Date post: | 27-Mar-2015 |
Category: |
Documents |
Upload: | alexander-willis |
View: | 213 times |
Download: | 0 times |
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Status of ITER like wall project
V. Philipps
ITER
2 options are under preparation, decision about time schedule at a given time
EU-PWI-Task Force
TF Meeting, 17-19 2005 Cadarache
1
Physics research in associations
• Fusion devices
• linear plasmas
• lab experiments
etc..
2
EFDA PWI technology programme
• specific tasks
• integration of work outside
associations
3
Integrated wall experiments in fusion devices
Organisation & work structure
See Albertos talk
AUG
JET wall experiment
Main part of our meeting
JET with Be wall and all Tungsten divertor
Objectives
• Demonstrate low T retention
• Study effect of Be on W erosion
• Study ELMs and disruptions on wall & divertor, melt layer behaviour
• Develop control / mitigation techniques for ELMs and disruptions
• Test de-tritiation techniques
• Operate Tokamak without C - radiation
Demonstrate operation of ITER scenarios at high current and heating power with a Be/W material choice
EU PWI Task ForceJET ITER like Wall material experiment
EU PWI Task Force
Full Be wall with ITER like Carbon/tungsten divertor
Objectives
Similar to an all W divertor but including carbon chemistry
• Effect of Be deposition on carbon release and transport
• Study of Be/C(W) layers, their thermal stability, T-retention
demonstrate that an ITER-like material selection has sufficiently low fuel retention to meet ITER requirements.
STRATEGY: Prepare both options, decide options depending on requirements
Demonstrate operation of ITER scenarios at high current and heating power with Be/C/ W wall choice
EU PWI Task ForceWall material experiments
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Organisation
Manual + RH Installation now integrated
Be main chamber
NBI Shinethrough protection
Upper Dump plate
Inner wall cladding
Inner wall guard limiters
Saddle coil protection
Saddle coil protection
Outer poloidal limiters
LH + ICRH protection
KC1 coil covers
Total main wall tiles = 4404
Main wall: Be wherever possible , on some areas W coated CFC: responsible JOC (operator)
Global carbon deposition TEC
Institut für PlasmaphysikAssoziation EURATOM-Forschungszentrum JülichV. Philipps, ITPA Tarragona, June 05
Inner Wall Material Distribution
Shinethrough Area
Restraint ring protection
Option for Be coating of inconel cladding is being investigated
W coated CFC 15mm back from limiter edge
X?
Proposals:• Configuration - Final decision 2006• complete set of divertor tile
replacements ordered (marked in red)
→ RD task to IPP Garching for W coating on CFC substrate
→ RD task to FZJ Jülich on W bulk concept
Divertor options
Association “thick” method
“thin” method total number
CEA VPSCVD
CVD 4 and 10 3
ENEA VPS 1
TEKES PVD 4 and 10PVD/Re interl. 4 or 10
3
IPP Garching VPSCVD
PVD (4 and 10)CVD (4 and 10)
6
MEC/CEA CMSII/TVA(probably 10µm by CMSII)
1
: VPS=Vacuum Plasma Spray, CVD=Chemical Vapor DepositionPVD=Physical Vapor Deposition, TVA=Thermionic Vacuum ArcCMSII=Combined Magnetron Sputtering and Ion Implantation
Different Coating Types provided by Associations
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
W coating task, status ( H. Maier IPP )
shipment of coatings to IPP, due Sep 1
status: 10 out of 14 types delivered4 on the way
summary: 14 out of 14 possibly in test program
Meeting oct 7 for final agreement among parties on benchmarking of testing procedures for NDT for the procurement of the coated tiles for the entire divertor
Next steps until february
• Thermal screening of delivered coatings
completion anticipated by mid-november (+accompanying analysis )
Selection process: november
Cyclic loading at IPP, up to end february
Proposed ELM-like loading at FZJ: Under discusion, open issue, time constraints
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Non-destructive testing: Infrared thermography
Lock-in thermography developed at CEA
Xavier Courtois
Pulsed thermography under developmentat UKAEA
Glenn Counsell,Camera defect !
Benchmarking can only be done with CEA method
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Design concepts
1. First option: Lamellae design (full W body design)2. Back up option: W brazing design (W + CFC design)
Design limitation1. No active cooling under ~ 7 MW/m2 for 10 s2. Temperature limits (surface temp., temp at fixing structure)3. Weak supporting structure against EM forces4. Weight limit (80 kg/assembly) due to remote handling
The tileLBSRP (270 x 170 x 40 mm3)
ApproachesTemperature distribution by FEMEM forces by FEMMechanical tests for CFC and brazingHHF tests by electron beam facilities
Most critical issues are EM forces in disruptions
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Bulk W divertor
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
W lamellae design
Forschungszentrum Jülichin der Helmholtz-Gemeinschaft
inward and outward views: approximation of 3D-shaping by tilted planes (shadowing kept)
steps
top view: approximation of toroidal curvature by 2 straight linesref. radius2667 mm
Outward and inward views:
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
W lamellae 50x 6 mm
W lamellae design Opt2
3 fixing screws /stack
New base plate design
New wedge design
Spacers for insulation (TZM+ Al2O3 )
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Critical issues
Be first wall
mechanical accuracy and stability for castellated structures
Coatings:
Stability of W coating on Dunlop type CFC
Lifetime of W coating (see talk by J. Likonen)
W-bulk
Performance under high heat loads (200 cycles foreseen from 200C (7 MW for 10 sec) + destructive tests
Integration of new support structure in JET engineering
Costs and very narrow time schedule for all systems
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Many questions remain which can be worked on with help of EU PWI
• Calculations of EM forces
• Diagnostic of W-sources and W in the plasma
• Thermography in a full metal wall surrounding (reflectivity, emissivity)
• Production of fast particles and impact of Be and W erosion in main chamber (in particular with ICRH, LH)
• Modelling of W erosion and transport in divertor and predictions for coating lifetime
• Interaction of W with Be
• In situ diagnostic of material deposition and fuel retention
• Laser desorption/ablation diagnostics (JET FT, EU TP)
• Gas balance
• etcc
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
The main answers on the scientific goals of the JET wall project must be given by
SpectroscopySpecial wall diagnostic probespost mortem tile analysis
in situ fuel inventory/recycling (gas balance )
And the overall evaluation of plasma performance
upgrade of diagnostics needed
Diagnostic for the JET wall project
Embedded diagnostics
Langmuir probes
Thermo-couples
(direct part of the wall project)
Spektros-copy
(W, Be,C)
12.9:expert meeting (FZJ)
4/5.10: kick Off meeting
Responsible persons identified
Working programme defined
Wall diagnostic (probes)
19.9: expert meeting
Responsible persons identified
Be marker
R&D project on markers
Project settled
Project leader M. Rubel
Thermo-graphy
(upper view)
Project
settled
Project leader T. Eich
Working plan approved by PB
Improved Thermo-graphy
6.10: IR expert Working group meeting
Critical projects, not enough support form EU associations
EU-PWI-Task Force
V. Philipps, TF Meeting, 17-19 2005 Cadarache
Be cost will decrease under negotiation
Greatest uncertainty
Inconel 625 is hard
+ 750 for the RH boom
Move to shutdown?
Move to shutdown?
Decide March 2006
Depends on R&D
Article 7 Cost Estimates (kEuros) PB#1 PB#2 Var.
1. Beryllium material 9,000 9,800 800
Scrap beryllium buy-back credit -3,500 -2,800 700
2. Beryllium machining + tile assembly 7,500 7,691 191
3. CFC material 2,600 2,800 200
4. CFC machining 500 464 -36
5. Casting of Inconel carriers and cladding 600 633 33
6. Machining of metallic parts 600 1,425 825
7. Manufacture of fasteners 600 653 53
8. Embedded diagnostics - TC array etc. 1,200 1,248 48
9. Tungsten coating of CFC tiles 1,700 1,700 0
10. Beryllium tile baking facility 300 300 0
11. Bulk Tungsten LBSRP 2,000 2,000 0
Contingency 0 0 0
TOTAL 23,100 25,914 2,814
Main chamber Limiter tile design
Sliced to reduce eddy forces
No visible bolt holes to maximise power handling
Castellated to avoid cracking
IWGL is 3cm thicker than CFC
Global carbon deposition TEC
Institut für PlasmaphysikAssoziation EURATOM-Forschungszentrum JülichV. Philipps, ITPA Tarragona, June 05
W coatings for the divertor
IPP Garching is coordinatingFive EURATOM associations are involved in R&D to develop tungsten coating on JET- type (Dunlop) CFC
Problem:
•Anisotropic therm. expansion of CFC
•Therm. expansion mismatch with W
Strategy:
•Variation of production methods
•Very thin coatings (4µm)
→ Investigation of 4µm, 10µm “thin“ films
In addition:
Possible fallback solution for bulk tungsten
→ 200µm “thick“coatings
Hans Maier
Association “thick” method
“thin” method total number
CEA VPSCVD
CVD 4 and 10 3
ENEA VPS 1
TEKES PVD 4 and 10PVD/Re interl. 4 or 10
3
IPP Garching VPSCVD
PVD (4 and 10)CVD (4 and 10)
6
MEC/CEA CMSII/TVA(probably 10µm by CMSII)
1
: VPS=Vacuum Plasma Spray, CVD=Chemical Vapor DepositionPVD=Physical Vapor Deposition, TVA=Thermionic Vacuum ArcCMSII=Combined Magnetron Sputtering and Ion Implantation
Different Coating Types provided by Associations
Mechanical and heat flux tests of coatings from September this year, decision early 2006
Bulk W divertor prototype in JET
Currently 2 design concepts1. Lamellae design (full W body design)2. W brazing design (W + CFC design)
Design limitation1. No active cooling under ~ 7 MW/m2 for 10 s2. Temperature limits (surface temp., temp at fixing structure)3. Weak supporting structure against EM forces4. Wight limit (80 kg/assembly) due to remote handling
The tileLBSRP (270 x 170 x 40 mm3)
ApproachesTemperature distribution by FEMEM forces by FEMMechanical tests for CFC and brazingHHF tests by electron beam facilities
JET divertor with LBSRP
The most critical questions are EM forces in disruptions
Existing JET CFC tile on mechanical structure ( wedge and base plate)
EM forces calculated by JET and recalculated by FZJ : agreement within a factor of two, at the margin for the dumbbell + screw
40 mm CFC corresponds to < 1 mm W solid plate and few millimetres solid Inconel plate
No solution which meets the EM forces with the present structure unless connecting W teeth to existing CFC target
Toroidal segmentation: 6 mm thick W plates Mechanically assembled
Lamellae design (W body design)Needs design and construction of newMechanical support, compatible with remotehandling
Lamellae and brazing designs
26/9
W brazing design (W + CFC design)
Cw= ~ 20 mmCCFC= 49 - CW mm
W coating
CCFC
CW
A B
CCFC
CW
CCFC
CW
A B
A= ~10-20 mmB= 30 ~ 50 mm
CFC
W
FE model for EM Loading
SM analysis FEM results
preload eddy load
= detachment
V. Philipps, EU-PWI-Task Force, TFE
Agreed diagnostic proposals for FP7 with respect to the new wall project.
1.Upgrading of many spectrometers:
2. Refurbishment of erosion/deposition diagnostics
3. IR Thermography from top (in addition to wide angle IR installed presently)