cost of New EquipmentWHAT WE DO NOT TELL YOU:

REGARDLESS OF THE ITEM’S CLASSIFICATION ALL WORKIS PERFORMED UNDER OUR FULLY IMPLEMENTED 10 CFR 50 App B NQA PROGRAM … TREATED AS SAFETY RELATED.

www.dsusainc.com (24/7) Phone 914.456.0227 15

DS USA, Inc Basis For Its Reverse DS USA, Inc Basis For Its Reverse ,,Engineering ApproachEngineering Approach

EPRI NP 107372 J l 1998 id EPRI NP 107372, July 1998 provides sufficient guides on Approach, Criteria, and Benefits of Reverse Engineering whenBenefits of Reverse Engineering when addressing OBS in Nuclear Safety and non-Safety applications, Sam A Yousif Sam A Yousif ––CoauthorCoauthorCoauthor, Coauthor,

INPO Procedure NX1037, Rev 1, November 2003 Recognizes Reverse Engineering as an2003 Recognizes Reverse Engineering as an OBS Solutions (This was based on a NUOG initiative), Sam A Yousif Sam A Yousif –– Technical Review. Technical Review.

www.dsusainc.com (24/7) Phone 914.456.0227 16

The Benefits To YOUR PLANT ByThe Benefits To YOUR PLANT ByThe Benefits To YOUR PLANT ByThe Benefits To YOUR PLANT ByUsing Our Reverse Engineering ApproachUsing Our Reverse Engineering Approach

C l t l D li t F Fit F ti Completely Duplicates Form, Fit, Function, Materials, and Interface/Performance of Original Part, Component, or Assembly,Original Part, Component, or Assembly,

Allows and provides a: “Like-For-Like / Equivalent Replacement unit” ,

No Prohibitive Modification Cost to your Plant,O l “SIMPLE” E i l P NP 5652 Only a “SIMPLE” Equivalency Per NP-5652 Is Required,

www.dsusainc.com (24/7) Phone 914.456.0227 17

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

HOW Do YOU GET

FROM THIS?Figure 1: 28 Years OLD OBS HUMISTAT

AND THIS: Figure 2: HUMISTATA Humidity Sensor Installation

Installed Humistat Humistat Sensor Installation

www.dsusainc.com (24/7) Phone 914.456.0227 18

Inside a Huffman BoxHumistat Sensor Installation

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

HOW Do YOU GET

TO THIS?Figure 3: Reverse Engineered Class 1E Qualified Like-

For-Like Replacement

AND THIS:Figure 4: RE Unit's Sensor INSIDE Humidity ChamberDuring ATP BEFOR & AFTER CLASS 1E Qualification

www.dsusainc.com (24/7) Phone 914.456.0227 19

–– VIRTUAL TOURVIRTUAL TOUR ––REVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORYREVERSE ENGINEERING SUCCESS STORY

HOW Do YOU GET

AND THIS TO THIS?Figure 5: Reverse Engineered Class 1E Qualified Like-

For-Like HUMISTAT PCB

AND THIS: Figure 6: Reverse Engineered Class 1E Qualified Like-

For-Like HUMISTAT

www.dsusainc.com (24/7) Phone 914.456.0227 20

DS USA, Inc REVERSE ENGINEEREDDS USA, Inc REVERSE ENGINEEREDQualified Class 1E HumistatQualified Class 1E HumistatQualified Class 1E HumistatQualified Class 1E HumistatSPECIFICATION SHEET

SPECIFICATION & FEATURES: DS USA, Inc Acceptance Test Procedure SPECIFICATION & FEATURES: Model No: DS6398 Power: 115 VAC, 10% Frequency: 50 / 60 Hz Dimensions: 4.1 x 4.1 x 4.1 in

, pDevelopment: ATP 2005-10

Class 1E NUCLEAR QUALIFICATION Seismic Qualification – IEEE-344 & IEEE-

3231) Qualification Procedure No. ER2005-01, Rev. B2) DS USA, Inc Report No. QR2005-01, Rev. B

Connections: Lug less Wire Terminal Block

Circuit Operating Temperature:(0 0 C to 70 C)

Circuit Storage Temperature:

) S US , c epo t o Q 005 0 , e EMI / RFI Qualification – EPRI TR-102323,

Rev. 21) Qualification Procedure No. ER2005-02, Rev. A2) DS USA, Inc Report No. QR2005-02, Rev. ADS USA, Inc Acceptance Test Procedure

Development: ATP 2005-10 (- 40 0 C to 85 C) Relay Type: Dry Contacts Rely Output: NO & NC, 8 A @ 115 VAC, 5 A @ 24 VDC Signal Output: 0 to 1 VDC, Proportional

Development: ATP 2005 10

Signal Output: 0 to 1 VDC, Proportional to Hygrosensor Dial Reading

Alarm Indication: Red LED indicates sensor reading above set point

Set Point Calibration:Hydrodynamics' Set Points

www.dsusainc.com (24/7) Phone 914.456.0227 21

y y

Class 1E Nuclear QualificationsClass 1E Nuclear Qualifications Overview – As ApplicableAs Applicable

Dedication of Commercial Grade ItemsDedication of Commercial Grade Items 100 %100 % Dedication of Commercial Grade Items Dedication of Commercial Grade Items –– 100 %100 %Governed By: 10 CFR PART 21, EPRI TR-106439, EPRI NP-5652, EPRI NP-6406, NRC Generic Letter 89-2 91 05 DS USA Inc KF13172, 91-05, DS USA, Inc KF1317

Environmental Qualification Environmental Qualification –– Prototype OnlyPrototype OnlyGoverned By: IEEE-323 & 10 CFR 50.49

EMI/RFI (EMC) Qualification EMI/RFI (EMC) Qualification –– Prototype OnlyPrototype OnlyGoverned By: MIL-STD-461D (Test Methods) & US NRC Reg. Guide 1.180Reg. Guide 1.180/EPRI-TR102323 (Acceptance M th d )Methods)

Seismic Qualification Seismic Qualification –– Prototype OnlyPrototype OnlyGoverned By: IEEE-344 & IEEE-323 (10% Margin)

www.dsusainc.com (24/7) Phone 914.456.0227 22

Governed By: IEEE 344 & IEEE 323 (10% Margin)

Over 54 DevicesOver 54 Devices, all Installed & , all Installed & F i l Wi h A P blF i l Wi h A P blFunctional Without Any Problem Functional Without Any Problem

DS USA Inc has successfully Reverse Engineered Fabricated andDS USA, Inc has successfully Reverse Engineered, Fabricated and Tested / Qualified a wide variety of components, parts, and assemblies, SOME ARE:

1)1) Printed Circuit BoardsPrinted Circuit Boards1)1) Printed Circuit Boards, Printed Circuit Boards, 2)2) AC and DC Motors, AC and DC Motors, 3)3) Power Supplies, Power Supplies,

R t t & T ittR t t & T itt4)4) Rotameter, & Transmitters,Rotameter, & Transmitters,5)5) ASME III, Class 3, Heat Exchanger ASME III, Class 3, Heat Exchanger 6)6) Expansion Detectors, & Turbine Parts, Expansion Detectors, & Turbine Parts, )) p , ,p , ,7)7) Mechanical Gears and Fittings, Mechanical Gears and Fittings, 8)8) Rotary Relays, Coils, Rotary Relays, Coils, 9)9) Fire Detection ComponentsFire Detection Components9)9) Fire Detection Components. Fire Detection Components.

www.dsusainc.com (24/7) Phone 914.456.0227 23

CONCLUSION No 1YOUR PLANT GREATLY CAN BENEFIT USINGYOUR PLANT GREATLY CAN BENEFIT USING

REVERSE ENGINEERING OPTIONREVERSE ENGINEERING OPTION

a) Resolves Serious Lead Time Problem!b) Extend the USEFUL Mean LifeUSEFUL Mean Life of Your

Systems & EquipmentsSystems & Equipments, c) No Prohibitive Modification Cost,

) 40 60 % C t S i O Nd) 40 - 60 % Cost Savings Over New Equipment,

e) No Downtime Riske) No Downtime Risk, f) No Substantial Lead Time,

www.dsusainc.com (24/7) Phone 914.456.0227 24

CONCLUSION No 2REVERSE ENGINEERING EXECUTEDREVERSE ENGINEERING EXECUTEDREVERSE ENGINEERING EXECUTED REVERSE ENGINEERING EXECUTED

CORRECTLY Is BOTH LEGAL & ETHICALCORRECTLY Is BOTH LEGAL & ETHICAL

MidMid 1980 U S G t S d th1980 U S G t S d th MidMid--1980: U.S. Government Sponsored the 1980: U.S. Government Sponsored the Development of Large Scale Reverse Engineering Development of Large Scale Reverse Engineering Program .Program .gg

MIL-HDBK-115: DOE / US Air Force Launched a Reverse Engineering Program – 494 Revere Engineering Projects That

Yielded a $ 378 Million …

Average Return On Investment of 14:1 Average Return On Investment of 14:1 EPRI TR 107273 Chapter 3 & 4: Provides Guides On: EPRI TR 107273, Chapter 3 & 4: Provides Guides On:

Patents/Trademarks: Are Protected for 20 Years20 Years,

Trade Secrets: Are Not Protected If Obtained Legally (Agreement). (Agreement).

www.dsusainc.com (24/7) Phone 914.456.0227 25

Questions?

www.dsusainc.com (24/7) Phone 914.456.0227 26

Purpose Statement

Reverse Engineering maybe used to • identify an obsolescence solution,

• achieve cost savings by purchasing from an alternate supplier,

resolve lead time concerns or• resolve lead-time concerns or

• improve an item’s performance.

3

Site Roles and Responsibilities

Procurement Design EngineeringProcurement Engineering• Interface with the

Design Engineering• Provide technical

assistance as• Interface with the applicable vendor throughout the

assistance as required

gentire reverse engineering process

• Develop criteria & approve drawings

4

• Perform evaluation

DefinitionEPRI defines reverse engineering as the process g g p

of developing technical information sufficient to duplicate an item by • physically examining, measuring or testing existing

items;

• reviewing technical data; and/or• reviewing technical data; and/or

• performing engineering analysis.

Refer to EPRI TR-107372 "Guidelines forRefer to EPRI TR 107372, Guidelines for Reverse Engineering at Nuclear Power Plants“.

5

Definition of Like-for-LikeExelon’s governance and oversight procedure g g p

defines a replacement item as like-for-like if there is a high level of confidence that there have been no changes in the design, material, or manufacturing process since the procurement of the item being replacedthe item being replaced.

6

Is Reverse Engineering Considered Is Reverse Engineering Considered Like-for-Like?

Based upon the nature of a reverse engineered item, both the design and manufacturing of the new item will inherently change.

7

Therefore, the item would not meet the definitionnot meet the definition of…

lik f liklike-for-like.

8

Reverse Engineering vs Item Reverse Engineering vs. Item Equivalency Evaluation

Reverse Engineering and Item Equivalency Evaluation processes are not the same.

Item Equivalency Evaluation may be necessary to document the replacement item is acceptable if h h b d th t t hchanges have been made that warrant such an

evaluation. (i.e.., material changes)

9

Who Performs Reverse Engineering?

Station • Follows the guidance in

EPRI TR-107372

Vendors• Interfaces with the

requesting station to ensureEPRI TR-107372

• Perform evaluations for items that pass the SM-AA-300 IEE Screening and are

requesting station to ensure that item meets the; technical aspects of the

original300 IEE Screening and are not prohibited by SM-AA-300-1001 Attachment C

original

design features that are unique to nuclear safety-related

10

Legal Issues

Reverse Engineering is a legal practice and, when performed ethically, is not a form of design infringement or theft.

Any legal concerns about Reverse Engineering h ld b dd d b b ishould be addressed on a case-by-case basis

with the legal department.

11

Proprietary Data

Technical data that embodies trade secrets developed at private expense, such as • design procedures or techniques

• chemical composition of materials or

f t i th d t t t• manufacturing methods, processes, or treatments, including minor modifications

12

Proprietary data (cont.)

Is not generally known or available from other sources

Has not been made available by the owner to others

And is not readily available to the public without obligation concerning confidentiality

13

Proprietary data (cont.)

OEM documents may not be given to vendors assisting in Reverse Engineering.

It is acceptable to transcribe design data / requirements from OEM documents and submit th h t itt l f d i i f tithrough a transmittal of design information.

14

Design Information

Written documents or graphical information which establish design, fabrication, construction, installation, erection, and operational or test requirements for a system, structure or componentcomponent.

15

Where to start

Identify the item’s end use applications and function.

Perform a failure mode effect analysis (FMEA).

Identify the item’s critical characteristics for design.

16

Reverse Engineering “To Do” List of Reverse Engineering To Do List of Activities

Collect / Review the Item’s Design Data.• This may include component / item drawings, system

drawings, vendor specification, vendor procedures, vendor manual information, station procedures and Exelon specifications.Exelon specifications.

17

Reverse Engineering “To Do” List of Reverse Engineering To Do List of Activities

Inspect, measure and test the original item.• This data should be recorded in the form of drawings

and / or reports by either the site or the vendor. It should be documented whether the item is new or used. If used, the service time and conditions are to beused. If used, the service time and conditions are to be identified. This information will be useful when evaluating critical characteristics.

18

Reverse Engineering “To Do” List of Reverse Engineering To Do List of Activities

Evaluate Plant / Component / Item Interfaces including Fits & Tolerances, Inputs / Outputs.• This includes mechanical and electrical interfaces. If a

vendor is assisting in the Reverse Engineering, interfacing item data or actual interfacing parts mayinterfacing item data or actual interfacing parts may need to be supplied to the vendor.

19

Reverse Engineering “To Do” List of Reverse Engineering To Do List of Activities

Review Item History. • This is to include a review of OPEX / EPIX and Exelon

condition reports. Historical failures may identify inadequate design characteristics that could be alleviated during the Reverse Engineering.alleviated during the Reverse Engineering.

20

Reverse Engineering Activities (cont.)

Establish Item’s Design.

Design drawings / requirements for the Reverse E i d it t b d l d b th itEngineered item are to be developed by the site or vendor.

All documents that are prepared by a vendor must beAll documents that are prepared by a vendor must be provided to the site for approval prior to manufacturing. Special tests / inspections / procedures that are required to demonstrate the replacement item will performto demonstrate the replacement item will perform acceptably are to be identified.

The manufacturing of a prototype may be required.

21

g p yp y q

Screening

Once it has been determined to proceed with the Reverse Engineered item, an Item Equivalency Screening must be performed.

22

Documenting Procurement Documenting Procurement Engineering approval

The item may be approved as a Pre-Engineered Solution if it is manufactured to industry standards.

The item may be approved by a Safety Basis evaluation if dimensions and tolerances are the only unknowns. Justification is to be provided on why the dimensions and tolerances were determined to be acceptable.

An Item Equivalency Evaluation is required when there are changes to An Item Equivalency Evaluation is required when there are changes to fit, form or function. When enhancements are made to the item, an Item Equivalency Evaluation is required.

23

Configuration Control

“It is incumbent upon all engineering groups to maintain appropriate configuration control.”

24

Reverse Engineering Guidelines

link to Reverse Engineering Flowchart

25

In Summary

Reverse Engineering maybe used to identify an obsolescence solution, achieve cost savings by purchasing from an alternate supplier, resolve lead-time concerns or improve an item’s performanceperformance.

But………if performed incorrectly can result in legal ramifications as well as loss of configurationlegal ramifications as well as loss of configuration control.

26

27

Reverse Engineering Guidelines

Identify Item’s End Use Applications, Function and perform a FMEA

Determine Need for Reverse Engineering Obsolete, i.e. no longer available Cost Savings • Resolve Lead-Time Concerns Enhancement / Improvement

Identify the Item’s Critical Characteristics for Design Reference the critical characteristics / parameters section of the IEE template SM-AA-300-1001-F-01

Collect / Review Item’s Design Data OEM documents shall NOT be sent to vendors. OEM information may be transcribed Design data / requirements are to be transmitted to vendors using a TODI.

Inspect, Test and Measure Item On-Site Vendor

Evaluate Plant / Component / Item Interfaces including Fits & Tolerances, Inputs / Outputs Data or actual interfacing parts may need to be supplied to the vendor

Review Item History OPEX / EPIX review

Establish Item’s Design Create drawings and specifications Identify Special tests / inspections / procedures If a prototype is required, identify / perform required testing

Sufficient Information to

Duplicate Item?

Document Procurement Engineering Review / Acceptance of Reverse Engineered Item. Pre-Engineered Solution Safety Basis Evaluation Item Equivalency Evaluation

Does the Item Pass the

Equivalent Item Screening Form?

Can Additional

Information Be Obtained?

Use Other Plant Design Change processes

No

Yes Yes

No

NoYes

NUPIC U d tNUPIC Update

EPRI Procurement Forum August 24, 2011

Fawaz JabaliNUPIC Vice ChairmanNUPIC Vice Chairman

Arizona Public Service (APS)1

2

3

4

5

NUPIC is ANUPIC is A Learning Organization

NRC Vendor Inspection Report

NRC Observation of NUPIC Audit Team

Mi d O t it R iMissed Opportunity Reviews

Peer Review

Audit Team Feedback Audit Team Feedback

Supplier Feedback Questionnaire

NUPIC Member Performance Monitoringg

Vendor Performance Monitoring

Training

6

NUPIC Checklist U C C ec st

NUPIC Audit Checklist Revision 15NUPIC Audit Checklist Revision 15became effective 08/01/2010: Added more attributes for 10CFR21 evaluation

Timeframes requirements for 10CFR21 records retention/maintenance (10 years)retention/maintenance (10 years)

Added attribute for overall effectiveness of internal audit process

Added attribute for overall effectiveness of corrective action process

R i i 16 C i SRevision 16 Coming Soon7

Performance BasedPerformance Based Supplier Audit (PBSA)

Audit Focus Upon Product Quality and Performance-Related Activities

Input from NUPIC users is crucial

Avoid Generic Programmatic Attributes Avoid Generic Programmatic Attributes that are Already Covered in the Checklist

I l d T h i l Ch t i ti d Include Technical Characteristics and Acceptance Criteria

Include Operating Experience8

NUPIC Ch llNUPIC Challenges

Software Dedication

A2LA/NVLAP A2LA/NVLAP

ILAC Accreditation Process

C b S it Cyber Security

Control of Safeguards

Safety Conscious Work Environment

Safety Culture Safety Culture

9

NUPIC Ch llNUPIC Challenges

Continuity of the NUPIC Organization

New Auditors and Training

Driving Performance Improvements in Closing Audits that Have Been Open for aClosing Audits that Have Been Open for a Considerable Length of Time

10

C ll b ti Eff tCollaborative Efforts

NUPIC & EPRI Working to develop New Guidance for the Dedication of Commercial Software

NUPIC & EPRI working to develop course NUPIC & EPRI working to develop course for NUPIC Audit Team Leader

NUPIC & NEI working to Develop a NUPIC & NEI working to Develop a Method of Acceptance for International Laboratory Accreditation CooperationLaboratory Accreditation Cooperation (ILAC) 11

Q ti ?Questions?

12

Becoming a Becoming a NUPIC SupplierNUPIC Supplier

EPRI Procurement Forum August 25 2011August 25, 2011

Fawaz JabaliNUPIC Vice ChairmanNUPIC Vice Chairman

Arizona Public Service (APS)1

2

NUPICNUPIC Provides a Cooperative Program for the

Evaluation of Vendor PerformanceDo not Certify Vendors like ISO/ASME

Perform Joint Utility Audits

Exchange Results of Individual Utility Auditsg y

Develop Methodologies to Monitor and Improve Vendor Performance

Provides a Forum to Constantly Improve the Utility Oversight Process of Vendors

3

NUPICNUPIC Provide a Forum for Discussion of

P t Q lit A IProcurement Quality Assurance Issues

Exchange Vendor Performance Information

Discuss Concerns Resulting from Quality g yAssurance Regulatory Issues

Assist Vendors in the Resolution of Member Concerns

4

NUPICNUPIC Provides an Interface for ProcurementProvides an Interface for Procurement

Quality Assurance ActivitiesMaintain Interface with NEI to CoordinateMaintain Interface with NEI to Coordinate

Communication/Dialogue with the NRC

Maintain Interface with NEI to Provide Input a ta te ace t to o de putand feedback on Industry Positions/Commitments Regarding Procurement Quality Assurance Issues

Maintain Interfaces with EPRI & JUTG

5

O ll POverall Process

One Utility Shared Utility NUPIC

One Utility At a time One Utility At a time

Good Work Brings More Work

Sh d Utilit A dit Shared Utility Audit

5 Utility Users NUPIC Supplier Audit

5/2006 (1) 5/2009 (3) 5/2011 (13)

6

Wh Y G C llWho You Gonna Call

Plant Users/Organizations (Eng, Projects)

Plant Needs Must Be Established Plant Needs Must Be Established

Existing ASL Supplier Vs. New

P d R i Prudency Review

Cost Benefit Justification

Request for New Supplier Evaluation

Supplier QA Evaluation Starts Supplier QA Evaluation Starts

7

What Do I Need to DoWhat Do I Need to Do Have/Develop a QA Program which p g

Implements the Requirements of 10CFR50 Appendix B and 10CFR21pp

Market your QA Program as Well as the Safety Related Products or ServicesSafety Related Products or Services

Successfully Pass a Utility Audit per10CFR50 Appendix B and 10CFR21per10CFR50 Appendix B and 10CFR21

Contact NUPIC Rep. for Utility that Audited you to ensure NUPIC database isAudited you to ensure NUPIC database is Updated to list your Company as a User 8

S li A l PSupplier Approval ProcessUtilit O l A dit ($$$ + Ti C i ) Utility Only Audit ($$$ + Time Consuming)

Planning & Scheduling

Assemble Auditors & Technical Specialist

Perform Audit Perform Audit

Issue Report and Any Findings

A l T & S li N tifi ti Approval Type & Supplier Notification

Procurement May Now Commence

Update NUPIC Database9

Supplier Approval ProcessSupplier Approval Process Audit/Survey Exists ($ + Fairly Quick)y ( y )

Source: NUPIC/Shared/One Utility

Obtain Audit File & QA Manual Obtain Audit File & QA Manual

Perform 3rd Party ReviewS f S l /L iScope of Supply/Location

Findings and Significance

Approval Type & Supplier Notification

Procurement May Now Commencey

Update NUPIC Database10

Att ib t f T S liAttributes of Top Suppliers Strong Quality Culture Strong Quality CultureSatisfactory Implementation of 10CFR50

Appendix B and 10CFR21Appendix B and 10CFR21

Management Embraces & Leverages Audit Team Input and ExperienceTeam Input and Experience

Readiness for Audit Through Detail Planning, Records Retrievability & Staff Availability y y

QA Manual RevisionClear Description of Changes MadeClear Description of Changes Made

Highlighted Text of Changes Made11

Att ib t f T S liAttributes of Top Suppliers

Order Entry Review and Final Certification Detail Review of Technical & Quality Requirements

Well Defined Exception Process

Detail Final Review Prior to Shipment

Commercial Grade DedicationWell Documented Dedication Process

Cl Id tifi ti f C iti l Ch t i ti Clear Identification of Critical Characteristics Adequately Tied to Safety Function

Adequate Verification & Justification Adequate Verification & Justification

12

Att ib t f T S liAttributes of Top SuppliersRobust Internal AuditRobust Internal Audit

Comprehensive System of Planned and Periodic Internal Audits

Qualified Audit Participants have No Direct Responsibility in the Areas Being Audited

Checklists/Procedures Used with Documented Objective Evidence

Intrusive Intrusive

Follow-up Action Taken Where Needed

13

Att ib t f T S liAttributes of Top Suppliers Robust Sub-Supplier Audits/Surveys Robust Sub-Supplier Audits/Surveys Effective Control and Release of Procurement

Documents Including Changes

Effective Evaluation, Selection and Assessment of Sub-suppliers with Clear Program Distinction Between Audit Vs Commercial Grade SurveyBetween Audit Vs. Commercial Grade Survey

Comprehensive and Instrusive Audits

Qualified Audit Participants have No direct Qualified Audit Participants have No direct Responsibility in the Areas Audited

Checklists/Procedures used with Documented Obj ti E idObjective Evidence

Follow-up Action is Taken Where Needed 14

Att ib t f T S liAttributes of Top Suppliers Strong Corrective Action SystemStrong Corrective Action System

Low Threshold to Identify Issues and Proper Classification Relative to Significance

Clear Connection between the Nonconformance and Corrective Action Processes and 10CFR21

Measures Established and Implemented to AssureMeasures Established and Implemented to Assure Conditions Adverse to Quality are Promptly Identified and Corrected

Adequate Actions Taken to Prevent Recurrence for any Significant Conditions Adverse to Quality

Deficiencies Identified by Customers are Adequately Deficiencies Identified by Customers are Adequately Assessed and Entered into the Nonconformance/Corrective Action Program 15

Q ti ?Questions?

16

Acquiring the ASME “N” Stamp; Development of the Required Programs and Implementation Development of the Required Programs and Implementation 

a Suppliers Experience

Bill HenwoodVP & Director, NuclearJUTG Procurement ForumAugust 24, 2011

Who is VALVtechnologies?

Over 460 Employees Worldwide

Corporate Headquarters & Factory L tiLocations:

• Houston, Texas (2)• United Kingdom• China

Sales Offices:  Direct Personnel • Dubai• China• China• Korea• France• Netherlands• South Africa• South America

N‐3328 N‐3329

The Global Leader in Absolute ZERO LEAKAGEMetal Seated Valve Technology

Who is VALVtechnologies?

Authorizations & Qualifications

• ASME III Class 1, 2 & 3 • 10CFR50 Appendix B• Part 21 Acceptance• ANSI N45.2• NQA‐1• ISO 9001 ‐ 2000• PED Compliant (Europe) • Lloyds EMEA Register SIL‐3 (Europe)• Nuclear Industry Assessment Committee 

N‐3328 N‐3329

Primary Manufacturing Plant in Houstony g

Bingle Road 125,000 Square Ft

Bingle Road 1986

Railhead 40,000 Square Ft on 15 AcresPlanned 150,000 Square Ft Factory Site

Valves for Nuclear Power

“Application Solutions” for the Next 60 Years…”ppVTI technology did not exist during the Generation II and early Generation III 

plant design phases (1960’s – 1980’s).

MSBV PSGV Control Valve Inline Check

Nuclear Future

VALVtechnologies NuclearManagement Commitment

“Nuclear is  a significant contributor to the future of our company; perhaps the single largest area of growth for the next 10 years”  perhaps the single largest area of growth for the next 10 years   

‐ Kevin Hunt , CEO

Attracting New Nuclear Suppliersg ppThe Nuclear Energy Institute:

•Since 2008 the NEI has conducted 9 vendor workshops in strategic locations throughout the United States. 

•The effort is intended to attract new and former nuclear suppliers to participate in the Nuclear Renaissance. 

•Thousands of potential vendors have attended, most serious vendors have attended more than one. 

• The abandonment of qualified nuclear suppliers in the post Three Mile Island era when most of the US domestic projects were halted and/or cancelled has caused a huge void.

•The effort is supported by the NSSS and EPC’s involved in the new build arena•The effort is supported by the NSSS and EPC s involved in the new build arena.

•The efforts are necessary and well intentioned… but no one talks about the costs!

Cost of Nuclear at VTI:Cost of Nuclear at VTI:

$4,773,000.004,773,Program development and implementation costs since 2005

Cost of Nuclear at VTI:Cost of Nuclear at VTI:

$4 773 000 00

•Commencing in early 2005 though September 2007 personnel initially assigned  to develop and implement the nuclear program were not totally dedicated to the 

$4,773,000.00

develop and implement the nuclear program were not totally dedicated to the process. Personnel were assigned to other Engineering and Quality related duties and thus distracted from the task at hand.

•Costs for the first 2 + years, for salaries, consultants, programmatic development resulting in a unusable program. 

Approximately   $1,600,000.00

•Investment in  Dedicated Personnel, Consultants, Programmatic Development, Training, Supplier Audits, Implementation and ASME Audit since October 2007.

Approximately $3,173,000.00

State of the Industry

ASME “N” Stamp Holders

Nuclear Vessels, Pumps, Valves, Piping Systems, Storage Tanks, Core Support Structures, Concrete Containments, and Transport Packaging

ASME N  Stamp Holders

• 213  Authorizations Worldwide• Held by 157 companies• VTI was Number 110 in March of 2009• 1008 ASME “N” Stamps in 1980p 9• 62 at the low point in the mid ‐ late 1990’s

Source ASME as of 08/04/2011

Organization

VTI Nuclear Organizationg

VTI Nuclear Organizationg

VTI Nuclear Organizationg

VALVTechnologies Nuclear Organization Chart

Director of Quality Assurance

Nuclear Quality Assurance ManagerNuclear Quality Assurance Manager

QC Inspectors DocumentationNDE

Level IIIDocument

Lead AuditorsGage Calibration Welding

QC Inspectors DocumentationLevel IIIExaminers

ControlLead Auditors

Inspector

Document Control

Technicians

Specialist

WeldingInspector

Technicians

Figure 3

p

VTI Nuclear Organizationg

The VTI Nuclear TeamThe VTI Nuclear Team

Core Nuclear Team – 85 years of combined experience…

Noel MathenyNuclear Industry 

Specialist

Cesar MejiaNuclear Engineering 

SpecialistManager

Dave Coon Tim HowardDave CoonNuclear Quality 

Manager

Tim HowardNuclear Territory 

Manager

The VTI Nuclear TeamThe VTI Nuclear Team

Focused Key Personnel  assigned to Team…

Erica ChavezProject Manager

Ken RickardMarketing Manager

Donna Moritz Peter MiddletonDonna MoritzPurchasing

Peter MiddletonEngineering

Hi t   P  D l tHistory ‐ Program Development

History ‐ Program Developmenty g p

Major Milestones in Program Development at VTI:

Efforts to develop and implement the VTI nuclear program commenced in 2005 as the ramp up to the “Nuclear Renaissance”  was in full swing. 

(O t b   ) N l  I d t  Di t(October 2007) Nuclear Industry Director‐ Reports directly to the  CEO with responsibility for the general oversight of all nuclear operations, sales and marketing efforts.

(November 2007) Nuclear Engineering Manager‐ Reports to the Director of the Nuclear Industry. His responsibilities include all aspects of engineering design. The NEM is the technical design authority, and supports all nuclear operations.  He is also responsible for contract administration, project management.

(December  2007) Nuclear Quality Assurance Manager‐ Reports to the Director of (December  2007) Nuclear Quality Assurance Manager‐ Reports to the Director of Quality,  responsible for the overall nuclear quality program, including maintaining and updating the NQAM’s, our nuclear procedures, the ASL; he is our Certified Lead Auditor, and interfaces with our ANIS.

(January 2008) Consultants Hired‐ Reported to the Director of the Nuclear Industry.  They ( y ) p y yconducted a complete assessment of all existing quality programs within VTI, including ISO 9000, ASME, API and PED for consistency and incorporation in our nuclear program development.

History ‐ Program Developmenty g p

Major Milestones in Program Development at VTI:

(May 2008) 10CFR50 Appendix B ‐ Introduced for supply of Safety Related VTI Product to the existing Nuclear Plant Operators, NSSS and EPC’s for the New Build Industry

(October 2008) Nuclear Industry Assessment Committee ‐ NIAC Membership granted (October 2008) Nuclear Industry Assessment Committee NIAC Membership granted (NIAC) Organized in 1994 as a result of an industry initiative to share audits among members; it performs supplier qualification activities eliminating the redundancy and costs associated with duplicate audits

(January 19 21  2009)ASME “N” and “NPT” Audit ‐Successful audit with four (January 19‐21, 2009)ASME  N  and  NPT  Audit ‐Successful audit with four observations and ZERO findings.  Certificate issuance in early March 2009

(May 2009) Appointed the VTI Nuclear Territory Manager ‐ Hired to cover the US existing fleet  and  manage our representative network  Focuses on the Charlotte NC based NSSS & EPC’sexisting fleet, and  manage our representative network. Focuses on the Charlotte NC based NSSS & EPC s

(November 2009) First NUPIC based audit was performed by Duke Energy – 4 day audit was a prelude to our first ever ASME Section III order.  Zero findings or observations placed VTI in the Duke Energy Approved Suppliers List (ASL)gy pp pp ( )

History ‐ Program Development

Major Milestones in Program Development at VTI:(November 2009) First ASME “N” Stamped Order from Duke Energy – 12‐ 6” 300# 316SS MSBV with qualified gear operators and extended flexible drives. Acceptable PO received in mid December after 7 PO revisions.  

Duke Oconee High Pressure Injection ValvesDuke Oconee High Pressure Injection Valves

(January 2010) DFT and VTI Sign License Agreement for Nuclear industry – Rounds out the VTI product offering and provides a path for DFT products to the Nuclear Industry

(March 2010) Successfully tested and delivered the first 4 ASME valves to Duke –(March 2010) Successfully tested and delivered the first 4 ASME valves to Duke 14 week delivery. 8 valves remained. 4 more tested and delivered in August 2010.  Surveillance for the  remaining required by March 2011 has been lifted.

Challenges –Moving Forward

Challenges ‐Moving Forward

f d d h l d d h f

g g

•Acceptance of our products and technology. Our products require a paradigm shift in an industry that thrives on obsolescence and is reluctant to change

•Placement on utilities Approved Suppliers List is key to the success. As a result of the Duke placement VTI is now on the ASL for the following Utilities:

• Progress Energy• Bruce Power (Canada)• EDF Energy (formerly British Energy)EDF Energy (formerly British Energy)• Nuklearna Elektrarna Krsko (Slovenia)

•ASL status as a commercial supplier will not allow for automatic acceptance for SR or ASME  applications once your programs and authorizations are in placeor ASME  applications once your programs and authorizations are in place.

Challenges ‐Moving Forwardg g

•Nuclear Procurement Issues Committee (NUPIC) was formed in 1989 by a 

The Holy Grail‐NUPIC acceptance

partnership involving all domestic and several international nuclear utilities. The NUPIC program evaluates suppliers furnishing Safety‐Related components and services to nuclear utilities in accordance with 10CFR50 Appendix B.

•NUPIC based audits are not driven by suppliers with an ASME Section III programs as it is not a requirement.

• Audits are not automatic regardless of an existing Appendix B program or • Audits are not automatic regardless of an existing Appendix B program or NIAC membership; they are expensive, time consuming and will not occur unless a utility requires your product or service. 

•Full NUPIC  acceptance and automatic placement on the utility ASL requires five independent audits or audit results accepted by an auditing utility and 4 additional member utilities. A full NUPIC audit will be scheduled to review your 10CFR50 A di  B     thi     d     i   l d i  th   t tiAppendix B program once this occurs and your company is placed in the rotation.

Challenges ‐Moving Forwardg g

•We continue have ASL issues at most  nuclear utilities where NUPIC acceptance is a i  W     hi   i h R i   h  i  NUPIC  di d  H  i  requirement. We counter this with Representation who is NUPIC audited. However it 

can add cost and loss of any competitive edge.

•Keeping representatives motivated…p g p

•New construction activity has slowed to a crawl.•NRC approval, political and economic pressures along with  the new found ab ndance of nat ral gas are hindering the progression of ne  n clear abundance of natural gas are hindering the progression of new nuclear construction.

•Shift in focus in existing fleet applications through major projects such as Extended Power Up  rates and Steam Generator replacement are the new focusPower Up ‐rates and Steam Generator replacement are the new focus.

•Up to the equivalent of 8 new 1000MW plants will be added to the grid without building a single plant by 2015

•Return on the investment … 

Lessons Learned

Lessons Learned

•Be well financed… whatever you think it going to cost… double it!

•Have the commitment and patience at the highest levels of  management; it  is paramount.

•Focus… once you decide don’t look back… don’t distract.

•Find and hire the best and brightest Core Team. (Quality & Engineering)

•Don’t go it alone; the right consultants can make all the difference.

•Carefully select your ANIS – they are your advocate.

•Educate your team members – dispel the fear of nuclear.

Lessons Learned

•Establish realistic deadlines and hold the team accountable.

•Contact the ASME as early as possible to schedule your audit; do all you can to hold to it.

•Focus on training; document it… and do it again.

•Be prepared to demonstrate and defend your processes.  Don’t be adversarial p p y p

•Be organized, be prepared to make real‐time manual changes; have your documentation and  procedures available and ready for review.

•Live the process… a nuclear program can improve your overall product quality, reduce rework, hold sub‐suppliers more accountable, advance customer satisfaction and increase profitability.p y

QUESTIONS?

How to Get a NUPIC AuditHow to Get a NUPIC Audit

For:For:

Joint Utility Task GroupJoint Utility Task Groupy py pAugust 2011August 2011

By:By:

Rick EasterlingRick EasterlingSr. DirectorSr. Director--US Business DevelopmentUS Business Development

[email protected]@kinectrics.com804804--550550--31093109804804 550550 31093109

About KinectricsAbout Kinectrics Formerly the Technical Division of

Ontario Hydro, one of North America’s largest, most reliable utilities

Mechanical TestingLab High Voltage/

High Current Lab

Comprehensive facilities & advanced specialized laboratories near Toronto, ON Canada

300,000 SQFT on 15+ Acres Almost 100 years of advanced technical

expertise & experience In business as Kinectrics since 2001 Increased Business, Revenue and

Employees every year since 2001p y y y Over 400 scientists, engineers &

professional staff ~$100 000 000 Annual Revenue$100,000,000 Annual Revenue US Office (Cincinnati, OH)

Quality Quality Management and AuditsManagement and AuditsQuality Programs 10 CFR 50 Appendix B (US)/NQA-1CSA Z299.2CSA Z299.2CSA N285/NCA 4000ISO 9001-2000ISO 17025•Analytical & Environmental Chemistry Testing •MetrologyMetrology•High Voltage / High Current Labs

Numerous Audits:Exelon Audit per NUPIC Checklist (August 2008)MOX Project Audit (August 2010)NIAC Member and Approved Audits (January 2011)pp ( y )NUPIC Audit Completed (April 2011)Numerous other OEM audits (SI Audit May 2011)

TopicsTopics• About Kinectrics

• How to Get An Audit?• How to Get An Audit?

• Politics

• The First Sponsor

• Hard Work• Hard Work

• Patience

• The Audit

• ResolutionResolution

• Reflections

Politics•KI Chairman

S li iti t•Soliciting support

•Solve a business issue dor need

The Sponsor

•Need a willing utility sponsor:

T i t i dit ( NUPIC Ch kli t)• To invest in an audit (per NUPIC Checklist)

• To share the audit report

• To order something

• To keep you on the ASL

Hard Work

•Add as many utilities, leveraging the audit.

U bili i ibl•Use as many capabilities as possible to perform safety related work:

• Forensic/failure analysis

• Special analysis (oil and refrigerant)

• Small dedication projects

• Field testing services

•Be creative as well

• BeggingBegging

• Quid pro quo projects

Patience is a Virtue

•Patience comes from Latin root “patior: toLatin root patior: to suffer”

•Actual time fromActual time from focused effort to audit completion:

4 Y !4 Years!

Finally, the Audit

•Extensive reviews and preparationpreparation

•Self-assessment

Ki t i dit•Kinectrics audit was more complex:

L d b S h• Led by Southern

• Included Exelon, SCE&G, OPG, Bruce personnel

• NRC Observers (2)

• CNSC Observed NRC on behalf of IAEAbehalf of IAEA

Conditional Entropy

Audit Resolution

•Audit completed April 2011

3 Fi di f A di•3 Findings from Audit

•Audit findings closed in June 2011

•Kinectrics audit report now available in NUPIC databaseNUPIC database

Reflections/Summary

•Be committed to the industry you seek toindustry you seek to serve

•Use political andUse political and product leverage where possible

•Be prepared for a significant investment gof time and resources


Recommended