+ All Categories
Home > Documents > ES Workshop Sydney Aug 2007 - Project Controls and CPM...

ES Workshop Sydney Aug 2007 - Project Controls and CPM...

Date post: 25-Jun-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
158
Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 1 Earned Schedule Earned Schedule Workshop Workshop Walt Lipke Kym Henderson PMI Oklahoma City Chapter PMI Sydney Chapter USA Australia
Transcript
Page 1: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 1

Earned ScheduleEarned ScheduleWorkshopWorkshop

Walt Lipke Kym HendersonPMI Oklahoma City Chapter PMI Sydney Chapter

USA Australia

Page 2: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 2

Copyright 2007 Lipke & Henderson

Earned Schedule WorkshopBasic� EVM Schedule Indicators

� Introduction to Earned Schedule

� Concept & Metrics

� Indicators

� Predictors

� Terminology

Page 3: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 3

Copyright 2007 Lipke & Henderson

Earned Schedule WorkshopBasic� Application of Concept

� Analysis & Verification

� Prediction Comparisons

� Demonstration of ES Calculator

� V1 & V2 Calculators

� Interpolation Error

Page 4: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 4

Copyright 2007 Lipke & Henderson

Earned Schedule WorkshopBasic� Exercise – Calculate ES, SV(t), SPI(t)

� ES Usage & Propagation

� Applications

� PMI-CPM Earned Value Practice Standard

� ES Website

� Summary - Basic

Page 5: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 5

Copyright 2007 Lipke & Henderson

Earned Schedule WorkshopAdvanced� Analysis Tool Demonstration

� Re-Baseline Effects

� Critical Path Study

� Network Schedule Analysis

� Drill Down

� Impediments / Constraints

� Rework

Page 6: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 6

Copyright 2007 Lipke & Henderson

Earned Schedule WorkshopAdvanced� EV Research

� Schedule Adherence

� Effective Earned Value

� Derivation

� Indicators

� Prediction

Page 7: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 7

Copyright 2007 Lipke & Henderson

Earned Schedule WorkshopAdvanced� Statistical Prediction

� Statistical Process Control

� Planning for Risk

� Performance Indication & Analysis

� Outcome Prediction

� Summary - Advanced

� Quiz & Discussion

� Wrap Up

Page 8: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 8

Earned Schedule Earned Schedule

Workshop Workshop -- BasicBasic

Page 9: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 9

Earned Value ManagementEarned Value Management

Schedule IndicatorsSchedule Indicators

Page 10: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 10

Copyright 2007 Lipke & Henderson

EVM Schedule Indicators

Time

$$

PVEVSPI=

ACEV CPI =

BACPV

AC

EV

SV

CV

PV = Planned ValueEV = Earned ValueAC = Actual CostBAC = Budget at CompletionPD = Planned Duration

SV = EV – PV

Something’s wrong !!

Page 11: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 11

Copyright 2007 Lipke & Henderson

EVM Schedule Indicators

� SV & SPI behave erratically for projects behind schedule� SPI improves and concludes at 1.00 at end of project

� SV improves and concludes at $0 variance at end of project

� Schedule indicators lose predictive ability over the last third of the project

Page 12: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 12

Copyright 2007 Lipke & Henderson

EVM Schedule Indicators

� Why does this happen?� SV = BCWP – BCWS

� SPI = BCWP / BCWS

� At planned completion BCWS = BAC

� At actual completion BCWP = BAC

� When actual > planned completion� SV = BAC – BAC = $000

� SPI = BAC / BAC = 1.00

Regardless of lateness !!

Page 13: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 13

Introduction to Introduction to

Earned ScheduleEarned Schedule

Page 14: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 14

Copyright 2007 Lipke & Henderson

$

5

Σ PV

Σ EV

Time Now

71 2 3 4 6 8 9 10

A

B

SVc

SVtES AT

Earned Schedule ConceptEarned Schedule Concept

The idea is to determine the time at which the EV accrued should have occurred.

For the above example, ES = 5 months …that is the time associated with thePMB at which PV equals the EV accrued at month 7.

Page 15: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 15

Copyright 2007 Lipke & Henderson

Earned Schedule MetricEarned Schedule Metric

� Required measures� Performance Measurement Baseline (PMB) – the

time phased planned values (PV) from project start to completion

� Earned Value (EV) – the planned value which has been “earned”

� Actual Time (AT) - the actual time duration from the project beginning to the time at which project status is assessed

� All measures available from EVM

Page 16: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 16

Copyright 2007 Lipke & Henderson

Earned Schedule CalculationEarned Schedule Calculation

� ES (cumulative) is the:

Number of complete PV time increments EV equals or exceeds + the fraction of the incomplete PV increment

� ES = C + I where:

C = number of time increments for EV ≥ PV

I = (EV – PVC) / (PVC+1 – PVC)

Page 17: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 17

Copyright 2007 Lipke & Henderson

Interpolation CalculationInterpolation Calculation

$$

I /1 mo = p / q

I = (p / q) ∗ 1 mo

p = EV – PVCq = PVC+1 – PVC

I = ∗ 1moEV – PVC

PVC+1 – PVC

PVC+1

••

ES(calc)

EV

PVC

ES

JulyJuneMay

1 mo

I

p

q

Time

Page 18: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 18

Copyright 2007 Lipke & Henderson

ES Computation Example

BCWS

BCWPSPI($) =

AT

ESSPI(t) =

$

Time

BCWS

BCWP

Projection of BCWPonto BCWS

7AT

BCWS(May) - BCWS(June)

BCWS(May) - BCWP($) 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

BCWSBCWPSV($) −=

ATES SV(t) −=

BCWS

BCWPSPI($) =

BCWS

BCWPSPI($) =

AT

ESSPI(t) =

AT

ESSPI(t) =

$

Time

BCWS

BCWP

Projection of BCWPonto BCWS

7AT

BCWS(May) - BCWS(June)

BCWS(May) - BCWP($) 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

BCWSBCWPSV($) −= BCWSBCWPSV($) −=

ATES SV(t) −= ATES SV(t) −=

Page 19: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 19

Copyright 2007 Lipke & Henderson

ES Computation Example

BCWS

BCWPSPI($) =

AT

ESSPI(t) =

$

Time

BCWS

BCWP

Projection of BCWPonto BCWS

7AT

BCWS(May) - BCWS(June)

BCWS(May) - BCWP($) 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

BCWSBCWPSV($) −=

ATES SV(t) −=

BCWS

BCWPSPI($) =

BCWS

BCWPSPI($) =

AT

ESSPI(t) =

AT

ESSPI(t) =

$

Time

BCWS

BCWP

Projection of BCWPonto BCWS

7AT

BCWS(May) - BCWS(June)

BCWS(May) - BCWP($) 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

BCWSBCWPSV($) −= BCWSBCWPSV($) −=

ATES SV(t) −= ATES SV(t) −=

Earned Schedule requires the:1) PMB; and 2) Accrued EV for calculation.The equation is: ES = C + I

The first step is to compute C. The value of C is found by counting the number of the PV time increments EV equals or exceeds. In this example the count is from January through May. C = 5 (months).

Page 20: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 20

Copyright 2007 Lipke & Henderson

ES Computation Example

BCWS

BCWPSPI($) =

AT

ESSPI(t) =

$

Time

BCWS

BCWP

Projection of BCWPonto BCWS

7AT

BCWS(May) - BCWS(June)

BCWS(May) - BCWP($) 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

BCWSBCWPSV($) −=

ATES SV(t) −=

BCWS

BCWPSPI($) =

BCWS

BCWPSPI($) =

AT

ESSPI(t) =

AT

ESSPI(t) =

$

Time

BCWS

BCWP

Projection of BCWPonto BCWS

7AT

BCWS(May) - BCWS(June)

BCWS(May) - BCWP($) 5 ES

June of Portion May of AllES

=

+=

+=

J J JF M MA A S O N

BCWSBCWPSV($) −= BCWSBCWPSV($) −=

ATES SV(t) −= ATES SV(t) −=

Thus far, ES = 5 + I (months). In the small box at the lower right, is the equation for calculating I.For the example, let1) EV = 1002) PV5 (May) = 90 3) PV6 (June) = 110.

Let’s calculate I:I = (100 – 90) / (110 – 90) = 0.5

ES = 5 + 0.5 = 5.5 (months)

From ES (5.5 months) we can now calculate the ES indicators:SV(t) and SPI(t).

The EV is reported at Actual TimeAT = 7, the end of June.

SV(t) = 5.5 – 7 = - 1.5 months

SPI(t) = 5.5 / 7 = 0.79

Page 21: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 21

Copyright 2007 Lipke & Henderson

ES Periodic Metrics

� Periodic measures are needed for trending

� Periodic measures are derived from the cumulative measures

� ESperiod(n) = EScum(n) – EScum(n-1) = ∆EScum

� ATcum

� ATperiod(n) = ATcum(n) – ATcum(n-1) = ∆ATcum

� ∆ATcum is normally equal to 1

Page 22: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 22

Copyright 2007 Lipke & Henderson

Earned Schedule Indicators

� Schedule Variance: SV(t)

� Cumulative: SV(t) = EScum – ATcum

� Period: ∆SV(t) = ∆ EScum – ∆ ATcum

� Schedule Performance Index: SPI(t)

� Cumulative: SPI(t) = EScum / ATcum

� Period: ∆SPI(t) = ∆EScum / ∆ATcum

Page 23: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 23

Copyright 2007 Lipke & Henderson

Earned Schedule Indicators

� What happens to the ES indicators, SV(t) & SPI(t), when the planned project duration (PD) is exceeded (BCWS = BAC)?

They Still Work …Correctly!!� ES will be ≤≤≤≤ PD, while AT > PD

� SV(t) will be negative (time behind schedule)

� SPI(t) will be < 1.00

Reliable Values from Start to Finish !!

Page 24: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 24

Copyright 2007 Lipke & Henderson

SV Comparison

-400

-300

-200

-100

0

J F M A M J J A S O N D J F M

-3

-2

-1

0

0

20

40

60

80

100

J F M A M J J A S O N D J F M

0

0.2

0.4

0.6

0.8

1

SV($) SV(t)

Early Finish Project

Late Finish Project

$ Mo

$ Mo

-400

-300

-200

-100

0

J F M A M J J A S O N D J F M

-3

-2

-1

0

0

20

40

60

80

100

J F M A M J J A S O N D J F M

0

0.2

0.4

0.6

0.8

1

SV($) SV(t)

Early Finish Project

Late Finish Project

$ Mo

$ Mo

0

20

40

60

80

100

J F M A M J J A S O N D J F M

0

0.2

0.4

0.6

0.8

1

SV($) SV(t)

Early Finish Project

Late Finish Project

$ Mo

$ Mo

SV($) SV(t)SV($) SV(t)

Early Finish Project

Late Finish Project

$ Mo

$ Mo

Page 25: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 25

Copyright 2007 Lipke & Henderson

SPI Comparison

0.98

1.00

1.02

1.04

1.06

1.08

1.10

1.12

J F M A M J J A S O N D J F M

0.70

0.80

0.90

1.00

1.10

1.20

1.30

J F M A M J J A S O N D J F M

SPI($) SPI(t)

Early Finish Project

Late Finish Project

0.98

1.00

1.02

1.04

1.06

1.08

1.10

1.12

J F M A M J J A S O N D J F M

0.70

0.80

0.90

1.00

1.10

1.20

1.30

J F M A M J J A S O N D J F M

SPI($) SPI(t)SPI($) SPI(t)

Early Finish Project

Late Finish Project

Page 26: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 26

Copyright 2007 Lipke & Henderson

Earned Schedule Predictors� Can the project be completed as planned?

� TSPI = Plan Remaining / Time Remaining

= (PD – ES) / (PD – AT)where (PD – ES) = PDWR

PDWR = Planned Duration for Work Remaining

� …..completed as estimated?� TSPI = (PD – ES) / (ED – AT)

where ED = Estimated Duration

Not Achievable> 1.10

Achievable≤ 1.00

Predicted OutcomeTSPI Value

Page 27: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 27

Copyright 2007 Lipke & Henderson

Earned Schedule Forecasting

� Long time goal of EVM …Forecasting of total project duration from present schedule status

� Independent Estimate at Completion (time)

� IEAC(t) = PD / SPI(t)

� IEAC(t) = AT + (PD – ES) / PF(t)where PF(t) is the Performance Factor (time)

� Analogous to IEAC used to forecast final cost

� Independent Estimated Completion Date (IECD)

� IECD = Start Date + IEAC(t)

Page 28: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 28

Copyright 2007 Lipke & Henderson

Earned Schedule TerminologyEarned ScheduleEVM

To Complete Schedule Performance Index (TSPI)

To Complete Performance Index (TCPI)

Independent EAC (time)IEAC(t) (customer)

Independent EAC (IEAC) (customer)

Estimate at Completion (time) EAC(t) (supplier)

Estimate at Completion (EAC) (supplier)Prediction

Variance at Completion (time) VAC(t)

Variance at Completion (VAC)

Estimate to Complete (time) ETC(t)Estimate to Complete (ETC)Work

Planned Duration for Work Remaining (PDWR)

Budgeted Cost for Work Remaining (BCWR)Future

SPI(t)SPI

SV(t)SV

Actual Time (AT)Actual Costs (AC)Status

Earned Schedule (ES)Earned Value (EV)

Earned ScheduleEVM

To Complete Schedule Performance Index (TSPI)

To Complete Performance Index (TCPI)

Independent EAC (time)IEAC(t) (customer)

Independent EAC (IEAC) (customer)

Estimate at Completion (time) EAC(t) (supplier)

Estimate at Completion (EAC) (supplier)Prediction

Variance at Completion (time) VAC(t)

Variance at Completion (VAC)

Estimate to Complete (time) ETC(t)Estimate to Complete (ETC)Work

Planned Duration for Work Remaining (PDWR)

Budgeted Cost for Work Remaining (BCWR)Future

SPI(t)SPI

SV(t)SV

Actual Time (AT)Actual Costs (AC)Status

Earned Schedule (ES)Earned Value (EV)

Page 29: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 29

Copyright 2007 Lipke & Henderson

Earned Schedule Terminology

at Completion (time)

Independent Estimate

Performance Index

To Complete Schedule

Schedule Performance Index

Schedule Variance

Actual Time

Earned Schedule

IEAC(t) = AT + (PD – ES) / PF

IEAC(t) = PD / SPI(t)IEAC(t)Predictors

TSPI(t) = (PD – ES) / (ED – AT)

TSPI(t) = (PD – ES) / (PD – AT)TSPI(t)

SPI(t) = ES / ATSPI(t)Indicators

SV(t) = ES - ATSV(t)

AT = number of periods executedATcum

ES = C + I number of complete periods (C) plus an incomplete portion (I)

EScumMetrics

at Completion (time)

Independent Estimate

Performance Index

To Complete Schedule

Schedule Performance Index

Schedule Variance

Actual Time

Earned Schedule

IEAC(t) = AT + (PD – ES) / PF(t)

IEAC(t) = PD / SPI(t)IEAC(t)Predictors

TSPI(t) = (PD – ES) / (ED – AT)

TSPI(t) = (PD – ES) / (PD – AT)TSPI(t)

SPI(t) = ES / ATSPI(t)Indicators

SV(t) = ES - ATSV(t)

AT = number of periods executedATcum

ES = C + I number of complete periods (C) plus an incomplete portion (I)

EScumMetrics

Page 30: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 30

Copyright 2007 Lipke & Henderson

Earned Schedule Key Points

� ES Indicators constructed to behave in an analogous manner to the EVM Cost Indicators, CV and CPI

� SV(t) and SPI(t)

� Not constrained by BCWS calculation reference

� Provide duration based measures of schedule performance

� Valid for entire project, including early and late finish

� Facilitates integrated Cost/Schedule Management(using EVM with ES)

Page 31: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 31

Application of ConceptApplication of Concept(Using Real Project Data)(Using Real Project Data)

Page 32: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 32

Copyright 2007 Lipke & Henderson

ES Applied to Real Project Data:Late Finish Project: SV($) and SV(t)

Commercial IT Infrastructure Expansion Project Phase 1

Cost and Schedule Variancesat Project Projection: Week Starting 15th July xx

-160

-140

-120

-100

-80

-60

-40

-20

0

20

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Elapsed Weeks

Do

lla

rs (

,00

0)

-16

-14

-12

-10

-8

-6

-4

-2

0

2

We

ek

s

CV cum SV cum Target SV & CV SV (t) cum

Stop wk 19

Re-start wk 26Sched wk 20

Page 33: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 33

Copyright 2007 Lipke & Henderson

ES Applied to Real Project Data:Late Finish Project Analysis

� No EVM data prior to week 11

� SV($) and SV(t) show strong correlation until week 19 � Week 20 (The week of the project’s scheduled completion)

Client delay halted project progress until resolution in Week 26

� SV($) static at -$17,500 in spite of schedule delay� Before trending to $0 at project completion

� SV(t) correctly calculates and displays� Week on week schedule delay� Project -14 week schedule delay at completion

� Conclusion� SV(t) provides greater management utility than SV($)

for portraying and analyzing schedule performance

Page 34: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 34

Copyright 2007 Lipke & Henderson

Early Finish Project: SV($) and SV(t)

Commerical IT Infrastructure Expansion Project: Phases 2 & 3 Combined

Cost and Schedule Variancesas at Project Completion: Week Starting 9th October xx

-25.0

-15.0

-5.0

5.0

15.0

25.0

35.0

45.0

55.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Elapsed Weeks

Do

lla

rs (

$,0

00

)

-2.0

-1.0

0.0

1.0

2.0

3.0

4.0

5.0

We

ek

s

Target SV & CV CV cum SV ($) cum SV (t) cum

Stop wk 16

Re-start wk 19

Sched wk 25

Page 35: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 35

Copyright 2007 Lipke & Henderson

Early Finish Project Analysis

� This project completed 3 weeks ahead of schedule

� In spite of externally imposed delay between weeks 16 and 19

� SV($) and SV(t) show strong correlation over life of project

� Including the delay period

� SV(t)’s advantage is calculating delay as a measure of duration

� With Early Finish projects

� ES metrics SV(t) and SPI(t) have behaved consistently with their

historic EVM counterparts

� Conclusion� SV(t) provides greater management utility than SV($)

for portraying and analyzing schedule performance

Page 36: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 36

Prediction ComparisonsPrediction Comparisons

Page 37: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 37

Copyright 2007 Lipke & Henderson

Schedule Duration Prediction

� Calculation of IEAC(t): short form

IEAC(t) = Planned Duration / SPI(t)

� Planned Duration for Work Remaining

PDWR = Planned Duration – Earned Schedule cum

� Analogous to the EVM BCWR

� Calculation of IEAC(t): long form

PDWRIEAC(t) = Actual Time +

Performance Factor

Page 38: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 38

Copyright 2007 Lipke & Henderson

IEAC(t) Prediction ComparisonEarly and Late Finish Project Examples

� In both examples, the pre ES predictors (in red) fail to correctly calculate the Actual Duration at Completion!

� The ES predictor, SPI(t) alone correctly calculates the Actual Duration at Completion in both cases

Planned Duration (weeks) 25Actual Time (weeks) 22

Percentage Complete cum 100%CPI cum 2.08

SPI(t) cum 1.14SPI($) cum 1.17

Critical Ratio cum 2.43IEAC(t) PD/SPI(t) cum 22.0IEAC(t) PD/SPI($) cum 21.4

IEAC(t) PD/CR cum 10.3

IEAC(t) Metrics at Project Completion

Early Finish Project

Planned Duration (weeks) 20

Actual Time (weeks) 34

Percentage Complete cum 100%

CPI cum 0.52

SPI(t) cum 0.59

SPI($) cum 1.00

Critical Ratio cum 0.52

IEAC(t) PD/SPI(t) cum 34.0

IEAC(t) PD/SPI($) cum 20.0

IEAC(t) PD/ CR cum 38.7

IEAC(t) Metrics at Project Completion

Late Finish Project - pre ES

Page 39: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 39

Copyright 2007 Lipke & Henderson

“Further Developments in Earned Schedule”Schedule Duration Prediction (continued)

�Pre ES formulae and results algebraically flawed

“... there is little theoretical justification for EVM practitioners continuing to use the pre ES predictorsof schedule performance. Conversion to and use of the ES based techniques is strongly recommended.”

There’s got to be a better

method!

- Kym Henderson

Page 40: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 40

Copyright 2007 Lipke & Henderson

IEAC(t) Predictions using ES Techniques:Same Early and Late Finish Project Examples

� Use of the ES “long form” IEAC(t) formula, results in correct calculation of Actual Duration at Completion

Planned Duration (weeks) 20Actual Time (weeks) 34

Earned Schedule cum 20.0Planned Duration Work

Remaining0.0

Percentage Complete cum 100%CPI cum 0.53

SPI(t) cum 0.59SPI($) cum 1.00

Critical Ratio cum 0.52Critical Ratio ES cum 0.30

IEAC(t) PF = SPI(t) cum 34.0IEAC(t) PF = SPI($) cum 34.0

IEAC(t) PF = CR cum 34.0IEAC(t) PF = CR ES cum 34.0

IEAC(t) Metrics at Project Completion

Late Finish Project using ES

Planned Duration (weeks) 25Actual Time (weeks) 22

Earned Schedule cum 25.0Planned Duration Work

Remaining0.0

Percentage Complete cum 100%CPI cum 2.08

SPI(t) cum 1.14SPI($) cum 1.17

Critical Ratio cum 2.43Critical Ratio ES cum 2.37

IEAC(t) PF = SPI(t) cum 22.0IEAC(t) PF = SPI($) cum 22.0

IEAC(t) PF = CR cum 22.0IEAC(t) PF = CR ES cum 22.0

IEAC(t) Metrics at Project Completion

Early Finish Project using ES

Page 41: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 41

Copyright 2007 Lipke & Henderson

IEAC(t) Predictions using ES TechniquesLate Finish Project Example

Commercial IT Infrastructure Expansion Project Phase 1

Earned Schedule, Independent Estimate At Completion (time) - IEAC(t)as at Project Completion: Week Starting 15th July xx

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Actual Time (Weeks)

Du

rati

on

(W

eeks)

Planned Schedule Earned Schedule cum IEAC(t) PD/SPI(t)

Stop wk 19 Re-start wk 26

Plan Dur wk 20

Page 42: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 42

Copyright 2007 Lipke & Henderson

IECD Predictions using ES TechniquesIndependent Estimate of Completion Date

Commercial IT Infrastructure Expansion Project Phase 1

Earned Schedule, Independent Estimates of Completion Date (IECD)as at Project Completion: Week Starting 15th July xx

0

5

10

15

20

25

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Actual Time (Weeks)

Dura

tion (W

eeks)

27 Jan 90

10 Feb 90

24 Feb 90

10 Mar 90

24 Mar 90

07 Apr 90

21 Apr 90

05 May 90

19 May 90

02 Jun 90

16 Jun 90

30 Jun 90

14 Jul 90

28 Jul 90

Planned Schedule Earned Schedule cum Planned Completion Date Independent Estimate of Completion Date

Plan Dur wk 20

Compl Apr 7

Re-start wk 26

Stop wk 19

Page 43: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 43

Copyright 2007 Lipke & Henderson

IEAC(t) Predictions using ES Techniques

�ES formulae and results are algebraically correct

“Whilst assessments of the predictive utility of the ES

calculated IEAC(t) and the relative merits of using the

various performance factors available are matters for

further research and empiric validation, the theoretical

integrity of ES now seems confirmed.”

There IS a

better

method!

- Kym Henderson

Page 44: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 44

Copyright 2007 Lipke & Henderson

Independent Confirmation

� SPI(t) & SV(t) do portray the real schedule performance

� At early & middle project stages pre-ES & ES forecasts of project duration produce similar results

� At late project stage ES forecasts outperform all pre-ES forecasts

� The use of the SPI(t) in conjunction with the TSPI(t) has been demonstrated to be useful for managing the schedule

� “The results reveal that the earned schedule method outperforms, on the average, all other forecasting methods.”

Stephan Vandevoorde – Fabricom Airport Systems, Belgium

Mario Vanhoucke & Stephan Vandevoorde“A Simulation and Evaluation of Earned Value Metrics to Forecast Project Duration”

Journal of the Operational Research Society (September 2006)

Page 45: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 45

Copyright 2007 Lipke & Henderson

Vanhoucke M., S. Vandevoorde, “A simulation and evaluation of earned value metrics to

forecast the project duration,” Journal Of Operations Research Society September 2006

Forecast Accuracy and the Completion of WorkSimulation runs performed: 1 run project finish ahead of schedule, 1 run projects finish behind

Mean Percentage Error (MPE)

for early finish projects

-0,20

-0,15

-0,10

-0,050,00

0,05

0,10

0%-30% 30%-70% 70%-100%

PD/SPI PD/SPI(t)

Mean Percentage Error (MPE)

for late finish projects

-0,10

-0,05

0,00

0,05

0,10

0%-30% 30%-70% 70%-100%

PD/SPI PD/SPI(t)

Research Results

Page 46: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 46

Demonstration of Earned Demonstration of Earned

Schedule CalculatorSchedule Calculator

Page 47: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 47

Copyright 2007 Lipke & Henderson

Earned Schedule Calculator

Earned Schedule Calculator (V1)

Page 48: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 48

Interpolation ErrorInterpolation Error

Page 49: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 49

Copyright 2007 Lipke & Henderson

Interpolation Error

� The PMB is an S-Curve. Does the linear interpolation introduce large ES error?

� Is error larger where the S-Curve is steepest?

� What affects the accuracy of the ES calculation?

Page 50: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 50

Copyright 2007 Lipke & Henderson

Interpolation Error

$$

I /1 mo = p / q

I = (p / q) ∗ 1 mo

p = BCWP – BCWSC

q = BCWSC+1 – BCWSC

I = ∗ 1moBCWP – BCWSC

BCWSC+1 – BCWSC

BCWSC+1

••

ES(calc)

BCWP

BCWSC

ES

JulyJuneMay

1 mo

I

p

q

Time

Page 51: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 51

Copyright 2007 Lipke & Henderson

Interpolation Error

ES = Number of whole months (C) + Increment on curve (F)

= C + F

ES(calc) = C + calculated increment (I) Error (δ) = I - F

% error =

Example = .05 / 8.12 = 0.6%As C ⇒ larger

- % error ⇒ smaller- ES(calc) ⇒ more accurate

Weekly EV make ES more accurate

| δ |

C + F

Time

$$

•BCWSC+1

••BCWP

ES(calc)

BCWSC

JulyJuneMay

(C) (C + 1)ES

F

I

δδδδ error

Page 52: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 52

Copyright 2007 Lipke & Henderson

Interpolation Error

� After a few months of status (C > 4) -interpolation error is negligible (≤ 3%)

� What about central portion of PMB, where S-Curve is steepest? Is error greater?

� Where slope is large, the resolution of the interpolation is maximized

� Curvature of PMB is minimized

� Interpolation error is negligible

Page 53: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 53

Copyright 2007 Lipke & Henderson

Other Sources of Error

� Partial Month – 1st month

� Much more significant than interpolation error

� Error decreases as C becomes larger

� Correctable – adjust calculator output

� Earned Value recorded

� By far, the largest source of ES error

� Low accuracy for EV ⇒ inaccurate ES

Page 54: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 54

BREAK BREAK –– 15 Minutes15 Minutes

Page 55: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 55

Exercise Exercise –– CalculateCalculate

ES, SV(t), SPI(t)ES, SV(t), SPI(t)

Page 56: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 56

Copyright 2007 Lipke & Henderson

Exercise # 1

� Complete Early & Late Worksheets (tan areas only)

by calculating ES, SV(t), SPI(t)

� Earned Schedule Formulas:

� ES = Nr of Completed BCWS Time Periods

+ Fraction of Uncompleted Period

� Fraction = (BCWP – BCWSC) / (BCWSC+1 – BCWSC)

� AT = Actual Time (number of periods from start)

� Schedule Variance: SV(t) = ES – AT

� Schedule Performance Index: SPI(t) = ES / AT

Page 57: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 57

Copyright 2007 Lipke & Henderson

Early Finish Project (Cumulative Values)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

BSWS($) 105 200 515 845 1175 1475 1805 2135 2435 2665 2760 2823

BCWP($) 115 220 530 870 1215 1525 1860 2190 2500 2740 2823 ------

SV($) 10 20 15 25 40 50 55 55 65 75 63 ------

SPI($) 1.095 1.100 1.029 1.030 1.034 1.034 1.030 1.026 1.027 1.028 1.023 ------

Month Count 1 2 3 4 5 6 7 8 9 10 11 12

ES(cum)

SV(t)

SPI(t)

ES Exercise - Worksheet

Page 58: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 58

Copyright 2007 Lipke & Henderson

Late Finish Project (Cumulative Values)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

BSWS($) 105 200 515 845 1175 1475 1805 2135 2435 2665 2760 2823 ------ ------ ------

BCWP($) 95 180 470 770 1065 1315 1610 1900 2150 2275 2425 2555 2695 2770 2823

SV($) -10 -20 -45 -75 -110 -160 -195 -235 -285 -390 -335 -268 -128 -53 0

SPI($) 0.905 0.900 0.913 0.911 0.906 0.892 0.892 0.890 0.883 0.854 0.879 0.905 0.955 0.981 1.000

Month Count 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

ES(cum)

SV(t)

SPI(t)

Year 01 Year 02

ES Exercise - Worksheet

Page 59: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 59

Copyright 2007 Lipke & Henderson

ES Exercise - AnswersJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

BSWS($) 105 200 515 845 1175 1475 1805 2135 2435 2665 2760 2823

BCWP($) 115 220 530 870 1215 1525 1860 2190 2500 2740 2823 ------

SV($) 10 20 15 25 40 50 55 55 65 75 63 ------

SPI($) 1.095 1.100 1.029 1.030 1.034 1.034 1.030 1.026 1.027 1.028 1.023 ------

Month Count 1 2 3 4 5 6 7 8 9 10 11 12

ES(mo) 1.105 2.063 3.045 4.076 5.133 6.152 7.167 8.183 9.283 10.789 12.000 ------

SV(t) 0.105 0.063 0.045 0.076 0.133 0.152 0.167 0.183 0.283 0.789 1.000 ------

SPI(t) 1.105 1.032 1.015 1.019 1.027 1.025 1.024 1.023 1.031 1.079 1.091 ------

Early Finish Project (Cumulative Values)

Page 60: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 60

Copyright 2007 Lipke & Henderson

ES Exercise - Answers

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

BSWS($) 105 200 515 845 1175 1475 1805 2135 2435 2665 2760 2823 ------ ------ ------

BCWP($) 95 180 470 770 1065 1315 1610 1900 2150 2275 2425 2555 2695 2770 2823

SV($) -10 -20 -45 -75 -110 -160 -195 -235 -285 -390 -335 -268 -128 -53 0

SPI($) 0.905 0.900 0.913 0.911 0.906 0.892 0.892 0.890 0.883 0.854 0.879 0.905 0.955 0.981 1.000

Month Count 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

ES(mo) 0.905 1.789 2.857 3.773 4.667 5.467 6.409 7.288 8.050 8.467 8.967 9.522 10.316 11.159 12.000

SV(t) -0.095 -0.211 -0.143 -0.227 -0.333 -0.533 -0.591 -0.712 -0.950 -1.533 -2.033 -2.478 -2.684 -2.841 -3.000

SPI(t) 0.905 0.894 0.952 0.943 0.933 0.911 0.916 0.911 0.894 0.847 0.815 0.794 0.794 0.797 0.800

Year 01 Year 02

Late Finish Project (Cumulative Values)

Page 61: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 61

ES Usage & PropagationES Usage & Propagation

Page 62: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 62

Copyright 2007 Lipke & Henderson

Early Adopters

� EVM instruction including ES � Performance Management Associates, Management

Technologies, George Washington University, University of Florida …

� Boeing, Lockheed Martin, US State Department, Secretary of the Air Force, UK MoD …

� Several Countries - Australia, Belgium, United Kingdom, USA ….(Spain, Brazil, Serbia, Sweden, Canada, India, …)

� Applications across weapons programs, construction, software development, …

� Range of project size from very small and short to extremely large and long duration

Page 63: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 63

Copyright 2007 Lipke & Henderson

PMI-CPM EVM Practice Standard

� Inclusion of Emerging Practice Insert into PMI - EVM Practice Standard� Dr. John Singley, VP of CPM

� Included in Box 3-1 of EVM Practice Standard� Describes basic principles of

“Earned Schedule”� Provides foundation for

acceptance as a valid extension to EVM

� EVM Practice Standard released at 2004 IPMC Conference

Page 64: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 64

Copyright 2007 Lipke & Henderson

Earned Schedule Website

� Established February 2006

� Contains News, Papers, Presentations, ES Terminology, ES Calculators

� Identifies Contacts to assist with application

� The activity growth of the website over this year has been astounding – beginning at 4,000 and now aboutthan 13,000 requests per month

Page 65: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 65

Copyright 2007 Lipke & Henderson

� Freely available add on tool for the Deltek Cobra product

� Requires registration to Earned Value Forums

� Contact:Mike BoultonWST Pacific

[email protected]

+61 8 8150 5500

http://www.evforums.net.au/forums/showthread.php?t=15

EVM Tool with ES

Page 66: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 66

Copyright 2007 Lipke & Henderson

ES Tool for MS Project

� Earned Schedule macro for MS Project 2003

� Created by Diego Navarro

[email protected]

� Spanish version

http://www.armell.com/excel/earned_schedule_es.zip

� English version being tested

Page 67: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 67

Copyright 2007 Lipke & Henderson

Available Resources

� PMI-Sydney http://sydney.pmichapters-australia.org.au/

� First repository for ES Papers and Presentations

� Earned Schedule Website http://www.earnedschedule.com/

� Wikipedia now references Earned Schedulehttp://en.wikipedia.org/wiki/Earned_Schedule

Page 68: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 68

Summary Summary -- BasicBasic

Page 69: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 69

Copyright 2007 Lipke & Henderson

Summary - Basic

� Derived from EVM data … only

� Provides time-based schedule indicators

� Indicators do not fail for late finish projects

� Application is scalable up/down, just as is EVM

� Schedule prediction is better than any other EVM method presently used� SPI(t) behaves similarly to CPI

� IEAC(t) = PD / SPI(t) behaves similarly to

IEAC = BAC / CPI

Page 70: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 70

Copyright 2007 Lipke & Henderson

Summary - Basic

� Schedule prediction – much easier and possibly better than “bottoms-up” schedule analysis

� Application is growing in both small and large projects

� Practice recognized as “Emerging Practice”

� Resource availability enhanced with ES website and Wikipedia

� Research indicates ES superior to other methods

Page 71: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 71

BREAK BREAK –– 15 Minutes15 Minutes

Page 72: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 72

Earned Schedule Earned Schedule

Workshop Workshop -- AdvancedAdvanced

Page 73: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 73

Analysis Tool Analysis Tool

DemonstrationDemonstration

Page 74: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 74

Copyright 2007 Lipke & Henderson

Earned Schedule CalculatorAnalysis Tool

Earned Schedule Analysis Tool

Page 75: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 75

ES and ReES and Re--BaseliningBaselining

Page 76: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 76

Copyright 2007 Lipke & Henderson

ES and Re-Baselining

� ES indicators are affected by re-baselining� Behaviour of SV(t) and SPI(t) is analogous to CV and

CPI�� See examplesSee examples

� PMB change affects schedule prediction similarly to cost

� Earned Schedule brings attention to the potential schedule impact of a declared “cost only” change

Page 77: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 77

Copyright 2007 Lipke & Henderson

0.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00D

ura

tio

n (

We

ek

s)

Actual Time (weeks) 0.00 4.00 8.00 12.00 17.00 21.00 25.00 26.00 30.00 34.00

Planned Schedule ReBline #1 0.00 4.00 8.00 12.00 17.00 21.00 25.00 26.00 30.00 33.00

Planned Schedule cum CBB 0.00 4.00 8.00 12.00 17.00 20.00 20.00 20.00 20.00 20.00

Earned Schedule cum 0.00 3.84 8.60 12.56 16.87 17.45 17.59 25.91 28.70 33.00

IEAC(t) SPI(t) 20.85 18.60 19.11 20.15 24.07 28.42 33.12 34.50 34.00

01 Jan 29 Jan 26 Feb 26 Mar 30 Apr 28 May 25 Jun 02 Jul 30 Jul 27 Aug

Earned Schedule – Re-Baseline Example Real project data – nominal re-baseline

1. Nominal Re-plan 02 JulyCost and schedule overrun

2. Schedule delay

3. Re-baseline effect

Page 78: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 78

Copyright 2007 Lipke & Henderson

-140

-120

-100

-80

-60

-40

-20

0

20

40

60

Do

lla

rs ,

00

0

-8.00

-7.00

-6.00

-5.00

-4.00

-3.00

-2.00

-1.00

0.00

1.00

2.00

We

ek

s

Actual Time (weeks) 0.00 4.00 8.00 12.00 17.00 21.00 25.00 26.00 30.00 34.00

CV cum 0.00 (12.14) (23.70) (42.92) (87.31) (108.61) (121.43) 6.96 11.09 (2.30)

SV($) cum 0.00 (0.41) 6.65 6.73 (1.42) (22.07) (46.48) (8.60) (5.22) 0.00

Target CV and SV 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

SV(t) cum 0.00 (0.16) 0.60 0.56 (0.13) (3.55) (7.41) (0.09) (1.30) (1.00)

01 Jan 29 Jan 26 Feb 26 Mar 30 Apr 28 May 25 Jun 02 Jul 30 Jul 27 Aug

Earned Schedule – Re-Baseline Example CV, SV($) and SV(t)

1. Nominal Re-plan 02 JulyCost and schedule overrun

2. Cost Overrun

3. Schedule delay

4. “Sawtooth” effect of re-baselining (CV, SV($) and SV(t)

5. 1 week completion delay on re-baselined

PMB

Page 79: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 79

Critical Path Study Critical Path Study

Page 80: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 80

Copyright 2007 Lipke & Henderson

Critical Path Study Outline

� The Scheduling Challenge

� Case Study Project

� The project

� The EVM, Earned Schedule and Network Schedule

approach

� Earned Schedule vs Critical Path predictors

� Real Schedule Management with Earned Schedule

� Initial experience and observation

Page 81: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 81

Copyright 2007 Lipke & Henderson

The Scheduling Challenge

� A realistic project schedule is dependent on multiple, often complex factors including accurate:

� Estimation of the tasks required,

� Estimates of the task durations

� Resources required to complete the identified tasks

� Identification and modeling of dependencies impacting the execution of the project

� Task dependencies (e.g. F-S process flows)

� “Dependent” Milestones (internal and external)

� “Other logic”

Page 82: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 82

Copyright 2007 Lipke & Henderson

The Scheduling Challenge� From small projects into large projects and programs,

scheduling requirements becomes exponentially more complex

� Integration

� Of schedules between “master” and “subordinate” schedules

� Often across multiple tiers of

�� Activities and Activities and

�� Organisations contributing to the overall program of Organisations contributing to the overall program of

workwork

� Essential for producing a useful integrated master schedule

Page 83: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 83

Copyright 2007 Lipke & Henderson

Compounding Schedule Complexity

� Once an initial schedule baseline has been established progress monitoring inevitably results in changes

� Task and activity durations change because “actual

performance” does not conform to plan

� Additional unforeseen activities may need to be added

� Logic changes as a result of corrective actions to contain slippages; and

� Improved understanding of the work being undertaken

� Other “planned changes” (Change Requests) also contribute to schedule modifications over time

Page 84: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 84

Copyright 2007 Lipke & Henderson

Wouldn’t it be nice ….

� To be able to explicitly declare “Schedule Reserve” in the project “schedule of record”

� Protect committed key milestone delivery dates

� To have schedule macro level indicators and predictors � Ideally, derived separately from the network schedule!

� Provides a means for comparison and validation of the measures and predictors provided by the network schedule

� An independent predictor of project duration would be a particularly useful metric

�� “On time” completion of projects usually considered important“On time” completion of projects usually considered important

� Just like EVM practitioners have for cost ….

� The potential offered by Earned Schedule

Page 85: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 85

Copyright 2007 Lipke & Henderson

Case Study Project

� Commercial sector software development and enhancement project� Small scale: 10 week Planned Duration � Time critical: Needed to support launch of revenue

generating marketing campaign� Cost budget: 100% labour costs

� Mixture of:� 3 tier client server development

�� Mainframe, Middleware, WorkstationMainframe, Middleware, Workstation

� 2 tier client server development�� Mainframe to Workstation directMainframe to Workstation direct

Page 86: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 86

Copyright 2007 Lipke & Henderson

The EVM and ES Approach� Microsoft Project 2002 schedule

� Resource loaded for time phased effort and cost estimation

� Control Account – Work Package views developed in the schedule

� Actual Costs captured in SAP time recording system

� Limited (actual) cost – schedule integration

� Contingency (Management Reserve) managed outside the schedule

� Top level Planned Values cum “copied and pasted” into Excel EVM and ES template

� High level of cost – schedule integration achieved

Page 87: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 87

Copyright 2007 Lipke & Henderson

Schedule Management� Weekly schedule updates from week 3 focusing on:

� Accurate task level percentage work completion updates

� The project level percentage work completion (cumulative) calculated by Microsoft Project

� Percentage work complete transferred to the EVM and ES template to derive the progressive Earned Value (cumulative)measuremeasure

� Schedule review focusing on critical path analysis� Schedule updates occurred as needed with

� Revised estimates of task duration and

� Changes to network schedule logic

particularly when needed to facilitate schedule based correctiveaction

� Actual costs entered into the EVM and ES template as they became available (weekly)

Page 88: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 88

Copyright 2007 Lipke & Henderson

An Integrated Schedule Analysis ChartCritical Path, IECD, SPI(t) and SPI($) on one page

Earned Schedule Example Project #1

Earned Schedule IECD, Critical Path, SPI(t) and SPI($)

0.4

0.6

0.8

1.0

1.2

1.4

1.6

Time (Weeks)

SP

I(t)

& S

PI(

$)

02 Aug

12 Aug

22 Aug

01 Sep

11 Sep

21 Sep

01 Oct

11 Oct

Co

mp

leti

on

Da

tes

SPI(t) cum 0.73 0.65 0.68 0.72 0.70 0.82 0.77 0.74 0.80 0.77 0.77

SPI($) cum 0.55 0.54 0.64 0.71 0.69 0.87 0.85 0.87 0.96 0.98 1.00

Planned Completion Date 31 Aug 31 Aug 31 Aug 31 Aug 31 Aug 31 Aug 31 Aug 31 Aug 14 Sep 14 Sep 14 Sep 14 Sep 14 Sep 14 Sep 14 Sep

IECD (PD/SPI(t) 23 Sep 06 Oct 30 Sep 25 Sep 27 Sep 13 Sep 19 Sep 21 Sep 15 Sep 19 Sep 19 Sep

Critical Path Completion 24 Aug 31 Aug 08 Sep 07 Sep 13 Sep 07 Sep 03 Sep 09 Sep 09 Sep 10 Sep 16 Sep

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Page 89: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 89

Copyright 2007 Lipke & Henderson

Schedule Analysis

� Initial expectation� The critical path predicted completion date would be

more pessimistic than the IECD

� In fact� The ES IECD trend line depicted a “late finish” project with

improving schedule performance

� The critical path predicted completion dates showed an “early finish project” with deteriorating schedule performance

� Became the “critical question” in Week 8� ES IECD improvement trend reversed

� Continued deterioration in the critical path predicted completion

dates

Page 90: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 90

Copyright 2007 Lipke & Henderson

Schedule Analysis Result

� IECD the more credible predictor in this circumstance� Work was not being accomplished at the rate planned

� No adverse contribution by critical path factors

� e.g. Externally imposed delays caused by “dependent milestone”

� Two weeks schedule delay communicated to management� Very late delay of schedule slippage a very sensitive issue

� Corrective action was immediately implemented� Resulted in two weeks progress in one week based on IECD

improvement in week 9

� Project substantively delivered to the revised delivery date

Page 91: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 91

Copyright 2007 Lipke & Henderson

IECD vs Critical Path Predictors

� Network schedule updates do not usually factor past (critical path) task performance into the future

� Generally concentrate on the current time window

� Task updates

� Corrective action to try and contain slippages

� Critical path predicted completion date is not usually calibrated by past actual schedule performance

� The ES IECD

� Cannot directly take into account critical path information

� BUT does calibrate the prediction based on historic schedule performance as reflected in the SPI(t)

Page 92: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 92

Copyright 2007 Lipke & Henderson

Further Observations

� Much has been written about the consequences ofnot achieving work at the EVM rate planned� At very least, incomplete work needs to be rescheduled …� Immediate critical vs non critical path implication requires

detailed analysis of the network schedule� Sustained improvement in schedule performance is a difficult

challenge� SPI(t) remained in the .7 to .8 band for the entire project!� In spite of the corrective action and recovery effort

� Any task delayed eventually becomes critical path if not completed

� SPI(t) a very useful indicator of schedule performance� Especially later in the project when SPI($) was resolving

to 1.0

Page 93: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 93

Copyright 2007 Lipke & Henderson

Questions of Scale� We know that ES is scalable as is EVM

� Issues of scale did not arise due to small size of the project

� Detailed analysis of the ES metrics is required� The same as EVM for cost

� The “masking” or “washout” effect of negative and positive ES variances at the detailed level can be an issue

� The same as EVM for cost

� Apply Earned Schedule to the Control Accounts and Work Packages on the critical path� And “near” critical path activities

� Earned Schedule augments network schedule analysis –it doesn’t replace it� Just as EVM doesn't replace a bottom up ETC and EAC

Page 94: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 94

Copyright 2007 Lipke & Henderson

Real Schedule Management with Earned Schedule

� ES is of considerable benefit in analysing and managing schedule performance

� The “time critical” dichotomy of reporting “optimistic” predicted task completions and setting and reporting realistic completion dates was avoided

� ES metrics provided an independent means of sanity checking the critical path predicted completion date

� Prior to communicating overall schedule status to management

� ES focused much more attention onto the network schedule than using EVM alone

Page 95: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 95

Copyright 2007 Lipke & Henderson

Final Thoughts

� ES is expected be of considerable value to the schedule management for large scale projects and programs

� Exponential increase in the network scheduling complexities

� Unavoidable and necessary on those programs and so

� The need and benefit of an independent means of sanity checking schedules of such complexity is much greater

� ES is anticipated to become the “bridge” between EVM and the Network Schedule

Page 96: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 96

Network Schedule Network Schedule

Analysis Analysis

Page 97: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 97

Copyright 2007 Lipke & Henderson

Schedule Analysis with EVM?

� The general belief is EVM cannot be used to predict schedule duration

� Most practitioners analyze schedule from the bottom up using the networked schedule ….“It is the only way possible.”

� Analysis of the Schedule is overwhelming

� Critical Path is used to shorten analysis(CP is longest path of the schedule)

Page 98: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 98

Copyright 2007 Lipke & Henderson

Schedule Analysis with EVM?

� Duration prediction using Earned Schedule provides a macro-method similar to the method for estimating Cost

�A significant advance in practice� But, there’s more that ES facilitates ….

Page 99: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 99

Copyright 2007 Lipke & Henderson

ES Facilitates Drill-Down Analysis

� ES can be applied to any level of the WBS, to include task groupings such as the Critical Path (CP)

� Requires creating PMB for the area of interest

� EV for the area of interest is used to determine its ES

� Enables comparison of forecasts, total project (TP) to CP

� Desired result: forecasts are equal

� When TP forecast > CP forecast, CP has changed

� When CP > TP, possibility of future problems

� And there is more ….

Page 100: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 100

Copyright 2007 Lipke & Henderson

Earned ScheduleBridges EVM to “Real” Schedule

$$

Time

PV

BAC

PD

EV

ESES ATAT

SV(t)

Page 101: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 101

Copyright 2007 Lipke & Henderson

How Can This Be Used?

� Tasks behind – possibility of impediments or constraints can be identified

� Tasks ahead – a likelihood of future rework can be identified

� The identification is independent from schedule efficiency

� The identification can be automated

PMs can now have a schedule analysis tool connected to the EVM Data!!

Page 102: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 102

BREAK BREAK –– 15 Minutes15 Minutes

Page 103: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 103

Earned Value ResearchEarned Value Research

Page 104: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 104

Copyright 2007 Lipke & Henderson

Earned Value Research

� Most research conducted since 1990

� Result of cancellation of Navy A-12 Avenger

� Primary researcher, Dr. David Christensen, Southern Utah University

� Cost studies using very large DOD projects

� EVM Literature on Dr. Christensen’s website http://www.suu.edu/faculty/christensend/ev-bib.html

Page 105: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 105

Copyright 2007 Lipke & Henderson

Results from EV Research

� Dr. Christensen’s & associates’ findings

� CPI stabilizes @ 20% complete

� CPI tends to worsen as EV ⇒ BAC

� |CPI(final) – CPI(20%)| ≤ 0.10

� IEAC = BAC / CPI ≤ Final Cost

when Percent Complete is 20% ⇔ 70%

Page 106: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 106

Copyright 2007 Lipke & Henderson

Discussion of EV Research

� CPI tends to worsen as EV ⇒ BAC

� IEAC = BAC / CPI ≤ Final Cost when Percent Complete is ≥ 20%

� IEAC condition must be true if CPI tendency is true

� Rationale supporting CPI tendency� Rework increasing as EV approaches BAC

� Late occurring impacts from constraints/impediments

� Lack of available EV toward end of project

� My conjecture: SPI(t) & IEAC(t) = PD / SPI(t) behave similarly to CPI & IEAC = BAC / CPI

Page 107: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 107

Copyright 2007 Lipke & Henderson

CPI & IEAC Behavior

CPIcum versus

Percent Complete

0.96

0.98

1.00

1.02

1.04

1.06

0.2 0.4 0.6 0.8 1.0

Percent Complete

CP

Icu

m

IEAC Behavior

-0.10

-0.08

-0.06

-0.04

-0.02

0.00

0.2 0.4 0.6 0.8 1.0

Percent CompleteP

erce

nt

Dif

fere

nce

(IE

AC

- F

inal

Cost

) / F

inal

Cost

Page 108: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 108

Schedule Adherence Schedule Adherence

Page 109: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 109

Copyright 2007 Lipke & Henderson

EV and Task Sequence

� EV isn’t connected to task sequence

� Hypothesis: Completion sequence of tasks affects performance efficiency

� Incorrect task sequencing occurs when there is..

� Impediment or constraint

� Poor process discipline

� Improper performance sequence may cause …

� Overloading of constraint

� Performance of tasks w/o complete inputs

Page 110: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 110

Copyright 2007 Lipke & Henderson

Result of Improper Sequence

� Result from improper performance sequence …� Constraint limited output

� Schedule lengthens� Cost increases while waiting (when other EV

available is severely limited) � Rework occurs (~ 50%)

� Schedule lengthens� Cost escalates

� Constraint problem & Rework appear late causing …� CPI & SPI(t) to decrease as EV ⇒ BAC

Page 111: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 111

Copyright 2007 Lipke & Henderson

Measure of Schedule Adherence

� Generally, following the schedule yields the most efficient performance

� Following the schedule requires maintaining the precedence relationship between tasks

� Determining manually whether or not precedence is being maintained is tedious and exceedingly difficult for large projects

� A method is needed to measure and report schedule adherence …automatically

� Earned Schedule provides the answer. ES provides the ability to compare actual schedule performance to the planned network schedule.

Page 112: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 112

Copyright 2007 Lipke & Henderson

ES Facilitates the Measure � The following chart illustrates the idea of Schedule

Adherence.

� ES is found from a point on the PMB. The value of PV at that point determines the tasks which should becompleted, or in-work.

� The tasks to the left of the red ES line should be colored green up to the line, indicating accomplishment. The tasks to the right of the ES line should not be colored green.

� But …tasks to the right of the ES line are colored green, indicating task precedence has not been maintained.

� The measure of Schedule Adherence, P, is determined by the EV to the left of the ES line divided by the total EV accrued.

Page 113: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 113

Copyright 2007 Lipke & Henderson

Earned ScheduleBridges EVM to Network Schedule

$$

Time

PV

BAC

PD

EV

ES AT

SV(t)

Page 114: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 114

Copyright 2007 Lipke & Henderson

Schedule Adherence� Schedule Adherence measure is used to

enhance the EVM measures

� Early warning for later cost and schedule problems

� Adherence Measure: From the project plan, determine the

tasks which should be completed or started for the duration associated with ES. Compare the associated PV with the EV of the tasks which directly correspond. A condition of the EV credited for the matching tasks is they cannot exceed the corresponding PV value. Calculate the ratio:

P =Σ EVj (matching tasks) / Σ PVj (@ ES)

where EVj is restricted to ≤ PVj & Σ PVj = EV

Page 115: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 115

Copyright 2007 Lipke & Henderson

Schedule Adherence� Characteristics of the P measure

� P measure cannot exceed 1.0

0 ≤ P ≤ 1.0

� At project completion P = 1.0

� P is likely unstable until project is 20% complete {similar to the behavior of CPI}

� The behavior of P may explain Dr. Christensen’s findings for CPI & IEAC

� P used to compute effective earned value {EV(e)}

Page 116: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 116

Effective Earned Value Effective Earned Value

Page 117: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 117

Copyright 2007 Lipke & Henderson

Effective Earned Value

ΣΣΣΣEVj ⇐⇐⇐⇐ PV @ ES

Total EV

EV(r) is performed at risk of creating reworkPortion colored is usablePortion colored is unusable

EV(r)

Effective EV

Page 118: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 118

Copyright 2007 Lipke & Henderson

Effective EV Relationships

� P-Factor (or P) = ΣEVj / ΣPVj = ΣEVj / EV

ΣEVj = P ∗ EV

� EV(p) is portion of EV consistent with the plan

EV(p) = ΣEVj = P ∗ EV

� EV(r) is portion of EV with anticipated rework

EV(r) = EV – EV(p) = EV – P ∗ EV

EV(r) = (1 – P) ∗ EV

Page 119: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 119

Copyright 2007 Lipke & Henderson

Effective EV Relationships

� Rework proportion, R = f(r) / f(p)

f(r) = fraction of EV(r) unusable

f(p) = fraction of EV(r) usable

f(r) + f(p) = 1

� Portion of EV(r) usable

f(r) = f(p) ∗ R ….thus

(f(p) ∗ R) + f(p) = 1

f(p) = 1 / (1 + R)

Page 120: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 120

Copyright 2007 Lipke & Henderson

Effective Earned Value

� Effective earned value is a function of EV, P, and Rework: EV(e) = f (EV, P, Rework)

EV(e) = EV(p) + (fraction usable) ∗ EV(r)

= P ∗ EV + [1 / (1 + R)] ∗ [(1 − P) ∗ EV]

� General equation for Effective Earned Value

EV(e) = [ (1 + P ∗ R) / (1 + R) ] ∗ EV

� Special case, when R = 1/2

EV(e) = [ (P + 2) / 3 ] ∗ EV

Page 121: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 121

Copyright 2007 Lipke & Henderson

Effective Earned Value

� Effective ES is computed using EV(e)

{i.e., ES(e)}

� Effective EV and ES indicators are …

� CV(e) = EV(e) – AC

� CPI(e) = EV(e) / AC

� SV(te) = ES(e) – AT

� SPI(te) = ES(e) / AT

Page 122: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 122

Copyright 2007 Lipke & Henderson

CPI, CPI(e) & P - Factor (notional data)

0.7

0.8

0.9

1.0

1.1

1.2

0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0

Percent Complete

Ind

ex V

alu

e

CPI

CPI(e)

P – Factor

Page 123: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 123

Copyright 2007 Lipke & Henderson

CPI, SPI(t) & P - Factor (real data)

0.7

0.8

0.9

1.0

1.1

1.2

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0

Percent Complete

Ind

ex V

alu

e CPI

CPI(e)

SPI(t)

SPI(te)

P- Factor

Page 124: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 124

Prediction & ForecastingPrediction & Forecasting

using using

Effective Earned ValueEffective Earned Value

Page 125: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 125

Copyright 2007 Lipke & Henderson

Prediction withPrediction with

Effective Earned ValueEffective Earned Value

TCPI = [BAC – EV(e)] / [EAC – AC]Estimated Cost

TCPI = [BAC – EV(e)] / [BAC – AC]Planned Cost

TSPI = [PD – ES(e)] / [ED – AT]Estimated Duration

TSPI = [PD – ES(e)] / [PD – AT]Planned Duration

Not Achievable> 1.10

Achievable≤ 1.00

Predicted OutcomeT_PI Value

Page 126: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 126

Copyright 2007 Lipke & Henderson

Forecasting withEffective Earned Value

IEAC(e) = BAC / CPI(e)Cost Prediction

IEAC(te) = PD / SPI(te)Schedule Prediction

Page 127: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 127

Copyright 2007 Lipke & Henderson

Schedule & Cost Forecasts

Cost Forecast Comparison

$950

$1,050

$1,150

$1,250

0.2 0.4 0.6 0.8 1.0

Percent Complete

(x 1

000)

Schedule Forecast Comparison

35

37

39

41

43

45

0.2 0.4 0.6 0.8 1.0

Percent CompleteM

on

ths

IEAC(e)

IEAC

BAC = $1,000,000PD = 36 months

IEAC(t)

IEAC(te)

Page 128: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 128

Copyright 2007 Lipke & Henderson

Summary:Effective Earned Value� Lack of adherence to the schedule causes EV to

misrepresent project progress

� P indicator introduced to measure schedule adherence

� Effective EV calculable from P, R and EV reported

� Prediction & Forecasting for both final cost and project duration hypothesized to be improved with Effective Earned Value

Page 129: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 129

Statistical Prediction Statistical Prediction

Page 130: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 130

Copyright 2007 Lipke & Henderson

Statistical Prediction

� Statistical Process Control

� Planning for Risk

� Performance Indication & Analysis

� Outcome Prediction

Page 131: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 131

Copyright 2007 Lipke & Henderson

Application Problems

� Distributions of periodic values of CPI & SPI(t) are right-skewed

� Logarithms transform to Normal Distribution

� Research indicates CPI tends to worsen as

EV ⇒ BAC

� Statistics application assumes lack of any tendency

� Effective EV used to remove tendency

Page 132: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 132

Copyright 2007 Lipke & Henderson

Statistical Process Control

� SPC is a Quality method used to identify anomalous behavior of the process

� For application to CPI and SPI(t), SPC is used to identify anomalous periodic performance

� Clarifies “true” performance

� Allows better analysis

� Improves prediction

Page 133: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 133

Copyright 2007 Lipke & Henderson

Statistical Process Control

-1

-0.5

0

0.5

1

1.5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

0.266σ =

0.994SPI(t) =

ln(SPI)

Months

+3σ

-3σ

anomaly

Page 134: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 134

Copyright 2007 Lipke & Henderson

Planning for Risk

� Risk mitigation ⇒ Schedule Reserve

� Data needed

� Performance variation from similar historical project

[Standard Deviation = σH]

� Planned Duration of new project [provides the number of performance observations (n)]

� Variation of Means (ln SPI(t)m-1) = σH / √ n = σm

� Probability of Success Desired (PS)

Page 135: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 135

Copyright 2007 Lipke & Henderson

Means (ln SPI(t)m-1)

Rel

ati

ve

Fre

qu

ency

ln Schedule Ratio

ln SPI(t)c-1

Area of Success Failure

Planning for Risk

Page 136: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 136

Copyright 2007 Lipke & Henderson

Performance Indication & Analysis

� Performance Window Indicator

� Combines CPI & SPI(t) onto one chart

� Depiction is invariant to project size

� Provides visual of performance in relation to Plan & Negotiated requirement

� Illustrates diminishing opportunity for recovery

� Provides Probability of Success separately for Cost & Schedule

Page 137: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 137

Copyright 2007 Lipke & Henderson

Performance Indication & Analysis

0

0.5

1

1.5

2

2.5

3

0 0.5 1 1.5 2 2.5 3

Time

Co

st

0.565ΡSΡSPlan

sc ==

0.772ΡSΡS

Complete 50% ~

sc ==

Note: Graph axes scales are multipliers of Budget at Completion (Cost) and Period of Performance (Time).

Performance - Plan and 50% CompleteSPI-1avg = 1.0, CPI-1avg = 1.0

Red - Failure

Yellow - Reserves

Green - Plan

Schedule distribution

Cost distribution

Page 138: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 138

Copyright 2007 Lipke & Henderson

Outcome Forecasting

� Apply SPC to establish “true” performance for CPI & SPI(t)

� Residual Cumulative value

� Standard Deviation of periodic performance

� Compute the adjustment for accomplished portion of project

� Compute adjusted Standard Deviation of the Means (σ∗)

Page 139: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 139

Copyright 2007 Lipke & Henderson

Outcome Forecasting

� Using the results …

� Determine Confidence Limits for the Performance Window – e.g., 95% confidence ….that is, the high and low expectations for performance

� Calculate Probability of Success for both Cost & Schedule separately

Page 140: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 140

Summary Summary -- Advanced Advanced

Page 141: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 141

Copyright 2007 Lipke & Henderson

Summary - Advanced

� Project analysis tool [EV & ES application]

� Re-baseline impacts SPI(t) similarly to CPI

� Duration prediction from ES much easier than using Critical Path analysis …and may be better

� Network schedule analysis enhanced by ES

� Identifies future problems & today’s impediments

Page 142: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 142

Copyright 2007 Lipke & Henderson

Summary - Advanced

� ES connects EV to the schedule

� Schedule Adherence

� Effective Earned Value

� Possible enhancement of outcome prediction for schedule & cost

� Statistical techniques provide facility to improve planning, analysis, and outcome prediction

Page 143: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 143

Quiz & Discussion Quiz & Discussion

Page 144: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 144

Copyright 2007 Lipke & Henderson

Question #1

� What is the problem with the EVM schedule indicators, SV and SPI?

O They measure schedule performance in $$

O They sometimes are erroneous

O They can be poor predictors of outcome

O All of the above

Page 145: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 145

Copyright 2007 Lipke & Henderson

Question #2

� Why do SPI & SV fail to provide reliable schedule information ?

O EVM measures schedule performance in $$

O PV is constrained to BAC

O They are not related to the networked schedule

O All of the above

Page 146: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 146

Copyright 2007 Lipke & Henderson

Question #3

� What elements are required to compute Earned Schedule?

O AT & EV

O AC & PMB

O EV & PV

O EV & PMB

O All of the above

Page 147: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 147

Copyright 2007 Lipke & Henderson

Question #4

� What does Earned Schedule measure?

O Time at which Actual Cost appears on PMB

O Time at which Planned Value equals Earned Value

O Time at which Earned Value is reported

O None of the above

Page 148: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 148

Copyright 2007 Lipke & Henderson

Question #5

� The equation for Earned Schedule is

EScum = C + I. How is I calculated?

O I must be determined graphically

O I = EV / PV

O I = (EV – PVC) / (PVC+1 – PVC)

O I = ∆EV / ∆PV

Page 149: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 149

Copyright 2007 Lipke & Henderson

Question #6

� What is the largest source of error for the Earned Schedule measure?

O Earned Value reported

O Interpolated portion of the ES value

O Earned Value accounting practice

O Crediting first month as a full month

Page 150: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 150

Copyright 2007 Lipke & Henderson

Question #7

� Earned Schedule can be used to provide information about future rework and project constraints and impediments.

O True

O False

Page 151: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 151

Copyright 2007 Lipke & Henderson

Question #8

� What fundamental elements are needed to predict the completion date for a project?

O Start Date + AC, EV, PV

O Start Date + AC, AT, PMB

O Start Date + PMB, EV, AT

O Start Date + PV, PMB, AT

O Start Date + ES, AT, PD

Page 152: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 152

Copyright 2007 Lipke & Henderson

Question #9

� What does the P-Factor help us understand about project performance?

O How closely the project is following its plan

O Why performance has the tendency to become less efficient as EV ⇒ BAC

O Improves analysis of true project accomplishment

O All of the above

Page 153: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 153

Copyright 2007 Lipke & Henderson

Question #10

� How does Effective Earned Value differ from Earned Value?

O Effective EV ≤ EV

O Effective EV accounts for rework

O Allows for earlier prediction of final project outcome

O All of the above

O None of the above

Page 154: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Copyright 2007 Lipke & Henderson Sydney Australia 20 August 2007 154

WrapWrap--Up Up

Page 155: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 155

Copyright 2007 Lipke & Henderson

Wrap Up

� Derived from EVM data … only

� Provides time-based schedule indicators

� Indicators do not fail for late finish projects

� Application is scalable up/down, just as is EVM

� Schedule prediction is better than any other EVM method presently used

� SPI(t) behaves similarly to CPI

� IEAC(t) = PD / SPI(t) behaves similarly to

IEAC = BAC / CPI

Page 156: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 156

Copyright 2007 Lipke & Henderson

Wrap Up� Schedule prediction – much easier and possibly better

than “bottoms-up” schedule analysis

� Facilitates bridging EVM to schedule analysis

� Identification of Constraints / Impediments and Rework

� Calculation of Schedule Adherence

� Creation of Effective Earned Value

Leads to improved Schedule & Cost Forecasting

Page 157: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 157

Copyright 2007 Lipke & Henderson

Conclusion

� “Whatever can be done using EVM for Cost Analysis can also be done using Earned Schedule for Schedule Analysis”

� Earned Schedule

� A powerful new dimension to Integrated Project Performance Management (IPPM)

� A breakthrough in theory and application

the first scheduling system

Page 158: ES Workshop Sydney Aug 2007 - Project Controls and CPM ...microplanning.com.au/wp-content/uploads/downloads/... · ES Applied to Real Project Data: Late Finish Project Analysis No

Sydney Australia 20 August 2007 158

Copyright 2007 Lipke & Henderson

Contact Information

+61 414 428 537Phone+1 405 364 1594

[email protected]@cox.net

Kym HendersonWalt Lipke


Recommended