1
University of Rome Tor Vergata
May 2014
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
European Bank for Reconstruction and Development
Module 12 - Contract Management
Evgeny Smirnov
Senior Procurement Specialist
Procurement Department
2
Objectives
During this module we will discuss:
Relationship between procurement process and contract management
Main type of contracts
Roles and Responsibilities of the parties under different contracts
Proactive contract management
Establishing systems and practices to avoid disputes and to resolve disputes when they arise
2
University of Rome Tor Vergata
May 2014
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
Contracts
4
What is contract?
A voluntary, deliberate, and legally binding agreement between two or more competent parties.
Contracts are usually written but may be spoken or implied.
A contractual relationship is evidenced by an offer,
acceptance of the offer, and
a valid (legal and valuable) consideration - the promise given by both parties as the
"price" of entering into the agreement.
Each party to a contract acquires rights and duties relative to the rights and duties of the other parties.
While all parties may expect a fair benefit from the contract (otherwise courts may consider them as inequitable) it does not mean that each party will benefit to an equal extent.
Existence of contractual-relationship does not necessarily mean the contract is enforceable, or that it is not void or voidable.
Contracts are normally enforceable whether or not in a written form, although a written contract protects all parties to it. Some contracts must be in writing to be legally binding and enforceable. Other contracts are assumed in, and enforced by, law whether or not the involved parties desired to enter into a contract.
3
5
Key Factors
Quality
Time
Cost/Price
For the success of the contract the parties shall maintain the balance between COST, QUALITY and TIME.
6
Ability to influence
Time
Ability to influence
4
7
Relationships between parties
Positive
Neutral
Negative
Positive
Maximum
benefits for
both parties
Risks of
negative
influence by
external factors
Lack of
motivation,
losses
Neutral
Risks of low
quality
Risk of
disputes, high
risk of negative
influence by
external factors
Delays,
loss of profit,
disputes
Negative
Low quality,
delays, cost
overruns
High risks of
cost and time
overruns, low
quality
Substantial loss
of time and
resources by
both parties
8
Contract types
• Service contracts • Consultancy service • Goods supply • Works contracts
Small works
Construction works
Design and Build
Supply and Installation of Plant and Equipment
Engineering, procurement and construction
Managing contract
•Complex contracts Output and performance based contracts
Target price
DBFO
Partnership
5
9
Selection of an appropriate contract type
• Nature, complexity and magnitude of the objectives
• Environment
• Sector and country business practices
• Resource availability
• Risk allocation between the parties
MIN (Risk) = MAX (Success)
10
Factors of influence
EXTERNAL FACTORS
Legal Framework
Industry practices
Development
Market conditions
Ethics (corruption)
CONTRACT
INTERNAL FACTORS
Objectives
Requirements
Parameters
In-house expertise/resources
capability
6
11
Understanding the environment
Contract environment - political
- social
- economic
- legal
- industrial
- technical
- environmental
Limitations
Rules of the game
12
Risks as seen by suppliers/contractors
Typical risks:
Political risks
Ownership of land and/or plant/Access rights
Regulatory requirements/bureaucracy
Climate/environment
Quality/reliability
Country/local experience
Presence/lack of local relationship
Contract conditions/local laws
ForEx risk
Local reporting/accounting
7
13
Relationship between tendering process
and contract management
Chart from “Contract Management Guide" State Government of Victoria
14
Tender
documents
Selection criteria Specifications
Project definition
External factors
Contractor selection
procedures
Contracting arrangements
Contract Tender procedures
Relationship between tendering process
and contract management
8
15
Contract cycle
16
Contract cycle
9
17
What is Contract Management?
Purpose - maximizing financial and operational performance and minimizing risks
Process - systematic and efficient management
Phases
contract creation;
execution; and
analysis
Key activities establishing (negotiating) the TERMS and CONDITIONS of contracts;
PLANNING activities;
controlling IMPLEMENTATION;
REPORTING progress;
making PAYMENTS;
managing VARIATIONS that may arise during the implementation phase;
documenting and handling CLAIMS;
preventing and resolving DISPUTES.
18
Contract management functions
Analyse contractual obligations
Assemble a project team
Establish communication
Monitor performance
Document performance
Correct performance variances
Manage contract changes
Prevent and manage disputes
10
University of Rome Tor Vergata
13-14 June 2013
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
Goods Supply Contracts
20
Goods supply contracts
UN Convention on Contracts for the international sale of goods
Vienna, 1980
General provisions
Obligations of the seller
Delivery of the goods and documents
Conformity of the goods and third party claims
Remedies for breach of contract
Obligations of the buyer
Payment of the price
Taking over
Remedies for breach of contract
Passing of risks
Anticipatory breach and instalment contracts
Damages
Exemptions
Effect of avoidance
Preservation of the goods
11
21
Logistics
Assessment of the circumstances
Risk identification
Development of risk mitigation and action plan
Packing Transportation Storage Customs clearance Documents
04/05/2014
22
Incoterms
04/05/2014
INCOTERMS – International Commercial Terms
Internationally recognized standard, which is used in international AND
domestic contracts for the SALE OF GOODS.
First published in 1936
Launched in mid-September 2010, Incoterms 2010 came into effect on 1
January 2011.
Incoterms are recognized by UNCITRAL as the global standard for the
interpretation of the most common terms in foreign trade.
12
23
Incoterms
24
Payment terms
Currency
Time of payment
Method of payment
Documents
Forms
Barter
Cash
Cheque
Bank draft
Wire transfer
Payment on collection
Escrow account
Letter of Credit
13
25
Payment terms
26
Inspections
Allow to ensure that the Goods meet the technical requirements
An instrument to identify problems at early stages
Inspections can be undertaken at different stages and in different forms
Tests/Certification
Own resources/Outsource
04/05/2014
14
27
Operation and maintenance
• Training
• Operation and maintenance manuals and other documents
• Call centres
• Spare parts stock and supply
• Warranty support
• Post warranty support
28
Disputes
Partnership – Mutual Benefits
Problems – Failure Who is to blame? Insurances Securities Liquidated damages Arbitration Warranties Termination
15
29
Risks
Factors that pose significant risk:
• imprecise/uncertain scope, requirements, specifications
• technical or logistical complexity
• large scale and/or short duration
• delivery terms are too optimistic
• weak contract administration
• reduction/loss of attention/interest by the Supplier
• inappropriate form of contract
• imprecise/inappropriate responsibilities, liabilities, damages
• conflicts of interest, collusion, corrupt practices
• unwillingness, inability to enforce contract conditions
• deliveries to other purchasers
• sub-suppliers’ failure to perform on time
• force majeure/unforeseen factors
• imperfection of legal system
University of Rome Tor Vergata
13-14 June 2013
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
Works Contracts
16
31
Investments in Infrastructure
Infrastructure is fundamental to both
economic development and plays a
crucial role in determining the quality
of life of individuals and societies.
An infrastructure deficit that some estimate
would require an annual investment of over
US$ 2 trillion each year over the next 20 years.
32
Construction
Building is an inherently complex process that
involves directing the efforts of many people to create
a given result
It is a process that involves the evolution of an idea to a
graphical and written representation, which then must be
ultimately transformed into to a physical reality
At various points along the way, theory collides with
reality, resulting in conflict
In the long term, how fairly this process is done may
affect the number of willing participants in the process
Gene Ming Lee, A Case for Fairness in Public Works Contracting
17
33
Construction process
34
Why is it important?
Understanding Public Sector Procurement Process, Industry Capability Network, New Zealand
18
35
Direct Account
Owner buys all materials and hires all staff and labor required for the works
Owner manages and supervises all works
Many public agencies (e.g. utilities) have traditionally worked this way
Used for activities such as maintenance, rehabilitation, small works, etc. Owner
project
design materials manage labour
36
Multiple Contract Packages
Referred to as package deals, island packages
Project broken up into a number of discreet contract packages
Owner responsible for design, project management, interfaces and overall performance
Owner can also contract out design and/or management
Examples: construction management, management contract, project management
Owner
A/E
S S S S S
contractor contractor contractor
19
37
Conventional
Two separate sequential contracts
design/supervision (architect/engineer)
construction (general/prime contractor)
A/E
SC SC SC
S S S S
Owner
General contractor
38
Single contract
•Single responsibility
•Design and build
•EPC
•Turnkey
•Concession/BOT
Single responsibility
contractor
Owner
Design Engineering Construction
Procurement
Administration/Finance
SC
SC
SC
S
20
39
Selection of contract terms and conditions
• Identification of risks and risk mitigation plan
• Contract structure Number of contracts
Contract types
• Are influenced by:
Project requirements
Employer’s own resources
Market situation
External factors
40
Selection of contract terms and conditions
21
41
New Engineering Contracts (NEC)
42
FIDIC Contracts
The International Federation of Consulting Engineers
(FIDIC) is an international standards organisation for the
construction industry
Fédération Internationale Des Ingénieurs-Conseils
Best known for the FIDIC family of contract templates.
It was established in 1913
The FIDIC founding member countries were Belgium,
France and Switzerland
89 member countries as of 2012 (with a target of 100
members by end 2013)
22
43
Roles and Responsibilities
FIDIC Contract Types
Construction (CONS/Red Book) / Plant and Design-Build (P&DB/Yellow
Book)
– Use where: the Employer wishes to be kept fully informed of the Contract’s
progress and appoints an Engineer to administer the Contract on his
behalf.
EPC/Turnkey (EPCT/Silver Book)
– Use where: the Employer wants greater certainty of final cost and project
duration and wishes the Contractor to take total responsibility for the
design and construction of the facility.
Other forms of Contract
– Short Form (Green Book)
– Design, Build and Operate (Gold Book)
– Multilateral Development Bank (MDB) Harmonised Edition of the Red Book
(Pink Book)
44
Roles and Responsibilities
Summary of Roles by Contract Type:
FIDIC Contract Type Role
Employer Contractor Engineer Employer’s
Representative
Construction
(Red Book) X X X
MDB Harmonised Construction
(Pink Book) X X X
Plant and Design-Build
(Yellow Book) X X X
EPC/Turnkey
(Silver Book)
X X X
Design Build and Operate
(Gold Book) X X X
23
45
Works Contracts
Contract
Employer
Contractor Engineer
46
Roles and Responsibilities: the Employer
Owner of the site
The beneficiary of the Works
Responsible for defining the intended
purpose of the Works and for setting out
the Employer’s Requirements
Enters into a contract agreement with the Contractor
Appoints a Representative/Engineer to oversee the execution of the
Works
Has the right to amend the contract
Pay for the Works done
Jointly with the Contractor, appoints a Dispute Adjudication Board (DAB)
Takes over the Works, when completed
24
47
Roles and Responsibilities: the Contractor
Design, execute and complete the Works and remedy any defects
Undertake all other responsibilities
Manage staff and labour in accordance
Carry out the manufacture of Plant, the production and manufacture of
Materials, and all other execution of the Works according to good practice
and with properly equipped facilities
Abide by the laws and bylaws, as well as the instructions of the Engineer
Make claims in accordance with the Contract
Complete all the Works within the Time for Completion
48
FIDIC: The importance of the Engineer
For this reason care must be taken when reviewing the TOR for the engineers.
They must be suitably experienced in FIDIC and must have an adequate funding
Role of Engineer crucial
The Engineer acts for the Employer in supervising
the activities by the Contractor
The Engineer issues all contractual notices to the
Contractor
The Engineer determines any variations
The Engineer issues the Interim Payment
Certificates
The Engineer under FIDIC is NOT independent –
he acts for and on behalf of the Employer
25
49
Roles and Responsibilities: the Engineer
When using Red or Yellow Book the Engineer Key Responsibilities are:
Exercises authority on behalf of the Employer as specified in the Contract
Makes fair determinations on matters related to Contract execution
Review the Contractor’s quality assurance system
Review the Contractor’s work programme
Oversee Tests on Completion
Manage Variations
Issue Payment Certificates
Manage Claims
50
Roles and Responsibilities: Administration of the Contract by the Employer (EPC/T)
Employer’s Administration:
May delegate authority to an Employer’s Representative
Retains authority for the administration of the project and executes most
of the functions assigned to the Engineer in CONS and P&DB.
Expects much less of a hands-on administrative role than in CONS or
P&DB.
26
51
FIDIC Red Book
General provisions
The Employer
The Engineer
The Contractor
Nominated Subcontractors
Staff and Labour
Plant, Materials and Workmanship
Commencement, Delays and Suspension
Test on Completion
Employer’s Taking Over
Defects Liability
Measurement and Evaluation
Variations and Adjustments
Contract Price and Payment
Termination by Employer
Suspension and Termination by Contractor
Risk and Responsibility
Insurance
Force Majeure
Claims, Disputes and Arbitration
FIDIC CONDITIONS OF CONTRACT FOR CONSTRUCTION FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER
52
FIDIC Order of Precedence
Contract agreement
Letter of acceptance
Letter of tender
Particular conditions
General conditions
Specifications
Drawings
Schedules
Other documents
27
53
Organisation Structure
Contract organisation structure and human resources
54
Contract management unit
•Composition •Education, knowledge and experience in:
– Management – Engineering and other technical skills
– Operation and maintenance experience
– Financial management and accounting
– Environment protection
– Health and safety
– Legal issues
– Communication skills
– Individual qualities
28
55
Organisation and Mobilisation
56
Planning
29
57
Planning
58
Establishing a Project Plan
Questions to ask:
Is the project still on programme?
Does the Employer’s Requirements still reflect the Employer’s needs?
Will the Contractor still be able to supply works, goods and materials on time?
Who will supervise the works?
Have the administrative procedures been documented and agreed to?
How will variations be priced and authorised?
What work has to be completed before each interim payment?
Has a Dispute Adjudication Board been appointed (if a standing DAB is
selected)?
30
59
Establishing a Project Plan
60
Establishing a Project Plan
Guidelines for drafting a Project Plan
Keep the plan simple and clear
Ensure the Employer and Contractor are equally considered;
Include a risk matrix with clear contingency plans
31
61
Common pitfalls in Planning
Not committing sufficient resources upfront for the preparation and support of
a project plan;
Failing to establish an accurate baseline for the Project Programme at the
commencement of the works;
Failure to establish clear levels of authority for authorisations of claims and
variations;
Assuming that the conditions of contract are clear on particulars of payments
and reporting and fully understood by both Parties;
Other pitfalls – relating to failure to complete items on the project plan
template/checklist
62
Site Organisation
32
63
Construction Methods
64
Quality Control
33
65
Quality Control
66
Time Control
34
67
Cost Control
68
All
Information required
Minimal
Lump sum
Recalculation
Cost cover
Min Employer’s Risks Max
Max Contractor’s Risks Min
Contract pricing
35
69
Contract pricing
Unit price based
70
Contract pricing
04/05/2014
Unit price based
36
71
Lump sum based
Contract pricing
72
Cost Control
•Analysing
•Planning
•Budgeting
•Monitoring and controlling
•Reporting
Costs:
Itemised plan
Cash flow
Responsibilities
37
73
Cost Control
CUMULATIVE CASH FLOW
Cash flow
amount
Time
Forecasted cash flow
Actual cash flow
74 © European Bank for Reconstruction and Development 2010 | www.ebrd.com
Cost control
Issues to consider:
• Foreign exchange fluctuations
• Index dynamic
• Labour/material market situation
• Logistics
• Actual cost
38
75
Contract pricing
Fixed or Adjustable price?
Time
Costs
Tender price
Actual cost
Price
escalation
BD TO CS Contract implementation
76
Financial control
39
77
78
40
79
Time control
80
Time control
41
81
Progress control
82
Triple Constraint for Works Contracts
Contract Management
“Triple Constraint”
Time
(Time for Completion)
can be extended by
CLAIMS/VARIATIONS
Cost
(Contract Price)
can be adjusted by CLAIMS/VARIATIONS
Scope
(Scope of Works/BOQ)
can be changed through VARIATIONS
42
83
Managing the Triple Constraint
VARIATIONS
Variations to change scope may originate with the Engineer or the Employer at any time
Under the Value Engineering clause the Contractor may propose variations to benefit the
Employer
CLAIMS (are claims for time or cost or both):
Made with respect to the Contractor’s entitlements under the Contract (shall not to be
confused with disputes).
Originate when the Contractor notifies the Engineer or Employer.
84
Records of Contractor
43
85
Records of Contractor
Monthly reports
86
Control
44
87
FIDIC Contract Issues
Provisional sums
Day works
Price adjustment
Work program
Insurance policies and certificates
Deviations and/or alternatives
Subcontractors
Adjudication/arbitration
88
Risks in construction
Injury and damage risks
• Employer’s risk
• Contractor’s risks
• Contractor’s obligation to insure
Financial risk
• Employer or Contractor fails to meet contractual obligations
• Inflation (if there is no price adjustment)
• Technical risks
• Cost increase
• Design errors
• Unforeseen conditions (especially underground)
45
89
Factors that pose significant risk include:
imprecise/uncertain scope, requirements, specifications;
large number of interfaces;
technical or logistical complexity;
large scale and/or long duration;
weak project management and/or contract administration;
inappropriate form of contracts;
imprecise/inappropriate responsibilities, liabilities, damages;
conflicts of interest, collusion, corrupt practices;
unwillingness, inability to enforce contract conditions;
force majeure/unforeseen factors;
Bureaucracy;
imperfection of legal system
BEWARE OF CONTRACTUAL RISKS!
Risks in construction
90
Risks in construction
46
91
Insurances
92
Issues to consider
Contract implementation phase
Standards
GOST (State Standards)
SNiP (Construction Norms and Rules)
ENiR (Unified Norms and Rates)
SanPiN (Sanitary Norms)
Conformity
Certification by RosTechRegulation
Ordinary goods/equipment
Certification by RosTechNadzor
High danger goods (high pressure/temperature/lifting equipment etc.)
Certification by RosPoterbNadzor
Chemicals, building materials, water supply equipment etc.
47
93
Issues to consider
Contract implementation phase
Licensing/SRO membership
Main activities
Specialised works
Accounting
Taxation
Customs clearance
Procedures
Documents
Time
94
Beware of corruption
• Identification
• Prevention
• Monitoring and audit
• Liquidation
C = f (M, DM, R)
where:
C Corruption M Monopoly DM Decision Making
О Responsibility
48
95
Delays
Delays can occur frequently and both parties tend to blame each other.
Common delays:
• Late possession of site
• Employer has not obtained required permits
• Contractor, employer or local authorities has not provided/approved design
• Local construction law or practice differs from assumptions
• Extreme weather conditions
• Rise in cost of materials/labour
• Reactive/passive position FIDIC engineer
• Delay in payments
• Failure of sub-contractors
• Failure to issue acceptance certificate
• Technical faults
• Disputes
96
Common claims
Uncertain requirements
Employer’s/Authorities’ interference
Delayed access to site
Climatic and environmental differences
Personnel and labour risks
Payment delays
Subsoil conditions
Availability of materials
Variations
Acceleration of works/extension of time
Cost increase
Quality of works
49
97
Disputes
The Engineer determines claims by both parties
If no agreement, amicable settlement available
If no settlement, refer to DAB
If parties do not agree on DAB decision then refer to arbitration
Generally arbitration under local courts and national law.
Can be under UNCITRAL or ICC rules or other rules
98
Resolve performance issues
Can issue contract notice or ‘notice to correct’ under FIDIC
Amend the contract to mitigate the performance issue
Impose liquidated damages
Threaten suspension or termination of contract
Go to adjudication or arbitration
Appoint Dispute Arbitration Board
File with local/international courts
50
99
Avoiding and Resolving Disputes
General Principles
Ensure all of the Parties clearly understand their specific roles and
responsibilities under the chosen form of Contract;
Clearly lay out the implications of the Contract pricing structure for pricing
and managing Claims made by the Contractor;
Clearly specify a framework for pricing and administering Variations;
Consider carefully the administrative structure of the Engineer and the
Engineer’s staff;
Assess the benefits of appointing a standing DAB;
Take care to ensure the appointment of an Engineer with the request
technical expertise and experience in Contract Administration and will
execute the role with care and fairness
100
The Role of the Engineer
Must exercise professionalism and independent thinking in applying the
Contract to facts and circumstances presented by the Parties;
Makes determinations (in accordance with over 35 sub-clauses in CONS
and P&DB);
Be proactive in the identification and resolution of potential areas of conflict
(“prevention better than cure”);
Consider the benefits of keeping the Site at arm’s length and conduct
administration through the Engineer (in order to increase objectivity)
Avoiding and Resolving Disputes
51
101
Stages of Dispute Elevation
Step 1 - “Court of the first instance”
The “court of the first instance” is the Engineer and the Engineer’s staff. The
Resident Engineer should be the first point of contact if a dispute arises;
The Resident Engineer (depending on her level of authority to resolve claims
and other sources of disputes) elevates the dispute to the Engineer;
If the Parties do not agree with the Engineer’s determination, the dispute is
presented to Dispute Arbitration Board;
102
Stages of Dispute Elevation
Step 2 – Dispute Arbitration Board
A standing DAB has the advantage of on-going access to the Site and real-
time dispute resolution;
A standing DAB can maintain open lines of communication with the Parties
and the Engineer can address potential disputes as they arise rather than
waiting until the Parties are entrenched in their positions;
Use of a DAB can avoid going to international arbitration;
Failing resolution by the DAB, a dispute can proceed to local
court/international arbitration, a potentially costly and time-consuming
process.
52
103
Pro et Contra of using FIDIC contracts
“There is nothing either good or bad, but thinking makes it so…” Hamlet, William Shakespeare
Questionnaire, April 2012
20 questions about FIDIC contracts Section A; General Information
Section B; Overall experience with FIDIC contracts
Section C; Specific issues (anti-corruption, social and
environmental provisions, Engineer’s role, DAB)
Responses
• 12 countries in Eastern Europe, Turkey and FSU countries
• Power, Transport, Municipal and Nuclear Safety sectors
• 38 respondents
• Contracts range: EUR 3 million to EUR 990 million
104
Pro et Contra of using FIDIC contracts
“What's in a name? That which we call a rose…” Romeo and Juliet, William Shakespeare
View of EBRD
• Well balanced contracts
• Easily adoptable to specific country conditions
• Specific MDB provisions included
• Suitable for a wide range of projects
• Well known on the market
• Aimed at timely completion within the original cost
• Presence of a professional engineering support
• Efficient dispute resolution mechanism
53
105
Pro et Contra of using FIDIC contracts
“Beauty is bought by judgement of the eye, Not utter'd by base sale of chapmen's tongues…”
Love's Labours Lost, William Shakespeare
View of Respondents
• Users are generally satisfied
• Well balanced risks of the parties
• Fair and complete
• Well known throughout the industry
• Simple, but covering main contractual issues well, being based on vast experience
• Standardisation and availability of the documents for different type of projects
106
Pro et Contra of using FIDIC contracts
“Oft expectation fails and most oft there
Where most it promises, and oft it hits
Where hope is coldest and despair most fits”
All’s Well That Ends Well, William Shakespeare
Other views
• Requires localisation, as some terms contradicts to a local legislation
• Not well known by local contractors
• Lack of experience and incomplete understanding by some employers
• Open for claims
• Lack of (limited) control in respect of delays in the course of the works
• Cost and time overruns are quite common
• Requires more detailed procedures in respect of delays and suspension of the
works
• Engineers act in favour of their employers and often carry their duties passively
• Dab is used rarely and is not efficient
• Sometimes clients use incorrect forms of FIDIC contract on their projects
54
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
GRAZIE MILLE!
THANK YOU VERY MUCH!
European Bank for Reconstruction and Development
One Exchange Square
London EC2A 2JN
United Kingdom
Phone: +44 20 7338 6807
Fax: +44 20 7338 7472
Internet address: www.ebrd.com