ERCOT MARKET EDUCATION ERCOT Nodal 101
Transcript
Page 1: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT MARKET EDUCATION

ERCOT Nodal 101

Page 2: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Legal Disclaimers and Admonitions

PROTOCOL DISCLAIMER

This presentation provides a general overview of the Texas Nodal Market

Implementation and is not intended to be a substitute for the ERCOT Nodal

Protocols (available at http://www.ercot.com/mktrules/nprotocols/current), as

amended from time to time. If any conflict exists between this presentation and the

ERCOT Nodal Protocols, the ERCOT Nodal Protocols shall control in all respects.

ANTITRUST ADMONITION

ERCOT strictly prohibits market participants and their employees, who are

participating in ERCOT activities, from using their participation in ERCOT activities

as a forum for engaging in practices or communications that violate antitrust laws.

The ERCOT Board has approved Guidelines for Members of ERCOT Committees,

subcommittees, and working Groups to be reviewed and followed by each market

participant attending ERCOT meetings.

Slide 2

Page 3: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Slide 3

• Attendance sheet

• Questions

• Exam

• Restrooms

Please turn off cell phones & other electronics

Housekeeping

Page 4: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Education

Training Curriculum

• ERCOT Nodal 101

• Load Serving Entity 201

• Congestion Revenue Rights

• Settlements 301

• Basic Training Program

• Generation in RUC and Real-Time

• Generation in Day Ahead Market

• Transmission 101

• Various Workshops as needed

Slide 4

Page 5: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Target Audience

ERCOT Nodal 101:

A high-level overview of the ERCOT Nodal Market for all

Market Participants and ERCOT personnel.

Slide 5

Page 6: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Course Objectives

Upon completion of this course…

…you will be able to:

• Identify major components of the Nodal Market

• For each component of the Nodal Market, describe

• Purpose

• Inputs

• Outputs

• Processes

Slide 6

Page 7: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Introduction to ERCOT

Page 8: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Overview

Topics in this lesson . . .

• Key features of the ERCOT Grid

• ERCOT Responsibilities

• Reliability and Markets

• Capacity and Energy

• Congestion Management

• Network Modeling

• Market Overview

Slide 8

Page 9: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Introduction

Key Features of the ERCOT Grid

• Represents 90% of Texas Load

• 74,000 MW of generation capacity

• 43,000 miles of transmission lines

• Electrical island with several DC Ties

Slide 9

Page 10: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

ERCOT’s Primary Responsibility is Reliability

• Match generation with demand

• Operate transmission system within established limits

Execute competitive markets for reliability services

Slide 10

Page 11: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Operational Concepts

Reliability and Competitive Markets

• Markets support reliability

• Reliability makes the markets

possible

Slide 11

ERCOT finds the balance between Reliability and

Economics.

Page 12: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

Energy and Capacity

ERCOT dispatches Energy to follow the system demand.

Slide 12

Page 13: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

Energy and Capacity

Capacity

ERCOT must also ensure sufficient Capacity is on-line to meet the forecasted demand.

Forecast

Slide 13

Page 14: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

More about Capacity

ERCOT Responsibility

Capacity Reserved for Ancillary Services

Ancillary Services needed to respond quickly to changing

system conditions.

Slide 14

Page 15: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

Ancillary Service Capacity

Acquired through

competitive markets

Slide 15

System Capacity

Ancillary Service

Capacity

Page 16: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

Ancillary Service Capacity

Three types of Ancillary Services

Non-Spin Reserve

Regulation Reserve

Responsive Reserve

Slide 16

Page 17: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

Transmission Congestion

• Generators and Loads

separated by distance

• Transmission system

has limits

Congestion management keeps transmission system operating

within limits

Slide 17

Page 18: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Responsibility

Network Operations Model

Models allow ERCOT to:

• “See” grid at any point in time

• Predict how various actions

affect grid

Representation of a physical system.

Slide 18

Page 19: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Network Operations Model

• Physical characteristics

• Ratings

• Operational limits

Including

• Transmission Elements

• Resources

• Topology

• Telemetry

ERCOT Responsibility

Slide 19

Page 20: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Overview

Page 21: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Participants

Who are the Players?

Slide 21

QSE

LSE

TSP

DSP

Resource

Entity

Qualified Scheduling Entities

Load Serving Entities

Transmission Service Providers

Distribution Service Providers

Resource Entities

Page 22: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Relationships

Slide 22

Market Participants

Page 23: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Nodal Market Design

Commercial Markets

• Bilateral Market

• ERCOT Facilitated Markets

• Day-Ahead Energy Market

• Day-Ahead Ancillary

Services Market

• Real-Time Energy Market

Slide 23

Page 24: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Nodal Market Design

Energy Dispatch

• Resource specific offers

• Resource specific dispatch

Goal

• Balance generation & demand

• Manage congestion

Energy Pricing

• Local prices for energy

• Prices include congestion costs

Slide 24

Page 25: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Nodal Market Design

Congestion Costs

• All costs are directly

assigned

• Congestion Revenue Rights

available for hedging

Slide 25

Page 26: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Nodal Market Design

ERCOT is an energy-only market

… but what does that mean?

In ERCOT, these costs must be

recovered with revenues from

energy production and

operating reserves.

It’s all about the recovery of costs to build generation.

Slide 26

Page 27: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

ERCOT Nodal Market Design

ERCOT is an energy-only market

… but what does that mean?

Scarcity pricing – higher

energy prices during periods

where energy reserves are

scarce

Energy Pricing must support investment in new generation

Slide 27

Page 28: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

You Are Here!

Slide 28

Page 29: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

An Independent Market Information System Registered Entity (IMRE) may register with ERCOT solely to access MIS Secure.

Slide 29

Page 30: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

You Are Here!

Slide 30

Page 31: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Locational Marginal Pricing

Page 32: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Overview

Topics in this lesson . . .

• Locational Marginal Prices (LMPs)

• Define LMPs

• Determination of LMPs

• Congestion Rent

• Settlement Point Prices

• Scarcity Pricing Mechanism

• Market Information

Slide 32

Page 33: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

What is Locational Marginal Pricing (LMP)?

Pricing: Cost

Marginal: to serve the next increment of Load

Locational: at an Electrical Bus

Locational Marginal Pricing

Locational Marginal Pricing

Slide 33

Page 34: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Locational Marginal Pricing

LMP Components

• Energy

• Congestion

In some markets, LMPs have a component for losses.

The Nodal Market does NOT

include losses in LMPs.

Slide 34

Page 35: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Locational Marginal Pricing

Introducing the players…

Slide 35

Gen 1

Gen 2

Page 36: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Let’s solve for LMPs at each Bus:

Locational Marginal Pricing

Slide 36

10 MW ($4 per MWh)

20 MW ($2 per MWh)

10 MW

Gen 1

Gen 2

Page 37: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Locational Marginal Pricing

When there is no congestion, all LMPs are equal.

Slide 37

10 MW ($4 per MWh)

20 MW ($2 per MWh)

10 MW

Gen 1

Gen 2

Page 38: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Locational Marginal Pricing

Slide 38

Charges to Load

LMP MW

$2 10 $20

Total $20

Payment to Resources

LMP MW

$2 0 $0

$2 10 $20

Total $20

Example: No Congestion

Gen 1

Gen 2

Page 39: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Now there is congestion.

Locational Marginal Pricing

Slide 39

10 MW ($4 per MWh)

20 MW ($2 per MWh)

10 MW

4 MW constraint

Gen 1

Gen 2

Page 40: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Locational Marginal Pricing

Slide 40

10 MW ($4 per MWh)

20 MW ($2 per MWh)

10 MW

With congestion, LMPs are different.

4 MW constraint

Gen 1

Gen 2

Page 41: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Charges to Load

LMP MW

$4 10 $40

Total $40

Locational Marginal Pricing

Payment to Resources

LMP MW

$4 6 $ 24

$2 4 $8

Total $32

Slide 41

Example: Congestion

Gen 1

Gen 2

Page 42: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Rent

$40

$32

$8

Payment to Resources

Congestion Rent used to fund Congestion Revenue Rights (CRRs) Charges to

Load

Slide 42

Page 43: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

LMPs and Settlement Point Prices

• LMPs at Electrical Buses

• Settlement Points used for financial

settlement

• Settlement Point Prices calculated

using LMPs

Settlement Point Price

LMP1

LMP2

LMP3

LMP4

LMP5

Electrical

Buses

Slide 43

Page 44: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

44

Additional Real-Time pricing component…

• Reserve Price Adder: the economic value of reserves

that are available for energy dispatch in Real-Time

• LMPs and Reserve Price Adders are used together to

form SPPs in Real-Time

LMPs are location-specific. Reserve Price Adders represent the value of

reserves ERCOT-wide.

Page 45: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Slide 45

How often are LMPs & Settlement Point Prices calculated?

LMPs and Settlement Point Prices

• Every Hour

LMPs and Reserve Price Adders

• Every 5 minutes*

Settlement Point Prices

• Every 15 minutes

* LMPs and Reserve Price Adders generated at each SCED cycle (possibly more often than 5 minutes)

Page 46: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Slide 46

Three Types of Settlement Points:

Resource

Nodes

Load

Zones Hubs

Page 47: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

What is a Resource Node?

An Electrical Bus where a Resource’s

measured output is settled

Slide 47

Resource Electrical Bus

Page 48: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Day-Ahead Market

LMP at the Resource Node

Real-Time Operations

Time-Weighted Average of

LMPs at the Resource Node

Time-Weighted Average of

Reserve Price Adders

Resource Electrical Bus

Slide 48

Settlement Point Prices for Resource Nodes

+

Page 49: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

What is a Load Zone?

A group of Electrical Buses

assigned to the same Load Zone

All Load must be assigned to a Load Zone for Settlement purposes

Slide 49

Page 50: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Settlement Point Price for Load Zones

Day-Ahead Market

Load-Weighted Average of LMPs

in Load Zone

Real-Time Operations

Load-Weighted and Time-Weighted

Averages of LMPs in Load Zone

Time-Weighted Average of

Reserve Price Adders

Slide 50

+

Page 51: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Three types of Load Zones

• Competitive Load Zones

• Non Opt-in Entity Load Zones

• DC Tie Load Zones

Slide 51

Page 52: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Competitive Load Zones

• North

• South

• West

• Houston

Slide 52

2003 Congestion Management zones

Page 53: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

Non Opt-in Entity Load Zones

Established by one or more NOIE(s)

Some large NOIEs required to

establish own NOIE Load Zones

NOIEs that don’t establish NOIE Load Zone

are assigned to Competitive Load Zone

Slide 53

Page 54: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

DC Tie Load Zones

• Used to settle exports across

DC Ties

• One for each DC Tie

• Contains only the electrical

bus connected to the DC Tie.

All Load must be assigned to a Load Zone for Settlement purposes

Slide 54

Page 55: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Settlement Point Prices

What is a Hub?

• Group of 345kV Hub-buses

• Defined by Protocols

Slide 55

Hub

Page 56: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Four Regional Hubs

• North

• West

• South

• Houston

Two Average Hubs

ERCOT Hub Average

ERCOT Bus Average

Settlement Point Prices

Six Hubs in ERCOT Market

Slide 56

Page 57: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Hub

Settlement Point Price for Hubs

Day-Ahead Market

Simple average of LMPs

at Hub Buses in each Hub

Real-Time Operations

Simple average of Time-Weighted Average

LMPs at the Hub Buses in the Hub

Time-Weighted Average of

Reserve Price Adders

Settlement Point Prices

Slide 57

+

Page 58: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

LMP Contour Map

• Day-Ahead

Market SPPs

• Real-Time LMPs

• Real-Time SPPs

Slide 58

Page 59: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Operations

Page 60: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Operations

Nodal Market Operations

Market Components

Slide 60

Page 61: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Operations

Congestion Revenue Rights

Page 62: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Overview

Topics in this lesson . . .

• Purpose of CRRs

• CRR Account Holders

• Types of CRRs

• How CRRs are acquired

• Settlements

• Market Information System

Slide 62

Page 63: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

You Are Here!

Slide 63

Page 64: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Purpose of Congestion Revenue Rights

• Financial instruments

• Hedge against congestion costs

• Financial investment

• Payment or charge when

Grid is congested

Congestion Revenue Rights

A CRR is not a right to

deliver physical energy

Slide 64

Page 65: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Costs

Congestion Cost exposure

Congestion costs are built in to the Settlement Point prices.

Resource Node A

Resource Node B

$30/MWh $40/MWh

$45/MWh

Load Zone

Slide 65

Page 66: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights

Introducing a new player:

CRR Account Holder

Slide 66

Page 67: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights

To own CRRs, Market Participants:

• Must be registered with ERCOT

• Must qualify as CRR Account Holders

Slide 67

Page 68: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights

Barred from owning CRRs:

• TSPs & DSPs

• ERCOT

Slide 68

Page 69: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights as Financial Instruments

• Designated point of injection (source)

and point of withdrawal (sink)

• Settlement based on difference

between sink and source Settlement

Point Prices

• Two Instruments:

• PTP Options – payment only

• PTP Obligations – payment or charge

Point-to-Point Congestion

Revenue Rights

Congestion Revenue Rights

Slide 69

Page 70: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

$5/MWh

$10/MWh

$15/MWh

Source A

Source C

Sink B

Obligation AB Payment = $5.00

Obligation CB Payment = -$5.00

Point-to-Point (PTP) Obligations

Congestion Revenue Rights

Slide 70

?

Page 71: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Option AB Payment = $5.00

Option CB Payment = $0.00

$5/MWh

$15/MWh

Source A

Source C

Sink B

Point-to-Point (PTP) Options

Congestion Revenue Rights

?

Slide 71

$10/MWh

Page 72: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights

Three ways of acquiring CRRs:

• CRR Auction

• Allocation (Special Case)

• Bilateral Trades

Auction

Allocation

Trade

CRRs

Slide 72

Page 73: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights

Slide 73

CRRs are auctioned and allocated by:

• Time-of-Use Blocks

• One month strips

Page 74: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

CRR Auction

• Monthly and Semi-Annual Auctions

• Based on Network Operations Model

Congestion Revenue Rights

Slide 74

Page 75: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Allocation of CRRs

Pre-Assigned CRRs (PCRRs)

• Allocated to Non-Opt-In Entities (NOIEs)

• Based on long-term supply contracts

• May be allocated as Options or Obligations

• No charge or a percentage of the Auction clearing price

Congestion Revenue Rights

Slide 75

Page 76: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Trading CRRs Bilaterally

• PTP Options

• PTP Obligations

• Characteristics remain unchanged

• Both parties must meet credit requirements.

Congestion Revenue Rights

Slide 76

Page 77: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

CRR Settlements

Three Settlement Processes

• CRR Auction Settlement

• CRR Settlement

• CRR Balancing Account

Congestion Revenue Rights

Slide 77

Page 78: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Congestion Revenue Rights Settlements

CRR Auction Settlements

Settlements

Payments

Charges

Slide 78

Page 79: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

CRR Auction Settlements Timeline

Congestion Revenue Rights

Slide 79

Auction Completed Day 1* Day 3** Day 4**

Auction Invoice

Payments Due to ERCOT

Payments Due to CRR Account Holders

Auction Results

Day 2** Day 5***

** Bank Business Day

*** Business Day and Bank Business Day

* Business Day

Page 80: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

CRR Auction Settlement

Congestion Revenue Rights

Slide 80

Monthly

CRR Auction

Revenues

+

PCRR Revenues

Pay to QSEs

representing Load

Page 81: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

CRR Settlement

Congestion Revenue Rights Settlements

CRRs are settled in the Day-Ahead Market

Payments

Charges

Slide 81

Page 82: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Payment due to

CRR Account Holders

Hourly

CRR Settlement

Congestion Revenue Rights

Slide 82

Page 83: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Payment due to

CRR Account Holders

Hourly

CRR Settlement

Congestion Revenue Rights

may be short paid

in some hours

Slide 83

Page 84: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Payment due to

CRR Account Holders

Monthly Pay to QSEs

representing Load

Congestion Revenue Rights

CRR Balancing Account

Slide 84

Page 85: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Payment due to

CRR Account Holders

Congestion Revenue Rights

CRR Balancing Account

Monthly

Slide 85

X

may remain

short paid

Page 86: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

Posted after each Auction:

Slide 86

• CRRs awarded

• CRR Account Holders

• Auction clearing prices

• CRR Bids and offers

Page 87: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Operations

Day-Ahead Market

Page 88: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Overview

Topics in this lesson . . .

• Purpose of Day-Ahead Market

• Market Participants

• Day-Ahead Market Process

• Process Inputs and Outputs

• Settlements

• Market Information System

Slide 88

Page 89: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

You Are Here!

Slide 89

Page 90: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

Purpose of the Day-Ahead Market

• Centralized Forward Market

• Buy and sell Energy

• Sell Ancillary Services to ERCOT

• Forward market provides price

certainty

Slide 90

Page 91: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

Only QSEs participate in the

Day-Ahead Market.

Slide 91

Page 92: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

CRRs are settled with Day-Ahead Market Prices

Slide 92

Page 93: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

When does the Day-Ahead Market occur?

• Market opens at 0600

• Clearing Process begins at 1000

• Results posted by 1330

Slide 93

06:00 13:30 00:00

Page 94: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

A Bid is a proposal to buy:

• A Product

• At a Location

• For a Price

An Offer is a proposal to

sell:

• A Product

• At a Location

• For a Price

Energy

LoadZone 4

$40

Day-Ahead Market

Slide 94

Page 95: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Day-Ahead Market

Day-Ahead Market

Slide 95

Page 96: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Day-Ahead Market

Day-Ahead Market

Slide 96

Page 97: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Day-Ahead Market

Day-Ahead Market

Types of Offers: • Three-Part Supply Offer • Ancillary Service (AS) Offer • Day-Ahead Market Energy-Only Offer

Slide 97

Page 98: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Startup Offer Minimum-Energy Offer Energy Offer Curve

$ / MWh (at LSL) $ / MWh (above LSL)

$ / Start

Three-Part Supply Offer

Day-Ahead Market

Energy Offer Curve can be submitted without Start-up or Minimum Energy Offers

Slide 98

Page 99: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Ancillary Service (AS) Offers:

• Resource specific

– Regulation Reserve

– Responsive Reserve

– Non-Spinning Reserve

• A Resource may be offered

– For multiple Ancillary Services

– For Energy and Ancillary Services

Day-Ahead Market

Ancillary Service Offer

Slide 99

Page 100: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market Energy-Only Offer

• Proposal to sell energy in DAM

• Offered at any Settlement Point

DAM Energy-Only Offer

h

Day-Ahead Market

Slide 100

Valid only in the Day-Ahead Market

Financial obligation in Real-Time

Slide 100

Page 101: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Day-Ahead Market

Day-Ahead Market

Slide 101

Types of Bids: • Energy Bid • PTP Obligation Bid

Page 102: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market Energy Bid

• Proposal to buy energy

• Submitted at any Settlement Point

DAM Energy Bid

h

Day-Ahead Market

Slide 102

Valid only in the Day-Ahead Market

Financial credit in Real-Time

Page 103: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market PTP Obligation Bids

• Purpose of DAM PTP Obligations

• Hedge against congestion

costs in Real-Time

• Charge or payment when

Grid is congested in Real-Time

Day-Ahead Market

Slide 103

Page 104: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Day-Ahead Market

Day-Ahead Market PTP Obligation Bids

• Like coupled Energy Bid and Energy Offer

• Purchased at DAM Settlement Point Price Spread

• Settled at Real-Time Settlement Point Price Spread

DAM PTP Obligation can result in a payment or charge

Source A

Sink B

Energy Offer

Energy Bid

PTP Obligation

Slide 104

Page 105: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market PTP Obligations

The Day-Ahead Market

QSE charge in Day Ahead Market = $2

QSE payment in Real Time = $7 ?

?

Slide 105

$10/MWh $12/MWh

Source A Sink B

PTP Obligation

DAM :

$8/MWh $15/MWh Real-Time :

Settlement Point Prices

Page 106: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Day-Ahead Market

Slide 106

CRR Auction Day-Ahead Market Real-Time

Page 107: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Day-Ahead Market

Slide 107

Page 108: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

The Current Operating Plan (COP)

• Anticipated Resource operating conditions

• Resource Status

• Resource Limits

• Ancillary Service Commitments

• Submitted by QSE

QSE must maintain the COP for each

hour of the next 7 days

Day-Ahead Market

Slide 108

Page 109: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Day-Ahead Market

Slide 109

Page 110: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Network Model in the Day-Ahead Market

• Day-Ahead Market does

not solve reliability issues

• System must support the

Day-Ahead Market solution

The Network Operations Model ensures that DAM

solution respects system limits

Slide 110

Page 111: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Day-Ahead Market

Slide 111

Page 112: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Day-Ahead Market

Slide 112

Cleared Offers = Costs

Cleared Bids = Revenues

Page 113: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Day-Ahead Market clearing process

Slide 113

Maximize

The Gap

Bid-based Revenues

Offer-based Costs

Page 114: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Offer-based Costs

Maximize

The Gap

Bid-based Revenues

The Day-Ahead Market is a Co-optimized Market

Day-Ahead Market

The Day-Ahead Market clearing process

Slide 114

Energy & Ancillary Service Costs

Page 115: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

The Day-Ahead Market

Slide 115

Page 116: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market

After Day-Ahead Market

• QSEs may update COP

• Awarded Energy Offers

• Ancillary Service Commitments

• QSEs may submit Trades

Slide 116

Page 117: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Trades

• QSE-QSE transactions

• Transfers financial responsibility

• Types

• Capacity

• Energy

• Ancillary Service

Day-Ahead Market

Trades are used only in Settlements

Slide 117

Page 118: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Market Settlements

Payments

Charges

Slide 118

Page 119: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Settlement Timeline

• Daily statements include

• Payments due

• Charges incurred

Day-Ahead Market

Slide 119

Operating Day

Day 2 Day Ahead

DAM Statement

Day 1

Page 120: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Single Daily Settlement Invoice

• Daily invoices include

• DAM Statements

• RTM Statements

Day-Ahead Market

Slide 120

Operating Day

Day 5 Day 6

ERCOT Issues DAM

Statement & Invoice Payment Due

(to ERCOT)

Payment Due (to Market Participant)

Day 2

1700 1700

Day Ahead

Invoice Day + 2

Invoice Day + 3

ERCOT Issues Invoice • DAM Statements • RTM Statements

Payment Due (to ERCOT)

Payment Due (to Market Participant)

Invoice Day

1700 1700

Page 121: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

Posted by 0600 Day-Ahead:

Slide 121

• Network Operations Model

• Weather Assumptions

• Load Forecasts (next 7 days)

• Forecasted Load Profiles

Page 122: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

Slide 122

Posted by 1330 Day-Ahead:

• LMPs

• Settlement Point Prices

• MCPCs for each Ancillary Service

• Energy bought and sold

Page 123: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Operations

Reliability Unit Commitment

Page 124: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Overview

Topics in this lesson . . .

• Purpose of Reliability Unit Commitment (RUC)

• Market Participants involved

• The RUC Process

• Settlements

• Capacity Shortfall

• Market Information System

Slide 124

Page 125: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

You Are Here!

Slide 125

Page 126: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Purpose of Reliability Unit Commitment (RUC)

It ensures:

• Enough capacity is committed to serve

the forecasted load

• Committed capacity is in the right locations

Slide 126

Page 127: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Operational impacts on:

QSEs with Resources

Slide 127

Page 128: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Funds collected from:

• Capacity-Short QSEs

• QSEs representing Load

Slide 128

Page 129: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

The Reliability Unit Commitment Process

Slide 129

Page 130: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Committing Enough Capacity

Slide 130

Page 131: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Committing Capacity in the Right Locations

Slide 131

Page 132: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

What if ERCOT must commit additional capacity?

Slide 132

Page 133: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Potential Results of RUC Process:

Slide 133

• Resource Commitments

• Resource Decommitments

• No additional Commitments

Page 134: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

When does Reliability Unit Commitment (RUC) occur?

Day-Ahead Reliability Unit Commitment (DRUC)

Hourly Reliability Unit Commitment (HRUC)

Slide 134

HRUC DRUC

Page 135: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Make-Whole

Payments

Reliability Unit Commitment Settlements

*RUC-Committed Resources

Capacity

Short

Charges

Slide 135

Make-Whole

Uplift

Charges

Page 136: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Make-Whole Payments

RUC-committed Resources recover their commitment costs

Slide 136

Resource Costs

Resource Revenues

$

RUC Make-Whole Payment

Make-Whole Payment

Page 137: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Capacity Short Charge

Capacity Obligations

Capacity Supply

Capacity Shortfall

Slide 137

QSEs with Capacity Shortfall are assessed Capacity Short Charges

Page 138: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

What is included in the QSE’s capacity obligation?

• Load (Adjusted Metered Load )

• Capacity Trades where the QSE is a seller

• Energy Trade where the QSE is a seller

• Cleared DAM Energy Offer

Capacity Required to meet QSE Obligations

Slide 138

Capacity Obligations

Page 139: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

How can a QSE arrange to meet these obligations?

• Show capacity from its Resources in its COP

• Capacity Trades where the QSE is a buyer

• Energy Trades where the QSE is a buyer

• Cleared DAM Energy bids

Capacity arranged by QSE

Slide 139

Capacity Supply

Page 140: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

To Minimize Capacity Short Charges…

QSE must arrange for enough Capacity to meet Obligations

Capacity Obligations

Capacity Supply

Capacity Shortfall

Slide 140

Page 141: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Revenues may not be enough for make-Whole Payments

Difference uplifted to QSEs representing Load

Slide 141

Gen 1

RUC

Make-Whole

Payments

Make-Whole

Uplift

Charges

Capacity

Shortfall

Charges Capacity

Short

Page 142: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Reliability Unit Commitment

Slide 142

Make-Whole

Payments Capacity

Short

Charges

Make-Whole

Uplift

Charges

RUC Payments and Charges are included in Real-Time Settlements

Page 143: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

Posted after process completion:

Slide 143

• Resources committed

• Resources decommitted

• Active transmission constraints

Page 144: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Nodal Market Operations

Real-Time Operations

Page 145: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Overview

Topics in this lesson . . .

• Purpose of Real-Time Operations

• Market Participants

• Real-Time Operations Process

• Security Constrained Economic Dispatch

• Load Frequency Control

• Settlements

• Market Information System

Slide 145

Page 146: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

You Are Here!

Slide 146

Page 147: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

Purpose of Real-Time Operations

• Manage reliability

• Match generation with demand

• Operate transmission system

within established limits

• Operate the system at least cost

Slide 147

Page 148: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

ERCOT provides dispatch instructions

to QSEs with Resources.

Slide 148

Page 149: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

ERCOT may also provide

dispatch instructions to TSPs.

Slide 149

Page 150: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

When do Real-Time Operations occur?

• Operating Period

• Includes Operating Hour and Hour-Ahead

Slide 150

60 mins.

prior to

Operating Hour

00:00

Page 151: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

The Operating Period includes:

• Operating Hour - Real-Time dispatch of energy

• Hour-Ahead – Preparations for Real-Time Operations

Slide 151

60 mins.

prior to

Operating Hour

00:00

Page 152: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

Slide 152

Page 153: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

• Network Security Analysis

identifies transmission

constraints

• Security Constrained

Economic Dispatch (SCED)

determines least-cost

solution

Network Security Analysis

Security Constrained

Economic Dispatch

Network Security Analysis and SCED

Slide 153

Real-Time Operations

Page 154: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

Provide Real-Time system data

Slide 154

Page 155: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

Identify Constraints, both Transmission & Resource

Transmission Constraints & Resource Dispatch Limits

Slide 155

Page 156: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

SCED evaluates Offers to determine least-cost solution

Transmission Constraints & Resource Dispatch Limits

Slide 156

Page 157: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

SCED uses Energy Offer Curves:

Energy Offer Curve Submitted by QSEs:

• Three-Part Supply Offer

• Stand Alone Energy Offer Curve

During:

• Day-Ahead Market

• Adjustment Period

Real-Time Operations

Slide 157

Page 158: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

SCED produces Prices and Dispatch Instructions

Slide 158

Page 159: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

How often does all this happen?

At least

every 5

minutes

Slide 159

Page 160: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations

Real-Time Price Calculations

Every 5 minutes (when SCED runs)

LMPs

• Electrical buses

Every 15 minutes

Settlement Point Prices

• Resource Nodes

• Load Zones

• Hubs

Slide 160

Reserve Price Adders

• ERCOT-wide

Page 161: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

SCED

Real-Time Operations

SCED Dispatch Instructions

• Every 5 minutes

• Based on economics

SCED SCED

5 minutes 5 minutes

Base point

Base point

Base point

Slide 161

Page 162: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Load Frequency Control (LFC)

• Matches generation with demand

• Responds to frequency deviations

• Deploys Regulation Reserve Service

Frequency (Hz)

Real-Time Operations

5 minutes 5 minutes

Base point

Base point

Base point

Slide 162

Page 163: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Operations Settlements

Payment for Net Supply

Charge for Net Obligation

Slide 163

Page 164: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

• Metered Generation

• DAM Purchase

• Trades as Buyer

Examples

•__________________

•__________________

•__________________

Real-Time Operations Settlements

Slide 164

Page 165: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

•Metered Load

•DAM Sale

•Trades as Seller

Examples

•__________________

•__________________

•__________________

Real-Time Operations Settlements

Slide 165

Page 166: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Real-Time Settlement Timeline

• Daily statements include

• Payments due

• Charges incurred

Slide 166

Day 180

Operating Day

Day 5

Initial Statement

Final Statement

True-Up Statement

Day 55

Real-Time Operations Settlements

Page 167: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Single Daily Settlement Invoice

• Daily invoices include

• DAM Statement

• RTM Statements

Slide 167

Operating Day

Day 5 Day 6

ERCOT Issues DAM

Statement & Invoice Payment Due

(to ERCOT)

Payment Due (to Market Participant)

Day 2

1700 1700

Day Ahead

Invoice Day + 2

Invoice Day + 3

ERCOT Issues Invoice • DAM • RTM Initial • RTM Final • RTM True-up

Payment Due (to ERCOT)

Payment Due (to Market Participant)

Invoice Day

1700 1700

Real-Time Operations Settlements

Page 168: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Market Information System

Posted after completion of SCED:

Slide 168

• Locational Marginal Prices

• Settlement Point Prices

• Active transmission constraints

Page 169: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Course Conclusion

Page 170: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Additional Resources

ERCOT Nodal Market Protocols

http://www.ercot.com/mktrules/nprotocols/

ERCOT Training

http://www.ercot.com/services/training/

Market Education Contact

[email protected]

Slide 170

Page 171: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Appendix: Pathways to Referenced Data

Access Market Information System from ERCOT public website:

Digital

Certificate

required

Slide 171

Page 172: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

LMP Contour Map: http://www.ercot.com/content/cdr/contours/rtmLmpHg.html

Appendix: Pathways to Referenced Data

Slide 172

Page 173: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Public access:

http://www.ercot.com/mktinfo/crr/index.html

CRR Auction section, Auction Results posting (zip folder) • CRRs, CRRAHs awarded, and Auction Clearing Prices

o Common_MarketResults file (CSV or XML format)

• CRR Bids and Offers

o Common_AuctionBidsAndOffers file (CSV or XML format)

Appendix: Pathways to Referenced Data

CRR Auction Results

Slide 173

Page 174: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Appendix: Pathways to Referenced Data

CRR Auction Results via Market Information System

Slide 174

Page 175: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Day-Ahead Network Operations Model (posted by 0600)

Slide 175

Appendix: Pathways to Referenced Data

Page 176: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Posted by 0600 Day-Ahead:

Slide 176

• Weather assumptions

o Public access:

http://www.ercot.com/mktinfo/dam/index.html, under

System Conditions

o MIS Secure: Markets > Day-Ahead Market > Day-Ahead

Public Information

• Forecasted Load Profiles

o Public access:

http://www.ercot.com/mktinfo/loadprofile/index.html,

under Current Information

o MIS Secure: Markets > Load Profiling > Load Profiling

Reports and Extracts (Public)

Appendix: Pathways to Referenced Data

Page 177: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Posted by 0600 Day-Ahead:

Slide 177

• Load Forecasts (next 7 days)

o Public access:

http://www.ercot.com/gridinfo/load/index.html, under

Current Information

o MIS Secure: Grid > Forecasts > Significant System

Conditions

• List of transmission constraints

o Public access:

http://www.ercot.com/gridinfo/generation/index.html,

under Current Information

o MIS Secure: Grid > Generation > Public Generation

Information > Weekly RUC Active and Binding

Transmission Constraints

Appendix: Pathways to Referenced Data

Page 178: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Slide 178

Posted by 1330 Day-Ahead:

• DAM Hourly LMPs

• DAM Settlement Point Prices

• DAM Clearing Prices for Capacity

• DAM Total Energy Purchased

• DAM Total Energy sold

o Public access:

http://www.ercot.com/mktinfo/dam/index.html, under

Day-Ahead Market Results Reports

o MIS Secure: Markets > Day-Ahead Market > Day-

Ahead Market Results

Appendix: Pathways to Referenced Data

Page 179: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Posted after RUC completion:

Slide 179

• RUC Committed or Decommitted Resources

o MIS Secure: Grid > Generation > Reliability

Unit Commitment

• Active transmission constraints

o Public access:

http://www.ercot.com/gridinfo/generation/ind

ex.html under Current Information

o MIS Secure: Grid > Generation > Public

Generation Information

Appendix: Pathways to Referenced Data

Page 180: ERCOT Nodal 101 · The ERCOT Board has approved Guidelines for Members of ERCOT Committees, subcommittees, and working Groups to be reviewed and followed by each market participant

Posted after completion of SCED:

Slide 180

• Locational Marginal Prices

• Settlement Point Prices

o Public access:

http://www.ercot.com/mktinfo/rtm/index.html, under

Real-Time Prices Reports

o MIS Secure: Markets > Real-Time Market > Real-

Time Prices

• Active transmission constraints

o MIS Secure: Markets > Real-Time Market > Real-

Time Operations

Appendix: Pathways to Referenced Data