+ All Categories
Home > Documents > ERC Case No. 2010-O97RC

ERC Case No. 2010-O97RC

Date post: 12-Jan-2016
Category:
Upload: talbot
View: 70 times
Download: 6 times
Share this document with a friend
Description:
PANAY ELECTRIC COMPANY, INC. Expository Presentation Application for Approval of PECO – PEDC 2010 EPPA. ERC Case No. 2010-O97RC. 9:00 AM, September 09, 2010, Iloilo Business Hotel, Small Ville Complex, North Diversion Road, Iloilo City. PECO –Franchise Holder - ILOILO CITY. - PowerPoint PPT Presentation
22
ERC Case No. 2010-O97RC Expository Presentation Application for Approval of PECO – PEDC 2010 EPPA 9:00 AM, September 09, 2010, Iloilo Business Hotel, Small Ville Complex, North Diversion Road, Iloilo City PANAY ELECTRIC COMPANY, INC.
Transcript
Page 1: ERC Case No. 2010-O97RC

ERC Case No. 2010-O97RC

Expository Presentation Application for Approval of

PECO – PEDC 2010 EPPA

Expository Presentation Application for Approval of

PECO – PEDC 2010 EPPA

9:00 AM, September 09, 2010, Iloilo Business Hotel, Small Ville Complex, North Diversion Road, Iloilo City

PANAY ELECTRIC COMPANY, INC.

Page 2: ERC Case No. 2010-O97RC

PECO –Franchise Holder - ILOILO CITY

PECO –Franchise Holder - ILOILO CITY

Panay Electric Company is the Franchise Holder for the distribution of electricity in the City of Iloilo by virtue

of NEC License Number 158 issued on January 19, 1994 by the National Electrification Commission.

Page 3: ERC Case No. 2010-O97RC

PECO’s Franchise – City of IloiloPECO’s Franchise – City of Iloilo

Page 4: ERC Case No. 2010-O97RC

PECO Serves Its Franchise Through 4 Main Substations

PECO Serves Its Franchise Through 4 Main Substations

Substation capacity – Location Available Capacity

10 MVA Substation – Jaro 10 MVA

25/30 MVA Substation - Mandurriao 30 MVA

25/30 MVA Substation – Molo 30 MVA

20 MVA Substation – City Proper 20 MVA

TOTAL RATED CAPACITY 90 MVA

Page 5: ERC Case No. 2010-O97RC

PECO is connected to its power suppliers through its 69 kV Sub-

Transmission (Loop) system

PECO is connected to its power suppliers through its 69 kV Sub-

Transmission (Loop) system

Page 6: ERC Case No. 2010-O97RC

PECO’s Forecasted Supply Requirement

PECO’s Forecasted Supply Requirement

2010 (See explanation *) - 78.3 MW

2011 5% growth rate

- 82.2 MW

2012 7% growth rate

- 88.0 MW

2013 5% growth rate

- 92.3 MW

2014 5% growth rate

- 97.0 MW * 2010 Load Adjusted to remove Impact of El Nino

Page 7: ERC Case No. 2010-O97RC

Existing PECO Supply ContractsExisting PECO Supply Contracts1) PECO – PPC 1997 PPA - 72 MW (Diesel Contract)

This contract is for 25 Years and will end on 2023

2) PECO – GCGI 2010 (Non-Firm) – 10 MW (Geothermal)

July to December 2010

Supply Available During

Off Peak Period Only

(Cheap power but mostly not available when needed)

Page 8: ERC Case No. 2010-O97RC

Problems Encountered by PECO with Existing PECO Supply

Contracts

Problems Encountered by PECO with Existing PECO Supply

ContractsConsidering the volatility of Diesel Prices as

influenced by world crude prices, PECO’s Generation Charge Rate is restrictive (If this is pure diesel without low cost NPC Supply, this is higher than P9 / kWh).

The total Diesel Plant Capacity of 72 MW is now lacking when compared to the total load of PECO (The 78.3 MW is the load recorded at PECO’s sub-stations but in terms of total required plant output, this is already beyond 82 MW) This results to load shedding during PECO’s Peak Hours (10 AM to v4 PM)

Page 9: ERC Case No. 2010-O97RC

PECO’s Typical Daily Load CurvePECO’s Typical Daily Load Curve

Typical May 2010 Daily Loading

0

10000

20000

30000

40000

50000

60000

70000

80000

90000

Mon 44897 43180 40894 39600 38058 37728 38036 44035 57939 68569 74944 76664 76035 80598 81973 77196 72208 64105 68888 63918 59612 58482 53514 49583

Tue 46402 43935 41712 40172 39048 38653 38406 43323 56863 67089 75921 76873 76050 80669 77049 76725 72713 65310 67505 66369 59776 57542 53668 50086

Wed 46293 43609 41369 39666 38705 38100 37666 44896 59727 66329 73336 74107 74021 78052 77789 75483 72367 64295 67107 63414 58886 56408 54247 49473

Thu 49331 46666 44015 42397 41167 40204 39043 44446 56103 69857 76487 77235 76818 80498 80337 75910 70165 64399 68334 64066 60192 57776 53870 50308

Fri 46467 44595 41904 39785 38794 38432 37185 42954 56938 68749 75777 76709 76444 77595 78607 74142 70719 63937 68214 66004 60224 57326 54032 49915

Sat 46590 44008 41349 39862 38054 36287 35350 39173 49000 60992 66610 67605 66799 69270 68554 65944 62398 59059 63523 61032 57206 54218 52125 49451

Sun 45801 43163 39897 38189 37290 35671 34248 36509 40512 48247 53558 54041 56218 57774 58476 56380 54225 53289 60620 59964 56751 54425 51419 47371

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Page 10: ERC Case No. 2010-O97RC

Problems Encountered by PECO with Existing PECO Supply

Contracts

Problems Encountered by PECO with Existing PECO Supply

ContractsDue to lack of Power Supply, PECO consumers are now experiencing 2

hours of rotational outages in around 6 to 8 of its 19 feeders during the 10 AM to 5 PM time slot. During emergency

shutdowns of one of the 6 units of PPC plant number 1, these outages extend

up to 9:30 PM (Interruption report from May to August of 2010 attached to my

judicial affidavit would provide specifics of these rotational outages).

Page 11: ERC Case No. 2010-O97RC

What benefits will signing a contract with PEDC have for PECO

consumers?

What benefits will signing a contract with PEDC have for PECO

consumers?Signing a contract with the PEDC Coal

Fired Power Plant and getting ERC approval for the same would bring the following advantages to Iloilo City:

1) Lower Electricity Prices – Coal pricing is lower than the cost for diesel generation. The impact of Diesel price fluctuations will be greatly reduced considering that the sister company of PEDC, PPC, has agreed to reduce our diesel contract from 72 MW to 15 MW. The amended and restated PPC-PECO diesel contract is now being finalized.

Page 12: ERC Case No. 2010-O97RC

What benefits will signing a contract with PEDC have for PECO

consumers?

What benefits will signing a contract with PEDC have for PECO

consumers?

Furthermore, having an embedded generator will provide savings in terms of Transmission Charges and this will give Iloilo City customers an edge over other consumers relying 100% from NGCP to connect to their suppliers.

Page 13: ERC Case No. 2010-O97RC

What benefits will signing a contract with PEDC have for PECO

consumers?

What benefits will signing a contract with PEDC have for PECO

consumers?2) Enhanced Reliability – Power interruptions can come from various sources. Mostly, they are attributable to Supply / Generation Problems, Transmission Problems or Distribution Problems.

By introducing a new power plant with a higher capacity and bigger generators, we will eliminate generation tripping significantly. Also, since this huge generator is embedded within our franchise, we eliminate the effects of transmission faults to our system. This is a very solid power plant only 2.5 kilometers away from PECO’s 69 kV Loop system.

Page 14: ERC Case No. 2010-O97RC

What benefits will signing a contract with PEDC have for PECO

consumers?

What benefits will signing a contract with PEDC have for PECO

consumers?Furthermore, PEDC is installing two

units of 82 MW each at the PEDC power plant. This reduces the risk of loosing all of the 65 MW that we have contracted considering that there is a pro-rata reduction provision in the PEDC contact to all its customers during maintenance.

Page 15: ERC Case No. 2010-O97RC

Procurement ProcessProcurement Process

Other options for PECO’s Power Supply Requirements:

• Green Core Geothermal

Corporation• ASEA One Power Corporation• SNRE Corporation• Salcon Power Corporation

Page 16: ERC Case No. 2010-O97RC

Procurement ProcessProcurement Process

Green Core Geothermal – Rates are acceptable but the issues are a) Reliability because of distance, b) Timeliness of available supply since what they can offer now is just non-firm supply c) They cannot displace the PPC Diesel contract and contracting with them and maintaining the PPC Diesel Contract would drive PECO’s prices higher.

Page 17: ERC Case No. 2010-O97RC

Procurement ProcessProcurement ProcessASEA ONE Power – Renewable source

but no real indication as to when they will start the power plant. Also, rates are subject to increments in transportation costs still driven by diesel prices to a huge extent. A major concern as well would be the sourcing of the fuel supply, at the rate of consumption projected during their presentation, we have questions on the sustainability of fuel supply. Also they could not displace PPC Diesel. Can only provide minimal capacity

Page 18: ERC Case No. 2010-O97RC

Procurement ProcessProcurement Process

SNRE Corporation – Also a renewable source of supply that provided an offer to PECO and actually signed an agreement to construct a Biomass power plant in Ingore but failed to deliver. This agreement was signed in 2008 but never prospered. This has limited capacity (only for 5 MW) and apparently lacks financing to push the project through.

Page 19: ERC Case No. 2010-O97RC

Procurement ProcessProcurement Process

Salcon Power Corporation – Rates are diesel rates even more expensive than PPC (Sells at P 9.50 / kWh). This will not solve Iloilo City’s dependence on high cost diesel. Also, considering the plant location, we will have to add P 1.00 / kWh more or less for the NGCP charges to bring their supply to PECO. Reliability also suffers due to NGCP transmission limitations.

Page 20: ERC Case No. 2010-O97RC

Procurement ProcessProcurement Process

After considering all offers given to PECO, It is very clear that only PEDC can provide higher reliability considering its location and lower costs considering its offer to amend and restate the existing PPC Diesel contract from an existing obligation of 72 MW to a revised value of only 15 MW in consideration of the coal contract that we signed.

Page 21: ERC Case No. 2010-O97RC

URGENCY of GIVING PECO and PEDC a PROVITIONAL APPROVAL of

this APPLICATION

URGENCY of GIVING PECO and PEDC a PROVITIONAL APPROVAL of

this APPLICATIONThe PECO – PEDC contract provides for the

supply of power on a non-firm basis from the commissioning phase of the Power Plant which is expected to commence on the first week of October 2010. Providing a PA on this application would afford PECO the chance to cover its daily peaking requirement from the output of the Coal Plant starting next month. This will minimize the recurring rotational outages in the city and will also bring down prices of electricity.

Page 22: ERC Case No. 2010-O97RC

End of Presentation


Recommended