+ All Categories
Home > Documents > Estimates

Estimates

Date post: 01-Dec-2015
Category:
Upload: gage-floyd-eroc-bitayo
View: 1,136 times
Download: 0 times
Share this document with a friend
Popular Tags:
48
Table of Contents 1. History of Concrete 2. Excavation and Earthfil 3. Angle of Repose 4. Concrete Proportioning 5. Concrete Mixture 6. Approximate Time Limit before the Removal of Forms and Supports 7. Amount of water per bag of cement 8. Approximate quantity of surface water carried by average aggregates 9. Fuller’s Formula 10. Masonry/ CHB 11. Plaster, CHB Finish per Sq. M. 12. Mortar 13. Volume of cement per CHB 14. Materials required for 1000 square ft. of varying thickness of mortar 15. Quantity of mortar per 1000 bricks 16. Requirements for mortar 17. Concrete Pipe Joint Collars 18. Factor per adobe stone 19. Mortar 1 cm. Thick for adobe stone concrete factor 20. Concrete footing for CHB 21. Adobe stone for zocalo wall and foundation 22. Adobe Plaster 23. Red ceramic blocks 24. Miscellaneous Bricks and Stone 25. Adobe Buttress 26. Decorative blocks mortar 27. Lumbering (board measure/ Bd. Ft.) 28. Floor Joists 29. T & G Flooring 30. External Sidings 31. Studs Bd. FT. of Studs Per Square Meter 32. Ceiling Joist/ Ceiling Board 33. Trusses and Rafters 34. Quantity of nails per 1000 board Ft. 35. Size of Posts 36. Roofings 37. Purlins for Standard Corrugated G.I. Roofs 38. Corrugated Roofing Sheets 39. Estimating Procedures 40. Roofing Hardwares 41. Plain G.I. Straps per sheet 42. Roofing Nails and Hardwares 43. Kinds of Asbestos Roofing
Transcript
Page 1: Estimates

Table of Contents

1. History of Concrete2. Excavation and Earthfil3. Angle of Repose4. Concrete Proportioning5. Concrete Mixture6. Approximate Time Limit before the Removal of Forms and Supports7. Amount of water per bag of cement8. Approximate quantity of surface water carried by average aggregates9. Fuller’s Formula10. Masonry/ CHB11. Plaster, CHB Finish per Sq. M.12. Mortar13. Volume of cement per CHB14. Materials required for 1000 square ft. of varying thickness of mortar15. Quantity of mortar per 1000 bricks16. Requirements for mortar17. Concrete Pipe Joint Collars18. Factor per adobe stone19. Mortar 1 cm. Thick for adobe stone concrete factor20. Concrete footing for CHB21. Adobe stone for zocalo wall and foundation22. Adobe Plaster23. Red ceramic blocks24. Miscellaneous Bricks and Stone25. Adobe Buttress26. Decorative blocks mortar27. Lumbering (board measure/ Bd. Ft.)28. Floor Joists29. T & G Flooring30. External Sidings31. Studs Bd. FT. of Studs Per Square Meter32. Ceiling Joist/ Ceiling Board33. Trusses and Rafters34. Quantity of nails per 1000 board Ft.35. Size of Posts36. Roofings37. Purlins for Standard Corrugated G.I. Roofs38. Corrugated Roofing Sheets39. Estimating Procedures40. Roofing Hardwares41. Plain G.I. Straps per sheet42. Roofing Nails and Hardwares43. Kinds of Asbestos Roofing44. 4-V Corrugated Sheets45. Placa Romana46. Tencor Corrugated sheets47. Ardex Corrgated sheets48. Ceramic roofing tiles49. Tile work50. Precast Terrazo and Granulithic tiles51. Vinyl and rubber tiles52. Moldings53. Bathroom tiles and accessories

Page 2: Estimates

54. Reinforcement55. Weights and Hook allowance of rod Philippine Standard56. No. of Pcs. Of Lateral tie in one 6.0M bar57. Lateral tie and tie wire computation by direct counting method58. Length of spiral reinforcement59. Concrete slab reinforcement60. CHB – reinforcement61. CHB – rebar62. Horizontal bar spacing63. Electrical estimates64. Painting works65. Spreading rate of paint66. Kinds of paint67. Paint coverage68. Labor estimate69. Construction work capacities in manhours70. Capabilities of manual labor per hour71. Capabilities of equipment72. Longitudinal section of septic vault73. Inside dimensions of the digestion chamber74. Important features of septic vaults75. Average pol consumption for various construction equipment76. Rough estimates77. General checklist78. Checklist of items to be considered79. Site excavation and siteworks80. Sample computations81. Excavation and backfil82. Lumbering, roofing, tilework83. Reinforcing bars84. CHB reinforcement85. Drawings86. Symbols87. Switches88. Common nails and spikes89. Mensuration formulas90. Materials symbols plans and sections91. Feet head of water to PSI92. Water pressure to feet head93. Simplified table for conversion94. Conversion from Inches to meter95. List of abbreviations

History of Concrete

Concrete, as we know it today, had its beginning in 1824, when Joseph Aspdin took out a patent in England on “Portland” cement. Concrete became widely used in Europe during the late 1800’s and was brought to the United States late in that century and in all over the world. Its used continued to spread rapidly as knowledge about it and experience with it grew.

Page 3: Estimates

Concrete

Concrete = is a stone like material obtained by permitting a carefully proportioned mixture of cement, gravel and sand or other inert materials, and water to harden in forms of the shape and dimensions of the desired structures.

Estimating = is a project study of determining the quality, quantity and cost of every material used in a mass, or in every finished work.

Excavation & Earth Fill

Excavation = a hallow cavity formed by cutting or digging out earth, an open earth cutting.

Excavator = one who or that which excavates a digging machine.

Please refer to Table 1-1 for Angle of Repose Slope and Weight of Earth.

EARTH FILL:Compact Volume = 1.25 VWhere: V = Loose VolumeOne truck load = 4 to 6 cu. meter

Angle or ReposeTable 1-1

Type ofMaterials

ApproximateSlope: A/B

Angle of Repose Wt./ Cu. Ft. Lbs.

Sand Dry 1/ 2.8 to 1/ 1.4 20 to 35 90 to 110Sand Moist 1/ 1.75 to 1/ 1.0 30 to 45 100 to 110Sand Wet 1/ 1.8 to 1/ 1.2 20 to 40 110 to 120Ord. Earth, Dry 1/ 2.8 to 1/ 1.0 20 to 45 80 to 100Ord. Earth, Moist 1/ 2.1 to 1/ 1.0 25 to 45 80 to 100Ord. Earth, Wet 1/ 2.1 to 1/1.75 25 to 30 100 to 120Gravel 1/ 1.75 to 1/ 0.90 30 to 48 100 to 135Gravel, Sand & Clay 1/ 1.80 to 1/ 1.30 20 to 30 100 to 115

Concrete ProportioningTable 1-2QUANTITY FOR 1 CU.M. CONCRETE

USING 94 LBS PORTLAND CEMENT

Class Proportion Cement Sand Gravel

AA 1 : 2 : 3 10.50 0.42 .84A 1 : 2 : 4 7.84 0.44 0.88B 1: 2.5 : 5 6.48 0.44 0.88C 1 : 3 : 6 5.48 0.44 0.88D 1: 3.5 : 7 5.00 0.45 0.90

Page 4: Estimates

USING 88 LBS PORTLAND CEMENT

A 1 : 2 : 4 8.20 0.44 0.88B 1 : 2.5 : 6.80 0.46 0.88C 1 : 3 : 6 5.80 0.47 0.89D 1: 3.5 : 7 5.32 0.48 0.90

NOTE:

Class A = Shall be used for beams, slabs, columns, and for all members which are subjected to bending stress.

Class B = Shall be used for all members not reinforced for bending stress. Class C = Used for footing not under water.

Concrete MixtureTable 1-3

Type of Construction Proportion

Side Walk 4” thick 1 : 2 : 4Floor Slab 4” thick 1 : 2 : 4Wall 1 : 2.5 : 5Footing 1 : 2.5 : 5Post 1 : 2.5 : 5Machinery Foundation 1 : 3 : 6Reinforced Concrete 1 : 2 : 4Foundations 1 : 2.5 : 5Top Dressing on Wearing Surp. 1 : 2 :Water Roofing 1 : 2

NOTE: Keep all concrete wet 7-days and protect from sun.

Approximate Time LimitBefore the Removal ofForms and Supports:

Table 1-4

Arch Centers 14-21 DaysCentering Under Beams 14 DaysFloor Slabs 3-10 DaysWalls 7-14 DaysColumns, Slides of Beams and Griders 3-10 Days

Amount of Water

Page 5: Estimates

Per Bag of CementTable 1-5

Mix Type of Const.

Gallon of Water/ Bag Mix

Dry Mix Moist Mix Wet Mix Aggr. ø

1 : 3 : 5 Figs. Reinf. Wall 7.5 6.0 5.0 2”1 : 2 : 3 Side Walk, Step 5.5 4.5 3.75 1”1 : 2 : 2 Fence Post 4.5 3.75 3.5 ¾”

WATER CEMENT RATIO

Us Gal./ 94 Lbs Bag Cem. Assumed Comp. Stress at 28 Days

7.5 2000 PSI6.75 2500 PSI6.0 3000 PSI5.0 3750 PSI

Approximate Quantity ofSurface Water Carried by

Average AggregatesTable 1-6

Aggregate Classification Gal. Cu. Ft.Very Wet Sand 3/ 4 to 1/ 0Moderately Wet Sand 1/ 2Moist Sand 1/ 4Moist Gravel, Crushed Rocks 1/ 4

FULLER’S FORMULA

Let C = No. of Part Cement, S = Sand G = Gravel or Stone, Then:

Px = 1 = no. of barrel portland cement required for one cu. yd. of concrete C+S+G

Pm = 32.2875 Px = no. of barrel portland cement required for one cu. m. of concrete

Pm x S x 3.8 = no. of cubic meter sand for one cubic meter of concrete

32.2875

Pm x G x 3.8 = no. of cubic meter gravel for one cubic meter of concrete

32.2875

NOTE: 1 barrel = 4 bags of 96 Lbs. Portland cement = 3.76 Cu. Ft.

Page 6: Estimates

Masonry

There are different kinds of sizes and patterns of locally available materials classified under masonry. Three kinds are as follows:1) Block 2) Brick 3) Tile

CHB = Concrete Hollow Block

Table 2-1

Stock Cell Volume Per Block Plas. Vol/ Blk.Width 1 Cell 2 Cells 3 Cells 4 Cells 1 Face 2 Faces

4” 0.0007 0.0014 0.0021 0.0028 0.0010 0.00205” 0.001 0.002 0.003 0.004 0.0010 0.00208” 0.002 0.004 0.006 0.008 0.0010 0.00203” None None None None 0.00.10 0.0020

13 CHB PER SQ.M. OF WALL AREASAND APPROX. 1/ 10/ BAG CEMENT

Table 2-2

CHB LAID PER BAG CEMENT:4” x 8” x 16” 55 to 60 Pieces6” x 8” x 16” 30 to 36 Pieces8” x 8” x 16” 25 to 30 Pieces

NOTE:

1 Bag of Cementequal = one cubic ft.

PlasterTable 2-3

Class Mix Cement Lime Sand In Bags Cu.M.

A 1 : 2 8.5 8.5 0.90B 1 : 3 5.5 5.5 0.90C 1 : 4 4.5 4.5 0.90

Plaster Vol. Per Sq. M. = 0.012 Cu. M.

CHB FINISH PER SQUAREMETER

Type of FinishingCement Sand

Bag Cu. M.Tooled Finish 1 / 8 0.0107Plaster Finish 1 / 4 0.0213

Page 7: Estimates

MORTAR

Proportion 1.1 1.2 1.3 1.4 1.5 1.6Cement 24.08 16.24 12.04 9.44 7.88 7.60Sand 0.65 0.87 0.97 1.02 1.06 1.10

Volume of CementPer CHB

4” x 8” x 16” 0.001 Cu. M.6” x 8” x 16” 0.003 Cu. M.8” x 8” x 16” 0.004 Cu. M.

Materials Required For1000 Square Ft. of Varying

Thickness of MortarTable 2-4

Thickness Proportionof 1 : 2 1 : 3

Mortar Cem. Bag Cu. Ft. Sand Cem. Bag Cu. Ft. Sand3 / 8” 1.4 2.8 1.0 3.01 / 2” 1.8 3.6 1.3 4.03 / 4” 2.7 5.4 2.0 6.0

1” 3.7 7.4 2.7 8.11 1/ 4” 4.5 9.0 3.3 101 1/ 2” 5.4 10.8 4.0 121 3/ 4” 6.4 12.8 4.8 14.1

2” 7.3 14.6 5.4 16.2

Quantity of Mortar Per 1000 BricksTable 2.5

Joints 3/ 16 8 cubic feetJoint 5/ 16 12 cubic feetJoints 1/ 4 12 cubic feetJoints 3/ 8 15 cubic feetJoints 1/ 8 18 cubic feet

Requirements for MortarTable 2-6

Kinds Mix Cement Sand

Plain Cement Floor Finish 1 : 2 0.33 B/ SM 0.0018 CM/SMCem. Plas. Fin. 38 Thk. One Face “ 0.11 “ 0.006 “Peeble Wash Out Floor Finish “ 0.43 “ 0.024 “Laying of 6” CHB “ 0.63 “ 0.37 “4” Fill All Holes & Joints “ 0.36 “ 0.019 “Plaster Perlite “ 0.22 “ 0.12 “Grouted Riprap : 3 4 B / CM 0.324 CM/ CM

Page 8: Estimates

Concrete Pipe Joint Collars

A. 4” Ø Non-Reinf. Conc. Pipe 1 : 2 0.02 B/ JT 0.001 CM/ JTB. 6” Ø Non-Reinf. Conc. Pipe 1 : 2 0.03 B/ JT 0.002 CM/ JTC. B” Ø Non-Reinf. Conc. Pipe 1 : 2 0.05 B/ JT 0.003 CM/ JTD. 12” Ø Non-Reinf. Conc. Pipe 1 : 2 010 B/ JT 0.005 CM/ JTE. 15” Ø Reinf. Conc. Pipe 1 ; 2 0.15 B/ JT 0.008 CM/ JTF. 18” Ø Reinf. Conc. Pipe 1 ; 2 0.20 B/ JT 0.011 CM/ JTG. 24” Øreinf. Conc. Pipe 1 : 2 0.35 B/ JT 0.019 CM/ JTH. 30” Ø Reinf. Conc. Pipe 1 : 2 0.50 B/ JT 0.027 CM/ JTI. 36” Ø Reinf. Conc. Pipe 1 : 2 0.70 B/ JT 0.038 CM/ JTJ. 42” Ø Reinf. Conc. Pipe 1 : 2 0.95 B/ JT 0.051 CM/ JTK. 48” Ø Reinf. Conc. Pipe 1 : 2 0.20 B/ JT 0.065 CM/ JT

Mortar 1 CM Thick for Adobe Stone

Factor Per Adobe Stone

1. Cross Footing …………………… 0.00065 cu. one side2. Buttress and Stairs ……………… 0.001575 cu. two sides one end3. Wall ……………………………… 0.009 cu. m. one side one end

Mortar 1 Cm. Thick for Adobe StoneTable 2-7

Stock Size Cubic Meter/ Stone No. of Pcs./ Sq. M6” x 6” x 16” 0.002 18

6” x 12” x 16” 0.004 10

Concrete Footing for CHB(Jackbilts Specification)

Table 2-8

Concrete Hollow Footing Footing VolumeThickness Thickness Width Meter

3” 4” (0.10) 12” (0.30) 0.03 Cu. M.4” 4” (0.10) 12” (0.30) 0.03 Cu. M.6” 6” (0.15) 14” (0.35) 0.0525 Cu. m.8” 8” (0.20) 16” (0.40) 0.08 Cu. M.

Adobe Stone for ZocaloWall and Foundation

(Based on 0.15 M x 0.35 M x 0.45 M Blocks)Table 2-9

1. Wall 13 pcs. Per sq. m.2. Cross Footing 6 pcs. Per meter run3. Adobe Stair 90 pcs. Per cu. m.

Page 9: Estimates

Adobe PlasterTable 2-10

Plastering Bag Cement Per Stone SandClass A Class B

One Face 0.0152 0.010125 0.00085Two Faces 0.0304 0.020250 0.00170

Red Ceramic BlocksTable 2-11

Stock Size Wall Thickness Pieces Sq. M.2” x 4” x 10” 2” 32

4” 593” x 4” x 10” 3” 32

4” 424” x 4” x 10” 4” 32

3” x 10” x 10” 3” 1410” 42

Miscellaneous Bricks and StoneTable 2-12

Stock Pieces Per Bag cem./ sq.m (1” mortar) SandSize Sq. Meter Class “A” Class “B” Cu.M.

2” x 4” 200 0.45 0.30 0.0252” x 6” 133 0.45 0.30 0.0252” x 8” 100 0.45 0.30 0.0252” x 10” 80 0.45 0.30 0.025

Adobe ButtressTable 2-13

Finished Cross Section No. of Stone PerMKS FPS Course Meter Height

0.35 x 0.50 14” x 20” 2 120.50 x 0.50 20” x 20” 3 180.50 x 0.65 20” x 26” 4 240.50 x 0.80 20” x 32” 5 300.50 x 0.95 20” x 38” 6 36

NOTE: When wall is supported by buttress then,

1. Estimate first for the buttress stone2. Estimate stone for wall3. Cross footing estimated as continuous

Page 10: Estimates

Decorative Blocks Mortar

Table 2-14

Stock Size inches Pcs. Per Sq. Meter Cem./ Blk Bag Sand/ Blk. Cu. M.2 1/ 4 8 1/ 2 5 54.4 0.000880 0.000024 x 7 1/ 4 x 7 1/ 4 25.6 0.004070 0.00011

4 x 7 x 7 27.5 0.003940 0.000114 x 5 1/ 2 x 9 ½ 23.0 0.004220 0.00012

4 x 9 x 10 24.0 0.005342 0.000154 x 8 5/ 8 x 10 33.2 0.005202 0.00014

4 x 8 x 8 22.5 0.004500 0.000134 x 8 x 10 17.8 0.005062 0.00014

4 x 10 x 11 16.0 0.005910 0.000164 x 10 x 10 13.5 0.005620 0.00015

Lumbering(Board Measure = Board Ft.)

Table 3-1

SIZE L E N G T H S1” X 2” 6’ 8’ 10’ 12’ 14’ 16’ 18’

1 1.33 1.66 2 2.33 2.66 34 2 2.66 3.33 4 4.66 5.33 66 3 4 5 6 7 8 98 6” 8” 10” 12” 14” 16” 18”

4 5.33 6.33 8 9.33 10.66 1210 5 6.66 8.33 10 11.66 13.33 1512 6 8 10 12 14 16 18

2” x 2” 2 2.66 3.33 4 4.66 5.33 63 3 4 5 6 7 8 94 4 5.33 6.66 8 9.33 10.66 126 6 8 10 12 14 16 18

2” x 8” 8 10.66 13.33 16 18.66 21.66 2410 10 13.33 16.66 20 23.35 26.66 3012 12 16 20 24 2.8 32 36

3” x 3” 4.5 6 75 8 10.50 12 13.54 6 8 10 12 14 16 186 9 12 15 18 21 24 2718 12 16 20 24 28 32 3610 15 20 24 30 35 40 4512 18 24 30 36 42 48 54

4” x 4” 8 10.66 13.33 16 18.66 21.33 245” x 5” 12.5 16.66 20.83 25 29.66 33.33 37.5

Page 11: Estimates

Floor Joists(Board Ft. of Floor Joist Per Square Meter)

Table 3-2

SIZE INCHES SPACING ON CENTER10” (0.25) 12” (0.30) 14” (0.35)

2 x 4 12.26 10.78 9.502 x 5 18.08 13.81 11.742 x 6 18.11 16.10 14.082 x 7 21.12 18.78 16.422 x 8 24.15 21.33 17.72

2 x 10 30.18 26.73 23.473 x 4 18.11 16.10 14.083 x 5 22.63 20.12 17.603 x 6 24.18 24.15 21.123 x 7 31.70 28.17 24.653 x 8 36.22 32.20 28.17

3 x 10 45.27 39.00 35.21

Steps:

1. Subtract all floor openings from gross floor area.2. Round total to 100 bd. ft.3. For girts, girders, post, etc. – Estimate by direct counting

T & G FlooringTable 3-3

Stock Size No./ M. Run Bd. Ft./ Sq. M.1” x 3” 18.30 20.001” x 4” 12.50 13.701” x 6” 8.0 10.801” x 8” 5.8 8.34

Solve gross area and subtract all openings.

External SidingsTable 3-4

Stock Size Effective Width Bd. Ft./ Sq. M.1” x 3” 2 1/ 8 16.221” x 4” 3 1/ 8 14.831” x 5” 4 1/ 8 13.341” x 6” 5 1/ 8 13.001” x 8” 6 1/ 8 12.86

Studs Board Ft. of Studs Per Square MeterTable 3-5

SROCK SIZE S P A C I N G0.40 X 0.40 0.40 X 0.60 0.60 X 0.60

2 x 2 6.410 5.50 4.502 x 3 9.630 8.40 6.802 x 4 12.840 10.90 9.00

Page 12: Estimates

Ceiling JoistTable 3-6

Stock BOARD FT. PER SHEET OF CEILING PANELSize 3” x 6” 4’ x 8’ 5’ x 10’

18” x 24” 18” 24” 24” x 18” 16 24” x 20” 20o.c o.c. bw. o.c. bw. o.c. o.c. bw. o.c. o.c. bw.

1” x 2” 3.85 4.4 5.862 7.326 8.800 10.076 11.002” x 2” 7.70 8.8 11.726 14.663 17.400 20.152 22.002” x 3” 11.55 18.20 17.600 22.000 26.400 30.250 33.002” x 4” 15.40 17.60 29.450 29.330 35.200 40.300 44.00

Ceiling BoardTable 3-7

Size No. of Pcs./ Sq.M. Size No. of Pcs. Sq.M.12” x 12” 11.30 24” x 24” 2.8316” x 16’ 6.35 3” x 6” 0.6516” x 24” 2.82 4” x 8” .038

Trusses and Rafters

1. Estimate by direct counting and measuring method2. Make a checklist of components:

a) Top chordb) Bot. Chordc) Collar Plated) Strut or web membere) Bracef) Wind or sway bracing

3. For components of shorter lengths, compute according to their sizes combined together and adjust to commercial size.

4. Lumber over 24” shall have splicing with 8-1 / 2” diameter bolt per splice.5. Add 20% for waste and splicing or 15% for waste alone.6. Round to 10 bd. ft. for each truss or rafter.7. Truss bolt size – 1 2 diameter minimum8. Minimum truss bolt requirements

a) Top joints = 5 boltsb) End joints = 2 boltsc) Intermediate at bottom chord = 1 boltd) Intermediate at top chord = 2 bolts

Page 13: Estimates

Quantity of Nails Per 1000 Board Ft.Table 3-8

Rafters 6 KG 3” – 4” CWNPurlins 9-10 KG 3” CWNFloor Joist 11 KG 4” CWNFlooring 1” x 2” 5 KG 3” CWN 7/ 8” x 2” 9 KG 1 1/ 4” – 3” CWN 1 1/ 2” x 2” 14 KG 3” CWN 1” x 4” 10-12 KG 3” CWN 1” x 6” 8 KG 2 1/ 2” CWNCeiling Joist 8 KG 2 1/ 2” CWNStuds 4 KG 3” CWNSidings 8 KG 2” CWNBaseboards 7 KG 2 1/ 2” FIN. NDoor and Window Frame 1/ 2 KG 2 1/ 2” CWNBridging 1” x 4” 14 KG 2 1/ 2” CWN 2” x 4” 23 KG 3” CWNTrusses 10 KG 4” CWNFascia Board 11 KG 2 1/ 2” CWNBalustrade 8 KG 2 1/ 2” FIN. NT & G Forms 7 KG 2 1/ 2” CWN

Size of PostsTable 3-9

As Required by the Department of Engineeringof the City of Manila (Ipil or its Equivalent)

Type of Bldgs. Max. Ht. 1st Flr. (M)

Max. Total Ht. (M)

Max. Spacing of Post (M)

Req’d Min. Size of Post

One storey 3.00 5.00 4” x 4”One storey 4.00 4.00 4” x 4”One storey 5.00 4.00 5” x 5”Chalets 100-150 5.00 3.50 5” x 5”Two storey 300 6.00 3.00 5” x 5”Two storey 3.50 7.00 4.00 6” x 6”Two storey 4.00 8.00 4.50 7” x 7”Two storey 5.00 9.00 4.50 8” x 8”Three storey 4.50 10.00 4.50 8” x 8”House 4.50 10.00 400-500 9” x 9”House 5.00 12.00 5.00 10” x 10”

Page 14: Estimates

RoofingsRoof Pitch and Percentage Addition

Table 4-1

PITCHPERCENT ADDITION TO

FLAT AREA FORTRUSSES AND RAFTERS

Symmetrical Unsymmetrical0.32 5.5 20.36 6 30.40 8 40.45 10 50.50 12 60.55 14 70.60 16 80.70 22 110.80 28 140.90 35 1800 42 21

Purlins for Standard CorrugatedG.I. Roofs

(For Trusses Not Greater Than3.0M on Centers)

Table 4.2

Purlin Size 2 WD Block BD FT/ SM 2” x 2” WD Cleat BF/ SM2” x 3” 3.271 3.4402” x 4” 4.369 4.5112” x 5” 5.321 5.4582” x 6” 6.335 6.500

Corrugated Roofing Sheets(Effective Coverage)

Table 4-3

Commercial 10” End Lap 2”Corr. Side Lap

12” End Lap 2”Corr. Side Lap

Size English Metric English Metric32” x 6” 27” x 5” – 2” 1.03 SM 27” x 5’ 1.05 SM32” x 7” 27” x 6” – 2” 1.29 SM 27” x 6” 1.255 SM32” x 8” 27” x 7” – 2” 1.50 SM 27” x 7” 1.465 SM

32” x 12” 27” x 11” – 2” 2.335 SM 27” x 11” 2.300 SM

Estimating Procedure

1. Solve for total flat area2. Add pitch factor (see table 4-1 for roof pitch)3. Sum of 1 and 2 is called sloped area which the actual covered area.4. Solve for purlin based on table 4-2 and round up to 10 bd. ft5. Solve for roofing sheets and round up to 10 sheets.

Page 15: Estimates

Roofing Hardwares

6. Roofing Rivets = 180 pcs. Per kgs.7. Corr. G.I. sheet – 6 rivets per sheet8. Corr. G.I. sheet – 9 rivets per sheet9. Corr. G.I. sheet – 9-12 rivets per sheet10. 2’ corr. G.I. sheet – 12 rivets per sheet11. Lead washers = 86 pcs. Per kilo12. Plate (washer) = 152 pcs. Per kilogram

Plain G.I. Straps Per Sheet( 36” x 8” – 0”)

Table 4-4

Purlin Size Strap Size No. of Strap2” x 3” 1” x 8” 3802” x 4” 1” x 10” 3402” x 5” 1” x 11” 3102” x 6” 1” x 12” 285

Roofing Nails

102 pieces per kg. 2 ½188 pieces per kg. 2 ½

No. of Roofing Nails

6’, 7’ & 8’ Length = 12 pcs. Per sheet9’ & 10’ Length = 16 pcs. Per sheet12 Length – 18 pcs. Per sheet

No. of washers per sheet = no. of rivets for 3 purlins per G.I. sheet.12 straps7 pcs. Rivets non-engaging26 pcs. Rivets engagingFor 4 purlins per G.I. sheet16 straps, 7 pcs. Rivets non-engaging32 pcs. Rivets engagingNon-engaging rivets 3/ 8” x 1/ 4” = 189 pcs. Per kg.Engaging rivets 1/ 2” x 1/ 4” = 153 pcs. Kg.

Rivets Needs2 ………. G.I. Washers1 ………. Lead Washer

Strap Needs2 pcs. Rivets engaging2 pcs. Lead washer2 pcs. G.I. washer2 pcs. 1 1/ 2 flatheadNails 0.06 kg. Per sheet2 pcs. 2 ½” roof nails0.082 kg. Per sheet

Page 16: Estimates

Plain G.I. Gutter, Ridge Roll, Fascia FlashingStandard Lengths = 8FT.No. of sheets required = total linear Mt. X 0.44

Nikolite Soldering LeadGutterNo. of bars = no. of pcs. Of gutter + 4DownspoutNo. of bars = no. of pcs. Of downspout + 5Muriatic acid = 10 cc. Per bar

Kinds of Asbestos Roofing

1. Standard corrugated sheets2. 4-V Corrugated Sheets3. Kanaletas4. Placa Romana5. Tencor Corrugated Sheets6. Ardex Lightweight Corrugated Sheets

a. Std. Ardex b. Super Ardex

Technical Data

Standard Corrugated SheetsLength …………………… = 4 to 10 ft.End Lapping Below 20º = 0.30 M

Above 20º = 0.15 MWidth: Effective Width = 0.838 MRidge Roll Effective Length = 0.838 MGutter Effective Length = 2.336 MOutside Flashing = 2.286 MHIP Roll = 1.676 M

NOTE:Other accessories, estimate by direct counting

4-V Corrugated Sheets

Figure # 2Standard Length = 2.438 M.Effective Width = 0.965 M.Ridge Roll Eff. Length = 0.965 M.Outside Flashing Eff. Length = 2.286 M.

KANALETAS

Standard Length = 7.315 M.Effective Width = 0.885 M.Eaves Flashing = 0.885 M.Outside Flashing Effective Length = 8 to 10 ft.Other accessories, estimate byDirect counting method

Page 17: Estimates

Placa Romana

Standard Length = 0.812 M.Effective Length = 0.600 M.Standard Width = 1.80 M.Effective Width = 1.100 M.End Lap = 0.200 M.Side Lap = 0.080 M.Ridge Roll Effective Length = 1.100 M.Outside Flashing Effective Length = 2.286 M.Ridge Flashing Effective Length = 1.100 M.Eaves Flashing Effective Length= 1.100 M.

Other accessories, estimate byDirect counting method

Tencor Corrugated SheetsStandard Length = 2.44 M.Lapping = 0.30 M.Effective Length = 2.14 M.Effective Width = 0.675 M.Standard Width = 0.748 M.Outside Flashing = 5 to 10 ft. longMinus Lapping = 6 inchesRidge Roll = 0.952

Ardex Corrugated SheetsTable 4-5

MEASUREMENTStandard Super

Std. Width 0.52 M. 1.05 m.Effective Width 0.45 M. 0.95Nominal Length 2.5 – 10.5 ft. 8 – 12 ft.

Ridge Roll Eff. Length 0.9525 M. 0.9525 M.Outside Flashing 5 to 10 ft. 5 to 10 ft.

Side Lapping 6 inches 6 inches

Ceramics Roofing TilesTable 4-6

Description Wt. / Pc. Pcs. Required PerMarceille Type (Flat) 3.6 Kg. Sq. M. 14Ondula Type (Wavy) 4.0 Kg. Sq. M. 15

SR (STD. Ridge) 2.8 Kg. Lin. M. 2.5Half-Marceille 2.0 Kg. Line 1.0

JRT - 1 3.0 Kg. Sq. M. 13JRT – 2 3.75 Kg. Lin. M. 4JRT – 3 3.2 Kg. Line 1JRT – 4 3.2 Kg. Line 1JRT – 5 2.2 Kg. Lin. M. 4SRT – 1 4.0 Kg. Sq. m. 13SRT – 2 2.2 Kg. Line 1SRT – L 2.25 Kg. Line 1SRT – R 2.25 Kg. Line 1

Page 18: Estimates

JRS - 2.0 Kg. Lin. M. 1SRT – U 1.75 Kg. Sq. M. 25SRT – T 1.50 Kg. Sq. M. 25

JRS - 3.0 Lin. M. 4

Tile WorkTable 5-1

Classification Size (in.) Pcs./ Sq. M.Cement Tiles 4 x 4 100

6 x 6 448 x 8 25

10 x 10 1620 x 20 4

Vetrified Tiles 3 x 3 178Mosaic Tiles 4 x 4 100

4 1/ 4 x 4 1/ 4 866 x 6 44

12 x 12 12Hexagonal Tiles 2 x 2 480

3 x 3 1904 ¼ x 4 1/ 4 95

Pcs./ Lin. M.5-pt. Hexagonal 2 204-pt. Hexagonal 2 16

Capping 4 ½ 9Internal Bead 4 ½ 9

NOTE:

1. Round values to 50 pcs. Except for 20 x 20 cement tile, capping and internal bead which are to be rounded to 10 pcs.

2. Tile cement mortar shall be 1 cm. Thick3. Mortar volume shall be based on rounded values of tiles4. Aggregates for mortar shall be rounded as follows: Cement =

5 bags; Sand = 1 cu.m./Lime = 5 bags5. Use 5 – points hexagonal tiles along shorter lengths6. Use 4 – points hexagonal tiles along shorter lengths7. For wainscoting corner moulding, estimate by direct count. White

cement filler mortar = 1 kl. Per square meter Portland cement paste = 0.08 bag/ square meter

Precast Terrazo and GranulithicTiles

Table 5-2

Stock size Pcs. Sq. M. Cem. Bags Sq. M. Sand Brass Div.Class A Class B Cu.M. M. Sq. M.

8” x 8” 25 0.34 0.22 0.18 11.009” x 9” 20 0.34 0.22 0.018 10.00

10” x 10” 16 0.34 0.22 0.018 9.0012” x 12” 12 0.34 0.22 0.018 8.0014” x 14” 8.5 0.34 0.22 0.018 6.0016” x 16” 6.5 0.34 0.22 0.018 5.90

Page 19: Estimates

VINYL AND RUBBER TILES

Stock size Pieces Gallons of AsphaltPer Sq. M.T. Per Sq. M.T.

1/ 8” x 8” x 8” 25.00 0.0421/ 8” x 9” x 9” 19.75 0.042

1/ 8” x 10” x 10” 16.00 0.0421/ 8” x 12” x 12” 11.11 0.042

Reinforcement

Available lengths of commercial bars:20 ft. (6.0M); 25 ft. (7.5M); 30 ft. (9.0)

Weights and hook allowance of rod.

Table 6-1

Bar No. Bar Dia. Kg/ M Hook Allowance2 1/ 4 0.249 33 3/ 8 0.559 4.54 1/ 2 0.993 6.05 5/ 8 1.550 7.56 3/ 4 2.230 9.07 7/ 8 3.040 10.58 1 3.970 12.09 1 1/ 8 5.030 13.5

10 1 1/8 6.200 15

NOTE:Kg x 0.001102 = TonLb x 0.453 = Kg.

TIE WIRE:No. 16 G.I. Tie Wire = 20 Kg/ Ton of rebar

= 0.02 x total weight of rebar= 35 Kgs per roll

Weights and Hook AllowanceOf Rod Philippine Standard

Table 6-2

Bar No. Bar Designation (mm) Kg/ M.T. Hook All. 6D x 2 (mm)

2 6 0.222 723 10 0.616 1204 12 0.888 1445 16 1.579 1926 20 2.466 2408 25 3.854 3009 28 4.833 336

10 32 6.313 38412 36 7.991 43213 40 9.864 48016 50 15.413 600

Page 20: Estimates

No. of Pcs. Of Lateral Tie in One 6.0 M BarTable 6-3

Lateral Tie Dimension No. of Pcs.W L In one Bar (n)

5 in. 0.125 5 in 0.12 5m 9M. 7 0.175 8

9 0.225 711 0.275 613 0.325 5

7 0.175 7 0.175 79 0.225 611 0.275 513 0.325 515 0.375 4

9 0.225 9 0.225 511 0.275 513 0.325 415 0.375 4

11 0.275 11 0.275 413 0.325 415 0.375 4

Lateral Tie and Tie Wire Computation by Direct Counting Method:

Let N = no. of pcs. Of bars required

N = no of pcs. In one bar (see table # 6-3)L = total length of all columnsS = spacing of lateral tie

N = ( L + 1) + n S

Round value to next 10.

FOR TIE WIRE:

Let N = no. of kilos of tie wire required V = no. of vertical bars L = length of tie wire/ tying points = 12 inches = 0.30 m. on the average T = no. of tying points = (L/S + 1) V1 kl. No. 16 tie wire = 53 m approximately

N = L” T + 53 = 0.30 (L/S + 1) V 53

N = 0.00566 (L + 1) V S

Page 21: Estimates

Length of Spiral ReinforcementTable 6-4

Col. Pitch Length of Col. Pitch Length ofDiam. Spiral/ M. Ht. Diam. Spiral/ M. Ht.12 2 14.85 M 20 2 28.05 M

2 1/ 2 12.03 2 1/ 2” 27.713 9.9 3 18.69

13 2 16.50 21 2 29.702 1/ 2 13.35 2 1/ 2” 24.04

14 3 11.10 3 19.8014 2 18.15 22 2 31.35

2 1/ 2 14.70 2 1/ 2” 25.373 12.10 3 20.89

15 2 19.80 23 2 33.0015” 2 1/ 2” 16.05 M 23” 2 1/ 2” 26.70 M15” 3” 13.20 23” 3” 22.0716” 2” 21.45 24” 2” 34.6416” 2 1/ 2” 17.37 24” 2 1/ 2” 28.0416” 3” 14.30 24” 3” 23.1017” 2” 23.10 25” 2” 36.3017” 2 1/ 2” 18.70 25” 2 1/ 2” 29.4017” 3” 15.40 25” 3” 24.1918” 2” 24.75 26” 2” 37.9518” 2 1/ 2” 20.03 26” 2 1/ 2” 30.7218” 3” 16.50 26” 3” 25.29

Concrete Slab ReinforcementTable 6-5

Bar One Way Slab Two Way SlabSpacing 20 Bar Tie Wire 20 Bar Tie WireInches Per sq. m Klg/ sq. m Per sq. m. Klg./ sq. m.

4 3.350 0.218 4.150 0.4595 2.842 0.175 3.440 0.3896 2.450 0.152 3.040 0.2827 2.250 0.129 2.550 0.1988 2.083 0.113 2.350 0.1329 1.884 0.102 2.020 0.10510 1.762 0.080 1.820 0.08311 1.669 0.080 1.710 0.06912 1586 0.074 1.600 0.056

CHB – ReinforcementTable 6-6

Spacing of Vertical Length of Bars in Meter PerBars in Meter Block Sq. Meter

0.4 0.25 3.00.6 0.17 2.10.8 0.12 1.5

Horizontal BarsEvery 2 Layers 0.22 2.7

3 0.15 1.94 0.13 1.75 0.11 1.4

Page 22: Estimates

NOTE: Rebars for spiral column, slab and chb indicated in the tables include the allowance for bending, splicing and end hook.

CHB Rebar(Jackbilt Specification)

Table 6-7

VERTICAL BAR SPACINGBlock

Thickness16 O.C.

0.4024 O.C.

0.6032 O.C.

0.8040 O.C.

1.0048 O.C.

1.204” 3/ 8” Ø 3/ 8” Ø 3/ 8” Ø 3/ 8” Ø 3/ 8” Ø6” 3/ 8” Ø 3/ 8” Ø 3/ 8” Ø 3/ 8” Ø 1/ 2” Ø8” 3/ 8” Ø 1/ 2” Ø 1/ 2” Ø 5/ 8” Ø 5/ 8” Ø

Horizontal Bar SpacingTable 6-8

Brick Thickness Every Third Course or 0.60

Every Fourth Course or 0.80

Every Fifth Course or 0.0

4” 3/ 8” Ø 3/ 8” Ø 3/ 8” Ø6” 1/ 2” Ø 1/ 2” Ø 1/ 2” Ø8” 1/ 2” Ø 1/ 2” Ø 1/ 2” Ø

Electrical EstimatesTable 7-1

Class of Work Unit Labor – HourElectrical Helper

Install thin-wall conduit withOutlet boxes 1/ 2 & 3/ 4 in. 100 L.F. 4 – 6 4 – 6

1.0 in. 100 L.F. 4.3 – 7 4.3 – 7 1.25 in. 100 L.F. 4.5 – 7.5 4.5 – 7.5 1.50 in. 100 L.F. 5.5 – 9 5.5 – 9

Install flexible conduitWith outlet boxes

1/ 2 & 3/ 4 in. 100 L.F. 3 – 5 3 – 5 1 & 1.25 in. 100 L.F. 4 – 6 4 – 6

Install service Entrance cap and conduit

Each 0.5 – 1.0 0.5 – 1.0

Install conduit & fuse panel Each 0.5 – 1.0 0.5 – 1.0Install heavy rigid conduit with outlet boxes

1/ 2 & 3/ 4 in. 100 in. F. 5.0 – 10 5.0 – 101 & 1.25 in. 100 in. F. 50 – 11 50 – 11

1 1/ 2 in. 100 in. F. 30 – 13 30 – 132 100 in. F. 12 – 17 12 – 17

2 1/ 2 in 100 in. F. 15 – 21 15 – 213 100 in. F. 20 – 28 20 – 284 100 in. F. 25 - 35 25 - 35

Page 23: Estimates

Painting Works

A. Wood:1. First coating for wood = 1 gal. Per 20 sq. m.2. Second coating for wood = 1 gal. Per 25 sq. m.B. Masonry:1. First coating for wood = 1 gal. Per 25 sq. m.2. Second coating for wood = 1 gal. Per sq. m.

Inside for wood – use interior paintOutside for wood – use exterior gloss paintMasonry for wood – use monokote paintFor coloring: - interior flat or exterior gloss paint

- Tinting color (assorted)Masonry paint for coloring – Agri colorPaint thinner – 2 gals. Per 20 gals. Of paintsLinseed oil – 1 gal. Per 20 gals. Of paints

Spreading Rate of Paint(No. of Sq. M. Covered by one Gallon)

Table 8-1

Kind of Paint Character of Surface 1 Coat 2 Coats 3 CoatsOil paint Smooth wood 55.76 30.20 20.95Gloss Finish Rough wood 32.53 18.50 12.55

Metal 65.05 31.60 21.37Plaster 41.82 23.23 18.26Hard brick 37.17 20.91 14.87Soft brick 32.53 18.58 13.94Smooth cem. Struc. 32.53 18.58 13.94Rough cem. Struc. 18.58 9.29

Enamel Paint Smooth painted withUndercoat 46.50 23.29

Extr. Varnish Smooth wood 46.50 22.55 18.58Interior Varnish Smooth wood 41.82 23.23 18.26Shellac Smooth wood 55.76 27.88

Rough wood 11.61 6.97Shingles Stain Smooth wood 23.23Oil Paint smooth Wood wall bd. 46.50 27.25 18.58

Plaster 37.17 20.91 14.87Hard brick 32.53 18.58 13.94Soft brick 27.88 18.26 11.61Rough cem. Struc. 13.94 6.97

Calcinine Plaster 37.175-LB Powder Wood 23.23White Wash Brick 18.584-5 Hydrated Lime Plaster 27.88

Page 24: Estimates

Kinds of PaintTable 8-2

Kinds of Paint Character of Surf. 1 CoatAsphalt Roof Paint Rough wood 13.54Asphalt – Asbestos Roof Paint

Smooth wood 9.29

5 Lbs powder cold water paint

Smooth wood 27.88

Paint Coverage (Sq. M./ Gal.)

Wood Preservation - 9.30 – 1 coatOutside Lead oil - 27.88 – 2 coatsFlat White Paints - 27.88 – 2 coatsFloor Oil Paint Stain - 55.76 – 1 coatEnamel Floor - 23.23 – 2 coatsWall side for wall board - 27.88 – 1 coatAluminum - 46.50 – 1 coatVarnish - 55.76 – 1 coat

Labor Estimate

1. Concreting of Plain Flooring 2 men pour 1.2 cu. m. concrete/ day

2. Concreting of Reinf. Flooring2 men pour 0.84 cu. m. concrete/ day

3. Concreting of Column & Beam:2 men pour 0.50 cu. m. concrete/ day

4. Finishing of Flooring (rough):2 men finishes 72 sq. m./ day

5. Finishing of C.H.B. Joints:2 men finishes 420 pcs./ day

6. Plastering of C.H.B.2 men plasters 8 sq. m./ day

7. Laying of C.H.B.2 men lay 100 pcs./ day

8. Breaking Old R.C. Flooring:2 men break 0.30 cu.m./ day

9. Laying of Glazed Tile, 4” x 4”2 men lay 100 pcs./ day

10. Laying of Glazed Tile, 6” x 6”2 men lay 72 pcs./ day

11. Installation of Water Closet:2 men install 1 – set W.C/ 2 days

12. Installation of Lavatory:2 men install 1-set Lav. / 1 1/ 2 day

13. Installation of G.I. sheets 32” x 8 on steel Frames:2 men installs 11 sheets/ day

14. Installation of G.I. sheets 32” x 8” on Wooden Frames2 men installs 20 sheets/ day

15. Installation of G.I. sheets 32” x 12” on Steel Frames:2 men installs 10 sheets/ day

Page 25: Estimates

16. Installation of G.I. sheets 32” x 12” on Wooden Frames:2 men installs 15 sheets/ day

17. Fabricating and installation of Gutter Downspout, Ridgeroll:2 men fabricated install 5 sheets:32 x 8” G.I. sheets/ day

18. Installation of G.I. Pipe 1/ 2 Ø x 20”2 men install 20 lights/ day

19. Installation of door and windows jamb:1 man install 3 pcs. 2” x 5” x 16” or 40 bd. ft./ day

20. Installation of Door (Complete with Hinges and Knob):1 man install 2 pcs. Door/ day

21. Fabrication of Door (Excluding Planning of Frames)1 man makes 3 pcs./ day

22. Planning Rough Lumber (including Alignment):1 man planes 4 pcs. 2” x 4” 18” 120 bd. ft./ day

23. Planning Rough Lumber (No Alignment):1 man planes 10 pcs. 2” x 4” x 18” 120 bd. ft./ day

24. Installation of Plywood Board:2 men install 15 sheets 4” x 8”/ day

25. Installation of Wooden Post:2 men install 6 pcs. 4” x 4” x 12” or 96 bd. ft./ day

26. installation of Wood Jalousie Windows1 man install 2 pcs. 30” x 45” or 18.75 sq. ft./ day

Construction Work Capacities in Man-hoursI. EARTH WORK:

a. Excavation – 1.82 to 2.89 man-hour/ cu.m.b. Backfill – 1.34 man-hours/ cu.m.

II. FORMWORKa. Footing, grade beams, column – 2.5 man-hours/ sq.m.b. Beams, bond beams, floor slabs – 2.8 man-hours/ sq. m.c. Roof beams and bond beams – 3.01 man-hours/ sq. m.d. Root slabs – 3.34 man-hours/ sq. m.e. Retaining walls – 2.4 man-hours/ sq. m.f. Stairs and landings – 2.48 man-hours/ sq. m.g. Form oil application – 6.0 man-hours/ 10 sq. m.

III. REINFORCEMENT:a. Reinforcement of footings up to roofing average 9.0 man-hours/ 100 kilosb. B. Grade slab EWP – 13 man-hours/ 100 sq. m.c. Floor membrane – 15 man-hours/ 100 sq. m.

IV. CONCRETE WORKa. Column footings, wall footing grade beam, grade slab and Column – 2.34 man-hours/

cu. m.b. Floor beams and bond beams – 2.82 man-hours/ cu. m.c. Floor slabs (suspended) – 2.60 man-hours/ cu. m.d. Roof beams and bond beams – 2.88 man-hours/ cu. m.e. Stairs – 2.6 man-hours/ cu. m.f. Roof slab – 2.91 man-hours cu. m.g. Curing (water) – 2.0 man-hours/ day for 7 daysh. Equipment

1. Vibrator – 16 min./ cu. m.2. Crane with concrete bucket – 4 cu. m./ man-hour

Page 26: Estimates

Capabilities of Manual Labor Per Hour

Unit Type of work Capability1. man a. Excavating Loam or sand 0.76 cu. m.

b. Excavating clay or heavy soil 0.61 cu. m.c. Excavating rock 0.38 cu. m.d. Backfilling 1.22 cu. m.e. Spreading, tamping & grading 2.09 cu. m.f. Placing escombro fill 2.0 cu. m.g. Placing binders 4.0 cu. m.h. Cleaning undergrowth and small brush 20 sq. m.i. Cleaning underground and brush 12” Ø 20 sq. m.

2. 1 mason & a. Laying of CHB and Adobe 22 pcs. 1 helper b. Cement finish 28 sq. m.3. 1 carpenter a. Erecting forms 1.86 sq. m. & 1 helper b. Removing forms 1.86 sq. m.

CAPABILITIES OF EQUIPMENT

Item Type of work Capability1. Dozer a. Clearing 500 sq. m/ hr.

b. Stripping 200 sq. m/ hr.c. Excavation 25 cu. m/ hr.d. Quarrying 50 cu. m/ hr.e. Pushing 3 sq. m/ hr.

2. Grader a. sub-grading 300 sq. m/ hr.b. Spreading 50 cu. sq. m/ hr.

3. Payloader a. Loading 30 cmph4. Crane Shovel a. Loading 35 cmph5.Sheep’s foot a. Static Rolling (12 passes – 15 cm. Lift) Roller b. Vibratory Rolling (4 passes – 15 cm. Lift) 135 cmph6. No. 3 W Road a. Static Rolling (6 passes – 20 cm. Lift) 24 cmph Roller7. Tractor-drawn a. Vibratory Rolling (6 passes – 20 cm. Lift) 240 cmph Roller (1 – D)8. Tandem Roller a. Static Rolling (6 passes – 20 cm. Lift) 24 cmph

b. Vibra Rolling (6 passes – 60 cm. Lift) 72 cmph9. 5-T Dump a. Hauling common borrow 3.5 cmpt Truck b. Hauling selected borrow base coarse 5 cmptNOTE: Cmph – cu. m./ hour; cmpt = cu. m./ truck10. 2-1/ 2-T a. Hauling common borrow 2.5 c.m./ trip Dump Truck b. Hulting SBBC 2.0 c.m./ trip11. Buggy a. Hauling concrete mix 0.17 c.m./ trip12. Wheel barrow a. Hauling aggregates 0.07 c.m./ trip13. Water Truck a. Watering 1000 sq.m./ hr.14 Asphalt a. Spraying Distributor Asphalt prime 300 sq. m./ hr.15. 16-S Concrete 9 cu.m./ hr. Mixer16. Rock Crusher a. Crushing mixed Sand and gravel 30 cu.m./ hr.17. Concrete a. Vibrating concrete mix 40 cu.m./ hr. Vibrator18. Concrete Floor a. Finishing concrete floor 40 sm./ hr. Finisher 19. Scraper Towed a. Hauling heap capacity 1 cu.m./ trip

Page 27: Estimates

12 CY Cap20. Scraper Tour- a. Hauling heap capacity 22 cu.m./ trip Mapull 45 ton21. Percussion a. Drillings hard rock 0.23 m/ hr.

b. Drillings loose rock 0.30 m/ hr.c. Drillings limestone 0.38 m/ hr.d. Drilling sticky clay 0.49m/ hr.e. Drilling loose clay 0.76 m/ hr.

1. Metric ton of Asphalt concrete covers 8 sq. m. of pavement 0.05 m. thick or 0.43 cu. m. of Asphalt concrete.

Inside Dimension of the Digestion ChamberNo. of Person Depth (m.) Width (m.) Length (m.)

10 1.20 0.90 1.8015 1.20 1.10 2.2020 1.20 1.25 2.5025 1.20 1.40 2.8030 1.30 1.50 3.0035 1.30 1.60 3.2040 1.40 1.65 3.3045 1.40 1.80 3.5050 1.50 1.80 3.5060 1.50 1.90 3.9070 1.60 2.00 4.0080 1.60 2.20 4.4090 1.80 2.20 4.40

100 1.80 2.30 4.60

Important Features of Septic Vaults

1. Septic tanks are no longer allowed in Manila where the sanitary sewer in now in operation. They may still however, be of great service in sub-urban communities.

2. Location: no septic tank shall be installed within or under the house3. Tanks must be built water-tight of concrete, stone or brick4. Both compartments are provided with manholes and tight covers for cleaning and necessary

repairs.5. Inlets and outlets are submerged in such a way that neither scum or sludge be unduly disturb.6. Inlets and outlets are arranged so as to deliver the sewage to the middle third of the tank

depth. For instance, in a tank 1.20 m deep, the inlet and outlet be submerged 0.40 meters.7. The vault is vented thru the sanitary fees in the inlet and outlet, having top ends open and

screened to make-tank mosquito-proof.8. The bottom of the tank should 1:10 min. toward the manhole in the center facilitate cleaning.9. Not less than 0.20 m. of airspace should be left between the top of the sewage and the under

part of the rank over.

Average Pool Consumption forVarious Construction Equipment

Page 28: Estimates

Table 10-1

Equipment Diesel Engine Grease Gear Oil GasolineFuel (liter) Oil (liter) (Pound) (Liter) (Liter)

Pay loader 10 ltrs./ hr. 3 ltrs./ hr. 1 lb./ day 1 ltr./ dayBull dozer 12 ltrs./ hr. 3 ltrs./ hr. 1 lb./ day 1 ltr./ dayRd. Grader 10 ltrs./ hr. 3 ltrs./ hr. 1 lb./ day 1 ltr./ dayRd. Roller 5 t 2 ltrs./ hr. 2 lbs./ wk 6 6 ltrs./ hr.Rd. Roller10-12 t 5 ltrs./ hr. 2 ltrs./ hr. 2 lbs./ wk 1 ltr./ wkRd. roller5-8 t 5 ltrs./ hr. 2 ltrs./ hr. 2 lbs./ wkCrane Truck mounted

4 ltrs./ fly 2 lbs./ day 1 ltr./ day 12 ltrs./ hr.

Pneumatic Tractor

1 ltr./ day 2 lbs./ day 1 ltr./ day 12 ltrs./ hr.

Trk. Tractor w/ trafler

2 km./ ltr. 1 ltr./ day 1 lb./ wk.

Water trk. W/ pump

1/ 5 ltr./ day 1 lb./ day 1 ltr./ wk. Brake fld.

8 ltrs./ hr.

Paver 5 ltrs./ day 2 ltrs./ day 1 lb./ day 1 Pint/ wk.Dump Truck 3 kms./ ltr. 1 ltr./ day 1 lb./ day 2 ltrs./ wk.

Brake fld. 1 pint/ wk

Tractor Crawler Cat D-7

10 ltrs./ hr. 2 ltrs./ day 2 lbs./ day 1 ltr./ day

Stake Trk. (H Loadstax 80 ton)

1 ltr./ km. 1 ltr./ day 1 lb./ day 1 ltr./ day

Concrete Mixer 4 bagger

1/ 2 lb./ day 1/ 2 lb./ day 8 ltr./ hr.

Rough Estimates

100 BD. FT./ CU.M. FORM LUMBERCement – 10 bags/ cu.in. plasterSteel Reinf. – 100 to 130 kgs./ cu.m. of concreteRoof Frmg. – 14 bd. ft./ sq. m. of roof areaCeiling Frmg. – 7 bd. ft./ sq.m. ceilingNails – 20 kgs./ 1000 bd. ft.Studding, 2” x 3” – 4 bd. ft./ sq.m.Siding – 10.7 bd. ft./ sq.m.Flooring – 10.8 bd. ft./ sq.m.Floor Joists, 2” x 6” – 15 bd. ft./ sq.m.Ceiling Joists, 2” x 2” – 4 bd. ft./ sq.m.Purlins, 2” x 4” – 4.4 bd. ft./ sq.m.G.I. Sheets, 32” x 8” – 0.7238 pcs./ sq.m.Roof nails, 2 1/ 2” – 0.082 kg./ sq.m.Roof cement – 0.042887 gal/ sq.m.Straps, 3” x 8” – 0.0452377 sht./ sq.m.Rivets, 3/ 8” x 1/ 4” – 0069 kg/ sq.m.G.I. washer, 1/ 4” – 0.15888 kg/ sq.m.

General Checklist:

Page 29: Estimates

I. FOUNDATIONConcrete footing, piers, lumber forms, earthfill, reinforcing bars, hardwares

II. CONCRETE AND MASONRY WORKSReinforced concrete: columns, beams, slabs and zocalo; Slab on fill, CHB zocalo, CHB walls, CHB fence, CHB fillers, Plaster, Forms and Falseworks, Various hardwares materials, mortar

III. LUMBER FRAMEWORKSPosts, Girders, Floor joists, Bridging, T & G Flooring, Ceiling joists hangers, Siding, Various hardwares.

IV. ROOFINGTrusses, Rafters, Purlins, Purlin blocks, Fascia boards, Air ventilators

V. PENESTRATIONSWindow sash/ framing, door sash/ framing, window glass, door glass.

VI. MILLWORKSPanel/ flush doors, baseboards, general moulding, special moulding, various hardwares.

VII. STAIRSStringers, Treads, Riser, Handrails, Balustrades, Paneling, Various hardwares

VIII. STOCK PANELExterior siding, Double wall, Partition, flooring, Ceiling, Various hardwares.

IX. TILE WORKUnglazed floor tiles, Glazed tiles, Face bricks, Mortar, Various hardwares.

X. ROUGH HARDWARESCommon wire nails, G.I. nails with lead washers, Tension bars, machine bolts and washers, post W.I. straps, tie wire.

XI. FINISHING HARDWARESLoose pin hinges, Closets and cabinet hinges locksets, Cabinet handles, Friction catches, Door automatic closer, Cabinet drawer locks, Aluminum screen.

XII. PLUMBING WORKC.I. soil pipes, C.I. soil pipe fittings, Floor drains, Faucet, Stop cock, Shower head, Water heater, Kitchen sink.

XIII. ELECTRICALElectrical wires, Switches, Convenience outlets, Ceiling receptacles, Main switch, Circuit breaker.

XIV. BATH AND TOILET FIXTURESWater closets, Lavatories, bath tubs, Shower stalls, urinals, Bidets, toilet and bath accessories.

XV. SPECIAL CARPENTRY WORKSClosets, built-in cabinets, movable partitions, Cabinets, Cupboards, Covelighting, Various built-in units.

XVI. TINSMITHRY

Page 30: Estimates

Corrugated G.I. roofing, Gutter/ Flushing, Flushing, Ridge roll, Hook bolts, valley roof straps, conductors, downspouts.

XVII. PAINTINGRoof paint, masonry paint, Oil base paint, Varnish, Patching powder, Thinner, Linseed oil, Sand Paper.

Checklist of Items to be Considered:

JOB OVERHEAD

1. EQUIPMENT: rental, delivery, loading, erecting, and dismantling2. PERSONNEL: Salaries, fringe benefits and payroll taxes for superintendent, foreman,

timekeeper, clerk etc.3. FIELD OFFICE : rental, telephone, electricity, office supplies4. TEMPORARY FACILITIES: light and power, water, sanitary facilities, fuel, gas for gas for

welding roads, stair, barricades, runways, fences, tool-shed, warning lights5. PERMIT: building, street, sidewalk water, sewer, for transporting heavy loads over city street,

for use of city dumps.6. QUALITY CONTROL: Soil compaction test and boring, concrete tests for aggregate, slump

and strength manufacturer’s and materials suppliers certifications and samples.7. MEETING AND SUBMITTALS: As-built drawings, progress photographs, shop schedules,

progress report, job meeting.8. TRANSPORTATION AND FREIGHT: Railway, trucking, demurraged, unloading.9. COORDINATING: Cutting and patching, inspecting subcontractor work.10. FINAL CLEAN-UP: Patching, touchup, janitorial work, handling debris final inspection.11. BONDS: Surety, labor and material payment bond, performance, bid, completion supply.12. INSURANCE: General liability, fire, damage etc.13. PROTECTION: Safety requirements, etc.14. REPAIRS: Sidewalk, streets, and curbs.15. Miscellaneous: Professional fee for engineer, attorney, general company overhead, real state

taxes, contingencies.

SITE EXCAVATION AND SITEWORK:

Demolition, clearing and grubbing remove excess materials and debris, strip and stockpile top soil, borrow material from offsite sources. Rough grading, spread back top soil, landscaping, concrete and bituminous walks, driveway, curb. Catch basin and storm drain.

BUILDING EXCAVATING AND BACFILLING STRUCTURAL METALS: handling and erection. ARCHITECTURAL AND MISCELLANEOUS METALS. CONTRACTOR AND OWNER FURNISHED OR BUILT-IN EQUIPMENT.

SAMPLE COMPUTATIONS

Page 31: Estimates

CONCRETING

Find the quantity of cement in bags, sand and gravel in cu.m. needed for a plain concrete slab on fill 0.10 m thick and 6.0 x 9.0 m in dimension.

Solution:1. Find the volume: V = 0.10 x 9 x 6 = 5.40 cu. m.2. Referring on Table 1-2, Class ‘B’

Cement: 5.4 x 6.48 = 35 bagsSand: 5.4 x 0.44 = 2.5 cu. m.Gravel: 5.4 x 0.88 = 5.0 cu. m.

MASONRY:

The net area of a certain masonry wall is 100 sq. m. Find the no. of 4” x 6” x 8 CHB, bag of cement and lime, and cu. m. of sand. The wall is to be tooled finished on one side. Use 1:3 mixture for plaster and mortar

1. pcs. Of CHB = 100 x 13 = 1300 pcs.2. Mortar volume: referring on and Table 2-1 and 2-4 filler vol. = 1300 x 0.0028 = 3.64 cu. m.

mortar vol.

= 100 (3.28)2 sq. ft. x 6 cu. ft. x cu. m. 100 sq. ft. (3.28) cu. ft.

mortar volume – 1.83 cu. m.

Total mortar volume = 3.64 + 1.83 = 5.47 cu. m. referring on Table 2-3, using 1:3 mixtureCement: 5.47 x 12.07 – 66 bagsSand: 5.47 x 0.97 = 55 cu. m.

3. Plaster Volume: referring on Table 2-3V = 100 x 0.012 = 1.2 cu. m.Cement: 1.2 x 5.5 = 6.6 bagsLime: 1.2 x 5.5 = 6.6 bagsSand: 1.2 x 0.90 = 1.1 cu. m.

Compute the quantity of cement in bags sand in cu. m. and 0.35 x 0.45 adobe stones for a wall supported by buttress as shown.

Solution:

1. Buttress: referring on Table 2-13Total height = 2 x 3 = 6.0 mNo. of stones = 6(12) = 72 pcs.

Mortar volume, referring on page 12 and 13V = 72(0.001575) = 0.1134 cu. m.

Referring on using 1.3 mixtureCement: 0.1134(12.04) = 2 bagsSand: 0.1134(0.97) = 0.11 cu. m.

2. Wall : referring on page 15Area = [10 – 3 (0.35))] (2) = 17.90 sq. m.

No. of stones = 17.9 (13) = 233 pcs.For class ‘A” plaster on two faces<cement : 233 (0.0304) = 7 bagsSand : 233 (0.0017) = 0.5 cu. m.

3. Cross-footing: referring on Table 2-9

Page 32: Estimates

No. of stones = 10(6) = 60 pcs.Mortar volume,V = 60(0.0065) = 0.39 cu. m.

Referring on Table 2-3 using 1:3 mixtureCement: 0.39 (12.04) = 5 bagsSand : - .39(0.97) = 0.5 cu. m.

Compute the quantity of cement and sand for mortar to lay 100 pcs. Of 36” Ø concrete pipe for drainage.

No. of joints = no. of pipes – 1 = 99 referrign on Table 2-6Cement: 99(0.70) = 70 bagsSand: 99(0.038) = 4 cu. m.

Excavation and Backfill

Find the total volume of excavation and backfill. Assume the soil to be moist ordinary earth. From page 3, the slope for this kind of soil varies from 1:2.1 – 1:1

Lumbering

Compute the needed materials for the floor system shown using 1” x 6” T&G flooring system shown using 1” x 6” T&G flooring supported by 2” x 6” joist spaced at 12” on center.

Solution:

1. For 1” x 6” T&G Flooring:Referring Table 3-3 10.8 Bd. FT./Sq.M.Total BF = 10.8 (3 x 6) = 194.4; N = 24 pcs.

2. For 2” x 6” x 12’ Floor Joist:Referring to Table 3-2 16.10 bd. ft./ sq.m.Total BF = 16.10 (3 x 6) = 289 bd. ft.N – 2” x 6” x 12’ + 12 = 289.8, N = 24 pcs.

Compute the needed materials for the ceiling frame shown. Use 3’ x 6’ joist 18” o.c.

Solution:

1. Divide 4+ 0.9 = 5; 10 + 1.8 = 6Pcs. Of ceiling panel = 5 x 6 = 30 pcs.

2. For ceiling joist:Referring to Table 3-6 8.8 bd. ft./ sht.No. of pcs. W/o considering cuttingWastage = (4 x 10) + (9 x 1.8) = 25 pcs.Total BF = 25 (8.8) = 220 bd. ft.N – 2” x 2” x 12’ + 12 = 220, N = 55 pcs.

3. Nail from Table 3-8No. of Kis (1 1/ 2) CWN = 8 (334.4) x 10 = 2.7 kis.

Roofing

Page 33: Estimates

As shown in the figure, find the mat’ls needed using 32” x 6” corr. G.i. with 12” end lapping and two corrugation for side lapping, and 2” x 4” purlins.

Solution:

Pitch = 1.28 + 4 = 0.32From Table 4-1, percentage addition for pitch = 5.5

Flat area = 4 x 9 = 36 sq. m.Slopped area = 36 + 36 (0.055) = 37.98 sq. m.

From p. 28, effective coverage = 1.05 sq.m./ sht.No. of sheets = 37.98 + 1.05 = 36 shts.From pp. 29 and 30 using 3 purlins per sheets pcs. Of straps = 13 x 36 = 468 pcs.Referring on pages 30 to 31

No of engaging rivets = 2 x 468 = 936 pcs.No. of kilos = 936 + 153 = 5 kls.

Lead washer: 86 pcs. Per kiloNo. of pcs. = 936, no. of kilos = 936 + 86 = 11 kls.

G.I. washer: 152 pcs. Per kiloNo. of kilo = 2 (468) + 152 = 6 kls.1 1/ 2” flathead Nails = 36 (0.06) = 2.5 kls.2 1/ 2” Roofing Nails = 36 (0.082) = 3.0 kls.Wood block referring to table 4-2

Total bd. ft. = 37.98 (4.369) = 166 bd. ft.N – 2” x 4” x 10’ + 2 = 166, N = 25 pcs.

Wood Cleats; referring to Table 4-2Total BF = 37.98 (4.511) = 171.33 bd. ft.N – 2” X 4” X 10’ + 12 = 171.33; N = 26 pcs.

Purlins; by direct counting42 pcs. Of 2” x 4” x 10’

Tile work

Find the quantity of file work materials for a bathroom shown. Use 12” x 12” mosaic tiles and 4 1/ 2” x 4 1/ 2” unglazed tiles.

A. Mosaic Tiles: refer to table 5-1A = 1.15 (2.25) = 2.59 sq. m.

No. of pcs. = 2.59 (12) = 32 pcs.B. Glazed Tiles

A wall = 1.5 [2 x 2.25 + 1.15 + 0.45] = 9.15 sq. m. No. of pcs. = 9.15 (95) = 870 pcs.C. External Bead 4 1/ 2”

Linear meter = 1.5 + 1.5 = 3.0 m No. of pcs. = 3(9) = 27 pcs.D. Internal Bead : 4 1/ 2

L.M. = 2.25 x 2 + 1.15 + 0.45 = 6.1 m No. of pcs. = 6.1 (9) = 55 pcs.E. Capping:

L = 6.1 m; No. of pcs. = 6.1 (9) = 55 pcs.F. Internal Corner Angel Bead = 4 pcs.G. Internal Corner Angle Capping = 4 pcs.H. External Corner Angle Bead = 2 pcs.I. Portland cement paste: refer on 38

No. of bags = 0.08 (2.59 + 9.15) = 1 bagJ. White cement mortar:

No. of kls. = 1(2.59 + 9.15) = 12 kls.

Page 34: Estimates

K. Mat’ls for setting preparation: class “A”Cement = 0.012 (11.74) (8.5) = 2 bagsLime – 0.012 (11.74) (8.5) = 2 bags

Sand = 0.012 (11.74) (0.9) = 0.5 cu. m.

Reinforcing Bars

In a certain building plan, 10 columns have identical cross-section and height. Estimate the needed rebars and tiewire.

1. Vertical bars: using 16mm x 6.0m barNo. of pcs. = 4 x 10 = 40 pacs. Vert. Bar

2. Lateral tie: using 6mm x 6.0 m barRefer to table 6-3 43; for 9” x 9” lateral tie,n = 5 L = 10 (5.5) = 55m; S = 0.20mN = (L/S + 1) + n = (55/0.2 + 1) + 5 = 56 pcs. Order56 pcs. Of 6mm x 6.0 m lateral tie

3. Tie wireV = 4 bars; L = 55m; S = 0.20 m

N = 0.0056 (L/S + 1) V = 0.0056 (55/ 0.2 + 1) 4 = 6.5Order 6.5 kls. Of no. 16 tie wire

CHB Reinforcement

Copute the require 10 mm x 6.0 m deformed rebars of a masonry fence 2.0m high and 100 m in perimeter. It is reinforced with vertical bars spaced at 0.80m o.c. and a horizontal bar at every three layers.

Solution:

Referring to Table 6-6Area of masonry fence = 2 x 100 = 200 sq.m.

For vertical rebars:No. of pcs. = 200 (1.5) + 6 = 50 pcs.

For horizontal rebars:No. of pcs = 200 (1.9) + 6 = 64 pcs.

COMMON NAILS AND SPIKES

STEEL, CUT NAILS AND SPIKES

Page 35: Estimates

PENNY LENGTH NO. PER KILOSIZE INCH NAILS SPIKES

4d 1 1/ 2 6905d 1 3/ 4 5906d 2 3907d 1 1/ 4 3508d 2 1/ 2 190

10d 3 13016d 3 1/ 2 72 3720d 4 50 3030d 4 1/ 2 35 2240d 5 26 1950d 5 1/ 2 22 1760d 6 17 15

STEEL, WIRE NAILS AND SPIKESPENNY LENGTH NO. PER KILO

SIZE INCH NAILS SPIKES4d 1 1/ 25d 1 3/ 46d 2 3457d 2 1/ 48d 2 1/ 2 215

10d 3 15016d 3 1/ 2 107 6620d 4 68 5030d 4 1/ 2 52 3740d 5 89 2850d 5 1/ 2 80 2260d 6 24 19

Standard Conversion for Welding

Pcs./ pack Packs/ box Kg../ boxCerlicon 60

5/32” Ø 127 4 203/16” Ø 81 4 201/6” Ø 185 4 20

Chamfer Rod Pcs./ box1/6” Ø 123 45/32” Ø 76 4

Supercito 705/32” Ø 76 4 201/8” Ø 110 4 20Arcair Pcs./ box1/ 4” Ø 505/16” Ø 50Gencord Pcs./ pack

60133/16” Ø 50 4 20

Mensuration Formulas

Triangle …………………… Area= 1/ 2 base x altitude

Page 36: Estimates

Parallelogram ……………… Area = base x altitudeTrapezoid …………………. Area= 1/ 2 sum of parallel side times altitudeCircle ……………………… Area = 0.7854 x diameter

= 3.1416 x radiusCircumference = 3.1416 x diameter

= 6.2832 x radiusEllipse …………………….. Area = 0.7854 x short

Diameter times long diameterCylinder ………………… Surface = length x circumference plus area of ends

Volume = 0.7854 x length x (dia)2Cone …………………….. Surface = 1/ 2 slant height x circumference of base

(curved only)Sphere …………………… Surface = 3.1416 x (diameter)2

= circumference x diameter Volume = 0.5236 x (diameter)2

= 1/6 circumference x (dia)2= 2/ 3 volume of circumscribing cylinder

Material symbolsPLANS AND SECTIONS

EarthConcrete BlockBrickPlaster or SandGypsum TileInsulation (Loose or Rigid)Ceramic Tile-Small ScaleGlass-Large ScaleGlass-Small ScaleStructural SteelSteel and Iron-Large ScaleSteel and Iron-Small ScaleAluminumWood-ContinousWood-Finish (Plan)Plywood-Large ScaleConcrete (Normal)Concrete (High Density)Wood Blocking

Feet Head of Water to PSI

Feet Head Pounds Per Square Inch

Feet head Pounds Per Square Inch

Page 37: Estimates

1 .43 100 43.312 .87 110 47.643 1.30 120 51.974 1.73 130 56.305 2.17 140 60.636 2.60 150 64.967 3.03 160 69.298 3.46 170 73.639 3.90 180 77.96

10 4.33 200 86.6215 6.50 250 108.2720 8.66 300 129.9325 10.83 350 151.5830 12.99 400 173.2440 17.32 500 216.5550 21.65 600 259.8560 25.99 700 303.1670 30.32 800 346.4780 34.64 900 389.7890 38.98 1000 433.00

NOTE:

One foot of water at 62º Fahrenheit equal .433 pound pressure per square inch for any feet head not given in the table above, multiply the feet head by .433.

Water Pressure to Feet Head

Pounds Square Inch Feet Head Pounds Per Square Inch

Feet Head

1 2.31 100 280.902 4.62 110 253.983 6.93 120 277.074 9.24 130 300.165 11.54 140 323.256 13.85 150 346.347 16.16 160 369.438 18.47 170 392.529 20.78 180 415.61

10 23.09 200 461.7815 34.63 250 577.2420 46.18 300 692.6925 57.72 350 808.1330 69.27 400 922.5840 92.36 500 1154.4850 115.45 600 1385.8960 138.54 700 1616.3070 161.63 800 1847.2080 184.72 900 2078.1090 207.81 1000 2309.00

NOTE:

Page 38: Estimates

One pound of pressure per square inch of water equals 2.309 feet of water at 62 Fahrenheit. Therefore, to find the feet head of water for any pressure not given in the table above, multiply the pressure pounds per square inch by 2.309.

Simplified Table for Conversion

Table 11-1

Inches Meter Inches Meter1 .025 21 .5252 .050 22 .5503 .075 23 .5754 .100 24 .6005 .125 25 .6256 .150 26 .6507 .175 27 .6758 .200 28 .7009 .225 29 .725

10 .250 30 .75011 .275 31 .77512 .300 32 .80013 .325 33 .82514 .350 34 .85015 .375 35 .87516 .400 36 .90017 .425 37 .92518 .450 38 .95019 .475 39 .97520 .500 40 1.000

NOTE: Conversion

Meter to feet = divide the length by 30 Ex: 6.00 + .30 = 20 ft.

Feet to meter = multiply feet by .30Ex: 30 ft. x .30 = 9.00 meters

Conversion from Inches to MeterTable 11-2

Inches Meter Inches Meter1 .0254 21 .53342 .0508 22 .55883 .0762 23 .58424 .1016 24 .60965 .1270 25 .63506 .1524 26 .66047 .1778 27 .68588 .2032 28 .71129 .2286 29 .7366

10 .2540 30 .762011 .2794 31 .787412 .3048 32 .8128

Page 39: Estimates

13 .3302 33 .838214 .3556 34 .863615 .3810 35 .889016 .4064 36 .914417 .4318 37 .939818 .4572 38 .965219 .4826 39 .990620 .5080 40 1.0160

Values given are accurate from English to Metric.


Recommended