+ All Categories
Home > Documents > ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Date post: 24-Dec-2015
Category:
Upload: noah-booth
View: 216 times
Download: 0 times
Share this document with a friend
Popular Tags:
119
ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES
Transcript
Page 1: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ERLDC

Power System Operation Corporation

SHARING OF ISTS TRANSMISSION CHARGES

& LOSSES

Page 2: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

INTRODUCTION

Page 3: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

EVOLUTION OF TRANSMISSION PRICINGEVOLUTION OF TRANSMISSION PRICING

04/19/23 3

• (Usage & Distance/Direction sensitivity based)

Page 4: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

PARADIGM CHANGE: EA-2003 AND NEP

► EA-2003: Facilitate competitive markets► Generation de-licensed► Non-discriminatory open access► Efficient, coordinated and economical development of ISTS:

Responsibility of CTU

► National Electricity Policy► Section 5.3.2 and 5.3.5► Prior agreement with beneficiaries not a pre-condition for ISTS

development► CTU/STU should undertake network expansion after

identifying the requirements in consultation with stakeholders and taking up the execution after due regulatory approvals.

► Transmission tariff to be made sensitive distance, direction and quantum of flow

► CERC has released the Grant of Regulatory Approval for execution of Inter-State Transmission Scheme to CTU regulations Dtd.31/05/10

Page 5: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

5 04/19/23

TARIFF POLICY ON TRANSMISSION PRICING

►Section 7.1 (2), (3) & (4) and Section 7.2

►Sensitive to distance, direction and quantum

►Sharing in proportion to utilization

►Facilitate planned development/augmentation

►Discourage non-optimal investment

►Prior agreement not pre-condition

►Apportionment of losses- distance and direction sensitive

Page 6: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

6 04/19/23 POWERGRID

NEED FOR CHANGE IN PRICING FRAMEWORK►Synchronous integration of Regions- Meshed Grid

►Changes caused by law and policy

►Open Access and Competitive Power Markets►Pricing Inefficiencies, Market Players’ concern

►National Grid / Trans-regional ISGS►Changing Network utilization►Agreement of beneficiaries a challenge►Ab-initio identification beneficiaries difficult

Page 7: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 7

Changing Structure of Indian Power Sector and development of Electricity Markets

Page 8: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

VERTICALLY INTEGRATED UTILITY

GENERATION

DISTRIBUTION

TRANSMISSION

Page 9: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

TR

AN

SM

ISS

ION

SE

RV

ICE

PR

OV

IDE

R (

TS

P-1

)

UT

ILIT

Y (

U-1

)

ONE UTILITY (U-1) WITH ONE TRANSMISSION SERVICE PROVIDER ( TSP-1 )

Transmission Assets (TA-1 to n)

Page 10: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ONE REGIONAL GRID

TWO UTILITIES WITH ONE TRANSMISSION SERVICE PROVIDER (TSP-1)

TR

AN

SM

ISS

ION

SE

RV

ICE

PR

OV

IDE

R (

TS

P-1

)

UTILITY (U-2)

UTILITY (U-1)Transmission Assets (TA – 1 to n)

Page 11: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ONE REGIONAL GRID

MULTIPLE UTILITIES WITH ONE TRANSMISSION SERVICE PROVIDER (TSP-1)

TR

AN

SM

ISS

ION

SE

RV

ICE

PR

OV

IDE

R (

TS

P-1

)

UTILITY (U-2)

UTILITY (U-1)

Transmission Assets (TA – 1 to n)

UTILITY (U-4)

UTILITY (U-3)

UTILITY (U-n)

Page 12: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ONE REGIONAL GRID

MULTIPLE UTILITIES WITH TWO TRANSMISSION SERVICE PROVIDERS

TRANSMISSION SERVICE

PROVIDER (TSP – 1)

Transmission Assets (T1A 1-n)

UTILITY (U-2)

UTILITY (U-1)

UTILITY (U-4)

UTILITY (U-3)

UTILITY (U-n)

TRANSMISSION SERVICE

PROVIDER (TSP – 2)

Transmission Assets (T2A 1-n)

Page 13: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ONE REGIONAL GRID

MULTIPLE UTILITIES WITH MULTIPLE TRANSMISSION SERVICE PROVIDERS

TSP – 1Transmission Assets (T1A 1-n)

UTILITY (U-2)

UTILITY (U-1)

UTILITY (U-4)

UTILITY (U-3)

UTILITY (U-n)

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

Page 14: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DISCOMS: COMPLEXITY INCREASED FURTHER(D-1 TO D-N): DISCOMS PAY DIRECTLY TO TSPS

ONE REGIONAL GRID

TSP – 1Transmission Assets (T1A 1-n)

U-2

U-1

U-4

U-3

U-n

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

Page 15: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

MULTIPLE REGIONS

REGIONAL GRID -1

TSP – 1Transmission Assets (T1A 1-n)

U-2

U-1

U-4

U-3

U-n

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

REGIONAL GRID -2

TSP – 1Transmission Assets (T1A 1-n)

U-2

U-1

U-4

U-3

U-n

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

Inter-Regional Interconnections

Page 16: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

TSPS IN ONE REGION HAVING CUSTOMERS IN ANOTHER REGION ALSO

REGIONAL GRID -1

TSP – 1Transmission Assets (T1A 1-n)

U-2

U-1

U-4

U-3

U-n

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

REGIONAL GRID -2

TSP – 1Transmission Assets (T1A 1-n)

U-2

U-1

U-4

U-3

U-n

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

Inter-Regional Interconnections

Page 17: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ALTERNATE FEASIBLE MODEL

TSP – 1Transmission Assets (T1A 1-n)

TSP – 2Transmission Assets (T2A 1-n)

TSP – mTransmission Assets (TmA 1-n)

TSP – 3Transmission Assets (T3A 1-n)

U-2

U-1

U-4

U-3

U-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-nAGENCY

FORBILLING

&COLLECTION

U-2

U-1

U-4

U-3

U-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

D-1 D-n

Reg

ion

-1

Reg

ion

-2

Page 18: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

18

FOCUS

►Economic/Regulatory Objective►Operational Efficiency

► Minimisation of Present Operating Cost►Dynamic Efficiency

► Long-term development of system►Allocative Efficiency

► Equity and fairness in assigning costs

Page 19: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

19 04/19/23 POWERGRID

ALLOCATIVE EFFICIENCY - OBJECTIVES

►Simplicity►Non-discriminatory/Equitable►Predictable►Strong signal for efficiency, location and

expansion►Ease of regulation and administration

►Dispute free Implementation

►Minimize Cross Subsidies►Transparency of Procedures►Continuity – Smooth transition from existing

practice

Page 20: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Transmission Pricing Paradigms

Page 21: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Paradigm

►Rolled in Paradigm► Postage stamp► Contract Path Method► MW-Mile

► Distance based

► Power flow based (several variant such as MM, DFM, ZCF)

► Incremental Transmission Pricing Paradigm► Long/Short Run Incremental/Marginal

►Composite embedded / incremental transmission Pricing Paradigm

Page 22: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

22 04/19/23 POWERGRID

Comparison of different methods in Transmission Pricing Paradigm

► Postage Stamp Method – ++ Simple, familiar, most widely used in developing market -- insensitive to distance & direction

► Zonal Postage Stamp Method ++ sensitive to distance and direction -- complex, difficult to implement, load flow

condition varies with dispatch scenario

► Contract Path Methodology++ Sensitive to distance -- provides wrong economic signal, based on

fictitious path, power flow on parallel path is ignored

Page 23: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

► Distance Based MW-Mile Methodology++ Simple, sensitive to distance -- based on physical distance, not on actual power flow

► Power Flow Based MW- Methodology ( MM/ DFM/ZCF)/Power Tracing

++ sensitive to distance, takes planning and usage of network in consideration

-- issue of net vs absolute power flow, absolute ignores directional sensitiveness, varies with dispatch scenario

► Point tariff, Nodal Pricing or Locational Marginal Pricing (LMP)

++Provides economic signals, suitable for developed/saturated market -- complex, not suitable for developing market, losses forms the part of transmission pricing, based on MWh

not on MW.

COMPARISON OF DIFFERENT METHODS IN TRANSMISSION PRICING PARADIGM

Page 24: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

SHARING OF INTER-STATE TRANSMISSION CHARGES AND LOSSES-REGULATIONS

Page 25: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DEFINITIONS

Page 26: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DEFINITIONS

► Designated ISTS Customers (‘DIC’s) Users of any segments/elements of the ISTS and shall include all generators, STUs, SEBs or load serving entities directly connected to the ISTS including Bulk Consumer and any other entity/person

► Implementing Agency (IA) The agency designated by the Commission to undertake the estimation of allocation of transmission charges and transmission losses at various nodes/zones for the Application Period along with other functions

► Approved Injection Injection in MW vetted by IA for the DIC for each representative block of months, peak and other than peak scenarios at the ex-bus of the generator or any other injection point of the Designated ISTS Customer into the ISTS, and determined based on the generation data submitted by the DIC incorporating total injection into the grid, considering the long term and medium term contracts;

Page 27: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DEFINITIONS► Approved Additional Medium Term Injection means the

additional injection, as per the MTOA approved by CTU after submission of data to NLDC by the DIC over and above the Approved Injection for the DIC for each representative block of months, peak and off-peak scenarios at the ex-bus of the generator or any other injection point of the DIC into the ISTS

► Approved Short Term Injection The injection, as per the STOA approved by RLDC /RLDC & including PX

► Similarly we have Approved Withdrawal (simultaenous withdrawal), Approved additional MT withdrawal & Approved ST withdrawal

► Deemed Inter State Transmission System (Deemed ISTS) Transmission system which has regulatory approval of the Commission as being used for interstate transmission of power and qualified as ISTS

► Point of Connection (PoC) transmission charges Nodal / zonal charges determined using the POC method

Page 28: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DEFINITIONS

►Yearly Transmission Charge (YTC) Annual Transmission Charges for existing lines determined by the Commission in accordance with the Terms and Conditions of Tariff Regulations or adopted in the case of tariff based competitive bidding in accordance with the Transmission License Regulations and for new lines based on benchmarked capital costs

►Uniform Charge Charged determined by dividing the YTC of the ISTS Licensees by the sum of the Approved Injection and Approved Withdrawal from the grid(postage stamp charge)

Page 29: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

SCOPE OF THE REGULATIONS► Power Stations / Generating Stations that are regional

entities as defined in the Indian Electricity Grid Code (IEGC)

► SEBs/ STUs connected with ISTS (on behalf of distribution companies, generators and other bulk customers connected to the transmission system owned by the SEB/STU/intrastate transmission licensee)

► Any bulk consumer directly connected with the ISTS

► Any designated entity representing a physically connected entity as per clauses above

► Regional Entity Those who are in the RLDC control area and whose metering and energy accounting is done at the regional level

Page 30: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

PRINCIPAL/MECHANISM FOR SHARING OF ISTS CHARGES AND LOSSES

►PRINCIPLES:►Load Flow Based Method►Point of Connection Charging Method

►MECHANISM ►PoC Charges and Losses in advance

►Based on Technical and Commercial Information provided by DICs, ISTS Transmission Licensees, NLDC, RLDCs and SLDCs

►Charges for LTA/MTOA : Rs/MW/Month►Charges for STOA : Rs/MW/Hour

Page 31: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

PROCESS FOR DETERMINATION OF POC CHARGES & LOSSES

► Data Collection Regulation 7(1)► DICs, Transmission Licensees to submit Basic Network

Data

► Network Data for Load Flow Analysis Regulation 7(1)(b)► Electrical Plant or line upto 132 kV ► Generators connected at 110 kV► Inflow from lower levels generation at that node► Outflow towards lower levels Load at that node

► Dedicated Transmission Lines Regulation 7(1)(c)► Owned and Operated by ISTS………. Included in Basic

Network► Owned and Operated by Generator….Excluded

Page 32: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Data Collection (1)► As per the Regulation and Data Collection Procedure

► All concerned entities to submit► Details of Network Elements

► Generation and Load at various nodes

► Yearly Transmission Charges

► Forecast Injection / Withdrawal

► Additional Medium Term Withdrawal / Injection► By 10th of every month by every DIC

► RPC to send list of certified non-ISTS lines to IA► IA to send the lists to CERC for approval

► YTC of Certified non-ISTS lines to be approved from appropriate commission

Page 33: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

INFORMATION PROCEDURES

►Data to be submitted by DICs►YTC, Basic Network Details of ISTS, Deemed ISTS,

Certified ISTS Lines►Demand or Injection Forecast for each season►On or Before the end of fourth week of November

►Data to be submitted by CTU, Owners of Deemed ISTS and DICs►Entire Network Data for first year of Implementation►Dates and data of commissioning of any new

transmission asset for subsequent years

Page 34: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

INFORMATION PROCEDURES

► Injection and Withdrawal forecast for different blocks of months (Peak and Other than Peak):

Regulation 16(4)

► April to June…………………………… (May 15)► July to September……………………. (August 31)► October to November………………… (October 30)► December to February……………….. (January 15)► March…………………………………… (March 15)

► In case any of the above fall on a Weekend/Public Holiday, the data shall be submitted for working days immediately after the dates indicated.

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 34

Page 35: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

FLOW CHART FOR DATA ACQUISITION

STU/SEBs/CTU

Implementing Agency

Network Parameters Line wise YTC

Designated ISTS Customers

Nodal Injection / Withdrawal

Additional Medium Term Injection / Withdrawal

Approved Injection

Approved Withdrawal

Basic Network

Network Parameters

Page 36: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

► Nodal Generation / Demand Regulation 7(1)(d) / (e)

► Based on Forecast provided by DICs► Forecast should be based on Long Term and Medium Term

Contracts► Forecast Generation to be vetted by IA based on Historic

Generation / Demand.► Changes in Generation /Demand to be Communicated to DICs► In case of conflict validation committee to take final decision

► IA to perform AC Load flow Regulation 7(1)(h) ► To obtain LGB & for achieving convergence adjustments may be

required to be made on vetted generation/demand► Converged Load Flow results to be verified by Validation

Committee Regulation 7(1)(i)

Page 37: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

VALIDATION COMMITTEE

►Nominee from Commission to Chair the Committee

Regulation 7(1)(g)

►Validation Committee Comprises two officials each from:► Implementing Agency► National Load Despatch Centre► Regional Power Committee► Central Transmission Utility► Central Electricity Authority► Central Electricity Regulatory Commission

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 37

Page 38: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

NETWORK TRUNCATION

► Network Truncation by IA Regulation 7(1)(k)

► Upto 400 kV except NER, where it shall be reduced to 132 kV

Annexure I, Clause 2.3

► Power inflow from Lower voltage Level : Generation Node Annexure I, Clause 2.3

► Power outflow from Lower voltage Level : Demand Node Annexure I, Clause 2.3

► AC Load Flow on Truncated Network

Annexure I, Clause 2.3

Page 39: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

COMPUTATION OF POC CHARGES (1)► Average YTC per circuit km(for each voltage level & conductor

configuration) shall be used for computation of chargesRegulation 7(1)(l)

► e.g. 400 KVD/C twin Moose, 400 kV Quad Moose, 400 kV Quad Bersimis etc.,

► YTC of substations to be apportioned in line

Regulation 7(1)(m)► 2/3 to higher voltage lines► 1/3 to lower voltage lines► Apportionment among lines on the basis of length in ckt. kms

► PoC Charges to be computed for 5 blocks of month for peak and other the peak conditions

Page 40: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

COMPUTATION OF POC CHARGES (2)

► Representative Blocks of Months Regulation 7(1)(o)► April to June► July to September► October to November► December to February► March

► Peak Hours : 8hrs Regulation 7(1)(o)

► Other the Peak Hours :16 Hrs

► Average YTC to be apportioned to peak and other than peak based on the no. of hours constituting these periods

Regulation 7(1)(p)

► 50% recovery through Hybrid Methodology and 50% through Uniform Charge Sharing Mechanism(for first two years )Regulation 7(1)(q)

Page 41: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

COMPUTATION OF POC LOSSES

► Loss Allocation Factor to be computed for each season using Hybrid Methodology

Regulation 7(1)(r)

► 50% losses through Hybrid Method and 50% through Uniform Loss Allocation Mechanism(for first two years)

Regulation 7(1)(s)

► Weighted average of LAF for peak and other than peak conditions shall be used

Regulation 7(1)(s)

► Loss Application as per the Procedure prepared by NLDC

Page 42: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ZONING► Criteria for Zoning of nodes: Regulations7(1)(t)

► Costs within the same range► Geographically and electrically proximate► Nodes with connectivity to Thermal Generators > 1500 MW or

Hydro Generators > 500 MW to be taken as separate zone.► Demand zones : Sate Control Area► Except NER states where entire region is to be taken as one zone.

► Zonal Charges : Weighted Average of Nodal Charges

Annexure I, Clause 2.2► Revision of Zones in a financial year

► Significant Changes in Power System► Prior approval from commission Regulations7(1)(t)(vi)

► Generating stations connected to ISTS network < 400KV would be charged at zonal charges where physically located

► No transmission charges/losses for solar projects (for the entire useful life) commissioned within next 3 years.

Page 43: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

SPECIFIC CHARGES

► Charges thus determined to the extent of approved injection/withdrawal for each DIC

► In the event of a Designated ISTS Customer failing to provide its requisition for demand or injection for an Application Period, the last demand or injection forecast supplied by the DIC and as adjusted by the Implementing Agency for Load Flow Analysis shall be deemed to be Approved Withdrawal or Approved Injection

► In case the metered MWs (ex-bus) of a power station or the aggregate demand of a Designated ISTS Customer exceeds, in any time block,

(a) In case of generators: The Approved Injection + Approved Additional Medium Term Injection + Approved Short Term Injection or;

(b) In case of demand customers: The Approved Withdrawal + Approved Additional Medium Term Withdrawal + Approved Short Term Demand,

Additional charges would be applicable for deviation

Page 44: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

SPECIFIC CHARGES

► For deviation > 20% in any time block, the DIC shall be required to pay transmission charges for excess generation @ 25% above the zonal POC charges determined for zone where the Designated ISTS Customer is physically located

► Such additional charges would not be applicable in case::

► Rescheduling of the planned maintenance program which is beyond the control of the generator

► Certified by RPC

► Payment on account of additional charges for deviation by the generator shall not be charged to its long term customer and shall be payable by the generator

Page 45: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

SPECIFIC CHARGES

►Even if in case of injection / withdrawal < Approved injection/withdrawal allocated transmission charges to be fully paid

►After declaration of COD of a generator, charges payable by generators for LT supply shall be billed directly to the LT customers based on capacity share in the generating stations

►However, before COD, charges to be borne by generators

►There would be no differentiation between POC charges/losses for LT/MT/ST customers

Page 46: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

IMPLEMENTING AGENCY (IA) (Chapter 8)

►For First Two Years Regulation 18(1)► NLDC shall be Implementing Agency

►Procedures to be prepared by IA► Procedure for Data Collection► Procedure for Loss Sharing► Procedure for Transmission Charge Computation

►Expenses of IA to be included in YTC and approved by Commission Regulation 18(4)

Page 47: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

TREATMENT OF HVDC Annexure I Clause 2.7

►Zero Marginal Participation for HVDC Line► HVDC line flow regulated by power order.

►MP Method can not recover its cost directly.

►HVDC line can be modeled as:► Load at sending end► Generator at receiving end

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 47

Page 48: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Indirect Method for HVDC Cost Allocation

► Compute Transmission Charges for all load and generators with all HVDC lines in service.

► Disconnect HVDC line and again compute new transmission charges for all loads and generators

► Compute difference between nodal charges with or without HVDC.

► Identify nodes which benefits with the presence of HVDC[Benefit = (old cost i.e. base case with injection from Talchar Kolar) minus (new usage cost i.e. with link disconnected)]

► In case benefit –ve same to be collared to zero

► Allocate HVDC line cost to the identified nodes.

Page 49: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Module on Computation of PoC Transmission Charges

National Load Despatch Centre

Power System Operation Corporation

Page 50: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Process Chart for Computation of PoC Charges

Data Collection

Basic Network Preparation

Load Flow Studies

Zoning

Network Reduction

PoC Charges & Losses Computation

Page 51: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Data Collection (2)

►NLDC to specify :► Nodes/group of nodes on which DICs would submit the

forecasted injection/withdrawal.

► IA to specify :► Peak and other than Peak conditions for each representative

blocks for the next application period.

Page 52: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Approved Injection/ Withdrawal

►Approval of Forecasted Injection/Withdrawal on the basis of

► Long Term and Existing Medium Term Contracts► Database of RLDC/NLDC

►Approved Demand/Withdrawal to be notified on the website of IA

►Adjustments in forecasted Injection/withdrawal to be intimated to concerned DIC.

Page 53: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Computation of AC Load Flows

►Seprately for NEW and SR Grid

►Adjustments for converging Load Flow► If Load > Generation

► Pro-rata scaling down of Load

► If Generation > Load► Pro-rata scaling down of Generation

►Validation committee to validate► Converged Load Flow Results► Basic Network► Nodal Injection / Withdrawal

Page 54: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Network Reduction

Reduction upto 400 kV (except NER where the network will be reduced to 132 kV)

► Injection from Lower Voltage : Generation

►Drawal from Lower Voltage : Demand

SoftwareReduced Network

Average YTC after Truing up

PoC Charges and LAF

Page 55: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Computation of Charges

► Annual Average YTC to be apportioned to peak and Other than peak conditions

►Net PoC Charge = 50% PoC Charge + 50% Uniform Charge

► UC = Total ARR /(Approved injection +approved Withdrawal)

► Calculation of Uniform Charge on All India Basis

► Scaling on Pro-rata basis to adjust over or under recovery

► Treatment of Generators connected at 220 kV► Charged at PoC Charge of the zone

Page 56: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Zoning

►As per the regulations

►Fixed for an application period

►Zonal Charges / Zonal LAF► Weighted average of all nodes in the zone

►Treatment of nodes feeding more than one zone► To be used in both zones► Pro-rata charges in both zones based on ratio of power flow.

Page 57: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Information to RPC

► Approved Withdrawal/Injection (MW) for peak and other than peak hours for each season

► Zonal Point of Connection Charge (Rs/MW/month) for Generation and Demand Zones

► Approved Additional Medium Term Withdrawal / Injection (MW)

► Details of Short Term Open Access

As per format I and II of the Procedure

Page 58: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Information on Public Domain►Approved Basic Network Data and Assumptions, if

any

►Zonal or nodal transmission charges for the next financial year differentiated by block of months;

►Zonal or nodal transmission losses data;

►Schedule of charges payable by each constituent for the future Application Period, after undertaking necessary true-up of costs

Username and Password to view critical data

Page 59: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Format I :Approved Withdrawal/Injection (MW) & Zonal PoC Charge

Name of the Zone

Approved Withdrawal(MW)

Approved Injection(MW)

Zonal PoC

Charge*

(Rs/MW/

Month)

PeakOther

Than Peak PeakOther

Than Peak

Season I

Season II

Season III

Season IV

Season V

Page 60: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Format II: Approved Additional Medium Term Withdrawal/Injection

Name of DIC Duration

Approved Additional Medium Term Withdrawal

(MW)

Approved Additional Medium

Term Injection(MW)

From To PeakOther Than

Peak PeakOther Than

Peak

Page 61: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

ACCOUNTING BILLING & COLLECTION OF CHARGES(CHAPTER 5)

Page 62: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

INPUTS FOR MONTHLY TRANSMISSION ACCOUNTS

► Approved injection / withdrawal from IA

► Zonal POCs from IA

► Approved additional MT injection/withdrawal RLDC/NLDC

► Approved ST injection/withdrawal from RLDC/NLDC

► SEM data for deviation computations

► RPCs to issue monthly transmission accounts(1st working day of the Month)

► RPCs to issue monthly transmission deviation acounts(by 15th of the Month)

► CTU shall be responsible for raising the transmission bills, collection and disbursement of transmission charges to ISTS transmission licensees

► Expenses incurred by CTU on account of this function shall be reimbursed as part of YTC

Page 63: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Accounting Regulation 10

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 63

Regional Transmission Accounts

(1st Working Day of Every Month

for the previous Month)

Regional TransmissionDeviation Accounts

(by 15th Day of Every Month

for the previous Month)

Regional Power

Committee

Regional Power

Committee

Page 64: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Billing (1) Regulation 11

►Responsibility of Central Transmission Utility (CTU)► Based on Accounts issued by RPC

►Long Term Customers shall be billed directly for:► Own Transmission Charges► Generator Transmission Charges in proportion to MW entitlement after

“Commercial Operation”

►Generators shall be billed only for deviations.

►Bill to be raised only on DIC’s► SEB/STU may recover such charges from DISCOMs, Generators and

Bulk Consumers.

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 64

Page 65: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Billing (2)

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 65

Central Transmission

Utility

Central Transmission

UtilityFirst Part

(Based on Approved Injection/Withdrawal and

PoC Charge)

Third Part(Adjustments Based on

FERV,Interest, Rescheduling of Commissioning)

Fourth Part(Deviations)

Second Part(Recovery of Charges for Additional Medium Term

Open Access)

1st Day of a Month

1st Day of a Month

Biannually(1st Day of September and March

18th Day of a

Month

Page 66: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

BILL PART-I

► To be raised by 1st working day of the month by CTU► Independent of Transmission accounts to be issued by RPCs

For Generators[ (PoC Transmission Charge of generation zone in Rs / MW / month for peak hours)× (Approved Injection for peak hours) ]

+ [ (PoC Transmission Charge of generation zone in Rs / MW /

month for off-peak hours) x (Approved Injection for off-peak hours) ]

For Demand[ (PoC Transmission Charge of demand zone in Rs / MW / month for peak hours)x(Approved withdrawal for peak hours) ]

+ [ (PoC Transmission Charge of demand zone in Rs / MW /

month for off-peak hours) x (Approved withdrawal for off-peak hours) ]

Page 67: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

BILL PART-II► To be simultaneously raised alongwith BILL-PART-I

For Generators[ (PoC Transmission Charge of generation zone in Rs / MW / month for peak hours)× (Approved Additional MediumTerm Injection for peak hours) ]

+ [ (PoC Transmission Charge of generation zone in Rs / MW / month for

off-peak hours) x (Approved Additional MediumTerm Injection for off-peak hours) ]

For Demand[ (PoC Transmission Charge of demand zone in Rs / MW / month for peak hours)x(Approved Additional MediumTerm withdrawal for peak hours) ]

+ [ (PoC Transmission Charge of demand zone in Rs / MW / month for off-

peak hours) x (Approved Additional MediumTerm withdrawal for off-peak hours) ]

► Revenue from Additional MTOA alongwith interest to be used for truing up the YTC for next F.Y.(i.e would be adjusted in YTC of the licensee for computation of POC for next F.Y.)

Page 68: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

BILL PART-IV (TREATMENT OF DEVIATIONS) REGULATION 11(7)

► Deviation calculations after considering additional MT & Short Term Open Access for each time block

► Deviation =

[Average MW injected/withdrawn]

-[ (Approved injection/withdrawal+Approved additional MT

injection/withdrawal+ST injection/withdrawal) ]► Charge to be Calculated on Block wise Deviation

► Deviations by Generator shall not be charged to Long Term Customers

► No additional Charge for Deviations in case :► Rescheduling of Maintenance Schedule for reasons beyond control

of geenrator OR Certified by RPC

Page 69: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Treatment of Deviations -GENERATOR

Generator

Net Injection Net Drawl

1.25 times PoC Charge for the average MW withdrawal

Deviation Less than

20%

Deviation Greater

than 20%

PoC Charge

1.25 times PoC Charge for the

excess deviation > 20%

Page 70: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Treatment of Deviations –Demand Customer

Demand

Net Drawl Net Injection

1.25 times PoC Charge for the average MW

injected

Deviation Less than

20%

Deviation Greater

than 20%

PoC Charge

1.25 times PoC Charge for the

excess deviation > 20%

Page 71: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

BILL PART-IV (TREATMENT OF DEVIATIONS) REGULATION 11(7)

► Thus additional charges due to deviations =

1.25 x POC transmission charge for demand / withdrawal x Deviations

In case a generator withdraws from grid::► Additional charges = 1.25 x POC transmission charge for the

demand zone x Average MW withdrawn for the corresponding blocks

In case a withdrawing DIC becomes a net injector::► Additional charges = 1.25 x POC transmission charge for the

generation zone x Average MW injected for the corresponding blocks

► Bill for deviations to be raised by CTU within 3 days of issue of Transmission deviation accounts by RPC.

► This part alongwith interest would be used for truing up the YTC for next F.Y.(i.e would be adjusted in YTC of the licensee for computation of POC for next F.Y.)

Page 72: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

BILL PART-III

► The 3rd Part of the Bill to be raised bi-annully by CTU on the first working day of September & March for the previous six months

► The bill shall be used to adjust any variations in interest rates, FERV, rescheduling of commissioning of transmission assets, etc.

► Recovery/Reimbursement would be on basis of under-recovery/over-recovery, in proportion to average approved injection/withdrawal over previous six months

► CTU to transfer the 3rd part to respective ISTS licensees for whom the adjustment is required

Page 73: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

COLLECTION AND DISBURSEMENTREGULATION 12

► CTU to collect charges on behalf of ISTS service providers.

► CTU to disburse in proportion to Monthly Transmission Charges.

► Payment and Disbursement shall be executed through RTGS.

► Delayed Payments shall result in pro-rata reduction in all payouts

► Payment Security as per detailed procedure prepared by CTU

Page 74: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

TRANSMISSION SERVICE AGREEMENT(TSA) REGULATION 13

► Existing BPTAs realigned TSA► TSA provides for all relevant matters regarding the POC losses/charges

mechanism(e.g.)::► Detailed Commercial/adminsitrative provisions► Metering, accouitnitng, billing, charges recovery provisions► Procedures for interconnection► Treatment in delay of line commissioning► Payment security mechanisms► default & consequences► Termination & Force majeure conditions

► Draft TSA to be finalized by CTU and approved by CERC► Notified TSA would be the default transmission agreement and would

mandatorily apply to all DICs► Signing of TSA not a precondition for construction of new network

elements by CTU/licensees after approval by CERC► TSA may have certain aspects which could be modified from time to time

without rendering the TSA infructuous e.g. contracted capacity, etc..

Page 75: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

TRANSMISSION SERVICE AGREEMENT(TSA) REGULATION 13

►CTU to prepare revenue sharing agreement which is to be approved by CERC for disbursal of monthly transmission charges to various ISTS licnesees

►The impact of any delayed payment/non-payment by any DIC would be shared pro-rata in proportion of YTC by all the ISTS transmission licensees including CTU

►Users to ensure that existing contracts(e.g. BPTAs) are realigned to these regulations within a period of 60 days from the date of notification of the TSA

Page 76: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

LIST OF PROCEDURES AS A PART OFTRANSITION REGULATION 15

► Commission would notify detailed procedures prepared by IA, NLDC & CTU as a part of transition mechanism

►Procedure for obtaining data IA

►Procedure for computation of POC charges IA

►Procedure for sharing of losses IA

►Procedures for Billing and collection of charges by the CTU on behalf of Transmission Licensees and redistribution CTU

►Payment and payment security related procedures CTU

Page 77: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Information on Public DomainRegulation 17

► Approved Basic Network Data and Assumptions, if any

► Zonal or nodal transmission charges for each block of month

► Zonal or Nodal Transmission losses data

► Schedule of Charges payable by each constituent after undertaking necessary true up costs

► Underlying network information & base load flows

Page 78: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Module on Information Submission By DIC’s

National Load Despatch Centre

Power System Operation Corporation

Page 79: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Introduction

►Hybrid Method : Based on Load Flow (Offline Studies)

►Average participation for slack bus identification

►Marginal Participation for usage identification

►Recovery of Charges► 50% by Uniform Charge Method► 50% by PoC Charge Method

Page 80: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Importance of Data in Hybrid Methodology

► Input to the Offline Line Model for Load Flow Studies► Network Parameters► Load and Generation Data ( MW & MVAr)

►Results of offline line studies highly dependent upon the input to the model

► Inconsistent data may not make solution Converged

►May lead to modifications in Approved Demand / Injection

Page 81: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►PoC Charge Calculation depends upon :► Converged and Reduced Network► Line wise YTC provided by Transmission Licensees

►Approved Injection / Withdrawal

►Data to be submitted on or before 4th Week of November for next F.Y.

►The information may be sought by the IA at times other than those if necessary

Page 82: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Flow Chart

Load Flow Studies

Input

Output

Network ParametersLoad & Generation Data

Converged Network

Network Reduction

Software for PoC Charge & Loss Computation

Reduced Network

Line wise YTC

PoC Charges and LAF

Page 83: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

How to Give Information to IA ?

► Identify a person(s) who will coordinate with Implementing Agency

►Communicate the details of Identified Person to the Designated Officer of IA.► Name► Designation► Company Name► Office Address► Contact Number : Official (Landline)

Mobile Number► Letter of Authorization

Page 84: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►Formats would be available on the website of IA and all RLDCs after getting permission from the Commission► www.nldc.in► www.nldcindia.in

►Submission of data shall be only in electronic spreadsheet formats (MS Excel).

►For all communication puposes► emailid of IA : [email protected]

►Written communication confirming submission of data by e-mail.

Page 85: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Network Parameters

►Network Data upto 132 kV except where generators are connected to Grid at 110KV

► Injection below 132 kV : Generation ►Withdrawal below 132 kV : Load

►Also include states generation.

Page 86: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Type of Data

DIC’s

Load & Generation Data

Network DataForecast Injection /

Withdrawal

YTC of each ISTS Line

Transmission Licensees

Page 87: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Category of Network Parameters

Network Parameters

Switched Shunt Data

Transformer Data

DC Line Data

AC Line Data

Generator Data

Bus Data

Page 88: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Bus Data

►Bus Type

►Bus Name : Full Name of Substation

►Conductance► Real Component of Shunt admittance to ground► In MW at one per unit voltage► Should not include resistive impedance load

Page 89: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

► Susceptance► Reactive Component of Shunt admittance to ground► In Mvar at one per unit► Should not include reactive impedance load , line charging and line

connected shunts

Sign Convention

+ for Capacitor

- for Reactor► Voltage in kV

Page 90: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Generator Data►Bus Name

►Generator Real Power Ouput► Ex Bus Output in MW

►Generator Reactive Power Output► Ex Bus Output in Mvar

►Maximum and Minimum Generator Reactive Power Output

► IREG► Bus Name of remote type 1 bus whose voltage is to be regulated

by this plant

Page 91: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►Resistance and Reactance on MVA base

►MVA Base► Total MVA base of the units represented by this machine

►RT, XT► Step up Transformer Impedance in per unit on MVA Base

►GTAP► Step up Transformer off-nominal turns ratio (in pu)

►Maximum and Minimum Real Power Output►RMPCT

► Percent of total Mvar required to hold the voltage at bus IREG

Page 92: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Load Data

►Bus Name

►Real & Reactive Power Component► Constant MVA Load► Constant Current Load► Constant Admittance Load

Page 93: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

AC Line Data

► From Bus Name (I)

► To Bus Name (J)

► Circuit Number► For D/C line one line will have 1 in this data and 2 for other line

► Branch Resistance, Reactance and Charging Susceptance► In pu on 100 MVA base

► Rate A ► Operating limit considering the compensations and length of line► Minimum of Thermal, Voltage and Stability limits.

Page 94: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►Transformer off-nominal tap ratio

►Transformer phase shift angle► In degrees► Positive from untapped to tapped side and vice versa

►Complex admittance of the line shunt at bus I (GI+j BI)

►Complex admittance of the line shunt at bus J

(GJ+j BJ)

►Line Length

Page 95: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DC Line Data (Line quantities and Control)

►DC Line Number

►Control Mode► 0 – Blocked► 1 – Power► 2 – Current

►DC Line resistance in Ohms

►Current or Power Demand► If Control mode is 1 then power, if 2 then current.

Page 96: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

► Scheduled Compounded dc voltage in kV

► Mode Switch dc voltage► If inverter voltage falls below this value and control mode is 1 then it

changes to 2.

► Compounding Resistance

► Metered end code► R for rectifier or I for inverter

► Minimum Compounded dc voltage

Page 97: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

DC Line Data (Rectifier & Inverter

►Rectifier converter bus name

►Number of bridges in series

►Nominal maximum rectifier firing angle

►Minimum steady state rectifier firing angle

►Rectifier commutating transformer resistance & reactance per bridge

Page 98: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

► Rectifier primary base ac voltage

► Rectifier transformer ratio

► Rectifier tap setting

► Maximum rectifier tap setting

► Minimum rectifier tap setting

► Rectifier tap step

Page 99: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►Rectifier firing angle

►Tapped side “ from bus” name

►Untapped side “ to bus” name

►Commutating capacitor reactance

Page 100: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Transformer Data

► From Bus

► To Bus

► Circuit Number

► Resistance and Reactance in per unit

► Phase shift angle

► Nominal Tap Ratio

Page 101: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►Controlled Bus Name

►Maximum Voltage of Controlled Bus

►Minimum Voltage of Controlled Bus

►Max Turns Ratio

►Turns Ratio Step Increment

Page 102: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Switched Shunt Data

► Bus Name

► Control Mode► 0 – Fixed► 1 – Discrete► 2 – Continuous

► Desired Voltage Upper & Lower Limit

► Ni : Number of steps for block I► Bi : Admittance increment for each Ni steps in block i

Page 103: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Forecast Nodal Injection / Withdrawal (1)

► Two figure for each block of months

► One for peak and other for offpeak

► Five Representative Blocks

► April to June…………………………… (May 15)

► July to September……………………. (August 31)

► October to November………………… (October 30)

► December to February……………….. (January 15)

► March…………………………………… (March 15)

► The data should be of the date mentioned against each block of month.

► In case any of the above fall on a Weekend/Public Holiday, the data shall be submitted for working days immediately after the dates indicated.

► In case large changes in POC are foreseen on account of network or usage IA may undertake revised computations after petition from Commission & directions from CERC

► Duration of peak hours for each block

► Specified by NLDC

Page 104: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Forecast Nodal Injection / Withdrawal (2)►MW & MVAr Injection / Withdrawal at each node►Forecast of MVAr on the basis of

► Historic Injection /Withdrawal► Anticipated Change in Load pf

►Forecast of MW► On the basis of MW entitlements

►Forecast required for 5 blocks of month►For Generators forecast should be equal to the rated

capacity

Forecast = max(G1) + max(G1) +……………….

Page 105: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Commercial Data

►Line wise YTC of each ISTS Line

►Breakup of total YTC among different Voltage Levels.

► In case of YTC not approved by SERC/CERC► Benchmark/Reference cost to be used.

►YTC of substations to be apportioned in line► 2/3 to higher voltage lines► 1/3 to lower voltage lines► Apportionment among lines on the basis of length.

Page 106: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Certified Non-ISTS Lines

► Non-ISTS lines certified by RPC as being used as ISTS line will be included in the model.

► Transmission Licensees to get them certified in RPC.

► Line wise YTC to be also certified by RPC and approved by CERC.

► Such List to be provided to IA by Transmission Licensee► Latest by Fourth week of November

Page 107: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Sharing of Inter-State Transmission Losses

Based on PoC LossesNational Load Despatch Centre

Power System Operation Corporation

Page 108: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Introduction

►The procedure aims to keep computation:► Simple► Non-Recursive

►Loss Application on Regional Basis► In line with existing practice► No Pan caking.

► Injection and withdrawal loss would be calculated for each zone.

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 108

Page 109: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

New Methodology

► Point of Connection Losses► Independent of Contract Path

►50% PoC losses + 50% Uniform Losses

►Uniform Loss component► Based on Regional Losses of last week

►Moderation of Losses ► Based on Actual Regional Losses of last week and Losses

based on studies

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 109

Page 110: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

PoC Loss Computation (1)

► Computation of changes in losses in the system due to incremental injection / withdrawal at each node.

► Loss Allocation Factor

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 110

Page 111: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

PoC Loss Computation (2)

► Output of System Studies► MW Losses of each node► Loss Allocation Factor ► Weighted average losses (%) for each region

► Zonal Loss : Weighted Average of losses at each node

► Moderation of Zonal Losses

► One PoC Loss for each entity per day► Weighted average of peak and other than peak

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 111

Page 112: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Loss Sharing Mechanism

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 112

Zonal Losses as Computed from Hybrid

Method

Calculation of Previous week Losses from SEM Data

Total Losses based on PoC

Software Provided by

CERC

Total Losses(50% PoC+50%UC)

Moderation Of PoC Losses

Page 113: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Moderation of Losses (1)

► Need of Moderation► Difference in actual and study scenarios► Correct computation of injection and drawal schedule of various utilities.► Scheduled losses to be closer to actual losses in the system so that

system mismatch is avoided.► Minimizing the mismatch between UI payable and receivable

► Moderation at regional Level► Moderation Factor

= Actual Losses of previous week (Aact) ( In %)

------------------------------------------------------------------

Regional Losses based on Studies (As)(In %)

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 113

Page 114: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

►Regional Losses Based on Studies (As)► Weighted average losses of a region

where A is Total MW losses of a region

∑GNG = Total Injection in a region

∑IIR = Inter Regional Exchange

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 114

A*100 / (∑GNG ±(∑IIR )

Page 115: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Application of Losses in Scheduling

►Net PoC Loss = 50% Moderated PoC Loss + 50% Uniform Loss

►Net PoC Loss to be applied on each regional entity

►Drawee Entity to bear full losses for :► Long Term Transactions► Medium Term Transactions► Bilateral Transactions

► Injecting Entity and Drawee Entity to share losses for:► Collective Transactions

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 115

Page 116: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Case I : Intra-Regional Transactions

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 116

A

B

100 MW

92.15 MW

Zone Moderated Loss (%)

A 3

B 5

Page 117: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Case II : Inter Regional Transactions

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 117

B

A

Zone Moderated Loss (%)

A 3

B 5

100 MW97 MW

92.15 MW

Page 118: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

Case III : Transactions Involving Wheeling Region

04/19/23 रा�ष्ट्री�य भा�रा प्रे�षण कें� द्र 118

B

A

100 MW

92.15 MW

97 MW

97 MW

Page 119: ERLDC Power System Operation Corporation SHARING OF ISTS TRANSMISSION CHARGES & LOSSES.

THANK YOU!


Recommended