Estimation Manual

Date post: 03-Apr-2018
Category:
Upload: mayurlanjewar
View: 234 times
Download: 0 times
Share this document with a friend

of 32

Transcript
  • 7/29/2019 Estimation Manual

    1/32

    INDEX

    Title PageIntroduction..2

    2. Responsibilities of Billing Engineer3

    3. Documents to be Maintained by Billing Engineer.4

    4. Mathematical Formulae..5

    5. Cement Coefficient..11

    6. Method of measurements

    Earth work and Back filling.13

    Plain cement concrete15

    Reinforced cement concrete15

    Form works..16

    Reinforcement.20

    Masonry..21

    Plastering21

    Paving, Floor finishes, Dado & Skirting.23

    Whitewashing, Colour washing, Distempering..24

    & Painting works

    Demolition & Dismantling works...24

    Antitermite works..24

    Gypsum and False ceiling works25

    7. Running Bills, Prefinal and Final Bills26

    8. NT Items and Deviations.27

    9. QAD Auditing.28

    10. Bill Certification.29

    11. Reconciliation.30

    12. Invoicing31

    13. Billing Mechanism/ Standards32

    1

  • 7/29/2019 Estimation Manual

    2/32

    2. MATHEMATICAL FORMULAE

    01. SQUAREA

    A Area = A * A

    A Length of one side

    02. RECTANGLEL

    B B Area = L * B

    L - LengthB - Breadth

    03. CIRCLE

    Area = *R*R2

    R- Radius of the Circle

    04.EQUILATERAL TRIANGLE

    h = ( a * 3) /2

    A = (a2 * 3) / 4a a

    B - Base of The TriangleH Height of the Triangle

    2

  • 7/29/2019 Estimation Manual

    3/32

    a5. ISOSCELES TRIANGLE

    Area = c/4*sqrt (4a2

    c2

    )a a c - Base of The Triangle

    a Side of the Triangle

    c

    06. PARALLELOGRAM

    Area = B * H

    B Base lengthH perpendicular Ht of Parellogram

    07. TRAPEZOID

    Area = (A+B)*H2

    A B H- Perpendicular distance btn Parallel sides

    08. SECTOR OF CIRCLE

    Area = Q**R2360

    Where Q = Angle of the SectorR = Radius of the Circle

    3

  • 7/29/2019 Estimation Manual

    4/32

    09. AREA OF RHOMBUS:Area = d1d2

    2

    Where d1 and d2 are the diagonals.

    10. SEGMENT OF CIRCLE:Segment of the circle is that part of the circle contained between the arc and its chord.

    Area = 2*L*H Where L- Length of the Arc3 H - Rise of the arc

    11. QUADRILATERALS:

    A=0.5*d (p1 + p2)

    Where A = area; d = Diagonal; p1 and p2 are the offsets of the Diagonal.

    12. REGULAR HEXAGON:A = (3 a23)/2

    Where A = area; a = side of the Hexagon

    13 REGULAR OCTAGONS: A = 2 a2 (1+2)

    Where A = area; a = side

    14 REGULAR DODECAGONS (12 SIDES):

    A = 6 a2(7/4 + 3)

    Where A = area; a = side

    15 ELLIPSE: A = ab C=DM

    Where A = area; a = semi-major axis; and b= semi- minor axis; C= Circumference; multiplier. Ifvalue of d/D = 0.2,0.3,0.4,0.5,0.6,0.7,0.8,and 0.9 then the corresponding multiplier (M) sill be2.1010,2.1930,2.3013,2.4221,2.5527,2.6912,2.8361, and 2.9866 respectively. D= a*2 and d=2*b.

    4

  • 7/29/2019 Estimation Manual

    5/32

    11. IRREGULAR SURFACES:Divide the area or Figure into an even number (n) of parallel strips by means of (n+1)

    ordinates, spaced at equal distances, d. Let the ordinates be yi

    A. TRAPEZOIDAL RULE:

    Area = d*((y0+yn)/2 + y1 +y2 ++yn-1)

    B. DURANDS RULE:

    Area = d*[0.4(y0 + yn) + 1.1(y1+yn-1)+y2+y3+. +yn-1]

    C. SIMSONS RULE:

    Area = d*[( y0 + yn ) +4*(y1 + y3 +..+yn-1) +2*(y2 + y4 + +yn-2)]3

    VOLUME:1.CIRCULAR CONES: A Cone is a solid whose base is a circle and whose convex surface tapersuniformly to a point called the vertex.

    Volume = 1/3 X area of base X Vertical Ht.Convex Area = X Perimeter of base X Slant Ht.

    2.RECTANGULAR SOLIDS:i) V = abc

    ii) V = A1c = A2b = A3aiii) V = (A1A2A3)iv) V = 2 (ab + bc+ ca)

    v) D = (a2+b2+c2)

    Where V= Volume; S = Whole surface; a = length; b- breadth; c = Depth; A1=Area of

    base; A2 = area of side; A3 = area of end; d = diagonal.3.CUBES:

    i) V = a3

    ii) S = 6 a2

    iii) D = a 3Where V = Volume; S = Whole surface; a = edge; D = Diagonal.

    5

  • 7/29/2019 Estimation Manual

    6/32

    4.CYLINDERS:i) V = r2 h

    ii) S = 2 r (h+r)

    Where V =Volume; S = whole Surface; r= radius of base; h = height.

    5.CYLINDRICAL RINGS:i) V = 2/4 (R+r) (R- r) 2

    ii) V = 1/32 (C + c) (C c) 2

    iii) S = 2 (R2 r2)

    iv) S = (C2 c2)

    Where V = Volume; S= Whole Surface; R= Outer radius; r=inner radius; C= Outer Circumference;c = Inner circumference.

    6.PYRAMIDS AND CONES:V = 1/3 Ah

    Where V = Volume; A = area of base; h= height.

    7.REGULAR TETRAHEDRONS:i) V = (2*2/3) a3

    ii) S = 4 a23iii) H = 2a(2/3)

    Where V = Volume; S = Whole Surface; 2a= edge; h= height

    8.FRUSTRA OF PYRAMIDS, CONES and TRAPEZOIDAL VOLUME:V= H/3 (A1 + A2 + (A1 + A2)

    Where V= Volume; h= height;A1 and A2 are the ends; P and p are the perimeters of the ends; s = slant height.

    9.FRUSTRA OF RIGHT CIRCULAR CONES:i) V= h/3 (R2 + r2 + Rr)ii) S = 0.5 s (C + c)

    iii) S = s (R + r)

    6

  • 7/29/2019 Estimation Manual

    7/32

    Where V = Volume; S = Curved Surface; R and r are the radii of the ends; C and c are thecircumferences of the ends; s = slant height; h= perpendicular height.

    10.SPHERES:i) V = d3/6

    ii) V = 4/3 r3

    iii) S = d2

    iv) S = 4 r2Where V = Volume; S = Surface; d= Diameter; r = radius.

    11.SPHERICAL SHELLS:i) V = /6 (D3 d3)ii) V = 4/3 (R3 r3)

    Where V = Volume; R=Outer radius; r = inner radius; D = Outer diameter;

    d= inner diameter;

    12.ZONES OF SPHERES:i) V = h/3 [3(r1 2 + r22)+ h2]

    ii) S = dh

    Where V = Volume; S = Curved surface; r1 and r2 are the radii of the two ends; h = height;

    d = dia of sphere.

    13.Square of same area as a circle Side = diameter X 0.88623

    14.Circle of same area as a Square Diameter = side x 1.12838

    15.PARABOLAS AND PARABLOIDS: Area of space within the parabola = Base x 2/3 perpendicular height Volume of parabloid (Solid) = r2h

    Where r = radius of the base of the parabloid

    h = height

    7

  • 7/29/2019 Estimation Manual

    8/32

    CEMENT CO-EFFICIENTS FOR RECONCILIATION & OHPS/N DESCRIPTION UNIT CO-EFF

    CONCRETE1 P.C.C.1: 4:8 below foundation/floors CUM 3.30

    2 R.C.C. M-25 footing CUM 7.50

    3 RCC M20 for Roof slab/beam, columns, stair case CUM 6.80

    4 DPC 1:3:6 CUM 4.50

    MASONRY WORKS5 SSM for foundation/basement in CM 1:6 CUM 1.60

    6 200 mm Solid block in CM 1:6 SQM 0.18

    7 100 mm Solid Block in CM 1:6 SQM 0.12

    8 150 mm Solid Block in CM 1:6 SQM 0.15

    9 230 mm Brick Masonry in CM 1:6 CUM 1.23

    10 115 mm Brick Masonry in CM 1:4 SQM 0.14

    PLASTERING11 12 mm Ceiling plastering in CM 1:4 SQM 0.13

    12 12 mm Internal wall plastering in CM 1:6 SQM 0.12

    13 15 MM Rough plaster in walls IN 1:4 SQM 0.12

    14 External plastering SQM 0.20

    15 Basement waterproof plastering SQM 0.18

    16 Duct Plastering SQM 0.18

    17 Plastering Grooves 19mm width and 15 mm Deep RM 0.05

    18 Drip moulds RM 0.0319 PVC beading for Grooves above skirting RM 0.05

    STAIRCASE WORKS20 Tread-Multicolour-20mm thk. SQM 0.22

    21 Riser-Multicolour-20mm thk. SQM 0.22

    8

  • 7/29/2019 Estimation Manual

    9/32

    22 Tread-Sadharalli -10mm thk. SQM 0.22

    23 Riser-Sadharalli -10mm thk. SQM 0.22

    FLOORING24 Screed concrete SQM 0.40

    25 Multicolour granite 20 mm SQM 0.22

    26 Multicolour granite 10 mm SQM 0.22

    27 Sadaralli granite SQM 0.22

    28 Vitrified tile flooring (Labor only) SQM 0.22

    29 Cudappa slab flooring SQM 0.22

    30 Eurocon Tiles for ramp SQM 0.22

    31 Broken tile flooring SQM 0.30

    32 Grano Flooring SQM 0.30

    WALL TILING33 Toilets & Pantry SQM 0.22

    34 Ceramic tile dadoing (1:4) SQM 0.22

    35 Ceramic tile dadoing (1:1) SQM 0.40

    36 Multi color Wall Dado 20 mm thick SQM 0.22

    37 Jet Black Wall Dado 20mm thick SQM 0.22

    38 Door Jambs with Granite SQM 0.22

    SKIRTING39 Granite tile-Multi colour 100 High Rm 0.03

    40 Sadharalli granite 100 High Rm 0.03

    41 Vitrified tile-glossy(Labor only) 100 High Rm 0.03

    42 Cudappah slab skirting 100 High Rm 0.03

    43 Cement skirting 100 High Rm 0.03

    44 190 mm High Skirting Rm 0.04

    45 Clay Tile Skirting works in Terrace Rm 0.10

    MISCELLANEOUS46 Multi colour granite coping 20 mm SQM 0.22

    47 Multi colour granite coping 10 mm SQM 0.22

    48 Hume Pipe RM 0.60

    9

  • 7/29/2019 Estimation Manual

    10/32

    MODE AND METHOD OF MEASUREMENTS:EARTHWORK AND BACK FILLING:

    1. Block Levels has to be taken at the start of the work. The intervals can be of 3m or 5m.

    2. The Uom is in CUM and should be rounded off to nearest two decimals.

    3. For Pit Excavation an offset of 30 cm can be taken on either side of the footing up to 1.5 m

    depth and for more than 1.5 m depth it can be taken as 50 to 60 cm.

    4. For Pit excavation Depth can be arrived by taking

    = Average top level Average Bottom Level

    5. For Mass Excavation Earth work quantity can be calculated by using any of the rules like

    Trapezoidal or simsons rule etc. Proper CVI (Reasons) has to be maintained for Mass

    Excavation

    6. For hard rock and soft rock the top levels and bottom levels should be taken with consultant

    approval. The Quantity can be arrived with top and bottom levels or the quantity can be

    arrived by stacking the Hard rock. The place for stacking should be selected in accordance with

    clients approval and must be recored with joint measurement from client and contractor.

    7. Back filling quantity can be arrived using trapezoidal or simsons rule.

    8. Final quantity is arrived by deducting the volume of concrete and size stone masonry below

    ground level from the total quantity.

    9. Earth brought from outside or to be carted away is calculated by

    = Total Excavated Quantity - Total Backfilling Quantity.

    If Value is - Ve - It is Earth brought from outside

    +Ve - It is Earth to be carted away.

    10. For Jungle clearance item, the area to be considered is 5m off set all-round the building and if

    for road works, 1m offset should be considered on either side.

    11. For EX: The below is the block level of area 40 m X 20 m with levels of 5 m interval with mass

    excavation to be done for entire area with excavation bottom level as 95.2

    10

  • 7/29/2019 Estimation Manual

    11/32

    BlockLevel

    98.7

    98.75

    98.65

    98.55

    98.78

    98.85

    98.95

    98.98

    98.90

    98.85

    98.68

    98.72

    98.76

    98.78

    98.80

    98.92

    98.93

    98.95

    98.95

    98.75

    98.78

    98.80

    98.75

    98.90

    98.85

    98.65

    98.75

    98.65

    98.55

    98.35

    98.54

    98.64

    98.7

    98.68

    98.45

    98.38

    98.7

    98.68

    98.45

    98.58

    98.60

    98.68

    98.54

    98.65

    98.28

    The volume can be found by taking average rectangle/square method. The depth of excavation

    =(98.75+98.7+98.68+98.85)/4 95.2 (i.e. Avg Top lvl Bottom lvl.).

    = 3.545 m

    Area = 5 X 5 = 25 sqm

    Volume of Earth = Area X Depth = 25 X 3.545 = 88.63 cum

    11

  • 7/29/2019 Estimation Manual

    12/32

    Similarly Volume of Earth has to be calculated for Other Square areas and to be added to get

    the total quantity. If there is hard rock, it can be stacked separately. The volume of Hard rock

    stacked can be found by taking site measurements. For Ex, refer below sketch as stack

    measurement.

    The Hard rock is stacked in trapezoidal shape generally.

    Stacked Quantity = H/3 (A1 + A2 + (A1 + A2)

    A1 = Lx B = 10 x 8 = 80 m2

    A2 = L1xB1= 6 x 4 = 24 m2

    = 2/3x(80+24+(80+24))= 76.13 cum

    The Volume of Hard rock = The volume of stacked quantity Deduction for voids.

    Deduction for Voids should be preaccepted and normally stated in percentage of stacked

    quantity. From the total Quantity of the mixture the quantity of hard rock excavated thus arrived at

    shall be deducted to work out the quantity of the soft, disintegrated rock excavated.

    PLAIN CEMENT CONCRETE:

    1. Quantities should be taken only as per drawings with offset as mentioned in drawings.

    2. Any variations with respect to drawings should be recorded and CVI should be got from clients

    and should be intimated to Estimation Department and Project head immediately.

    3. The variation can be like mass Pcc, Variation in Thickness due to site requirement, Grade

    change, laying using pump etc. Variation due to faulty execution cannot be claimed.

    4. Shuttering for edges has to be claimed unless it is mass execution.

    12

  • 7/29/2019 Estimation Manual

    13/32

    5. UOM is usually in cum. For Screed it is in sqm .

    REINFORCED CEMENT CONCRETE:

    1. The Quantities can be rounded off to the nearest two decimals.

    2. Concrete in Structural members, such as columns, Beams and slabs shall each be measured

    separately.

    3. No Deductions shall be made for the following.

    Opening up to 0.1 m2 Volume occupied by reinforcement. Volume occupied by pipes, conduits, sheathing, etc not exceeding 100 cm2 each in

    cross-section.

    Moulds, drips moulding, chamfers, splays rounded or covered angles, beds, grooves

    and rebates up to 10 cm in girth

    4. Footings:Volume of concrete = L *B *D for Rectangular and Square footing.

    For Trapezoidal Footing, Volume of Concrete is calculated in two parts. Bottom

    Rectangular portion is calculated separately and Trapezoidal volume is calculated separately.

    Rectangular Volume = L*B*D

    Trapezoidal Volume V= H/3 (A1 + A2 + (A1 + A2)

    Total Volume = Rectangular Volume + Trapezoidal Volume

    Where V= Volume; h= height;

    A1 and A2 are area at the Top and Bottom ends.

    5. Columns: Columns shall be measured from top of Column base to underside of first floor slaband subsequently from top of floor slab to underside of floor slab above. Incase of Columns for

    flat slabs, flare of column shall be included with column for Measurement.

    6. Beams: Beams shall be measured from face to face of columns and shall include haunches, ifany, between columns and beams. The depth of beams shall be measured from bottom of slab

    to bottom of the beam except incase of inverted beam where it shall be measured from top of

    slab to top of beam.

    13

  • 7/29/2019 Estimation Manual

    14/32

    7. Pedestals: Pedestals is measured from top of Footing to top/ Bottom of plinth beamdepending on site conditions. If measured up to bottom of Plinth beam then Ground floor

    column can be measured from Bottom of plinth beam to underside of slab. The Height of

    Pedestal can be arrived from levels of footing and plinth beam. The Height shall be

    crosschecked with site also.

    FORM WORKS:

    1. Dimensions shall be measured to the nearest 0.01 m.

    2. Areas shall be worked out to the nearest 0.01 m2.

    3. Formwork shall be measured in sqm as the actual surfaces in contact with the concrete or any

    other material requiring formwork.4. Shuttering For PCC Edges has to be taken unless otherwise it is mass Pcc.

    5. Footing:

    Footing shuttering = 2(L+B)*D Where L Length, B Breadth, D Depth.

    6. Column shuttering is calculated same as above. But height of column should be taken from

    top of column base to underside of floor slab. Pedestal shuttering is also normally taken in

    Column shuttering. Circular Columns should be taken separately i.e. Q= 2 r h/ dh where r-

    radius and d Diameter, h - Column height.

    7. In case of Flat slabs for column-shuttering height of column is taken up to bottom of column

    capital and capital shuttering should be taken separately.

    8. No Deductions shall be made for opening up to 0.4 m 2. No Deduction shall be made for any

    opening /cutouts when slip form technique is used.

    9. Formwork to secondary beams shall be measured up to the sides of main beams, but no

    deduction shall be made from the formwork of the main beam where the secondary beam

    intersects it. Formwork to beam shall be measured up to sides of column, but no deduction

    shall be made from the formwork to stanchion or column casings at intersections of beam.

    10. Examples for calculating Footing Concrete & Shuttering: Size of Footing = 4 m x 3m x 0.8 m

    with PCC 100 mm thick below with offset of 100 mm all sides.

    14

  • 7/29/2019 Estimation Manual

    15/32

    0.8m 0.9 m

    4 m

    4.2 m

    Rectangular Footing

    Footing PCC quantity = Lx B x D = 4.2 x 3.2 x 0.1 = 1.34 cum

    Footing PCC Shuttering = 2x(L+B) x D = 2x (4.2+3.2) x 0.1 = 1.48 sqm

    Footing Concrete Quantity = Lx B x D = 4 x 3 x 0.8 = 9.6 cum

    Footing Shuttering Quantity = 2 x (L + B) x D = 2 x (4 + 3) x 0.8 = 11.2 sqm

    3 m

    1.28 m

    .8 m

    1.0 m

    5 m

    5.2 m

    1m 3m 5.2m 5m

    15

  • 7/29/2019 Estimation Manual

    16/32

    3m

    1m

    Trapezoidal FootingPCC concrete and shuttering quantity is calculated similarly as above example.

    Concrete quantity for trapezoidal footing = Trapezoidal volume +Rectangular Volume

    = d/3 x (A1+A2+(A1+A2))+Lx B x D

    A1 = 5 x 5 = 25 m2

    A2 = 3 x 3 = 9 m2

    Concrete Quantity = 0.8/3 x (25 + 9 + (25+9))+5x5x1 = 10.62+25=35.62 cum

    Shuttering Quantity = 2 x (L+B) x D = 2 x (5+5) x 1 = 20 m2

    Example for Beam, column and Slab Concrete & Shuttering:

    C1 B1 C1

    A AB1 SLAB 100mm thk 3.6 m B14 m

    5.6 m

    C1 B1 C1

    6mSlab 100 mm thk

    16

  • 7/29/2019 Estimation Manual

    17/32

    Beam 200 x 6004.5 m

    2.9m 3.0 m 2.4 m

    Section AAC1 Column 200 x 750 mm; B1 Beam 200 x 450 mm

    Column Concrete & Shuttering:Column concrete for C1 = L x B x D = 0.75 x 0.2 x 2.9 = 0.44 cum

    For four no = 4 x 0.44 = 1.76 cumColumn shuttering for C1 = 2 x (L + B) x D = 2 x (0.75+0.2) x 2.9 = 5.51 m2

    For Four no = 4 x 5.51 = 22.04 m2

    Slab Concrete & Shuttering:Slab Concrete = L x B x D = 6 x 4 x 0.1 = 2.4 m3

    Slab Shuttering = L x B = 5.6 x 3.6 = 20.16 m2

    Beam Concrete:Beam Concrete in longer span = L x B x D = 4.5 x 0.2 x 0.5 = 0.45 cum

    For 2 Beams = 2 x 0.45 = 0.9 cumBeam concrete in shorter span = L x B x D = 3.6 x 0.2 x 0.5 = 0.36 cum

    For 2 Beams = 2 x 0.36 = 0.72 cum

    Total Beam Concrete = 0.72+0.9 = 1.62 cum

    Beam Shuttering:

    17

  • 7/29/2019 Estimation Manual

    18/32

    Beam Shuttering in longer span = 2 x L x (D1 + D2) = 2 x 4.5 x (0.6+0.5) = 9.9 m2

    For 2 beams = 2 x 9.9 = 19.8 m2

    Beam Shuttering in Shorter span = 2 x L x (D1 + D2) = 2 x 3.6 x (0.6+0.5) = 7.92 m2

    For 2 Beams = 2 x 7.92 = 15.84 m2

    Total Beam Shuttering = 19.8 + 15.84 = 35.64 m2

    Reinforcement:1. Reinforcement is measured normally in metric tones-MT. Unit weight of steel is 7850 kg/cum

    2. Weight of bars/rm for different dia can be calculated using w= D2/162 where w-weight in kg;

    D-Dia of bar in mm

    3. Normally lap of bars is taken as 50 times diameter. When two different dia is lapped together

    the lap length is taken as 50 times of smaller dia.

    4. Normally no. of bars in footing mat is calculated by

    No of bars in shorter direction =(Length of longer side cover in both ends/ spacing) +1

    No of bars in Longer direction =(Length of Shorter side cover in both ends/ spacing) +1

    5. Cover of footing is 50 mm, Column is 40 mm, beam is 25 mm and slab is 15mm.It

    may vary as per design and site.

    6. For Tie Bars in columns and stirrups in beam the hook length is taken as 100mm normally.

    7. Extra rods provided as per site should be claimed with proper back up and site instruction.

    8. Chair rods in footing, slab and spacer bars in Beam should be claimed unless otherwise it is

    mentioned in the purchase order.

    9. Tie bars and stirrups will not be claimed in beam-column junction unless or otherwise it is done

    in site.

    Masonry works:1. For size stone masonry proper CVI should be maintained at site confirming the width and

    depth of courses to be done. Site measurements should be taken and hand sketches should be

    made with location, width, Depth and length of the courses. Appropriate levels can also

    support it. UOM is in cum.

    2. Pcc Below SSM and Damp proof course above SSM should be claimed including shuttering tothe sides in Plain cement concrete Item.

    3. Blocks of different sizes and specification should be claimed separately. Actual Height is taken

    including concrete packing at the top course.

    4. Block work is measured in sqm and 12.5 Blocks is considered for 1 sqm.

    18

  • 7/29/2019 Estimation Manual

    19/32

    5. Openings for windows and Doors and other opening should be deducted. Area for lintels above

    doors and windows shall not be deducted.

    6. Soling is measured in cum. The depth should be supported with levels. Any deviations should

    be recorded and can be claimed if it can be justified.

    7. Block work/Brickwork for step works is normally missed out. PCC Below steps and shuttering

    for edges also should be taken in to account while billing.

    8. Brickwork 115 mm thk is measured in sqm. Normally it is done as skin wall in toilet in water

    closet area.

    9. Brickwork more than 115 mm thk is measured in cum. If standard bricks are used, 500 nos are

    required for 1 cum.

    10. Cinder filling is measured in cum and is done in sunken and hollow portions like

    Stepped/sloped classrooms and toilets.

    Plastering works:1. Dimensions shall be measured to the nearest 0.01 m.

    2. Areas shall worked out to the nearest 0.1 m2

    3. Preparatory work, such as raking out joints, scarifying and cleaning, shall be included in the

    description of item unless otherwise specified.

    4. Plasterwork shall be classified according to the material used and each classification shall be

    measured separately.

    5. The following particulars shall be given for each classification.

    Mix of mortar;

    Number of coats and thickness of each coat;

    Nature of surface treatment;

    Nature of base;

    Curved work, conical work, spherical work and elliptical work stating the radius; and

    Any special treatment of base.

    6. Plastering on roofs, ceilings and walls shall be measured separately.

    7. Removing plaster by scraping or otherwise shall be measured separately in sqm.

    8. Plastering in Isolated widths or in Widths not forming part of general plastering work (as in

    bands, cornices, sunk, panels, etc) and in chamfers, rounded angles exceeding 80 mm in girth

    shall be measured as below:

    30 cm or below in width/girth, in running meters; and

    Width/girth above 30 cm in sqm.

    19

  • 7/29/2019 Estimation Manual

    20/32

    9. Plastering at a height greater than 10 m above ground / datum level shall be measured

    separately in stages of 5 m height except interior plastering incase of building which shall be

    measured separately for each storey.

    10. All plastering shall be measured in sqm unless otherwise described

    11. No Deductions shall be made for ends of joists, beams, posts, etc, and openings not exceeding

    0.5 m2 each and not exceeding 0.5 m2 each and no addition shall be made for reveals, jambs,

    soffits, etc, of these openings nor for finish to plaster around ends of joists, beams, posts, etc.

    12. Deductions for openings exceeding 0.5 m2 but not exceeding 3 m2 each shall be made as

    follows and no addition shall be made as follows and no addition shall be made for reveals,

    jambs, soffits, sill, etc, of these openings:

    When both faces of wall are plastered with same plaster, deduction shall be made fro

    one face only.

    When two faces of wall are plastered with different types of plaster 50% Deductionshall be made on either side.

    When only one face is plastered and the other face is not, full deduction shall be made

    from plaster if width of reveal on plastered side is less than that on unplastered side

    but if widths of reveal on both sides are equal or width of reveal on both sides are

    equal or width of reveal on plastered side is more, no deduction shall be made.

    13. Incase of openings of area above 3 m2 each, deduction shall be made for opening on each face

    but jambs, soffits and sills shall be measured.

    14. Ceilings shall be measured between walls or partitions and dimensions before plastering shall

    be taken. Width covered by cornices or coves, if any shall be deducted.

    15. Soffits of stairs shall be measured as plastering on ceilings. Ribs and mouldings on ceilings shall

    be measured as for cornices, deduction being made from plastering if width/girth exceeds 15

    cm.

    16. Measurement of wall plastering shall be taken between walls or partitions (Dimensions before

    plastering being taken) for length and from top of floor or skirting to ceiling for height. Depth

    of cornices or coves, if any, shall be deducted. When taken from top of skirting, for deduction

    of doors, height of opening should be considered subtracting the skirting height.

    17. Plastering on honeycomb work shall be described and measured in sqm on the basis of overall

    superficial area without deducting openings.

    Paving, Floor Finishes, Dado and Skirting:

    20

  • 7/29/2019 Estimation Manual

    21/32

    1. Dimensions shall be measured to the nearest 0.01m and areas shall be worked out to nearest0.01 m2 Except for skirting, which is measured in Rm.

    2. Expansion and dummy joints shall be described and measured separately in Rm stating depth

    and width of joints. The filler shall be described and included in the description of item.

    3. Curved work, conical work and spherical work shall be measured separately.

    4. Insitu finishes shall be classified according to the kind of material (for Example, granolithic,

    terrazzo, mosaic, etc) and measured separately. The following particulars shall be given for

    each classification:

    Composition and mix;

    Thickness, which shall be exclusive of keys, grooves and open joints;

    Number of coats;

    Nature of surface treatment (for example, steel trowelled, wood floated, polished,

    sprinkled with carborundum powder, etc);

    Nature of base and any special treatment to the same; and

    Situations, for example, whether in flooring or in dado/skirting

    5. No Deduction shall be made for voids not exceeding 0.2 m2.6. Work in treads, risers and edges of landings shall be measured in square meters. Work in

    landing shall be included in main item.

    7. Moulded nosing shall be measured in Rm. Dodos shall be measured in sqm. Skirting shall be

    measured in Rm stating height.

    8. Granite and tile works should be described in detail like thickness of mortar bed / cerabond or

    araldite backing with details like nosing and chamfering and width incase it is measured in rm.

    White washing, colour washing, Distempering, and painting works etc

    1. Method of measurements is same as that of plastering.

    2. The Description should be clear like number of basecoats and final coats.

    3. Deductions for openings are same as like that of plastering

    4. Corrugated surfaces shall be measured flat as fixed and not girthed. Quantities so measured

    shall be increased by the following % and resultant shall be included in general areas:

    Corrugated steel sheets - 14 percent

    Corrugated asbestos cement sheet - 20 percent

    Semi-corrugated asbestos cement sheets - 10 percent

    Nainital pattern roofs (Plain sheeting with rolls) - 10 percent

    Nainital pattern roofs with corrugated sheets - 25 Percent

    21

  • 7/29/2019 Estimation Manual

    22/32

    5. Area of uneven surfaces be converted into equivalent plain areas as under:

    External walls of plain brick work faced with recessed, raised or weather stuck

    pointing - 20 percent

    Sand faced plaster width up to 4 mm size - 50 percent

    Rough cast plaster with stone aggregate up to 10 mm 100 percent

    Pebble dash finish 275 percent

    6. Rcc jallies up to 50 mm thick, the quantity shall be increased by 50 percent if painted on one

    side and 70 percent if painted on both sides; when thicker than 50 mm the quantity shall be

    based on actual area painted.

    Demolition and Dismantling:

    1. Dimensions shall be measured to the nearest 0.01 m, Areas shall be worked out to the nearest

    0.01 m2 and volume to nearest .01 m3.

    2. Works required to be demolished and to be dismantled shall be measured separately.

    3. Distances exceeding 100 m and up to 1 km shall be measured in units of 100 m and those

    exceeding 1 km in units of 500 m.

    Antitermite Treatment:1. Antitermite treatment is measured in sqm.

    2. Area to be considered is the plinth area of the building.

    Gypsum and false ceiling works:

    1. Grid ceiling works is measured in sqm

    2. If client supply the material it should be billed separately and our supply is there it should be

    billed separately. Wastage should not exceed more than 5%.

    3. Materials normally used are Grid tiles 600 x 600(owatiles, aerolite). The materials used for Grid

    works are Main Tee, Cross Tee 1.2 m, Cross Tee 0.6 m, J hook, MS wires, perimeter angles, &

    Black screw.

    22

  • 7/29/2019 Estimation Manual

    23/32

    4. Gypsum ceiling is measured in sqm. Plain and Decorative ceilings should be billed separately.

    The drops for the ceiling should be taken in to account based on the rate analysis. Normally for

    Infosys projects the drops are also measured for the gypsum ceiling quantity.

    5. Gypsum partitions are measured in sqm. The width of the partition, Double side board or single

    side board, number of boards on either side etc should be clearly mentioned based on which

    the rates are decided.

    6. Gypsum cladding and Boxing for Beams and columns are measured in sqm.

    7. Wastage allowed is only 5%. If wastage increases it has to be supported with proper backup

    and workings, so that it can be claimed.

    8. Gypsum punning and POP punning is measured in sqm. The method of measurement followed

    for plastering and painting is applicable for POP/Gypsum punning.

    5.RUNNING BILLS & FINAL BILLSRunning Bills:

    Running bills are prepared every month based upon the work executed in the site. The Billing engineerhas to take the actual measurement at site and prepare the bill. The running bills should be raised

    before 25 th of every month and submitted for certification, along with the invoice before 28 th of the

    month. A copy of the running bill has to be forwarded to estimation department on 25 th of every

    month. The running bills should be certified within 28 days from preparation. The Bill submission date

    varies as per Location of site and requirement of client.

    Running bill abstract shall be divided into three parts

    23

  • 7/29/2019 Estimation Manual

    24/32

    Annexure A: Items as per PO

    Annexure B: Items Exceeding PO

    Annexure C: Non Tendered Items

    In Annexure A, all the items as per the Purchase order / work order should be included irrespective of

    whether its executed in the site or not. If an item is not executed then the quantity and value will be

    zero.

    In Annexure B, only the items, which are exceeding the PO/WO, shall be included. The items number

    should be same as that of the PO. The quantities that are exceeding the PO quantity shall be included

    in this annexure.

    In Annexure C, all non-tendered items are included. The specification and quantity as executed in the

    site are shown in this annexure. The estimation department will give the rate for the non-tendered

    item. All non-tendered items should be supported by any of the following.

    (a) Site Instruction from Client/architect/consultant

    (b) Drawings issued by the architect

    (c) Confirmation of Verbal instruction issued by client/consultant/architect

    (d) Minutes of meeting, if the same is discussed & approved in the meeting

    Pre final

    The pre final / final bill should be prepared within 14 days after the handing over/completion of the

    project. The final bill should have the following

    Reconciliation statement (client supply and company supplied materials)

    Certified copy of all running bills

    Supporting documents for Non Tendered items

    Rates for Non tendered items (Which shall be provided by estimation department)

    The copy of the Pre final bill should be given to QAD for final checking. The final bill should be

    submitted for certification after QAD auditing.

    The Pre final bill should be certified within 56 days from the date of preparation/submission.

    After certification of Pre Final bill, a copy of the bill has to be forwarded to estimation department for

    amendment of the PO. The estimation department will take up the PO amendment.

    FINAL BILL:

    24

  • 7/29/2019 Estimation Manual

    25/32

    Final bill shall be raised only after the amendment of PO. The final bill value should be

    equal to the Amended PO Value, so that there will be no problem in accounting the invoice and for

    closure of the PO.

    6. NT ITEMS AND DEVIATIONS FROM PO

    The Non Tendered items and deviations will happen in almost all projects. Any item that is not

    considered in the estimate is a Non Tendered item. Any which is considered in the estimate and during

    the time of execution there is a change in the specification can be considered as deviation item. For

    example, in the estimate the following item is considered

    (a) Providing and fixing 190mm high skirting in Jet Black Granite flushed to the wall surface with

    mortar backing including chamfering the edges for Staircase

    It is decided to use Multi color granite instead of jet-black granite, and then the item will be a deviation

    item from the original specification. Although the item is considered in estimate, the rate for the item

    varies due to change in specification.

    If an entirely new item of work, which is not considered in the estimate, is introduced, the item is billed

    in Non Tendered item. In normal case, the specification of non-tendered item has to be clearly decided

    and the rate has to be finalized before starting the job. But in very few exceptional cases, the item can

    be executed with the written approval of client/consultant.

    7. QAD AUDITINGThe quantity audit department will audit the client bills periodically. Its the

    responsibility of the billing engineer to give full support to the audit team. Each item has to be

    explained properly and any variation informed by the audit team should be incorporated in the

    subsequent bills. The audit team will scrutinize the following elements

    25

  • 7/29/2019 Estimation Manual

    26/32

    a. Method of measurement

    b. Status of drawing

    c. NT items

    d. Site Instruction

    e. Stages of certification

    f. Expenditure Vs Bill - Comparison

    g. Missed out / Deviation Items

    h. Rates

    The billing engineer has to produce the clear facts related to above items. The audit team will explain

    the drawbacks, if any, and care should be taken to avoid it.

    8. BILL CERTIFICATION:This is one of the most important jobs as far as billing engineers are

    concerned. Bill prepared has to be properly submitted to the client/consultant with necessary

    documents such as invoice, abstract sheet, detailed measurement sheet, site instruction/CVI, drawings

    etc. The client/consultant will verify the bill as executed in site and certify based on actual. The billing

    engineer has to explain each item properly with the help of drawings, hand sketch. There should not be

    26

  • 7/29/2019 Estimation Manual

    27/32

    any disparity in the bill submitted. Any correction proposed by the client/consultant has to be done

    immediately.

    Following points has to be noted before submitting the bill

    Properly file the abstract, measurement sheet. The original has to be submitted and the copy

    to be retained by the billing engineer.

    The invoice in the first page followed by bill abstract, copy of PO and measurement sheet

    The measurement sheet should be numbered and the page no has to be indicated in the

    remarks column of abstract sheet against the item of work

    Relevant drawings/ hand sketches to be filed along with the measurement sheet

    Any carry over / back file to be indicated with page numbers

    After the certification of the bills, necessary corrections as mentioned by the architect/consultant/client

    to be incorporated in the bill and a copy of the bill duly signed by the architect/consultant/client to be

    forwarded to estimation/billing department. The architect/consultant/client may issue a certificate of

    payment, which reflects the amount due to the contractor and taxes to be paid by the client against

    the work executed.

    The billing engineer should take minimum time possible for certification of the bills. The time allotted

    for certification of running bills is 28 days and final bill is 56 days.

    9.RECONCILIATION

    All materials used in the project have to be reconciled and the reconciliation

    of client-supplied material has to be attached with the final bill. The intention of reconciliation is to

    arrive the percentage of wastages incurred during the course of the project and comparing with

    the permissible percentage of wastages. The reconciliation has to be carried out monthly so that a

    27

  • 7/29/2019 Estimation Manual

    28/32

    control on excess wastages of materials is achieved. The major items, which are to be recon

    ciliated, are

    Civil & Finishes Works

    1. Ready mix concrete All Grades

    2. Cement

    3. Steel

    4. Sand

    5. Tiles

    6. Size Stone

    7. Blocks

    8. Structural Steel

    9. Gypsum Materials

    10. Grid Ceiling materials

    11. Granite

    The format used for preparing the reconciliation statement is attached.

    10.INVOICINGThe bill carries details about the specification, Unit of measurement, quantity, rate and

    amount. Apart from these there is a tax component, which may not be shown in the bill abstract. The

    tax component may be for the entire amount of bill raised or for certain item of work. While we submit

    the bill to the client, the tax component has to be added and we have to raise a claim for the entire

    amount. The Invoice is the claim put forward by the contractor for the item of work executed as per

    the agreement along with the taxes/duties as applicable.

    28

  • 7/29/2019 Estimation Manual

    29/32

    The accounts department does invoicing in co ordination with billing department.

    The invoice will carry following details

    Name and Address of the client Invoice No and Date

    Project Name

    Running bill No

    TIN/CST No and date

    PO/WO/LOI No and date

    PAN No/ Service tax No and date

    Bill Value

    Taxes

    Total Invoice value

    Signature of authorized person

    If the tax component is for the entire bill value then its shown in the invoice itself. If the tax

    component is for certain item of work then there should be separate working sheet attached clearly

    showing the applicable taxes and the same has to be reflected in the invoice.

    The copy of the bill has to be forwarded to accounts department for invoicing. The accounts

    department will provide the appropriate tax percentage/value as per the terms and conditions in

    PO/WO/LOI.

    ANNEXURE(1) Format of measurement sheet

    (2) Format of bill abstract

    (3) Format of reconciliation statement

    COST CONTROL CHECK LIST FOR PROJECTS

    ACTIVITIES POINTS TO BE NOTED BILLING MECHANISM / STANDARDS

    EARTH WORKS

    Working space 300mm from Footing face

    Natural Ground levels Block leveling before excavation starts

    Excavation depth Not more than shown in the Drawings

    Stacking excavated earthLocation to be agreed with Client to avoid anydouble shifting

    29

  • 7/29/2019 Estimation Manual

    30/32

    PCC WORKS

    Depth of PCC Not more than shown in the Drawings

    Grade of PCC As mentioned in Drawings

    Offset of PCC from Footing Not more than shown in the Drawings

    REINFORCEMENT

    Wastages Not more than 3%

    Cut pieces Try to use maximum in Lintels / Grade slabs

    RCC WORKS

    Wastages in RMCNo wastages (0%), ideally there should besavings of reinforcement volume.

    Thickness of Slabs Not more than shown in the Drawings

    RMC volume receivedShould be cross verified every time for majorconcreting with the actual quantity of workdone to the Theoretical Quantity

    SHUTTERING WORKS

    No of RepetitionsNot less than 4 for ordinary plywood

    Not less than 8 for film faced plywood

    If standard repetitions not availableMust be worked out at the beginning saybefore 30 days from Starting of the Projectand informed to Contracts.

    BLOCK WORKS

    Wastages In Blocks Not more than 5%

    Mortar wastagesNo wastages allowed, it must be reusedsimultaneously

    Mortar mixMust be maintained as per proportion byVolume batching

    PLASTERING

    Average Thickness of Plaster

    Not more than 15mm for internal plastering

    Not more than 25mm for External plastering

    Mortar wastagesNo wastages allowed, it must be reusedsimultaneously

    Mortar mixMust be maintained as per proportion byVolume batching

    TILE FLOORINGTile normal wastages Not more than 6% unless design flooring

    Any Additional wastages

    Must be worked out in the beginning and

    documented with the approval fromArchitects/Clients/Contracts

    Average Mortar bed thickness Not more than as shown in the drawings forexample for 50mm thick floor finishes it mustbe equal or less than 42mm (50mm-8mm)considering thickness of tile as 8mm

    30

  • 7/29/2019 Estimation Manual

    31/32

    Mortar mixMust be maintained as per proportion byVolume batching

    GRANITE FLOORING

    Granite normal wastages Not more than 10% unless design flooring

    Any Additional wastages

    Must be worked out in the beginning and

    documented with the approval fromArchitects/Clients/Contracts

    Average Mortar bed thickness

    Not more than as shown in the drawings forexample for 50mm thick floor finishes it mustbe equal or less than 30mm (50mm-20mm)considering thickness of Granite as 20mm

    Mortar mixMust be maintained as per proportion byVolume batching

    TILE DADOING

    Tile normal wastages Not more than 8% unless design

    Any Additional wastagesMust be worked out in the beginning anddocumented with the approval fromArchitects/Clients/Contracts

    Rough plastering thickness Not more than 15mm

    Average Mortar backing thickness Not more than 20mm

    Mortar mixMust be maintained as per proportion by

    Volume batching

    FALSE CEILING

    Gypsum board wastages Not more than 5% unless design

    Grid tile wastages Not more than 5% unless design

    Any Additional wastages

    Must be worked out in the beginning and

    documented with the approval fromArchitects/Clients/Contracts

    GENERAL MATERIALSCement wastages Not more than 3%

    Sand wastages Not more than 20%

    PRELIMINARIES

    Site infrastructure like Office, go

    down, stores, lab etc

    Location must be studied at the beginning and

    Client approval must be taken on a drawing.

    Any relocation must be as per the instructions

    from Architects/Clients, which must be claimed

    in the bill and get certified.

    Material stack yard Same as above

    Labour sheds Same as above

    31

  • 7/29/2019 Estimation Manual

    32/32

    TRACTOR LOADS Shifting works

    Any shifting as per Client/Architect instructions

    must be documented with approx loads before

    starting the work on Site instructions, which

    may be other contractors work, demolition

    works, office shifting, stack yard shifting etc.

    (which are not due to our internal

    requirement)

    WATER & ELECTRICITYSupplied to Other Client side

    Contractors

    Must be charged to them with some lumpsum

    amount fixed at the beginning. This is only if

    we are sourcing the supply (when Client is not

    supplying the Water & electricity free of cost

    or if he is supplying and deducting from our

    bills based on the consumption)

    SCAFFOLDING

    Provided to Other Client side

    Contractors

    Must be charged to them with some lumpsum

    amount fixed at the beginning.

    Provided at a later stage for

    modifications due to Architect /

    Client instructions

    Must be recorded and charged to Client with

    Site instructions

    RECONCILIATION Reconciliation of Major materials

    It must be done monthly for Cement, Sand,

    Aggregates, RMC, Reinforcement, Granite and

    Tiles, Gypsum & Grid tiles.


Recommended